04.08.2013 Views

chhatru hydro electric project (3x36 =108 mw) - Ministry of Power

chhatru hydro electric project (3x36 =108 mw) - Ministry of Power

chhatru hydro electric project (3x36 =108 mw) - Ministry of Power

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

CHHATRU HYDRO ELECTRIC PROJECT (3X36 <strong>=108</strong> MW)<br />

HIMACHAL PRADESH<br />

1. INTRODUCTION<br />

The Chhatru Hydro<strong>electric</strong> Project located in Lahaul & Spiti district <strong>of</strong><br />

Himachal Pradesh envisages utilization <strong>of</strong> the waters <strong>of</strong> the river Chandra<br />

for power generation on a run <strong>of</strong> river type development, harnessing a<br />

head <strong>of</strong> about 177m.<br />

The <strong>project</strong> with a proposed installation <strong>of</strong> 108 MW (<strong>3x36</strong> MW) would<br />

afford an net annual energy generation <strong>of</strong> 455.72 GWH, in a 90 %<br />

dependable year. The tariff energy from the <strong>project</strong> at present day cost<br />

would be Rs 2.28/unit (levellised) at power house bus bars.<br />

The diversion site is located between Latitude 32 o 18'11" North Longitude<br />

77 o 24'41"East. The barrage site is approachable from Chandigarh by road<br />

being at a distance <strong>of</strong> 410 kms approx. The nearest rail head is located at<br />

Kiratpur and nearest airport is located at Bhunter.<br />

2. SCOPE OF WORKS<br />

The Chhatru HE <strong>project</strong> envisages construction <strong>of</strong> :<br />

a 19m high diversion barrage across river Chhatru to provide a net<br />

live storage <strong>of</strong> 87.50 hacm. with FRL at 3421.00m and MDDL at<br />

3413.50m;<br />

two numbers desanding basins <strong>of</strong> length 381m(L) and size 13m<br />

(W)x19.60m(H) to remove silt particles <strong>of</strong> size 0.20 mm and<br />

above;<br />

a 6.5 km long and 5.10m dia. modified horse shoe shaped head<br />

race tunnel terminating in a surge shaft;<br />

a 91.80m high ,15m dia surge shaft;<br />

350m long, 4.70m dia pressure shaft;<br />

a surface power house having an installation <strong>of</strong> 3 Francis driven<br />

generating units <strong>of</strong> 36 MW each operating under a net head <strong>of</strong> 160<br />

m; and<br />

1150m long tail race tunnel to carry the power house releases back<br />

to the river Chandra.<br />

The power generated from the <strong>project</strong> would be evacuated through. 220<br />

kV double circuit line from Khoskar to 400 KV pooling point at Tandi,<br />

1


eyond which the evacuation will be through 400 KV double circuit net<br />

work to pooling station near Panarsa to feed power to the power grid .<br />

The Salient features <strong>of</strong> the <strong>project</strong> are given at Annex-I and a layout map<br />

at Plate-I<br />

3. HYDROLOGY<br />

The river Chandra drains a catchment area <strong>of</strong> about 1583 Sq. km. at the<br />

proposed barrage site. The discharge data <strong>of</strong> rivder Chandra at diversion<br />

site <strong>of</strong> Chhatru HEP has been derived from June 1973- May 2000 from the<br />

discharge data <strong>of</strong> river Chandra at Ghousal (site Monitored by CWC).<br />

Discharge data <strong>of</strong> river Chandra at Ghousal has been reduced on<br />

catchment area basis at diversion site. For design flood, flood frequency<br />

analysis has been carried out by Gumble Method.The design flood has<br />

been assessed as approx. 1500 cumecs.<br />

4. POWER POTENTIAL STUDIES<br />

The computed inflow series for 27 years viz June 1973 to May, 2000 has<br />

been considered in the assessment <strong>of</strong> a power benefits from the <strong>project</strong>. As<br />

per GOI notification for tariff, the year 1992-93 corresponds to 90%<br />

dependable year. An installation <strong>of</strong> 108 MW comprising 3 generating<br />

units <strong>of</strong> 36 MW each has been proposed. The energy availability from the<br />

<strong>project</strong> in a dependable and an average year has been summarized below:<br />

Particulars<br />

Annual Energy Generation<br />

Dep. Yr. Avr. Yr.<br />

Gross annual Energy Generation (GWH) 455.72 475.80<br />

Annual Load Factor (%) 50.00 52.00<br />

Generation during Lean Flow Season (Dec.-Feb.)<br />

Energy Output (GWH) 41.86<br />

Load Factor (%) 18.00<br />

The design energy at 95 % machine availability in a 90% dependable year<br />

has been worked out at 455.72 GWH.<br />

A net live pondage <strong>of</strong> 75.00 ham. has been provided in the diversion<br />

barrage, which would enable the station to operate as peaking station. The<br />

pondage is equivalent to 280.79 MWH which is sufficient to operate the<br />

station for 3 hours.<br />

2


5. POWER EVACUATION ASPECTS<br />

The power generated from the <strong>project</strong> would be evacuated through. 220<br />

kV, double circuit lines from Khoskar to 400 KV pooling point at Tandi,<br />

beyond which the evacuation will be through 400 KV double circuit net<br />

work to pooling station near Panarsa to feed into the Grid which in turn<br />

connected to National Grid<br />

6. ENVIRONMENTAL ASPECTS<br />

The <strong>project</strong> is located in Lahaul & Spiti valley <strong>of</strong> H.P. Based on<br />

assessment <strong>of</strong> environmental impacts, management plans have to be<br />

formulated for Catchment Area Treatment, compensatory afforestation<br />

and other environmental issues. These issues would be addressed during<br />

investigations for preparation <strong>of</strong> DPR.<br />

7. ESTIMATES OF THE COST<br />

The <strong>project</strong> is estimated to cost Rs. 585.15 crores at power house bus bars<br />

including IDC at Oct., 2003 price level. The preliminary cost estimate <strong>of</strong><br />

the <strong>project</strong> has been prepared as per guidelines <strong>of</strong> CEA / CWC. The break<br />

down <strong>of</strong> the cost estimates is given below:<br />

Civil works : Rs. 386.79 Crores<br />

Electro Mechanical works : Rs. 136.12 Crores<br />

Sub total (Generation) : Rs. 522.91 Crores<br />

Transmission works : Rs. 8.45 Crores<br />

Total Cost : Rs. 531.36 Crores<br />

On Generation works<br />

Interest During Construction : Rs. 62.24 Crores<br />

Total : Rs. 585.15 Crores<br />

8. FINANCIAL ASPECTS<br />

As indicated above, the Chhatru HE <strong>project</strong> with an estimated cost <strong>of</strong> Rs.<br />

585.15 (including IDC <strong>of</strong> Rs.62.24 crores) at power house bus bars with<br />

net energy <strong>of</strong> 455.72 GWH in a 90% dependable year. The <strong>project</strong> is<br />

proposed to be completed in a period <strong>of</strong> 4½ years. The tariff has been<br />

worked out considering a debt-equity ratio <strong>of</strong> 70:30, 16% return on equity,<br />

annual interest rate on loan at 10% .The tariff for first year and levellised<br />

tariff have been work out Rs. 2.89 /kWh & Rs. 2.28/kwh respectively at<br />

power house bus bars.<br />

3


9. CONCLUSIONS<br />

The economy <strong>of</strong> the Himachal Pradesh predominantly depends on<br />

agricultural and allied sectors. The <strong>electric</strong> power being a vital and<br />

essential infrastructure has a significant role to play in economic<br />

upliftment <strong>of</strong> the state. The construction <strong>of</strong> <strong>project</strong> will provided<br />

employment to the local people. The <strong>project</strong> has a distinct advantage <strong>of</strong><br />

being located along a motorable road making it possible to be completed<br />

within four and half year.<br />

4


GENERAL PROJECT FEATURES<br />

5<br />

Annexure-I<br />

LOCATION<br />

State Himachal Pradesh<br />

District Lahaul Spiti<br />

River Chandra river(Chenab Basin)<br />

Barrage site ± 5 km. u/s <strong>of</strong> Chhatru village<br />

<strong>Power</strong> house site ± 3.5 km d/s <strong>of</strong> Chhatru village<br />

on right bank <strong>of</strong> Chandra river<br />

HYDROLOGY<br />

Catchment Area<br />

at diversion site 1583 Sq. km.<br />

Snow catchment 48 Sq. km. above El. 4200m<br />

Probable maximum flood 1500cumecs<br />

Standard <strong>project</strong> flood<br />

Observed maximum flood 828.00 cumsecs<br />

RESERVOIR<br />

Full reservoir (FRL) 3421.00m<br />

Maximum reservoir level (MRL) 3422.00m<br />

Maximum draw down level (MDDL) 3413.50m<br />

Gross storage upto FRL 112.50 Hect-m<br />

Live storage 87.50 Hect-m<br />

Net live storage 70.00 Hect-m<br />

DIVERSION STRUCTURE<br />

Type Barrage<br />

Max. height from R.B.L. 19m<br />

Elevation <strong>of</strong> top <strong>of</strong> dam or bridge ±3424.00m<br />

Average bed level ±3405.00m<br />

SPILLWAY<br />

Design flood 1500cumecs<br />

Type Gated spillways with radial gates<br />

Nos. <strong>of</strong> spillways, Crest elevation 6 Nos. El. 3407.00m<br />

Length <strong>of</strong> gated spillways 5.00m each.


Energy dissipation<br />

Length 98.00m<br />

Down stream bed level ±3403.00m<br />

INTAKE STRUCTURE<br />

Type Surface<br />

Sill level El. 3410.00m<br />

No. & size <strong>of</strong> opening 8 Nos., 5.50mx3.0m<br />

APPROACH TUNNEL<br />

No. 1<br />

Size and type 6.00m dia, Circular concrete Lined<br />

Velocity 3.30m/sec<br />

Length 200m<br />

Design discharge from intake 93.75 cum/sec<br />

DESANDING BASIN<br />

Type Underground, central gutter type<br />

No. <strong>of</strong> basins 2 nos.<br />

Length <strong>of</strong> each basin 381m<br />

Size <strong>of</strong> basins Width13.00m,Depth 19.60m<br />

Minimum particle size to be removed 0.2mm<br />

Flushing tunnel, size 4.00m, D-Shaped<br />

Flushing tunnel, length 1000m<br />

HEAD RACE TUNNEL<br />

No. 1<br />

Size & Shape 5.10m diameter, Modified<br />

Horse shoe shaped Concrete lined<br />

Length 6500 m<br />

Design discharge 75 cumecs<br />

Slope 1 in 120.50 m<br />

Velocity 3.63m/sec<br />

Adit 275m leangth 5m D- shaped<br />

SURGE SHAFT<br />

Type Underground, restricted orifice type<br />

Size 15m dia, 91.80m high<br />

Orifice 2.50m dia<br />

Maximum upsurge level El. 3436.10m<br />

6


Minimum down surge level El. 3396.60m<br />

Bottom level El. 3350.50m<br />

Top level El. 3436.00m<br />

Adit to top <strong>of</strong> surge shaft 4mx6m, D-Shaped<br />

2no. 75m each<br />

PRESSURE SHAFT<br />

Type Underground<br />

Size:<br />

Main 1 No., 4.70m dia,<br />

± 350m long<br />

Branches 3 Nos., 2.70m dia, ± 50m<br />

long each<br />

Velocity 4.32 m/sec.<br />

POWER HOUSE<br />

Type Underground<br />

Installed capacity 108 MW<br />

No. and capacity <strong>of</strong> unit 3 Nos. 36 MW<br />

Size <strong>of</strong> machine hall 67mx15m<br />

Service bay elevation EL 3250m<br />

Type <strong>of</strong> turbine Francis, Vertical axis<br />

Speed <strong>of</strong> turbine 428.60 RPM<br />

Gross Head 177.33 m<br />

Normal tail water level El. 3240.00m<br />

Max. net operating head for<br />

design discharge 182.50m<br />

Minimum net operating head for<br />

design discharge 173.50m<br />

Net operating head for design<br />

discharge 160.00m<br />

Peaking duration 3.00 hrs.<br />

Maximum discharge during peaking hours 75 cumecs.<br />

Firm discharge in 90% dep. Year 11.18 cumecs<br />

TAIL RACE<br />

Size and shape 6.00 m diameter,<br />

D-Shaped concrete lined<br />

Length ± 1150 m<br />

7


SWITCHYARD<br />

Type underground<br />

TRANSMISSION LINE<br />

No. <strong>of</strong> circuits D/C Line<br />

Length <strong>of</strong> each 150Km<br />

Voltage 220.KV<br />

POWER GENERATION<br />

Installed capacity <strong>3x36</strong> MW<br />

Annual energy generation 455.72 MUs<br />

90% dep. Year<br />

8


50 000 MW HYDROELECTRIC INITIATIVE<br />

Government <strong>of</strong> India<br />

<strong>Ministry</strong> <strong>of</strong> <strong>Power</strong><br />

Central Electricity Authority<br />

108 MW CHHATRU<br />

H.E. PROJECT<br />

HIMACHAL PRADESH<br />

Preliminary Feasibility Report<br />

(HYDROLOGY AND POWER POTENTIAL STUDIES)<br />

MARCH ,<br />

22000044<br />

Consultant:<br />

fgekpy izns'k jkT; fctyh cksMZ<br />

Himachal Pradesh State Electricity Board<br />

( H.P.Government Undertaking )


CHAPTER - V<br />

HYDROLOGY<br />

5.1 RIVER CHENAB AND CATCHMENT CHARACTERISTICS.<br />

V -<br />

The river orginates from the snow covered slopes <strong>of</strong> Great Himalayan <strong>of</strong><br />

Pir-Panjal ranges in Lahaul Spiti district and flows in a steep gradient with<br />

a series <strong>of</strong> loopes and bends. The river is formed by the two major<br />

tributaries in the head reaches namely Chandra and Bhaga.The river<br />

Chandra originates from Bara Lachala and is further augmented by<br />

Chandra Tal. The river Bhaga takes <strong>of</strong>f from Suraj Tal in the vicinity <strong>of</strong><br />

Bara Lachala and is further joined by Jhankar and Millang nallahs in the<br />

head reaches. The catchments <strong>of</strong> these two major tributaries have snow<br />

covered peaks at height ranging from ± 3500 m to 5500 m elevation. The<br />

Chandra river and Bhaga river joins at Tandi to form Chandra-Bhaga i.e.<br />

the Chenab. Further downstream <strong>of</strong> confluence, it is joined by other<br />

significant tributaries namely Shansha nallah near Rashil, Thirot nallah at<br />

Thirot, Miyar nallah at Udaipur, Saichu nallah at Dawag, Mahal Nallah at<br />

Killar & Dheda nallah at Lujai d/s <strong>of</strong> Killar. Chenab river drains a<br />

catchments <strong>of</strong> about 7500 Sq. Km. before it crosses in to J&K border.<br />

5.1.1 HYDROMETEOROLOGY OF THE CATCHMENT<br />

This region is a low rainfall area as most <strong>of</strong> the precipitation in the region<br />

is in the form <strong>of</strong> snow. The rainfall takes place during the monsoon months<br />

only and the catchment experiences snowfall during the remaining period<br />

2


V -<br />

<strong>of</strong> the year. There is only one rain gauge station in this region, installed at<br />

Keylong and the rainfall data has not been recorded regularly even at this<br />

station. It is observed that the most <strong>of</strong> the run<strong>of</strong>f in the river results from<br />

the melting <strong>of</strong> snow.<br />

5.2 DISCHARGE DATA AND WATER AVAILABILITY<br />

The discharge data <strong>of</strong> river Chandra at diversion site <strong>of</strong> Chhatru HEP has<br />

been derived from June 1973-May 2000 from the discharge data <strong>of</strong> river<br />

Chandra at Ghousal (site monitored by CWC).<br />

Discharge data <strong>of</strong> river Chandra at Ghousal is given in table 5.1 while the<br />

computed discharge data reduced on catchment area basis at diversion site<br />

is given in Table– 5.2<br />

Based upon ten daily discharge data, a flow duration curve has been<br />

developed. From this curve, it is seen that flow corresponding to 90% &<br />

50% availability works out to 10.41 cumecs & 26.30 cumecs respectively.<br />

The design discharge <strong>of</strong> 75 cumecs is available for 32.15 % <strong>of</strong> the period.<br />

Flow duration curve for lean-season (Dec. to Feb.) has also been<br />

developed . From this curve , it is seen that flow corresponding to 90% &<br />

50% availability works out to 6.96 cumecs & 12.95 cumecs respectively.<br />

5.2.1 CO-RELATION STUDY<br />

W.B. Langbein’s log deviation method has been used to obtain the coefficient<br />

<strong>of</strong> co-relation between discharges <strong>of</strong> river Chandra at Ghousal and<br />

discharges <strong>of</strong> river Bhaga at Tandi.<br />

The Co-relation factors are as follows:<br />

June-July = 0.92<br />

3


Aug.-Sept. = 0.96<br />

Oct.-May = 0.96<br />

These calculations have been shown in Table- 5.3<br />

V -<br />

Similarly coefficient <strong>of</strong> co-relation has been obtained between discharges<br />

<strong>of</strong> river Chenab at Udaipur and the sum <strong>of</strong> discharges <strong>of</strong> river Chandra at<br />

Ghousal & river Bhaga at Tandi.<br />

June-July = 0.94<br />

Aug.-Sept. = 0.96<br />

Oct.-May = 0.88<br />

These calculations have been shown in Table-5.4<br />

From the above co-relation factors it is evident that the discharges <strong>of</strong> river<br />

Chandra at Ghousal & river Bhaga at Tandi including river Chenab at<br />

Udaipur are consistent. Thus the discharges <strong>of</strong> river Chandra at Ghousal<br />

have been approved by CWC and used for carrying out studies which<br />

stands submitted to the CWC and comments are awaited.<br />

5.3 DESIGN FLOOD<br />

The <strong>project</strong> falls in Western Himalayas Zone seven in map <strong>of</strong> India. The<br />

total catchment area <strong>of</strong> river Chenab in India is about 31,047 Sq. Kms. The<br />

catchment is mostly fed by snow. The majority percentage <strong>of</strong> the run<strong>of</strong>f in<br />

the catchment is derived from the snow & glaciers which constitutes a<br />

potential reservoir. Winter precipitation which occurs in the form <strong>of</strong> snow<br />

goes on accumulating till summer. As the summer advances, the<br />

accumulated snow melts and releases water into the stream.<br />

Design Flood has been computed on the basis <strong>of</strong> Flood Estimation report<br />

for Western Himalayas-zone 7 & accordingly <strong>hydro</strong>graphs have been<br />

prepared. The max.. flow due to rain contribution comes out to be 291.59<br />

4


V -<br />

cumecs which has return period <strong>of</strong> 1 in 50 years. The maximum flow for<br />

return period <strong>of</strong> 1 in 100 years is 321.38 cumecs. The snow contribution<br />

has been taken to be 342.09 cumecs ie the maximum discharge <strong>of</strong> flow<br />

during 2 nd week <strong>of</strong> July in flow series at diversion site. Thus the total<br />

design flood works out to be 663.47 cumecs. Flood frequency analysis has<br />

also been carried out by Gumble’s method.<br />

Return period <strong>of</strong> 1 in 1000 years has been considered for computing the<br />

SPF which works out to be 1377.59 cumecs. The designed flood has been<br />

taken as 1500 cumecs. The computations have been shown in Annexure-<br />

V-1.<br />

5.4 SEDIMENTATION ASPECTS<br />

Detailed studies shall be carried out at DPR stage. However 20% <strong>of</strong> the<br />

live storage has been proposed to be kept reserved for silt deposition in the<br />

reservoir.<br />

5


V -<br />

6


PARA DESCRIPTION PAGE<br />

5.1 RIVER CHENAB AND CATCHMENT<br />

CHARACTERISTICS<br />

V -<br />

5.1.1 HYDROMETEOROLOGY OF THE CATCHMENT V-1<br />

5.2 DISCHARGE DATA AND WATER AVAILABILITY V-2<br />

5.2.1 CO-RELATION STUDIES V-2 TO V-3<br />

5.3 DESIGN FLOOD V-3 TO V-4<br />

5.4 SEDIMENTATION ASPECTS V-4<br />

5.5 COMMENTS BY CWC V-4<br />

TABLE – 5.1 TEN DAILY AVERAGE DISCHARGE DATA OF<br />

RIVER CHANDRA AT GHOUSAL<br />

TABLE – 5.2 COMPUTED DISCHARGE DATA AT DIVERSION<br />

SITE<br />

V-1<br />

INFLOWS OF RIVER CHANDRA AT GHOUSAL V-15<br />

INFLOWS OF RIVER BHAGA AT TANDI V-16<br />

TABLE-5.3 CO-RELATION BETWEEN DISCHARGES OF<br />

RIVER CHANDRA AT GHOUSAL & RIVER<br />

BHAGA AT TANDI<br />

INFLOWS OF RIVER CHENAB AT UDAIPUR V-23<br />

INFLOWS OF RIVER BHAGA AT TANDI PLUS<br />

RIVER CHANDRA AT GHOUSAL<br />

TABLE-5.4 CO-RELATION BETWEEN DISCHARGES OF<br />

RIVER CHENAB AT UDAIPUR & THE SUM OF<br />

DISCHARGES OF RIVER CHANDRA AT<br />

GHOUSAL & RIVER BHAGA AT TANDI<br />

7<br />

V-5 TO V-9<br />

V-10 TO V-14<br />

V-17 TO V-22<br />

V-24<br />

V-25 TO V-30<br />

ANNEX.-5 DESIGN FLOOD COMPUTATIONS V-31 TO V-40<br />

PLATE -5.1 FLOW DURATION CURVE (OVER ALL) V-41<br />

PLATE -5.2 FLOW DURATION CURVE (LEAN SEASON) V-42<br />

PLATE -5.3 SYNTHETIC UNIT HYDROGRAPH V-43<br />

PLATE -5.4 DESIGN FLOOD HYDROGRAPH V-44<br />

ANNEXURE-V COMMENTS


1. INTRODUCTION<br />

HIMACHAL PRADESH STATE ELECTRICITY BOARD<br />

EXECUTIVE SUMMARY<br />

As a part <strong>of</strong> an exercise to assess the balance <strong>hydro</strong> potential <strong>of</strong> the country<br />

Central Electricity Authority(CEA ) identified more than 399 Hydro-<strong>electric</strong><br />

Projects with probable installed capacity <strong>of</strong> 1,50,000 MW. After carrying<br />

out ranking studies, 162 <strong>project</strong>s have been identified for preparation <strong>of</strong><br />

Preliminary Feasibility Reports. Chhatru in Chenab basin has been<br />

identified as one <strong>of</strong> these <strong>project</strong>s for preparation <strong>of</strong> PFR by HPSEB so that<br />

it could be taken up for further development during the 10th & 11th Plans.<br />

The identified Chhatru HEP in Lahaul & Spiti valley in HP by CEA<br />

involved construction <strong>of</strong> diversion weir on Chandra river<br />

(32°18’11”Latitude 77°24’41”Longitude) 5 km. upstream <strong>of</strong> village Chhatru<br />

and river Beas and a power house about 3.5 km d/s <strong>of</strong> Chhatru village on<br />

right bank <strong>of</strong> Chandra river (32°20’9”- Latitude 77°20’51” Longitude) with<br />

an installed capacity <strong>of</strong> 108 MW.<br />

A site visit was made to the area by engineers <strong>of</strong> HPSEB and Geologists <strong>of</strong><br />

GSI during January, 2004 for identification /selection <strong>of</strong> suitable site. The<br />

identified/ proposed Chhatru Hydro-<strong>electric</strong> Project is located about 5 km.<br />

u/s <strong>of</strong> village Chhatru (El. ± 3405m). The <strong>project</strong> has been found technoeconomically<br />

feasible. It is located along a motorable road. The diversion<br />

site <strong>of</strong> <strong>project</strong> is also well connected to road, whereas <strong>project</strong> roads have<br />

been proposed to power house and surge shaft. The <strong>project</strong> is about 410<br />

km. approx. from Chandigarh.<br />

2. SCOPE OF THE PROJECT


The <strong>project</strong> comprises a diversion barrage on river Chandra +19m high<br />

above river bed level, an intake arrangement on the right bank, for drawing<br />

discharge <strong>of</strong> 93.75 cumecs, through 6m dia approach tunnel leading to an<br />

underground desilting arrangement comprising two no chambers each<br />

(381mx13mx19.60m), to exclude all particles down to 0.20mm, 5.10m dia,<br />

6500m long modified horse shoe shaped tunnel designed for a discharge <strong>of</strong><br />

75 cumecs, opening into one 15m dia underground restricted orifice type<br />

surge shaft, one pressure shaft <strong>of</strong> 4.70m dia 350m long bifurcating into three<br />

2.70m dia, 50 long each branch pressure shafts feeding three Francis vertical<br />

axis generating units <strong>of</strong> 36 MW each, through a net head <strong>of</strong> 160m in an<br />

underground power house on the right bank <strong>of</strong> Chandra river about 3.50 km.<br />

d/s <strong>of</strong> Chhatru village. The <strong>project</strong> will enable energy generation <strong>of</strong> 455.72<br />

GWH in 90% dependable year at power house bus bars.<br />

3. HYDROLOGY<br />

The river orginates from the snow covered slopes <strong>of</strong> Great Himalayan <strong>of</strong><br />

Pir-Panjal ranges in Lahaul Spiti district and flows in a steep gradient with a<br />

series <strong>of</strong> loopes and bends. The river is formed by the two major tributaries<br />

in the head reaches namely Chandra and Bhaga.The river Chandra originates<br />

from Bara Lachala and is further augmented by Chandra Tal. The river<br />

Bhaga takes <strong>of</strong>f from Suraj Tal in the vicinity <strong>of</strong> Bara Lachala and is further<br />

joined by Jhankar and Millang nallahs in the head reaches. The catchments<br />

<strong>of</strong> these two major tributaries have snow covered peaks at height ranging<br />

from ± 3500 m to 5500 m elevation. The Chandra river and Bhaga river<br />

joins at Tandi to form Chandra-Bhaga i.e. the Chenab. Further downstream<br />

<strong>of</strong> confluence, it is joined by other significant tributaries namely Shansha<br />

nallah near Rashil, Thirot nallah at Thirot, Miyar nallah at Udaipur, Saichu<br />

nallah at Dawag, Mahal Nallah at Killar & Dheda nallah at Lujai d/s <strong>of</strong><br />

Killar. Chenab river drains a catchments <strong>of</strong> about 7500 Sq. Km. before it<br />

crosses in to J&K border.


This region is a low rainfall area as most <strong>of</strong> the precipitation in the region is<br />

in the form <strong>of</strong> snow. The rainfall takes place during the monsoon months<br />

only and the catchment experiences snowfall during the remaining period <strong>of</strong><br />

the year. There is only one rain gauge station in this region, installed at<br />

Keylong and the rainfall data has not been recorded regularly even at this<br />

station. It is observed that the most <strong>of</strong> the run<strong>of</strong>f in the river results from the<br />

melting <strong>of</strong> snow.<br />

The discharge data <strong>of</strong> river Chandra at diversion site <strong>of</strong> Chhatru HEP has<br />

been derived from June 1973-May 2000 from the discharge data <strong>of</strong> river<br />

Chandra at Ghousal (site monitored by CWC). W.B. Langbein’s log<br />

deviation method has been used to obtain the co-efficient <strong>of</strong> co-relation<br />

between discharges <strong>of</strong> river Chandra at Ghousal and discharges <strong>of</strong> river<br />

Bhaga at Tandi.<br />

The design flood works out to be 663.47 cumecs. Flood frequency analysis<br />

has also been carried out by Gumble’s method. The designed flood has been<br />

taken as 1500 cumecs. Similarly coefficient <strong>of</strong> co-relation has been<br />

obtained between discharges <strong>of</strong> river Chenab at Udaipur and the sum <strong>of</strong><br />

discharges <strong>of</strong> river Chandra at Ghousal & river Bhaga at Tandi.<br />

From the above co-relation factors it is evident that the discharges <strong>of</strong> river<br />

Chandra at Ghousal & river Bhaga at Tandi including river Chenab at<br />

Udaipur are consistent. Thus the discharges <strong>of</strong> river Chandra at Ghousal<br />

have been approved by CWC and used for carrying out studies which stands<br />

submitted to the CWC and comments are awaited.<br />

4. POWER POTENTIAL STUDIES<br />

Chhatru Hydro-<strong>electric</strong> Project has been contemplated as a peaking station<br />

to operate in Western part <strong>of</strong> North Regional Grid. Installed capacity <strong>of</strong> the<br />

<strong>project</strong> has been presently kept as 108 MW comprising 3 units <strong>of</strong> 36 MW


each. The <strong>project</strong> will generate 455.72 GWH in 90% dependable year.<br />

Accordingly energy exploitation <strong>of</strong> 62.08% with plant load factor <strong>of</strong> 50% in<br />

90% dependable year will be accomplished.<br />

5. POWER EVACUATION ASPECTS<br />

During the 14 th meeting <strong>of</strong> the Standing Committee on Transmission system<br />

planning <strong>of</strong> Northern Region held on 30.12.02, it has been decided that<br />

PGCIL will construct a Parbati Pooling Point at downstream <strong>of</strong> Parbati-III<br />

HEP which will cater to Allain-Duhangan, Malana-II and other<br />

<strong>project</strong>s/small HEPs <strong>of</strong> Himachal Pradesh. Hence, it is proposed to<br />

evacuate power generated at Chhatru <strong>project</strong> by laying a 15 km. long, 220<br />

KV D/C line from Khoksar to 400 KV pooling point at Tandi.Beyond which<br />

the evacuation will be through 400 KV D/C net work to Pooling point at<br />

Panarsa sub station <strong>of</strong> PGCIL.<br />

6. ENVIRONMENTAL ASPECTS<br />

Environmental Management Plan (EMP) aims at the preservation <strong>of</strong><br />

ecological system by considering certain mitigating measures at the<br />

proposed site. The EMP is required to ensure sustainable development in<br />

the study area <strong>of</strong> 10 km. radius <strong>of</strong> the proposed Chhatru HEP site.<br />

Government regulating agencies like Pollution Control Board working in<br />

the region and more importantly the people living in the area need to extend<br />

their co-operation and contribution in this direction.<br />

It has been evaluated that the study area shall not be affected adversely with<br />

the proposed activity , but is likely to get new economical fillip due to hydel<br />

power generation, not only for the study area but also for the region as<br />

whole.


7. ESTIMATES OF COST<br />

The estimates <strong>of</strong> cost has been prepared on the basis <strong>of</strong> “CEA Guidelines for<br />

rates and cost <strong>of</strong> civil and <strong>electric</strong>al works for Preliminary Feasibility<br />

Reports <strong>of</strong> Hydro-<strong>electric</strong> Projects” received during Oct. 2003.<br />

Accordingly cost <strong>of</strong> <strong>project</strong> works out to be Rs.386.79 crore for civil works,<br />

Rs. 136.12.crore for <strong>electric</strong>al works and Rs. 8.45 crore for transmission<br />

works.<br />

8. FINANCIAL ASPECTS<br />

The financial & economic evaluation has been carried out as per CEA<br />

guide lines considering Interest During Construction (IDC) @ 10% and<br />

interest on working capital @ 9.75%. The life <strong>of</strong> <strong>hydro</strong>-<strong>electric</strong> <strong>project</strong> has<br />

been considered as 35 years. The 455.72 GWH energy units are available<br />

at power house bus bars in 90% dependable year and cost per unit at power<br />

house bus bars works out to Rs. 2.89 per Kwh in the first year <strong>of</strong> operation.<br />

The levelised tariff rate <strong>of</strong> energy works out to be Rs.2.28 per Kwh.<br />

9. CONCLUSION<br />

The economy <strong>of</strong> the Himachal Pradesh is predominantly dependent on<br />

agricultural and allied sectors. The <strong>electric</strong> power being a vital and essential<br />

infrastructure has a significant role to play in economic upliftment <strong>of</strong> the<br />

state. The construction <strong>of</strong> <strong>project</strong> will provide employment to the local<br />

people. The <strong>project</strong> has a distinct advantage <strong>of</strong> being located along a<br />

motorable road making it possible to be completed within four and half<br />

years period.


INDEX<br />

SR.NO. DESCRIPTION PAGE<br />

CHAPTER-I SUMMARY I-1 TO I-6<br />

CHAPTER-II BACKGROUND INFORMATION II-1 TO II-2<br />

CHAPTER-III PROJECT AREA III-1 TO III-2<br />

CHAPTER-IV TOPOGRAPHIC AND GEOTECHNICAL<br />

ASPECTS<br />

IV-1 TO IV-7<br />

CHAPTER-V HYDROLOGY V-1 TO V-52<br />

CHAPTER-VI CONCEPTUAL LAYOUT & PLANNING VI-1 TO VI-35<br />

CHAPTER-VII POWER POTENTIAL STUDIES VII-1 TO VII-45<br />

CHAPTER-VIII POWER EVACUATION VIII-1 TO VIII-10<br />

CHAPTER-IX ENVIRONMENTAL ASPECTS IX-1 TO IX- 22<br />

CHAPTER-X INFRASTRUCTURE X-1 TO X-7<br />

CHAPTER-XI CONSTRUCTION PROGRAMME XI-1 TO XI-7<br />

CHAPTER-XII COST ESTIMATE XII-1 TO XII-34<br />

CHAPTER-XIII ECONOMIC EVALUATION XIII-1 TO XIII-14


PARA DESCRIPTION PAGE<br />

1.0 SUMMARY I-1<br />

1.1 GENERAL PROJECT FEATURES I-4<br />

1.2 STUDIES UNDERTAKEN I-4 TO I-5<br />

1.3 COST ESTIMATE & FINANCIAL ASPECTS I-5 TO I-6<br />

PLATE 1.1 ALTERNATIVE PROPOSAL


1.0 SUMMARY<br />

CHAPTER – I<br />

SUMMARY<br />

The Chhatru Hydro-<strong>electric</strong> Project has been contemplated as a power<br />

generation development on river Chandra in Lahul & Spiti District <strong>of</strong> H.P.<br />

It is an upstream development <strong>of</strong> Proposed Khoksar Hydro-<strong>electric</strong> Project<br />

(90MW) preliminary feasibility report <strong>of</strong> which has been submitted to CEA<br />

recently by HPSEB and is located about 410 km. from Chandigarh. The<br />

<strong>project</strong> envisages utilization <strong>of</strong> river Chandra water through a gross head <strong>of</strong><br />

177.33m for generation <strong>of</strong> 108MW <strong>of</strong> power in a power station.<br />

GENERAL PROJECT FEATURES<br />

LOCATION<br />

State Himachal Pradesh<br />

District Lahaul Spiti<br />

River Chandra river(Chenab Basin)<br />

Barrage site ± 5 km. u/s <strong>of</strong> Chhatru village<br />

<strong>Power</strong> house site ± 3.5 km d/s <strong>of</strong> Chhatru village on right<br />

bank <strong>of</strong> Chandra river


HYDROLOGY<br />

Catchment Area<br />

at diversion site 1583 Sq. km.<br />

Snow catchment 48 Sq. km. above El. 4200m<br />

Probable maximum flood 1500cumecs<br />

Standard <strong>project</strong> flood<br />

Observed maximum flood 828.00 cumsecs<br />

RESERVOIR<br />

Full reservoir (FRL) 3421.00m<br />

Maximum reservoir level (MRL) 3422.00m<br />

Maximum draw down level (MDDL) 3413.50m<br />

Gross storage upto FRL 112.50 Hect-m<br />

Live storage 87.50 Hect-m<br />

Net live storage 70.00 Hect-m<br />

DIVERSION STRUCTURE<br />

Type Barrage<br />

Max. height from R.B.L. 19m<br />

Elevation <strong>of</strong> top <strong>of</strong> dam or bridge ±3424.00m<br />

Average bed level ±3405.00m<br />

SPILLWAY<br />

Design flood 1500cumecs<br />

Type Gated spillways with radial gates<br />

Nos. <strong>of</strong> spillways, Crest elevation 6 Nos. El. 3407.00m<br />

Length <strong>of</strong> gated spillways 5.00m each.<br />

Energy dissipation<br />

Length 98.00m<br />

Down stream bed level ±3403.00m<br />

INTAKE STRUCTURE<br />

Type Surface<br />

Sill level El. 3410.00m<br />

No. & size <strong>of</strong> opening 8 Nos., 5.50mx3.0m<br />

APPROACH TUNNEL<br />

No. 1<br />

Size and type 6.00m dia, Circular concrete Lined<br />

Velocity 3.30m/sec<br />

Length 200m<br />

Design discharge from intake 93.75 cum/sec<br />

DESANDING BASIN<br />

Type Underground, central gutter type<br />

No. <strong>of</strong> basins 2 nos.


Length <strong>of</strong> each basin 381m<br />

Size <strong>of</strong> basins Width13.00m,Depth 19.60m<br />

Minimum particle size to be removed 0.2mm<br />

Flushing tunnel, size 4.00m, D-Shaped<br />

Flushing tunnel, length 1000m<br />

HEAD RACE TUNNEL<br />

No. 1<br />

Size & Shape 5.10m diameter, Modified<br />

Horse shoe shaped Concrete lined<br />

Length 6500 m<br />

Design discharge 75 cumecs<br />

Slope 1 in 120.50 m<br />

Velocity 3.63m/sec<br />

Adit 275m leangth 5m D- shaped<br />

SURGE SHAFT<br />

Type Underground, restricted orifice type<br />

Size 15m dia, 91.80m high<br />

Orifice 2.50m dia<br />

Maximum upsurge level El. 3436.10m<br />

Minimum down surge level El. 3396.60m<br />

Bottom level El. 3350.50m<br />

Top level El. 3436.00m<br />

Adit to top <strong>of</strong> surge shaft 4mx6m, D-Shaped<br />

2no. 75m each<br />

PRESSURE SHAFT<br />

Type Underground<br />

Size:<br />

Main 1 No., 4.70m dia,<br />

± 350m long<br />

Branches 3 Nos., 2.70m dia, ± 50m<br />

long each<br />

Velocity 4.32 m/sec.<br />

POWER HOUSE<br />

Type Underground<br />

Installed capacity 108 MW<br />

No. and capacity <strong>of</strong> unit 3 Nos. 36 MW<br />

Size <strong>of</strong> machine hall 67mx15m<br />

Service bay elevation EL 3250m<br />

Type <strong>of</strong> turbine Francis, Vertical axis


Speed <strong>of</strong> turbine 428.60 RPM<br />

Gross Head 177.33 m<br />

Normal tail water level El. 3240.00m<br />

Max. net operating head for<br />

design discharge 182.50m<br />

Minimum net operating head for<br />

design discharge 173.50m<br />

Net operating head for design<br />

discharge 160.00m<br />

Peaking duration 3.00 hrs.<br />

Maximum discharge during peaking hours 75 cumecs.<br />

Firm discharge in 90% dep. Year 11.18 cumecs<br />

TAIL RACE<br />

Size and shape 6.00 m diameter, D-Shaped<br />

concrete lined<br />

Length ± 1150 m<br />

SWITCHYARD<br />

Type underground<br />

TRANSMISSION LINE<br />

No. <strong>of</strong> circuits D/C Line<br />

Length <strong>of</strong> each 150Km<br />

Voltage 220.KV<br />

POWER GENERATION<br />

Installed capacity <strong>3x36</strong> MW<br />

Annual energy generation 455.72 MUs<br />

90% dep. Year<br />

1.2 STUDIES UNDERTAKEN<br />

The Layout <strong>of</strong> the Chhatru HEP has been finalized keeping in view various<br />

studies undertaken by HPSEB from time to time to conceive a most<br />

economical and viable scheme on Chandra river above the proposed<br />

Khoksar HEP.


Proposal-I<br />

The proposed Chhatru HEP envisages diversion <strong>of</strong> river Chandra about<br />

5km. u/s <strong>of</strong> Chhatru village in Lahaul & Spiti Distt. <strong>of</strong> Himachal Pradesh at<br />

El. 3405m by constructing a diversion Barrage comprising 6 nos. spill bayse<br />

bays each <strong>of</strong> size 5.00mx6.00m with crest El. at 3407m to pass the design<br />

flood <strong>of</strong> 1500 cumecs. The reservoir formed u/s <strong>of</strong> the barrage shall provide<br />

a peaking storage for 3 hrs. The diverted flows will be carried to<br />

underground desilting tank designed to exclude all silt particles down to<br />

0.20 mm size. The inflows will further be carried to surge tank 91.80 high,<br />

15m dia, through 5.10m modified house shoe shaped head race tunnel ±<br />

6.50 km. long . From surge tank, the flow will be carried to underground<br />

power house located on right bank <strong>of</strong> Chandra river through a 4.70m dia.<br />

Pressure shaft bifurcating near the power house to feed 3 nos. vertical axis<br />

generating units <strong>of</strong> 36 MW (108MW) installed capacity each, utilizing a<br />

design discharge <strong>of</strong> 75 cumecs and net head <strong>of</strong> 160 m. Further the water<br />

shall be discharge to Chandra river through underground tail race ± 1150m<br />

long and 6.00m dia D-shaped tunnel.<br />

Proposal-II<br />

About 600m d/s <strong>of</strong> the Proposal-I the diversion barrage has been proposed,<br />

where river terrace <strong>of</strong> about 200m width is available as proposed in GSI<br />

report. The proposal envisages the diversion at El. ± 3397m, to pass a<br />

design flood <strong>of</strong> 1500 cumecs. The diverted flow will be further carried to<br />

underground desilting tank, designed to exclude all silt particles down to<br />

0.20mm size. The inflow will further be carried to surge tank 91.80 high,<br />

15m dia, through 5.10m modified horse shoe shaped head race tunnel<br />

±6.00km. The flow will be carried to under ground power house to feed 3<br />

nos. generating units each <strong>of</strong> 33 MW (99MW) installed capacity each,<br />

utilizing a design discharge <strong>of</strong> 75 cumecs and net head <strong>of</strong> 151m. The HRT


after Chhatru nallah, surge shaft, pressure shaft, power house and tail race<br />

are the same <strong>of</strong> as Proposal-I.<br />

The proposal has been rejected on the fact that the installed capacity <strong>of</strong> the<br />

<strong>project</strong> has been reduced from 108 MW to 99 MW and there is always threat<br />

<strong>of</strong> Hamta glacier to damage the diversion structure <strong>of</strong> the <strong>project</strong>.<br />

The alternative proposals are shown in Plate-1.1.<br />

1.3 COST ESTIMATE & FINANCIAL ASPECTS<br />

COST ESTIMATE<br />

Capital cost <strong>of</strong> the <strong>project</strong> (At Price level Oct.2003):<br />

Civil works Rs. 386.79 Crore<br />

Electrical works<br />

(P-Production) Rs. 136.12Crore<br />

Cost <strong>of</strong> generation Rs. 522.91 Crore<br />

T-Transmission Rs. 8.45 Crore<br />

Total Rs 531.36 Crore<br />

Capital cost <strong>of</strong> Generation Rs. 585.15 Crore<br />

(Including IDC Rs. 62.24Crore)<br />

Loan 70% Rs. 409.60Crore<br />

Equity 30% Rs. 175.54Crore<br />

FINANCIAL ASPECTS<br />

Cost <strong>of</strong> generation per MW <strong>of</strong><br />

Installed capacity Rs. 4.84Crore<br />

Levelized tariff at PH<br />

Bus bars in 90% dep. Year<br />

Rs. 2.28/Kwh


Energy available in 90% dep. Year<br />

at power house bus bars<br />

455.72GWH


PARA DESCRIPTION PAGE<br />

2.0 BACK GROUND INFORMATION II-1<br />

2.1 GENERAL INFORMATION II-1<br />

2.2 POWER SCENARIOS & EXISTING<br />

INSTALLATIONS<br />

2.2.1 POWER ABSORPTION IN NORTH REGION II-1<br />

2.2.2 POWER LOAD DEVELOPMENT II-1 TO II-2<br />

2.3 NECESSITY OF THE PROJECTS AND<br />

RELATED ASPECTS<br />

PLATE 2.1 MASTER PLAN OF BEAS BASIN<br />

II-1<br />

II-2


CHAPTER – II<br />

BACKGROUND INFORMATION<br />

2.0 BACKGROUND INFORMTION<br />

2.1 GENERAL INFORMATION<br />

Hydel potential <strong>of</strong> Chenab basin in H.P. has been identified as 3155.30 MW<br />

as indicated in Plate –2.1 for this basin. The hydel <strong>project</strong>s under operation<br />

are Sisu (0.10 MW),Biling(0.20 Mw), Shansha(0.20 MW), Killar (0.30<br />

MW) and Thirot (4.50 MW) in this basin. The proposed <strong>project</strong>s as per<br />

CEA ranking study are Chhatru (108 MW), Khoksar (90 MW), Gondhala<br />

(144 Mw), Bardang(114 MW) and Sach-Khas (70 MW) in addition to<br />

Tunsha(150 MW), Rashil(150 MW), Palam(60 MW), Tingal(81 MW),<br />

Miyar(90 MW), Seli(600 MW), Dugli(360 MW), Sagpari(210 Mw) and<br />

Dugar (360 <strong>mw</strong>). The investigation <strong>of</strong> Gyspa (240 MW) is already under<br />

investigation.<br />

2.2 POWER SCENARIOS & EXISTING INSTALLATIONS<br />

2.2.1 POWER ABSORPTION IN NORTHERN REGION<br />

2.2.2 POWER LOAD DEVELOPMENT<br />

The Northern Region comprises the states <strong>of</strong> Himachal, Haryana, Punjab,<br />

Rajashtan, Jammu & Kashmir, Uttar Pradesh and Union territory <strong>of</strong> Delhi<br />

and Chandigarh. The Northern Regional <strong>Power</strong> Grid comprises the power<br />

system controlled by the Electricity Boards <strong>of</strong> above states/Union territories<br />

and Bhakhra Beas Management Board.<br />

The <strong>Power</strong> system in this region is now operating in an inter-connected and<br />

co-ordinated manner. Even in co-ordinated operation <strong>of</strong> existing <strong>hydro</strong>,<br />

nuclear and thermal power stations, including benefits from the ongoing


<strong>project</strong>s and as well from the new schemes cleared by CEA, the Northern<br />

region is expected to face severe power deficits in the 10 th Five Year Plan.<br />

2.3 NECESSITY OF THE PROJECT AND RELATED ASPECTS<br />

From the growth <strong>of</strong> peak demand and anticipated installed generation<br />

capacity on the basis <strong>of</strong> schemes proposed for benefits under<br />

construction/consideration during 9 th and early 10 th Five Year Plan period it<br />

is observed that power supply position in the Northern region would become<br />

all the more acute from the start <strong>of</strong> 10 th Five Year Plan and power region<br />

shortages would have to be faced unless additional schemes are taken up<br />

immediately and implemented to derive timely benefits. The most<br />

important source <strong>of</strong> power development in the Northern region is its<br />

abundant <strong>hydro</strong> resources located in Himachal Pradesh, Uttar Pradesh and<br />

Jammu & Kashmir. Priority would have to be given to the development <strong>of</strong><br />

these untapped resources because <strong>of</strong> the following distinguishing features <strong>of</strong><br />

the <strong>hydro</strong> stations.<br />

i) They estimate the most economic source <strong>of</strong> power development.<br />

ii) They provide the cheapest source <strong>of</strong> peaking capacity.<br />

iii) They enable improvement in the utilization <strong>of</strong> thermal/nuclear power<br />

stations in the region.<br />

iv) They provide much needed operation & flexibility to the system.<br />

Thus there is an urgent need <strong>of</strong> rapid <strong>hydro</strong> potential exploitation for<br />

providing additional generation capacity in the Northern region. Among the<br />

various sites, available for <strong>hydro</strong> development, Gharopa Hydro-<strong>electric</strong><br />

Project is considered very attractive from point <strong>of</strong> view <strong>of</strong> deriving benefits<br />

during 11 th Five Year Plan. The <strong>project</strong> is located on NH-21 and all the<br />

sites are well connected with NH-21. The existing communication facilities<br />

will be <strong>of</strong> considerable utility in cutting down the pre-construction time.


PARA DESCRIPTION PAGE<br />

3.0 PROJECT AREA III-1<br />

3.1 DESCRIPTION OF PROJECT INCLUDING<br />

RIVER SYSTEM<br />

III-1<br />

3.2 SOCIO ECONOMIC AND OTHER ASPECTS III-2


CHAPTER – III<br />

PROEJCT AREA<br />

3.0 PROJECT AREA<br />

3.1 DESCRIPTION OF PROJECT INCLUDING RIVER SYSTEM<br />

Himachal Pradesh has the unique distinction <strong>of</strong> providing water both to the<br />

Indus and Ganges basins. The major river systems <strong>of</strong> the region are<br />

Chander Bhaga or Chenab , the Ravi, the Satluj and the Yamuna. These<br />

perennial rivers are both snow and rain fed and are protected by fairly<br />

extensive cover <strong>of</strong> natural vegetation.<br />

River Chandra originates from the snow covered slopes <strong>of</strong> Great Himalayan<br />

<strong>of</strong> Pir Panjal ranges in Lahaul Spiti Distt. flows in a steep gradient. The<br />

river is formed by the two major tributaries namely Chandra & Bhaga.<br />

This <strong>project</strong> comprises a diversion barrage on river Chandra, ± 19m high<br />

above river bed level near village Chhatru, an intake arrangement on the<br />

right bank for drawing discharge <strong>of</strong> 93.75 cumecs through two approach<br />

tunnels leading to an underground desilting arrangement to exclude all silt<br />

particles down to 0.2mm, 5.10m dia, 6500m long modified horse show<br />

shaped tunnel designed for a discharge <strong>of</strong> ± 75 cumecs opening into one<br />

15m dia, underground restricted orifice type surge shaft, one pressure shaft<br />

<strong>of</strong> 4.70m dia 350m long bifurcating into three 2.70m dia, 50m long each<br />

branch pressure shafts, feeding three Francis vertical axis generating units <strong>of</strong><br />

36 MW each through a net head <strong>of</strong> 160m in an underground power house<br />

on the right bank <strong>of</strong> Chandra river. The <strong>project</strong> will enable energy<br />

generation <strong>of</strong> 455.72 GWH in 90% dependable year <strong>of</strong> flows.


3.2 SOCIO-ECONOMIC AND OTHER ASPECTS<br />

The economy <strong>of</strong> the Himachal Pradesh is predominantly dependent on<br />

agricultural and allied sectors. The per capital income <strong>of</strong> Himachal Pradesh<br />

in 1997-98 was Rs. 8747 as compared to Rs. 10400 at the national level.<br />

The <strong>electric</strong> power being a vital and essential infrastructure has a significant<br />

role to play in economic upliftment <strong>of</strong> the state. The construction <strong>of</strong> <strong>project</strong><br />

will provide employment to the local people. When completed it will be<br />

another step towards realization <strong>of</strong> the dreams <strong>of</strong> the state and exploiting its<br />

power potential for heralding an era <strong>of</strong> progress and prosperity for not only<br />

<strong>of</strong> Himachal Pradesh but for the entire northern region.


