ORNL-2106 - the Molten Salt Energy Technologies Web Site
ORNL-2106 - the Molten Salt Energy Technologies Web Site
ORNL-2106 - the Molten Salt Energy Technologies Web Site
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
i<br />
E<br />
ART FACILITY<br />
F. R. McQuilkin<br />
Construction work is nearing completion on <strong>the</strong><br />
contract portion of <strong>the</strong> Aircraft Reactor Test (ART)<br />
facility in Building 7503. Package 1 work on <strong>the</strong><br />
building additions, building alterations, and cell<br />
installation was approximately 7% behind schedule<br />
at <strong>the</strong> 92.5% completion point on June 1, 1956.<br />
About onehalf <strong>the</strong> deficiency may be accounted<br />
for by lack of breakers and reactors for <strong>the</strong> eiec-<br />
trical switchgear. During <strong>the</strong> quarter <strong>the</strong> principal<br />
work accomplished included final erection of <strong>the</strong><br />
cell tanks; erection of <strong>the</strong> stack; placement of<br />
concrete for <strong>the</strong> main air duct, <strong>the</strong> penthouse, <strong>the</strong><br />
radiator pit, <strong>the</strong> blower house floor and equipment<br />
bases, <strong>the</strong> cell encasement, and <strong>the</strong> main building<br />
floor at an elevation of 852 ft; painting; grading;<br />
fencing; and general job and site cleanup.<br />
Package 2 work on <strong>the</strong> installation of diesel<br />
generators and facility, electrical control centers,<br />
and spectrometer-room electrical and air-condition-<br />
ing equipment progressed to <strong>the</strong> 79% completion<br />
point during <strong>the</strong> quarter. The installation of <strong>the</strong><br />
electrical control centers and <strong>the</strong> diesel generators<br />
will complete this work. The estimated date for<br />
shipment of <strong>the</strong> diesel generators is June 25,1956.<br />
The contract for Package A work on <strong>the</strong> installa-<br />
tion of auxiliary piping was negotiated with <strong>the</strong><br />
V. L. Nicholson Company . . at a contract price of<br />
$50,351.62, with completion scheduled for June 15, .<br />
1956, unless material delivery schedules interfere.<br />
Some of <strong>the</strong> Package 1 and Package 2 work MY<br />
1.5. PROCUREMENT AND CONSTRUCTION<br />
ilding. The dark-sided<br />
n building is <strong>the</strong> addition which<br />
actor cell, <strong>the</strong> heat dumps, and<br />
The appurtenances to<br />
W. F. Boudreau<br />
PERIOD ENDING JUNE IO, 1956<br />
wide door that is required in order that <strong>the</strong> reactor<br />
and <strong>the</strong> tops of <strong>the</strong> cell tanks may pass into <strong>the</strong><br />
building. The cylinder bank in <strong>the</strong> left foreground,<br />
which served as helium storage for <strong>the</strong> Aircraft<br />
Reactor Experiment (ARE) will be used for storage<br />
of nitrogen for he ART. In <strong>the</strong> foreground, in<br />
front of <strong>the</strong> truck, may be seen <strong>the</strong> 1500-kva transformer<br />
and substation that will serve <strong>the</strong> purchased<br />
power (TVA) portion of <strong>the</strong> power service to <strong>the</strong><br />
facility. The openings in <strong>the</strong> generator house,<br />
on <strong>the</strong> right, will receive <strong>the</strong> radiators for <strong>the</strong><br />
five diesel generators that will have 300-kw continuous<br />
ratings and will supply <strong>the</strong> locally generated<br />
power service to <strong>the</strong> facility. In Fig. 1.5.3<br />
may be seen <strong>the</strong> pressure vessel and water tank<br />
that make up <strong>the</strong> containment cell. The 24-ft-dia,<br />
36-ft-high pressure vessel is within <strong>the</strong> 30-ft-dia<br />
water tank. The top portion of <strong>the</strong> water tank had<br />
been removed and was sitting on <strong>the</strong> main floor<br />
when <strong>the</strong> photograph was taken. Although <strong>the</strong><br />
pressure vessel manhole is 5 ft in diameter and<br />
will pass most of <strong>the</strong> items to be installed within<br />
<strong>the</strong> vessel, <strong>the</strong> contractor will remove <strong>the</strong> top head<br />
to provide <strong>the</strong> required access for <strong>the</strong> reactor.<br />
The pressure vessel was field stress-relieved and<br />
hydrostatically tested at 300 psi during <strong>the</strong> quarter.<br />
Inspection of <strong>the</strong> welded joints between <strong>the</strong> 24-in.dia<br />
junction panel sleeves and <strong>the</strong> 4-in.-thick shell<br />
walls revealed a failure of a joint in <strong>the</strong> heataffected<br />
zone of <strong>the</strong> sleeve base metal. Therefore<br />
all eight of <strong>the</strong> one-piece sleeves were replaced<br />
with two-piece units and a revised joint design<br />
and welding procedure was used. The field stress-<br />
c ich is Q view from a relief procedure and <strong>the</strong> hydrostatic pressure tests<br />
B.l’<br />
ion of <strong>the</strong> 10-ft-dia and<br />
and <strong>the</strong> generator house MY be Seen in Fig. 1.52.<br />
On <strong>the</strong> left may be seen <strong>the</strong> newly installed 32-ft-<br />
Will be repeated.<br />
The concrete penthouse adjacent to <strong>the</strong> cell is<br />
shown in Fig. 1.5.4. This structure will house<br />
<strong>the</strong> NaK pumps, pump motors, and <strong>the</strong> mechanisms<br />
for supporting <strong>the</strong>se units and <strong>the</strong> radiators, and<br />
will also house <strong>the</strong> NaK piping to <strong>the</strong> main air<br />
t and to <strong>the</strong> radiator pit below, The special<br />
ipment room is directly below und covered by<br />
e roof plugs shown in <strong>the</strong> open doorway.<br />
Design work continued on Package 3, which<br />
omprises <strong>the</strong> process equipment, process piping,<br />
etc. to be installed by <strong>ORNL</strong>. The design will<br />
probably be completed in July 1956.<br />
69