05.08.2013 Views

ORNL-2106 - the Molten Salt Energy Technologies Web Site

ORNL-2106 - the Molten Salt Energy Technologies Web Site

ORNL-2106 - the Molten Salt Energy Technologies Web Site

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

i<br />

E<br />

ART FACILITY<br />

F. R. McQuilkin<br />

Construction work is nearing completion on <strong>the</strong><br />

contract portion of <strong>the</strong> Aircraft Reactor Test (ART)<br />

facility in Building 7503. Package 1 work on <strong>the</strong><br />

building additions, building alterations, and cell<br />

installation was approximately 7% behind schedule<br />

at <strong>the</strong> 92.5% completion point on June 1, 1956.<br />

About onehalf <strong>the</strong> deficiency may be accounted<br />

for by lack of breakers and reactors for <strong>the</strong> eiec-<br />

trical switchgear. During <strong>the</strong> quarter <strong>the</strong> principal<br />

work accomplished included final erection of <strong>the</strong><br />

cell tanks; erection of <strong>the</strong> stack; placement of<br />

concrete for <strong>the</strong> main air duct, <strong>the</strong> penthouse, <strong>the</strong><br />

radiator pit, <strong>the</strong> blower house floor and equipment<br />

bases, <strong>the</strong> cell encasement, and <strong>the</strong> main building<br />

floor at an elevation of 852 ft; painting; grading;<br />

fencing; and general job and site cleanup.<br />

Package 2 work on <strong>the</strong> installation of diesel<br />

generators and facility, electrical control centers,<br />

and spectrometer-room electrical and air-condition-<br />

ing equipment progressed to <strong>the</strong> 79% completion<br />

point during <strong>the</strong> quarter. The installation of <strong>the</strong><br />

electrical control centers and <strong>the</strong> diesel generators<br />

will complete this work. The estimated date for<br />

shipment of <strong>the</strong> diesel generators is June 25,1956.<br />

The contract for Package A work on <strong>the</strong> installa-<br />

tion of auxiliary piping was negotiated with <strong>the</strong><br />

V. L. Nicholson Company . . at a contract price of<br />

$50,351.62, with completion scheduled for June 15, .<br />

1956, unless material delivery schedules interfere.<br />

Some of <strong>the</strong> Package 1 and Package 2 work MY<br />

1.5. PROCUREMENT AND CONSTRUCTION<br />

ilding. The dark-sided<br />

n building is <strong>the</strong> addition which<br />

actor cell, <strong>the</strong> heat dumps, and<br />

The appurtenances to<br />

W. F. Boudreau<br />

PERIOD ENDING JUNE IO, 1956<br />

wide door that is required in order that <strong>the</strong> reactor<br />

and <strong>the</strong> tops of <strong>the</strong> cell tanks may pass into <strong>the</strong><br />

building. The cylinder bank in <strong>the</strong> left foreground,<br />

which served as helium storage for <strong>the</strong> Aircraft<br />

Reactor Experiment (ARE) will be used for storage<br />

of nitrogen for he ART. In <strong>the</strong> foreground, in<br />

front of <strong>the</strong> truck, may be seen <strong>the</strong> 1500-kva transformer<br />

and substation that will serve <strong>the</strong> purchased<br />

power (TVA) portion of <strong>the</strong> power service to <strong>the</strong><br />

facility. The openings in <strong>the</strong> generator house,<br />

on <strong>the</strong> right, will receive <strong>the</strong> radiators for <strong>the</strong><br />

five diesel generators that will have 300-kw continuous<br />

ratings and will supply <strong>the</strong> locally generated<br />

power service to <strong>the</strong> facility. In Fig. 1.5.3<br />

may be seen <strong>the</strong> pressure vessel and water tank<br />

that make up <strong>the</strong> containment cell. The 24-ft-dia,<br />

36-ft-high pressure vessel is within <strong>the</strong> 30-ft-dia<br />

water tank. The top portion of <strong>the</strong> water tank had<br />

been removed and was sitting on <strong>the</strong> main floor<br />

when <strong>the</strong> photograph was taken. Although <strong>the</strong><br />

pressure vessel manhole is 5 ft in diameter and<br />

will pass most of <strong>the</strong> items to be installed within<br />

<strong>the</strong> vessel, <strong>the</strong> contractor will remove <strong>the</strong> top head<br />

to provide <strong>the</strong> required access for <strong>the</strong> reactor.<br />

The pressure vessel was field stress-relieved and<br />

hydrostatically tested at 300 psi during <strong>the</strong> quarter.<br />

Inspection of <strong>the</strong> welded joints between <strong>the</strong> 24-in.dia<br />

junction panel sleeves and <strong>the</strong> 4-in.-thick shell<br />

walls revealed a failure of a joint in <strong>the</strong> heataffected<br />

zone of <strong>the</strong> sleeve base metal. Therefore<br />

all eight of <strong>the</strong> one-piece sleeves were replaced<br />

with two-piece units and a revised joint design<br />

and welding procedure was used. The field stress-<br />

c ich is Q view from a relief procedure and <strong>the</strong> hydrostatic pressure tests<br />

B.l’<br />

ion of <strong>the</strong> 10-ft-dia and<br />

and <strong>the</strong> generator house MY be Seen in Fig. 1.52.<br />

On <strong>the</strong> left may be seen <strong>the</strong> newly installed 32-ft-<br />

Will be repeated.<br />

The concrete penthouse adjacent to <strong>the</strong> cell is<br />

shown in Fig. 1.5.4. This structure will house<br />

<strong>the</strong> NaK pumps, pump motors, and <strong>the</strong> mechanisms<br />

for supporting <strong>the</strong>se units and <strong>the</strong> radiators, and<br />

will also house <strong>the</strong> NaK piping to <strong>the</strong> main air<br />

t and to <strong>the</strong> radiator pit below, The special<br />

ipment room is directly below und covered by<br />

e roof plugs shown in <strong>the</strong> open doorway.<br />

Design work continued on Package 3, which<br />

omprises <strong>the</strong> process equipment, process piping,<br />

etc. to be installed by <strong>ORNL</strong>. The design will<br />

probably be completed in July 1956.<br />

69

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!