PARA DESCRIPTION PAGE<br />

4.0 GEOLOGY IV-1<br />

4.1 INTRODUCTION IV-1<br />

4.2 REGIONAL GEOLOGY IV-1 TO IV-3<br />

4.3 STRUCTURE & TECTONICS IV-4 TO IV-5<br />

4.4 SEISMO TECTONICS AND SEISMICITY IV-5 TO IV-6<br />

4.5 GEO-TECHNICAL APPPRAISAL IV-6 TO V-7<br />

4.6 REFERENCES IV-7<br />

PLATE- 4.1 GEOLOGICAL MAP


CHAPTER – IV<br />

TOPOGRAPHIC & GEO-TECHNICAL<br />

ASPECTS<br />

The geo-technical studies <strong>of</strong> <strong>project</strong> area have been got carried out from GSI<br />

during Jan. 2004 which is appended in below;<br />

4.0 GEOLOGY OF AREA AROUND CHHATRU HYDROELECTRIC<br />

PROJECT, CHENAB BASIN, LAHAUL AND SPITI DISTRICT,<br />

HIMACHAL PRADESH.<br />

4.1 INTRODUCTION<br />

The Central Electricity Authority in an effort to assess the balance<br />

<strong>hydro</strong><strong>electric</strong> potential in the country have identified 1,50,000 MW <strong>of</strong><br />

balance <strong>hydro</strong><strong>electric</strong> potential which can be harnessed through 399<br />

proposed schemes. After carrying out ranking studies, the CEA have<br />

selected a few schemes in Chandra valley <strong>of</strong> which Chhatru is one that is<br />

being taken up in the first phase for preparation <strong>of</strong> Pre Feasibility Reports.<br />

The proposed Chhatru Hydro<strong>electric</strong> Project is located on Chandra river,<br />

upstream <strong>of</strong> its confluence with Bhaga river and upstream <strong>of</strong> the village<br />

Chhatru in Lahaul and Spiti district <strong>of</strong> Himachal Pradesh.<br />

The proposed scheme is a run <strong>of</strong> river scheme that envisages construction <strong>of</strong><br />

a diversion dam/ weir across the river Chandra, 5 Km upstream <strong>of</strong> the<br />

village Chhatru (32 0 18’00” N: 77 0 28’ 00” E; 52 H/7), a water conductor<br />

system comprising 12 km long head race tunnel and a powerhouse on the<br />

right bank <strong>of</strong> Chandra River, about 3.5 km upstream <strong>of</strong> Chhatru bridge<br />

(32 0 19’00” N: 77 0 27’00” E; 52 H/7) with probable installed capacity <strong>of</strong> 140<br />

MW.<br />

4.2 REGIONAL GEOLOGY<br />

The area where <strong>project</strong> is located forms a part <strong>of</strong> Great Himalayan Range<br />

and constitutes both northern and southern slopes <strong>of</strong> Chandra Valley. The<br />

altitude in the area, varies between 2750m and 6020m. The terrain in upper<br />

reaches <strong>of</strong> tributaries shows typical glacial landscape characterized by<br />

rugged towering peaks, cirque glaciers and moraine deposits. Chandra river<br />

forms the main drainage <strong>of</strong> the area. It is joined by a number <strong>of</strong> tributaries<br />

on its either bank. These are mostly snow/ glacier fed. These tributaries


show sub-dendritic to trellis pattern. The higher reaches <strong>of</strong> slopes on either<br />

side <strong>of</strong> Chandra river have a number <strong>of</strong> glaciers which form the perennial<br />

source <strong>of</strong> discharge in tributaries. There are several conspicuous moraines<br />

that are well developed towards left bank. There are a number <strong>of</strong> water falls<br />

in the area <strong>of</strong> which the one at Sissu village and that about 4 km upstream <strong>of</strong><br />

Sissu Nala are prominent ones. The presence <strong>of</strong> abundant waterfalls in the<br />

area, besides glacier fed discharge is attributable to thick-bedded nature <strong>of</strong><br />

rocks and flat disposition <strong>of</strong> beds. Besides drainage, the lakes are a common<br />

feature in glacial terrain. The lower Chandra valley is characterized by the<br />

river terraces that are being used for habitation and cultivation by local<br />

inhabitants. Although three levels <strong>of</strong> terraces have been identified in Sissu<br />

area, only one prominent terrace has been identified in Chhatru and Khoksar<br />

areas. These terraces are very thick and extend up to 3225 m elevation in<br />

lower reaches i.e. near Sissu and Retil villages.<br />

The valley slopes in the area are characterised by the stretches <strong>of</strong> unusually<br />

abundant debris. These could have been due to the fractured or weathered<br />

rocks transported in abundance by snow, avalanches and landslides to the<br />

lower elevations on the banks <strong>of</strong> the river.<br />

The area around the proposed <strong>project</strong>s exposes the rocks belonging to<br />

Rohtang Group <strong>of</strong> Pre-Cambrian age (Prashara & Kumbkarni, 1986-87).<br />

But same has been named as Lahul Group by Prashra (1992). At higher<br />

elevations, it is succeeded by the rocks belonging to Haimanta Group in the<br />

east and those belonging to Vaikrita Group extending from Chandra area in<br />

west.<br />

The Pre-Cambrian stratigraphic succession in the area given by Prashra at El<br />

(1986-87) and Prashra (1992) is given below:-<br />

GROUP FORMATIO<br />

N<br />

Haimanta<br />

Kunzum La<br />

Batal<br />

Chola Thach<br />

LITHOLOGY AGE<br />

Greenish grey siltstone, shale &<br />

dolomite<br />

Quartzite, phyllite, carbonaceous and<br />

pyritous<br />

( It also includes Manjir and Katarigali<br />

Formations)<br />

Garnetiferous schist and quartzite<br />

Proterozoic


Lahaul or Rohtang<br />

Gneissic Group<br />

Gufa<br />

Damphung<br />

Kulti<br />

Granite gneiss, migmatite and meta<br />

sediments<br />

Matamorphites with subordinate gneiss<br />

and migmatite<br />

Granite gneiss, migmatites with high<br />

grade metamorphites<br />

According to Prashra (1992), the rocks <strong>of</strong> Lahaul Group are divisible into<br />

two lithological units i.e. Rohtang Gneissic Complex and Chola Thach<br />

Formation. While the Rohtang Geneissic Complex is predominantly made<br />

up <strong>of</strong> gneisses, granites and migmatites with subordinate metasediments, the<br />

latter represents primarily metasedimentary sequence. The Rohtang Gneissic<br />

Complex has further been subdivided into different formations namely<br />

Kulti, Damphung and Gufa.<br />

Kulti is the oldest Formation and is exposed between Khoksar and Chhota<br />

Dara in the valley <strong>of</strong> Chandra river, the area in which the <strong>project</strong> is located.<br />

It comprises mostly migmatite and granite gneisses which from about 80%<br />

<strong>of</strong> lithology. Schists and quartzites form intercalations within gneisses and<br />

migmatites. The individual gneiss bands are thin (0.25m to 1. 0m) and these<br />

attain thickness up to 5.0m between Kulti and Chhatru on left bank <strong>of</strong><br />

Chandra River. Quartzite is generally light grey, fine grained and micaceous<br />

and with increase in mica content it grades into mica- schist.<br />

The rocks belonging to Damphung Formation/ Member conformably overly<br />

the rocks <strong>of</strong> Kulti Formation. These are well exposed on both the slopes <strong>of</strong><br />

Chandra Valley upstream <strong>of</strong> Khoksar- Damphung area. These comprise<br />

mica schist, micaceous quartzite and quartz schist. This schist is commonly<br />

kyanite, staurolite, garnet and occasionally sillimanite bearing on the eastern<br />

slopes <strong>of</strong> Chhatru Nala. Grey to dark grey-banded quartzite appears at same<br />

stratigraphic level as <strong>of</strong> Damphung Formation indicating that these two are<br />

facies variant <strong>of</strong> each other. The rocks <strong>of</strong> Damphung Formation pass into<br />

those <strong>of</strong> Gufa Formation. Lithologically these resemble the rocks belonging<br />

to Kulti Member and comprises predominantly granitic and migmatitic<br />

gneisses besides subordinate schist and quartzite.<br />

The rocks belonging to Chola Thach Formation represent the sedimentary<br />

sequence in Lahaul or Rohtang Group and overlie the rocks <strong>of</strong> Gufa<br />

Formation with gradational contact. This Formation is exposed in low-lying<br />

stretches around Sissu and Teling areas. It consists <strong>of</strong> grey fine-grained<br />

quartzite, quartz schist and mica schist that are partly garnetiferous.<br />

Proterozoic


Haimanta Group <strong>of</strong> rocks has been divided into Batal and Kunzum- La<br />

Formations. In the southeastern part <strong>of</strong> the Lahaul i.e. in the valley <strong>of</strong><br />

Chenab or Chandra-Bhaga, the Batal Formation <strong>of</strong> this group is regarded to<br />

be represented by Manjir and Katarigali Formations <strong>of</strong> Vaikrita Group in<br />

Chamba area. Here Rapa & Gadhoke (1984) mapped two formations i.e.<br />

Bagotu and Dunai which were regarded equivalents <strong>of</strong> Manjir and Salooni<br />

Formations <strong>of</strong> Chamba area. Subsequently unfossiliferous part <strong>of</strong> Salooni<br />

Formation was renamed as Bharmour Formation and correlated it with<br />

Katarigali Formation <strong>of</strong> Jammu & Kashmir. These formations have not been<br />

defined in the rest <strong>of</strong> Lahaul area except that the pelites underlying the<br />

Tandi Group were correlated with Salooni and conglomerate exposed at<br />

Chobia and Trilokinath with Manjir Formation by Raina and Prashara<br />

(1973).<br />

Manjir Formation conformably overlies the Chamba Formation which is<br />

considered extension <strong>of</strong> the Batal Formation <strong>of</strong> Lahaul. It is characterized by<br />

diamictite, shale, slate and quartzite. The frame work <strong>of</strong> clasts is constituted<br />

<strong>of</strong> quartzite, vein quartz, phyllite, slate, limestone and granite. The clasts <strong>of</strong><br />

pelitic rocks show considerable stretching and diamictite facies at places<br />

change into grit and quartz wacke.<br />

The rocks belonging to Katarigali Formation conformably overlie those <strong>of</strong><br />

Manjir Formation. These are mainly composed <strong>of</strong> quartzite, slate & phyllite.<br />

The area encompassing the <strong>project</strong> exposes the rocks belonging to Katarigali<br />

Formation<br />

4.3 STRUCTURE AND TECTONICS<br />

Tectonically, the present area forms part <strong>of</strong> Central Axial Zone <strong>of</strong><br />

Himalayas. The structural elements <strong>of</strong> the area can be grouped in two i.e.<br />

non-diastrophic and diastrophic structures. The non-diastrophic structures<br />

include colour and compositional banding, current bedding in the quartzites<br />

<strong>of</strong> Manjir and Katarigali Formations etc. The diastrophic structures include<br />

schistosity, crenulation cleavage, fracture cleavage, joints etc. Schistosity is<br />

most penetrative planar structure in the area and has general NW-SE trend<br />

with shallow dips (10 o -25 o ). It is developed parallel to axial plane <strong>of</strong> first<br />

folds and is parallel to sub parallel to bedding. Crenulation cleavage has<br />

developed parallel to axial plane <strong>of</strong> second phase folds. It has folded<br />

bedding as well as schistosity. General trend <strong>of</strong> this structural plane is NW-<br />

SE with 15 o -30 o dips towards NE. Fracture cleavage is represented by<br />

fractures developed parallel to the axial plane <strong>of</strong> third phase folds. It’s trend<br />

varies from NNE-SSW to NNW-SSE and dips sub-vertically to vertically.<br />

Broadly there are three prominent sets <strong>of</strong> joints having NNE-SSW, E-W and<br />

NNW-SSE to N-S trends and have steep to very steep dips.


Three phases <strong>of</strong> folding are identifiable in the area. The folds belonging to<br />

first phase (F1) are rarely preserved. These are invariably tight in nature and<br />

have NW-SE trend in general. The mesoscopic folds belonging to second<br />

phase (F2) are most common folds in the area. These are open to tight and<br />

upright to recumbent. These are coaxial with folds <strong>of</strong> F1 phase and have<br />

NW-SE general trend with 5 o -10 o plunge towards NW. The third phase folds<br />

(F3) are represented by open warps. These are transverse to F1 and F2 folds<br />

and have a general low plunge towards N to NE. The rocks <strong>of</strong> this area are<br />

disposed in the form <strong>of</strong> a regional anticline, the axes <strong>of</strong> which coincides<br />

with the Chandra river. This anticline is represented by a broad upright warp<br />

with large crestal area. It shows 5 o -10 o plunge towards NW exposing the<br />

younger formations towards downstream.<br />

4.4 SEISMOTECTONICS AND SEISMICITY<br />

Seismotectonically, the area encompassing the proposed <strong>project</strong> is located in<br />

Central Himalayas on the western margin <strong>of</strong> Shimla Seismic Block <strong>of</strong><br />

Narula (1999). The Shimla Seismic Block is bound by Sunder Nagar Fault<br />

in west and Kaurik Fault in east. As per Seismotectonic Atlas <strong>of</strong> India and<br />

its environs (Narula et al., 2000), the litho tectonic packets <strong>of</strong> Himalayan<br />

Orogenic Belt in the region are poorly metamorphosed litho units <strong>of</strong><br />

Tethyan Unit, high and low grade assemblages <strong>of</strong> Central crystalline and<br />

Lesser Himalayan Belt along with granitoids and basic volcanics. The<br />

southern fringe <strong>of</strong> Himalayan belt is occupied by the cover rocks <strong>of</strong> frontal<br />

belt.<br />

Within Himalayan Belt, the northern most conspicuous structural element is<br />

the Main Himalayan Thrust (MCT). From Manali towards east up to eastern<br />

syntaxes through out the entire Himalayas, this is considered as most<br />

important tectonic surface. However, it is not clearly discernible northwest<br />

<strong>of</strong> Manali. Further south, within the lesser Himalayas, the most important<br />

tectonic surface is Vaikrita Thrust (VT). The Lesser Himalayan Belt is<br />

separated from the Frontal Belt by the Main Boundary Thrust (MBT).<br />

Further south, the southern limit <strong>of</strong> the Frontal Belt is marked by the Main<br />

Frontal Thrust (MFT) that has its surface manifestations at a few places only<br />

within MBT and MFT, the belt is traversed by several subsidiary thrusts that<br />

have considerable spatial extent.<br />

In addition to the structural discontinuities sub-parallel to regional trend,<br />

there are a number <strong>of</strong> faults and lineaments transverse to this fold-thrust<br />

belt. The Sunder Nagar Fault located in the <strong>project</strong> area is a dextral<br />

transverse structure that extends from Higher Himalayas to Frontal Belt.<br />

The Ropar Fault (Tear ?) is postulated to be continuation <strong>of</strong> Sunder Nagar<br />

Fault. Another fault similar to above has been identified in south east <strong>of</strong><br />

Chandigarh. All these transverse faults including Yamuna Tear located<br />

further southeast exhibit neo-tectonic activity.


A total <strong>of</strong> about 80 seismic events having magnitude >4.0 have been<br />

recorded in the Himalayan Belt in the area. Out <strong>of</strong> these 17 events had<br />

magnitude >5 and were mostly confined to the depths less than 40 km. The<br />

events having magnitude >4 and >5 are predominant in the area. Seismic<br />

activity is concentrated mainly in the Himalayan Belt, particularly in NW<br />

sector around Chamba- Kangra in adjoining Kangra Seismic Block. Out <strong>of</strong><br />

the 17 events having magnitude >5, 14 events are located in this zone. In<br />

this region <strong>of</strong> Himalayas, 4 events having magnitude >6 were recorded and<br />

three out <strong>of</strong> these including the Great Kangra earthquake <strong>of</strong> 1905 are located<br />

along MBT and one event on the surface trace <strong>of</strong> Sunder Nagar Fault. Six<br />

earthquakes from the area have caused considerable damage and these<br />

include Kangra Earthquake <strong>of</strong> 4 th April 1905 (Ms=8.0); Chamba<br />

Earthquake <strong>of</strong> 22 nd June, 1945 (Ms=6.5.); Dharamshala earthquake <strong>of</strong> 14 th<br />

June, 1978 and 26th April, 1986 and Chamba Earthquake <strong>of</strong> 24 th March,<br />

1995 . Keeping in view the seismic status and seismotectonic setup in view,<br />

the area has been kept on the margins <strong>of</strong> Zones V and IV as per Map <strong>of</strong><br />

India showing Seismic Zones (IS: 1893 (Part-I):2002). Therefore it is<br />

suggested that suitable seismic coefficient be specifically evolved for the<br />

area and incorporated in the design <strong>of</strong> the appurtenant structures <strong>of</strong> the<br />

<strong>project</strong>s.<br />

4.5 GEOTECHNICAL APPRAISAL<br />

The site was visited on 24.8.2003 along with Shri A.K. Gupta, Director<br />

Planning, HPSEB, Sundernagar and other HPSEB <strong>of</strong>ficers. The proposed<br />

Chhatru Hydro<strong>electric</strong> Project is located in the upper reaches <strong>of</strong> Chandra<br />

Valley where both terrain and climate are hostile. The valley flanks are<br />

dotted with recent and sub-recent avalanches which have accumulated as<br />

talus cones which go upto 100 m above river bed at places. The proposed<br />

dam site is located about 5 km upstream <strong>of</strong> Chhatru. The river Chenab<br />

flows towards west. The area exposes granitic gneiss belonging to Rohtang<br />

Gneissic Group. The rocks are folded into an anticline and river flows along<br />

this anticlinal axis. The river bed is about 100 m wide. The talus cones<br />

extend on abutments upto about 100 m above river bed. This site does not<br />

appear to be suitable for dam as bed rock is expected to be deep both in the<br />

river bed and on the abutments. The abutments are covered with boulders<br />

upto 5 m in size. It is suggested that temporary diversion structure founded<br />

on permeable strata be considered here. Similarly, the site for locating<br />

intake structure for HRT in bed rock is not available at least up to 2 km on<br />

both sides from the site <strong>of</strong> diversion structure. Therefore the tunnel<br />

alignment in the initial reaches has to be explored for delineating the bed<br />

rock so that proper intake structure is constructed. Upto the point where<br />

adequate rock cover is available over the tunnel the same will have to be<br />

designed as structural tunnel with false portal. The desilting arrangement<br />

has to be designed underground due to topographic and climatic constraints.


About 600 m downstream <strong>of</strong> the proposed site, the ridge between two<br />

hanging glaciers can be utilized for temporary diversion structure. The<br />

diversion structure could be located in the ridge upstream <strong>of</strong> Hamta Glacier.<br />

However, the behavior <strong>of</strong> glacier has to be investigated at this site. About<br />

200 m wide terrace is available for transferring discharge to right abutment<br />

where bed rock is exposed right from terrace. The intake structure can be<br />

located in bed rock. The 8 km long HRT will encounter granitic gneiss.<br />

These are foliated and jointed. The foliation trends NW-SE and dips about<br />

25 o -30 o towards NE. The HRT will be crossing Chhatru Nala. It is<br />

suggested that HRT be aligned in such a way that adequate rock cover is<br />

available over the structure. The possibility <strong>of</strong> locating an intermediate<br />

construction adit in Chhatru Nala may be looked into.<br />

The proposed powerhouse with 100 MW installed capacity is located on<br />

right bank <strong>of</strong> Chenab about 2.5 km downstream <strong>of</strong> Chhatru Bridge. The<br />

proposed site is located between two nalas which have debris cones at their<br />

mouth. The site has thin debris fans comprising boulders up to about 50 m<br />

above riverbed. Above it, the granite gneiss is exposed on steep slope upto<br />

200 m above riverbed. The rock is jointed. The site is suitable for an<br />

underground powerhouse. There is also possibility <strong>of</strong> locating the<br />

switchyard on left bank <strong>of</strong> the river on a terrace where sufficient space is<br />

available. Otherwise the same may be kept underground.<br />

4.6 REFRENCES<br />

Narula, P.L., (1991) Seismotectonic evaluation <strong>of</strong> NW Himalaya, Rec. Geo.<br />

Surv. Ind., 127(8), 14949.<br />

Narula, P.L., Acharayya, S.K. and Banerjee, J. (2000) Seismotectonic Atlas<br />

<strong>of</strong> India and its environs. Pub. Geol. Surv. Ind.<br />

Prashara, K.C., Des Raj and Kumbkarni, S. (1986- 87). Geology <strong>of</strong> Parts <strong>of</strong><br />

Chandra Valley, Lahaul and Spiti district, Himachal Pradesh, Unpubl. G S I<br />

Report for F S: 1986-87<br />

Prashara, K.C. (1992) Final Report on Geology <strong>of</strong> Lahaul and Spiti District,<br />

Himachal Pradesh., Unpublished GSI Compilation<br />

Raina, V. K. and Prashara, K. C., (1973). Geological Mapping in Parts <strong>of</strong><br />

Pangi Valley, Chamba and Lahaul Spiti districts, Himachal Pradesh,<br />

Unpublished GSI Report for F. S. 1971- 72 .<br />

Rapa, D.A. and Gadhoke, S.K. (1983). Geology <strong>of</strong> Parts <strong>of</strong> Chamba district,<br />

Himachal Pradesh, Unpub. GSI Report for F.S. 1982- 83


PARA DESCRIPTION PAGE<br />

5.1 RIVER CHANNEL AND CATCHMENT<br />

CHARACTERISTICS<br />

5.1.1 HYDROMETEOROLOGY OF THE CATCHMENT V-1<br />

5.2 DISCHARGE DATA AND WATER AVAILABILITY V-2<br />

5.2.1 CO-RELATION STUDY V-2 TO V-3<br />

5.3 DESIGN FLOOD V-3 TO V-4<br />

5.4 SEDIMENTATION ASPECTS V-4<br />

TABLE-5.1 TEN DAILY AVERAGE DISCHARGE DATA OF<br />

RIVER CHANDRA AT GHOUSAS FROM JUNE 1973<br />

TO MAY 2000<br />

TABLE-5.2 TEN DAILY AVERAGE DISCHARGE DATA<br />

DIVERSION SITE<br />

TABLE-5.3 INFLOW OF RIVER CHANDRA AT GHOUSAL &<br />

INFLOW OF RIVER BHAGA AT TANDI<br />

TABLE-V-5.3(1)<br />

TO 5.3(6)<br />

REGRESSION ANALYSIS BETWEEN DISCHARGES<br />

OF TANDI & GHOUSAL<br />

TABLE- 5.4 INFLOWS OF RIVER CHANDRA AT UDAIPUR &<br />

INFLOWS OF RIVER BHAGA AT TANDI PLUS<br />

RIVER CHANDRA AT GHOUSAL<br />

TABLE- 5.4(1)<br />

TO 5.4 (6)<br />

REGRESSION ANALYSIS BETWEEN DISCHARGES<br />

OF TANDI PLUS GHOUSAL AND UDAIPUR<br />

V-1<br />

V-5- TO V-9<br />

V-10 TO V-14<br />

V-15<br />

V-16<br />

V-17 TO V-22<br />

V-23<br />

V-24<br />

PLATE –5.1 FLOW DURATION CURVE (OVER ALL) V-31<br />

PLATE-5.2 FLOW DURATION CURVE (LEAN PERIOD) V-32<br />

V-25 TO V-30<br />

ANNEXURE-V-1 ESTIMATE OF DESIGN FLOOD V-33 TO V-45<br />

ANNEXURE-V-2 COMMENTS RAISED BY CEA/CWC ON<br />

HYDROLOGY<br />

ANNEXURE-V-3 REPLY TO THE COMMENTS ON HYDROLOGY V-52<br />

V-46 TO V-51


CHAPTER – V<br />

HYDROLOGY<br />

5.1 RIVER CHENAB AND CATCHMENT CHARACTERISTICS.<br />

The river orginates from the snow covered slopes <strong>of</strong> Great Himalayan <strong>of</strong><br />

Pir-Panjal ranges in Lahaul Spiti district and flows in a steep gradient with a<br />

series <strong>of</strong> loopes and bends. The river is formed by the two major tributaries<br />

in the head reaches namely Chandra and Bhaga.The river Chandra originates<br />

from Bara Lachala and is further augmented by Chandra Tal. The river<br />

Bhaga takes <strong>of</strong>f from Suraj Tal in the vicinity <strong>of</strong> Bara Lachala and is further<br />

joined by Jhankar and Millang nallahs in the head reaches. The catchments<br />

<strong>of</strong> these two major tributaries have snow covered peaks at height ranging<br />

from ± 3500 m to 5500 m elevation. The Chandra river and Bhaga river<br />

joins at Tandi to form Chandra-Bhaga i.e. the Chenab. Further downstream<br />

<strong>of</strong> confluence, it is joined by other significant tributaries namely Shansha<br />

nallah near Rashil, Thirot nallah at Thirot, Miyar nallah at Udaipur, Saichu<br />

nallah at Dawag, Mahal Nallah at Killar & Dheda nallah at Lujai d/s <strong>of</strong><br />

Killar. Chenab river drains a catchments <strong>of</strong> about 7500 Sq. Km. before it<br />

crosses in to J&K border.<br />

5.1.1 HYDROMETEOROLOGY OF THE CATCHMENT<br />

This region is a low rainfall area as most <strong>of</strong> the precipitation in the region is<br />

in the form <strong>of</strong> snow. The rainfall takes place during the monsoon months<br />

only and the catchment experiences snowfall during the remaining period <strong>of</strong><br />

the year. There is only one rain gauge station in this region, installed at<br />

Keylong and the rainfall data has not been recorded regularly even at this<br />

station. It is observed that the most <strong>of</strong> the run<strong>of</strong>f in the river results from the<br />

melting <strong>of</strong> snow.


5.2 DISCHARGE DATA AND WATER AVAILABILITY<br />

The discharge data <strong>of</strong> river Chandra at diversion site <strong>of</strong> Chhatru HEP has<br />

been derived from June 1973-May 2000 from the discharge data <strong>of</strong> river<br />

Chandra at Ghousal (site monitored by CWC).<br />

Discharge data <strong>of</strong> river Chandra at Ghousal is given in table 5.1 while the<br />

computed discharge data reduced on catchment area basis at diversion site is<br />

given in Table– 5.2<br />

Based upon ten daily discharge data, a flow duration curve has been<br />

developed. From this curve, it is seen that flow corresponding to 90% &<br />

50% availability works out to 10.41 cumecs & 26.30 cumecs respectively.<br />

The design discharge <strong>of</strong> 75 cumecs is available for 32.15 % <strong>of</strong> the period.<br />

Flow duration curve for lean-season (Dec. to Feb.) has also been developed .<br />

From this curve , it is seen that flow corresponding to 90% & 50%<br />

availability works out to 6.96 cumecs & 12.95 cumecs respectively.<br />

5.2.1 CO-RELATION STUDY<br />

W.B. Langbein’s log deviation method has been used to obtain the coefficient<br />

<strong>of</strong> co-relation between discharges <strong>of</strong> river Chandra at Ghousal and<br />

discharges <strong>of</strong> river Bhaga at Tandi.<br />

The Co-relation factors are as follows:<br />

June-July = 0.92<br />

Aug.-Sept. = 0.96


Oct.-May = 0.96<br />

These calculations have been shown in Table- 5.3<br />

Similarly coefficient <strong>of</strong> co-relation has been obtained between discharges<br />

<strong>of</strong> river Chenab at Udaipur and the sum <strong>of</strong> discharges <strong>of</strong> river Chandra at<br />

Ghousal & river Bhaga at Tandi.<br />

June-July = 0.94<br />

Aug.-Sept. = 0.96<br />

Oct.-May = 0.88<br />

These calculations have been shown in Table-5.4<br />

From the above co-relation factors it is evident that the discharges <strong>of</strong> river<br />

Chandra at Ghousal & river Bhaga at Tandi including river Chenab at<br />

Udaipur are consistent. Thus the discharges <strong>of</strong> river Chandra at Ghousal<br />

have been approved by CWC and used for carrying out studies which stands<br />

submitted to the CWC and comments are awaited.<br />

5.3 DESIGN FLOOD<br />

The <strong>project</strong> falls in Western Himalayas Zone seven in map <strong>of</strong> India. The<br />

total catchment area <strong>of</strong> river Chenab in India is about 31,047 Sq. Kms. The<br />

catchment is mostly fed by snow. The majority percentage <strong>of</strong> the run<strong>of</strong>f in<br />

the catchment is derived from the snow & glaciers which constitutes a<br />

potential reservoir. Winter precipitation which occurs in the form <strong>of</strong> snow<br />

goes on accumulating till summer. As the summer advances, the<br />

accumulated snow melts and releases water into the stream.


Design Flood has been computed on the basis <strong>of</strong> Flood Estimation report for<br />

Western Himalayas-zone 7 & accordingly <strong>hydro</strong>graphs have been prepared.<br />

The max.. flow due to rain contribution comes out to be 291.59 cumecs<br />

which has return period <strong>of</strong> 1 in 50 years. The maximum flow for return<br />

period <strong>of</strong> 1 in 100 years is 321.38 cumecs. The snow contribution has been<br />

taken to be 342.09 cumecs ie the maximum discharge <strong>of</strong> flow during 2 nd<br />

week <strong>of</strong> July in flow series at diversion site. Thus the total design flood<br />

works out to be 663.47 cumecs. Flood frequency analysis has also been<br />

carried out by Gumble’s method.<br />

Return period <strong>of</strong> 1 in 1000 years has been considered for computing the<br />

SPF which works out to be 1377.59 cumecs. The designed flood has been<br />

taken as 1500 cumecs. The computations have been shown in Annexure-V-<br />

1.<br />

5.4 SEDIMENTATION ASPECTS<br />

Detailed studies shall be carried out at DPR stage. However 20% <strong>of</strong> the live<br />

storage has been proposed to be kept reserved for silt deposition in the<br />

reservoir.


Annexure-V-3<br />

Reply to the comments raised by Director Hydrology, CWC, New Delhi on <strong>hydro</strong>logy<br />

vide letter no. 1/HP/26/2004/CWC/131 dated 19.04.04, further intimated by Dy.<br />

Director, HPI, CEA vide letter No. 7/91/HPSEB/2004/HPI/877/dated 21.04.04.<br />

Design flood<br />

1. The water way and free board in barrage have been designed as per design flood <strong>of</strong><br />

1500 cumecs workout by flood frequency analysis for 1000 years return period,<br />

which is already on higher side. However, the same shall be revised at DPR stage<br />

after the finalization <strong>of</strong> design flood as suggested.<br />

2. As suggested efforts to collect data <strong>of</strong> annual instantaneous flood peak series at<br />

Ghousal G&D site from CWC Jammu are being made. The results as per best fit<br />

distribution shall be carried out at DPR stage.<br />

3. SPE values from IMD and instantaneous peaks at Ghousal have not been received<br />

so far, as such study will be carried out as DPR stage.<br />

4. As agreed the design flood shall be reviewed at DPR stage.<br />

5. Recommendations:-<br />

i) The new gauge discharge observation may be opened before the preparation<br />

<strong>of</strong> DPR .<br />

ii) Few SRRG, ORG, station, weather stations may be established in the<br />

<strong>project</strong> area to collect more information regarding precipitation and snow<br />

melt contribution.<br />

iii) The above mentioned suggestions shall be taken care <strong>of</strong> the immediately<br />

after the availability <strong>of</strong> funds for investigation in near future.


PARA DESCRIPTION PAGE<br />

6.0 CONCEPTUAL LAYOUT OF PROJECT<br />

COMPONENTS<br />

VI-1<br />

6.1 FINALIZATION OF CONCEPTUAL LAYOUT VI-1<br />

6.2 PRELIMINARY DESIGN FEATURES VI-2<br />

6.2.1 BARRAGE VI-2<br />

6.2.1.1 GENERAL VI-2<br />

6.2.1.2 RESERVOIR VI-2<br />

6.2.1.3 BARRAGE BAYS VI-3<br />

6.2.1.4 ENERGY DISSIPATION VI-3<br />

6.2.2 RIVER DIVERSION WORKS VI-3 TO VI-4<br />

6.2.2.1 INTAKE STRUCTURE VI-4<br />

6.2.3 DESANDING ARRANGEMENT VI-4 TO VI-5<br />

6.2.4 HEAD RACE TUNNEL VI-5<br />

6.2.4.1 GENERAL VI-5<br />

6.2.4.2 CROSS SECTION VI-6<br />

6.2.5 SURGE SHAFT VI-6<br />

6.2.5.1 GENERAL VI-6<br />

6.2.5.2 HYDRAULIC PARAMETERS VI-6<br />

6.2.5.3 CONCRETE LINING VI- 7<br />

6.2.6 PRESSURE SHAFT VI-7<br />

6.2.6.1 GENERAL VI-7<br />

6.2.6.2 ECONOMIC DIAMETER VI- 8<br />

6.2.7 POWER HOUSE VI-8<br />

6.2.7.1 GENERAL VI-8<br />

6.2.7.2. TYPE VI- 9


6.2.7.3 MACHINE HALL VI-9 TO VI-<br />

10<br />

6.2.7.4 TRANSFORMER HALL VI-10<br />

6.2.8 AUXILIARY SURGE SHAFT AND TAIL RACE<br />

TUNNEL<br />

VI-10<br />

6.3 PRELIMINARY DRAWINGS VI-11<br />

6.4 DESIGN COMPUTATIONS VI-12 TO VI-<br />

33<br />

DRAWINGS<br />

CHHATRU-<br />

FR-1<br />

CHHATRU-<br />

FR-2<br />

CHHATRU-<br />

FR-3<br />

CHHATRU-<br />

FR-4<br />

CHHATRU-<br />

FR-5<br />

CHHATRU-<br />

FR-6<br />

CHHATRU-<br />

FR-7<br />

CHHATRU-<br />

FR-8<br />

CHHATRU-<br />

FR-9<br />

CHHATRU-<br />

PLATE-6.1<br />

VICINITY MAP 1 SHEET<br />

MASTER PLAN OF CHENAB BASIN (CEA<br />

SCHEMES)<br />

1 SHEET<br />

CATCHMENT AREA PLAN 1 SHEET<br />

GENERAL LAYOUT PLAN 1 SHEET<br />

DIVERSION BARRAGE, INTAKE,& DESANDING<br />

BASIN<br />

HEAD RACE TUNNEL, SURGE SHAFT & PRESSURE<br />

SHAFT<br />

POWER HOUSE AND TRANSFORMER HALL PLAN,<br />

L- SECTION AND SINGLE LINE DIAGRAME<br />

2 SHEETS<br />

1 SHEET<br />

3 SHEETS<br />

CONSTRUCTION FACILITIES 1 SHEET<br />

CONSTRUCTION PROGRAME 1 SHEET<br />

AREA CAPACITY CURVE 1 SHEET


CHAPTER – VI<br />

CONCEPTUAL LAYOUT<br />

AND PLANNING


CHAPTER – VI<br />

CONCEPTUAL LAYOUT<br />

AND PLANNING<br />

6.0 CONCEPTUAL LAYOUT OF PROJECT COMPONENTS<br />

6.1 FINALIZATION OF CONCEPTUAL LAYOUT<br />

The proposed Civil Engineering Structures have been planned and designed<br />

to divert and conduct 75 cumecs <strong>of</strong> water, from river Chhatru for generating<br />

108MW <strong>of</strong> power in an underground power house by utilizing a gross head<br />

<strong>of</strong> 177.33m. The main works <strong>of</strong> the <strong>project</strong> comprise a diversion barrage,<br />

intake, underground desanding basins for removing all particles down to<br />

0.20mm size, 6500m long head race tunnel, a restricted orifice type surge<br />

shaft and an underground power house to accommodate 3 vertical axis,<br />

Francis turbines driven generating units each <strong>of</strong> 36 MW. After diversion, all<br />

the civil engineering components have been kept underground keeping in<br />

view the topography <strong>of</strong> the area. Comments on the draft PFR <strong>of</strong> the <strong>project</strong><br />

issued by Director, HCD (NW&S) <strong>of</strong> CWC vide no. CWC<br />

U.O.NO.22/1/03/HCD(NW&S) dated have been<br />

incorporated. A brief geological site specific feasibility note titled “Geotechnical<br />

appraisal” founded on preliminary site inspection about each<br />

component is appended as Para 4.5 in chapter-IV titled “Geographic & Geotechnical<br />

Aspects”.


6.2 PRELIMINARY DESIGN FEATURES<br />

6.2.1 BARRAGE<br />

6.2.1.1 GENERAL<br />

The slope <strong>of</strong> river at the diversion site u/s <strong>of</strong> Chhatru village is <strong>of</strong> the order<br />

<strong>of</strong> 1:23. Peak annual flood <strong>of</strong> river Chandra at diversion site has been<br />

adopted as 1500 cumecs for design <strong>of</strong> spillways/barrage bays. Barrage 185m<br />

long including abutments with crest level <strong>of</strong> barrage bays at El. 3407m &<br />

non over flow section has been proposed to pass the estimated design flood<br />

at FRL El. 3421.00m. The proposed barrage comprises 6 bays <strong>of</strong> 5.00m<br />

each with 3.00m thick piers and is capable <strong>of</strong> passing the estimated design<br />

flood even when one bay is considered inoperative during period <strong>of</strong> high<br />

floods. The max. pond level/ FRL (El. 3421.00m) attained during winter<br />

months shall also cater to peaking requirement . During high flood max.<br />

water level to be attained has been proposed as 3422.00m. Radial gates in<br />

the barrage bays shall be provided from top <strong>of</strong> crest El. 3407m to the bottom<br />

<strong>of</strong> RCC breast wall El. 3413.00m spanning between the piers. The breast<br />

wall is supported on the piers and is provided between El. 3413.00m and El.<br />

3424.00m.<br />

6.2.1.2 RESERVOIR<br />

The full reservoir level (FRL) is fixed at El. 3421.00. The minimum draw<br />

down level (MDDL) has been fixed at El. 3413.50m. The reservoir so<br />

formed has a gross storage capacity <strong>of</strong> 112.50 ha-m at FRL and 25.00 ha-m<br />

at MDDL. Available diurnal storage <strong>of</strong> 70.00 ha-m ( 87.50 -20% reserved<br />

for silt deposits) is sufficient for running the power station as a peaking<br />

station at full installed capacity for 3.00 hrs. The discharge availability in<br />

lean period(Nov. to Feb) in 90% dep. year is 11.18 cumecs. The reservoir<br />

spreads over an area <strong>of</strong> 16.00 hectares and is about 1.00 km long. The area


capacity curve for the reservoir has been drawn from the available contour<br />

plan <strong>of</strong> the area on 1:2500 scale and is shown in Plate No. 6.1<br />

6.2.1.3 BARRAGE BAYS<br />

6 barrage bays 5.00m wide each have been provided to pass the design flood<br />

discharge i.e. 1500 cumecs. Total floor <strong>of</strong> 136m length has been proposed<br />

comprising u/s floor, sloping glacis u/s & d/s (4:1) and d/s floor <strong>of</strong> 50m<br />

including end still. A 4 m deep cut <strong>of</strong>f extending up to 3401m at u/s side <strong>of</strong><br />

the floor and 5.00m deep cut <strong>of</strong>f at the end <strong>of</strong> d/s floor extending up to El.<br />

3390m have been provided to protect the u/s and d/s floor from scour/<br />

piping action. Cement concrete blocks extending 10m each beyond u/s and<br />

D/s floors have been provided. Protection to cement concrete blocks have<br />

been provided with stone filled wire crates extending 10m beyond u/s & d/s<br />

floors. Consolidation grouting has not been proposed in the river bed,<br />

keeping in view the fact that rock is not available upto reasonable depth in<br />

the river bed.<br />

6.2.1.4 ENERGY DISSIPATION<br />

Dissipation <strong>of</strong> energy is proposed to be done by providing a horizontal<br />

stilling basin depressed below the river bed level (El. 3395m) with solid end<br />

sill to facilitate formation <strong>of</strong> hydraulic jump. Layout & details <strong>of</strong> barrage<br />

have been shown in drawing No. CHHATRU-FR-5.<br />

6.2.2 RIVER DIVERSION WORKS<br />

The river diversion works have been designed for a discharge <strong>of</strong> 600<br />

cumecs. The construction <strong>of</strong> diversion works i.e. half <strong>of</strong> barrage, intake<br />

structure from inlet have been proposed to be taken up by making Ist Stage<br />

c<strong>of</strong>fer dam <strong>of</strong> length 300m allowing flow <strong>of</strong> water along the left bank <strong>of</strong><br />

river. After the completion <strong>of</strong> diversion barrage upto El. 3407m & <strong>Power</strong>


intake upto El. 3410m the Ist stage c<strong>of</strong>fer dam shall be removed and water<br />

shall be diverted on right bank <strong>of</strong> river through barrage constructed, by<br />

making 2 nd stage c<strong>of</strong>fer dam. Thereafter, the construction <strong>of</strong> remaining half<br />

<strong>of</strong> the barrage shall be completed. The construction <strong>of</strong> diversion works has<br />

been proposed to be completed within three months period. Construction <strong>of</strong><br />

c<strong>of</strong>fer dam is proposed to be modified as per site conditions after each<br />

monsoon season.. The provision for construction <strong>of</strong> c<strong>of</strong>fer dam has been<br />

made accordingly, adding 50% quantum <strong>of</strong> work being involved due to<br />

repetition <strong>of</strong> job after each season in the cost estimate <strong>of</strong> the <strong>project</strong>. The<br />

provision <strong>of</strong> plain cement concrete <strong>of</strong> grade M-10 has been made on the top<br />

and side slopes <strong>of</strong> c<strong>of</strong>fer dam to prevent the seepage <strong>of</strong> water towards<br />

working area.<br />

6.2.2.1 INTAKE STRUCTURE<br />

The intake structure comprising single intake with eight no. openings,has<br />

been proposed on the right bank <strong>of</strong> river, to handle a discharge <strong>of</strong> 93.75<br />

cumecs. A semi circular trash rack structure with reinforced concrete<br />

columns has been proposed for intake. Crest elevation <strong>of</strong> intake is proposed<br />

as 3410m. Stop logs has been proposed for controlling flow through intake<br />

bays 8 nos.(5.50mx3m) each during repairs. A suitable transition is<br />

provided to convert the rectangular opening into a 6.00m dia circular<br />

approach tunnel. Approach tunnel is 200m long and shall lead the water into<br />

two desanding basins. Details are shown in drawing No. CHHATRU-FR-5.<br />

6.2.3 DESANDING ARRANGEMENT<br />

An underground desanding arrangement to exclude all silt particles down to<br />

0.20mm has been proposed ±100m d/s <strong>of</strong> barrage on the right bank <strong>of</strong> river<br />

Beas. A lateral rock cover more than 1.5xexcavated width has been ensured<br />

for locating chamber No. 1. Rock cover <strong>of</strong> the order <strong>of</strong> twice the width <strong>of</strong>


excavated cavity <strong>of</strong> the chamber has been ensured in between the two<br />

chambers. Stop logs will be provided at the inlet and outlet <strong>of</strong> all the<br />

chambers to facilitate closing <strong>of</strong> any chamber for maintenance/repairs, while<br />

the others will enable continuous operation <strong>of</strong> the power station. Layout<br />

and details <strong>of</strong> desilting arrangement are given in drawing No. CHHATRU-<br />

FR-5.<br />

6.2.4 HEAD RACE TUNNEL<br />

6.2.4.1 GENERAL<br />

The head race tunnel 5.10m dia, 6500m modified horse shoe type has been<br />

proposed to carry a design discharge <strong>of</strong> 75 cumecs from the junction point<br />

<strong>of</strong> feeder tunnels <strong>of</strong> desilting chamber with HRT to the surge shaft. The<br />

tunnel is located along right bank <strong>of</strong> river Chandra. Layout <strong>of</strong> the tunnel has<br />

been fixed keeping in view the topography <strong>of</strong> the area and location <strong>of</strong><br />

construction adit from Chhatru nallah for completing the tunnel excavation<br />

work on schedule. Adequate rock cover has been ensured in entire reach <strong>of</strong><br />

the tunnel. The invert level <strong>of</strong> tunnel at RD-0 is at El. 3402.50m and at<br />

outlet end at El. 3348.45m resulting in a slope <strong>of</strong> 1 in 120.<br />

Three adits each 5m D-shaped at inlet, outlet and at intermediate location<br />

(RD 3500m) have been provided to facilitate construction <strong>of</strong> HRT from four<br />

faces. The inlet and outlet adits are so provided that they shall separate the<br />

construction activity <strong>of</strong> the head race tunnel from that <strong>of</strong> desilting chambers<br />

and surge shaft. The layout <strong>of</strong> the tunnel and other details are indicated in<br />

Drawing. No. CHHATRU-FR-6.


6.2.4.2 CROSS SECTION<br />

Based on geological, hydraulic, structural and functional considerations,<br />

modified horse shoe shaped cross section, 5.10m dia has been adopted. The<br />

tunnel is proposed to be lined with concrete M:20.<br />

6.2.5 SURGE SHAFT<br />

6.2.5.1 GENERAL<br />

The underground restricted orifice type surge shaft <strong>of</strong> 15m dia and 91.80m<br />

height has been proposed at the outlet end <strong>of</strong> Head race tunnel at RD 6500.<br />

Top level <strong>of</strong> surge shaft is proposed at El. 3448.00m. Two adits each 6m Dshaped,<br />

one approaching the top at El. 3438.00m and other at the bottom at<br />

El. 3348.00m have been proposed. The bottom adit will also be utilized to<br />

facilitate excavation <strong>of</strong> surge shaft and horizontal portions <strong>of</strong> pressure shaft.<br />

After execution <strong>of</strong> the <strong>project</strong> this adit will be plugged near junction <strong>of</strong><br />

pressure shaft and rest <strong>of</strong> it will be used as a drainage gallery. General<br />

layout and details <strong>of</strong> surge shaft are shown in drawing No. Gharopa-FR-6.<br />

6.2.5.2 HYDRAULIC PARAMETERS<br />

Surge shaft area has been worked out by using Thomas’s criteria for<br />

incipient stability with factor <strong>of</strong> safety as 1.6m conforming to IS:7396 (Part-<br />

I) 1979. Maximum upsurge and minimum down surge levels have been<br />

computed by computer analysis as per above mentioned IS code. Maximum<br />

upsurge level works out to be 3436.00m and minimum down surge level as<br />

3996.60m. For calculating maximum upsurge and minimum down surge<br />

levels the friction co-efficient have been taken as 0.012 and 0.016<br />

respectively.


6.2.5.2 CONCRETE LINING<br />

It is proposed to provide reinforced concrete lining for surge shaft. Lateral<br />

cover around surge shaft at all heights has been kept more than three times<br />

the excavated diameter <strong>of</strong> the surge shaft. It is assumed that upsurge being<br />

<strong>of</strong> very short duration will not cause any saturation in the surrounding rock<br />

mass.<br />

6.2.6 PRESSURE SHAFT<br />

6.2.6.1 GENERAL<br />

A 4.70m dia pressure shaft with centre line at El. 3351.00m will take <strong>of</strong>f<br />

from surge shaft for leading the water in to turbines. In the initial 75m<br />

horizontal reach, a valve gallery has been proposed to accommodate<br />

butterfly valve.The inclined length <strong>of</strong> main pressure shaft is 340m. Three<br />

nos. branch pressure shaft <strong>of</strong> 2.70m dia totalling 50m in length ,takes <strong>of</strong>f<br />

from the main pressure shaft to feed three units in the power house. The<br />

entire length <strong>of</strong> the pressure shaft will be steel lined. An adit at an elevation<br />

±3348.00m to valve gallery has been provided to facilitate excavation <strong>of</strong><br />

the top horizontal reach and some inclined portion from the top and will also<br />

be utilized as drainage gallery to relieve external pressure. The excavation<br />

<strong>of</strong> remaining inclined portion will be carried out from power house cavity.<br />

The space between liner and excavated rock will be back filled with M-20<br />

conc. Adequate contact grouting will be done at contact points <strong>of</strong> concrete<br />

with liner and rock. Consolidation grouting has also been proposed in the<br />

reach, where the pressure shaft will pass through poor rock. Details <strong>of</strong><br />

pressure shaft are shown in Drawing No. CHHATRU-FR-6.


6.2.6.2 ECONOMIC DIAMETER<br />

Economical dia <strong>of</strong> the pressure shaft has been worked out by cost<br />

optimization studies for various diameters. Accordingly, a diameter <strong>of</strong><br />

4.70m has been adopted to carry the design discharge <strong>of</strong> 75 cumecs with<br />

velocity <strong>of</strong> flow as 4.32m/sec. The diameters <strong>of</strong> branches has been kept as<br />

2.70m.<br />

6.2.7 POWER HOUSE<br />

6.2.7.1 GENERAL<br />

The proposed underground power house is located about 3.50km. d/s <strong>of</strong><br />

Chhatru village on right bank <strong>of</strong> Chandra river. This site has been<br />

considered suitable for underground power house as per geo-technical<br />

appraisal note received from GSI (Ref. Chapter-IV). The tail race tunnel<br />

from power house will discharge in to river Chandra. The erection bay and<br />

transformer hall floor levels, are proposed at El. 3250m. The approach to<br />

power house and transformer hall cavern is through 7m D-shaped main<br />

excess tunnel. The machine hall and transformer hall are proposed in<br />

underground parallel cavities at suitable spacing. The control room is<br />

proposed in power house cavity while the SF6 switchgear is proposed in<br />

transformer hall cavity. A cable cum ventilation gallery/tunnel is proposed,<br />

which will initially be used for carrying out excavation and providing<br />

support system in the crown portion <strong>of</strong> power house and transformers hall<br />

cavities. Vertical and lateral cover each <strong>of</strong> ±200m approx. respectively has<br />

been provided in machine cavity and transformer hall cavity. The safety <strong>of</strong><br />

power house complex from flooding, from tail water end during<br />

construction stage will be adequately ensured.


6.2.7.2 TYPE<br />

Reconnaissance surveys for location <strong>of</strong> underground or surface power house<br />

were undertaken during the site visit <strong>of</strong> <strong>project</strong> area by HPSEB engineers<br />

and GSI authority during Jan. 2004. Surface power house has been ruled<br />

out due to the reason that the power house area remains under snow cover<br />

for maximum period in the year.<br />

Keeping in view the above fact, an underground power house with<br />

underground transformer hall has been proposed on right bank <strong>of</strong> Chandra<br />

river. Also the GIS unnderground 220 KV Switchyard has been proposed<br />

keeping in view the terrain and reliability <strong>of</strong> the system.<br />

6.2.7.3 MACHINE HALL<br />

The internal dimensions <strong>of</strong> power house cavity has been proposed as length<br />

67m and width 15m. The unit bay will be 36m long at 11.50m spacing<br />

while the erection bay and control bay have been proposed 15m and 15m<br />

long respectively . For support system in crown portion <strong>of</strong> cavity 6m long<br />

mechanically anchored , tensioned and grouted rock bolts 1.50m spacing,<br />

staggered has been proposed. 100mm thick shotcreting reinforced with<br />

welded mesh has been proposed in crown portion and sides <strong>of</strong> cavity. The<br />

spacing <strong>of</strong> rock bolts in sides has been kept at 2m c/c staggered. The<br />

columns in unit bay and erection bay have been kept 1.60m x 0.80m. For<br />

columns a nich in the side measuring 0.80mx0.80m has been proposed<br />

which will be supported by grouted anchors 25mm dia at 1m spacing. All<br />

rock bolts will be tensioned to 12 tonnes immediately after installation and<br />

pull out tests will be carried out on 2% rock bolts.<br />

The control bay is proposed on opposite side <strong>of</strong> erection bay in the end <strong>of</strong><br />

power house. Cavern for housing control room and various<br />

auxiliaries/<strong>of</strong>fices, 5 nos. floor have been proposed at El. 3248m, El.


3250m, El. 3254m, El. 3257.50m and El. 3260.50m respectively. The main<br />

inlet valve is proposed to be housed in power house cavity just u/s <strong>of</strong><br />

turbine. EOT crane <strong>of</strong> 125/25 tonnes capacity has been proposed in erection<br />

bay and unit bay to facilitate erection and repair <strong>of</strong> heavy equipment<br />

including main inlet valves.<br />

6.2.7.4 TRANSFORMER HALL<br />

The size <strong>of</strong> transformer hall cavity has been proposed as 60m long, 15m<br />

wide. The clear spacing between these two cavities has been kept at 30m.<br />

In addition to main generator transformers, space for spare transformers and<br />

station transformer has also been provided in the cavern. The transformer<br />

hall cavern will be connected to erection bay by 5mx7m D-shaped gallery<br />

for carriage <strong>of</strong> transformers at erection stage and for repairs. NG rail track<br />

is proposed between transformer hall and erection bay for transportation <strong>of</strong><br />

transformers. The transformer hall will be connected by 3 nos. bus duct<br />

galleries 3m D-shaped.<br />

The detail <strong>of</strong> power house has been shown in Drg. No. Chhatru-PF-7.<br />

6.2.8 AUXILLIARY SURGE SHAFT AND TAIL RACE TUNNEL<br />

The outflow from the end <strong>of</strong> draft tube will be taken through 3 nos. separate<br />

branch tail race tunnels. Vertical lift gates have been proposed in these<br />

branch tail race tunnels to prevent entry <strong>of</strong> silt etc. into draft tube and for<br />

facilitating repair in turbines. Downstream <strong>of</strong> this, all the branch tail race<br />

tunnels will be joined to one main tail race tunnel 6m D shaped .<br />

Auxiliary surge shaft has been proposed at the beginning <strong>of</strong> main tail race<br />

tunnel, which is ±1150m long. Broad crested weir has been proposed at its<br />

outfall.


6.3 PRELIMINARY DRAWINGS<br />

Drg. No.Chhatru-FR-1 Vicinity map 1 Sheet<br />

Drg. No.Chhatru-FR-2 Master Plan <strong>of</strong> Chenab basin(CEA schemes) 1 Shhet<br />

Drg. No.Chhatru-FR-3 Catchment Area Plan 1 Sheet<br />

Drg. No.Chhatru-FR-4 General Layout Plan 1 Sheet<br />

Drg. No.Chhatru-FR-5 Diversion Barrage, Intake, Desanding basin 2 Sheets<br />

Drg. No.Chhatru-FR-6 Head race tunnel, Surge shaft & Pressure shaft 1 Sheet<br />

Drg. No.Chhatru-FR-7 <strong>Power</strong> House & Transformer Hall 3 Sheets<br />

Drg. No.Chhatru-FR-8 Construction Facilities 1 Sheet<br />

Drg. No.Chhatru-FR-9 Construction Programme 1 Sheet<br />

Plate-6.1 Area Capacity Curve 1 Sheet


6.4 DESIGN COMPUTATIONS<br />

A. Diversion Barrage ( REF. DRG. NO. CHHATRU-FR-5)<br />

i) Design Parameters<br />

Design flood discharge = 1500 cum/sec.<br />

Average bed level <strong>of</strong> the river = ± 3405m<br />

Safe exit gradient <strong>of</strong> Nallah material (assumed) = 1 in 4<br />

The water bays <strong>of</strong> the barrage has been so proposed that design flood<br />

discharge i.e. 1500 cum/sec passes through all the bays <strong>of</strong> barrage.<br />

However, stilling basin has been designed corresponding to max. observed<br />

discharge in Chenab river i.e. 928 cumecs Say 1000 cumecs.<br />

Hence design flood discharge for stilling basin = 1000 cumecs<br />

ii) Fixation <strong>of</strong> crest level and water bay<br />

Average bed level <strong>of</strong> river = ± 3405m<br />

The crest level <strong>of</strong> barrage bays has been kept 2m higher than the average<br />

bed level at El. ±3407m . Six No. bays each 5.00m wide with 3m thick pier<br />

has been provided. The total water bay <strong>of</strong> overflow portion works out to be<br />

48.00m[(6x5)+(3.00x6)] . Two meter wide fish ladder Originating from<br />

reservoir, left bank at M.D.D.L. El. ± 3413.50m joining river bed d/s has<br />

been provided.<br />

iii) Storage capacity<br />

The live storage available in barrage reservoir between M.D.D.L. El.<br />

3413.50m and F.R.L. El. 3421m is 87.50 Hect. m. (Ref. area capacity<br />

curve). This storage capacity will run the power station at full installed<br />

capacity for 3 hrs. a day.<br />

CHECKING OF LEVELS AND CALCULATIONS FOR SIZE OF<br />

GATES<br />

Design discharge for power generation = 75 cumecs<br />

Total discharge i/c flushing discharge @ 20% = 75/(1-0.20)<br />

=75/80 = 93.75 cumecs<br />

Fixing crest level <strong>of</strong> intake = ± 3410m


a) F.R.L. Condition<br />

M.D.D.L. = ± 3413.50m<br />

F.R.L. = ± 3421.00 m<br />

Providing one no. power intake, having 8 no. bays each <strong>of</strong> size<br />

= 5.50 m(b)x3m(h)<br />

Intake crest behaves as a rectangular large orifice<br />

H1<br />

H2<br />

Discharge Passed<br />

= 11.00m<br />

= 750m<br />

Q1 = 2/3xCdxLx√ 2g (H1 3/2 -H2 3/2 )<br />

= 2/3x0.61x44√2x9.81 (11.00 3/2 –7.50 3/2 )<br />

= 316.47 cumecs >93.75 cumecs<br />

Hence O.K.


) M.D.D.L CONDITION<br />

H1 = 3.50m<br />

H2 = 0.50m<br />

Q = 2/3xCdxLx√2g (H1 3/2 -H2 3/2 )<br />

= 2/3x0.61x44x√2x9.81 (3.50 3/2 -0.50 3/2 )<br />

= 2/3x0.61x44x4.43x619 =491.00 cumecs > 93.75 cumecs<br />

Hence O.K.<br />

CHECK FOR VELOCITY THROUGH TRASH RACK<br />

Aligning trash rack at 75°<br />

Design discharge through intake/trash rack = 93.75 cumecs<br />

F.R.L. Condition<br />

Length <strong>of</strong> trash rack = xm<br />

19.50/x = Sin75°<br />

x = 19.50/Sin75° = 12.42m<br />

Area = 12.42x44 = 546.62 Sqm.<br />

Less 25% area for trash rack bars = 546.62-546.62x0.25= 409.96 Sqm.<br />

Considering 50% clogging <strong>of</strong> trash rack bars<br />

Net area available during floods = 409.96/2 = 204.98 Sqm.


Velocity through trash rack = 93.75/204.98 0.46m/sec.<br />

M.D.D.L. condition<br />

Length <strong>of</strong> trash rack = 3.50/x = Sin75°<br />

x = 3.50/Sin75<br />

x = 3.62 m<br />

Area available = 3.62x44 = 159.28 Sqm.<br />

Less 25% area <strong>of</strong> rack bars<br />

Net area = 159.28-159.28x0.25 =119.46 Sqm.<br />

Considering 50% area <strong>of</strong> trash rack bars<br />

Net area = 119.46-119.46x0.50 = 59.73 Sqm.<br />

Velocity through trash rack = 93.75/59.73 = 1.50m/sec.<br />

Hence size <strong>of</strong> intake provided and levels fixed are O.K.<br />

Gated barrage is to be provided<br />

Parameters will be as under;<br />

R.B.L. = 3405m<br />

Crest level = 3407m<br />

<strong>of</strong> barrage bays (fixed)<br />

M.D.D.L. = 3413.50m<br />

F.R.L. = 3421m<br />

M.R.L. = 3422m<br />

Top <strong>of</strong> barrage = 3424m<br />

Height <strong>of</strong> structure = 3424-3405 =19m<br />

Design flood = 1500 cum/sec.<br />

Size <strong>of</strong> gate = 8mx8.50m<br />

No. <strong>of</strong> gate = 3 No.<br />

Storage available between El. MDDL 3413.50m and F.R.L. 3421m


Live storage = 112.50-25.00 = 87.50m<br />

Less 20% for sedimentation<br />

Net = 87.50-17.50 = 70 hect .m.<br />

Time in hr = 70x10 4 /(75-10.41)x3600 = 3.01 hours<br />

For Base Load Station<br />

90% available discharge = 10.41 cumecs<br />

Design discharge = 51 cumecs<br />

<strong>Power</strong> = 9.81x51x150x0.92/1000 = 69 MW<br />

Hydraulic design <strong>of</strong> free flowing/ungated structure<br />

Design discharge for power generation = 75 cumecs<br />

Modified discharge including 20% flushing<br />

Discharge in desanding basin = 75/(1-0.20)= 93.75 cum<br />

If it is the head over intake crest to pass 93.75 cumecs discharge<br />

Q = CLH 3/2<br />

93.75 = 1.70x44xH 3/2<br />

H 3/2 = 93.75/1.70x44<br />

H = 1.16m<br />

R.B.L. = 3405m<br />

Crest level <strong>of</strong> over flow bay = 3407m<br />

Crest level <strong>of</strong> intake crest = 3410m<br />

Head over crest to pass 93.75 cumecs discharge = 1.16m<br />

Say 1.20m<br />

Water level = 3410+1.20 = 3411.20m<br />

Hence if ungated barrage is to be provided the level <strong>of</strong><br />

Ungated crest will have to be kept as 3411.20m<br />

Height <strong>of</strong> structure =3411.20-3405 = 6.20m<br />

Live storage (Between El. 3410& 3411.20m)= 12.50-6.25 = 6.25 hacm.<br />

Time in hours = 6.25x10 4 /(75-10.41)x3600 = 0.27 hrs.<br />

If height <strong>of</strong> structure is kept upto El. 3415m<br />

Height <strong>of</strong> structure = 3415-3405 = 10m<br />

Live storage (Between El. 3410 & El. 3415) = 36.89-6.25= 30.64 hacm.


Time in hrs = 30.64x10 4 /(75-100.41)x3600 = 1.31 hrs.<br />

Time to filling up <strong>of</strong> this storage = 8 months.<br />

CALCULATIONS FOR SIZE OF GATES IN BARRAGE BAYS<br />

As per I.S. recommendations, 10% gates are considered to be inoperative during<br />

floods(with min. one gate)<br />

R.B.L. = 3405m<br />

Crest level = 3407m<br />

M.D.D.L. = 3413.50m<br />

F.R.L. = 3421.00m<br />

M.R.L. = 3422.00m<br />

No. <strong>of</strong> barrage bays = 6 nos.<br />

Width <strong>of</strong> each barrage bay =5m<br />

Providing radial gate from El. 3407m to El. 3411.00m & breast wall<br />

Thereafter upto El. 3424m<br />

Size <strong>of</strong> gate = 5mx6m<br />

Discharge through breast wall spillway is estimated by the equation<br />

Q = Cb.L.D. [2g(He+Vo 2 /2g] 0.50<br />

Where L = Total width <strong>of</strong> water bays available<br />

= 5x6 =30m<br />

D = Height <strong>of</strong> opening = 6.00m<br />

He = Head from C/L <strong>of</strong> spillway<br />

He =[(3413.00-3407)/2]+[3421-3413.50]<br />

= 3.00+7.50 =10.50m<br />

Vo = Vel. <strong>of</strong> approach <strong>of</strong> flood water<br />

= 1500/185x 10.50 = 0.77m/sec.


Vel. head = Vo 2 /2g = 0.77 2 /2x9.81 = 0.03<br />

For calculating discharge co-efficient<br />

Head H = 3421-307 = 14.00m<br />

Considering that design head may be exceeded by 25%<br />

H/Hd = 1.25<br />

Design head Hd = H/1.25 = 14/1.25 = 11.20m<br />

Choosing Hd = 11.50m<br />

H/Hd = 1.4/11.50 = 1.22<br />

Corresponding value <strong>of</strong> Cb = 0.809<br />

When all the bays are open<br />

Discharge passed =Q = Cb.L.D. [2g(He+Vo 2 /2g) ] 0.50<br />

When one barrage bay is inoperative<br />

Q = 0.809x30x6.00 [2x9.81(10.50+0.03) ] 0.50<br />

= 2093.07 cumecs<br />

Q = Cb.L.D. [2g(He+Vo 2 /2g) ] 0.50<br />

= 0.809x24x6.00 [2x9.81(10.50+0.03) ] 0.50<br />

= 1674.45 cumecs<br />

HYDRAULIC DESIGN OF STILLING BASIN<br />

Fixation <strong>of</strong> pre-jump velocity and depth <strong>of</strong> flow<br />

The theoretical velocity at the start <strong>of</strong> the jump is calculated by the following relation:<br />

VT = √ 2g (H-0.50 Hd)<br />

Where VT = Theoretical velocity in m/sec.<br />

H = Difference in u/s reservoir<br />

El. and stilling basin invert in meters<br />

H = 3422-3395 = 27m<br />

H = Head over crest <strong>of</strong> barrage bays in meters


= 3422-3407 = 15m<br />

g = Acceleration due to gravity in m/sec = 9.81 m/sec.<br />

VT = √ 2x9.81 (27.00-0.50x15.00)<br />

VT = 19.55m/sec.<br />

Due to surface friction, the actual velocity is less than VT<br />

Considering VA= VT = 19.55m/sec<br />

Discharge equation<br />

Q = A1xV1<br />

Where<br />

1000 = A1x19.55 VA=V1 20.53m/sec.<br />

A1 = 1000/19.55 = 51.15 Sqm. Q = Design flood discharge <strong>of</strong><br />

Stilling basin =1000 cum<br />

L.D1 = 51.15<br />

45.00xD1 = 51.15 ∴ D1 = 51.15/45.00 =1.14m<br />

Froude No. (F) = V1/√ gd1 = 19.55/√9.81x1.14m<br />

= 5.85<br />

For Froude no. 5.85>4.50, U.S.B.R. type-III stilling basin is recommended.<br />

D2 = Depth Conjugate to D1<br />

D2 = D1/2+√2q 2 /D1g +D1 2 /4<br />

Here<br />

q = 1000/45.00 =22.22 cum/sec<br />

D2 = -1.14/2+√2x22.22 2 /1.14x9.81+1.14 2 /4<br />

= -0.57+9.41 = 8.84m<br />

Length <strong>of</strong> basin = 5xD2 = 5x8.84<br />

= 44.21m Say 50m<br />

The floor <strong>of</strong> the basin is set at such a level at to provide 5% more water depth than<br />

Y2<br />

Hence depth <strong>of</strong> basin = 8.89x1.05 = 9.28m


Cistern level = 3405-9.28 = 3395.72m<br />

Hence provided cistern level = 3395m is O.K.<br />

SIZE OF APPROACH TUNNEL<br />

Design discharge Q = 75/0.80 = 93.75 cum/sec.<br />

No. <strong>of</strong> main tunnels = 1 no.<br />

Discharge through each tunnel = 93.75 cum/sec.<br />

Vel. in the tunnel = 3.30m/sec<br />

Dia <strong>of</strong> tunnel = √(93.75/3.30)/4/Π = 6m<br />

After bifurcation<br />

Q through each tunnel = 46.87<br />

V = 3.30 cum/sec.<br />

Dia <strong>of</strong> each tunnel √ 46.87x4/3.30xΠ = 4.25m<br />

After Desilting<br />

Total design discharge, Q = 75 cum/sec.<br />

No. <strong>of</strong> tunnels = 2 nos.<br />

Discharge through each tunnel = 75/2 =37.50 cum/sec<br />

Dia = 4.00m<br />

² =<br />

V = 37.50/Π/4(4.00)<br />

2.98m/sec.<br />

DESIGN OF APPROACH TUNNEL & INTAKE STRUCTURE<br />

A. APPROACH TUNNELS ( Ref. Drawing No. Chhatru-FR-5 sheet 2 <strong>of</strong> 2)<br />

Design discharge to be drawn i/c flushing discharge = 93.75 cum/sec.<br />

No. <strong>of</strong> tunnels = 1 nos.<br />

Discharge through each tunnel = 93.75 cum/sec.


Provide size <strong>of</strong> tunnel = 6m, circular concrete lined<br />

Area <strong>of</strong> each tunnel = Π/4(d²) = Π/4(6)² = 28.27 Sqm.<br />

Vel. through each tunnel = 93.75/28.27 = 3.31 m/sec.<br />

Length <strong>of</strong> tunnel = 200m<br />

B. INTAKE STRUCTURE<br />

Considering bell mouth intake with bottom flat<br />

Width <strong>of</strong> opening = 1.42857 D D = Size <strong>of</strong> conduit i.e. tunnel<br />

= 28.57x6.00 = 8.57m<br />

Height <strong>of</strong> opening<br />

h = h1+h2<br />

h1 [(1.21 tan 2 φ +0.0847) 1/2 +1/2 cosφ -1.1 tanφ )]D<br />

Where φ is the angle <strong>of</strong> inclination with Horizontal = 0°<br />

h1 = [(1.21 tan 2 0+0.0847) 1/2 +(1/2cos 0-1.1 tan0 )] xD<br />

= [(0+0.0847)1/2 + ½]x6<br />

= (0.291+0.50) 6 = 4.75m<br />

h2 = [0.791/ +0.077 tan0]xD<br />

= (0.791+0) x 6 = 4.75m<br />

h = h1+h2 =4.75+4.75 = 9.50m<br />

Provide clear opening for intake = 8.60x9.50m<br />

The opening is rectangular and depress it to circular from starting <strong>of</strong> intake face to<br />

a distance <strong>of</strong> 1.1 D = 1.1x6 = 6.60m<br />

Here<br />

a = 6.60m<br />

b = 3.50m


Hence size <strong>of</strong> bell mouth entrance 8.60m(b)x9.50m(d) from 6m circular section<br />

Min. water cushion provided above the opening <strong>of</strong> intake<br />

= 0.3 he = 0.3x9.50 = 2.85m<br />

El. at top <strong>of</strong> intake = 3413.50-2.85 = 3410.65m<br />

C/L <strong>of</strong> intake = 3410.65-4.75/2 = 3405.90m<br />

C/L <strong>of</strong> approach tunnel = 3405.90m<br />

Hence invert level <strong>of</strong> approach tunnel at RD 0 =3405.90-6/2<br />

=3402.90m<br />

And C/L <strong>of</strong> approach tunnel at inlet = 3405.90m<br />

Invert level as invert = 3402.90m<br />

At inlet <strong>of</strong> desanding basin<br />

Invert level = 3402.50m<br />

Overt level = 3402.50+4.25m<br />

= 3406.75m<br />

HYDRAULIC DESIGN OF DESANDING BASIN (Underground )<br />

(Ref. Drawing No. Chhatru-FR-5 sheet 2 <strong>of</strong> 2)<br />

Design criteria = All particles down to 0.20mm shall be removed<br />

Parameters<br />

Design discharge for power generation = 75 cumecs<br />

Design discharge i/c 20% for deflushing in desanding basin=75/0.80 = 93.75 cumecs<br />

HYDRAULIC DESIGN<br />

Particle size to be removed = 0.020mm and above<br />

Permissible flow through vel. as per camp’s formula<br />

V = 44√d for 1mm>d>0.10mm<br />

V = 44√0.020 = 19.67 cm/sec


Provide v = 19.50 cm/sec<br />

Effective area <strong>of</strong> flow = 93.75/0.1950 = 480.76 Sqm.<br />

Provide 2 No. chambers in the desanding basin<br />

Width <strong>of</strong> each basin = 13.00m<br />

Total width = 13x2 = 26m<br />

Effective area <strong>of</strong> flow <strong>of</strong> each chamber = 480.76/2<br />

= 240.38 Sqm.<br />

CHECK FOR CROSS SECTIONAL AREA<br />

Arch Portion<br />

r = (C²+4h²)/8h = (13²+4x3.50²)/8x3.50 = 7.78m<br />

Sin α/2 = C/2/2 = 6.50/7.78 = 0.835<br />

α/2 = 56.66° α = 113.33°<br />

Length <strong>of</strong> arch =Π/180xαxr<br />

L =Π/180x113.33x7.78<br />

= 15.38m<br />

A Area <strong>of</strong> Arch Portion<br />

A1<br />

A1<br />

= ½[r.L-C(r-h)]<br />

= ½[(7.78x15.38)-13(7.78-3.50)]<br />

= ½(119.65-55.64)<br />

= 32 Sqm.


A2 = Area <strong>of</strong> rectangular Portion<br />

= 13x16.10 = 209.30Sqm.<br />

Total area = A1 + A2 =32+209.30 =241.30 Sqm.>240.38 Sqm.<br />

Hence O.K.<br />

0.20mx0.20m openings are proposed to be provided at the bottom <strong>of</strong> each<br />

pit 10m<br />

c/c to carry the silt to gallery 1.50x1.80m rectangular shaped, from where silted<br />

water will be flushed back to Beas river.<br />

Settling vel. = 2.35cm/sec corresponding to 0.20mm particle<br />

size<br />

Vel. correction W 1 = 0.132xv/√h = 0.132x0.195/√19.60<br />

W 1 = 0.00581<br />

Corrected settling vel. = W-W 1 = 0.02350-0.00581 = 0.017685<br />

Length <strong>of</strong> desanding basin<br />

L = hxV/W-W 1 = 19.60x0.195/0.017685<br />

L = 216.11m Provide L = 381m<br />

Hence size <strong>of</strong> each chamber = 381m(L)x13m(b)x19.60m(h)<br />

No. <strong>of</strong> chambers = 2 nos.<br />

CHECK FOR THE SIZE<br />

Settling time t is given by<br />

t = h/W-W 1 = 19.60/0.017685 = 1108.28 sec.<br />

Water conveyed during this period<br />

Qxt = Discharge per chamber x settling time<br />

= (93.75/2) x 1108.28 = 51950.80 cum<br />

Capacity <strong>of</strong> one chamber = 241.30x381= 91935 cum>51950.80<br />

cum<br />

Hence O.K.<br />

Removal efficiency <strong>of</strong> particle size <strong>of</strong> 0.20mm<br />

ηt = 1-(e) –WxL/vxh<br />

= 1-e –2.35x381/19.50x19.60 = 1-0.0960<br />

= 90.40%<br />

Design <strong>of</strong> transitions


Inlet transition length<br />

= B-b/2tan 12.5º = 13-4.25/2tan 12.5º<br />

= 19.73m Say 20.00m<br />

Outlet transition length<br />

= 13-4.25/2tan 12.5º = 19.73m Say 20.00m<br />

HEAD RACE TUNNEL(REF. DRAWING NO. CHHATRU-FR-6)<br />

Parameters<br />

Design discharge = 75 cumecs<br />

Shape <strong>of</strong> the tunnel (adopted) = Modified horse shoe shaped<br />

Length <strong>of</strong> head race tunnel = 6500m<br />

M.D.D.L. = 3413.50m<br />

Min. down surge level<br />

(as per computer analysis) = 3396.96m<br />

Co-efficient <strong>of</strong> friction = 0.014<br />

HYDRAULIC DESIGN<br />

Calculation for economic diameter<br />

The most economical dia <strong>of</strong> tunnel would be such as to result in a minimum total<br />

value <strong>of</strong> the sum <strong>of</strong> the following.<br />

a) Recurring annual expenditure<br />

According to Manning formula’s<br />

V = 1/nx R 2/3 S 1/2<br />

Where<br />

V = Average vel.<br />

X = Rugosity co-efficient = 0.014<br />

R = Hydraulic mean radius = 0.506287 r<br />

D = Diameter S = Slope


Now<br />

V = 1/n R 2/3 S 1/2 = 1/n (D/4) 2/3 S 1/2<br />

S = 6.40 V²n²/D 1.33 -(i)<br />

In this equation S gives value <strong>of</strong> head loss in meter or hydraulic gradient<br />

If η is the overall efficiency <strong>of</strong> generation<br />

Then<br />

<strong>Power</strong> lost Pe = 9./80xQxSxη KW -(ii)<br />

Where<br />

Q = VxΠ/4 (D²)<br />

Or V = 1.275Q/D² -(iii)<br />

From equation (i) & (iii) we got<br />

S = 6.40n²/D 5.33 x[1.275Q/D²]² - (iv)<br />

Substituting the value <strong>of</strong> S in (ii) we get<br />

revenue lost per year<br />

Pe = 9.80Q [6.40n²/D 5.33 (1.275Q/D²)²]x η KW (A)<br />

Pe = 101.96 Q 3 / D1.33 xn²xη KW<br />

Revenue lost per year<br />

Re = Pex24x365x C0 (B)<br />

From equation A&B<br />

Re = [ 101.96 Q 3 /D5.33xn²xη]x24x365xC0<br />

Re = 8.95x10 5 x Qª/D 5.33 xn 2 xηxC0<br />

Re = 8.95x10 5 x Qª/D 5.33 xηxn 2 xC0<br />

C0 = Selling rate <strong>of</strong> power per unit = Rs. 2.50<br />

η = Overall efficiency = 0.92<br />

Q = Equivalent discharge =Design discharge x Load factor<br />

= 75x0.50 = 37.50 cum/sec.


∴ Re = [8.95x10 5 x(37.50) 3 x0.92x(0.014)²x2.50] /D 5.33<br />

Re = 2.127x10 7 /D 5.33<br />

Annual expenditure/Cost per year (Ae)<br />

Assuming lining thickness = D/16 (Including OB)<br />

Qty. <strong>of</strong> excavation per meter length = Π/4 (D+2xD/16)² = Π/4x81/64 D²<br />

= 0.994 D²<br />

Rate <strong>of</strong> Excavation<br />

Good rock = 903x0.60 = Rs. 541.80<br />

Moderately jointed rock = 1499x0.20 = Rs. 299.80<br />

Poor rock = 1906x0.20 = Rs. 381.20<br />

Total = Rs. 541.80+299.80+381.20 = Rs. 1222.80<br />

Rate <strong>of</strong> over break per cum = 2.3x1222.80 = Rs. 815.20/ cum<br />

Cost <strong>of</strong> excavation including over break = 1222.80+81.52 (10% <strong>of</strong> Rs.815.20)<br />

= Rs. 1304.32<br />

Rate <strong>of</strong> excavation per cum<br />

= Rs. 1304.32<br />

Say Rs. 1305.00<br />

Rate <strong>of</strong> lining M:20 = Rs. 3177 per cum<br />

Qty. <strong>of</strong> steel for ribs @ 18 kg.per cum = 0.018x56037 = Rs. 1008.66<br />

Say Rs. 1009.00<br />

Total cost <strong>of</strong> lining = 3177+1009 = Rs. 4186.00<br />

Area <strong>of</strong> lining = Π(D+D/16)D/16 = 0.2086 D²<br />

Cost <strong>of</strong> excavation = 0.994 D²x1305 = 1297.17 D²<br />

Cost <strong>of</strong> lining = 0.2086D²x4186 = 873.19D²<br />

Total cost = 1297.17 D²+873.19 D²= 2170.36D²<br />

Total cost including over head charges @ 15% on total cost =<br />

2495.91D²


Ae = Annual expenditure @ 15.50% <strong>of</strong> above cost =<br />

= 2495.91D²x0.155 = 386.87 D 2<br />

Now T Re+Ae<br />

T = 2.13x10 7 /D 5.33 +386.87D²<br />

For mix. value<br />

DT/Dd = 0<br />

T = 2.13x10 7 /D 5.33 +386.87 D² =2.13x10 7 xD -5.33 +386.87D²<br />

For min. value<br />

DT/Dd = -5.33 D -6.33 x2.13x10 7 +2D(386.87) = 0<br />

-1.135x10 8 D -6.33 = -773.74D<br />

D 7.33 = 1.135x10 8 /773.74 = 146690.10<br />

D = 5.07m Say 5.10m<br />

Hence dia <strong>of</strong> H.R.T. (fixed) = 5.10m<br />

Vel. in the H.R.T. = 75/20.63 = 3.63m/sec.<br />

D = 5.10m<br />

R = 5.00/2 = 2.55m<br />

r = 0.987580 R =0.987580x2.55 = 2.52m


R = RARIUS OF HYDRAULICALLY EQUIVALENT CIRCLE<br />

AREA OF SECTION = 3.253 572 r 2 = 20.63 Sqm.<br />

PERIMETRE OF SECTION = 6.426 334r = 16.19m<br />

HYDRAULIC RADIUS = 0.506 287 r = 1.27m<br />

A = 0.780 776 r = 1.97m<br />

B = 1.561 553 r = 3.93m<br />

θ = 31º-22’-01”<br />

SURGE SHAFT (REF. DRAWING NO. CHHATRU-FR-6)<br />

Hydraulic Design<br />

Design discharge = 75 cumecs<br />

Size & shape <strong>of</strong> head<br />

race tunnel = 5.10m, Modified horse shoe shaped<br />

Length <strong>of</strong> head race tunnel = 6500m<br />

Value <strong>of</strong> rugosity co-efficient (assumed) = 0.012 to 0.016<br />

Computations<br />

As per IS: code 7396 Part-I<br />

Thoma area <strong>of</strong> surge tank is given by the formula<br />

Ath<br />

L.At/B V1 2 H0 V1 2 /2g<br />

Sectional area <strong>of</strong> H.R.T. 5.10m modified horse shoe shaped<br />

At = 20.63 Sqm<br />

Vel. in H.R.T. = 3.63 m/sec.<br />

BV1 2<br />

= Friction losses in the tunnel & other losses<br />

= 6.4x3.63 2 x0.014 2 x6500/(5.10) 1.33 = 12.30m


For computation <strong>of</strong> Thoma area using min. value <strong>of</strong> rugosity co-fficient<br />

Head losses with n=0.014, = 12.30m<br />

Head losses with n=0.012, = 9.04m Say 9m<br />

Other losses in trash rack approach tunnel & desilting tank = 0.30m<br />

BV1 2<br />

= 12.30+0.30 = 12.60m For n=0.014<br />

And 9.00+0.30=9.30m<br />

With n=0.012<br />

Now, Ho = Net head on turbines<br />

Ho = Net head - losses in the system<br />

Total losses = Losses upto surge shaft + penstock losses<br />

Penstock losses, hf = 0.0085x350x4.32²/2x9.81x4.80 D= 4.80m<br />

= 0.589m Say 0.60m<br />

L= 465m<br />

Q= 75 cumecs<br />

V= 4.32m/sec.<br />

F = 0.0085<br />

Total losses = 12.60+0.60 = 13.20m Say 11m with n=.014<br />

And = 9.30+0.60 = 9.90m with n=0.012<br />

Say 10m<br />

H0= (3418.50-3247.00)-10 = 161.50m<br />

Ath = 6500x20.63x3.63²/161.50x10x2x9.81 = 55.76m 2<br />

Factor for safety = 1.60<br />

Ath = Area required 55.76x1.60 = 89.22m 2<br />

Provide 15m φ surge shaft<br />

Area <strong>of</strong> surge shaft = Π/4(15)² = 176.71 Sqm.


CALCULATIONS FOR AREA OF ORIFICE<br />

Orifice area is so provided as to satisfy Calame and Gaden condition for max. flow<br />

as given below<br />

2*/√2 + ¼ hf ≤ hor ≤ Z*/√2+¾ hf<br />

Here<br />

Z* = Vo √L/gxAt/As =3.63 √ 6500/9.81*20.63/176.71<br />

For N = 0.016<br />

Hf in tunnel system = 16.06m<br />

= 31.92m<br />

= 31.92/√2+16.06/4 ≤ hor ≤ 31.92/√2+3/4x16.06<br />

For n=0.012<br />

Then<br />

= 22.57+4.01≤ hor ≤ 22.57+12.04<br />

= 26.58 ≤ hor ≤ 34.61<br />

31.92/ √2+9.00/4 ≤ hor 31.92/√2+3/4x9.00<br />

22.57+2.25 ≤ hor 22.57+6.75<br />

24.82 ≤ hor 29.32<br />

Adopt Head loss across orifice = 30m<br />

Now<br />

hor = Q0 2 /Cd 2 xA0 2 x2g<br />

A0 = Q/Cd √2g hor = 75/0.62x√19.62x30<br />

A0 = 4.98 Sqm.<br />

D = √4.98x4/Π<br />

D = 2.52m<br />

Provide orifice dia = 2.50m


Max. up surge = 13.10m<br />

As per surge analysis on<br />

computer<br />

Min. Down surge = 11.90m<br />

Max. upsurge level FRL= 3421+14.96 =3435.96m Say 3436.00m<br />

Min. downsurge level MDDL = 3413.50-16.86 =3396.64m<br />

Say 3396.60m<br />

CALCULATIONS FOR SLOPE OF TUNNEL<br />

Invert level <strong>of</strong> tunnel at RD 0 <strong>of</strong> tunnel = 3402.50m<br />

C/L <strong>of</strong> the tunnel at RD 0 = 3402.50+5.10/2<br />

= 3402.50+2.55<br />

= 3405.05m<br />

C/L <strong>of</strong> tunnel at outlet = MDDL-Losses in HRT- 1.5x orifices losses-<br />

depth <strong>of</strong> orifice-radius <strong>of</strong> HRT<br />

= 3413.50-12.30-1.5(30)-2.50-2.55<br />

= 3413.50-12.30-45-2.50-2.55 = 3351.01m<br />

Say 3351.00m<br />

Difference in levels = (3402.50-2.55)-3351 = 54.05m<br />

(RD 0 & RD 6500)<br />

Length <strong>of</strong> tunnel = 6500m<br />

Slope <strong>of</strong> tunnel = 6500/54.05 = 1:120.25<br />

Say1:120<br />

Now<br />

V1 = Q/A = 75/20.63 = 3.63m/sec.<br />

V2 = 1/4 R 2/3 S ½ = 1/0.014x1.27 2/3 (1/120) ½<br />

V2>V1 Hence O.K.<br />

= 7.46m/sec.<br />

PRESSURE SHAFT (Ref. Drawing No. Gharopa-FR-6.)


Parameters<br />

Design discharge = 75 cumecs<br />

Design net head H = 160m<br />

Length <strong>of</strong> penstock = ± 350m<br />

Efficiency <strong>of</strong> turbine = 94%<br />

Rated HP <strong>of</strong> turbine<br />

P =1000x75x160x0.94/75 = 150400 H.P.<br />

No. <strong>of</strong> pressure shaft = 1 No.<br />

Hydraulic Design<br />

Economical dia <strong>of</strong> Pressure shaft<br />

a) By DOLOND’s FORMULA<br />

Diameter = D = 0.176 (P/H) 0.466<br />

= 0.176 (150400/160) 0.466 = 4.27m<br />

b) As per R.S. Nigam’s Hand Book<br />

D ≤ [ 1xfxc 1 xk2xQ 3 xt/ 1100xK1xH] 1/7<br />

Where<br />

H = 160+20% Water hammer effect<br />

= 192m<br />

c 1 = 2444 kg/cm 2 -Allowable stress insteel<br />

(0.2x1347+0.8x2728)<br />

f = 0.0085 = Friction factor<br />

K1<br />

= 75x0.1250 = 9.37 Rs./kg. = Annual cost <strong>of</strong> pressure shaft per kg.<br />

K2 = 2.00 = Value <strong>of</strong> KWH at generator terminal in same<br />

unit<br />

t = 365x24x0.50 = 4380 hrs. = Annual duration <strong>of</strong> operation in hrs.


D = [1x0.02x2444x2.00x(75) 3 x4380/ 1100x9.37x192]1/7= 5.11m<br />

Taking average dia <strong>of</strong> (a) & (b)<br />

Average diameter = 4.27+5.11/2 = 4.69m<br />

Velocity in pressure shaft<br />

Say 4.70m<br />

V = 75/ Π/4(4.70)²<br />

= 4.32m/sec.<br />

Dia <strong>of</strong> Branch penstock (3 units)<br />

Discharge = 75/3 = 25 cumecs<br />

V = 4.32m/sec.<br />

D = √25x4/4.32 x 4/Π = 2.71m<br />

Say 2.70m<br />

CALCULATIONS FOR GROSS HEAD & NET HEAD<br />

F.R.L. in reservoir = 3421.00m<br />

MD.D.L = 3413.50m<br />

Normal water level = 3413.50+7.50x2/3<br />

= 3413.50+5 = 3418.50m<br />

Min. tail water level = 3239.50m<br />

Normal tail water level = 3240.00m<br />

Max. tail water level = 3247m<br />

Max. gross head = Normal reservoir level-Min. tail water<br />

level<br />

= 3418.50-3239.50 = 179m<br />

Min. Gross head = Max. reservoir level -Max. tail water<br />

level<br />

= 3421-3247 = 174m<br />

Design gross head = 174+2/3 (179-174)


= 177.33m<br />

Total losses from intake<br />

to power house = 17.33m<br />

Design Net Head = 180.83-17.33 = 160m<br />

TAIL RACE TUNNEL (Ref. Drawing No. Gharopa-FR-7( Sheet 2 <strong>of</strong> 3).<br />

Data<br />

Design discharge = 75 cumecs<br />

Size shape = 6m, D-shaped<br />

Length <strong>of</strong> tunnel = 1150m<br />

Assumed value <strong>of</strong> Rugosity co-efficient= 0.014<br />

Hydraulic design<br />

i) Under normal conditions the TRT will behave as a free flow tunnel<br />

V = 1/0.014x( 12.60/10.20) 2/3 (1/182.50) .5 = 6.08m/sec.<br />

Discharge passed = 12.60/6.08 = 76.69cum/sec.<br />

ii) Under HFL conditions the TRT will behave as a pressurized conduit<br />

Gross cross sectional area <strong>of</strong> tunnel = [(6x3)+(Π/4x6²/2)] = 32.13<br />

Sqm.<br />

Velocity in tail race tunnel = 75/32.13<br />

= 2.33m/sec.<br />

Fixation <strong>of</strong> crest level <strong>of</strong> T.R.T.<br />

i) Crest level at outfall will behave as a broad crested weir<br />

Now<br />

Q = CLH 3/2<br />

75 = 1.71x6xH 3/2<br />

H = [ 75/1.71x6] 3/2 = 3.76 m<br />

Crest level at outfall = 3240.00-3.76 = 3236.24m


PARA DESCRIPTION PAGE<br />

7.0 GENERAL VII-1<br />

7.1 PATTERN OF FLOWS IN 90% DEPENDABLE AND 50%<br />

MEAN YEAR<br />

VII-1<br />

7.2 HEAD FOR POWER GENRATION VII-2<br />

7.2.1 DESIGN HEAD VII-2<br />

7.2.2. MAXIMUM HEAD VII-2<br />

7. 2.3 MINIMUM HEAD VII-3<br />

7.3 POWER GENERATION IN A 90% DEPENDABLE YEAR<br />

AND 50% MEAN YEAR<br />

VII-3<br />

7.4 INSTALLED CAPACITY STUDIES VII-4<br />

TABLE-7.1 YEARWISE COMPUTATIONS FOR UN-RESTRICTED<br />

ENERGY IN GWH.<br />

TABLE-7.2 COMPUTATION FOR DEPENDABLE YEAR ON THE<br />

BASIS OF ENERGY<br />

VII-5 TO<br />

VII-9<br />

VII-10<br />

TABLE –7.3 90% DEPENDABLE AND 50% MEAN YEAR DISCHARGE VII-11<br />

TABLE- 7.4<br />

& TABLE 7.5<br />

TABLE –7.6<br />

& TABLE 7.7<br />

POWER & ENERGY GENRATION IN 90% DEPENDABLE<br />

YEAR<br />

VII-12 TO<br />

VII-22<br />

POWER & ENERGY GENRATION IN 50% MEAN YEAR VII-23 TO<br />

VII-33<br />

TABLE 7.8 SUMMARY VII-34<br />

TABLE- 7.9 SUMMARY 90% DEPENDABLE YEAR VII-35<br />

TABLE –7.10 SUMMARY 50% MEAN YEAR VII-36<br />

PLATE-7.1 INSTALLED CAPACITY CURVE VII-37<br />

PLATE-7.2 TOTAL ENRGY VS I.C. CURVE VII-38<br />

ANNE.-VII-1 COMMENTS ON POWER POTENTIAL RAISED BY CEA<br />

DT.12.04.04<br />

ANNE.-VII-2 REPLY TO THE COMMENTS RAISED BY CEA<br />

DT.12.04.04<br />

ANNX-V11-3 COMMENTS ON POWER POTENTIAL RAISED BY CEA<br />

DT.13.05.04<br />

ANNX-V11-4 REPLY TO THE COMMENTS RAISED BY CEA<br />

DT.13.05.04<br />

VII-39 -40<br />

VII-41<br />

VII-42-43<br />

VII-44-45


7.0 GENERAL<br />

CHAPTER – VII<br />

POWER POTENTIAL STUDIES<br />

Chhatru Hydro-<strong>electric</strong> Project is essentially a run- <strong>of</strong>- the river<br />

development for generation <strong>of</strong> <strong>hydro</strong>-power on Chandra river in Himachal<br />

Pradesh. It has been contemplated as a peaking station to operate in western<br />

part <strong>of</strong> Northern Regional Grid. Installed capacity <strong>of</strong> the <strong>project</strong> has been<br />

presently kept as 108 MW comprising 3 units <strong>of</strong> 36 MW each with overall<br />

efficiency <strong>of</strong> generation as 0.92.<br />

7.1 PATTERN OF FLOWS IN 90% DEPENDABLE AND 50% MEAN<br />

YEAR<br />

The 27 years discharge data from June 1973 to May, 2000 <strong>of</strong> Chandra river<br />

at Ghousal has been used to develop a series at diversion site <strong>of</strong> Chhatru<br />

HEP on catchment area basis for power generation. Energy generation has<br />

been worked out for all the years as appended in Table 7.1. .Pattern <strong>of</strong> flows<br />

in 90% dependable and 50% mean years has been worked out on the basis<br />

<strong>of</strong> energy generation in 27 years by using Welbull’s relationship P= n/m+1,<br />

where P is percentage exceedence <strong>of</strong> occurrence, n is the event no. in<br />

descending order and m is total no. <strong>of</strong> events, presented in Table 7.2. Flows<br />

in 90% dependable and 50% mean years, so worked out are given in Table<br />

7.3.<br />

7.2 HEAD FOR POWER GENERATION


7.2.1 DESIGN HEAD<br />

Gross head for power generation has been worked as 178.50 m between<br />

weighted reservoir El. 3418.50 m and normal tail water level El. 3240 m.<br />

Losses in water conductor system corresponding to design discharge <strong>of</strong> 75<br />

cumecs from intake to generating units has been worked out as 18.33 m.<br />

Design net head therefore has been taken as 160 m. The calculations are as<br />

follows:<br />

Full Reservoir Level (FRL) = ± 3421.00 m<br />

Min. Draw Down Level (MDDL) = ± 3413.50 m<br />

Normal Tail Water Level (NTWL) = ± 3240.00 m<br />

Weighted Reservoir Level = MDDL+2/3(FRL- MDDL)<br />

= 3413.50+2/3 (3421.00 – 33413.50)<br />

= 3218.50 m<br />

Gross Head = Weighted Reservoir Level – NTWL<br />

= 3418.50 – 3240 = 178.50 m<br />

Losses = 18.33 m<br />

Net Head = Gross Head – Losses<br />

= 178.50 – 18.33 = 160.17m say 160.00m<br />

7.2.2 MAXIMUM HEAD<br />

Maximum gross head has been calculated as the difference <strong>of</strong> Maximum<br />

water level ( ± 3422 m ) & Minimum Tail water level ( ± 3239.50 m) &<br />

works out to be 182.50 m.<br />

7.2.3 MINIMUM HEAD


Minimum gross head has been taken as difference between MDDL( ±<br />

3413.50 m) & Maximum tail water level ( 3247 m) & works out to be<br />

166.50 m.<br />

7.3 POWER GENERATION IN A 90% DEPENDABLE YEAR AND<br />

50% MEAN YEAR<br />

<strong>Power</strong> generation studies in a 90% dependable year corresponding to<br />

installed capacity varying from 78 MW to 159 MW are given in Table 7.4<br />

The energy generation in 90% dependable year corresponding to the<br />

installed capacity <strong>of</strong> 108 MW is 468.83351.91 GWH. The energy generation<br />

in 90% dependable year corresponding to 95% machine availability works<br />

out to be 455.72 GWH as shown in Table 7.5.<br />

<strong>Power</strong> generation studies in a 50% mean year corresponding to installed<br />

capacity varying from 75 MW to 159 MW are given in Table 7.6 The<br />

energy generation in 50% mean year corresponding to the installed capacity<br />

<strong>of</strong> 108 MW is 488.85 GWH. The energy generation in 90% dependable year<br />

corresponding to 95% machine availability works out to be 475.80 GWH as<br />

shown in Table 7.7.


7.4 INSTALLED CAPACITY STUDIES<br />

<strong>Power</strong> generation studies for 90% dependable and 50% mean pattern <strong>of</strong><br />

flows with installed capacity varying from 78 MW to 159 MW have been<br />

done.From the study the incremental increase Vs installed capacity curve &<br />

total energy Vs installed capacity curve have been drawn as shown in Plate<br />

7.1 and Plate 7.2 respectively. The fall in incremental energy occurs beyond<br />

130 MW. Moreover the plant load factor for lean season ( Dec. to Feb. ) is<br />

just below 16% from 126 to 159 MW. While deciding the installed capacity<br />

<strong>of</strong> the <strong>project</strong> it was seen that during 90% dependable year (1992-93),<br />

minimum discharge <strong>of</strong> 10.41 cumecs ( obtained from overall flow duration<br />

curve) and design flow is available in only four 10 daily blocks which is<br />

only 25% <strong>of</strong> the period in 90% dependable year.<br />

Since the <strong>project</strong> is planned as a peaking station for 3 hours to meet with<br />

peaking power shortage in the country , the installed capacity <strong>of</strong> the <strong>project</strong><br />

has been fixed at 108MW with over all PLF <strong>of</strong> 50%. It was further studied<br />

that the minimum discharge during lean season ( Dec. to Feb.) in 90%<br />

dependable year is 11.18 cumecs and therefore peaking <strong>of</strong> 3 hrs. minutes<br />

can be done.<br />

The live pondage capacity <strong>of</strong> 70 Hac-m in terms <strong>of</strong> MW hours worksout to<br />

280.79MW hours. The rest <strong>of</strong> the MW hours shall be met with from<br />

minimum flow available during peaking hours.<br />

It is therefore concluded that the installed capacity <strong>of</strong> 108 MW shall be<br />

economically optimum. An overview <strong>of</strong> <strong>hydro</strong>logical & <strong>Power</strong> studies has<br />

been given in summary table 7.8,7.9 and 7.10 respectively.


Annexure-VII-2<br />

Reply to the comments raised by Dy. Director HPI, CEA, New Delhi on power<br />

potential chapter vide letter No. 7/9/HPSEB/HP&I/2004-778 dated<br />

12.4.2004(Annexure-I).<br />

1. The computations to fix FRL, MDL and tail water have been given in the design<br />

computations incorporated in Chapter VI, Para No. 6.4(A).<br />

2. The live pondage capacity in terms <strong>of</strong> MW hours and nos. <strong>of</strong> peaking hours have<br />

been given in Chapter-VII- Para No. 7.4.<br />

3. The area capacity curve have been annexed as Plate-6.1 in Chapter-VI.<br />

4. The drop between TWL (El. 3240m) <strong>of</strong> Chhatru & FRL(3212.40m) <strong>of</strong> Khoksar<br />

could not be utilized due to the reason that during the site inspection <strong>of</strong> these<br />

<strong>project</strong>s, no suitable site for location <strong>of</strong> power house <strong>of</strong> Chhatru below El. 3240m<br />

and diversion site for Khoksar up stream <strong>of</strong> El. 3212.40m was found as per<br />

topography <strong>of</strong> the area and geological conditions.<br />

5. Summary study <strong>of</strong> power potential aspects has been incorporated in the Chapter-VII<br />

Table 7.8, 7.9 & 7.10.<br />

6. Recommendation for DPR stage:-<br />

The <strong>project</strong> has been planned as per contour interval <strong>of</strong> 20m on the S.O.I. sheet<br />

available in Scale <strong>of</strong> 1:25000. After carrying out the detailed survey <strong>of</strong> the <strong>project</strong><br />

area at higher scale the exact topography <strong>of</strong> the area shall be depicted and there is<br />

possibility <strong>of</strong> increase/decrease in the head considered at present. As such the<br />

installed capacity may fluctuate at DPR stage.


Annexure-VII-4<br />

Reply to the comments <strong>of</strong> CEA on draft PFR <strong>of</strong> Chhatru HEP (108 MW) in<br />

HP, sent by Director (HP&I) vide letter No. 7/9/HPSEB/HP&I/2004/1008<br />

dated 13.05.04.<br />

General Comments<br />

1. Initial Environmental studies alongwith Satellite Remote Sensing<br />

Based Inputs from NRSA, Hyderabad has been incorporated in<br />

Chapter IX, as per scope <strong>of</strong> work.<br />

2. CEA guidelines for financial parameters have been adopted while<br />

preparing the Economic Evaluation <strong>of</strong> the <strong>project</strong> in Chapter XIII.<br />

3. The cost <strong>of</strong> the <strong>project</strong> has been worked out as per CEA guide lines<br />

and tariff calculations for present day cost with IDC @ 10% p.a.<br />

4. The necessary recommendation for further studies have been given<br />

in Chapter-V-3 “Hydrology” P-V-52 & Chapter-VII “<strong>Power</strong><br />

Potential Studies” P-VII-41.<br />

5. Hydrology adopted in PFR has been approved by CWC, by Director<br />

Hydrology, vide letter No. I/HP/26/2004 dated 19.4.04 endorsed by<br />

Director (HP&I) letter No. HPSEB/HPI/877 dated 21.4.04 (P-V-46<br />

& 51).<br />

6. The advice <strong>of</strong> CWC on the layout planning <strong>of</strong> the <strong>project</strong> shall be<br />

taken care <strong>of</strong> at the stage <strong>of</strong> preparing the Detailed Project Report <strong>of</strong><br />

the <strong>project</strong>.<br />

7. The view <strong>of</strong> SP&PA Division <strong>of</strong> CEA on power evacuation shall be<br />

obtained at the final DPR stage, however, the power evacuation<br />

system has been proposed as per proposed evacuation plan Chenab<br />

Valley (Ref. Plate VIII-1 attached).<br />

8. Executive Summary has been incorporated as per CEA guide lines<br />

dated 2 nd Dec. 2003.<br />

9. The geo-technical studies have been got carriedout by GSI and<br />

incorporated in Chapter-IV.


<strong>Power</strong> Potential Studies<br />

Comments <strong>of</strong> power potential studies earlier received vide CEA letter No.<br />

7/9/HPSEB/HP&I/2004-778 dated 12.4.2004 have been incorporated on<br />

P-VII-30-40 as Annexure-VII-1 and reply to the same including<br />

recommendations for further studies has been appended in Annexiure-VII-2<br />

P-VII-41.


PARA DESCRIPTION PAGE<br />

8 POWER EVACUATION VIII-1<br />

8.1 APPRAISAL OF EXISTING POWER EVACUATION<br />

FACILITIES<br />

VIII-1<br />

8.2 GENERATION EQUIPMENT FOR POWER HOUSE VIII-2<br />

8.2.1 MECHANICAL EQUIPMENT VIII-2<br />

8.2.1.1 TURBINES VIII-2<br />

8.2.1.2 GOVERNOR VIII-2 TO VIII-3<br />

8.2.1.3 MAIN INLET VALVES VIII-3<br />

8.2.1.4 COOLING WATER AND FIRE PROTECTION<br />

SYSTEM<br />

VIII-3<br />

8.2.1.5 POTABLE WATER AND SANITARY DRAINAGE VIII-4<br />

8.2.1.6 DRAINAGE AND DEWATERING SYSTEM VIII-4<br />

8.2.1.7 COMPRESSED AIR SYSTEM VIII-4<br />

8.2.1.8 OIL SYSTEM VIII-5<br />

8.2.1.9 VENTILATION AND AIR CONDITIONING VIII-5<br />

8.2.1.10 POWER HOUSE CRANE VIII-5<br />

8.2.2 ELECTRICAL EQUIPMENT VIII-5<br />

8.2.2.1 GENERATOR VIII-5 TO VIII-6<br />

8.2.2.2 EXCITATION SYSTEM VIII-6<br />

8.2.2.3 GENERATOR SWITCH GEAR AND CONNECTING<br />

CABLES<br />

VIII-6 TO VIII-7<br />

8.2.2.4 GENERATOR TRANSFORMERS VIII-7<br />

8.2.2.5 CONTROL AND MONITORING EQUIPMENT VIII-7 TO VIII-8<br />

8.2.2.6 STATION SERVICE /AUXILLARY SUPPLY VIII-8<br />

8.2.2.7 POWER PLANT GROUNDING VIII-8<br />

8.2.2.8 LIGHTING VIII-8<br />

8.2.2.9 SWITCHYARD AND SWITCHING SCHEME VIII-9<br />

8.3 PROPOSED EVACUATION ARRANGEMENT TO<br />

NEAREST FACILITIES<br />

PLATE VIII- PROPOSED EVACUATION PLAN FOR CHENAB<br />

I<br />

VALLEY<br />

VIII-9<br />

VIII-10


8. POWER EVACUATION<br />

CHAPTER – VIII<br />

POWER EVACUATION<br />

8.1 APPRAISAL OF EXISTING POWER EVACUATION FACILITIES<br />

At present there is only 33 KV network in the valley which is connected to<br />

132/33 KV Sub-Station, Bajaura (Sarabai) through 33 KV Sub-Station at<br />

Manali. Independent evacuation system for the up-coming power houses in<br />

the valley will have to be evolved. Number <strong>of</strong> power houses, namely Sach-<br />

Khas (70 MW), Gondala (90 MW), Khoksar (90MW), Chhatru (108 MW)<br />

and Bardang (114 MW) are envisaged to come up in the valley. Individual<br />

evacuation system from these power houses will not be possible due to<br />

inhospitable terrain and corridor problems. The power from these power<br />

houses will have to be pooled in at some centrally located suitable place and<br />

then evacuated through D/C 400 KV system to 400 KV pooling in substation<br />

being planned/set up by POWERGRID for Parbati-III HEP near<br />

Panarsa in Kullu valley. It is proposed to pool in the power <strong>of</strong> <strong>hydro</strong> <strong>electric</strong><br />

<strong>project</strong>s coming up in Chenab valley at Tandi near Keylong which has fairly<br />

flat area for construction <strong>of</strong> sub-station and then evacuate the pooled in<br />

power through 125 Kms, 400 KV D/C line to pooling in sub-station being<br />

set up by POWERGRID at Panarsa via Rohtang Pass. The cost <strong>of</strong> pooling<br />

in sub-station at Tandi, expansion at Panarsa and 400 KV line between<br />

Tandi and Panarsa which is approximated as 240 Crores has not been<br />

included in the <strong>project</strong> cost. This system will be executed by Central/State<br />

Agency. The executing agency <strong>of</strong> this system will charge the wheeling<br />

charges from the promoters <strong>of</strong> these HEPs.


8.2 GENERATION EQUIPMENT FOR POWER HOUSE<br />

8.2.1 MECHANICAL EQUIPMENT<br />

8.2.1.1 TURBINES<br />

The vertical shaft, Francis turbine <strong>of</strong> 36.90 MW capacity with a rated<br />

synchronous speed <strong>of</strong> 428.6 rpm has been found to be suitable in view <strong>of</strong><br />

the over all economy <strong>of</strong> the power house. As per the study there is only<br />

minor difference in the width <strong>of</strong> power house, hence lower speed has been<br />

adopted which has resulted in a suction head <strong>of</strong> 6.96mtrs. below the<br />

minimum tail water level. Lower speed has however increased the overall<br />

cost <strong>of</strong> the equipment marginally, but will be compensated with the<br />

reduction in the wear & tear <strong>of</strong> under water parts <strong>of</strong> turbine due to silt which<br />

is usually high in Himalayan rivers. Each turbine shall be provided with<br />

suitable oil pressure unit, electro hydraulic governor and other requisite<br />

control equipment.<br />

8.2.1.2 GOVERNOR<br />

Since Chhatru power house will be connected with 400 KV Pooling in<br />

Tandi sub-station being set up by Central/State Agency for evacuation <strong>of</strong><br />

power from all the <strong>project</strong>s located in the valley, it is <strong>of</strong> prime importance<br />

that the governor accuracy and sensitivity is <strong>of</strong> high order so as to ensure<br />

proper behaviour <strong>of</strong> the regulators. For any change in the system load to<br />

avoid hunting and over regulation, it is proposed to provide Electro<br />

Hydraulic governor. The governing system for each unit will have an<br />

individual oil pressure system consisting <strong>of</strong> oil to air mixer and an oil tank<br />

with two pumps as well as the automatic control equipment. Speed etc.<br />

would be indicated both on the governor cubicle and on the unit control


oard to facilitate supervision <strong>of</strong> operation <strong>of</strong> the unit. The controls would<br />

include provision for emergency shut down <strong>of</strong> unit in case <strong>of</strong> :-<br />

Loss <strong>of</strong> Pressure in the oil pressure vessel <strong>of</strong> Governor oil system.<br />

Excessive temperature rise in Bearing.<br />

Excessive speed rise <strong>of</strong> the unit.<br />

Electrical faults.<br />

8.2.1.3 Main inlet valves<br />

A main inlet valve <strong>of</strong> the Butterfly with flow guides type would be provided<br />

at each turbine inlet for maintenance <strong>of</strong> the turbine and for emergency<br />

isolation <strong>of</strong> the turbine in the event <strong>of</strong> governor failure. Each valve shall be<br />

actuated by means <strong>of</strong> servomotor which shall be fed from an independent<br />

oil pressure unit. Closing <strong>of</strong> the valve shall be through counter weights.<br />

Each valve unit shall constitute a complete independent unit with its own<br />

operating system for opening and closing, which will be connected to the<br />

automatic start and stop sequence <strong>of</strong> the respective turbine unit.<br />

8.2.1.4 COOLING WATER AND FIRE PROTECTION SYSTEM<br />

A pumping system would be provided to supply adequate quantity <strong>of</strong> water<br />

from the tail race for cooling <strong>of</strong> the turbine and generator bearings,<br />

generator air coolers and selected plant services.<br />

Water for fire protection would be taken from an elevated reservoir<br />

providing both reliable operation and ample capacity to fight fire in the<br />

power house. A back up water supply to this reservoir would also be<br />

provided.


8.2.1.5 POTABLE WATER AND SANITARY DRAINAGE<br />

Water from the cooling water system would be used to supply the plant’s<br />

potable and sanitary water needs. The potable water would be filtered and<br />

chemically treated as required. Sanitary sewerage would be treated in a<br />

septic system before discharge in to tail race <strong>of</strong> power plant.<br />

8.2.1.6 DRAINAGE AND DEWATERING SYSTEM<br />

A separate drainage and de-watering system with suitable number <strong>of</strong> pumps<br />

would be provided to drain and pump out miscellaneous inflows and ground<br />

water seepage in the power house.<br />

Starting and stopping <strong>of</strong> the pumps would be automatic and controlled by<br />

level switches in the drainage sump.<br />

8.2.1.7 COMPRESSED AIR SYSTEM<br />

A high pressure compressed air plant would be installed to meet the<br />

requirements <strong>of</strong> the governor oil system and the oil pressure system <strong>of</strong> the<br />

spherical valves.<br />

A low pressure compressed air plant would also be installed to meet the<br />

requirements <strong>of</strong> the station pneumatic tools, breaking and other general<br />

purpose in the power house.<br />

8.2.1.8 OIL SYSTEM<br />

A portable dehydration unit comprising <strong>of</strong> oil heaters, Filters, tank etc.<br />

would be provided in the power station for the treatment <strong>of</strong> governor/<br />

Bearings and switch gear oils.


8.2.1.9 VENTILATION AND AIR CONDITIONING<br />

<strong>Power</strong> house would be provided with ventilation system as required for the<br />

underground power house work areas and <strong>of</strong>fices. An air conditioning<br />

system would be provided to maintain the control room at the selected<br />

design temperature and humidity levels. The temperature and humidity level<br />

would be selected to suit the requirements <strong>of</strong> equipment and staff.<br />

8.2.1.10 POWER HOUSE CRANE<br />

In order to expedite the completion <strong>of</strong> various construction activities <strong>of</strong> the<br />

power house and keeping in view the dimension <strong>of</strong> power house, <strong>electric</strong><br />

over head travelling bridge crane having capacity <strong>of</strong> 125/25 tonnes would be<br />

installed in the power house primarily for erection, maintenance and repair<br />

<strong>of</strong> the generating units. The crane would be equipped with motor control<br />

system providing suitable procedure for equipment erection.<br />

8.2.2 ELECTRICAL EQUIPMENT<br />

8.2.2.1 GENERATOR<br />

Each generator shall be <strong>of</strong> vertical shaft, salient pole type, Synchronous<br />

generator directly coupled to the <strong>hydro</strong> turbine and having a rated out put <strong>of</strong><br />

40 MVA with 0.9 lag power factor. The generator bearing arrangement<br />

shall be <strong>of</strong> conventional type i.e. suspended type. It is proposed to equip the<br />

generators with dynamic braking in addition to the friction brakes. The<br />

generator shall have class-F insulation in line with modern practice and<br />

temperature restricted to class-B insulation.<br />

The generator will be air cooled with a closed ventilation system using air<br />

water heat exchanger placed around the stator frame. The generators are


proposed to be equipped with the following <strong>electric</strong>al protection<br />

equipment:-<br />

High speed differential protection for generator.<br />

Generator Over Voltage protection.<br />

Back up over current protection.<br />

Stator earth fault relay protection.<br />

Negative Phase Sequence Current protection.<br />

Rotor Field Circuit earth Fault Relay & protection.<br />

Loss <strong>of</strong> excitation relay schemes.<br />

Generator thermal relay protection.<br />

Phase balance relay.<br />

8.2.2.2 EXCITATION SYSTEM<br />

The excitation system <strong>of</strong> the generator will be <strong>of</strong> static type and will include<br />

static type voltage regulator <strong>of</strong> latest design, field suppression equipment<br />

and the associated accessories.<br />

The power for the excitation system will be taken from the generator main<br />

bus by means <strong>of</strong> a dry type or epoxy encased step down transformer. The<br />

excitation system will be self contained requiring only an external power<br />

source for field flashing at unit starting. The field flashing supply will be<br />

taken from the station battery.<br />

The excitation system including the voltage regulator will be placed in the<br />

cubicles adjacent to the generator pit.<br />

8.2.2.3 GENERATOR SWITCH GEAR AND CONNECTING CABLES


Each generator shall be connected to its step up transformer by means <strong>of</strong> 11<br />

kV bus ducts. Current transformers required for protection, control and<br />

metering will be located and form part <strong>of</strong> the bus ducts assemblies.<br />

The generator switch gear will be <strong>of</strong> the metal enclosed type placed in a<br />

separate room close to the generator. It will include the generator phase<br />

equipment and connections shown in the attached single line diagram. The<br />

equipment for the generator neutral side will be placed in a cubicle adjacent<br />

to the generator pit.<br />

8.2.2.4 GENERATOR TRANSFORMERS<br />

10 Nos. generator transformers <strong>of</strong> 15 MVA, 11/ 220/ / 3 kV , single phase,<br />

50 Hz rating will be provided and placed in a separate cavern on the down<br />

stream side <strong>of</strong> power house. The OFWF type <strong>of</strong> cooling is proposed for<br />

generator transformer.<br />

8.2.2.5 CONTROL AND MONITORING EQUIPMENT<br />

The plant will be designed to be operated as an attended type. Unit control<br />

will be provided locally while central control will be from various control<br />

panels located in the control and relay room <strong>of</strong> the power house. Control<br />

equipment will include metering and control panels, protections for<br />

supervision and operation <strong>of</strong> the generator turbine, 11 kV switch gear ,<br />

auxiliary power system, transformers and 220 kV switch gear.<br />

The control equipment will also include the PLC and Telecommunication<br />

equipment required for the transmission lines. Provision for connection to<br />

the state load dispatch center will also be provided. The control system<br />

shall be fully computerized.


8.2.2.6 STATION SERVICE/ AUXILIARY SUPPLY<br />

The station service supply is proposed to be taken through 11 kV Local<br />

Distribution system. In addition, for reliability, 500 KVA DG sets shall also<br />

be provided for the black start capability. This will also feed local area ,<br />

Colony, head works etc. The unit auxiliaries shall be fed through 11/0.415<br />

kV, 500 KVA transformers connected to each generator. The auxiliaries can<br />

also be fed from 2 Nos., 11/0.415 kV, 1 MVA station service transformers,<br />

which are connected to 11 kV bus connected to 11 kV local supply.<br />

8.2.2.7 POWER PLANT GROUNDING<br />

8.2.2.8 LIGHTING<br />

The power station will be provided with a complete earthing system. All<br />

exposed conductive parts and equipment in the power house and switch yard<br />

will be connected to the grounding system. The grounding system will be<br />

designed to minimize the “Step” and “Touch” potential within acceptable<br />

limits.<br />

The power plant lighting , following normal practice, will comprise <strong>of</strong><br />

interior and exterior lights as appropriate. While the majority <strong>of</strong> the<br />

illuminaries will be AC powered, emergency lighting will be DC supplied<br />

from station battery system. The emergency lighting will be provided only<br />

for essential locations e.g. control room, exit tunnels etc.<br />

8.2.2.9 SWITCH YARD AND SWITCHING SCHEME<br />

Keeping in view the terrain at the power house and reliability <strong>of</strong> the system,<br />

GIS underground 220 KV Switchyard with double bus and single breaker<br />

has been envisaged. Provision <strong>of</strong> Bus Coupler has also been made. It will


e located above the generator transformers in the transformer cavern.<br />

Switchgear shall be connected to the generator transformers through 220<br />

KV oil to SF-6 connectors. The Switchgear shall be connected through app.<br />

250 mtr long 220 KV Bus ducts to the pothead yard through bus duct tunnel.<br />

This has been envisaged because power <strong>of</strong> this power house (108 MW) shall<br />

be pooled in with the down stream Khoksar (90MW) power house<br />

transmission system by LILOing one Ckt <strong>of</strong> Khoksar- Tandi 220KV line for<br />

final pooling in at Tandi 400 KV pooling point. Space requirements for pot<br />

head yard will be app. 60 X 20 mtrs.<br />

8.3 PROPOSED EVACUATION ARRANGEMENT TO NEAREST<br />

FACILITIES<br />

It is proposed to evacuate the power generated at Chhatru <strong>project</strong> by<br />

LILOing one ckt. <strong>of</strong> 220KV D/C line from Khoksar to 400 kV Pooling point<br />

at Tandi which is proposed in this basin . Beyond this point, the evacuation<br />

will be through 400 KV D/C Network to Panarsa Pooling in Sub-Station <strong>of</strong><br />

PGCIL .


PARA DESCRIPTION PAGE<br />

9.1 DESCRIPTION OF THE PROJECT IX-1<br />

9.2 DESCRIPTION OF ENVIRONMENT IX-1<br />

9.2.1 PHYSICAL RESOURCE IX-1<br />

9.2.2 HYDROLOGY IX-1<br />

9.2.3 GEOLOGY IX-1<br />

9.2.4 SOIL IX-2<br />

9.3 ECOLOGICAL RESOURCE IX-2<br />

9.3.1 FORESTS IX-2<br />

9.3.2 FLORA AND FAUNA IX-2<br />

9.3.3 FLORA IX-2<br />

9.3.4 MECHICINAL PLANTS IX-2<br />

9.3.5 FAUNA IX-3<br />

9.4 BASELINE ENVIRONMENTAL STATUS IX-3<br />

9.4.1 CLIMATE AND TEMPERATURE IX-3<br />

9.4.2 TEMPERATURE, RAINFALL AND SNOWFALL DATA<br />

OF PATSCO (ADJOINING LAHAUL VALLEY)<br />

9.5 ENVIRONMENTAL IMPACT ASSESSMENT AND<br />

EVALUATION<br />

IX-3 TO IX-4<br />

IX-5<br />

9.5.1 IMPACT IDENTIFICATION IX-5<br />

9.5.2 IMPACT IDENTIFICATION DURING CONSTRUCTION<br />

PHASE<br />

9.5.3 IMPACT IDENTIFICATION DURING OPERATIONAL<br />

PHASE<br />

IX-5<br />

IX-6<br />

9.5.4 PREDICTION OF IMPACTS IX-7<br />

9.5.5 IMPACT ON AIR ENVIRONMENT IX-7<br />

9.5.6 IMPACT ON NOISE ENVIRONMENT IX-7<br />

9.5.7 IMPACT ON WATER ENVIRONMENT IX-7<br />

9.5.8 IMPACTS ON FLORA AND FAUNA IX-7<br />

9.6 E.R&R ASPECTS IX-7


9.7 ENVIRONMENTAL MANAGEMENT PLAN<br />

(MITIGATION MEASURES)<br />

IX-8<br />

9.7.1 ENVIRONMENTAL MANAGEMENT IX-8<br />

9.7.2 ENVIRONMENTAL MANAGEMENT AT<br />

CONSTRUCTION STAGE<br />

IX-8<br />

9.7.3 SITE PREPARATION IX-8<br />

9.7.4 CONSTRUCTION IX-8<br />

9.7.4.1 AIR ENVIRONMENT IX-8<br />

9.7.4.2 NOISE ENVIRONMENT IX-9<br />

9. 7.4.3 WATER ENVIRONMENT IX-9<br />

9.7.4.4 GREEN BELT DEVELOPMENT (COMPENSATORY<br />

AFFORESTATION)<br />

IX-9<br />

9.7.4.5 DISPOSAL OF MUCK IX-10<br />

Annexure-IX-<br />

1<br />

SATELLITE REMOTE SENSING BASED INPUTS FOR<br />

INITIAL ENVIRONMENTAL STUDIES FROM NRSA<br />

STUDY BACKGROUND IX-11TO IX-12<br />

OBJECTIVE IX-12 TO IX-<br />

13<br />

SALIENT FEATURES OF THE CHHATRU HYDRO<br />

POWER SITE<br />

SATELLITE DATA USED IX-14<br />

BRIEF METHODOLOGY OF SATELLITE DATA<br />

ANALYSIS<br />

IX-13 TO IX-<br />

14<br />

IX-14 TO IX-<br />

15<br />

OUTPUTS PROVIDED IX-15 TO IX-<br />

16<br />

LIST OF TABLE IX-16<br />

TABLE-1 LANDUSE-LAND COVER INFORMATION WITHIN THE<br />

SUBMERGENCE AREA.<br />

TABLE-2 LANDUSE-LAND COVER INFORMATION WITHINTHE 7<br />

KM RADIUS FROM THE DAM SITE AT CHHATRU<br />

IX-16<br />

IX-16


CRITICAL ANALYSIS OF SATELLITE BASED INITIAL<br />

ENVIRONMENTAL STUDY<br />

IX-17 -<br />

TO IX-18<br />

CONCLUSION & RECOMMENDATION IX-18<br />

LIST OF MAPS<br />

1.a IRS ID PAN+LISS III MERGED SATELLITE IMAGE OF<br />

21 ST SEPTEMBER, 2001.<br />

1.b SATELLITE DERIVED LANDUSE-LAND COVER MAP<br />

OF SORROUNDINGS OF PROPOSED HYDRO POWER<br />

SITE AT CHHATRU, HIMACHAL PRADESH.<br />

1.c LANDUSE-LAND COVER MAP OF SURROUNDINGS<br />

UPSTREAM OF PROPOSED DAM SITE AT CHHATRU<br />

1.d MAP OF NATIONAL PARKS /SANCTUARIES AND THE<br />

LOCATION OF CHHATRU HYDRO POWER SITE AND 7<br />

KM RADIUS CIRCLE FROM THE DAM SITE.<br />

IX-19<br />

IX-20<br />

IX-21<br />

IX-22


CHAPTER IX<br />

ENVIRONMENT ASPECTS<br />

9.1 A. Description <strong>of</strong> the Project<br />

This Project is a run-<strong>of</strong>-river scheme on river Chandra with diversion barrage at<br />

about 5 km upstream <strong>of</strong> Chhatru. The <strong>Power</strong> house is located about 3.5 km<br />

downstream <strong>of</strong> Chhatru village. The Project falls in Tehsil Keylong, District Lahaul<br />

& Spiti <strong>of</strong> Himachal Pradesh.<br />

The Project envisages construction <strong>of</strong> diversion structure + 19m high, for the<br />

diversion <strong>of</strong> + 75 cumecs <strong>of</strong> discharge through a +6.5 km long tunnel to an<br />

underground <strong>Power</strong> House utilizing a gross head <strong>of</strong> + 177.33m for generating 108<br />

MW <strong>of</strong> power.<br />

9.2 B. Description <strong>of</strong> Environment<br />

9.2.1 B.1 Physical Resource<br />

9.2.2 B.1.1 Hydrology<br />

Chenab is a major river <strong>of</strong> the Indus Basin originating from the snow covered<br />

slopes <strong>of</strong> Great Himalaya <strong>of</strong> Pir-Panjal ranges in Lahaul Spiti district and flows in a<br />

steep gradient with a series <strong>of</strong> loops and bends. The two major rivers in the head<br />

ridges namely Chandra and Bhaga form the Chanra Bhaga (Chenab) river.<br />

The river Chandra originates from Bara lacha and is further augmented by Chandra<br />

Tal. The river, after flowing for more than 48 km in south westerly direction turns<br />

abruptly to the west and flows for another 64 km until it meets the Bhaga river at<br />

Tandi. The average fall <strong>of</strong> the river is 1 in 60. The first 80 km <strong>of</strong> the valley is<br />

completely uninhabited, represented by barren, eroding mountain slopes, with large<br />

alluvial flats and fans at places.<br />

The Chandra Bhaga (Chenab) flows North West and maintains an average fall <strong>of</strong> 1<br />

in 176. After traversing a distance <strong>of</strong> about 101 km from the confluence at Tandi, it


passes at karunala in to Pangi valley <strong>of</strong> Chamba District. From Thirot onwards the<br />

river, in places, passes through rocky gorges several metres deep.<br />

9.2.3 B.1.2 Geology:<br />

Great mass <strong>of</strong> the mountains is composed <strong>of</strong> ancient rocks <strong>of</strong> the lurian age, chiefly<br />

Schists, Slates and Balaini conglomerates. The principal rock formation is Mica<br />

schist, Shale and Sandstone. Taken as a whole, the rock system is very fragile and<br />

liable to erosion, which is <strong>of</strong>ten accentuated by the rigours <strong>of</strong> severe winter,<br />

avalanches and the strong winds that accompany them.<br />

The insulation and absence <strong>of</strong> any water action has led to the accumulation <strong>of</strong><br />

abundant detrital products on dry uplands and valleys forming the mantle rock <strong>of</strong><br />

regolith <strong>of</strong> fresh, un decomposed fragments. The bare mountains thus exhibit<br />

typical desert colouration <strong>of</strong> rocks due to peculiar solar weathering. The right bank<br />

is generally rocky with steep slopes.<br />

9.2.4 B.1.3 Soil:<br />

The soil is generally grey and light, charactrised by scanty plant cover and low<br />

fertility status. In the absence <strong>of</strong> any substantial leaching <strong>of</strong> minerals from the soil,<br />

the bases are continuously added to the soil complex, rendering pH to the alkaline<br />

side.<br />

The soil in the Chandra valley is loam to sandy loam with gravel. Its depth varies<br />

inversely with slope. Generally on ridges, spurs, precipitous slopes and southern<br />

aspects soil tends to be shallow and dry with numerous outcrops <strong>of</strong> bare rocks or its<br />

strew with boulders. In the vicinity <strong>of</strong> villages and nearby areas, denuded slopes are<br />

subjected to year round concentrated grazing leading to poor soil. On northern<br />

aspects, in folds and hollows as also on easier slopes the soil is fairly deep and<br />

fertile for tree growth.<br />

9.3 B.2 Ecological Resource<br />

9.3.1 B.2.1 Forests<br />

The area is totally devoid <strong>of</strong> any vegetation except for a small patch <strong>of</strong> Birch forerst<br />

on the left bank. The reason for absence <strong>of</strong> vegetation is high altitude, rocky<br />

mountains and very cold climate. However some plantation <strong>of</strong> Broad leafed species<br />

has been raised.<br />

9.3.2 B.2.2 Flora and Fauna<br />

9.3.3 B.2.2.1 Flora


The only Trees species found in the area is Birch- Betula utilis.<br />

9.3.4 B.2.2.2 Medicinal plants<br />

Important Medicinal Plants found in the area are:<br />

S.N. Common Name Botanical Name<br />

1 Patish Aconitum heterophyllum<br />

2 Mitha Telia Aconitum violaceum<br />

3 Gandha Artemisia maritima<br />

4 Karoo Picorhiza kurroo<br />

5 Ban Kakri Podophyllum hexandrum<br />

6 Dhup Jurinea macrocephala<br />

7 Shingli Mingli Dioscorea deltoides<br />

8 Patishan roots Heracleum candicans spp.<br />

9 Chora Angelica glauca<br />

9.3.5 B.2.3 Fauna:<br />

No mammal, Bird or Fish worth its name is found in this area.<br />

9.4 C. Baseline Environmental status<br />

9.4.1 C.1 Climate and temperature<br />

The high mountains <strong>of</strong> Central Himalaya act as a barrier and block the rain bearing<br />

winds from the south and as such, receive very little or no rain during the whole<br />

year. However, during winters, which usually starts from the end <strong>of</strong> September in<br />

most <strong>of</strong> the areas receives snowfall and this continues even up to May. Summers<br />

are brief while winters are quite long.<br />

9.4.2 C.1.1 Temperature, rainfall and snowfall data <strong>of</strong> Patseo (adjoining Lahaul<br />

Valley)<br />

Year Month Temperature o C Snow Fall-cm Rain Fall-mm<br />

Max Min<br />

1983 Nov 1.14 -4.54 0 0<br />

Dec -0.22 -5.76 1.25 0<br />

Jan -1.86 -8.76 4.57 0<br />

1984 Feb -2.21 -8.15 4.37 0<br />

Mar 2.83 -5.44 7.07 0<br />

April 3.20 -3.62 5.28 0<br />

May 5.22 -1.07 0 0.75<br />

Nov 1.59 0.389 1.5 0


1985<br />

1986<br />

1987<br />

1988<br />

1989<br />

1992<br />

1993<br />

1994<br />

Dec -1.54 -5.65 14.70 0<br />

Jan<br />

-3.41 -8.96 6.74 0<br />

Feb -1.41 -9.37 4.28 0<br />

March 1.00 -4.63 6 0<br />

April 2.96 -2.94 11.08 0<br />

May 4.77 -0.99 15.5 0<br />

Nov 1.55 -3.59 0 0<br />

Dec -0.04 -5.25 5.44 0<br />

Jan -1.81 -8.58 1.5 0<br />

Feb -1.48 -8.30 6.3 0<br />

March -0.58 -6.78 6.91 0<br />

April 2.35 -4.44 7.67 0<br />

May 3.93 -1.87 3.67 0<br />

Nov 1.70 -4.08 11.37 0<br />

Dec -2.09 -8.06 12.45 0<br />

Jan -1.93 -9.06 8.6 0<br />

Feb -1.33 -7.67 6.86 0<br />

March 1.05 -6.36 6.7 0<br />

April 2.33 -4.15 19.46 0<br />

May 2.02 -4.32 0 0<br />

Dec 1.60 -4.63 5 0<br />

Jan -2.09 -6.96 4.57 0<br />

Feb -0.96 -6.89 8.42 0<br />

March -0.02 -6.91 13.96 0<br />

April 2.87 -3.29 0<br />

Nov 1.56 -3.59 3.69 0<br />

Dec 0.24 5.40 5.72 0<br />

Jan -1.74 -7.99 8.29 0<br />

Feb -1.88 -7.28 5.30 0<br />

march 1.31 -5.51 5.13 0<br />

April 2.07 -4.38 4 0<br />

Nov 3.15 -3.82 3.40 0<br />

Dec 0.35 -6.53 3.67 0<br />

Jan -2.44 -8.61 9.31 0<br />

Feb 0.14 -5.96 7.64 0<br />

march 0.22 -6.90 20.78 0<br />

April 3.90 -4.42 10 0<br />

Nov 2.50 -4.04 6.5 0<br />

Dec 0.77 -7.06 0 0<br />

Jan -1.72 -8.42 9.62 0<br />

Feb -0.84 -10.26 7.45 0<br />

March 2.83 -5.96 5.22 0<br />

April 3.32 -4.26 8.44 0


1995<br />

1996<br />

1999<br />

2000<br />

May 5.94 -1.40 9.16 0.6<br />

Nov 2.89 -4.07 0 0<br />

Dec -0.84 -6.07 7.35 0<br />

Jan -2.59 -10.72 5.67 0<br />

Feb -1.12 -7.32 5.89 0<br />

March 0.90 -6.72 5.90 0<br />

April 2.66 -3.58 8.87 0<br />

Nov -1.14 -6.59 3.00 0<br />

Dec -10.6 -18.7 5.31 0<br />

Jan -1.74 -8.04 13.36 0<br />

Feb 1.30 -7.75 15.68 0<br />

March 1.55 -5.60 9.56 0<br />

April 2.78 -3.82 9 0<br />

Nov 2.31 -4.99 4 0<br />

Dec 1.76 -6.44 1 0<br />

Jan -0.07 -7.99 0 0<br />

Feb 0.18 -7.87 0 0<br />

March 1.71 -8.95 5.80 0<br />

April 4.14 -2.24 2.17 0<br />

May 8.14 0.74 0 0<br />

Air, Water, Soil and Sound data will be collected at the time <strong>of</strong> doing detailed EIA.<br />

Since this is pre feasibility report, this has not been done at this stage.<br />

9.5 D. ENVIRONMENT IMPACT ASSESSMENT AND EVALUATION<br />

9.5.1 D.1 Impact Identification<br />

Environmental impacts both direct and indirect on various environmental attributes<br />

due to Chhatru Hydropower <strong>project</strong> in the surrounding environment, during<br />

construction & operational Phase are discussed.<br />

9.5.2 D.1.1 Impact identification during construction phase<br />

The impacts due to the construction <strong>of</strong> Chhatru HEP and power house installation<br />

commence from the exploration activities, construction <strong>of</strong> barrage, tunnels and<br />

approach roads, etc., may continue up to generation <strong>of</strong> hydel power, with the nature<br />

and extent <strong>of</strong> impacts varying throughout the stage <strong>of</strong> <strong>project</strong> development.<br />

Activities like site preparation, approach roads, excavation, drilling, blasting,<br />

foundations, tunneling, deployment <strong>of</strong> machinery, erection, transportation ,dumping<br />

are taken up during construction phase. The likely impacts on the environment due<br />

to these activities are listed in table.<br />

Tunneling and foundation works will involve land excavation, filling and concrete<br />

works effecting environment by noise and dust pollution. Structural, deployment <strong>of</strong>


machinery, approach roads construction and erection work will also result in dust,<br />

noise pollution and vehicular traffic. Material handling and transportation may<br />

significantly increase noise pollution.<br />

The labour for various activities during the construction phase shall be engaged<br />

from the surrounding villages. Some essential services are also required to be<br />

provided. This will have an impact on drinking water supply and sanitary facilities.<br />

Economy <strong>of</strong> the nearby area will be improved due to increased job opportunities<br />

with corresponding increase in income. Other associated business activities like<br />

transport, hotels, consumer goods etc., will also be benefited.<br />

The major environmental parameters likely to be effected during construction phase<br />

are noise, dust pollution and sanitation. Water spraying during high dust will<br />

minimise the dust level to some extent. A proper temporary housing with water<br />

supply and sanitation for workers should be planned. The effect due to construction<br />

phase is however, <strong>of</strong> temporary in nature and has no permanent effect on<br />

environment.<br />

Construction Phase Activity Potential Environmental<br />

Impact<br />

Site work / providing other<br />

facilities.<br />

Construction <strong>of</strong> approach<br />

roads, tunneling works and<br />

construction <strong>of</strong> under<br />

ground <strong>Power</strong> Station<br />

Clearing and grading Negligible<br />

Temporary facilities, such<br />

as, sheds approach roads,<br />

sanitary facilities.<br />

Earth work comprising <strong>of</strong><br />

excavation and trenches.<br />

Dust emission and change<br />

in traffic intensity.<br />

Soil erosion, run <strong>of</strong>f,<br />

increase in traffic, Dust<br />

emission<br />

Dust, visual and noise<br />

pollution<br />

Dust and noise pollution<br />

Foundation work, piling and<br />

construction <strong>of</strong> check dams.<br />

Construction <strong>of</strong> permanent<br />

structures like roads, colony<br />

etc<br />

Mechanical erection and Dust, noise and visual<br />

utility systems.<br />

impact.<br />

Excavation Dust, soil erosion,<br />

wastewater generation and<br />

noise<br />

Drilling and blasting Dust, noise and health<br />

hazards<br />

Dumping Dust, noise and visual<br />

Transportation Dust, noise and visual<br />

9.5.3 D.1.2 Impact identification during operational phase


There would be little environmental and ecological changes during the operational<br />

phase. The main activities that may cause environmental impact on the surrounding<br />

environment during <strong>project</strong> completion and after during operation are:<br />

i. Transportation <strong>of</strong> excessive solid waste material (muck)<br />

ii. Dumping <strong>of</strong> solid waste material<br />

iii. Removal <strong>of</strong> temporary facilities, cleaning etc.<br />

9.5.4 D.2 Prediction <strong>of</strong> Impacts<br />

The impact during the construction <strong>of</strong> Chhatru HEP on environment (air, water,<br />

noise, land etc. are predicted in this section. The construction activity may cause<br />

some adverse impacts on the surrounding environment unless proper environmental<br />

management plan is adopted.<br />

9.5.5 D.2.1 Impact on air environment.<br />

Considerable amount <strong>of</strong> air pollution will be caused during different stages <strong>of</strong><br />

construction <strong>of</strong> tunnels, barrage, roads and other operations such as excavation,<br />

drilling, blasting, loading and transportation <strong>of</strong> material. Suspended Particulate<br />

Matter (SPM) is the main pollutant during construction. Most <strong>of</strong> the dust arises<br />

from drilling, blasting, excavation, crushing and transportation operations. Large<br />

quantities <strong>of</strong> dust become wind borne and are carried away from overburden<br />

dumps. The fugitive dust released during the construction activities may cause<br />

immediate effect on the construction workers who are directly exposed to the<br />

fugitive dust. Vegetation will also be adversely affected as deposition <strong>of</strong> dust on the<br />

leaves will choke the photosynthesis activity, which, in turn, will have adverse<br />

effect on the health <strong>of</strong> the plants. However, the dust does not travel to longer<br />

distance because the <strong>project</strong> site is located in between hills and V-shaped valleys.<br />

9.5.6 D.2.2 Impact on noise environment<br />

The noise will be generated at the time <strong>of</strong> construction <strong>of</strong> barrage, powerhouse,<br />

tunnel boring machine operations, pumps, drilling machines, dumpers, etc.<br />

Continuous exposure <strong>of</strong> workers to high level <strong>of</strong> noise may result in annoyance,<br />

fatigue, and may cause temporary shift <strong>of</strong> threshold limit <strong>of</strong> hearing and even<br />

permanent loss <strong>of</strong> hearing. During operational phase, noise level will be increased<br />

due trouncing machinery and vehicular movement in the area. However, these<br />

impacts are only localized.<br />

9.5.7 D.2.3 Impact on water environment.<br />

During the construction <strong>of</strong> barrage, tunnel, and power house surface water (river<br />

water) may get polluted due to the generation <strong>of</strong> large quantities <strong>of</strong> suspended


particulate matter at the time <strong>of</strong> transportation <strong>of</strong> muck and waste water (sewage)<br />

coming from temporary arrangements like <strong>of</strong>fices, labour camp sheds, etc.,<br />

9.5.8 D.2.4 Impacts on Flora and Fauna<br />

Since there is no vegetation worth its name nor any wild life, there will not be any<br />

adverse impact. There is no Wild Life Sanctuary or National Park in the Project<br />

area.<br />

However, Compensatory afforestation will be done as per the general stipulations<br />

given by the Govt. <strong>of</strong> India MOEF at the time <strong>of</strong> sanction <strong>of</strong> diversion <strong>of</strong><br />

Forestland<br />

9.6 E. R & R Aspects<br />

Since the Project is a run-<strong>of</strong>-the-river type and there is no storage, therefore, there is<br />

no submergence. Hence, no dwellings, houses or hamlets will be submerged. So,<br />

there is no displacement and resettlement is involved.<br />

9.7 F. ENVIRONMENTAL MANAGEMENT PLAN (MITIGATION<br />

MEASURES)<br />

Environmental Management Plan (EMP) aims at the preservation <strong>of</strong> ecological<br />

system by considering certain mitigating measures at the proposed site. The<br />

mitigation measures are used to minimize or prevent adverse impacts on<br />

environment due to the proposed development activity. Some <strong>of</strong> the major criteria<br />

governing the environmental measures will be adopted, and the same is described in<br />

the following paragraphs.<br />

9.7.1 F.1 Environmental Management<br />

The EMP is required to ensure sustainable development in the area <strong>of</strong> 10 Km radius<br />

<strong>of</strong> the proposed Chhatru HEP site.<br />

It is expected that the study area shall not be affected much with the proposed<br />

activity and likely to get new economic fillip due to hydel power generation, not<br />

only for the study area but also for the region as a whole.<br />

The majority <strong>of</strong> the environmental impact pertains to the construction phase. It is<br />

planned to take corrective measures to ensure that these effects are kept to bare<br />

minimum. The EMP will therefore, be initiated during planning stage itself.<br />

Catchment Area Treatment Plan, which will be prepared at a later stage, will form<br />

part <strong>of</strong> the Environmental Management Plan. However, there is not much scope <strong>of</strong><br />

plantation in the area.


9.7.2 F.1.1 Environmental management at construction stage<br />

9.7.3 F.1.1.1 Site preparation<br />

Dust emission (fugitive) and solid waste will be generated during initial site<br />

preparation activity and there will be slight increase in the noise levels around the<br />

site. The environmental impacts during the clearing or clearing for site preparation<br />

will be temporary, localised and negligible. Water sprays at appropriate location<br />

will be provided for dust suppression, hence reducing the impacts. Solid waste will<br />

be disposed <strong>of</strong>f along with the muck at the designated sites.<br />

9.7.4 F.1.1.2 Construction<br />

9.7.4.1 Air environment<br />

As discussed earlier, construction <strong>of</strong> Chhatru HEP and powerhouse activities will<br />

generate large quantities <strong>of</strong> dust during drilling, blasting, loading and transportation<br />

operations. The following measures are required be taken to mitigate the fugitive<br />

dust from different operations.<br />

To avoid the dust generation from the drilling operations, wet-drilling methods will<br />

be adopted.<br />

Ceasing dust -generating activities during high winds<br />

Covering <strong>of</strong> vehicles carrying solid waste (muck).<br />

Watering <strong>of</strong> haul roads and other roads at regular intervals<br />

Plantation near muck disposal places and dumping yards.<br />

9.7.4.2 Noise environment<br />

The major noise generating sources from the proposed activity are working<br />

machinery, blasting and movement <strong>of</strong> vehicles. The following control measures are<br />

to be undertaken to bring down the noise levels.<br />

Traffic (vehicular movement) to be managed to produce a smooth flow instead <strong>of</strong> a<br />

noisier stop -and start flow.<br />

Ensuring timely preventive maintenance <strong>of</strong> the equipment involved. Since a well<br />

maintained equipment is generally quieter than poorly maintained equipment.<br />

Ensuring usage <strong>of</strong> personal protective devices i.e., earmuffs and earplugs by<br />

workers, working in high noise activity centers.


Plantation in the vicinity <strong>of</strong> the construction area will further reduce the noise<br />

levels.<br />

9.7.4.3 Water environment<br />

During construction phase the wastewater (sewage) coming from temporary<br />

arrangements like <strong>of</strong>fices, labour camp sheds, canteens etc., and impact due to soil<br />

erosion during monsoon period may cause surface water pollution.<br />

Some <strong>of</strong> the control measures adopted for controlling water pollution are as<br />

follows:<br />

Establishing septic tanks followed by soak pits to treat the domestic waste water<br />

generated from the <strong>of</strong>fices, canteens, labour camp sheds.<br />

Construction <strong>of</strong> Check dams /rock fill dams, wherever necessary to reduce siltation<br />

and suspended solids.<br />

9.7.4.4 Green belt development (Compensatory Afforestation)<br />

Afforestation is proposed to be done in open areas with moderate slope. This has to<br />

be supplemented with engineering/vegetative works like gully plugging and check<br />

dams etc where ever required. There is very limited scope <strong>of</strong> plantation. Where ever<br />

plantation is undertaken it should be closed to grazing, lopping etc. For proper<br />

protection, it is necessary that the area is fenced and the fence is maintained<br />

properly. Plants need to be protected till they attain a height, which is above grazing<br />

level.<br />

9.7.4.5 DISPOSAL OF MUCK<br />

By constructing a 6.5 km long tunnel, the quantity <strong>of</strong> muck to be generated is<br />

estimated to be more than 0.50 lac M 3 . After applying the swell factor, the volume<br />

to be disposed <strong>of</strong>f will be about 0.75 lac M 3 . It is expected that 25-35 % <strong>of</strong> this will<br />

be used for making aggregates. The rest will require to be disposed <strong>of</strong>f in a planned<br />

manner.<br />

This is the most important aspect to be dealt with. It is proposed that at different<br />

locations dumping sites will be identified at suitable places. Retaining walls will be<br />

constructed. After the filling is done, rehabilitation <strong>of</strong> this site will be done to<br />

ensure that neither it flows in to the water stream nor it poses any other<br />

environmental threat. Plantation, wherever possible, will also be done on these sites<br />

so that these get stabilised over a period <strong>of</strong> time and do not pose any environmental<br />

problem.


Annexure-IX-1<br />

REPORT OF SATELLITE DATA ANALYSIS<br />

SATELLITE REMOTE SENSING BASED INPUTS FOR<br />

INITIAL ENVIRONMENTAL STUDIES<br />

IN<br />

RESPECT OF 6 PROPOSED HYDRO-POWER SITES<br />

IN CHENAB BASIN IN HIMACHAL PRADESH<br />

NAME OF THE HYDRO-POWER SITE : CHHATRU<br />

1. Study Background<br />

Central Electricity Authority (CEA) under <strong>Ministry</strong> <strong>of</strong> power, Govt. <strong>of</strong> India<br />

has earlier identified 399 potential <strong>hydro</strong><strong>electric</strong> sites in the country with an<br />

installed capacity <strong>of</strong> 1,07,000 Megawatt ( MW). With a view to preparing<br />

an action plan to develop this <strong>hydro</strong><strong>electric</strong> potential and prioritizing the<br />

implementation <strong>of</strong> <strong>hydro</strong>-<strong>electric</strong> <strong>project</strong>s, a Ranking study was taken up by<br />

the CEA in 2001. This Ranking study identified 162 most potential sites<br />

with a total installed capacity <strong>of</strong> 50,560 MW for development.<br />

Preparation <strong>of</strong> Pre-Feasibility Reports (PFR) <strong>of</strong> these 162 sites has been<br />

initiated by the CEA in 2002 with works entrusted to a number <strong>of</strong><br />

Consultants, namely, National Hydro<strong>electric</strong> <strong>Power</strong> Corporation (NHPC),<br />

North Eastern Electric <strong>Power</strong> Corporation (NEEPCO), Water and <strong>Power</strong><br />

Consultancy Services India Limited (WAPCOS), Satluj Jal Vidyut Nigam<br />

Limited (SVJNL), Himachal Pradesh State Electricity Board (HPSEB),<br />

Uttaranchal Jal Vidyut Nigam Limited (UJVNL) and Kerala <strong>Power</strong><br />

Corporation Limited (KPCL) with time target <strong>of</strong> completion <strong>of</strong> the whole<br />

exercise by September 2003. To oversee the progress <strong>of</strong> the PFRs<br />

preparation in time and with full cooperation <strong>of</strong> the Central Government<br />

agencies, a Central Coordination Committee consisting <strong>of</strong> Central<br />

Electricity Authority (CEA), Central Water Commission (CWC), India<br />

Meteorological Department (IMD), <strong>Ministry</strong> <strong>of</strong> Environment & Forest,<br />

Survey <strong>of</strong> India, Geological Survey <strong>of</strong> India (GSI) and National Remote


Sensing Agency (NRSA) was constituted by the CEA with Member<br />

(Hydro-power) as its representatives <strong>of</strong> the Consultants to take stock <strong>of</strong> the<br />

completion <strong>of</strong> the studies. One <strong>of</strong> the mandates <strong>of</strong> PFR preparation is<br />

“Initial Environmental Study” with respect to each <strong>of</strong> the 162 proposed sites<br />

using satellite remote sensing data.<br />

As is well known in India and elsewhere in the world, space technology<br />

plays a very important role in terrain mapping and scientific assessment <strong>of</strong><br />

the ground condition at speed, and is ideally suitable for inaccessible<br />

mountainous regions where majority <strong>of</strong> these <strong>hydro</strong><strong>electric</strong> dam/diversion<br />

site are located. Computer processing <strong>of</strong> satellite digital data <strong>of</strong> the dam/<br />

diversion site and their immediate environ provides wealth <strong>of</strong> information<br />

for preparation <strong>of</strong> the Pre-Feasibility Reports. The Potential <strong>of</strong> this<br />

technology was amply demonstrated in the preliminary ranking study <strong>of</strong> the<br />

81 proposed <strong>hydro</strong>-<strong>electric</strong> sites in Indus Basin completed by NRSA in<br />

October 2001 on behalf <strong>of</strong> CEA. In view <strong>of</strong> this, NRSA has been<br />

approached by a number <strong>of</strong> consultants, namely, NHPC and HPSEB to take<br />

up Initial Environmental Studies in respect <strong>of</strong> 37 proposed <strong>hydro</strong>- power<br />

sites located in the States <strong>of</strong> Arunachal Pradesh., Himachal Pradesh, Jammu<br />

& Kashmir and Madhya Pradesh using most recent satellite remote sensing<br />

data.<br />

Himachal Pradesh State Electricity Board (HPSEB), Sundernagar has<br />

approached NRSA for satellite remote sensing based inputs for initial<br />

environmental study <strong>of</strong> 6 <strong>hydro</strong>- power sites located in Chenab Basin in<br />

Himachal Pradesh.<br />

This Report deals with Chhatru <strong>hydro</strong>-power site.<br />

2. Objective<br />

Principal objective <strong>of</strong> the satellite based study is to acquire Indian Remote<br />

Sensing satellites (IRS IC/1 D ) LISS-III and PAN sensor digital data <strong>of</strong><br />

the <strong>hydro</strong>- power sites and to make quick analysis <strong>of</strong> these data in terms <strong>of</strong>


estimation <strong>of</strong> the submergence area at proposed Full Reservoir Level (FRL)<br />

and mapping <strong>of</strong> land use-land cover information within and in immediate<br />

surrounding <strong>of</strong> the proposed submergence area as inputs for Initial<br />

Environmental Study (IES) <strong>of</strong> the Pre-Feasibility Report.<br />

The specific objectives and scope <strong>of</strong> the study are :<br />

• To estimate the area <strong>of</strong> submergence at proposed FRL <strong>of</strong> the proposed<br />

<strong>hydro</strong>- power sites.<br />

• To analyse the satellite data for identifying broad land use-land cover<br />

categories like agricultural land, forest land, barren land, scrub land,<br />

water bodies, settlements, infrastructural features (roads and bridges)<br />

and to estimate the area under each <strong>of</strong> the categories within and in<br />

immediate surrounding <strong>of</strong> the proposed submergence area at FRL.<br />

• To prepare land use- land cover map at 1:50,000 scale and/or 1:25,000<br />

scale <strong>of</strong> the submergence area and its immediate surrounding for each<br />

<strong>hydro</strong>-power site.<br />

3. Salient Features <strong>of</strong> the Chhatru Hydro-<strong>Power</strong> Site<br />

Proposed <strong>hydro</strong>-power site is located at Chhatru in Chenab River Basin<br />

in Himachal Pradesh falling in Survey <strong>of</strong> India topo sheeets No. 52 H/3<br />

& 52 H/7. The proposed <strong>project</strong> scheme at Chhatru envisages<br />

construction <strong>of</strong> a Dam on Chandra river and a power house. The Head<br />

Race Tunnel from the dam to the power house is proposed to be 8.5 km<br />

in length. The river water will be stored in the reservoir which will be<br />

diverted through the Head-Race Tunnel to the <strong>Power</strong> House for <strong>hydro</strong>power<br />

generation. The geographic location <strong>of</strong> Dam and <strong>Power</strong> House<br />

for this <strong>hydro</strong>-power site given below:


Dam <strong>Power</strong> House<br />

Latitude : 32°18’08” N 32°20’ 9” N<br />

Longitude : 77° 24’ 41” E 77° 20’ 51” E<br />

4. Satellite data Used<br />

Indian Remote Sensing Satellite, IRS-ID LISS and PAN sensors data <strong>of</strong> 21 st<br />

September,2001 covering the study site were procured from the NRSA<br />

Data Centre (NDC) after intensive browsing <strong>of</strong> the available satellite data<br />

for cloud-free and radiometric suitability, IRS-Id covers the study site by<br />

satellite geo- reference number Path 95 and Row 48. These data are<br />

geometrically and radiometrically corrected digital data products which can<br />

be used readily in Window based image analysis platform.<br />

5. Brief Methodology <strong>of</strong> Satellite Data Analysis<br />

Image processing and analysis was done using ERDAS Imagine image<br />

analysis s<strong>of</strong>tware in Windows platform. Satellite data <strong>of</strong> IRS ID LISS III<br />

sensor provides 23.5 m spatial resolution and PAN sensor provides 5.8 m<br />

spatial resolution. The two sensor data were geocoded and digitally merged<br />

using IHS transformation technique. Baseline information layers (like<br />

rivers/streams) and infrastructural features (like roads and bridges),<br />

settlements/ villages were initially interpreted on the digital image scene.<br />

Subsequently, image classification technique was performed to obtain the<br />

land use-land cover categories <strong>of</strong> the study area.<br />

Output maps were composed in the image processing system which provide<br />

the land use/land cover information alongwith other interpreted information<br />

such as roads, settlements etc. , within the 7 Km. radius from the dam site.<br />

The Full Reservoir Level (FRL) boundary, provided by the HPSEB,<br />

Sundernagar was superimposed on the satellite data as well as on the land<br />

use- land cover map. Area statistics <strong>of</strong> different land use-land cover


categories were generated within the submergence area at FRL and within<br />

the 7 Km. radius circle from the dam site.<br />

6. Outputs provided<br />

Based on the analysis <strong>of</strong> satellite data and other available ancillary<br />

information, the following outputs were generated:<br />

• Map 1 (a) Shows IRS 1 D PAN + LISS III merged satellite<br />

image <strong>of</strong> 21 st September, 2001 on 1:50,000 scale covering 7 km.<br />

radius from the dam site overlaid with FRL, location <strong>of</strong> dam site and<br />

power house.<br />

• Map 1 (b) Shows satellite derived landuse- landcover map on<br />

1:50,000 scale covering 7 km radius from the dam site overlaid<br />

with FRL, location <strong>of</strong> dam site and power house. Land use/land<br />

cover map shows the following categories: Forest (High and<br />

Medium and low Dense Forest), Agricultural Land, Open Scrub,<br />

Barren and Rock Outcrop, Snow, River course/ Dry River Bed.<br />

• Map 1 (c) Show the land use – land cover classes and their<br />

corresponding area statistics in hectares within the submergence area<br />

on 1:25000 scale overlaid with FRL, location <strong>of</strong> dam site and power<br />

house.<br />

• Map 1 (d) Shows the location <strong>of</strong> the National parks/Wildlife<br />

Sanctuaries vis-à-vis the location <strong>of</strong> the dam/<strong>Power</strong> House and 7 km<br />

radius area around the dam site.<br />

• Table. 1 Landuse-landcover Information within the<br />

Submergence Area.


S. No. Landuse-land cover Area under % <strong>of</strong> the total<br />

category<br />

submergence(Ha) submergence area<br />

1. High Dense Forest Nil Nil<br />

2. Medium Dense<br />

Forest<br />

Nil Nil<br />

3. Low Dense forest Nil Nil<br />

4. Open scrub Nil Nil<br />

5. Barren/Rock<br />

Outcrop<br />

9.25 55.22<br />

6. Snow Nil Nil<br />

7. Agriculture land Nil Nil<br />

8. Human Settlement Nil Nil<br />

9. River Course<br />

including dry river<br />

bed<br />

7.50 44.78<br />

Total 16.75 100<br />

• Table. 2 Landuse-landcover Information within the 7 Km<br />

Radius from the Dam site at Chhatru<br />

S. No. Landuse-land cover Area under % <strong>of</strong> the total<br />

category<br />

submergence(Ha) submergence area<br />

1. High Dense Forest - -<br />

2. Medium Dense<br />

Forest<br />

98 0.64<br />

3. Low Dense forest 42 0.27<br />

4. Open scrub 4270 27.74<br />

5. Barren/Rock<br />

Outcrop<br />

8665 56.29<br />

6. Snow 2210 14.36<br />

7. Agriculture land 108 0.70<br />

Total Area 15393 100.00


7. Critical Analysis <strong>of</strong> Satellite based Initial Environmental Study<br />

• Total area under submergence at proposed FRL is estimated to be<br />

16.75 ha (Table 1).<br />

• It is observed that the landuse -landcover is mostly dominated by<br />

barren /rock outcrop which is 9.25 ha (55.22% <strong>of</strong> the submergence<br />

area). It is followed by open scrub, which is present to the extent <strong>of</strong><br />

7.5 ha (44.78% <strong>of</strong> the submergence area at the proposed FRL).<br />

• There is no agricultural area present within the proposed<br />

submergence area which is positive sign to develop the<br />

proposed <strong>hydro</strong>power site.<br />

• There are no surface water bodies other than the river course.<br />

The area under river course including dry river bed is<br />

estimated to be 7.50 ha.<br />

• In the absence <strong>of</strong> available information from other sources<br />

about the existence and spatial extent <strong>of</strong> national parks and<br />

Wildlife sanctuaries, best efforts were made to collect<br />

information from the Internet. The information available in<br />

website <strong>of</strong> United Nations Environment programme World<br />

Conservation Monitoring Center (http;//www.unep-<br />

wcmc.org) regarding Himachal Pradesh State and its<br />

National Parks/Wild Sanctuaries, were browsed through.<br />

The information at hand is made use in preparing map 1 (d)<br />

which depicts the latitude and longitude <strong>of</strong> dam site and the<br />

sanctuaries/national parks. 7 km. radius circle around the<br />

dam is plotted and the radial distance to the various national<br />

park/sanctuary were estimated around the nearest national<br />

park/sanctuary which are <strong>of</strong> significant only are measured on<br />

the map 1 (d). The following points are observed from the<br />

map 1(d).


- The nearest sanctuaries are Mani, Kais and Kanwar which are about<br />

at distance <strong>of</strong> 28 Km, 38 Km. and 45 Km. respectively whose sizes<br />

interms <strong>of</strong> aerial extent are in the figure 1(d).<br />

- Since 7 Km. radius around the dam site was considered as the area <strong>of</strong><br />

study, efforts were made to check whether the geo-coordinates <strong>of</strong><br />

this Wildlife Sanctuary is falling within the area <strong>of</strong> study. The map<br />

No. 1(d) explains the location <strong>of</strong> the sanctuary vis-à-vis the dam site<br />

and the power house.<br />

8. Conclusion & Recommendation<br />

1. Satellite based study has provided insight into the landuselandcover<br />

pattern and their spatial extent within the<br />

submergence area at FRL and within the 7 Km radius<br />

vicinity <strong>of</strong> the proposed dam site. Such detail information on<br />

a scale <strong>of</strong> 1:25,000 are not available from any other sources<br />

at present.<br />

2. There is no agricultural land within submergence area. The<br />

environmental cost on this score is therefore nil.<br />

3. Settlements in the submergence area looks to be Nil. This has<br />

to be verified on the ground for detailed information.<br />

4. The forest vegetation in the submergence area is nil, hence it<br />

is a positive thing in respect <strong>of</strong> environmental impact due to<br />

the development <strong>of</strong> proposed <strong>hydro</strong> power site.<br />

5. The submergence area landuse-landcover mainly comprises<br />

<strong>of</strong> barren (denuded hills).<br />

6. The nearest sanctuaries are Mani, Kais and Kanawar which<br />

are about at distance <strong>of</strong> 28 Km. 38 Km and 45 Km<br />

respectively. The respective sizes <strong>of</strong> these sanctuaries are<br />

3180 ha, 1419 ha and 6070 ha. Hence, in view <strong>of</strong> the small<br />

sizes <strong>of</strong> these sanctuaries, development <strong>of</strong> this <strong>hydro</strong> power<br />

site may not have any significant impact on these sanctuaries


since the fetch distance <strong>of</strong> the reservoir submergence will be<br />

around 1.3 km. only.


PARA DESCRIPTION PAGE<br />

9.0 DESCRIPTION OF THE PROJECT IX-1<br />

9.1 Description <strong>of</strong> environment IX-1 TO IX-2<br />

9.2 Ecological resource IX-2 TO IX-3<br />

9.3 Baseline Environmental status IX-3 TO IX-6<br />

9.4 Environment impact assessment and evaluation IX-6 TO IX-10<br />

9.5 R&R aspects IX-10<br />

9.6 Environmental management plan (mitigation<br />

measures)<br />

9.7 INITIAL ENVIRONMENTAL STUDIES IX-13<br />

IX-10 TO IX-13<br />

ANNEXURE-IX-1 REPORT OF SATELLITE DATA ANALYSIS IX-14 TO IX<br />

iRS ID PAN + LISS III MERGED SATELLITE<br />

IMAGE OF 21 ST SEPTEMBER,2001.<br />

satellite derived land use- LAND COVER MAP OF<br />

SURROUNDINGS OF PROPOSED HYDRO<br />

POWER SITE AT KHOKSAR, HIMACHAL<br />

PRADESH.<br />

LAND USE-land cover map <strong>of</strong> immediate<br />

surroundings upstream <strong>of</strong> proposed dam site at<br />

khoksar.<br />

MAP OF NATIONAL PARKS/SANCTUARIES<br />

AND THE LOCATION OF KHOKSAR HYDRO<br />

POWER SITE AND 7 KM. RADIUS CIRCLE FROM<br />

THE DAM SITE.<br />

MAP- 1 (a)<br />

MAP- 1 (b)<br />

MAP- 1 (c)<br />

MAP- 1 (d)


PARA DESCRIPTION PAGE<br />

10.0 IDENTIFICATION OF THE BROAD INFRASTRUCTURAL<br />

REQUIREMENT FOR IMPLEMENTATION OF PROJECT<br />

10.1 ROADS X-1<br />

10.1.1 GENERAL X-1<br />

10.1.2 PROJECT ROADS X-2<br />

10.2 BUILDINGS X-2<br />

X-1


10.2.1 COLONY AT SUNDERNAGAR X-2<br />

10.2.2 COLONY AT VILLAGE CHHATRU X-3<br />

10.2.3 OFFICE COMPLEX FOR OUTLET SIDE WORKS X-3<br />

10.2.4 SCHOOL & HOSPITAL X-4<br />

10.2.5 FIELD HOSTEL AND REST HOUSE X-4<br />

10.3 DUMP AREA X-4<br />

10.4 JOB FACILITIES X-4<br />

10.5 QUARRY SITES X-4<br />

10.6 TELEPHONES X-5<br />

10.6.1 INTERNAL TELEPHONE SYSTEM X-5<br />

10.6.2 EXTERNAL TELEPHONE SYSTEM X-5<br />

10.7 WIRELESS SYSTEM X-5<br />

10.8 PLANT AREA X-5 TO<br />

X-6<br />

10.9 FIELD WORKSHOP X-6<br />

10.10 CONSTRUCTION POWER X-6<br />

10.11 SAFETY X-6 TO<br />

X-7


CHAPTER – X<br />

INFRASTRUCTURE<br />

10.0 IDENTIFICATION OF THE BROAD INFRASTRUCTURAL<br />

REQUIREMENT FOR IMPLEMENTATION OF THE PROJECT<br />

10.1 ROADS<br />

Chhatru Hydel Project is situated in Lahaul & Spiti Distt. <strong>of</strong> Himachal<br />

Pradesh. The barrage site on Chandra river about 5 km. u/s <strong>of</strong> Chhatru<br />

village is located about 407 Kms. from Chandigarh, which is approachable<br />

through an all weather road from Chandigarh to Manali(315 km)by NH-21,<br />

from Manali to Gramphu (Shiprang) motorable road (June to Oct.),70 km.<br />

and then to diversion site motorable raod (July to Sept.) 22 km. along<br />

Manali-Leh road. <strong>Power</strong> House site is only approachable by constructing a<br />

link road about 7 km. from suspension bridge on Manali-Leh road. The<br />

power house is about 8.50 km. d/s <strong>of</strong> proposed diversion site.<br />

Adequate provision for residential and non-residential accommodations with<br />

necessary amenities has been made for construction and design staff<br />

proposed for the <strong>project</strong>. Workshop, stores, POL pumps, explosive<br />

magazine and other infrastructural facilities have also been provided in the<br />

estimate. Necessary provision for telecommunication, medical , educational<br />

facilities and safety /security measures have also been made in the report.<br />

All infrastructure facilities proposed ro this <strong>project</strong> has been shown in Drg.<br />

No. Chhatru- FR-8.


10.1.1 GENERAL<br />

A total <strong>of</strong> about 2 km. length <strong>of</strong> (5/7m. wide) road shall be needed to<br />

connect the existing motorable road with the various <strong>project</strong> components.<br />

The widening <strong>of</strong> existing roads in the total length <strong>of</strong> 8.50 kms. has been<br />

proposed.<br />

10.1.2 PROJECT ROADS<br />

Approach road 5/7 m. wide, 4.9 Km. long will connect different work sites<br />

<strong>of</strong> the <strong>project</strong> with the existing motorable road.<br />

The following roads have been proposed.<br />

1. C/O proposed road to top <strong>of</strong> surge shaft<br />

and power house<br />

= 10.00 km.<br />

2. C/O proposed road to adit <strong>of</strong> HRT = 4.00 km<br />

3. C/O proposed road from main road to colony,<br />

Dumping areas & quarry site etc. = 6.00 km.<br />

4. Re-aligning <strong>of</strong> existing main road along<br />

proposed reservoir = 2.00 km<br />

Total = 17.00 km.<br />

5. Widening <strong>of</strong> existing motorable road from<br />

Diversion site <strong>of</strong> Khoksar HEP to power house<br />

<strong>of</strong> Chhatru HEP = 17.00 km.<br />

Total = 17.00 km.<br />

6. Provision <strong>of</strong> R..C.C.bridge in place <strong>of</strong><br />

existing suspension bridge = 1No.


10.2 BUILDINGS<br />

It is proposed to construct residential and non-residential colonies for this<br />

<strong>project</strong> at village Baran in private land.<br />

10.2.1 COLONY AT SUNDERNAGAR<br />

A permanent residential/non-residential complex for design organization will be<br />

constructed at Sundernagar. The same can be used for monitoring/planning liaison<br />

purpose after the completion <strong>of</strong> the <strong>project</strong>.<br />

10.2.2 COLONY AT VILLAGE CHHATRY<br />

Residential/non-residential colony for the construction <strong>of</strong> the <strong>project</strong> is<br />

proposed to be constructed at village Chhatru which is about 5 km from barrage<br />

and 3.50 km. from power house. Labour huts , stores and field <strong>of</strong>fices will be<br />

constructed nearby the <strong>project</strong> components on the small terraces available.<br />

10.2.3 OFFICE COMPLEX FOR OUTLET SIDE WORKS<br />

Office complex for the construction <strong>of</strong> power house complex, penstock, surge<br />

shaft and tunnel from outlet end is proposed on the terrace available near the<br />

inlet <strong>of</strong> main access tunnel to power house.<br />

10.2.4 SCHOOL & HOSPITAL


Adequate provision <strong>of</strong> buildings for Hospital, school etc.has been made in the<br />

<strong>project</strong> estimate under Sub-Head K-buildings to cater for construction force.<br />

First aid posts shall be provided at all <strong>project</strong> sites.<br />

10.2.5 FIELD HOSTEL & REST HOUSE<br />

Field hostel is proposed to be constructed in the <strong>project</strong> area near residential<br />

colony.<br />

10.3 DUMP AREA<br />

The muck <strong>of</strong> open & underground excavation shall be dumped in dump areas<br />

located d/s <strong>of</strong> diversion structure and inlet <strong>of</strong> HRT. The dumping station for<br />

power house muck may be proposed at 4.50 km from power house. Dump<br />

areas chosen are located much above the river/nallah banks and are provided<br />

with suitable retaining walls etc. Bull dozers shall be deployed in dump areas<br />

for spreading and compaction <strong>of</strong> dumped material.<br />

10.4 JOB FACILTIES<br />

Flat terraces available near the <strong>project</strong> components wherever possible shall be<br />

utilized for job facilities like stacking <strong>of</strong> construction material, D.G. sets, truck,<br />

trailers, cement carriers, road rollers and site <strong>of</strong>fice stores etc.<br />

10.5 QUARRY SITES<br />

The material in the river bed may be suitable for aggregate. Rock from<br />

different quarries in the vicinity <strong>of</strong> the <strong>project</strong> may also be identified, to assess<br />

their suitability for manufacturing aggregate.


10.6 TELEPHONE<br />

10.6.1 INTERNAL TELEPHONE SYSTEM<br />

It is proposed to have an independent telephone exchange for this <strong>project</strong>. All<br />

important work sites, <strong>of</strong>fices within the <strong>project</strong> area will be connected by<br />

telephones. A 50-lines capacity private automatic exchange (PBX) for the<br />

<strong>project</strong> will be provided .<br />

10.6.2 EXTERNAL TELEPHONE SYSTEM<br />

Telecommunication link between <strong>project</strong> sites and outside places will be<br />

provided by existing communication net work <strong>of</strong> Post & Telegraph<br />

Department connected to the nearest P&T exchange at Manali. This system<br />

would be operated and maintained by P&T Department on rental basis.<br />

<strong>Power</strong> Line communication carrier system is also proposed for the <strong>project</strong>.<br />

10.7 WIRELESS SYSTEM<br />

On the pattern <strong>of</strong> other on going hydel <strong>project</strong>s in H.P., fixed type VHF<br />

Wireless link is proposed to be provided between <strong>project</strong> sites and design <strong>of</strong>fice<br />

at Kullu, which will be further connected to existing wireless system <strong>of</strong> HPSEB<br />

at Shimla.<br />

10.8 PLANT AREAS<br />

Plant area for different sites <strong>of</strong> work have been provided near respective sites.<br />

It is proposed to install a central aggregate crushing, processing and<br />

classification plant near quarry site proposed at 15 miles station which will<br />

fulfill the requirements <strong>of</strong> aggregates for barrage & inlet end works and


powerhouse site to cater for the requirements <strong>of</strong> works <strong>of</strong> HRT from outlet end,<br />

surge shaft, penstock and powerhouse and appurtenant works. An adequate<br />

capacity batching and mixing plant will be installed near barrage to cater the<br />

requirements <strong>of</strong> concrete for all inlet side works including tunnel lining. Other<br />

batching and mixing plants <strong>of</strong> requisite capacity will be provided near power<br />

house site for concreting work in power house complex , pressure shaft, head<br />

race tunnel and surge shaft.<br />

Central compressor houses will be located near tunnel portal to meet up the<br />

requirements <strong>of</strong> the compressed air.<br />

10.9 FIELD WORKSHOP<br />

The workshops/repair shops are proposed to be established near barrage site &<br />

power house site.<br />

10.10 CONSTRUCTION POWER<br />

10.11 SAFETY<br />

Requirement <strong>of</strong> construction power will be met form existing transmission net<br />

work in the area by suitably augmenting the same to meet requirement <strong>of</strong> the<br />

<strong>project</strong> at various sites. Necessary provision for providing power lines and<br />

distribution system has been made in the <strong>project</strong> estimate.<br />

Adequate provision for stand by diesel generating sets has been made in the<br />

<strong>project</strong> estimate to meet up power requirements in the event <strong>of</strong> power failures,<br />

shutdowns / breakdown.<br />

Safety is an essential job requirement for a highly mechanized work set up.<br />

Adequate provision for fire fighting arrangements and security arrangements


has been made in the <strong>project</strong> estimate by way <strong>of</strong> police post/check-post and<br />

check barriers etc.<br />

Adequate safety/preventive measures against accidents are proposed to be taken<br />

in accordance with the following Indian Standard Codes:<br />

IS: 4756 For safety in tunneling work.<br />

IS 3996 For scaffolds and ladders.<br />

(Part I&II)<br />

IS: 3764 For excavation work.<br />

IS: 4081 For blasting and related drilling operations.<br />

IS: 4138 For working in compressed air.


PARA DESCRIPTION PAGE<br />

11.0 CONSTRUCTION PLANNING & SCHEDULE XI-1<br />

11.1 GENERAL APPROACH FOR CONSTRUCTION PLANNING FOR<br />

EXECUTION OF PROJECT COMPONENTS<br />

XI- 1<br />

11.1.1 CONSTRUCTION METHODOLOGY & EQUIPMENT PLANNING XI-1<br />

11.1.2 GENERAL XI-1<br />

11.1.3 COMPLETION TIME AND AVAILABLE WORKING SEASON XI-2<br />

11.1.4 APPROACH ROAD AND THE LOCATION OF THE PROJECT XI- 2<br />

11.1.5 CONSTRUCTION MATERIAL XI- 2<br />

11.1.5.1 CEMENT XI- 2<br />

11.1.5.2 STEEL XI-2 TO XI-3<br />

11.1.5.3 AGGREGATE XI- 3<br />

11.1.6 STORES, LUBRICATION& WORK SHOP XI- 3<br />

11.1.7 AGGREGATE PROCESSING PLANTS. XI- 3<br />

11.1.8 PLANT AREAS XI-3 TO XI-4<br />

11.1.9 DUMP AREAS XI-4<br />

11.1.10 PRE-CONSTRUCTION FACILITIES XI-4<br />

11.1.11 EQUIPMENT PROVISION XI- 4<br />

11.2 CONSTRUCTION SCHEDULE XI- 5<br />

11.2.1 INFRASTRUCTURAL WORKS XI-5<br />

11.2.2 DIVERSION BARRAGE XI-5<br />

11.2.3 INTAKE STRUCTURE XI-5 TO XI-6<br />

11.2.4 DESILTING TANK XI- 6<br />

11.2.5 MECHANICAL WORKS FOR THE ABOVE FEATURES XI- 6<br />

11.2.6 HEAD RACE TUNNEL XI-6 TO XI-7<br />

11.2.7 SURGE SHAFT XI- 6 TO XI-7<br />

11.2.8 PRESSURE SHAFT XI-7<br />

11.2.9 POWER HOUSE XI- 7<br />

11.2.10 TAIL RACE TUNNEL XI- 7<br />

11.2.11 INSTALLATION TESTING AND COMMISSIONING XI-7


CHAPTER – XI<br />

CONSTRUCTION PLANNING & SCHEDULE


11.0 CONSTRUCTION PLANNING & SCHEDULE<br />

11.1 GENERAL APPROACH FOR CONSTRUCTION PLANNING AND<br />

EXECUTION OF PROJECT COMPONENTS<br />

11.1.1 CONSTRUCTION METHODOLOGY & EQUIPMENT PLANNING<br />

11.1.2 GENERAL<br />

Chhatru Hydel Project is a 108 MW capacity run <strong>of</strong> the river scheme in<br />

Lahaul & Spiti District <strong>of</strong> H.P envisages utilization <strong>of</strong> 75 cumecs <strong>of</strong> design<br />

discharge and 177.83m <strong>of</strong> gross head. Diversion barrage about 5 km. u/s <strong>of</strong><br />

Chhatru village and power house about 3.50 km d/s <strong>of</strong> Chhatru village has<br />

been proposed . The <strong>project</strong> comprises following main civil structures:<br />

Barrage<br />

Intake structure<br />

Desilting arrangement<br />

Head Race Tunnel<br />

Surge Shaft<br />

Pressure shaft<br />

<strong>Power</strong> House<br />

Tail race tunnel<br />

11.1.3 COMPLETION TIME AND AVAILABLE WORKING SEASON<br />

Construction programme, selection <strong>of</strong> methodology and equipment have<br />

been planned with the aim <strong>of</strong> commissioning <strong>of</strong> the <strong>project</strong> in four and half<br />

years. Available working season in a year shall be <strong>of</strong> 12 months for all


underground works, 9 months for surface works above river bed and eight<br />

months for the works in the river bed.<br />

11.1.4 APPROACH ROAD AND THE LOCATION OF THE PROJECT<br />

A total <strong>of</strong> about 22 Km road (5/7 m wide) shall be needed to connect the<br />

existing motorable road with the <strong>project</strong> components i.e. Adit to HRT,<br />

surge shaft area, <strong>Power</strong> house and colony area .<br />

11.1.5 CONSTRUCTION MATERIAL<br />

11.1.5.1 CEMENT<br />

11.1.5.2 STEEL<br />

ACC cement factory located at Barmana in Distt. Bilaspur (HP), on NH-21<br />

and at a distance <strong>of</strong> 215 Kms from the <strong>project</strong> site shall be the main source<br />

<strong>of</strong> cement for meeting the entire cement requirement <strong>of</strong> the <strong>project</strong>. Bagged<br />

cement shall be transported in trucks and stored in <strong>project</strong> stores at different<br />

sites.<br />

Steel stockyard at Parwanoo, 400 Kms. from main <strong>project</strong> store, shall be the<br />

main source <strong>of</strong> structural and reinforcement/ tor. steel. Sizeable quantities <strong>of</strong><br />

reinforcement steel and structural steel shall have to be stocked and<br />

replenished regularly. Penstock steel plates if not available indigenously<br />

however, may have to be imported to suit the design specifications.<br />

11.1.5.3 AGGREGATE<br />

The material in the river bed may be suitable for aggregate, however, the<br />

same has to be got tested at detailed investigation stage.


Rock from different quarries in the vicinity <strong>of</strong> the <strong>project</strong> may also be got<br />

identified, to assess their suitability for manufacturing aggregate. Rock<br />

extracted from the quarries as well as from tunnel will be crushed and<br />

classified to various sizes <strong>of</strong> aggregate in batching and mixing plant one<br />

near the barrage site and other near power house ( for excavated material<br />

from tunnel).<br />

11.1.6 STORES, LUBRICATION & WORK SHOP<br />

The Petrol/diesel pumps, explosives magazine, workshops and other<br />

construction facilities shall be provided to facilitate execution <strong>of</strong> the <strong>project</strong>.<br />

While central stores for storage <strong>of</strong> cement, T&P articles, steel yard as well<br />

as timber yard and main workshop shall be provided . Site stores and field<br />

workshops will be established near respective sites. Petrol/diesel pump shall<br />

be established near the power house site.<br />

11.1.7 AGGREGATE PROCESSING PLANTS<br />

Two aggregate crushing classification and sand manufacturing plants shall<br />

be installed near each site <strong>of</strong> work and 2 nos. batching and mixing plants<br />

shall be located near <strong>Power</strong> house& barrage site.<br />

11.1.8 PLANT AREAS<br />

Plant areas for locating air compressor house, cement, aggregate, T&P<br />

stores and water storage tanks etc., shall be located near each site <strong>of</strong> work<br />

and 2 nos. batching and mixing plants shall be located near <strong>Power</strong> house&<br />

barrage site.<br />

11.1.9 DUMP AREAS


The muck <strong>of</strong> underground excavation shall be dumped in dump areas<br />

located within 1to 4.5 km from each portal. Dump areas for over ground<br />

excavation in barrage shall be at a maximum distance <strong>of</strong> 1 km and power<br />

house area at a distance <strong>of</strong> 4.50 km.. Dump areas chosen are located much<br />

above the river/nallah banks and are provided with suitable retaining walls<br />

etc. Bull dozers shall be deployed in dump areas for spreading and<br />

compaction <strong>of</strong> dumped material.<br />

11.1.10 PRE-CONSTRUCTION FACILITIES<br />

Pre construction facilities such as land acquisition for labour huts, plant<br />

areas, stores, residential and non residential buildings, approach roads,<br />

construction <strong>of</strong> bridges and explosive magazine in the valley shall be made<br />

available to facilitate construction <strong>of</strong> the <strong>project</strong>.<br />

11.1.11 EQUIPMENT PROVISION<br />

Since main works <strong>of</strong> the <strong>project</strong> are proposed to be executed on contract<br />

basis except the required infrastructural facilities as such the necessary<br />

provision <strong>of</strong> machinery like material trucks, trailors, cement carriers, motor<br />

grader and road rollers etc. has been made under Q-special-T&P, for<br />

carrying out the works <strong>of</strong> infrastructural facilities. Provisions for personal<br />

carriers, ambulance and field workshop equipment have also been made<br />

under <strong>project</strong> estimate.<br />

11.2 CONSTRUCTION SCHEDULE<br />

The <strong>project</strong> has been proposed to be completed in 4½ years. Method <strong>of</strong> execution <strong>of</strong><br />

various components and selection <strong>of</strong> equipments have been done with the object <strong>of</strong><br />

commissioning first <strong>hydro</strong> unit by the end <strong>of</strong> 3 rd month <strong>of</strong> the fifth year, the second unit


y the end <strong>of</strong> 5 th month <strong>of</strong> fifth year and the third unit by the end <strong>of</strong> 6 th month <strong>of</strong> fifth<br />

year.<br />

11.2.1 INFRASTRUCTURAL<br />

It is proposed that all infrastructural works on the <strong>project</strong> comprising roads, buildings,<br />

adits, workshops, stores, utility works, surveys, development <strong>of</strong> quarries, leveling <strong>of</strong> area<br />

for installation <strong>of</strong> equipment and plants, pre-qualification <strong>of</strong> tenders, award <strong>of</strong> contracts,<br />

detailed design <strong>of</strong> components and other preliminary works shall be continued upto 4 th<br />

year <strong>of</strong> <strong>project</strong> execution.<br />

11.2.2 DIVERSION BARRAGE<br />

i) C<strong>of</strong>fer dam:- During 7 th month <strong>of</strong> <strong>project</strong> construction.<br />

ii) Excavation <strong>of</strong> barrage Const. Ist stage<br />

From 8 th month to 13 th month <strong>of</strong> <strong>project</strong> construction.<br />

iii) Concreting <strong>of</strong> barrage Ist stage<br />

From 10 th month to 21 st month.<br />

iv) C<strong>of</strong>fer dam 2 nd stage<br />

During 22 nd month.<br />

v) Excavation <strong>of</strong> barrage 2 nd stage<br />

From 23 rd month to 31 st month.<br />

vi) Concreting <strong>of</strong> barrage 2 nd stage<br />

From 32 nd month to 36 th moth.<br />

11.2.3 INTAKE STRUCTURE<br />

Excavation:- From 22 nd month to 25 th month.<br />

Concreting:- From 26 th month to 37 th .<br />

11.2.4 DESILTING TANK


Excavation:- From 7 th month to 15 th month.<br />

Concreting:- From 13 th month to 36 th month.<br />

11.2.5 MECHANICAL WORKS FOR THE ABOVE FEATURES<br />

From 19 th to 48 th months.<br />

11.2.6 HEAD RACE TUNNEL<br />

Excavation from RD 0 to 3440m and 7000m to 3440m<br />

From 4 th month to 37 th month.<br />

Concreting from RD 0 to 3440m and 7000m to 3440m.<br />

From 38 th month to 46 th month.<br />

Grouting :- From 47 th month to 48 th month.<br />

From RD 700m to 9150m and 11300m to 9150m.<br />

Excavation from 13th month to 33rd month.<br />

Concreting from 34 th month to 39 th month.<br />

Grouting from 40th month to 41 st month.<br />

11.2.7 SURGE SHAFT<br />

Excavation from 13th month to 23rd month.<br />

Concreting:- From 24 th month to 31 st month.<br />

Grouting & Clean up:- From 32 nd month to 36 th month.


11.2.8 PRESSURE SHAFT<br />

Excavation:- From 13 th month to 21 st month.<br />

Concreting& linner:- From 22nd month to 38th months.<br />

11.2.9 POWER HOUSE<br />

Excavation:- From 13 th month to 26th month.<br />

Concreting:- From 27th month to 40th months.<br />

11.2.10 TAIL RACE TUNNEL<br />

Excavation:- From 19 th month to 22nd month.<br />

Concreting:- In 43 rd month.<br />

11.2.11 INSTALLATION, TESTING AND COMMISSIONING<br />

Installation <strong>of</strong> <strong>hydro</strong> units shall be started from the 32 nd month. A period <strong>of</strong><br />

3 months for testing and commissioning <strong>of</strong> each unit has been provided with<br />

first unit proposed to be commissioned in 51 st month and second unit in 53 rd<br />

month <strong>of</strong> construction and 3 rd unit in 54 th month thus completing the<br />

construction <strong>of</strong> the <strong>project</strong> as a whole in 54 month duration.


PARA DESCRIPTION PAGE<br />

12.0 GENERAL XII-1<br />

12.1 BASIS OF THE ESTIMATE XII-1<br />

12.2 DESCRIPTION OF ITEMS XII-2<br />

12.2.1 UNIT-I CIVIL WORKS XII-2 TO XII-4<br />

12.2.2 UNIT-III ELECTRICAL WORKS XII-5<br />

12.2.2.1 P-PRODUCTION XII-5<br />

12.2.2.2 T-TRANSMISSION XII-5<br />

12.3 DETAILED ESTIMATE OF COST XII-5 TO XII-34


12.0 GENERAL<br />

12.1 BASIS OF ESTIMATE<br />

CHAPTER – XII<br />

COST ESTIMATES<br />

The estimate <strong>of</strong> Unit-I Civil Works has been prepared to arrive at the capital<br />

cost <strong>of</strong> the Chhatru Hydel Project. The price level <strong>of</strong> the estimate Oct.,<br />

2003. It is presumed that major civil works will be executed on contract<br />

basis. The cost estimate does not include following items:-<br />

- Escalation after Oct., 2003<br />

- Interest during construction.<br />

Detailed estimate <strong>of</strong> cost for Unit-I civil works is based mainly upon<br />

various designs/drawings finalised for appurtenant structures and the rates<br />

for principal items <strong>of</strong> works as per guide lines furnished by CEA vide letter<br />

dt. 24 th Oct. 2003. A provision <strong>of</strong> 3% has been made for contingencies for<br />

C-works under Unit-I works. Guidelines for preparation <strong>of</strong> <strong>project</strong> estimate<br />

issued by CWC during March, 1997 have also been followed for<br />

formulation <strong>of</strong> the estimate.<br />

12.2 DESCRIPTION OF ITEMS<br />

12.2.2 UNIT-I CIVIL WORKS<br />

Under the heading civil works provision has been made for various<br />

components <strong>of</strong> the <strong>project</strong> as detailed here under;


A-Preliminary<br />

Under this sub-head, provision <strong>of</strong> Rs. 501.25 lac has been made for surveys<br />

and investigations conducted or to be conducted to arrive at the optimum<br />

designs <strong>of</strong> <strong>project</strong> components.<br />

B- Land<br />

This covers the provision for acquisition <strong>of</strong> land for construction <strong>of</strong> the<br />

<strong>project</strong> components, colonies, <strong>of</strong>fices and store complexes and<br />

compensation for trees and standing crops. Provision for forest trees in the<br />

<strong>project</strong> area has also been included. A L.S.provision for Rs. 350.00 lac has<br />

been made under this sub-head in the absence <strong>of</strong> data , which could not be<br />

collected being <strong>project</strong> area under snow cover during winter.<br />

C-Works<br />

This covers the cost <strong>of</strong> civil engineering structures comprising c<strong>of</strong>fer dam<br />

and diversion barrage. The cost on this sub head worksout to Rs.9572.95<br />

Lac.<br />

J <strong>Power</strong> Plant<br />

This covers the cost <strong>of</strong> Intake ,desanding chamber, head race tunnel, surge<br />

shaft, pressure shaft, underground power house complex and tail race<br />

tunnel. The total cost works to be Rs. 20057.42 lac.


K- Buildings<br />

Buildings both residential and non- residential have been grouped separately<br />

under permanent and temporary catagories. Under the permanent catagories,<br />

all those buildings have been included which will be subsequently utilised<br />

for the operation and maintenance <strong>of</strong> <strong>project</strong> whereas, under the temporary<br />

category, credit to the extent <strong>of</strong> 15% has been given to the <strong>project</strong> on<br />

account <strong>of</strong> resale there<strong>of</strong>. The cost has been worked out on basis <strong>of</strong> plinth<br />

area rates as notified by HPPWD.. A provision <strong>of</strong> Rs.1341.94 lac has been<br />

made under this sub-head.<br />

X-Environment & Ecology<br />

A provision <strong>of</strong> Rs.470 lac has been made under this sub-head maintaining<br />

and improving the environmental status <strong>of</strong> the <strong>project</strong> area and fir<br />

afforestation <strong>of</strong> affected area.<br />

II-Establishment<br />

A provision under this head has been made for Rs. 2760.24 lac i.e. 8% <strong>of</strong> I-<br />

Works.<br />

V-Receipts & Recoveries<br />

This provision covers estimated recoveries by way <strong>of</strong> resale or transfer <strong>of</strong><br />

special T&P and temporary buildings. The amount thus works out to Rs.<br />

328.84 lac only.


M-Plantation<br />

This covers the cost <strong>of</strong> plantation and protection <strong>of</strong> plants to be planted<br />

along <strong>project</strong> roads, colonies and in <strong>project</strong> area. Accordingly a provision <strong>of</strong><br />

25.00 lac has been made under this sub-head.<br />

O- Miscellaneous<br />

A provision <strong>of</strong> Rs. 966.77 lac has been made for meeting cost <strong>of</strong> various<br />

items listed therein.<br />

Q-Special T&P<br />

As the major civil works have been proposed to be got done on contract<br />

basis. Machinery required for departmental activities like infrstructural<br />

works, there subsequent repair/ maintenance and supervison works has<br />

mainly been includeed under theisd sub-head. A provision <strong>of</strong> Rs. 496.71 lac<br />

has been made under this sub-head.<br />

R-Communication<br />

A provision <strong>of</strong> Rs. 656.70 lac under this sub-head covers the cost <strong>of</strong> roads.<br />

The road width have been planned to cater to the anticipated traffic<br />

including movement <strong>of</strong> heavy trailors. Cost <strong>of</strong> roads is based on the rates<br />

as notified by State HPPWD .<br />

A provision <strong>of</strong> Rs. 38679.07 Lac.has been made to cover the costs under<br />

this subhead.


12.2.2 UNIT-III ELECTRICAL WORKS<br />

12.2.2.1 P-PRODUCTION<br />

Cost <strong>of</strong> generating plants and equipments is based on current budgetory<br />

prices. Prices <strong>of</strong> auxiliary equipments and services are based on historical<br />

prices.Excise duty has been considered @ 16% <strong>of</strong> the component. CST,<br />

Insurance and transport to site has been taken @ 6% <strong>of</strong> the cost <strong>of</strong><br />

respective component. Erection and commissioning charges have also been<br />

taken @ 10% as per experience gained on similar installations in the state. A<br />

provision <strong>of</strong> Rs. 13612.06 lacs has been made to cover the costs under this<br />

sub-head.<br />

12.2.2.2 T-TRANSMISSION<br />

It is proposed to evacuate the power generated at Chhatru <strong>project</strong> by<br />

LILOing <strong>of</strong> 220 KV D/C line from Khoksar to 400 KV Pooling point at<br />

Tandi which is proposed in this basin. Beyond this point the evacuation will<br />

be through 400 KV D/C net work to Panarsa Poolung in sub station <strong>of</strong><br />

PGCIL. The cost is based on detailed analysis on actual requirement and<br />

amounts to Rs. 844.68 lacs.<br />

12.3 DETAILED ESTIMATE OF COST<br />

Detailed estimate <strong>of</strong> cost as explained in above paras is given in succeeding<br />

paras.


PARA DESCRIPTION PAGE<br />

13.0 GENERAL XIII-1<br />

13.1 CAPITAL COST OF THE PROJECT XIII-1 TO XIII-2<br />

13.2 ECONOMIC JUSTIFICATION XIII-2<br />

13.3 CAPITAL STRUCTURE XIII-3<br />

13.4 REVENUE ANTICIPATION XIII-3<br />

13.5 REPAYMENT PERIOD XIII-3<br />

13.6 COST PER MW XIII-3<br />

13.7 INTEREST DURING CONSTRUCTION XIII-4<br />

13.8 ENERGY AVAILABLE FOR SALE XIII-4<br />

13.9 RATE OF DEPRECIATION XIII-4<br />

13.10 OPERATION AND MAINTENANCE<br />

CHARGES<br />

XIII-4<br />

13.11 CALCULATION OF TARRIF XIII-5<br />

13.12 INDIRECT BENEFIT XIII-6<br />

13.13 MERITS OF THE PROJECT XIII-6<br />

13.14 CONSTRUCTION SCHEDULE XIII-6<br />

ANNEXURE-13.1-(a)<br />

TO 13.1(c)<br />

ABSTRACT OF COST ESTIMATES OF<br />

CIVIL WORKS, P-PRODUCTION & T-<br />

TRANSMISSION<br />

ANNEXURE-13.2 YEARWISE PHASING OF FUNDS XIII-10<br />

ANNEXURE-13.3 CALCULATION OF INTEREST DURING<br />

CONSTRUCTION AT POWER HOUSE<br />

BUS BARS<br />

ANNEXURE-13.4 WEIGHTED AVERAGE DEPRECIATION<br />

ANNEXURE-13.5 LEVELLISED TARRIF OF ENERGY FOR<br />

90% DEPENDABLE YEAR AT POWER<br />

HOUSE BUS BARS.<br />

XIII-7 TO XIII-9<br />

XIII-11<br />

XIII-12<br />

XIII-13TO XIII-<br />

14


13.0 GENERAL<br />

CHAPTER-XIII<br />

ECONOMIC EVALUATION<br />

Chhatru Hydro- <strong>electric</strong> Project has been contemplated as a run <strong>of</strong> the river<br />

development on Chandra River in Lahul & Spiti district <strong>of</strong> Himachal<br />

Pradesh. This <strong>project</strong> is estimated to cost Rs. 531.36 Cr. at price level <strong>of</strong><br />

Oct,,2003. The cost at power bus bar worksout to Rs. 522.91 Cr.Abstract<br />

<strong>of</strong> cost estimate <strong>of</strong> Civil works, P-Production and T-Transmission have been<br />

given as per Annexure13.1-(a) to13.1-(c). Year wise phasing <strong>of</strong> expenditure<br />

for capital required on this <strong>project</strong> is given as per Annexure-13.2. Interest<br />

during construction has been considered as per Annexure- 13.3.


Depreciation on Civil and Electrical works has been worked out as 3.00% as<br />

per Annexure-13.4.The levelised tariff <strong>of</strong> energy generated at power house<br />

bus bars has been worked out as Rs. 2.28 per unit during 90% dependable<br />

year as per Annexure-13.5. The cost <strong>of</strong> energy in the Ist year <strong>of</strong> operation<br />

worksout to Rs. 2.89 per unit.<br />

13.1 CAPITAL COST OF THE PROJECT<br />

Abstract <strong>of</strong> the capital cost <strong>of</strong> the <strong>project</strong>, to the price level <strong>of</strong> Oct., 2003 is<br />

as under: -<br />

S.No. Description Amount<br />

(Rs. in Cr.)<br />

1. Unit-I Civil works 386.79<br />

2. P-Production (Electrical works) 136.12<br />

Total Generation Cost 522.91<br />

3. Transmission 8.45<br />

Grand total 531.36<br />

13.2 ECONOMIC JUSTIFICATION<br />

PGCIL will construct a Parbati pooling point at down stream <strong>of</strong> Parbati<br />

stage-III HEP at Pnarsa and which will cater the power <strong>of</strong> Chhatru HEP<br />

through 220 KV D/C to Khoksar and then to 400 KV Tandi pooling point..<br />

As laid down to CEA and CERC Guidelines, economic justification <strong>of</strong> a


hydel <strong>project</strong> is to be done by comparing cost <strong>of</strong> alternative sources<br />

<strong>of</strong> energy in that region. The levelized tariff <strong>of</strong> this <strong>project</strong> in 90%<br />

dependable year works out as Rs. 2.28/ unit at power use bus bars as per<br />

Annexure-13.5 ).This <strong>project</strong> will provide power at cheaper rates in<br />

comparison to thermal power rate which , at present is more than Rs.3.75 /<br />

unit. Additionally this <strong>project</strong> will provide pollution free power for years<br />

together at much cheaper rates considering the escalation in coal prices for<br />

Thermal <strong>Power</strong>.<br />

13.3 CAPITAL STRUCTURE<br />

Capital structure has been assumed as 70% debt from Financial Institution<br />

and 30% equity from Govt.<br />

13.4 REVENUE ANTICIPATION<br />

<strong>Power</strong> tariff for supply <strong>of</strong> power at powerhouse bus bars has been assumed<br />

as Rs. 2.75 per unit. Revenue has been assessed accordingly for 90%<br />

dependable year as Rs. 125.32 cr.<br />

13.5 REPAYMENT PERIOD<br />

.<br />

Normally, the leading financial institutions in India prescribe a repayment<br />

period <strong>of</strong> 15 years including 3 to 4 years moratorium period. A period <strong>of</strong> 12<br />

years has therefore been taken into account, as repayment period in fixation<br />

to tariff.


13.6 COST PER MW<br />

The estimated cost <strong>of</strong> the <strong>project</strong> at Oct 2003 price level is Rs. 531.36 Cr.<br />

including transmission and Rs. 522.91 Cr. at power bus bar for an installed<br />

capacity <strong>of</strong> 108W. This gives a capital cost <strong>of</strong> Rs. 4.92 Cr.per MW <strong>of</strong><br />

installed capacity including cost <strong>of</strong> transmission and Rs. 4.84 Cr. per MW<br />

at generation. At present price level, the cost <strong>of</strong> medium <strong>hydro</strong>-<strong>electric</strong><br />

<strong>project</strong> at Rs. 6.00 crore per MW is considered to be reasonable. From this<br />

criterion, the cost per MW for Gharopa Hydel Project is reasonable making<br />

the <strong>project</strong> suitable for exploitation.<br />

13.7 INTEREST DURING CONSTRUCTION<br />

The detail <strong>of</strong> expenditure during the construction period and the calculation<br />

<strong>of</strong> interest during construction have been shown in Annexure-13.3. It is<br />

seen that IDC @ 10.00 % on loan works out to Rs. 62.24. at power house<br />

bus bars.<br />

13.8 ENERGY AVAILABLE FOR SALE<br />

As per power studies <strong>of</strong> the <strong>project</strong>, the total energy generation in 90%<br />

dependable year has been arrived at 455.72 MUs. As per Govt. <strong>of</strong> India<br />

Guide Lines, an auxiliary consumption @ 0.7% and transformation losses<br />

@ 0.5% have been considered at power house bus bars .<br />

13.9 RATE OF DEPRECIATION<br />

As per the revised guide lines circulated by Govt. <strong>of</strong> India, <strong>Ministry</strong> <strong>of</strong><br />

<strong>Power</strong>, Vide notification dated 29 th March, 1994, the weighted rate <strong>of</strong><br />

depreciation has been worked out on the basis <strong>of</strong> straight line formula. The


ate <strong>of</strong> depreciation works out to 3.00% <strong>of</strong> the <strong>project</strong> cost as per<br />

Annexure-13.5.<br />

13.10 OPERATION AND MAINTENANCE CHARGES<br />

As per the guide lines <strong>of</strong> <strong>Ministry</strong> <strong>of</strong> <strong>Power</strong>, Govt. <strong>of</strong> India, the Operation<br />

and Maintenance charges inclusive <strong>of</strong> insurance have been taken as 1.50 %<br />

<strong>of</strong> the capital cost.<br />

11 CALCULATION OF TARIFF<br />

Calculation <strong>of</strong> tariff for primary energy during 35 years <strong>of</strong> operation for<br />

90% dependable year has been worked out as per GOI notification shown in<br />

Annexure-13.5 comprising the following.<br />

i) Interest on loan from PFC @ 10.00 % p.a.<br />

ii) Interest on working capital @ 9.75 % required for 2 months <strong>of</strong><br />

average billing for sale <strong>of</strong> <strong>electric</strong>ity and operation and maintenance<br />

expenses for one month.<br />

iii) O&M charges including insurance charges @ 1.5% p.a.<br />

iv) Income tax @ 35% and surcharge @ 10% on income tax has been<br />

considered.<br />

v) Discounting rate @ 12% for tariff calculation .<br />

vi) Free power for home state @ 12%.


At power house bus bar, it will be seen that sale rate <strong>of</strong> power shall be Rs.<br />

2.89 per unit during Ist year <strong>of</strong> operation and Rs. 1.37 per unit during 13 th<br />

year i.e after repayment <strong>of</strong> loan. The levelised tariff rate works out to Rs.<br />

2.28 per unit at power house bus bars.<br />

13.12 INDIRECT BENEFIT<br />

Besides providing pollution free power at a cheap rate to the Northern Grid;<br />

discussed in preceding paras, this <strong>project</strong>, located in Lahul & Spiti district <strong>of</strong><br />

HP will help in the overall development <strong>of</strong> the people <strong>of</strong> the area..<br />

Employment to skilled/non-skilled labour <strong>of</strong> the area, industrial and<br />

economic development are additional benefits from this <strong>project</strong>. Keeping<br />

these points in view, this <strong>project</strong> merits consideration for an implementation.<br />

13.13 MERITS OF THE PROJECT<br />

Gharopa HEP (108 MW) is a down stream development <strong>of</strong> proposed<br />

Khoksar (90 MW). Following are the strengths and weaknesses <strong>of</strong> the<br />

<strong>project</strong>.<br />

i) Project sites are located on the right bank <strong>of</strong> existing motorable<br />

road.<br />

ii) No resettlement <strong>of</strong> people required for construction <strong>of</strong> <strong>project</strong>.<br />

iii) Construction material is locally available.<br />

iv) Almost all the major sites <strong>of</strong> the <strong>project</strong> viz. Diversion, inlet portal<br />

and adit portal <strong>of</strong> HRT and power house are connected with NH-21.<br />

v) The levellised tariff works out to be Rs. 2.28 per unit at power<br />

house bus bar which is on lower side.


13.14 CONSTRUCTION SCHEDULE<br />

The construction <strong>of</strong> the <strong>project</strong> has been proposed to be completed in four<br />

and half years <strong>of</strong> period. The construction schedule has been presented in<br />

drawing No. Gharopa-FR-8 (attached).


CONSTRUCTION ORGANISATION<br />

PRE CONSTRUCTION STAGE<br />

FOR FIRST ONE YEAR<br />

S.E. (C/M ) 1/2<br />

E.E.-I (C) E.E.-II (C) E.E.-III (M) E.E.-IV (E)<br />

Land Acquisition Detialed surveys, R/M <strong>of</strong> w / shop, Arrangement <strong>of</strong><br />

c/o residential & non collection <strong>of</strong> G&D vehicles & procure - construction power<br />

residential buildings data, c/o adits & ment <strong>of</strong> stores & electrification <strong>of</strong><br />

and <strong>project</strong> roads. W/shop facilities. Equipments. Resd. Buildings.<br />

CONSTRUCTION STAGE<br />

Chief Enginer (C) Chief Enginer (E)<br />

Construction 1/2 Construction 1/3<br />

Four year Four year<br />

S.E.-Admn.& Works. S.E.-Admn&Works.<br />

(C/M) ( E)<br />

E.E.Admn. E.E.Works E.E.Admn. E.E.Works<br />

(C/M) (C/M) (E) (E)<br />

S.E.-Civil. -I S.E.-II (M ) 1/2 S.E.-P/H( E) S.E.T(E)1/2<br />

A.O. C/M A.O. C/M A.O. C/M A.O. C/M<br />

E.E. I (C) E.E.I I (C) E.E.III (C) E.E.IV (C) E.E.I (M) E.E.II (M) E.E. I (E) E.E.I I (E) E.E.III (E) E.E.IV (E) E.E.I (E) E.E.II (E)<br />

Barrage Rana aqueduct,HRT Surge shaft <strong>Power</strong> house & Tail Work shop, Pen stock fabrication, <strong>Power</strong> house , Sub station & Testing & Planning &<br />

Intake & Adits. & pressure Race works. Transport & fabrication & errection Works. Switch yard. commissioning Monitoring. Transmation & P L C C<br />

& Control survey, shaft Colony at Snail/ Stores. <strong>of</strong> Gates, hoist & Const.<br />

D/Tank colony & road maint.<br />

G/D data collection<br />

& Silt lab.<br />

civil works Anti Roads trash racks etc.<br />

HIMACHAL PRADESH STATE ELECTRICITY BOARD<br />

DIRECTOR PLANNING CIRCLE NO.I<br />

SAWRA KUDDU 110 MW<br />

CONSTRUCTION ORGANISATION CHART<br />

DSGN. CHKD. RECM.<br />

DRWN. SUBM. APPED.<br />

SUNDERNAGAR , APRIL-2003 DRG.NO.SAWRA KUDDU-PR-19


DESIGN ORGANISATION<br />

PRE CONSTRUCTION STAGE<br />

FOR FIRST HALF YEAR<br />

Director-D(C)1/4 Director-D(E)1/4<br />

E.E.-I(C) E.E.-I(E)<br />

Design <strong>of</strong> bridges &<br />

Roads, Preparation &<br />

processing <strong>of</strong> tenders<br />

etc., infrastructure<br />

facilities like adits,<br />

w/shop & stores<br />

Const. power,<br />

preliminary enquiry<br />

for generating<br />

equipment &<br />

turbines etc.<br />

Chief Engineer (C/M) Chief Engineer(E)<br />

Construction 1/3 Construction 1/3<br />

S.E. Admn & Four year Two year<br />

Works(C/M)<br />

Director Design C/M Director Design (E) S.E.Admn & Works<br />

E.E.Works E.E.Works Thrre year (E)<br />

(C/M) (C/M)<br />

E.E.I(C/M) E.E.II(C/M) E.E.III(C/M) E.E.IV(C/M) E.E.I(E) E.E.II(E) E.E.III(E) E.E.IV(E)<br />

Design <strong>of</strong><br />

infrastructure,<br />

job facilities,<br />

preparation &<br />

prosesing <strong>of</strong><br />

tenders,<br />

estimation,<br />

scheduling<br />

const.<br />

material<br />

Monitoring cost<br />

control & PERT/CPM<br />

planning, mech.<br />

desining <strong>of</strong> gates,<br />

hoisting, trash rack &<br />

penstock<br />

instrumentation & soil<br />

testing<br />

Specification<br />

design &<br />

const. design<br />

<strong>of</strong> barrage,<br />

intake<br />

structure,<br />

D/tanks.<br />

Construction Stage<br />

Specification,<br />

design & const.<br />

design <strong>of</strong> HRT,<br />

S/shaft, <strong>Power</strong><br />

House & Tail<br />

race<br />

Specification,<br />

design &<br />

tenders <strong>of</strong><br />

Generation<br />

equipments.<br />

Specification,<br />

design & tenders<br />

<strong>of</strong> <strong>Power</strong> house<br />

auxiliaries.<br />

Design &<br />

procurement<br />

<strong>of</strong><br />

Transmission<br />

lines &<br />

equipments<br />

DSGN. CHKD. RECM.<br />

DRWN. SUBM. APP.<br />

E.E.Admn. E.E.Works<br />

(E) (E)<br />

Specification,<br />

design & const.<br />

design <strong>of</strong> substation<br />

& switch<br />

yard<br />

HIMACHAL PRADESH STATE ELECTRICITY BOARD<br />

DIRECTOR PLANNING CIRCLE NO.I<br />

SAWRA KUDDU 110 MW<br />

DESIGN ORGANISATION CHART<br />

SUNDERNAGAR , APRIL-2003 DRG.NO.SAWRA KUDDU--PR-18


S No. Description Quantity Unit 1st Year 2nd Year 3rd Year 4th Year 5th Half year<br />

A PRE-CONSTRUCTION<br />

1 INFRASTRUCTURE<br />

i) a) Preliminary Job<br />

ii) b) Land Acquisition Job<br />

iii) c) Procurement Job<br />

2 AGGREGATE PROCESSING Job<br />

B WORK SCHEDULE<br />

1. Diversion Barrage<br />

i) C<strong>of</strong>fer dam Ist Stage Job<br />

ii) Excavation <strong>of</strong> barrage 1st stage 325300 Cum<br />

iii) Concreting <strong>of</strong> barrage 1st stage 54166 Cum<br />

iv) C<strong>of</strong>fer dam 2nd stage Job<br />

v) Excavation 2nd stage 325300 Cum<br />

vi) Concreting <strong>of</strong> 2nd stage 54166 Cum<br />

2. Iuntake structure<br />

i) Excavation 7890 Cum<br />

ii) Concreting 1830 Cum<br />

3. Desilting Tank<br />

i) Excavation 239450 Cum<br />

ii) Concreting 51900 Cum<br />

4. Mechanical works for the above features<br />

5. HRT<br />

a) Excavation from RD 0 to 3500 104760 Cum<br />

i) Concreting 18170 Cum<br />

ii) Grouting & clean up Job<br />

b) Excavation from RD 6500 to 3500 89240 Cum<br />

i) Concreting 15480 Cum<br />

ii) Grouting & clean up Job<br />

6 Surge shaft<br />

i) Excavation 15900 Cum<br />

ii) Concreting 3977 Cum<br />

iii) Grouting & cleanup Job<br />

7. Pressure Shaft<br />

i) Excavation 29900 Cum<br />

ii) Concreting & steel lining 3720 Cum<br />

8. <strong>Power</strong> house<br />

i) Excavation 61000 Cum<br />

ii) Concreting<br />

a) Sub-structure 9000 Cum<br />

b) Super structure 8000 Cum<br />

9. Auxilliary surge shaft<br />

and Tail Race Tunnel<br />

i) Excavation 45900 Cum<br />

ii) Concreitng 5100 Cum<br />

10. Installation, testing<br />

Unit No.I Job<br />

Unit No.II Job<br />

Unit No.III Job<br />

Months 3 6 9 12 15 18 21 24 27 30 33 36 39 42 45 48 51 54


S. NO. DESCRIPTION UNIT RATE<br />

A EXCAVATION<br />

1 Common excavation Cum 125.00<br />

2 Excavation in hard rock Cum 300.00<br />

3 Excavation in rock in tunnel Cum 1000.00<br />

4 Surge shaft excavation<br />

Without raise climber Cum 1200.00<br />

B<br />

C<br />

D<br />

E<br />

F<br />

APPENDIX-A<br />

RATES FOR MAJOR ITEMS OF CIVIL WORKS<br />

With raise climber Cum 1500.00<br />

Rock support<br />

Rock bolting (including drilling)<br />

25 mm RM 400.00<br />

32 mm RM 525.00<br />

36mm RM 625.00<br />

Shotcret rate without wiremesh Cum 4000.00<br />

Wiremesh Sq M 200<br />

Steel supprt<br />

Earth dam/Rockfill dam<br />

MT 42000.00<br />

1 Rate per cum earth fill in Dam (for lead 1 km.<br />

2 Rate per cum rock fill in Dam (for lead 1 km.)<br />

Cum 142.00<br />

From excavated material Cum 156.00<br />

From quarry Cum 318.00<br />

3 Rate per cum <strong>of</strong> impervious core in Dam( lead 1 km.) Cum 154.00<br />

4 Inverted filter (for lead 1 km) Cum 701.00<br />

5 Stone pitching (for lead 1 km Cum 581.00<br />

6 Incremental rate for each additional lead <strong>of</strong> 1 km. or par Cum 20.00<br />

Concreteing (including form work)<br />

1 Concrete lead 10 km (For lead <strong>of</strong> 10 Km. for aggegate quarry)<br />

M 25 Cum 3610.00<br />

M 20 Cum 3390.00<br />

M 15 Cum 2930.00<br />

M 10 Cum 2560.00<br />

2 Incremental rate for each additional lead <strong>of</strong> 5 km. or par Cum 100.00<br />

3 Concrete Cut-<strong>of</strong>f wall Sq m 20000.00<br />

4 Precast lagging including cost <strong>of</strong> reinforcement Cum 7000.00<br />

5 Concrete linging in DT & HRT ( M 20)<br />

Reinforcement Steel and Steel and Structural Steel<br />

Cum 4000.00<br />

1 Reforcement MT 27000.00<br />

2 Penstock liner MT 70000.00<br />

Hydro-Mechanical Work<br />

1 Radial gate MT 100000.00<br />

2 Sluicegate MT 100000.00<br />

3 Stoplog gate MT 60000.00<br />

4 Trashrack MT 50000.00<br />

5 Embedded parts MT 50000.00<br />

6 Hoist (Based on lifting capacity) MT 100000.00


APPENDIX-B<br />

RIVER DIVERSION ARRANGEMENT<br />

COFFER DAM (U/S & U/S)<br />

S. NO.<br />

1.0 Surface Excavation<br />

DESCRIPTION UNIT QTY. RATE (Rs.)<br />

Amt.in<br />

Lac<br />

1.1 Common excavation Cum 25000 125.00 31.25<br />

2.0 Embankment Construction<br />

2.1 Earth/rock rill Cum 50000 156.00 78.00<br />

2.1 Impervious core Cum NIL<br />

2.3 Filter Cum NIL<br />

3.0 Concrete<br />

3.1 M 10 Cum 7600 2560.00 194.56<br />

3.2 M 15 Cum NIL<br />

3.3 Concrete cut-<strong>of</strong>f wall if required Cum NIL<br />

Sub-Total (A) <strong>of</strong> 1 to 3<br />

4.0 Miscellaeneous<br />

4.1<br />

Various Miscellaneous works like wiremesh/steel fibre<br />

reinforcement , drilling & grouting, etc. (0.0 to 0.50% <strong>of</strong> Sub-<br />

Total (A) dpending upon the iste conditions & type <strong>of</strong><br />

303.81<br />

structure)<br />

0.50% 303.81 1.52<br />

Sub-Total (B) <strong>of</strong> 1 to 4 305.33<br />

5.0 Dewatering (3% <strong>of</strong> Sub-Total (B)<br />

6.0 Contingencies (3% <strong>of</strong> Sub-Total (B) except on<br />

3% 305.33 9.16<br />

L.S. items) 3% 305.33 9.16<br />

7.0 Work Charges Establishment (2% <strong>of</strong> Sub-Total(B)<br />

except on L.S. items)<br />

2% 305.33 6.11<br />

Total <strong>of</strong> 1 to 7 329.76


BARRAGE, CELLULAR WALL, RETAINING WALL & FISH LADDER<br />

S. NO. DESCRIPTION UNIT QTY. RATE (Rs.)<br />

Amt.in<br />

Lac<br />

1.0 Surface Excavation<br />

1.1 Common excavation Cum 325300 125.00 406.63<br />

1.2 Rock Excavation Cum 325300 300.00 975.90<br />

2.0 Support System<br />

2.1 Rock bolts M 300.00 525.00 1.58<br />

2.2 Shotcreting Cum 65.00 4000.00 2.60<br />

3.0 Fill Works<br />

3.1 Compacted Earthfill Cum NIL<br />

3.2 Compacted clay fill Cum 3000 156.00 4.68<br />

4.0 Concrete including form work<br />

4.1 Precast Concrete Block M-20 Cum 3500 7000.00 245.00<br />

4.2 M-15 Cum 26910 2930.00 788.46<br />

4.3 M-20 in Upstream Floor, road bridge Cum 7790 3390.00 264.08<br />

4.4 M-25 downstream floor and spillway glacis <strong>of</strong> barrage, piers<br />

& breast walls, trunion beam, fish ladder, retaining wall if<br />

required. Cum 70133 3610.00 2531.80<br />

4.5 Concrete lining in Channel Sides M-20 Cum NIL<br />

5.0 Steel<br />

5.1 (i) Reinforcement Steel Ton 7800 27000.00 2106.00<br />

5.2 (ii) Structrul Steel Ton 1200 70000.00 840.00<br />

6.0 Stone Pitching<br />

Cum. 4000 581.00 23.24<br />

Sub-Total (A) <strong>of</strong> 1 to 6 8189.97<br />

7.0 Miscellaeneous<br />

7.1<br />

Various Miscellaneous works like Site Clearance, drilling &<br />

grouting, PVC pipes & waterstops, Metal works, Launching<br />

Apron, Crate Work, Filter Below C.C. Block, Masonary<br />

Works, Archetectural Works (4-5% <strong>of</strong> Sub-Total (A)<br />

depdnding upon the site conditions & type <strong>of</strong> structure. 4-5% 0.05 8189.97 368.55<br />

Sub-Total (B) <strong>of</strong> 1 to to 7 8558.51<br />

8.0 Instrumentation ( 1% <strong>of</strong> Sub-Total (B) 1% 8558.51 85.59<br />

9.0 Dewatering (2% <strong>of</strong> Sub-Total (B) 2% 8558.51 171.17<br />

10.0 Contingencies (3% <strong>of</strong> Sub-Total (B) except on 3% 8558.51 256.76<br />

L.S. items)<br />

11.0 Work Charges Establishment (2% <strong>of</strong> Sub-Total(B) 2% 8558.51 171.17<br />

except on L.S. items)<br />

Sub-Total (B) <strong>of</strong> 1 to to 11 9243.19


INTAKE STRUCTURE<br />

APPENDIX-C<br />

S. NO. DESCRIPTION UNIT QTY.<br />

RATE<br />

(Rs.) Amt.in Lac<br />

1.0 Surface Excavation<br />

1.1 Common excavation Cum 1050 125.00 1.31<br />

1.2 Rock excavatin Cum 6840 300.00 20.52<br />

2.0 Underground excavation Cum NIL<br />

3.0 Support System<br />

3.1 Rockbolts M NIL<br />

3.2 Steel Rib Supports Ton NIL<br />

3.3 Shotrreting Cum NIL<br />

3.4 Concrete lagging if required Cum. NIL<br />

4.0 Concrete<br />

4.1 M-10 Cum 100 2560.00 2.56<br />

4.2 M 15 Cum NIL<br />

4.3 M 20 Cum NIL<br />

4.4 M 25 Cum 1730 3610.00 62.45<br />

5.0 steel<br />

5.1 (i) Reinforcing Steel Ton 173 27000 46.71<br />

5.2 (Ii) Structural Steel Ton 100 27000 27.00<br />

Sub-Total (A) <strong>of</strong> 1 to 5 160.56<br />

6.0 Miscellaeneous and Ancillary Works<br />

6.1 Various Miscellaneous works like<br />

wiremesh/steel fibre reinforcement , drilling &<br />

grouting, PVC pipes for drainge, slope<br />

protection works etc. (1-2% <strong>of</strong> Sub-Total (A)<br />

dpending upon the iste conditions & type <strong>of</strong><br />

structure) 1 to 2% 1.50% 160.56 2.41<br />

Cum<br />

Sub-Total (B) <strong>of</strong> 1 to 6 162.96<br />

7.0 Instrumentation ( 1% <strong>of</strong> Sub -Total )B) 1% 162.96 1.63<br />

8.0 Dewatering (1% <strong>of</strong> Sub-Total (B) 1% 162.96 1.63<br />

9.0 Contingencies (3% <strong>of</strong> Sub-Total (B) except<br />

on L.S. items) 3% 162.96 4.89<br />

10.0 Work Charges Establishment (2% <strong>of</strong> Sub-<br />

Total(B) except on L.S. items) 2% 162.96 3.26<br />

Total <strong>of</strong> 1 to 10 337.34


DESANDING CHAMBER<br />

S. NO. DESCRIPTION UNIT QTY. RATE (Rs Amt.in Lac<br />

1.0 Surface Excavation<br />

1.1 Common excavation Cum NIL<br />

1.2 Rock excavatin Cum NIL<br />

2.0 Underground excavation Cum 239450 1000.00 2394.50<br />

3.0 Support System<br />

3.1 Rockbolts M 69500 625 434.38<br />

3.2 Steel Rib Supports Ton 605 42000 254.10<br />

3.3 Shotrreting Cum 6720 4000 268.80<br />

3.4 Concrete lagging if required Cum. NIL<br />

4.0 Concrete<br />

4.2 M 15 Cum 17100 2930.00 501.03<br />

4.3 M 20 Cum 34800 4000.00 1392.00<br />

4.4 M 25 Cum NIL<br />

5.0 Reinforcing Steel Ton 350 27000 94.50<br />

Sub-Total (A) <strong>of</strong> 1 to 5 5339.31<br />

6.0 Miscellaeneous and Ancillary Works<br />

6.1<br />

Various Miscellaneous works like<br />

wiremesh/steel fibre reinforcement , drilling &<br />

grouting etc. (3-4% <strong>of</strong> Sub-Total (A) dpending<br />

upon the iste conditions & type <strong>of</strong> structure) 3 to 4% 3.50% 5339.31 186.88<br />

Sub-Total (B) <strong>of</strong> 1 to 6 5526.18<br />

7.0 Instrumentation ( 1% <strong>of</strong> Sub -Total )B) 1% 5526.18 55.26<br />

8.0 Dewatering (2% <strong>of</strong> Sub-Total (B) 2% 5526.18 110.52<br />

9.0 Contingencies (3% <strong>of</strong> Sub-Total (B) except<br />

on L.S. items) 3% 5526.18 165.79<br />

10.0 Work Charged Establishment (2% <strong>of</strong> Sub-<br />

Total(B) except on L.S. items) 2% 5526.18 110.52<br />

Total <strong>of</strong> 1 to 10 5968.28


HEAD RACE & TAIL RACETUNNEL<br />

S. NO. DESCRIPTION UNIT QTY.<br />

RATE<br />

(Rs.) Amt.in Lac<br />

1.0 Surface Excavation<br />

1.1 Common excavation Cum 100 125.00 0.13<br />

1.2 Rock excavatin Cum 400 300.00 1.20<br />

2.0 Underground excavation Cum 239900 1000.00 2399.00<br />

3.0 Support System<br />

3.1 Rockbolts M 92700 625 579.38<br />

3.2 Steel Rib Supports Ton 1342 42000 563.64<br />

3.3 Shotrreting Cum 10800 4000 432.00<br />

3.4 Concrete lagging if required Cum. NIL<br />

4.0 Concrete<br />

4.2 M 15 Cum 22400 2930.00 656.32<br />

4.3 M 20 Cum 16350 4000.00 654.00<br />

4.4 M 25 Cum NIL<br />

5.0 Reinforcing Steel Ton 795 27000 214.65<br />

Sub-Total (A) <strong>of</strong> 1 to 5 5500.31<br />

6.0 Miscellaeneous and Ancillary Works<br />

6.1 Various Miscellaneous works like<br />

wiremesh/steel fibre reinforcement , drilling &<br />

grouting, PVC pipes for drainge etc. (7-8% <strong>of</strong><br />

Sub-Total (A) dpending upon the iste<br />

conditions & type <strong>of</strong> structure) 7 to 8% 8% 5500.31 440.02<br />

Sub-Total (B) <strong>of</strong> 1 to 6 5940.33<br />

7.0 Instrumentation ( 1% <strong>of</strong> Sub -Total )B) 1% 5940.33 59.40<br />

8.0 Dewatering (2% <strong>of</strong> Sub-Total (B) 2% 5940.33 118.81<br />

9.0 Contingencies (3% <strong>of</strong> Sub-Total (B) except<br />

on L.S. items) 3% 5940.33 178.21<br />

10.0 Work Charges Establishment (2% <strong>of</strong> Sub-<br />

Total(B) except on L.S. items) 2% 5940.33 118.81<br />

Total <strong>of</strong> 1 to 10 6415.56


SURGE SHAFT<br />

S. NO. DESCRIPTION UNIT QTY.<br />

1.0 Surface Excavation<br />

1.1 Common excavation Cum NIL<br />

1.2 Rock excavatin Cum NIL<br />

RATE<br />

(Rs.) Amt.in Lac<br />

2.0 Underground excavation<br />

2.1 Surge Shaft excavation Cum 15900 1200 190.8<br />

2.2 Surge shaft excavation with raise borer Cum NIL<br />

2.3 Concrete lagging if required Cum NIL<br />

3.0 Support System<br />

3.1 Rockbolts M 9100 525 47.775<br />

3.2 Steel Rib Supports Ton 162 42000 68.04<br />

3.3 Shotcreting Cum 500 4000 20<br />

4.0 Concrete<br />

4.1 M 20 Cum 3840 3390 138.62<br />

4.2 M 25 Cum 137 3610 4.6443<br />

5.0 Steel Works<br />

5.1 Reinforcing Steel Ton 263 27000 71.01<br />

5.2 Steel liner Ton 92 70000 64.4<br />

Sub-Total (A) <strong>of</strong> 1 to 5 605.29<br />

6.0 Miscellaeneous<br />

6.1 Various Miscellaneous works like site<br />

clearance , drilling & grouting,wire mesh<br />

reinforcement, Airpipess, Lift arrangement,<br />

other steel works etc. (1-2% <strong>of</strong> Sub-Total (A)<br />

dpending upon the iste conditions & type <strong>of</strong><br />

structure) 1 to 2% 1.50% 605.29 9.08<br />

Sub-Total (B) <strong>of</strong> 1 to 6 614.37<br />

7.0 Instrumentation ( 1% <strong>of</strong> Sub -Total )B) 1% 614.37 6.14<br />

8.0 Dewatering (2% <strong>of</strong> Sub-Total (B) 2% 614.37 12.29<br />

9.0 Contingencies (3% <strong>of</strong> Sub-Total (B) except<br />

on L.S. items) 3% 614.37 18.43<br />

10.0 Work Charges Establishment (2% <strong>of</strong> Sub-<br />

Total(B) except on L.S. items) 2% 614.37 12.29<br />

Total <strong>of</strong> 1 to 10 663.52<br />

Add cost provision for auxilliary s/shaft @<br />

30% <strong>of</strong> cost <strong>of</strong> main surge shaft 30% 663.52 199.057<br />

G Total 862.58


PRESSURE SHAFT<br />

S. NO. DESCRIPTION UNIT QTY.<br />

RATE<br />

(Rs.) Amt.in Lac<br />

1.0 Underground excavation Cum 29900 1000.00 299.00<br />

2.0 Support System<br />

2.1 Rock bolts M 6200 525.00 32.55<br />

2.2 Steel ribs Support Ton NIL<br />

2.3 Shotcreting Cum 7970 4000.00 318.80<br />

3.0 Concrete<br />

3.1 M 15 backfill concrete Cum 3720 2930.00 109.00<br />

4.0 Penstock steel liners Ton 1460 70000 1022.00<br />

Sub-Total A) <strong>of</strong> 1 to 4 2643.93<br />

5.0 Miscellaeneous and Ancillary Works<br />

5.1 Various Miscellaneous works like<br />

wiremesh/steel fibre reinforcement , drilling &<br />

grouting, PVC pipes for drainge, slope<br />

protection works etc. (2-3% <strong>of</strong> Sub-Total (A)<br />

dpending upon the iste conditions & type <strong>of</strong><br />

structure) 2- 3% 2.50% 2643.93 66.10<br />

Sub-Total (B) <strong>of</strong> 1 to 5 2710.02<br />

6.0 Instrumentation ( 1% <strong>of</strong> Sub -Total )B) 1% 2710.02 27.10<br />

7.0 Dewatering (1% <strong>of</strong> Sub-Total (B) 1% 2710.02 27.10<br />

8.0 Contingencies (3% <strong>of</strong> Sub-Total (B) except<br />

on L.S. items) 3% 2710.02 81.30<br />

9.0 Work Charges Establishment (2% <strong>of</strong> Sub-<br />

Total(B) except on L.S. items) 2% 2710.02 54.20<br />

Total <strong>of</strong> 1 to 9 2899.73


POWER HOUSE COMPLEX<br />

S. NO. DESCRIPTION UNIT QTY.<br />

RATE<br />

(Rs.) Amt.in Lac<br />

1.0 Surface Excavation<br />

1.1 Common excavation Cum<br />

1.2 Rock excavation Cum 1000 300.00 3.00<br />

2.0 Underground excavation if underground<br />

<strong>Power</strong> House<br />

2.1 Excavation <strong>of</strong> P/H cavern, transformer cum<br />

MIV cavern and draft tube gate Cum 60000 1000.00 600.00<br />

3.0 Support System<br />

3.1 Rockbolts M 30000 625 187.50<br />

3.2 Steel Rib Supports Ton 300 42000 126.00<br />

3.3 Shotrreting Cum 1300 4000 52.00<br />

3.4 Concrete lagging if required Cum<br />

4.0 Concrete<br />

4.1 M 15 Cum NIL<br />

4.2 M 20 Cum 17000 4000 680.00<br />

4.3 M 25 Cum. NIL<br />

5.0 Reinforcing Steel Ton 1200 27000 324.00<br />

6.0 Structural Steel for ro<strong>of</strong> trusses etc. Ton NIL<br />

Sub-Total A) <strong>of</strong> 1 to 6 1972.50<br />

7.0 Miscellaeneous and Ancillary Works<br />

7.1 Various Miscellaneous works like site<br />

clearance,wiremesh/steel fibre reinforcement<br />

, drilling & grouting, flooring, water pro<strong>of</strong>ing<br />

system, swellex anchor, doors & windows,<br />

painting , lift arrangement, architectural<br />

works, other metal works etc. (4-5% <strong>of</strong> Sub-<br />

Total (A) dpending upon the iste conditions &<br />

type <strong>of</strong> structure)<br />

4 to 5 % 5% 1972.50 98.63<br />

Sub-Total (B) <strong>of</strong> 1 to 7 2071.13<br />

8.0 Instrumentation ( 1% <strong>of</strong> Sub -Total )B) 1% 2071.13 20.71<br />

9.0 Dewatering (2% <strong>of</strong> Sub-Total (B) 2% 2071.13 41.42<br />

10.0 Contingencies (3% <strong>of</strong> Sub-Total (B) except<br />

on L.S. items) 3% 2071.13 62.13<br />

11.0 Work Charges Establishment (2% <strong>of</strong> Sub-<br />

Total(B) except on L.S. items) 2% 2071.13 41.42<br />

Total <strong>of</strong> 1 to 11 2236.82


SWITCHYARD<br />

S. NO. DESCRIPTION UNIT QTY.<br />

RATE<br />

(Rs.) Amt.in Lac<br />

1.0 Under ground Excavation<br />

1.1 Common excavation Cum<br />

1.2 Rock excavation Cum 11696 1000.00 116.96<br />

2.0 Supports System<br />

2.1 Rockbolts M 1200 525 6.30<br />

2.2 Steel ribs suppots (if required) Ton 70 42000 29.40<br />

2.3 Shotcreting Cum<br />

3.0 Earth work in filling if required<br />

4.0 Concrete<br />

4.1 M 15 Cum 1400 2930.00 41.02<br />

4.2 M 20 Cum 100 3390.00 3.39<br />

4.3 M 25 Cum. NIL<br />

5.0 Reinforcing Steel Ton 43 27000 11.61<br />

6.0 Stone/Brick Masonary Cum NIL<br />

Sub-Total (A) <strong>of</strong> 1 to 6 208.68<br />

7.0 Miscellaeneous<br />

7.1 Various Miscellaneous works like Site<br />

clearence, PVC pippes,Control block building<br />

work like flooring,doors,windowes etc.<br />

including wate supply and sewerage, Boulder<br />

pitching,Metalworks etc. (4-5 % <strong>of</strong> Sub<br />

Total(A) depending on thte site conditions &<br />

type pf structure) 4 to 5% 4.50% 208.68 9.39<br />

Sub-Total (B) <strong>of</strong> 1 to 7 218.07<br />

8.0 Dewatering (2% <strong>of</strong> Sub-Total (B) 2% 218.07 4.36<br />

9.0 Contingencies (3% <strong>of</strong> Sub-Total (B) except<br />

on L.S. items) 3% 218.07 6.54<br />

10.0 Work Charges Establishment (2% <strong>of</strong> Sub-<br />

Total(B) except on L.S. items) 2% 218.07 4.36<br />

Total <strong>of</strong> 1 to 10 233.34


ADITS<br />

S. NO. DESCRIPTION UNIT QTY.<br />

RATE<br />

(Rs.) Amt.in Lac<br />

1.0 Surface Excavation<br />

1.1 Common excavation Cum 100 125.00 0.13<br />

1.2 Rock excavation Cum 200 300.00 0.60<br />

2.0 Under ground excavation<br />

2.1 Excavation <strong>of</strong> adits Cum 32650 1000 326.50<br />

3.0 Supports System<br />

3.1 Rockbolts M 16000 625 100.00<br />

3.2 Steel ribs suppots (if required) Ton 280 42000 117.60<br />

3.3 Shotcreting Cum 2830 4000 113.20<br />

3.4 Concrete lagging if required Cum NIL<br />

4.0 Concrete<br />

4.1 M 10 Cum 750 2560 19.20<br />

4.2 M 15 Cum NIL<br />

4.3 M 20 Cum. NIL<br />

4.3 M 25 Cum. NIL<br />

5.0 Reinforcing Steel Ton NIL<br />

Sub-Total (A) <strong>of</strong> 1 to 5 677.23<br />

6.0 Miscellaeneous<br />

6.1 Various Miscellaneous works like drilling &<br />

grouting, wiremesh reinforcement ,masonary<br />

works,PVC pipes for drainage etc. (3-4 % <strong>of</strong><br />

Sub Total(A) depending on the site conditions<br />

& type pf structure)<br />

3 to 4% 3.50% 677.23 23.70<br />

Sub-Total (B) <strong>of</strong> 1 to 6 700.93<br />

7.0 Instrumentaion (1% <strong>of</strong> Sub-Total (B) 1% 700.93 7.01<br />

8.0 Dewatering (2% <strong>of</strong> Sub-Total (B)<br />

Contingencies (3% <strong>of</strong> Sub-Total(B) except on<br />

2% 700.93 14.02<br />

9.0 L.S. items)<br />

Work Charges Establishment (2% <strong>of</strong> Sub-<br />

3% 700.93 21.03<br />

10.0 Total(B) except on L.S. items) 2% 700.93 14.02<br />

Total <strong>of</strong> 1 to 10 757.00


Hydro-Mechaniocal Works<br />

S. NO. DESCRIPTION UNIT QTY.<br />

1.0 DIVERSION TUNNEL WORKS<br />

Gate (size) Ton Ton<br />

Embeded Parts Ton NIL<br />

Rope drum Hoist (as per capacity) Set NIL<br />

Hoist supporting structure & trestle Set NIL<br />

RATE<br />

(Rs.) Amt.in Lac<br />

2.0 SPILL WAY STRUCTURE<br />

a Radial gates (Size) 5.00mx6m Ton 120 100000 120.00<br />

Embedded parts (including anchorage) Ton 42 50000 21.00<br />

Hydraulic hoist Set 2 100000 2.00<br />

b Bulk head gates (size )5.00mx6m Ton 12.4 100000 12.38<br />

Embedded parts Ton 4.3 50000 2.17<br />

Gantry Crane Set 1 500000 5.00<br />

3.0 INTAKE STRUCTURE<br />

a Intake Gate (size) Ton NIL<br />

Embedded parts for Intake gates Ton NIL<br />

Rope Drum Hoist (as per capacity) Set NIL<br />

Hoist Plateform & trustle Set NIL<br />

b Bulk head gates (size) 5.50mx3m Ton 40 100000 40.00<br />

Embedded Parts For Bulk Head Gates Ton 15 50000 7.50<br />

Gantry Crane as per capacity Set 1 500000 5.00<br />

4.0 THRASH RACKS/TRASH RACK CLEANING MACHINE<br />

a Trash Rack Cleaning Machine Set 1 100000 1.00<br />

b Thrash Racks and embedded parts Ton 49 50000 24.50<br />

5.0 Desanding Basin<br />

Stoplogs Ton 70 60000 42.00<br />

Embedded parts Ton 26 50000 13.00<br />

Gantry Crane Set 1 500000 5.00<br />

6.0 DRFT TUBE GATE<br />

gates (size) 4mx6.50m Ton 7.500 100000 7.50<br />

Embedded Parts For Draft Tube Gates Ton 2.500 50000 1.25<br />

Gantry Crane (as per capacity) Set 1 500000 5.00<br />

7.0 TAIL RACE<br />

a Outlet Stoplogs Set NIL<br />

b Embedded parts Ton NIL<br />

8.0 SURGE SHAFT<br />

a Stoplogs Ton 35 60000 21.00<br />

b Embedded parts Ton 13 50000 6.50<br />

c Travelling Hoist Set 1 500000 5.00<br />

G/Total (1to8) 346.79


J - <strong>Power</strong> Plant and Civil Works<br />

S.No. Description Unit Qty. RATE (Rs Amt.in Lac<br />

I) C<strong>of</strong>fer Dam 329.76<br />

II) Barrage 9,243.19<br />

C-Works 9572.95<br />

III) Intakes Structure 337.34<br />

IV) Desanding Chamber 5968.28<br />

V) Head Race Tunnel & Tailrace Tunnel 6,415.56<br />

VI) Surge Shaft 862.58<br />

VII) Pressure Shaft 2899.73<br />

VIII) <strong>Power</strong> House Complex 2236.82<br />

IX) Switch Yard 233.34<br />

X) Adits 757.00<br />

XI) Hydro-Mechaniocal Works 346.79<br />

Total J-<strong>Power</strong> Plant 20,057.42


Chhatru HEP (108MW ) in Chenab Basin <strong>of</strong> HIMACHAL PREDESH<br />

ABSTRACT OF COST OF CIVIL WORK<br />

Annex -D<br />

S.N. Description<br />

Amount in Lac<br />

A CIVIL WORKS<br />

1 DIRECT CHARGES<br />

I-Works<br />

A-Priliminary 501.25<br />

B-Land 350.00<br />

C-Works 9572.95<br />

J-<strong>Power</strong> Plant Civil Works 20,057.42<br />

K- Buildings 1341.94<br />

M-Plantation 25.00<br />

O-Miscelleoneous 966.77<br />

P- Maintenance 335.05<br />

Q- Special Tools & Plants 496.71<br />

R- Communication 656.70<br />

X- Envoirment & Ecology 470.00<br />

Y- Losses on Stock 79.27<br />

Total <strong>of</strong> I-Works 34853.06<br />

II - Establishment @ 8% <strong>of</strong> cost <strong>of</strong> I-Works 2760.24<br />

Less B- Land<br />

III - Tools & Plants @ 1% <strong>of</strong> cost <strong>of</strong> I - Works 348.53<br />

IV _ Suspence 680.04<br />

V - Recipts & Recoveries ( - )<br />

2 INDIRECT CHARGES<br />

a) Capatilised Value <strong>of</strong> Abatement <strong>of</strong> Land Revenue<br />

@5% <strong>of</strong> cost <strong>of</strong> land<br />

328.84<br />

TOTAL DIRECT CHARGES 38313.03<br />

17.50<br />

b) Audit & Account Charges @ 1% <strong>of</strong> cost <strong>of</strong> I - Works 348.53<br />

TOTAL INDIRECT CHARGES 366.03<br />

TOTAL DIRECT & INDIRECT CHARGES 38679.07<br />

Lac.


ABSTRACT OF COST<br />

A Civil Works 38679.07 Lac.<br />

B Electrical Works<br />

P- Production 13612.06 Lac.<br />

T-Transmission 844.68 Lac.<br />

TOTAL COST 53135.80 Lac.


S.N.<br />

1 Land Required for<br />

A. Reservoir submergence area<br />

B. Project features<br />

C. Township,store area and roads<br />

D. Quarry site<br />

E. Muck disposal Area & Job facilities<br />

F. Transit Camp And Guest Houses & Colony<br />

G. Project roads<br />

Name <strong>of</strong> Project Component<br />

H. Land for Rehablitation Purpose<br />

Total A<br />

Forest/<br />

Govt.<br />

/Pvt.<br />

Land<br />

Rates in<br />

Rs.Lacs./Ha<br />

Govt. 20.00 Nil<br />

Pvt.<br />

Area in<br />

Hac.<br />

Govt. 10.00 Nil<br />

Govt. 2.00 Nil<br />

Pvt. 4.00<br />

Govt. 1.50 Nil<br />

Govt. 1.00 Nil<br />

Pvt. 4.00<br />

Pvt. 6.00<br />

6.00<br />

NIL Nil<br />

2 Cost for impletation <strong>of</strong> R&R Plan L.S<br />

Total B<br />

3<br />

Cost <strong>of</strong> establishment for land acquisition<br />

and Rehablitation @6.25 % <strong>of</strong> item B<br />

6.25% 0.00<br />

4 Solitanium Charges @30 % <strong>of</strong> the cost <strong>of</strong><br />

the private land<br />

5 Interest Charges on amount <strong>of</strong> award for<br />

the period between taking over the possetion<br />

<strong>of</strong> land date <strong>of</strong> award @12 % per annum on<br />

25% <strong>of</strong> cost <strong>of</strong> total compensation for thte 2<br />

30% 0.00<br />

years<strong>of</strong> the cost <strong>of</strong> the private land<br />

12% 0.00 2<br />

6<br />

Lega charges @1 % <strong>of</strong> total compensation<br />

7 Labour and material charges for<br />

measurment & demarkation <strong>of</strong> land<br />

1% 0.00<br />

/Properties @ 1% <strong>of</strong> cost <strong>of</strong> land acquisition<br />

1% 0.00<br />

Total<br />

Total land<br />

B - LAND<br />

LS<br />

54.50 Hac.


Total Govt. land<br />

Total Private land<br />

40.50 Hac.<br />

14.00 Hac.


S.N. DESCRIPTION OF BUILDING UNIT<br />

TOTAL<br />

PLINTH<br />

AREA<br />

RATE IN Rs.<br />

1.0 Residential Building<br />

1.1 Permanent residential building Sq. m. 8800 4200<br />

Service Charges @ 31%<br />

1.2 Tem,porary Buildings Sq. m. 6000 3780<br />

Service Charges @ 27%<br />

Total Residential buildings<br />

2.0 Non - Residential Buildings<br />

2.1 Permanent Non - Residential Buildg. Sq. m. 9800 3800<br />

Service Charges @ 22.50%<br />

2.2 Temporary Non Residential Buildg. Sq. m. 2755 3420<br />

Service Charges @ 20.50%<br />

Total Non - Residential buildings<br />

K -BUILDING<br />

Grand Total (Residential + Non - Residential )


S.N. DESCRIPTIOPN<br />

QTY. UNIT RATE<br />

1.0 CAPITAL COST<br />

1.1 Electrification 5 YEAR 90000<br />

1.2<br />

1.3<br />

1.4<br />

2<br />

2.1 Maintenance & <strong>Power</strong> arrangements<br />

2.2 R &M <strong>of</strong> water supply facilities<br />

i.e. 8% <strong>of</strong> capital cost<br />

5 YEAR 3.40<br />

2.3 R & M <strong>of</strong> sanitation & drainage facilities<br />

i.e. 8% <strong>of</strong> capital cost<br />

2.4 R & M <strong>of</strong> Telecommunication system and<br />

5 YEAR 3.40<br />

post <strong>of</strong>ffice<br />

5 YEAR 0.42<br />

2.5 R & M <strong>of</strong> Hospital<br />

5 YEAR 10.00<br />

2.6 R & M <strong>of</strong> rest house and field hostel<br />

5 YEAR 1.00<br />

2.7<br />

2.8<br />

2.9<br />

Water supply, purification and distribution<br />

arrangements including puchase <strong>of</strong> water<br />

tankers, cost <strong>of</strong> tanks and chlorination<br />

Providing sewerage disposal and storm water<br />

drains at various coloney sites.<br />

Furnishing & equiping rest houses field<br />

hostels, hospitals schools etc.<br />

Maintenance & Service charges during<br />

execution period<br />

R & M <strong>of</strong> Research & Quality control<br />

laboratories<br />

Labour welfare compensation and<br />

retrenchment benfits<br />

O-MISCELLANEOUS<br />

Providing sequrity police including R & M <strong>of</strong><br />

Posts<br />

LS<br />

LS<br />

LS<br />

5 YEAR 25.00<br />

5 YEAR 15.00<br />

5 YEAR 5.00<br />

2.10 R & M <strong>of</strong> inspection vehicles and staff cars 5 YEAR 35.00


2.11 R & M <strong>of</strong> school buses and staff buses @ 2.5<br />

lakh per vehicle<br />

2.12<br />

5 YEAR 10.00<br />

5 YEAR 8.00<br />

2.13 R &M <strong>of</strong> field workshops<br />

5 YEAR 0.42<br />

2.14 Maintenance & Running <strong>of</strong> schools<br />

5 YEAR 35.00<br />

3.0 Miscelleonous<br />

3.1 Foundeation stone laying<br />

L.S<br />

3.2 Model exhibition<br />

L.S<br />

3.3 Group insurance<br />

L.S<br />

3.4 Compensation <strong>of</strong> accidents<br />

L.S<br />

3.5<br />

R & M <strong>of</strong> Ambulence @ RS 2.50 Lakh per<br />

Year per Vehicle<br />

Trainning <strong>of</strong> personnel abroad including<br />

study courses and visits<br />

L.S<br />

3.6 Others<br />

L.S<br />

TOTAL


Amount<br />

Rs.Lacs.<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0<br />

0<br />

0<br />

0<br />

350.00


AMT. IN<br />

LAC.<br />

369.60<br />

114.58<br />

226.80<br />

61.24<br />

772.21<br />

372.40<br />

83.79<br />

94.22<br />

19.32<br />

569.73<br />

1341.94


AMOUNT<br />

4.5<br />

43<br />

43<br />

50<br />

17.01<br />

17.01<br />

2.10<br />

50.00<br />

5.00<br />

125.00<br />

75.00<br />

25.00<br />

175.00


50.00<br />

40.00<br />

2.10<br />

175.00<br />

5.00<br />

8.00<br />

15.00<br />

25.00<br />

8.00<br />

8.00<br />

966.77


A-Preliminary<br />

Sr.No. Description Unit Qty. Rate Amount<br />

(lacs)<br />

1. Exprenditure on investigations alredy conducted 14.00<br />

2. Pre-construction and const. Stage investigations:<br />

I) Topographical surveys by the deptt. and survey<br />

<strong>of</strong> India L.S. 50.00<br />

ii) Hydro-meteorological data collection for 5 years<br />

including stablishing self rcording rain/snow<br />

gauge stations, climato-logical laboratory,<br />

silt laboratory and conducting sediment<br />

silt & water tests etc. L.S. 47.25<br />

iii) Geological and geophysical explorations,<br />

geotechnical testing and data collection<br />

sieismological observations and laboratories L.S. 40.00<br />

iv) Construction material testinmg, establishing<br />

soil and rock testing laboratory L.S. 45.00<br />

v) Environment and ecological surveys L.S. 10.00<br />

vi) Hydraulic model studies and testing L.S. 55.00<br />

3. Training <strong>of</strong> engineers and technicians L.S. 30.00<br />

4. Construction <strong>of</strong> access paths and jeepable<br />

roads, for investigation. L.S. 45.00<br />

5. Inspection vehicles for investiqation I/c<br />

R/M charges L.S. 25.00<br />

6. Surveys, drawing mathematicqal and <strong>of</strong>fice<br />

equipment like photo-copier, ammonia<br />

printing machine etc. L.S. 40.00<br />

7. Consultants fees L.S. 35.00<br />

8. Publication <strong>of</strong> brochures, <strong>project</strong> reports .<br />

comprising design reports, estimates, bulletins<br />

completion reports,history <strong>of</strong> the poject etc L.S. 40.00<br />

9. Personal computer along with CGA,<br />

printer and plotter etc. L.S. 25.00<br />

Total 501.25


Q- Special T&P<br />

S.No. Description Unit Qty. Rate Amount<br />

(in Rs.) (lacs)<br />

1. Hydraulic excavator Bucket capacity Nos 2 7500000 150<br />

2.0 cum "<br />

2. Dumper 20 ton capacity " 8 3200000 256<br />

3. Working platform 2 4000000 80<br />

4. Grouting pump " 1 700000 7<br />

5. Grout hole drilling crawler " 1 1500000 15<br />

6. Hydraulic rubber-wheel based drilling " 2 1500000 30<br />

2-boom jumbo<br />

7. Tower crane 25m/3 tons " 1 1E+07 100<br />

8. Concrete pump 40 cum/hr. 2 4500000 90<br />

9. Motor grader 10 tons 145 HP " 1 6500000 65<br />

10. Concrete lorry with 2.5 cum rotary drum " 1 1900000 19<br />

mixer 2.5 rotary drum mixer<br />

11. Draining pump (8 bar water <strong>hydro</strong>phore) " 20 75000 15<br />

30 HP<br />

12. Draining pump 10 HP " 20 50000 10<br />

13. Internal vibrator with <strong>electric</strong> motor<br />

& converter " 1 30000 0.3<br />

14. Transformer 315 KVA " 3 215000 6.45<br />

15. Shotcreting robot 1 8000000 80<br />

16. Hydraulic excavator 1.0 cum " 1 5000000 50<br />

17. Batching plant " 2 4800000 96<br />

18. Wheel loader 1.15 cum " 1 2200000 22<br />

19. Crawler dozer 180 HP " 1 4050000 40.5<br />

20. Air compressor <strong>electric</strong> 500 cfm " 5 750000 37.5<br />

21. Air compressor diesel 500 cfm 148 HP " 5 750000 37.5<br />

22. Jack hammer 52 lbs " 5 30000 1.5<br />

23. Pavement breaker " 1 30000 0.3<br />

24. Concrete mixer 10/7 cft " 4 80000 3.2<br />

25. Transit mixer 14/10 cft " 1 130000 1.3<br />

26. Pneumatic concrtete placer " 1 100000 1<br />

27. Grout pump " 1 700000 7<br />

28. Tipper 4.5 cum " 1 630000 6.3<br />

29. Material truck " 1 800000 8<br />

30. Coarse aggregate processing plant 30 ton " 2 3000000 60<br />

31. wagon drill " 1 800000 8<br />

32. Bus " 3 800000 24<br />

33. Car " 9 400000 36<br />

34 Jeep 20 400000 80<br />

35 Pick up van 4 450000 18<br />

36 Ambulance 2 450000 9<br />

37 Workshop equipment L.S 15<br />

Total cost <strong>of</strong> Q-Special T&P 1485.85<br />

Cost <strong>of</strong> personal carriers 167<br />

Cost <strong>of</strong> Q-Special T& P other than personal<br />

carriers 1318.85<br />

Cost <strong>of</strong> Q-Special T & P chargeable to estimate<br />

25% <strong>of</strong> (cost <strong>of</strong> Q-Special T&P other than<br />

personal carriers) 1318.9 25% 329.71<br />

Cost <strong>of</strong> personal carrier chargeable to<br />

estimate=100% 167 100% 167.00


Total 496.71


R-Comunication<br />

S.No. Description Unit Qty. Rate Amount<br />

(in lacs) (lacs)<br />

1<br />

2<br />

3<br />

4<br />

C/O proposed road from main road (suspension bridge) to<br />

surge shaft and power house 5/7m wide i/c metalling &<br />

tarring.<br />

C/O proposed road from main road to adit <strong>of</strong> HRT 5/7m<br />

wide i/c metalling & tarring.<br />

C/O proposed road from main road to colony 5/7m wide i/c<br />

metalling & tarring.<br />

Realignment <strong>of</strong> existing main road along the reservoir 5/7m<br />

wide i/c metalling & tarring.<br />

Km. 10 17.9 179.00<br />

Km. 4 17.9 71.60<br />

Km. 6 17.9 107.40<br />

Km. 2 17.9 35.80<br />

5 Widening <strong>of</strong> existing motorable road from diversion <strong>of</strong><br />

Khoksar HEP to diversion <strong>of</strong> Chhatru HEP 5/7m wide i/c<br />

metalling & tarring.<br />

Km. 17 14.3 243.10<br />

6 Proposed permanent RCC bridge in place <strong>of</strong> existig<br />

suspension bridge 7.50m wide.<br />

Rmt 22 0.9 19.80<br />

Total 656.70


S.No. Description Unit Qty. Rate Amount<br />

(in Rs.) (lacs)<br />

X-Environment and Ecology<br />

I) Cost <strong>of</strong> compensatory afforestation in <strong>project</strong> L.S. 20.00<br />

2) Cost <strong>of</strong> fule wood L.S. 30.00<br />

3)Cost <strong>of</strong> health facility L.S. 3.00<br />

4) Cost <strong>of</strong> catchment area treatment plan L.S. 400.00<br />

5) Cost <strong>of</strong> reclamation and plantation L.S. 9.00<br />

60 Cost <strong>of</strong> environment monitoring cell L.S. 8.00<br />

V-Receipt & Recoveries<br />

I) Temporary Buildings -<br />

Total 470.00<br />

Cost <strong>of</strong> temporary buildings 321.02 15% 48.15<br />

Credit @15 % -<br />

ii) Q-Special T&P Recoveries under the -<br />

sub-head<br />

'@ 75% <strong>of</strong> Q-Special T&P charged to estimate -<br />

other than personal carriers 329.71 75% 247.28<br />

-<br />

iii) Cost recoverable on a/c <strong>of</strong> resale value <strong>of</strong> personal<br />

carrier @20% <strong>of</strong> capital cost 167 20% 33.40<br />

Total 328.84


Y- Losses on stock<br />

Provision made @ 0.25% on the cost <strong>of</strong> I-Works less<br />

A-Preliminary, B-Land, M-Plantation, O-Misc., P-Maintenance,<br />

Q-Special T&P and X-Environment & Ecology. 31,708.28<br />

I-Works 34,853.06<br />

Less:<br />

A-Preliminary 501.25<br />

B-Land 350.00<br />

M-Plantation 25.00<br />

O-Miscellaneous, % <strong>of</strong> I Works less (A+B+Q) 966.77<br />

P-Maintence 335.05<br />

Q-Speci8al Tools & Plant 496.71<br />

X-Environment and Ecology 470.00<br />

Total 3144.78<br />

P - Maintenance<br />

0.25% 79.27<br />

1% <strong>of</strong> I- works less (A+B+Q) 1% 33505.10 335.05<br />

I-Works 34853.06<br />

less - A- Preliminary 501.25<br />

B-Land 350.00<br />

Q- Special T&P 496.71<br />

Net Total 33505.10


Name <strong>of</strong> <strong>project</strong>:- Chhatru HEP (108MW ) in Chenab Basin<br />

<strong>of</strong> Himachal Predesh<br />

ABSTRACT OF COST OF CIVIL WORK<br />

S.N.<br />

Annexure -13.1 (a)<br />

Annex -D<br />

Amount (in<br />

Crores) (June<br />

2003)<br />

A CIVIL WORKS<br />

1 DIRECT CHARGES<br />

I-Works<br />

A-Priliminary 501.25<br />

B-Land 350.00<br />

C-Works 9572.95<br />

J-<strong>Power</strong> Plant Civil Works 20057.42<br />

K- Buildings 1341.94<br />

M-Plantation 25.00<br />

O-Miscelleoneous 966.77<br />

P- Maintenance 335.05<br />

Q- Special Tools & Plants 496.71<br />

R- Communication 656.70<br />

X- Envoirment & Ecology 470.00<br />

Y- Losses on Stock 79.27<br />

Total <strong>of</strong> I-Works 34853.06<br />

II - Establishment @ 8% <strong>of</strong> cost <strong>of</strong> I-Works Less B- Land 2760.24<br />

III - Tools & Plants @ 1% <strong>of</strong> cost <strong>of</strong> I - Works 348.53<br />

IV _ Suspence 680.04<br />

2 INDIRECT CHARGES<br />

Description<br />

V - Recipts & Recoveries ( - )<br />

a) Capatilised Value <strong>of</strong> Abatement <strong>of</strong> Land Revenue<br />

@5% <strong>of</strong> cost <strong>of</strong> land<br />

328.84<br />

TOTAL DIRECT CHARGES 38313.03<br />

17.50<br />

b) Audit & Account Charges @ 1% <strong>of</strong> cost <strong>of</strong> I - Works 348.53<br />

TOTAL INDIRECT CHARGES 366.03<br />

TOTAL DIRECT & INDIRECT CHARGES 38679.07


CHHATRU HYDRO-ELECTRIC-PROJECT (108 MW)<br />

Annexure -13.1 (b)<br />

COST ESTIMATES OF ELECTRO-MECHANICAL WORKS FOR PRE-FEASIBILITY REPORT<br />

Sl.No Item Qty Rate Amount Excise Duty* Total<br />

Rs.(Lakhs) Rate Amount Amount<br />

(Rs. Lakhs) (Rs. Lakhs)<br />

1 2 3 4 5 6 7 8<br />

1 Generating Unit and 11 KV Bus Duct 36MW,<br />

428.6 RPM with net Head <strong>of</strong> 160 mtrs.<br />

3 Rs.5600/KW 6048.00 16% 967.68 7015.68<br />

2 Step-up transformer, 11/220KV,15MVA,single<br />

phase<br />

10 Rs.260/KVA 390.00 16% 62.40 452.40<br />

3 Auxiliary Electrical Equipment for <strong>Power</strong><br />

Stations (Except transformer) (5% <strong>of</strong> item 1).<br />

302.40 16% 48.38 350.78<br />

4 Auxiliary Equipment and Services for <strong>Power</strong><br />

Stations (5% <strong>of</strong> item-1)<br />

302.40 16% 48.38 350.78<br />

5 220 KV Switchyard GIS. 6 bays 300 Lacs/bay 1800.00 16% 288.00 2088.00<br />

6 Spares (5% <strong>of</strong> 1 and 3% <strong>of</strong> 2-5) 386.24 16% 61.80 448.04<br />

7 Sub-Total-1: 9229.04 10705.68<br />

8 Central Sales Tax ** 4% <strong>of</strong> item 1 to 6 428.23<br />

9 Transportation & Insurance 6% <strong>of</strong> item-7 642.34<br />

10 Erection and Commissioning 8% <strong>of</strong> item-7<br />

(except spares)<br />

820.61<br />

11 Sub-Total-2 : 12596.86<br />

12 Establishment, Contingency, other charges<br />

11% <strong>of</strong> item-7 (excluding duties)<br />

1015.20<br />

Grand Total :- 13612.06<br />

Say Rs. 13612 Lacs


Annexure -13.1 ( c )<br />

CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

MAIN ABSTRACT OF COST OF TRANSMISSION<br />

Sr.No. Description Amount ( in Lacs)<br />

1 Preliminary Works ( Annex. 1) 5.10<br />

2 Detailed Surveying ( Annex. 2) 1.74<br />

3 Compensation for land, Trees,<br />

Crops, Tree cutting and<br />

afforestation ( Annex. 3)<br />

13.20<br />

4 Transmission Line ( Annex. 4) 626.00<br />

5 Terminal Equipment at Tandi<br />

(LILO <strong>of</strong> one ckt. <strong>of</strong> Khoksar-<br />

Tandi 220Kv D/C line)<br />

0.00<br />

6 PLCC Equipment at Tandi 69.6<br />

7 Buildings 15<br />

8 Vehicles and Workshop<br />

machinery ( Annex. 13)<br />

34<br />

Sub Total-I 764.64<br />

9 Contingency @ 3% on Item 1 to<br />

8<br />

22.94<br />

Sub Total-II 787.58<br />

10 Establishment charges @ 4%, 57.10<br />

GRAND TOTAL 844.68<br />

Say Rs. 845 LACS


YEAR- WISE PHASING OF FUNDS<br />

Installed Capacity 108MW (3*36 MW)<br />

108 MW<br />

Peaking Capacity 108 MW<br />

Energy @ 90% Dependable Year (Over all Efficie<br />

455.72 Million Units<br />

Rate <strong>of</strong> Interest<br />

10.00%<br />

Discounting Rate<br />

12.00%<br />

ea<br />

Civil Works<br />

Electrical Works<br />

Transmission<br />

TOTAL<br />

Rs in Crores<br />

386.79<br />

136.12<br />

8.45<br />

531.36<br />

Civil Works Electrical Works<br />

Transmission<br />

Generation<br />

Gen.+<br />

Trans<br />

2 3 4 5 6 7 col. 3+5 Col3+5+7<br />

% Funds<br />

Reqd.<br />

Rs in<br />

Crores<br />

%<br />

Funds<br />

Reqd.<br />

Annexure 13.2<br />

Rs in<br />

Crores % Funds Reqd. Rs in Crores Rs in Crores<br />

Rs in<br />

Crores<br />

1 5.0% 19.34 0.0% 0.00 0.0% 0.00 19.34 19.34<br />

5.0% 19.34 2.5% 3.40 0.0% 0.00 22.74 22.74<br />

2 7.5% 29.01 5.0% 6.81 5.0% 0.42 35.82 36.24<br />

7.5% 29.01 5.0% 6.81 5.0% 0.42 35.82 36.24<br />

3 15.0% 58.02 10.0% 13.61 10.0% 0.84 71.63 72.48<br />

15.0% 58.02 17.5% 23.82 15.0% 1.27 81.84 83.11<br />

4 17.5% 67.69 20.0% 27.22 22.5% 1.90 94.91 96.81<br />

17.5% 67.69 20.0% 27.22 22.5% 1.90 94.91 96.81<br />

5 10.0% 38.68 20.0% 27.22 20.0% 1.69 65.90 67.59<br />

T 100% 386.79 100.0% 136.12 100.0% 8.45 522.91 531.36


ESCALATED COST<br />

Annexure<br />

Escalation on civil works 0.00% (Yerly)<br />

Escalation on elect. works 0.00% (Yerly)<br />

Gen.+<br />

ea Civil Works Electrical Works<br />

Transmission<br />

Generation Trans<br />

Envisaged Escalated Envisaged Escalated Envisaged Escalated Escalated Escalated<br />

2 3 4 5 6 7 col 3+ 5 col 3+5+7<br />

E<br />

x<br />

p<br />

.<br />

A<br />

l<br />

r<br />

e<br />

a<br />

d<br />

y<br />

i<br />

n<br />

c<br />

u<br />

r<br />

r<br />

e<br />

d 0.14 0.14 0.14 0.14<br />

19.20 19.20 0.00 0.00 0.00 0.00 19.20 19.20<br />

19.34 19.34 3.40 3.40 0.00 0.00 22.74 22.74<br />

29.01 29.01 6.81 6.81 0.42 0.42 35.82 36.24<br />

29.01 29.01 6.81 6.81 0.42 0.42 35.82 36.24<br />

58.02 58.02 13.61 13.61 0.84 0.84 71.63 72.48<br />

58.02 58.02 23.82 23.82 1.27 1.27 81.84 83.11<br />

67.69 67.69 27.22 27.22 1.90 1.90 94.91 96.81<br />

67.69 67.69 27.22 27.22 1.90 1.90 94.91 96.81<br />

38.68 38.68 27.22 27.22 1.69 1.69 65.90 67.59<br />

T<br />

G<br />

386.65 386.65 136.12 136.12 8.45 8.45 522.77 531.22<br />

.<br />

T<br />

386.79 386.79 136.12 136.12 8.45 8.45 522.91 531.36<br />

o<br />

Esclation: 0.00 0.00 0.00 0.00 0.00


COST OF THE PROJECT INCLUDING IDC. (At power house bus bars)<br />

Rate <strong>of</strong><br />

interest:-<br />

EQUITY 30% 156.87<br />

Loan @ 10.00% 70% 366.04<br />

Discounting factor 12.00% Total 522.91<br />

Annexure 13.3<br />

H<br />

a<br />

l<br />

f-<br />

Y<br />

e Phasing <strong>of</strong><br />

NPV <strong>of</strong><br />

a Escalated Equity LOAN loan Op.<br />

Int fin. From Int fin. From<br />

Total Discountin NPV <strong>of</strong> Esclated<br />

r Hard Cost 30% 70% Bal. Interest on loan. Eq.30% Loan.70% Total Loan Equity g Factor IDC Cost<br />

2 3 4 5 6 7 8 9 10<br />

19.34 5.80 13.54 0 0.34 0.10 0.24 13.77 5.90 1.00 0.34 19.34<br />

22.74 6.82 15.92 13.77 1.09 0.33 0.76 16.68 7.15 0.94 1.03 21.46<br />

35.82 10.74 25.07 30.46 2.15 0.64 1.50 26.58 11.39 0.89 1.91 31.88<br />

35.82 10.74 25.07 57.03 3.48 1.04 2.43 27.51 11.79 0.84 2.92 30.07<br />

71.63 21.49 50.14 84.54 5.48 1.64 3.84 53.98 23.13 0.79 4.34 56.74<br />

81.84 24.55 57.29 138.51 8.36 2.51 5.85 63.14 27.06 0.75 6.25 61.16<br />

94.91 28.47 66.44 201.65 11.74 3.52 8.22 74.66 32.00 0.70 8.28 66.91<br />

94.91 28.47 66.44 276.31 15.48 4.64 10.83 77.27 33.12 0.67 10.29 63.12<br />

65.90 19.77 46.13 353.58 14.12 4.24 9.89 56.02 24.01 0.63 8.86 41.35<br />

T 522.91 156.87 366.04 62.24 18.67 43.56 409.60 175.54 44.22 392.02<br />

Original Cost 522.91<br />

Esc. 0.00<br />

Hard Escalated 522.91 89.36% 89.36% Loan 409.60 70.00%<br />

IDC = 62.24 10.64% 10.64% Equity 175.54 30.00%<br />

Total = 585.15 100% 100.00% Total 585.15


COST OF THE PROJECT INCLUDING IDC. (At purchase center)<br />

Switch 2<br />

Rate <strong>of</strong><br />

interest:-<br />

EQUITY 30.00% 159.41<br />

Loan @ 10.00% 70.00% 371.95<br />

Discounting factor 12.00% Total 531.36<br />

Annexure 13.3 (b)<br />

H<br />

a<br />

l<br />

f-<br />

Y<br />

e Phasing <strong>of</strong><br />

NPV <strong>of</strong><br />

a Escalated Equity LOAN loan Op.<br />

Int fin. From Int fin. From<br />

Total Discountin NPV <strong>of</strong> Esclated<br />

r Hard Cost 30% 70% Bal. Interest on loan. Eq.30% Loan.70% Total Loan Equity g Factor IDC Cost<br />

2 3 4 5 6 7 8 9 10<br />

19.34 5.80 13.54 0 0.34 0.10 0.24 13.77 5.90 1.00 0.34 19.34<br />

22.74 6.82 15.92 13.77 1.09 0.33 0.76 16.68 7.15 0.94 1.03 21.46<br />

36.24 10.87 25.37 30.46 2.16 0.65 1.51 26.88 11.52 0.89 1.92 32.25<br />

36.24 10.87 25.37 57.33 3.50 1.05 2.45 27.82 11.92 0.84 2.94 30.43<br />

72.48 21.74 50.73 85.15 5.53 1.66 3.87 54.60 23.40 0.79 4.38 57.41<br />

83.11 24.93 58.17 139.75 8.44 2.53 5.91 64.08 27.46 0.75 6.31 62.10<br />

96.81 29.04 67.77 203.83 11.89 3.57 8.32 76.09 32.61 0.70 8.38 68.25<br />

96.81 29.04 67.77 279.92 15.69 4.71 10.98 78.75 33.75 0.67 10.43 64.39<br />

67.59 20.28 47.31 358.67 14.34 4.30 10.04 57.35 24.58 0.63 9.00 42.41<br />

T 531.36 159.41 371.95 62.96 18.89 44.07 416.03 178.30 44.72 398.03<br />

Original Cost 531.36<br />

Esc. 0.00<br />

Hard Escalated 531.36 89.41% 89.41% Loan 416.03 70.00%<br />

IDC = 62.96 10.59% 10.59% Equity 178.30 30.00%<br />

Total = 594.32 ###### 100.00% Total 594.32


Annexure -13.4<br />

DETAIL OF DEPRECIATION<br />

Life in % Rate Cost (Rs.in Dep. (Rs.<br />

years <strong>of</strong> Dep. Lac.) in Lac.)<br />

I-CIVIL WORKS<br />

Diversion Barrage 50 1.95 9,243.19 180.24<br />

Intake Structure 50 1.95 337.34 6.58<br />

Desanding Chamber 50 1.95 5,968.28 116.38<br />

Head Race Tunnel &<br />

Tail Race<br />

50 1.95 6,415.56 125.10<br />

Surge Shaft 35 3.4 862.58 29.33<br />

Pressure Shaft 35 3.4 2,899.73 98.59<br />

P/ House 35 3.4 2,236.82 76.05<br />

Buildings. 50 3.02 233.34 7.05<br />

R-Communication 50 3.02 757.00 22.86<br />

Total 28,953.82 662.18<br />

II-ELECTRICAL WORKS<br />

Generating Plant and Equi 35 3.4 5500 187.00<br />

Transformers 25 7.84 390 30.58<br />

Switchgears etc. 25 7.84 20 1.57<br />

Communication equipeme 15 12.77 180 22.99<br />

Batteries and DC equipts. 5 33.44 45 15.05<br />

Air conditioning and venti 15 12.77 50 6.39<br />

Bus ducts 50 1.95 150 2.93<br />

Plant handling equipts. 5 33.44 800 267.52<br />

Total 10294.96 534.01<br />

G. Total 39,248.78 1196.19<br />

Rate <strong>of</strong> Depreciation-<br />

Say<br />

3.05<br />

3%


Calculations for Levelised Tariff For Chhatru Hydro Electric Project (AT POWER HOUSE BUS BARS)<br />

Assumtions<br />

( without free power)<br />

Cost Of Project Rs. 522.91 Crores<br />

IDC Rs. 62.24 Crores<br />

Total Cost 585.15 Crores<br />

Loan<br />

70%<br />

Equity<br />

30% Return on Equity (Post Tax) 16.0%<br />

Loan amount<br />

409.60 Crores Income Tax @ 35% + 10% Surcharge 38.5%<br />

Design Energy 455.72 Million Units Assumed Sale Rate :<br />

Rs. 2.75 per unit<br />

Free <strong>Power</strong><br />

0%<br />

Available Energy<br />

Interest Rate<br />

455.72<br />

10.0%<br />

Million Units<br />

Working Capital: 1 month O&M Charges including spares + Actual recievables for 2 months<br />

Repayment Period<br />

12 Years Rs. 21.37 Crores<br />

O&M Charges<br />

1.5%<br />

Depreciation(yearly)<br />

3.00% (Straight Line Method up 90% <strong>of</strong> the value)<br />

Aux. Consumption<br />

0.7% Dep. Amount 90% <strong>of</strong> the total cost 526.63 Lac.<br />

Transformation Losses<br />

0.5% Dep. Amount recovered 526.63 Lac.<br />

Interest on Working Captial<br />

9.75%<br />

Discount Rate<br />

12.00%<br />

Transmission Losses 0.00%<br />

Year 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18<br />

Capacity Charges<br />

1 Interest on debt Rs. Crores 39.25 35.84 32.43 29.01 25.60 22.19 18.77 15.36 11.95 8.53 5.12 1.71 0.00 0.00 0.00 0.00 0.00 0.00<br />

2 Depreciation @ 3.00% Rs. Crores 17.55 17.55 17.55 17.55 17.55 17.55 17.55 17.55 17.55 17.55 17.55 17.55<br />

a AAD 1/12 <strong>of</strong> loan minus dep. Rs. Crores 16.58 16.58 16.58 16.58 16.58 16.58 16.58 16.58 16.58 16.58 16.58 16.58<br />

b Total Depriciation Rs. Crores 34.13 34.13 34.13 34.13 34.13 34.13 34.13 34.13 34.13 34.13 34.13 34.13 5.09 5.09 5.09 5.09 5.09 5.09<br />

3 Return on Equity Rs. Crores 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09<br />

4 O&M Charges Rs. Crores 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78<br />

5 Interest on W.C Rs. Crores 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08<br />

6 Income Tax on ROE Rs. Crores 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58<br />

7 Total<br />

129.92 126.50 123.09 119.68 116.26 112.85 109.44 106.02 102.61 99.20 95.78 92.37 61.62 61.62 61.62 61.62 61.62 61.62<br />

8 Equated energy Sent Out Rs/Kwh 2.89 2.81 2.73 2.66 2.58 2.51 2.43 2.35 2.28 2.20 2.13 2.05 1.37 1.37 1.37 1.37 1.37 1.37<br />

9 Discounted Calculations<br />

10 Rate<br />

12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00%<br />

11 Discounting Factor<br />

1.00 0.89 0.80 0.71 0.64 0.57 0.51 0.45 0.40 0.36 0.32 0.29 0.26 0.23 0.20 0.18 0.16 0.15<br />

12 Discounted Equated Charge Rs/Kwh 2.89 2.51 2.18 1.89 1.64 1.42 1.23 1.07 0.92 0.79 0.68 0.59 0.35 0.31 0.28 0.25 0.22 0.20<br />

Levelised Tariff(Discounted) Rs/Kwh<br />

Annexure 13.5<br />

2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28


Annexure 13.5 Contd.<br />

19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35<br />

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />

5.09 5.09 5.09 5.09 5.09 5.09 5.09 5.09 5.09 5.09 5.09 5.09 5.09 5.09 5.09 5.09 5.09<br />

28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09<br />

8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78<br />

2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08<br />

17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58<br />

61.62 61.62 61.62 61.62 61.62 61.62 61.62 61.62 61.62 61.62 61.62 61.62 61.62 61.62 61.62 61.62 61.62<br />

1.37 1.37 1.37 1.37 1.37 1.37 1.37 1.37 1.37 1.37 1.37 1.37 1.37 1.37 1.37 1.37 1.37<br />

12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00%<br />

0.13 0.12 0.10 0.09 0.08 0.07 0.07 0.06 0.05 0.05 0.04 0.04 0.03 0.03 0.03 0.02 0.02<br />

0.18 0.16 0.14 0.13 0.11 0.10 0.09 0.08 0.07 0.06 0.06 0.05 0.05 0.04 0.04 0.03 0.03<br />

2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28


CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

MAIN ABSTRACT OF COST OF TRANSMISSION<br />

Sr.No. Description Amount ( in Lacs)<br />

1 Preliminary Works ( Annex. 1) 5.10<br />

2 Detailed Surveying ( Annex. 2) 1.74<br />

3 Compensation for land, Trees,<br />

Crops, Tree cutting and afforestation<br />

( Annex. 3)<br />

13.20<br />

4 Transmission Line ( Annex. 4) 626.00<br />

5 Terminal Equipment at Tandi (LILO<br />

<strong>of</strong> one ckt. <strong>of</strong> Khoksar-Tandi<br />

220Kv D/C line)<br />

0.00<br />

6 PLCC Equipment at Tandi 69.6<br />

7 Buildings 15<br />

8 Vehicles and Workshop machinery<br />

( Annex. 13)<br />

34<br />

Sub Total-I 764.64<br />

9 Contingency @ 3% on Item 1 to 8 22.94<br />

Sub Total-II 787.58<br />

10 Establishment charges @ 4%, Tools<br />

and Plants @ 1%, Losses on stock<br />

@ 0.25%, Maintenance during<br />

construction @ 1%, Audit and<br />

accounts charges @ 1%<br />

57.10<br />

GRAND TOTAL 844.68<br />

Say Rs. 845 LACS


CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

COST OF PRELIMINARY WORKS<br />

Annexure-1<br />

Sr.No Description Qty Amount in Lacs<br />

1 Cost <strong>of</strong> Temporary Sheds and<br />

camping requirement ( Annex.- 1.1)<br />

2.5<br />

2 Cost <strong>of</strong> Reconnaisance and<br />

Preliminary survey ( Annex.- 1.2)<br />

0.60<br />

3 PTCC Clearance LS 2<br />

TOTAL<br />

Sheet 2<br />

5.10


CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

Annexure-1.1<br />

ABSTRACT OF COST FOR TEMPORARY SHEDS AT EACH<br />

CAMPING SITE<br />

Sr. No Description Qty Rate Unit Amount in Rs<br />

1 Temporary Sheds <strong>of</strong> CGI<br />

Sheets on sides and top with<br />

wooden ballies posts and<br />

Wooden Rafters<br />

100 700 Sq.Mtr 70000<br />

2 One Swiss Engineer Cottage,<br />

Engineer tent ( 3.65 x 3.65)<br />

1 5500 No 5500<br />

3 Four Labour tents for<br />

Chowkidars Double Ply<br />

4 5500 Nos 22000<br />

4 Area Fencing with Angle Iron/<br />

wooden Posts and barbed<br />

wire etc.<br />

1 22000 LS 22000<br />

5 Miscellaneous Tools for<br />

setting up Camp<br />

1 5500 LS 5500<br />

6 Total Cost <strong>of</strong> Each Camp 125000<br />

7 Number <strong>of</strong> Camps required<br />

for surveying the<br />

Transmission System under<br />

Sorang HEP<br />

2 Nos<br />

8 TOTAL COST OF 2 CAMPS 250000<br />

Sheet 3<br />

Say Rs 2.5<br />

Lacs


CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

Annexure-1.2<br />

ABSTRACT OF COST FOR RECONNAISANCE AND<br />

PRELIMINARY SURVEY OF 220 KV D/C LINES.<br />

Sr. No Description<br />

Reconnaisance and<br />

Preliminary survey ( Unit 1<br />

km <strong>of</strong> length )<br />

Qty Rate Unit Amount in Rs<br />

A SURVEYING PARTY<br />

I) Surveyor (Regular) 1 6000 No 6000<br />

ii) Beldar 6 2250 No 13500<br />

iii) Chowkidar 2 2250 Nos 4500<br />

Sub Total 24000<br />

B Labour for Reconnaisance<br />

and Preliminary survey <strong>of</strong> 1<br />

km <strong>of</strong> line<br />

Assuming 4 days for 1 Km<br />

<strong>of</strong> line and 25 working days<br />

in a month<br />

3840<br />

C Wooden Pegs 16 9 Nos 144<br />

Total (B+C) 3984<br />

Cost <strong>of</strong> conducting<br />

preliminary Survey per Km<br />

Line length<br />

3984<br />

Cost <strong>of</strong> conducting<br />

preliminary Survey for 15<br />

Kms Line length<br />

15 Kms. 59760<br />

Say Rs 0.60<br />

Sheet 4<br />

Lacs


CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

COST OF DETAILED SURVEYING OF 220 KV D/C LINE.<br />

Sr. No Description Qty Rate Unit Amount in Rs<br />

A SURVEYING PARTY<br />

Assuming 4 days for<br />

conducting <strong>of</strong> survey <strong>of</strong> 1<br />

km <strong>of</strong> line<br />

(I) Surveyor (Regular) 1 6000 No 6000<br />

(ii) Beldar (Daily Wages) 6 2250 Nos 13500<br />

(iii) Chowkidar (Daily Wages) 2 2250 Nos 4500<br />

(iv) Labour for 4 days<br />

( Assuming 4 days for 1 km<br />

and 25 working days in a<br />

month)<br />

3840<br />

(v) Wooden pegs 16 9 Nos 144<br />

Total 3984<br />

B Stacking ( Unit 1 Km <strong>of</strong><br />

line)<br />

0<br />

(I) Surveyor (Regular) 1 6000 Nos 6000<br />

(ii) Beldar (Daily Wages) 12 2250 Nos 27000<br />

(iii) Chowkidar (Daily Wages) 2 2250 4500<br />

Sub Total 37500<br />

(iv) Labour for 4 days<br />

( Assuming 4 days for 1 km<br />

and 25 working days in a<br />

month)<br />

6000<br />

(v) Stone Marking Pillars 8 80 Nos 640<br />

Total 6640<br />

C Transportation<br />

Camp Shifting Etc. 1000<br />

Total (A+B+C) 11624<br />

Cost <strong>of</strong> Detailed survey <strong>of</strong><br />

15 Kms <strong>of</strong> Line<br />

15 kms. 174360<br />

Say Rs 1.74<br />

Sheet 5<br />

Lacs<br />

Annexure-2


CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

Annexure-3<br />

COST OF COMPENSATION FOR LAND, TREES, CROPS,<br />

TREE CUTTING AND AFFORESTATION<br />

Sr. No Description Qty Rate Unit Amount in Rs<br />

1 Compensation for tree<br />

cutting and afforestation<br />

15 20000 Kms 300000<br />

2 Compensation for land<br />

falling under the towers and<br />

rent for camping site<br />

15 50000 Kms 750000<br />

3 Compensation to damage to<br />

crops under the line<br />

15 18000 Kms 270000<br />

Total 1320000<br />

Say Rs 13.2<br />

Lacs<br />

Sheet 6


CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

ESTIMATE OF COST FOR 220 KV D/C TRANSMISSION LINE FROM<br />

BARDANG TO TANDI 400 KV POOLING-IN STATION.<br />

Sr. No Description Qty Rate Unit Amount in Lacs<br />

1 220 KV D/C line (Snow<br />

Zone) ( Annex. 5)<br />

15 35.40 Kms 531.00<br />

2 Retaining Walls 65<br />

3 Benching <strong>of</strong> towers 30<br />

TOTAL 626.00<br />

Sheet 7


Annexure-4


CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

BREAK UP ESTIMATE FOR 1 KM OF 220 KV D/C LINE.<br />

(SNOW ZONE)<br />

Conductor size= 0.4 Sq. Inch Cu. Eq. "ACSR" ZEBRA<br />

Earth Wire Size= 7/3.18 mm GSS 140 Kgf Quality.<br />

Normal Span= 350 MTS<br />

Annexure-5<br />

Sr. No Description Qty Rate Unit Amount in Rs<br />

1 Steel for towers<br />

(Prefabricated galvanized/<br />

painted) ( Annex. 6)<br />

39.27 31000 MT 1217370.00<br />

2 Nuts and Bolts ( Annex. 6) 1.96 60000 MT 117600<br />

3 Tower Accessories<br />

( Annex. 7)<br />

4 Conductor ( Allowing<br />

1.5% for Sag and wastage)<br />

5 Conductor Accessories<br />

(Annex. 8)<br />

6 Ground Wire ( Allowing<br />

1.5% for Sag and Wastage)<br />

24770<br />

6.09 140000 Kms 852600<br />

16590<br />

1004.18 40 Kg 40167.2<br />

7 Ground Wire Accessories (<br />

Annex. 9)<br />

5760<br />

8 INSULATORS (ANNEX.<br />

10)<br />

I) Suspension 48 350 Nos 16800<br />

ii) Tension 510 400 Nos 204000<br />

9 INSULATOR<br />

HARDWARE (<br />

ANNEX. 12)<br />

I) Suspension 3 1600 Set 4800<br />

ii) Tension 30 2100 Set 63000<br />

10 Foundation Material, Sand,<br />

Bajri and Concrete<br />

(Annex. 7).<br />

55.37 3200 Cu Mt. 177184<br />

Sub Total 2740641.20


Sr. No Description Qty Rate Unit Amount in Rs<br />

11 Transportation @5%,<br />

Insutrance @ 1% and CST<br />

@ 4% ( Total 10% on Item<br />

1 to 10)<br />

274064.12<br />

12 Erection Charges<br />

( Annex. 11)<br />

525741.72<br />

GRAND TOTAL 3540447.04<br />

Say Rs 35.4<br />

Sheet 8 Lacs


CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

Annexure-5<br />

BREAK UP ESTIMATE FOR 1 KM OF 220 KV S/C LINE ON D/C TOWERS<br />

(NON SNOW ZONE)<br />

Conductor size= 0.4 Sq. Inch Cu. Eq. "ACSR" ZEBRA<br />

Earth Wire Size= 7/3.18 mm GSS 140 Kgf Quality.<br />

Normal Span= 350 MTS<br />

Sr. No Description Qty Rate Unit Amount in Rs<br />

1 Steel for Towers ( Prefabricated<br />

galvanised/ Painted ) Annex. 8<br />

27.13 31000 MT 841133.33<br />

2 Nuts and bolts ( Annex. 8) 1.36 60000 MT 81600<br />

3 Tower Accessories ( Annex. 9) 24770<br />

4 Conductor ( Allowing 1.5% for<br />

Sag and wastage)<br />

3.045 140000 Km 426300<br />

5 Conductor Accessories (Annex.<br />

10)<br />

8295<br />

6 Ground Wire Allowing (1.5% for<br />

Sag and Wastage)<br />

1004.18 40 Kg 40167.2<br />

7 Ground Wire Accessories (<br />

Annex. 11)<br />

5760<br />

8 INSULATORS (ANNEX. 12)<br />

I) Suspension 22.5 350 Nos 7875<br />

ii) Tension 240 400 Nos 96000<br />

9 INSULATOR HARDWARE<br />

(ANNEX. 12)<br />

I) Suspension 1.5 1600 Set 2400<br />

ii) Tension 15 2100 Set 31500<br />

10 Foundation Material, Sand, Bajri<br />

and concrete (Annex. 8)<br />

25.33 3200 Cu. Mt 81056<br />

Sub Total 1646856.53<br />

11 Transportation @ 5%, Insurance<br />

@ 1% and CST @ 4% ( Total<br />

10% on Item 1 to 10)<br />

164685.65<br />

12 Erection Charges ( Annex. 14) 292049.56<br />

GRAND TOTAL 2103591.7<br />

Say Rs 21.0<br />

Sheet 9 Lacs


Annexure-6<br />

CHHATRU HYDRO-ELECTRIC-PROJECT<br />

1 Span 350 Mtr<br />

2<br />

No. <strong>of</strong> Towers per 10 Km<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

Type <strong>of</strong> Tower Normal Tower Tower with<br />

3 mtr extn.<br />

Tower with 6<br />

mtr extn.<br />

Total<br />

W ( 0-2) 3 1 1 5<br />

X ( 2-15) 3 1 1 5<br />

Y ( 15-30) 10 1 1 12<br />

Z ( 30-60) 8 8<br />

Total 24 3 3 30<br />

3 No. <strong>of</strong> Tower<br />

Foundation / 10<br />

Kms<br />

W-Type X-Type Y-Type Z-Type<br />

Normal Soil 5 5 12 8<br />

4<br />

WEIGHT FOR TOWERS INCLUDING NUTS AND BOLTS<br />

Type <strong>of</strong> Tower Wt. Of Normal Wt. Of 3 Wt. Of 6 mtr.<br />

Tower mtr. Extn Extn<br />

W(0-2) 6.5x3=19.5 7.3 8.2<br />

X ( 2-15) 3x11.9= 35.7 13.5 14.6<br />

Y ( 15-30) 10x13.9= 139 15.7 17.2<br />

Z ( 30-60) 8x17.7=141.6<br />

Total 335.8 36.5 40<br />

5 TOTAL I/C<br />

NUTS AND<br />

BOLTS<br />

6 WT. OF NUTS<br />

AND BOLTS (<br />

5% OF TOWER<br />

WEIGHT)<br />

7 TOWER STEEL<br />

PER KM<br />

TOWER WEIGHT, CONCRETE FOR FOUNDATION<br />

AND EXCAVATION FOR FOUNDATION<br />

(SNOW ZONE)<br />

412.3 MT<br />

19.60 MT<br />

39.27 MT


8 WT. OF NUTS<br />

AND BOLTS<br />

PER KM<br />

1.96 MT<br />

9 VOLUME OF CONCRETE AND EXCAVATION FOR TOWER FOUNDATION<br />

Type <strong>of</strong> Tower No. <strong>of</strong> Tower<br />

Foundations<br />

/10 kms<br />

Volume <strong>of</strong><br />

Excavation<br />

( Cu. Mtr.)<br />

Volume <strong>of</strong><br />

Concrete (<br />

M^3)<br />

W 5 176.5 17.5<br />

X 5 334 39<br />

Y 12 1393.2 207.6<br />

Z 8 1453.6 289.6<br />

Total 30 3357.3 553.7<br />

10 VOLUME OF<br />

CONCRETE PER<br />

KM<br />

55.37 Cu. Mt<br />

11 VOLUME OF<br />

EXCAVATION<br />

PER KM<br />

335.73 Cu. Mt.<br />

Sheet 10


CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

Annexure-8<br />

TOWER WEIGHT, CONCRETE, FOR FOUNDATION<br />

AND EXCAVATION FOR FOUNDATION<br />

(NON SNOW ZONE)<br />

1 Span 350 Mtr<br />

2<br />

No. <strong>of</strong> Towers per 10 Km<br />

Type <strong>of</strong> Tower Normal Tower with 3 Tower with 6 Total<br />

Tower mtr extn. mtr extn.<br />

S ( 0-2) 3 1 1 5<br />

T ( 2-15) 3 1 1 5<br />

U ( 15-30) 10 1 1 12<br />

V ( 30-60) 8 8<br />

Total 24 3 3 30<br />

3 No. <strong>of</strong> Tower<br />

Foundation / 10<br />

Kms<br />

S-Type T-Type U-Type V-Type<br />

4<br />

Normal Soil 5 5 12 8<br />

WEIGHT FOR TOWERS INCLUDING NUTS AND BOLTS<br />

Type <strong>of</strong> Tower Wt. Of<br />

Normal<br />

Tower<br />

Wt. Of 3 mtr.<br />

Extn<br />

Wt. Of 6 mtr.<br />

Extn<br />

S(0-2) 6x3=18 6.7 7.6<br />

T ( 2-15) 3x7.5=<br />

22.5<br />

8.5 9.7<br />

U ( 15-30) 10x9.2=<br />

92<br />

10.4 11.9<br />

V ( 30-60) 8x12.2=9<br />

7.6<br />

Total 230.1 25.6 29.2<br />

5 TOTAL 284.9 MT<br />

6 WT. OF NUTS<br />

AND BOLTS (<br />

5% OF TOWER<br />

WEIGHT)<br />

13.60 MT<br />

7 TOWER<br />

STEEL PER<br />

KM<br />

27.13 MT


TOWER WEIGHT, CONCRETE, FOR FOUNDATION<br />

AND EXCAVATION FOR FOUNDATION<br />

(NON SNOW ZONE)<br />

8 WT. OF NUTS<br />

AND BOLTS<br />

PER KM<br />

1.36 MT<br />

9<br />

VOLUME OF CONCRETE AND EXCAVATION FOR TOWER<br />

FOUNDATION<br />

Type <strong>of</strong> Tower No. <strong>of</strong><br />

Tower<br />

Foundatio<br />

ns /10<br />

kms<br />

Volume <strong>of</strong><br />

Excavation (<br />

Cu. Mtr.)<br />

Volume <strong>of</strong><br />

Concrete (<br />

M^3)<br />

S 5 164.55 16<br />

T 5 252.15 26.2<br />

U 12 656.4 71.4<br />

V 8 934.48 139.68<br />

Total 30 2007.58 253.28<br />

10 VOLUME OF<br />

CONCRETE PER<br />

KM<br />

25.33 Cu. Mt<br />

11 VOLUME OF<br />

EXCAVATION<br />

PER KM<br />

Sheet 21<br />

200.76 Cu. Mt.


Annexure-7<br />

CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

TOWER FIXTURE FOR 220 KV D/C LINE.<br />

Sr. No Description Qty Rate Unit Amount in Rs<br />

1 Earthing Sets<br />

I) Counterpoise 25 3000 Nos 75000<br />

ii) Pipe Type 5 1400 NOs 7000<br />

2 Danger Plates 30 300 Nos 9000<br />

3 Number Plates 30 300 Nos 9000<br />

4 Bird Guard 5 540 Sets 2700<br />

5 Phase Plates 60 250 Sets 15000<br />

6 Anti Climbing 30 2500 Nos 75000<br />

7 Barbed wire<br />

Galvanised<br />

1000 40 Kg 40000<br />

8 Circuit Plates 60 250 Nos 15000<br />

Total Cost per 10 Kms 247700<br />

9 Cost per Km 24770<br />

Sheet 11


Annexure-8<br />

CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

CONDUCTOR ACCESSORIES FOR 220 KV D/C LINE.<br />

Sr. No Description Qty Rate Unit Amount in Rs<br />

1 Preformed Armour rods sets<br />

complete with Ferrules for<br />

Suspension Towers ( 2x3x5)<br />

30 550 Nos 16500<br />

2 Stock Bridge vibration<br />

Dampers ( 30x 2 x 3<br />

x2=360)<br />

360 330 Nos 118800<br />

3 Mid Span Compression Joints 52 300 Nos 15600<br />

4 Other Miscellaneous Items<br />

e.g. PG Clamps, Binding<br />

Wire etc.<br />

1 LS 15000<br />

Total Cost per 10 Kms 165900<br />

5 Cost <strong>of</strong> conductor<br />

Accessories per Km<br />

16590<br />

Sheet 13


Annexure-9<br />

CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

EARTHWIRE ACCESSORIES<br />

Sr. No Description Qty Rate Unit Amount in Rs<br />

1 Mid Span Compression<br />

Joint Assembly<br />

14 100 Nos 1400<br />

2 Suspension Assembly for<br />

GSS Wire 7/3.15 mm<br />

(2x5=10)<br />

10 300 Nos 3000<br />

3 Compression Type<br />

Tension Assembly for<br />

GSS Wire 7/3.15 mm<br />

with Terminal Jumpers<br />

( 25x2x 2=100)<br />

100 400 Nos 40000<br />

4 Flexible grounding Leads<br />

for Earthing GSS Wire<br />

(1x2x5+2x2x25)<br />

110 120 Nos 13200<br />

Total Cost for 10 Kms 57600<br />

Cost for 1 Km<br />

sheet 15<br />

5760


Annexure-10<br />

CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

QUANTITIES OF HARDWARES AND INSULATORS<br />

FOR 220 KV D/C LINE.<br />

Sr. No Description<br />

Qty<br />

Snow Zone<br />

A FOR SUSPENSION TOWERS<br />

I) Number <strong>of</strong> suspension Insulators Strings<br />

per 10 Kms ( Nos)<br />

30<br />

ii) Number <strong>of</strong> Discs per Suspension insulators<br />

Strings (Nos)<br />

16<br />

iii) Number <strong>of</strong> suspension Insulators Discs per<br />

10 Kms ( Nos)<br />

480<br />

iv) Number <strong>of</strong> suspension Insulators Discs per<br />

Kms ( Nos)<br />

48<br />

v) Number Suspension Hardware per 10 Kms<br />

( Sets)<br />

30<br />

vi) Number Suspension Hardware per Kms<br />

( Sets)<br />

3<br />

B FOR TENSION TOWERS<br />

I) Number <strong>of</strong> Tension Insulator Strings per 10<br />

Kms ( Nos)<br />

300<br />

ii) Number <strong>of</strong> Tension Discs per String ( Nos) 17<br />

iii) Number <strong>of</strong> Tension Discs per 10 Km<br />

( Nos)<br />

5100<br />

iv) Number <strong>of</strong> Tension Discs per Km ( Nos) 510<br />

v) Number <strong>of</strong> Tension Hardware per 10 Km<br />

( Sets)<br />

vi) Number <strong>of</strong> Tension Hardware per Km<br />

( Sets)<br />

Sheet 16<br />

300<br />

30


CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

SCHEDULE OF COST ANALYSIS FOR ERECTION<br />

CHARGES OF 220 KV D/C LINE ( SNOW ZONE)<br />

Annexure-11<br />

Sr. No Description Qty Rate Unit Amount in Rs<br />

1 Excavation and Backfill per<br />

Km<br />

335.73 185 Cu Mt 62110.05<br />

2 Concreting I/c Dewatering<br />

etc.<br />

55.37 4500 M^3 249165<br />

3 Erection <strong>of</strong> Towers 39.27 4000 MT 157066.67<br />

4 Stringing <strong>of</strong> Conductor 1 50000 Km 50000<br />

5 Stringing <strong>of</strong> Earth Wire 1 3800 Km 3800<br />

6 Earthing <strong>of</strong> Towers 3 1000 Nos 3000<br />

7 Fixing <strong>of</strong> Tower<br />

Accessories<br />

3 200 Nos 600<br />

Total Cost <strong>of</strong> Erection <strong>of</strong><br />

Towers per Km<br />

Sheet 17<br />

525741.72


KHOKSAR HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

Annexure-14<br />

SCHEDULE OF COST ANALYSIS FOR ERECTION<br />

CHARGES OF 220 KV S/C LINE ON D/C TOWERS (NON SNOW ZO<br />

Sr. No Description Qty Rate Unit Amount in Rs<br />

1 Excavation and<br />

Backfill per Km<br />

200.76 185 Cu Mt 37140.23<br />

2 Concreting I/c<br />

Dewatering etc.<br />

25.33 4500 M^3 113976<br />

3 Erection <strong>of</strong> Towers 27.13 4000 MT 108533.33<br />

4 Stringing <strong>of</strong> Conductor 1 25000 Km 25000<br />

5 Stringing <strong>of</strong> Earth<br />

Wire<br />

1 3800 Km 3800<br />

6<br />

3 1000 Nos 3000<br />

Earthing <strong>of</strong> Towers<br />

7 Fixing <strong>of</strong> Tower<br />

Accessories<br />

Total Cost <strong>of</strong><br />

Erection <strong>of</strong> Towers<br />

per Km<br />

Sheet 18<br />

3 200 Nos 600<br />

292049.56


ONE)


KHOKSAR HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

SCHEDULE OF COST ANALYSIS FOR TERMINAL<br />

EQUIPMENT AT TANDI<br />

Annexure-12<br />

Sr. No Description Qty Rate Unit Amount in<br />

Lacs<br />

1 220 KV SF6 Out doortype 3<br />

phase Circuit Breaker<br />

complete<br />

2 15 Nos 30<br />

2 220 KV Control and Relay<br />

Panels<br />

2 9.3 Nos 18.6<br />

3 220 KV 3 phase Isolators<br />

without Earth Swicth<br />

4 3.2 Sets 12.8<br />

4 220 KV 3 phase Isolators<br />

with Earth Swicth<br />

2 4.3 Sets 8.6<br />

5 220 KV LAs 6 0.78 Nos 4.68<br />

6 Multi Core Multi Ratio CTs 6 2 Nos 12<br />

7 Structures 60 0.32 MT 19.2<br />

8 Bus Bar Material and<br />

Insulators<br />

Lot LS 14<br />

9 <strong>Power</strong> and Control Cables<br />

and EI Works etc.<br />

Lot LS 24<br />

Sub Total-I 143.88<br />

10 Transportation @ 5%, Spares<br />

@ 3%, Insurance @ 1%, CST<br />

@ 4%,Civil Works @ 8% (<br />

Total 21% on Sub Total-I)<br />

30.21<br />

12 Erection and commissioning<br />

Charges @ 10% <strong>of</strong> Sub Total-<br />

I)<br />

14.39<br />

GRAND TOTAL<br />

Sheet 19<br />

188.48


CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

VEHICLES AND WORKSHOP MACHINERY<br />

Annexure-12<br />

Sr. No Description Qty Rate Unit Amount in Lacs<br />

1 7.5 Tons Trucks 2 8.5 Nos 17<br />

2 Jeep/ Car 2 3.5 Nos 7<br />

3 Maintenance van 1 4.5 Nos 4.5<br />

4 Workshop Equipment such as<br />

Lathe , Welding Sets, Drilling<br />

machines , <strong>Power</strong> Hacksaw etc.<br />

Lot LS 5.5<br />

TOTAL<br />

Sheet 20<br />

34


CHHATRU HYDRO-ELECTRIC-PROJECT (108 MW)<br />

COST ESTIMATES OF ELECTRO-MECHANICAL WORKS FOR PRE-FEASIBILITY REPORT<br />

Sl.No. Item Qty Rate Amount Excise Duty* Total<br />

Rs.(Lakhs) Rate Amount Amount<br />

(Rs. Lakhs) (Rs. Lakhs)<br />

1 2 3 4 5 6 7 8<br />

1 Generating Unit and 11 KV Bus Duct 36MW,<br />

428.6 RPM with net Head <strong>of</strong> 160 mtrs.<br />

3 Rs.5600/KW 6048.00 16% 967.68 7015.68<br />

2 Step-up transformer, 11/220KV,15MVA,single<br />

phase<br />

10 Rs.260/KVA 390.00 16% 62.40 452.40<br />

3 Auxiliary Electrical Equipment for <strong>Power</strong><br />

Stations (Except transformer) (5% <strong>of</strong> item 1).<br />

302.40 16% 48.38 350.78<br />

4 Auxiliary Equipment and Services for <strong>Power</strong><br />

Stations (5% <strong>of</strong> item-1)<br />

302.40 16% 48.38 350.78<br />

5 220 KV Switchyard GIS. 6 bays 300 Lacs/bay 1800.00 16% 288.00 2088.00<br />

6 Spares (5% <strong>of</strong> 1 and 3% <strong>of</strong> 2-5) 386.24 16% 61.80 448.04<br />

7 Sub-Total-1: 9229.04 10705.68<br />

8 Central Sales Tax ** 4% <strong>of</strong> item 1 to 6 428.23<br />

9 Transportation & Insurance 6% <strong>of</strong> item-7 642.34<br />

10 Erection and Commissioning 8% <strong>of</strong> item-7<br />

(except spares)<br />

820.61<br />

11 Sub-Total-2 : 12596.86<br />

12 Establishment, Contingency, other charges<br />

11% <strong>of</strong> item-7 (excluding duties)<br />

1015.20<br />

Grand Total :- 13612.06<br />

Say Rs. 13612 Lacs


DISCHARGE IN CUMECS<br />

350.00<br />

300.00<br />

250.00<br />

200.00<br />

150.00<br />

100.00<br />

50.00<br />

TIME IN HOURS<br />

0 1 2 3 4<br />

Effective rain fall in Cm<br />

CHHATRU HEP<br />

DESIGN FLOOD HYDROGRAPH FIG-A-II<br />

Qp = 291.59 Cumecs<br />

0.00<br />

0 2 4 6 8 10 12 14 16 18 20<br />

TIME IN HOURS<br />

Series1


CHHATRU HEP<br />

STANDARD PROJECT FLOOD HYDROGRAPH (SUG)<br />

TIME ORDINATE RAINFALL EXCESS IN CM. SUB TOTAL BASE TOTAL<br />

IN OF SUH DSRO IN FLOW FLOW IN<br />

HOURS IN 0.11 1.52 5.75 0.71 CUMECS IN CUMECS<br />

CUMECS CUMECS<br />

1 2 3 4 5 6 7 8 9 10<br />

1 0 0.00 0.00 2.40 2.40<br />

2 1 0.11 0.00 0.11 2.40 2.51<br />

3 7.5 0.79 1.52 0.00 2.30 2.40 4.70<br />

4 20.28 2.13 11.38 5.75 0.00 19.26 2.40 21.66<br />

5 40.25 4.23 30.76 43.14 0.71 78.83 2.40 81.23<br />

6 27.5 2.89 61.05 116.65 5.33 185.91 2.40 188.31<br />

7 15 1.58 41.71 231.50 14.40 289.19 2.40 291.59 PEAK<br />

8 8 0.84 22.75 158.17 28.58 210.34 2.40 212.74<br />

9 5.2 0.55 12.13 86.28 19.53 118.48 2.40 120.88<br />

10 3.5 0.37 7.89 46.01 10.65 64.92 2.40 67.32<br />

11 2.5 0.26 5.31 29.91 5.68 41.16 2.40 43.56<br />

12 1.55 0.16 3.79 20.13 3.69 27.78 2.40 30.18<br />

13 0.75 0.08 2.35 14.38 2.49 19.29 2.40 21.69<br />

14 0.3 0.03 1.14 8.92 1.78 11.86 2.40 14.26<br />

15 0 0.00 0.46 4.31 1.10 5.87 2.40 8.27<br />

16 0 0.00 0.00 1.73 0.53 2.26 2.40 4.66<br />

17 0.00 0.00 0.21 0.21 2.40 2.61<br />

18 0.00 0.00 0.00 2.40 2.40<br />

19 0.00 0.00 2.40 2.40<br />

20 0.00 2.40 2.40<br />

21 2.40 2.40<br />

22 0.00<br />

Flood for 1 in 100 years can be worked out from Fuller's formula as<br />

Q 100 =<br />

Q 50 (1+0.80 log T 100/1+0.80log T 50)<br />

Annexuure - 2<br />

= 321.38 Cumecs<br />

Snow contribution = = 342.09 Cumecs<br />

(Snow contribution has been taken as the maximum discharge in the flow series during<br />

the 2nd week <strong>of</strong> July)<br />

Total design flood = 663.468 Cumecs<br />

Say 665 Cumecs<br />

REM-<br />

ARKS


CHHATRU HEP Annexure - 1<br />

Cumputation <strong>of</strong> Equivalent slope <strong>of</strong> river Chenab in respect <strong>of</strong> Chhatru HEP<br />

S.No.<br />

Ruduced<br />

RD In K<br />

Level<br />

m<br />

in m<br />

leanth <strong>of</strong><br />

each<br />

segment<br />

Li in Km<br />

Height<br />

above (Di-1+Di) In<br />

Li X (Di-1+Di)<br />

Datum Di m<br />

in m<br />

1 2 3 4 5 6 7<br />

1 0.00 3405.00 0.00 0.00 0.00 0.00<br />

2 0.75 3420.00 0.75 15.00 15.00 11.25<br />

3 2.05 3440.00 1.30 35.00 50.00 65.00<br />

4 2.75 3460.00 0.70 55.00 90.00 63.00<br />

5 3.68 3480.00 0.93 75.00 130.00 120.90<br />

6 4.43 3500.00 0.75 95.00 170.00 127.50<br />

7 4.93 3520.00 0.50 115.00 210.00 105.00<br />

8 5.38 3540.00 0.45 135.00 250.00 112.50<br />

9 6.28 3560.00 0.90 155.00 290.00 261.00<br />

10 6.58 3580.00 0.30 175.00 330.00 99.00<br />

11 7.03 3600.00 0.45 195.00 370.00 166.50<br />

12 7.46 3620.00 0.43 215.00 410.00 176.30<br />

13 8.81 3640.00 1.35 235.00 450.00 607.50<br />

14 9.81 3680.00 1.00 275.00 510.00 510.00<br />

15 11.41 3720.00 1.60 315.00 590.00 944.00<br />

16 12.51 3760.00 1.10 355.00 670.00 737.00<br />

17 14.11 3800.00 1.60 395.00 750.00 1200.00<br />

18 16.11 3840.00 2.00 435.00 830.00 1660.00<br />

19 17.91 3880.00 1.80 475.00 910.00 1638.00<br />

20 23.91 3920.00 6.00 515.00 990.00 5940.00<br />

21 27.91 3960.00 4.00 555.00 1070.00 4280.00<br />

22 31.41 4000.00 3.50 595.00 1150.00 4025.00<br />

Total 22849.45<br />

S = Li X (Di-1+Di)/ L 2 = 23.16<br />

m/Km<br />

Datum = 3405 m I,e R.L. <strong>of</strong> river bed at point <strong>of</strong> study.


ESTIMATE OF DESIGN FLOOD FOR CHHATRU HEP<br />

UNIT HYDROGRAPH METHOD<br />

COMPUTATION OF ONE HOUR SYNTHETIC UNIT GRAPH<br />

Ref;- FLOOD ESTIMATION REPORT FOR WESTERN HIMALAYAS - ZONE 7 (CWC)<br />

i) Name <strong>of</strong> zone Western Himalayas<br />

ii) Name <strong>of</strong> river Chandra River in Chenab basin<br />

iii) Shape <strong>of</strong> Catchment Leaf Shaped<br />

iv) Location Lat. 32°-18'-08"<br />

Long. 77°-24'-39"<br />

v) Topography Steep slope<br />

Step -1 Physiographic Parameters<br />

1 Permanent Snow Line 4000 m<br />

2 Total catchment area at diversion site 1583 Sq. Km<br />

(Ref. Drg. No Chhatru-PR-3)<br />

3 Permaqnent snow covered area above EL4000m. 1535 Sq.km.<br />

4. Catchment area contribution to run-<strong>of</strong>f ( Ref.FIG - A) 48 Sq.km.<br />

5. Length <strong>of</strong> the longest (Stream) ( L ) 31.41 Km<br />

6 Length <strong>of</strong> the longest (Stream) from a point<br />

apposit to C.G. <strong>of</strong> catchment to point <strong>of</strong> study (LC) 11.80 Km<br />

7 Equivalent stream slope (S) 23.16 m/Km<br />

(Refer Annexure-1)<br />

Step -2:1-hr. Synthetic unit graph<br />

I) tp = 2.498(LxLC/S) 0.,156<br />

Annexure V - 1<br />

3.85 hrs<br />

4.00 hr<br />

and taken 0.5 hr. less than the completed value for<br />

highest peak. = 3.50 hrs<br />

ii) qp = 1.048(tp) -0.178<br />

0.84 Cum/SqKm<br />

iii) W50 = 1.954x(LxLC/S) 0.099<br />

2.57 hrs<br />

iv) W75= 0.972x(LxLC/S) 0.124<br />

1.37 hrs<br />

v) Wr50= 0.189x(W50) 1.769<br />

1.00 hrs<br />

vi) Wr75= 0.419x(W75) 1.246<br />

0.62 hrs<br />

vii) TB= 7.845x(tp) 0.453<br />

Taking tp in multiple <strong>of</strong> 1-0 hr. I.e.<br />

13.84 hrs<br />

viii) Qp = qpxA 40.25 Cumecs<br />

Estimated parameter <strong>of</strong> unit graph in Step-1 were plotted on a graph paper as shown in<br />

Fig. A-I. The plotted points were joined to draw synthetic unit graph. The discharge<br />

ordinates(Qi) <strong>of</strong> the unit graph at ti=tr=1 hr. interval were summed up and multiplied by<br />

tr=1 and compared with the volume <strong>of</strong> 1.00cm direct run-<strong>of</strong>f depth over the catchment<br />

computed from the formula.<br />

Q= Axd/0.36xtr<br />

Where A = Catchment area in Sq.km.<br />

d= 1.0m depth<br />

ti= tr(the unit duration <strong>of</strong> the UG)=1 hr.<br />

The following limb <strong>of</strong> the <strong>hydro</strong>graph is suitably modified without altering the points <strong>of</strong><br />

synthetic parameters.<br />

133 Cumecs


Step-3 Estimation <strong>of</strong> design storms<br />

a) Design storm duration<br />

The design storm duration TD has been adopted as 1,1x1xtp<br />

TD = 1.1xtp<br />

TD = 1.1x3.5 3.85 Say 4 Hrs<br />

b) Estimation <strong>of</strong> point rain fall and areal rainfall for storm duration<br />

Catchment under study was located on Plate-9, P=-58, showing 50 year 24 hr./ point<br />

rainfal. The point fainfall was found to be = 16 cm.<br />

Coversion factor read from Fig. 3, P-67 to convert 50-yr. 24 hr. point rainfall to<br />

50 yr. 4 hr. point rainfall is = 0.65<br />

Hence 50 year 4 hr, point rainfall is = 10.40 cm.<br />

Areal reduction factor = 0.97 corresp. to the C.A. = 48<br />

Sqkm. For TD = 4 hr. was interpolated from<br />

Annexure-4.2. P-42,for conversion <strong>of</strong> point rainfall to areal rainfall.<br />

50Year 4 hr. Areal rainfall worked out to be = 10.08 cm.<br />

The 50-yr. 4 hr. areal rainfall spilt in to 1-hr. rainfall increments using time<br />

distribution co-efficient given in Annexure-4.1, P-41.<br />

A design loss rate <strong>of</strong> 0.20 cm/hr. as recommended in para 3.5,P-15<br />

has been used to get effective rainfall hyetograph.<br />

Duration<br />

Hourly effective rainfall increments Table - 1<br />

Distribution<br />

co-efficient<br />

increment<br />

1 2 3 4 5 6<br />

1 0.62 6.25 6.25 0.50 5.75<br />

2 0.82 8.27 2.02 0.50 1.52<br />

3 0.94 9.48 1.21 0.50 0.71<br />

4 1.00 10.08 0.61 0.50 0.11<br />

Step-4 Estimation <strong>of</strong> base flow<br />

Taking design base flow <strong>of</strong> = 0.05 cumecs per Sq.km. as recommended.<br />

in para 3.6 P-15, the base flow as ground water estimated as<br />

2.4 cumecs for 48 Sq.km. catchment area.<br />

Step-5 Estimation <strong>of</strong> 50 year flood<br />

Storm<br />

rainfall<br />

(cm)<br />

a) Compputaiton <strong>of</strong> flood peak<br />

Rainfall<br />

increments<br />

(cm)<br />

Loss per<br />

hr. (cm)<br />

Effective rainfall<br />

increments<br />

For estimation <strong>of</strong> the peak discharge , the effective rainfall increments were<br />

re-arranged against ordinates such that the maximum effective rainfall<br />

is placed against the maximum U.G. oridnate,next lower value <strong>of</strong> effective<br />

rainfall against next lower value <strong>of</strong> U.G. ordinate and so on as shown in<br />

column (2) in Table - 2.Sum <strong>of</strong> the product <strong>of</strong> U.G. ordinates and effective<br />

rainfall increments gives total direct surface run <strong>of</strong>f to which<br />

base flow is added to get total peak discharge.


50 year Peak flood Table - 2<br />

U.G.<br />

1 hr.<br />

Time hrs.<br />

ordinates<br />

effective<br />

Direct run-<strong>of</strong>f<br />

cumecs<br />

rainfall<br />

1 2 3 4<br />

1 20.28 0.71 14.40<br />

2 40.25 5.75 231.50<br />

3 27.50 1.52 41.71<br />

4 15.00 0.11 1.58<br />

Total 289.19<br />

Base flow 2.40<br />

50 year flood peak 291.59<br />

Say 292 Cumecs<br />

b) Computation <strong>of</strong> design flood <strong>hydro</strong>graph<br />

Effective rainfall increments shown in col. 3 <strong>of</strong> table-2 in step 5. above were<br />

reversed to obtain critical sequence as shown below<br />

( Critical sequence <strong>of</strong> rain fall )<br />

Time in hrs. Crirital 1-hr. effective rainfall sequence cms.<br />

1 0.11<br />

2 1.52<br />

3 5.75<br />

4 0.71<br />

Table - 3.<br />

For computation <strong>of</strong> design flood <strong>hydro</strong>graph, the U.G. ordinates were tabulated in<br />

Col. (2) <strong>of</strong> Annexure-2. The critical sequence <strong>of</strong> effective rainfall increments were<br />

entered in col. 3 to 6 horizontally. Direct run <strong>of</strong> resulting from each <strong>of</strong> the<br />

effective rainfall increments was obntained by multiplying effective rainfall<br />

depths with the synthetic U.G. ordinates in col. 2 and direct run <strong>of</strong>f<br />

values were entered in columns against each unit with a successive lag <strong>of</strong> 1 hr.<br />

since the unit duration <strong>of</strong> S.U.G. is 1 hr. Direct run <strong>of</strong>f values are shown in col. 3 to 6.<br />

Direct run <strong>of</strong>f values were added horizontally and total direct run<strong>of</strong>fis shown in col. 7. Adding<br />

Adding total base flow <strong>of</strong> = 2.40 cumecs ( col.8) .<br />

Design flood <strong>hydro</strong>graph ordinates in col.9 were obtained. Design<br />

flood <strong>hydro</strong>graph was plotted against time as shown fig. A-II<br />

The peak obtained was = 291.59 cumecs for 1 in 50 years<br />

which talies with the peak shown in Table-2<br />

Flood for 1 in 100 years can be worked out from Fuller's formula<br />

and has been worked out as = 321.38 Cumecs (i)<br />

Snow contribution = = 342.09 Cumecs (ii)<br />

(Snow contribution has been taken as the maximum discharge in flow series during<br />

the 2nd week <strong>of</strong> July)<br />

The total design flood (i) + (ii) 663.47 cumecs<br />

The design flood has also been worked out by Gumble's flood frequency method<br />

considering top eight flood events <strong>of</strong> G&D site w.e.f. June 1973 to May 2001 as per data<br />

collected from CWC, Chenab Divn, Jammu vide letter Dt.13/1/04 (copy encl. Annexure. 3)<br />

which is = 1377.59 Cumecs for 1000 years (Annxure-4)<br />

However design flood <strong>of</strong> 1500 cumecs has been considered for computation<br />

<strong>of</strong> HFL for designing the diversion stucture <strong>of</strong> this <strong>project</strong>


1 HOUR SYNTHETIC UG<br />

ORDINATES<br />

1 HOUR SYNTHETIC<br />

UG PARAMETERS<br />

CA = 48.00 Sq. Km. 0 0<br />

tr = 1.00 Hr 1 1<br />

Qp = 40.25 Cumecs 2 7.5<br />

qp = 0.84 Hrs 3 20.28<br />

tp = 3.50 Hrs 4 40.25<br />

Tm = 4.00 Hrs 5 27.5<br />

TB = 13.84 Hrs 6 15<br />

W50 = 2.57 Hrs 7 8<br />

W75 = 1.37 Hrs 8 5.2<br />

Wr50= 1.00 Hrs 9 3.5<br />

Wr75 = 0.62 Hrs 10 2.5<br />

d = 1.00 Cm 11 1.55<br />

12 0.75<br />

13 0.3<br />

Q = A X d /tr X0,36 14 0<br />

133.33 Cumecs TOTAL 133.33


CHHATRU HEP ANNEXURE-4 ( i )<br />

DESIGN FLOOD - GUMBLE'S FLOOD FREQUENCY ANALYSIS<br />

C.A AT GHOUSAL 2406.25 SqKm<br />

C.A AT CHHATRU 1583 SqKm<br />

C.F. 0.658<br />

Sr. No. Date/ Year Max.Flood Discharge Max.Flood Discharge Max.Flood Discharge Q' - Q (Q ' - Q )^2<br />

in Cumecs at G& D in Cumecs at Q in Cumecs in<br />

Site Ghousal Diversion Site Descending order (Cumecs) (Cumecs)<br />

1 8.8.78 625 411 611 -121.870 14852.40<br />

2 25.7.87 636 418 579 -90.293 8152.77<br />

3 21.7.88 631 415 570 -81.082 6574.37<br />

4 29.7.89 866 570 461 28.124 790.96<br />

5 19.7.91 700 461 445 43.913 1928.34<br />

6 6.7.95 676 445 418 70.228 4931.92<br />

7 8.7.98 928 611 415 73.517 5404.75<br />

8 10.7.99 880 579 411 77.464 6000.70<br />

TOTAL 3909 0 48636<br />

MEAN DISCHARGE Q ' 488.63<br />

TOTAL NO. OF YEARS n 8<br />

Standard deviation d = (Q ' - Q )/n-1<br />

= 83.35<br />

Co-efficient <strong>of</strong> variation Cv = d / Q'<br />

Cv = 0.1706<br />

For 8 years period<br />

Reduced standard deviation Sn = 0.9496 Refer book Irrigation Engg &<br />

Reduced mean Yn = 0.4952 Hyd. Structure by S.K.Garg<br />

Q max. = Q' (1+Cv*(Y-Yn)/Sn) Page No.441<br />

= 488.63(1+0.1706*(Y-0.4952)/0.9496) 445.16<br />

Q max. = 445.16+87.78Y 87.78


CHHATRU HEP ANNEXURE-4 ( ii )<br />

COMPUTATION OF DESIGN FLOOD<br />

RETURN Xt = REDUCED VARIATE MAX. FLOOD INST. FLOOD PROBABILITY<br />

PERIOD log log( T/T-1) Y= Qmax = 1.15 TIMES OF<br />

T in Years 0.834032 - 2.302585Xt 445.16+87.78Y MAX.FLOOD % AGE<br />

10000 -4.362 10.878 1400.062 1610.07 0.01<br />

5000 -4.061 10.185 1339.213 1540.10 0.02<br />

1000 -3.362 8.575 1197.902 1377.59 0.1<br />

500 -3.061 7.882 1137.013 1307.57 0.2<br />

200 -2.662 6.964 1056.449 1214.92 0.5<br />

100 -2.360 6.268 995.384 1144.69 1<br />

50 -2.057 5.570 934.095 1074.21 2<br />

25 -1.751 4.867 872.350 1003.20 4<br />

10 -1.340 3.918 789.120 907.49 10<br />

Considering Design Flood <strong>of</strong> 1000 Years Return Period to be SPF<br />

which works Out to be = 1377.59 Cumecs


DISCHARGE (CUMECS)<br />

45<br />

40<br />

35<br />

30<br />

25<br />

20<br />

15<br />

10<br />

5<br />

0<br />

tr<br />

Wr50=1.00<br />

Hrs<br />

Tm=4 hrs CHHATRU HEP<br />

Wr75=0.62<br />

Hrs<br />

1 cm rainfall excess<br />

tp=3,50 HRS<br />

TB =13.84 Hrs<br />

SYNTHETIC UNIT HYDROGRAPH FIG-A-II<br />

Qp=40.25 Cumecs<br />

W 75= 1.37Hrs<br />

W 50 =2.57 Hrs<br />

0 2 4 6 8 10 12 14 16<br />

TIME (HOURS)


COMPUTATION NO- Chhatru HEP -PR-SS <strong>chhatru</strong> HEP<br />

REF DRG. NO-<strong>chhatru</strong>-PFR-<br />

CALCULATIONS OF UPSURGE & DOWNSURGE IN SURGE SHAFT<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

BASIC PARAMETERS 1) DIAMETER OF HRT =<br />

2) LENGTH OF HRT =<br />

3) DESIGN DISCHARGE =<br />

4) VELOCITY IN HRT =<br />

5) DIAMETER OF MAIN<br />

PENSTOCK =<br />

6) NO. OF MAIN PENSTOCK<br />

7) DIAMETER OF BRANCH<br />

PENSTOCK =<br />

8) NO.OF BRANCH PENSTOC<br />

9) VELOCITY IN PENSTOCK<br />

10) DIAMETER OF SURGE<br />

SHAFT =<br />

11) SURGE HT. NEGLECTIN<br />

LOSSES = Z* =<br />

12) HEAD LOSS IN ORIFIC<br />

MAXIMUM =<br />

MINIMUM =<br />

AVERAGE =<br />

13) RUGOSITY COEFFICIEN<br />

MAXIMUM =<br />

MINIMUM =<br />

AVERAGE =<br />

14) FRICTION COEFFICIEN<br />

MAXIMUM =<br />

MINIMUM =<br />

AVERAGE =<br />

15) HEAD LOSS IN HRT =h<br />

MAXIMUM =<br />

MINIMUM =<br />

AVERAGE =<br />

16) COEFFICIENT OF HYDR<br />

MAXIMUM =<br />

MINIMUM =<br />

AVERAGE =<br />

17) COEFFICIENT OF RESI<br />

MAXIMUM =<br />

MINIMUM =<br />

AVERAGE =<br />

18) TIME INTERVAL<br />

IN SECONDS =


CASE - I MAXIMUM UPSURGE FOR TOTAL REJECTION ( 100 - 0 )%<br />

AT MAXIMUM RESERVOIR LEVEL & MINIMUM LOSSES IN HRT<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

TIME VELOCITY UPSURGE CHANGE TOTAL V1^2 x<br />

INTERVAL IN HRT Z IN UPSUR- UPSURGE (B+N+1/2g)<br />

dt in V1 IN GE z+dz =Z<br />

sec. M/SEC. dz<br />

1 2 3 4 5 6<br />

0.00 3.64 -9.84 0.00 -9.84 0.00<br />

10.00 3.64 -9.84 4.20 -5.64 37.93<br />

20.00 3.15 -5.64 3.64 -2.00 28.44<br />

30.00 2.75 -2.00 3.18 1.18 21.69<br />

40.00 2.40 1.18 2.78 3.96 16.59<br />

50.00 2.09 3.96 2.42 6.38 12.58<br />

60.00 1.81 6.38 2.09 8.47 9.38<br />

70.00 1.54 8.47 1.78 10.25 6.79<br />

80.00 1.28 10.25 1.48 11.73 4.71<br />

90.00 1.03 11.73 1.19 12.92 3.06<br />

100.00 0.79 12.92 0.92 13.84 1.80<br />

110.00 0.56 13.84 0.64 14.48 0.89<br />

120.00 0.32 14.48 0.37 14.85 0.30<br />

130.00 0.10 14.85 0.11 14.96 0.03<br />

140.00 -0.13 14.96 -0.15 14.81 0.05<br />

150.00 -0.36 14.81 -0.41 14.40 0.36<br />

160.00 -0.58 14.40 -0.67 13.73 0.96<br />

170.00 -0.80 13.73 -0.92 12.81 1.84<br />

180.00 -1.02 12.81 -1.18 11.63 2.99<br />

190.00 -1.24 11.63 -1.44 10.19 4.42<br />

200.00 -1.46 10.19 -1.69 8.50 6.14<br />

210.00 -1.68 8.50 -1.95 6.56 8.13<br />

220.00 -1.90 6.56 -2.20 4.36 10.41


CASE - II MINIMUM DOWNSURGE AT MDDL OF RESERVOIR AT MINIMUM<br />

HEAD LOSSES IN HRT (100-0-33.33)% , V1 = 3.64<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

TIME VELOCITY MAXIMUM<br />

INTERVAL IN HRT Z in DOWN V1^2(-B-N+1/<br />

COMPUTATION NO- <strong>chhatru</strong> HEP -PR-SS<br />

REF DRG. NO-chhBHR-<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

1 2 3 4 5 6<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

140.00 -0.13 14.96 -0.15 14.81 -0.05<br />

150.00 -0.36 14.81 -0.41 14.40 -0.35<br />

160.00 -0.57 14.40 -0.66 13.75 -0.89<br />

170.00 -0.76 13.75 -0.88 12.87 -1.60<br />

180.00 -0.93 12.87 -1.08 11.79 -2.40<br />

190.00 -1.07 11.79 -1.24 10.55 -3.19<br />

200.00 -1.18 10.55 -1.37 9.18 -3.88<br />

210.00 -1.26 9.18 -1.46 7.72 -4.42<br />

220.00 -1.31 7.72 -1.52 6.20 -4.78<br />

230.00 -1.34 6.20 -1.54 4.66 -4.94<br />

240.00 -1.33 4.66 -1.54 3.12 -4.90<br />

250.00 -1.30 3.12 -1.51 1.61 -4.71<br />

260.00 -1.26 1.61 -1.45 0.16 -4.38<br />

270.00 -1.19 0.16 -1.38 -1.22 -3.94<br />

280.00 -1.12 -1.22 -1.29 -2.51 -3.45<br />

290.00 -1.03 -2.51 -1.19 -3.70 -0.73<br />

300.00 -0.96 -3.70 -1.11 -4.81 -0.64


CASE - II MINIMUM DOWNSURGE AT MDDL OF RESERVOIR AT MINIMUM<br />

Contd. HEAD LOSSES IN HRT . (100-0-33.33<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

TIME VELOCITY MAXIMUM -BV1^2<br />

INTERVAL IN HRT DZ in DOWN -N(V1-V2)^2<br />

dt in V1 IN m Z in m SURGE +1/2G*V1^2<br />

sec. M/SEC. Z+DZ (3+4)<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

1 2 3 4 5 6<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

240.00 -1.33 -3.66 3.12 -0.54 -28.47<br />

250.00 -0.89 -3.15 -0.54 -3.69 -19.91<br />

260.00 -0.54 -2.74 -3.69 -6.43 -14.13<br />

270.00 -0.23 -2.38 -6.43 -8.81 -9.97<br />

280.00 0.06 -2.06 -8.81 -10.87 -6.87<br />

290.00 0.32 -1.75 -10.87 -12.62 -4.56<br />

300.00 0.58 -1.45 -12.62 -14.07 -2.90<br />

310.00 0.84 -1.15 -14.07 -15.22 -1.82<br />

320.00 1.10 -0.85 -15.22 -16.07 -1.29<br />

330.00 1.36 -0.55 -16.07 -16.62 -1.31<br />

340.00 1.63 -0.24 -16.62 -16.86 -1.95<br />

350.00 1.91 0.09 -16.86 -16.77 -3.28<br />

360.00 2.22 0.44 -16.77 -16.33 -5.44<br />

370.00 2.55 0.82 -16.33 -15.51 -8.65<br />

380.00 2.91 1.24 -15.51 -14.27 -13.28<br />

390.00 3.33 1.72 -14.27 -12.55 -19.93<br />

400.00 3.82 2.29 -12.55 -10.26 -29.63


~~~<br />

5.10 METRES<br />

6500.00 METRES<br />

75.00 CUMECS.<br />

3.64 M/Sec.<br />

4.70 METRES<br />

K = 1.00 NOS.<br />

2.70 METRES<br />

CK = 3.00 NOS.<br />

K =<br />

MAIN = 4.33 M/Sec.<br />

BRANCH = 4.37 M/Sec.<br />

15.00 METRES<br />

NG<br />

CE =hor<br />

NT =n<br />

NT =f<br />

hf<br />

31.82 METRES<br />

30.19 METRES<br />

27.42 METRES<br />

29.20 METRES<br />

0.02<br />

0.01<br />

0.01<br />

0.02<br />

0.01<br />

0.01<br />

15.38 METRES<br />

9.84 METRES<br />

13.40 METRES<br />

RAULIC LOSSES IN HRT =B<br />

1.16 CASE-I<br />

0.74<br />

1.01<br />

CASE-II(i)<br />

ISTANCE FOR ORIFICE =N<br />

2.28<br />

2.07 CASE-II(ii)<br />

2.21<br />

10.00


~~~<br />

COL.(5+6) dv=-g/ L dt<br />

*Col.7<br />

7 8<br />

0.00 0.00<br />

32.30 -0.49<br />

26.44 -0.40<br />

22.87 -0.35<br />

20.54 -0.31<br />

18.96 -0.29<br />

17.85 -0.27<br />

17.04 -0.26<br />

16.44 -0.25<br />

15.98 -0.24<br />

15.64 -0.24<br />

15.37 -0.23<br />

15.15 -0.23<br />

14.99 -0.23<br />

14.86 -0.22<br />

14.76 -0.22<br />

14.69 -0.22<br />

14.64 -0.22<br />

14.62 -0.22<br />

14.62 -0.22<br />

14.64 -0.22<br />

14.69 -0.22<br />

14.77 -0.22


m/sec. v2 = 0.00 m/sec.<br />

~~~<br />

dv= -g/l dtx<br />

COL. Col.7<br />

~~~<br />

~~~<br />

7 8<br />

14.86 -0.22<br />

14.05 -0.21<br />

12.85 -0.19<br />

11.26 -0.17<br />

9.39 -0.14<br />

7.36 -0.11<br />

5.30 -0.08<br />

3.30 -0.05<br />

1.42 -0.02<br />

-0.28 0.00<br />

-1.79 0.03<br />

-3.10 0.05<br />

-4.22 0.06<br />

-5.17 0.08<br />

-5.96 0.09<br />

-4.43 0.07<br />

-5.44 0.08


0.00


V1 = 1.34 m/sec. v2 = 1.46 m/sec.<br />

~~~<br />

dv= -g/l dtx<br />

COL. *Col.7<br />

(5+6)<br />

~~~<br />

~~~<br />

7 8<br />

-29.01 0.44<br />

-23.60 0.36<br />

-20.56 0.31<br />

-18.78 0.28<br />

-17.74 0.27<br />

-17.18 0.26<br />

-16.97 0.26<br />

-17.04 0.26<br />

-17.36 0.26<br />

-17.93 0.27<br />

-18.81 0.28<br />

-20.05 0.30<br />

-21.77 0.33<br />

-24.16 0.36<br />

-27.55 0.42<br />

-32.48 0.49<br />

0.00 0.00


(0-33.33)% (0-100)% (100-0)%<br />

V1 = 0.00 0.00<br />

V2 = 4.37 4.33<br />

V1 = 1.34 3.64<br />

V2 = 1.46 0.00<br />

VI 1.63<br />

VII 1.46


COMPUTATION NO-<br />

REF DRG. NO-UHL<br />

CALCULATIONS OF<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

BASIC PARAMETER


CASE - I<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

TIME VELOCITY<br />

INTERVAL IN HRT<br />

dt in V1 IN<br />

sec. M/SEC.<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

1 2<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

0.00 3.05<br />

10.00 3.05<br />

20.00 2.72<br />

30.00 2.44<br />

40.00 2.21<br />

50.00 2.00<br />

60.00 1.81<br />

70.00 1.64<br />

80.00 1.47<br />

90.00 1.32<br />

100.00 1.16<br />

110.00 1.02<br />

120.00 0.88<br />

130.00 0.74<br />

140.00 0.60<br />

150.00 0.46<br />

160.00 0.33<br />

170.00 0.20<br />

180.00 0.07<br />

190.00 -0.06<br />

200.00 -0.19<br />

210.00 -0.32<br />

220.00 -0.45


CASE - II<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

TIME VELOCITY<br />

INTERVAL IN HRT<br />

COMPUTATION NO-<br />

REF DRG. NO-UHL<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

1 2<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

190.00 -0.06<br />

200.00 -0.19<br />

210.00 -0.32<br />

220.00 -0.44<br />

230.00 -0.55<br />

240.00 -0.65<br />

250.00 -0.74<br />

260.00 -0.82<br />

270.00 -0.88<br />

280.00 -0.93<br />

290.00 -0.97<br />

300.00 -0.99<br />

310.00 -1.00<br />

320.00 -1.00<br />

330.00 -0.98<br />

340.00 -0.96<br />

350.00 -0.93


-0.89<br />

-0.89


CASE - II<br />

Contd.<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

TIME VELOCITY<br />

INTERVAL IN HRT<br />

dt in V1 IN<br />

sec. M/SEC.<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

1 2<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

320.00 -1.00<br />

330.00 -0.78<br />

340.00 -0.56<br />

350.00 -0.36<br />

360.00 -0.15<br />

370.00 0.06<br />

380.00 0.26<br />

390.00 0.47<br />

400.00 0.68<br />

410.00 0.90<br />

420.00 1.12<br />

430.00 1.35<br />

440.00 1.59<br />

450.00 1.84<br />

460.00 2.11<br />

470.00 2.40<br />

480.00 2.71


- UHL STAGE-III-PR-SS-<br />

L-PR-15<br />

F UPSURGE & DOWNSURGE IN SURGE SHAFT<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

RS 1) DIAMETER OF HRT =<br />

2) LENGTH OF HRT =<br />

3) DESIGN DISCHARGE =<br />

4) VELOCITY IN HRT =<br />

5) DIAMETER OF MAIN<br />

PENSTOCK =<br />

6) NO. OF MAIN PENSTOCK =<br />

7) DIAMETER OF BRANCH<br />

PENSTOCK =<br />

8) NO.OF BRANCH PENSTOCK =<br />

9) VELOCITY IN PENSTOCK =<br />

10) DIAMETER OF SURGE<br />

SHAFT =<br />

11) SURGE HT. NEGLECTING<br />

LOSSES = Z* =<br />

12) HEAD LOSS IN ORIFICE =hor<br />

MAXIMUM =<br />

MINIMUM =<br />

AVERAGE =<br />

13) RUGOSITY COEFFICIENT =n<br />

MAXIMUM =<br />

MINIMUM =<br />

AVERAGE =<br />

14) FRICTION COEFFICIENT =f<br />

MAXIMUM =<br />

MINIMUM =<br />

AVERAGE =<br />

15) HEAD LOSS IN HRT =hf<br />

MAXIMUM =<br />

MINIMUM =<br />

AVERAGE =<br />

MAIN =<br />

BRANCH =<br />

16) COEFFICIENT OF HYDRAULIC LOSSES IN HRT<br />

MAXIMUM =<br />

MINIMUM =<br />

AVERAGE =<br />

17) COEFFICIENT OF RESISTANCE FOR ORIFICE =<br />

MAXIMUM =<br />

18) TIME INTERVAL<br />

IN SECONDS =<br />

MINIMUM =<br />

AVERAGE =


MAXIMUM UPSURGE FOR TOTAL REJECTION ( 100 - 0 )%<br />

AT MAXIMUM RESERVOIR LEVEL & MINIMUM LOSSES IN HRT<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

UPSURGE CHANGE TOTAL V1^2 x COL.(5+6)<br />

Z IN UPSUR- UPSURGE (B+N+1/2g)<br />

GE z+dz =Z<br />

dz<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

3 4 5 6 7<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

-12.65 0.00 -12.65 0.00 0.00<br />

-12.65 3.11 -9.54 40.33 30.79<br />

-9.54 2.77 -6.77 31.95 25.18<br />

-6.77 2.49 -4.28 25.82 21.54<br />

-4.28 2.25 -2.03 21.10 19.07<br />

-2.03 2.04 0.01 17.31 17.32<br />

0.01 1.85 1.86 14.20 16.05<br />

1.86 1.67 3.52 11.59 15.11<br />

3.52 1.50 5.02 9.37 14.40<br />

5.02 1.34 6.36 7.48 13.85<br />

6.36 1.19 7.55 5.86 13.41<br />

7.55 1.04 8.59 4.48 13.07<br />

8.59 0.89 9.48 3.32 12.80<br />

9.48 0.75 10.23 2.34 12.57<br />

10.23 0.61 10.84 1.55 12.39<br />

10.84 0.47 11.31 0.93 12.24<br />

11.31 0.34 11.65 0.47 12.12<br />

11.65 0.20 11.85 0.17 12.02<br />

11.85 0.07 11.92 0.02 11.94<br />

11.92 -0.06 11.86 0.02 11.87<br />

11.86 -0.20 11.66 0.16 11.82<br />

11.66 -0.33 11.33 0.45 11.78<br />

11.33 -0.46 10.88 0.87 11.75


MINIMUM DOWNSURGE AT MDDL OF RESIRVOIR AT MAXIMUM<br />

HEAD LOSSES IN HRT (100-0-50)% , V1 = 3.05 m/sec. v2 = 0.<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

MAXIMUM<br />

Z in DOWN V1^2(-B-N+1/2G COL.<br />

- UHL STAGE-III-PR-SS-<br />

L-PR-16<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

3 4 5 6 7<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

11.92 -0.06 11.86 -0.01 11.87<br />

11.86 -0.20 11.66 -0.13 11.53<br />

11.66 -0.32 11.34 -0.34 10.99<br />

11.34 -0.45 10.89 -0.65 10.24<br />

10.89 -0.56 10.33 -1.03 9.30<br />

10.33 -0.66 9.67 -1.44 8.23<br />

9.67 -0.75 8.91 -1.86 7.05<br />

8.91 -0.83 8.08 -2.27 5.81<br />

8.08 -0.90 7.18 -2.63 4.55<br />

7.18 -0.95 6.23 -2.94 3.29<br />

6.23 -0.98 5.25 -3.17 2.08<br />

5.25 -1.01 4.24 -3.32 0.92<br />

4.24 -1.02 3.22 -3.39 -0.17<br />

3.22 -1.02 2.21 -3.38 -1.17<br />

2.21 -1.00 1.20 -3.29 -2.09<br />

1.20 -0.98 0.22 -3.14 -2.92<br />

0.22 -0.95 -0.72 -2.94 -3.66


-0.65


MINIMUM DOWNSURGE AT MDDL OF RESERVOIR AT MAXIMUM<br />

HEAD LOSSES IN HRT (100-0-50)% , V1 = 0.92 m/sec. v2 = 2.<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

MAXIMUM -BV1^2<br />

DZ in DOWN -N(V1-V2)^2 COL.<br />

m Z in m SURGE +1/2G*V1^2 (5+6)<br />

Z+DZ (3+4)<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

3 4 5 6 7<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

-3.28 3.22 -0.06 -20.21 -20.27<br />

-3.02 -0.06 -3.08 -16.49 -19.57<br />

-2.77 -3.08 -5.85 -13.30 -19.15<br />

-2.53 -5.85 -8.38 -10.55 -18.93<br />

-2.30 -8.38 -10.68 -8.20 -18.88<br />

-2.06 -10.68 -12.74 -6.22 -18.96<br />

-1.82 -12.74 -14.56 -4.59 -19.15<br />

-1.58 -14.56 -16.14 -3.32 -19.46<br />

-1.33 -16.14 -17.47 -2.41 -19.88<br />

-1.08 -17.47 -18.55 -1.88 -20.43<br />

-0.82 -18.55 -19.37 -1.75 -21.12<br />

-0.56 -19.37 -19.93 -2.07 -22.00<br />

-0.28 -19.93 -20.21 -2.88 -23.09<br />

0.01 -20.21 -20.20 -4.26 -24.46<br />

0.32 -20.20 -19.88 -6.32 -26.20<br />

0.65 -19.88 -19.23 -9.19 -28.42<br />

1.01 -19.23 -18.22 -13.10 0.00


4.15 METRES<br />

9000.00 METRES<br />

41.30 CUMECS.<br />

3.05 M/Sec.<br />

3.40 METRES<br />

1.00 NOS.<br />

2.40 METRES<br />

2.00 NOS.<br />

4.55 M/Sec.<br />

4.56 M/Sec.<br />

13.00 METRES<br />

29.52 METRES<br />

30.76 METRES<br />

27.20 METRES<br />

29.49 METRES<br />

0.02<br />

0.01<br />

0.01<br />

0.02<br />

0.01<br />

0.02<br />

19.77 METRES<br />

12.65 METRES<br />

17.22 METRES<br />

=B<br />

2.12 CASE-I V1 =<br />

1.36<br />

1.85<br />

V2 =<br />

CASE-II V1 =<br />

=N V2 =<br />

3.30<br />

2.92<br />

3.16<br />

10.00


dv=-g/ L dt<br />

*Col.7<br />

8 UPSURGE<br />

0.00 0.00<br />

-0.34 0.00<br />

-0.27 0.00<br />

-0.23 0.00<br />

-0.21 0.00<br />

-0.19 0.00<br />

-0.17 0.00<br />

-0.16 0.00<br />

-0.16 0.00<br />

-0.15 0.00<br />

-0.15 0.00<br />

-0.14 0.00<br />

-0.14 0.00<br />

-0.14 0.00<br />

-0.14 0.00<br />

-0.13 0.00<br />

-0.13 0.00<br />

-0.13 0.00<br />

-0.13 11.92<br />

-0.13 11.86<br />

-0.13 11.66<br />

-0.13 11.33<br />

-0.13 10.88


00 m/sec.<br />

dv= -g/l dtx<br />

Col.7<br />

8<br />

-0.13<br />

-0.13<br />

-0.12<br />

-0.11<br />

-0.10<br />

-0.09<br />

-0.08<br />

-0.06<br />

-0.05<br />

-0.04<br />

-0.02<br />

-0.01<br />

0.00<br />

0.01<br />

0.02<br />

0.03<br />

0.04


0.00


28 m/sec.<br />

dv= -g/l dtx<br />

*Col.7<br />

8<br />

0.22<br />

0.21<br />

0.21<br />

0.21<br />

0.21<br />

0.21<br />

0.21<br />

0.21<br />

0.22<br />

0.22<br />

0.23<br />

0.24<br />

0.25<br />

0.27<br />

0.29<br />

0.31<br />

0.00


(0-50)% (0-100)% (100-0)%<br />

0.00 0.00<br />

4.56 4.55<br />

0.96 3.05<br />

2.28 0.00


(0-25)%<br />

V1 = 0.00<br />

V2 = 0.00<br />

V1 =<br />

V2 =


0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00


0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00


(0-50)% (0-100)% (100-0)%<br />

0.00<br />

0.00<br />

0.00<br />

0.00


CHHATRU HYDRO-ELECTRIC PROJECT<br />

TABLE 7.2<br />

COMPUTATIONS FOR DEPENDABLE YEAR ON THE BASIS OF ENERGY<br />

S.No. ANNUAL GENERATION GENERATION IN MU<br />

IN DESCENDING ORDER % DEP. YEAR<br />

YEAR IN MU. YEAR IN MU.<br />

1 1973-74 988.34 1998-99 1302.18 3.57<br />

2 1974-75 635.24 1999-00 1231.36 7.14<br />

3 1975-76 853.23 1987-88 1039.94 10.71<br />

4 1976-77 702.96 1973-74 988.34 14.29<br />

5 1977-78 833.62 1991-92 973.55 17.86<br />

6 1978-79 952.55 1994-95 966.89 21.43<br />

7 1979-80 927.92 1988-89 963.47 25.00<br />

8 1980-81 899.67 1978-79 952.55 28.57<br />

9 1981-82 787.20 1996-97 937.25 32.14<br />

10 1982-83 835.86 1979-80 927.92 35.71<br />

11 1983-84 885.81 1989-90 920.92 39.29<br />

12 1984-85 849.10 1990-91 909.46 42.86<br />

13 1985-86 804.87 1995-96 905.47 46.43<br />

14 1986-87 895.05 1980-81 899.67 50.00 50% mean<br />

15 1987-88 1039.94 1986-87 895.05 53.57 YEAR<br />

16 1988-89 963.47 1983-84 885.81 57.14<br />

17 1989-90 920.92 1975-76 853.23 60.71<br />

18 1990-91 909.46 1984-85 849.10 64.29<br />

19 1991-92 973.55 1982-83 835.86 67.86<br />

20 1992-93 755.22 1977-78 833.62 71.43<br />

21 1993-94 765.29 1997-98 833.35 75.00<br />

22 1994-95 966.89 1985-86 804.87 78.57<br />

23 1995-96 905.47 1981-82 787.20 82.14<br />

24 1996-97 937.25 1993-94 765.29 85.71<br />

25 1997-98 833.35 1992-93 755.22 89.29 90% Dep<br />

26 1998-99 1302.18 1976-77 702.96 92.86 YEAR<br />

27 1999-00 1231.36 1974-75 635.24 96.43


POWER & ENERGY GENERATION IN TABLE 7.4<br />

90% DEPENDABLE YEAR (1992-93)<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

90% Dep. Un-res. Restricted<br />

YEAR <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

1992-93 MW GWH MW GWH<br />

MONTH PERIOD DISCHA. 78<br />

I 59.21 85.50 20.52 78.00 18.72<br />

JUN II 134.86 194.75 46.74 78.00 18.72<br />

III 173.02 249.85 59.96 78.00 18.72<br />

I 132.89 191.90 46.06 78.00 18.72<br />

JUL II 196.70 284.05 68.17 78.00 18.72<br />

III 218.41 315.40 83.26 78.00 20.59<br />

I 162.49 234.65 56.32 78.00 18.72<br />

AUG II 155.26 224.20 53.81 78.00 18.72<br />

III 163.15 235.60 62.20 78.00 20.59<br />

I 139.47 201.40 48.34 78.00 18.72<br />

SEP II 68.42 98.80 23.71 78.00 18.72<br />

III 44.08 63.65 15.28 63.65 15.28<br />

I 39.47 57.00 13.68 57.00 13.68<br />

OCT II 32.24 46.55 11.17 46.55 11.17<br />

III 28.95 41.80 11.04 41.80 11.04<br />

I 22.37 32.30 7.75 32.30 7.75<br />

NOV II 18.42 26.60 6.38 26.60 6.38<br />

III 16.45 23.75 5.70 23.75 5.70<br />

I 15.79 22.80 5.47 22.80 5.47<br />

DEC II 15.13 21.85 5.24 21.85 5.24<br />

III 15.13 21.85 5.77 21.85 5.77<br />

I 13.82 19.95 4.79 19.95 4.79<br />

JAN II 13.16 19.00 4.56 19.00 4.56<br />

III 12.50 18.05 4.77 18.05 4.77<br />

I 11.84 17.10 4.10 17.10 4.10<br />

FEB II 11.18 16.15 3.88 16.15 3.88<br />

III 11.84 17.10 3.28 17.10 3.28<br />

I 11.84 17.10 4.10 17.10 4.10<br />

MAR II 12.50 18.05 4.33 18.05 4.33<br />

III 12.50 18.05 4.77 18.05 4.77<br />

I 13.82 19.95 4.79 19.95 4.79<br />

APR II 15.13 21.85 5.24 21.85 5.24<br />

III 20.39 29.45 7.07 29.45 7.07<br />

I 32.89 47.50 11.40 47.50 11.40<br />

MAY II 29.60 42.75 10.26 42.75 10.26<br />

III 55.92 80.75 21.32 78.00 20.59<br />

TOTAL ENERGY 755.22 395.07<br />

P. L. FACTOR 0.58<br />

INC.INC. IN ENR. 0.00<br />

GWH / MW 5.07<br />

% AGE UTILISN 52.31<br />

PLF (LEAN- P.) 0.25


MONTH PERIOD<br />

I<br />

JUN II<br />

III<br />

I<br />

JUL II<br />

III<br />

I<br />

AUG II<br />

III<br />

I<br />

SEP II<br />

III<br />

I<br />

OCT II<br />

III<br />

I<br />

NOV II<br />

III<br />

I<br />

DEC II<br />

III<br />

I<br />

JAN II<br />

III<br />

I<br />

FEB II<br />

III<br />

I<br />

MAR II<br />

III<br />

I<br />

APR II<br />

III<br />

I<br />

MAY II<br />

III<br />

TOTAL ENERGY<br />

P. L. FACTOR<br />

INC.INC. IN ENR.<br />

GWH / MW<br />

% AGE UTILISN<br />

PLF (LEAN- P.)<br />

POWER & ENERGY GENERATION IN<br />

90% DEPENDABLE YEAR (1992-93)<br />

TABL<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

Restricted Restrict Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong><br />

MW GWH MW GWH MW<br />

81 84 87<br />

81.00 19.44 84.00 20.16 85.50<br />

81.00 19.44 84.00 20.16 87.00<br />

81.00 19.44 84.00 20.16 87.00<br />

81.00 19.44 84.00 20.16 87.00<br />

81.00 19.44 84.00 20.16 87.00<br />

81.00 21.38 84.00 22.18 87.00<br />

81.00 19.44 84.00 20.16 87.00<br />

81.00 19.44 84.00 20.16 87.00<br />

81.00 21.38 84.00 22.18 87.00<br />

81.00 19.44 84.00 20.16 87.00<br />

81.00 19.44 84.00 20.16 87.00<br />

63.65 15.28 63.65 15.28 63.65<br />

57.00 13.68 57.00 13.68 57.00<br />

46.55 11.17 46.55 11.17 46.55<br />

41.80 11.04 41.80 11.04 41.80<br />

32.30 7.75 32.30 7.75 32.30<br />

26.60 6.38 26.60 6.38 26.60<br />

23.75 5.70 23.75 5.70 23.75<br />

22.80 5.47 22.80 5.47 22.80<br />

21.85 5.24 21.85 5.24 21.85<br />

21.85 5.77 21.85 5.77 21.85<br />

19.95 4.79 19.95 4.79 19.95<br />

19.00 4.56 19.00 4.56 19.00<br />

18.05 4.77 18.05 4.77 18.05<br />

17.10 4.10 17.10 4.10 17.10<br />

16.15 3.88 16.15 3.88 16.15<br />

17.10 3.28 17.10 3.28 17.10<br />

17.10 4.10 17.10 4.10 17.10<br />

18.05 4.33 18.05 4.33 18.05<br />

18.05 4.77 18.05 4.77 18.05<br />

19.95 4.79 19.95 4.79 19.95<br />

21.85 5.24 21.85 5.24 21.85<br />

29.45 7.07 29.45 7.07 29.45<br />

47.50 11.40 47.50 11.40 47.50<br />

42.75 10.26 42.75 10.26 42.75<br />

80.75 21.32 80.75 21.32 80.75<br />

403.86 411.93<br />

0.57 0.56<br />

8.79 8.06<br />

4.99 4.90<br />

53.48 54.54<br />

0.24 0.23


MONTH PERIOD<br />

I<br />

JUN II<br />

III<br />

I<br />

JUL II<br />

III<br />

I<br />

AUG II<br />

III<br />

I<br />

SEP II<br />

III<br />

I<br />

OCT II<br />

III<br />

I<br />

NOV II<br />

III<br />

I<br />

DEC II<br />

III<br />

I<br />

JAN II<br />

III<br />

I<br />

FEB II<br />

III<br />

I<br />

MAR II<br />

III<br />

I<br />

APR II<br />

III<br />

I<br />

MAY II<br />

III<br />

TOTAL ENERGY<br />

P. L. FACTOR<br />

INC.INC. IN ENR.<br />

GWH / MW<br />

% AGE UTILISN<br />

PLF (LEAN- P.)<br />

LE 7.4<br />

Energy<br />

GWH<br />

20.52<br />

20.88<br />

20.88<br />

20.88<br />

20.88<br />

22.97<br />

20.88<br />

20.88<br />

22.97<br />

20.88<br />

20.88<br />

15.28<br />

13.68<br />

11.17<br />

11.04<br />

7.75<br />

6.38<br />

5.70<br />

5.47<br />

5.24<br />

5.77<br />

4.79<br />

4.56<br />

4.77<br />

4.10<br />

3.88<br />

3.28<br />

4.10<br />

4.33<br />

4.77<br />

4.79<br />

5.24<br />

7.07<br />

11.40<br />

10.26<br />

21.32<br />

419.63<br />

0.55<br />

7.70<br />

4.82<br />

55.56<br />

0.22<br />

N


MONTH PERIOD<br />

I<br />

JUN II<br />

III<br />

I<br />

JUL II<br />

III<br />

I<br />

AUG II<br />

III<br />

I<br />

SEP II<br />

III<br />

I<br />

OCT II<br />

III<br />

I<br />

NOV II<br />

III<br />

I<br />

DEC II<br />

III<br />

I<br />

JAN II<br />

III<br />

I<br />

FEB II<br />

III<br />

I<br />

MAR II<br />

III<br />

I<br />

APR II<br />

III<br />

I<br />

MAY II<br />

III<br />

TOTAL ENERGY<br />

P. L. FACTOR<br />

INC.INC. IN ENR.<br />

GWH / MW<br />

% AGE UTILISN<br />

PLF (LEAN- P.)<br />

POWER & ENERGY GENERATION IN<br />

90% DEPENDABLE YEAR (1992-93)<br />

TABLE 7.4<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

Restric Restricted Restricted<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

90 93 96<br />

85.50 20.52 85.50 20.52 85.50 20.52<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 23.76 93.00 24.55 96.00 25.34<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 23.76 93.00 24.55 96.00 25.34<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

63.65 15.28 63.65 15.28 63.65 15.28<br />

57.00 13.68 57.00 13.68 57.00 13.68<br />

46.55 11.17 46.55 11.17 46.55 11.17<br />

41.80 11.04 41.80 11.04 41.80 11.04<br />

32.30 7.75 32.30 7.75 32.30 7.75<br />

26.60 6.38 26.60 6.38 26.60 6.38<br />

23.75 5.70 23.75 5.70 23.75 5.70<br />

22.80 5.47 22.80 5.47 22.80 5.47<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

21.85 5.77 21.85 5.77 21.85 5.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

29.45 7.07 29.45 7.07 29.45 7.07<br />

47.50 11.40 47.50 11.40 47.50 11.40<br />

42.75 10.26 42.75 10.26 42.75 10.26<br />

80.75 21.32 80.75 21.32 80.75 21.32<br />

426.98 434.32 441.66<br />

0.54 0.53 0.53<br />

7.34 7.34 7.34<br />

4.74 4.67 4.60<br />

56.54 57.51 58.48<br />

0.22 0.21 0.20


MONTH PERIOD<br />

I<br />

JUN II<br />

III<br />

I<br />

JUL II<br />

III<br />

I<br />

AUG II<br />

III<br />

I<br />

SEP II<br />

III<br />

I<br />

OCT II<br />

III<br />

I<br />

NOV II<br />

III<br />

I<br />

DEC II<br />

III<br />

I<br />

JAN II<br />

III<br />

I<br />

FEB II<br />

III<br />

I<br />

MAR II<br />

III<br />

I<br />

APR II<br />

III<br />

I<br />

MAY II<br />

III<br />

TOTAL ENERGY<br />

P. L. FACTOR<br />

INC.INC. IN ENR.<br />

GWH / MW<br />

% AGE UTILISN<br />

PLF (LEAN- P.)<br />

POWER & ENERGY GENERATION IN<br />

90% DEPENDABLE YEAR (1992-93)<br />

TABLE 7.4<br />

Net Head = 160.00 mtr N<br />

Eff. = 0.92<br />

Restricted Restricted Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

99 102 105<br />

85.50 20.52 85.50 20.52 85.50 20.52<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

99.00 26.14 102.00 26.93 105.00 27.72<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

99.00 26.14 102.00 26.93 105.00 27.72<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

98.80 23.71 98.80 23.71 98.80 23.71<br />

63.65 15.28 63.65 15.28 63.65 15.28<br />

57.00 13.68 57.00 13.68 57.00 13.68<br />

46.55 11.17 46.55 11.17 46.55 11.17<br />

41.80 11.04 41.80 11.04 41.80 11.04<br />

32.30 7.75 32.30 7.75 32.30 7.75<br />

26.60 6.38 26.60 6.38 26.60 6.38<br />

23.75 5.70 23.75 5.70 23.75 5.70<br />

22.80 5.47 22.80 5.47 22.80 5.47<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

21.85 5.77 21.85 5.77 21.85 5.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

29.45 7.07 29.45 7.07 29.45 7.07<br />

47.50 11.40 47.50 11.40 47.50 11.40<br />

42.75 10.26 42.75 10.26 42.75 10.26<br />

80.75 21.32 80.75 21.32 80.75 21.32<br />

448.96 455.58 462.21<br />

0.52 0.51 0.50<br />

7.30 6.62 6.62<br />

4.53 4.47 4.40<br />

59.45 60.32 61.20<br />

0.20 0.19 0.18


MONTH PERIOD<br />

I<br />

JUN II<br />

III<br />

I<br />

JUL II<br />

III<br />

I<br />

AUG II<br />

III<br />

I<br />

SEP II<br />

III<br />

I<br />

OCT II<br />

III<br />

I<br />

NOV II<br />

III<br />

I<br />

DEC II<br />

III<br />

I<br />

JAN II<br />

III<br />

I<br />

FEB II<br />

III<br />

I<br />

MAR II<br />

III<br />

I<br />

APR II<br />

III<br />

I<br />

MAY II<br />

III<br />

TOTAL ENERGY<br />

P. L. FACTOR<br />

INC.INC. IN ENR.<br />

GWH / MW<br />

% AGE UTILISN<br />

PLF (LEAN- P.)<br />

POWER & ENERGY GENERATION IN<br />

90% DEPENDABLE YEAR (1992-93)<br />

Net Head 160.00 mtr<br />

TABLE 7.4<br />

Eff. = 0.92<br />

Restrict Restricted Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

108 111 114<br />

85.50 20.52 85.50 20.52 85.50 20.52<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

108.00 28.51 111.00 29.30 114.00 30.10<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

108.00 28.51 111.00 29.30 114.00 30.10<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

98.80 23.71 98.80 23.71 98.80 23.71<br />

63.65 15.28 63.65 15.28 63.65 15.28<br />

57.00 13.68 57.00 13.68 57.00 13.68<br />

46.55 11.17 46.55 11.17 46.55 11.17<br />

41.80 11.04 41.80 11.04 41.80 11.04<br />

32.30 7.75 32.30 7.75 32.30 7.75<br />

26.60 6.38 26.60 6.38 26.60 6.38<br />

23.75 5.70 23.75 5.70 23.75 5.70<br />

22.80 5.47 22.80 5.47 22.80 5.47<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

21.85 5.77 21.85 5.77 21.85 5.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

29.45 7.07 29.45 7.07 29.45 7.07<br />

47.50 11.40 47.50 11.40 47.50 11.40<br />

42.75 10.26 42.75 10.26 42.75 10.26<br />

80.75 21.32 80.75 21.32 80.75 21.32<br />

468.83 475.46 482.08<br />

0.50 0.49 0.48<br />

6.62 6.62 6.62<br />

4.34 4.28 4.23<br />

62.08 62.96 63.83<br />

0.18 0.17 0.17


MONTH PERIOD<br />

I<br />

JUN II<br />

III<br />

I<br />

JUL II<br />

III<br />

I<br />

AUG II<br />

III<br />

I<br />

SEP II<br />

III<br />

I<br />

OCT II<br />

III<br />

I<br />

NOV II<br />

III<br />

I<br />

DEC II<br />

III<br />

I<br />

JAN II<br />

III<br />

I<br />

FEB II<br />

III<br />

I<br />

MAR II<br />

III<br />

I<br />

APR II<br />

III<br />

I<br />

MAY II<br />

III<br />

TOTAL ENERGY<br />

P. L. FACTOR<br />

INC.INC. IN ENR.<br />

GWH / MW<br />

% AGE UTILISN<br />

PLF (LEAN- P.)<br />

POWER & ENERGY GENERATION IN<br />

90% DEPENDABLE YEAR (1992-93)<br />

Net Head = 160.00 mtr<br />

TABLE 7.4<br />

Eff. = 0.92<br />

Restricted Restricted Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

117 120 123<br />

85.50 20.52 85.50 20.52 85.50 20.52<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

117.00 30.89 120.00 31.68 123.00 32.47<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

117.00 30.89 120.00 31.68 123.00 32.47<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

98.80 23.71 98.80 23.71 98.80 23.71<br />

63.65 15.28 63.65 15.28 63.65 15.28<br />

57.00 13.68 57.00 13.68 57.00 13.68<br />

46.55 11.17 46.55 11.17 46.55 11.17<br />

41.80 11.04 41.80 11.04 41.80 11.04<br />

32.30 7.75 32.30 7.75 32.30 7.75<br />

26.60 6.38 26.60 6.38 26.60 6.38<br />

23.75 5.70 23.75 5.70 23.75 5.70<br />

22.80 5.47 22.80 5.47 22.80 5.47<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

21.85 5.77 21.85 5.77 21.85 5.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

29.45 7.07 29.45 7.07 29.45 7.07<br />

47.50 11.40 47.50 11.40 47.50 11.40<br />

42.75 10.26 42.75 10.26 42.75 10.26<br />

80.75 21.32 80.75 21.32 80.75 21.32<br />

488.70 495.33 501.95<br />

0.48 0.47 0.47<br />

6.62 6.62 6.62<br />

4.18 4.13 4.08<br />

64.71 65.59 66.46<br />

0.17 0.16 0.16


MONTH PERIOD<br />

I<br />

JUN II<br />

III<br />

I<br />

JUL II<br />

III<br />

I<br />

AUG II<br />

III<br />

I<br />

SEP II<br />

III<br />

I<br />

OCT II<br />

III<br />

I<br />

NOV II<br />

III<br />

I<br />

DEC II<br />

III<br />

I<br />

JAN II<br />

III<br />

I<br />

FEB II<br />

III<br />

I<br />

MAR II<br />

III<br />

I<br />

APR II<br />

III<br />

I<br />

MAY II<br />

III<br />

TOTAL ENERGY<br />

P. L. FACTOR<br />

INC.INC. IN ENR.<br />

GWH / MW<br />

% AGE UTILISN<br />

PLF (LEAN- P.)<br />

POWER & ENERGY GENERATION IN<br />

90% DEPENDABLE YEAR (1992-93)<br />

TABLE 7.4<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

Restricted Restrict Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

126 129 132<br />

85.50 20.52 85.50 20.52 85.50 20.52<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

126.00 33.26 129.00 34.06 132.00 34.85<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

126.00 33.26 129.00 34.06 132.00 34.85<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

98.80 23.71 98.80 23.71 98.80 23.71<br />

63.65 15.28 63.65 15.28 63.65 15.28<br />

57.00 13.68 57.00 13.68 57.00 13.68<br />

46.55 11.17 46.55 11.17 46.55 11.17<br />

41.80 11.04 41.80 11.04 41.80 11.04<br />

32.30 7.75 32.30 7.75 32.30 7.75<br />

26.60 6.38 26.60 6.38 26.60 6.38<br />

23.75 5.70 23.75 5.70 23.75 5.70<br />

22.80 5.47 22.80 5.47 22.80 5.47<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

21.85 5.77 21.85 5.77 21.85 5.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

29.45 7.07 29.45 7.07 29.45 7.07<br />

47.50 11.40 47.50 11.40 47.50 11.40<br />

42.75 10.26 42.75 10.26 42.75 10.26<br />

80.75 21.32 80.75 21.32 80.75 21.32<br />

508.58 515.20 521.82<br />

0.46 0.46 0.45<br />

6.62 6.62 6.62<br />

4.04 3.99 3.95<br />

67.34 68.22 69.10<br />

0.15 0.15 0.15


MONTH PERIOD<br />

I<br />

JUN II<br />

III<br />

I<br />

JUL II<br />

III<br />

I<br />

AUG II<br />

III<br />

I<br />

SEP II<br />

III<br />

I<br />

OCT II<br />

III<br />

I<br />

NOV II<br />

III<br />

I<br />

DEC II<br />

III<br />

I<br />

JAN II<br />

III<br />

I<br />

FEB II<br />

III<br />

I<br />

MAR II<br />

III<br />

I<br />

APR II<br />

III<br />

I<br />

MAY II<br />

III<br />

TOTAL ENERGY<br />

P. L. FACTOR<br />

INC.INC. IN ENR.<br />

GWH / MW<br />

% AGE UTILISN<br />

PLF (LEAN- P.)<br />

POWER & ENERGY GENERATION IN<br />

90% DEPENDABLE YEAR (1992-93)<br />

TABLE 7.4<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

Restricted Restrict Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

135 138 141<br />

85.50 20.52 85.50 20.52 85.50 20.52<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

135.00 35.64 138.00 36.43 141.00 37.22<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

135.00 35.64 138.00 36.43 141.00 37.22<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

98.80 23.71 98.80 23.71 98.80 23.71<br />

63.65 15.28 63.65 15.28 63.65 15.28<br />

57.00 13.68 57.00 13.68 57.00 13.68<br />

46.55 11.17 46.55 11.17 46.55 11.17<br />

41.80 11.04 41.80 11.04 41.80 11.04<br />

32.30 7.75 32.30 7.75 32.30 7.75<br />

26.60 6.38 26.60 6.38 26.60 6.38<br />

23.75 5.70 23.75 5.70 23.75 5.70<br />

22.80 5.47 22.80 5.47 22.80 5.47<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

21.85 5.77 21.85 5.77 21.85 5.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

29.45 7.07 29.45 7.07 29.45 7.07<br />

47.50 11.40 47.50 11.40 47.50 11.40<br />

42.75 10.26 42.75 10.26 42.75 10.26<br />

80.75 21.32 80.75 21.32 80.75 21.32<br />

528.45 535.07 541.70<br />

0.45 0.44 0.44<br />

6.62 6.62 6.62<br />

3.91 3.88 3.84<br />

69.97 70.85 71.73<br />

0.14 0.14 0.14


MONTH PERIOD<br />

I<br />

JUN II<br />

III<br />

I<br />

JUL II<br />

III<br />

I<br />

AUG II<br />

III<br />

I<br />

SEP II<br />

III<br />

I<br />

OCT II<br />

III<br />

I<br />

NOV II<br />

III<br />

I<br />

DEC II<br />

III<br />

I<br />

JAN II<br />

III<br />

I<br />

FEB II<br />

III<br />

I<br />

MAR II<br />

III<br />

I<br />

APR II<br />

III<br />

I<br />

MAY II<br />

III<br />

TOTAL ENERGY<br />

P. L. FACTOR<br />

INC.INC. IN ENR.<br />

GWH / MW<br />

% AGE UTILISN<br />

PLF (LEAN- P.)<br />

POWER & ENERGY GENERATION IN<br />

90% DEPENDABLE YEAR (1992-93)<br />

TABLE 7.4<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

Restricted Restrict Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

144 147 150<br />

85.50 20.52 85.50 20.52 85.50 20.52<br />

144.00 34.56 147.00 35.28 150.00 36.00<br />

144.00 34.56 147.00 35.28 150.00 36.00<br />

144.00 34.56 147.00 35.28 150.00 36.00<br />

144.00 34.56 147.00 35.28 150.00 36.00<br />

144.00 38.02 147.00 38.81 150.00 39.60<br />

144.00 34.56 147.00 35.28 150.00 36.00<br />

144.00 34.56 147.00 35.28 150.00 36.00<br />

144.00 38.02 147.00 38.81 150.00 39.60<br />

144.00 34.56 147.00 35.28 150.00 36.00<br />

98.80 23.71 98.80 23.71 98.80 23.71<br />

63.65 15.28 63.65 15.28 63.65 15.28<br />

57.00 13.68 57.00 13.68 57.00 13.68<br />

46.55 11.17 46.55 11.17 46.55 11.17<br />

41.80 11.04 41.80 11.04 41.80 11.04<br />

32.30 7.75 32.30 7.75 32.30 7.75<br />

26.60 6.38 26.60 6.38 26.60 6.38<br />

23.75 5.70 23.75 5.70 23.75 5.70<br />

22.80 5.47 22.80 5.47 22.80 5.47<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

21.85 5.77 21.85 5.77 21.85 5.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

29.45 7.07 29.45 7.07 29.45 7.07<br />

47.50 11.40 47.50 11.40 47.50 11.40<br />

42.75 10.26 42.75 10.26 42.75 10.26<br />

80.75 21.32 80.75 21.32 80.75 21.32<br />

548.32 554.94 561.57<br />

0.43 0.43 0.43<br />

6.62 6.62 6.62<br />

3.81 3.78 3.74<br />

72.60 73.48 74.36<br />

0.13 0.13 0.13


MONTH PERIOD<br />

I<br />

JUN II<br />

III<br />

I<br />

JUL II<br />

III<br />

I<br />

AUG II<br />

III<br />

I<br />

SEP II<br />

III<br />

I<br />

OCT II<br />

III<br />

I<br />

NOV II<br />

III<br />

I<br />

DEC II<br />

III<br />

I<br />

JAN II<br />

III<br />

I<br />

FEB II<br />

III<br />

I<br />

MAR II<br />

III<br />

I<br />

APR II<br />

III<br />

I<br />

MAY II<br />

III<br />

TOTAL ENERGY<br />

P. L. FACTOR<br />

INC.INC. IN ENR.<br />

GWH / MW<br />

% AGE UTILISN<br />

PLF (LEAN- P.)<br />

POWER & ENERGY GENERATION IN<br />

90% DEPENDABLE YEAR (1992-93)<br />

Net Head = 160.00 mtr<br />

TABLE 7.4<br />

Eff. = 0.92<br />

Restricted Restrict Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

153 156 159<br />

85.50 20.52 85.50 20.52 85.50 20.52<br />

153.00 36.72 156.00 37.44 159.00 38.16<br />

153.00 36.72 156.00 37.44 159.00 38.16<br />

153.00 36.72 156.00 37.44 159.00 38.16<br />

153.00 36.72 156.00 37.44 159.00 38.16<br />

153.00 40.39 156.00 41.18 159.00 41.98<br />

153.00 36.72 156.00 37.44 159.00 38.16<br />

153.00 36.72 156.00 37.44 159.00 38.16<br />

153.00 40.39 156.00 41.18 159.00 41.98<br />

153.00 36.72 156.00 37.44 159.00 38.16<br />

98.80 23.71 98.80 23.71 98.80 23.71<br />

63.65 15.28 63.65 15.28 63.65 15.28<br />

57.00 13.68 57.00 13.68 57.00 13.68<br />

46.55 11.17 46.55 11.17 46.55 11.17<br />

41.80 11.04 41.80 11.04 41.80 11.04<br />

32.30 7.75 32.30 7.75 32.30 7.75<br />

26.60 6.38 26.60 6.38 26.60 6.38<br />

23.75 5.70 23.75 5.70 23.75 5.70<br />

22.80 5.47 22.80 5.47 22.80 5.47<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

21.85 5.77 21.85 5.77 21.85 5.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

29.45 7.07 29.45 7.07 29.45 7.07<br />

47.50 11.40 47.50 11.40 47.50 11.40<br />

42.75 10.26 42.75 10.26 42.75 10.26<br />

80.75 21.32 80.75 21.32 80.75 21.32<br />

568.19 574.82 581.44<br />

0.42 0.42 0.42<br />

6.62 6.62 6.62<br />

3.71 3.68 3.66<br />

75.24 76.11 76.99<br />

0.13 0.12 0.12


POWER & ENERGY GENERATION IN TABLE 7.6<br />

50% MEAN YEAR (1980-81)<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

50% Mean. Un-res. Restricted<br />

YEAR <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

1980-81 MW GWH MW GWH<br />

MONTH PERIOD DISCHA. 78<br />

I 132.89 191.90 46.06 78.00 18.72<br />

JUN II 154.60 223.25 53.58 78.00 18.72<br />

III 219.73 317.30 76.15 78.00 18.72<br />

I 231.57 334.39 80.25 78.00 18.72<br />

JUL II 223.68 323.00 77.52 78.00 18.72<br />

III 205.91 297.35 78.50 78.00 20.59<br />

I 223.02 322.05 77.29 78.00 18.72<br />

AUG II 146.71 211.85 50.84 78.00 18.72<br />

III 165.13 238.45 62.95 78.00 20.59<br />

I 103.29 149.15 35.80 78.00 18.72<br />

SEP II 65.13 94.05 22.57 78.00 18.72<br />

III 45.39 65.55 15.73 65.55 15.73<br />

I 35.52 51.30 12.31 51.30 12.31<br />

OCT II 23.03 33.25 7.98 33.25 7.98<br />

III 18.42 26.60 7.02 26.60 7.02<br />

I 13.82 19.95 4.79 19.95 4.79<br />

NOV II 13.16 19.00 4.56 19.00 4.56<br />

III 13.16 19.00 4.56 19.00 4.56<br />

I 11.84 17.10 4.10 17.10 4.10<br />

DEC II 11.18 16.15 3.88 16.15 3.88<br />

III 10.53 15.20 4.01 15.20 4.01<br />

I 11.18 16.15 3.88 16.15 3.88<br />

JAN II 10.53 15.20 3.65 15.20 3.65<br />

III 9.87 14.25 3.76 14.25 3.76<br />

I 9.87 14.25 3.42 14.25 3.42<br />

FEB II 10.53 15.20 3.65 15.20 3.65<br />

III 11.84 17.10 3.28 17.10 3.28<br />

I 11.18 16.15 3.88 16.15 3.88<br />

MAR II 11.18 16.15 3.88 16.15 3.88<br />

III 11.84 17.10 4.51 17.10 4.51<br />

I 12.50 18.05 4.33 18.05 4.33<br />

APR II 17.10 24.70 5.93 24.70 5.93<br />

III 24.34 35.15 8.44 35.15 8.44<br />

I 86.18 124.45 29.87 78.00 18.72<br />

MAY II 109.21 157.70 37.85 78.00 18.72<br />

III 128.28 185.25 48.91 78.00 20.59<br />

TOTAL ENERGY 899.67 389.24<br />

P. L. FACTOR 0.57<br />

INC.INC. IN ENR. 0.00<br />

GWH / MW 4.99<br />

% AGE UTILISN 43.26<br />

PLF (LEAN- P.) 0.20


POWER & ENERGY GENERATION IN TABLE 7.6<br />

50% MEAN YEAR (1980-81)<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

Restricted Restrict Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

81 84 87<br />

81.00 19.44 84.00 20.16 87.00 20.88<br />

81.00 19.44 84.00 20.16 87.00 20.88<br />

81.00 19.44 84.00 20.16 87.00 20.88<br />

81.00 19.44 84.00 20.16 87.00 20.88<br />

81.00 19.44 84.00 20.16 87.00 20.88<br />

81.00 21.38 84.00 22.18 87.00 22.97<br />

81.00 19.44 84.00 20.16 87.00 20.88<br />

81.00 19.44 84.00 20.16 87.00 20.88<br />

81.00 21.38 84.00 22.18 87.00 22.97<br />

81.00 19.44 84.00 20.16 87.00 20.88<br />

81.00 19.44 84.00 20.16 87.00 20.88<br />

65.55 15.73 65.55 15.73 65.55 15.73<br />

51.30 12.31 51.30 12.31 51.30 12.31<br />

33.25 7.98 33.25 7.98 33.25 7.98<br />

26.60 7.02 26.60 7.02 26.60 7.02<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 4.01 15.20 4.01 15.20 4.01<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

14.25 3.76 14.25 3.76 14.25 3.76<br />

14.25 3.42 14.25 3.42 14.25 3.42<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 4.51 17.10 4.51 17.10 4.51<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

24.70 5.93 24.70 5.93 24.70 5.93<br />

35.15 8.44 35.15 8.44 35.15 8.44<br />

81.00 19.44 84.00 20.16 87.00 20.88<br />

81.00 19.44 84.00 20.16 87.00 20.88<br />

81.00 21.38 84.00 22.18 87.00 22.97<br />

399.54 409.83 420.13<br />

0.56 0.56 0.55<br />

10.30 10.30 10.30<br />

4.93 4.88 4.83<br />

44.41 45.55 46.70<br />

0.19 0.19 0.18


POWER & ENERGY GENERATION IN TABLE 7.6<br />

50% MEAN YEAR (1980-81)<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

Restric Restricted Restricte<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

90 93 96<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 23.76 93.00 24.55 96.00 25.34<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 23.76 93.00 24.55 96.00 25.34<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 21.60 93.00 22.32 94.05 22.57<br />

65.55 15.73 65.55 15.73 65.55 15.73<br />

51.30 12.31 51.30 12.31 51.30 12.31<br />

33.25 7.98 33.25 7.98 33.25 7.98<br />

26.60 7.02 26.60 7.02 26.60 7.02<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 4.01 15.20 4.01 15.20 4.01<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

14.25 3.76 14.25 3.76 14.25 3.76<br />

14.25 3.42 14.25 3.42 14.25 3.42<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 4.51 17.10 4.51 17.10 4.51<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

24.70 5.93 24.70 5.93 24.70 5.93<br />

35.15 8.44 35.15 8.44 35.15 8.44<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 23.76 93.00 24.55 96.00 25.34<br />

430.42 440.72 450.55<br />

0.55 0.54 0.54<br />

10.30 10.30 9.83<br />

4.78 4.74 4.69<br />

47.84 48.99 50.08<br />

0.17 0.17 0.16


POWER & ENERGY GENERATION IN TABLE 7.6<br />

50% MEAN YEAR (1980-81)<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

Restricted Restrict Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

99 102 105<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

99.00 26.14 102.00 26.93 105.00 27.72<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

99.00 26.14 102.00 26.93 105.00 27.72<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

94.05 22.57 94.05 22.57 94.05 22.57<br />

65.55 15.73 65.55 15.73 65.55 15.73<br />

51.30 12.31 51.30 12.31 51.30 12.31<br />

33.25 7.98 33.25 7.98 33.25 7.98<br />

26.60 7.02 26.60 7.02 26.60 7.02<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 4.01 15.20 4.01 15.20 4.01<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

14.25 3.76 14.25 3.76 14.25 3.76<br />

14.25 3.42 14.25 3.42 14.25 3.42<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 4.51 17.10 4.51 17.10 4.51<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

24.70 5.93 24.70 5.93 24.70 5.93<br />

35.15 8.44 35.15 8.44 35.15 8.44<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

99.00 26.14 102.00 26.93 105.00 27.72<br />

460.12 469.70 479.28<br />

0.53 0.53 0.52<br />

9.58 9.58 9.58<br />

4.65 4.60 4.56<br />

51.14 52.21 53.27<br />

0.16 0.15 0.15


POWER & ENERGY GENERATION IN TABLE 7.6<br />

50% MEAN YEAR (1980-81)<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

Restricted Restrict Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

108 111 114<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

108.00 28.51 111.00 29.30 114.00 30.10<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

108.00 28.51 111.00 29.30 114.00 30.10<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

94.05 22.57 94.05 22.57 94.05 22.57<br />

65.55 15.73 65.55 15.73 65.55 15.73<br />

51.30 12.31 51.30 12.31 51.30 12.31<br />

33.25 7.98 33.25 7.98 33.25 7.98<br />

26.60 7.02 26.60 7.02 26.60 7.02<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 4.01 15.20 4.01 15.20 4.01<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

14.25 3.76 14.25 3.76 14.25 3.76<br />

14.25 3.42 14.25 3.42 14.25 3.42<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 4.51 17.10 4.51 17.10 4.51<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

24.70 5.93 24.70 5.93 24.70 5.93<br />

35.15 8.44 35.15 8.44 35.15 8.44<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

108.00 28.51 111.00 29.30 114.00 30.10<br />

488.85 498.43 508.00<br />

0.52 0.51 0.51<br />

9.58 9.58 9.58<br />

4.53 4.49 4.46<br />

54.34 55.40 56.47<br />

0.14 0.14 0.14


POWER & ENERGY GENERATION IN TABLE 7.6<br />

50% MEAN YEAR (1980-81)<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

Restricted Restrict Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

117 120 123<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

117.00 30.89 120.00 31.68 123.00 32.47<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

117.00 30.89 120.00 31.68 123.00 32.47<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

94.05 22.57 94.05 22.57 94.05 22.57<br />

65.55 15.73 65.55 15.73 65.55 15.73<br />

51.30 12.31 51.30 12.31 51.30 12.31<br />

33.25 7.98 33.25 7.98 33.25 7.98<br />

26.60 7.02 26.60 7.02 26.60 7.02<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 4.01 15.20 4.01 15.20 4.01<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

14.25 3.76 14.25 3.76 14.25 3.76<br />

14.25 3.42 14.25 3.42 14.25 3.42<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 4.51 17.10 4.51 17.10 4.51<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

24.70 5.93 24.70 5.93 24.70 5.93<br />

35.15 8.44 35.15 8.44 35.15 8.44<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

117.00 30.89 120.00 31.68 123.00 32.47<br />

517.58 527.16 536.73<br />

0.50 0.50 0.50<br />

9.58 9.58 9.58<br />

4.42 4.39 4.36<br />

57.53 58.59 59.66<br />

0.13 0.13 0.13


POWER & ENERGY GENERATION IN TABLE 7.6<br />

50% MEAN YEAR (1980-81)<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

Restricted Restrict Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

126 129 132<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

126.00 33.26 129.00 34.06 132.00 34.85<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

126.00 33.26 129.00 34.06 132.00 34.85<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

94.05 22.57 94.05 22.57 94.05 22.57<br />

65.55 15.73 65.55 15.73 65.55 15.73<br />

51.30 12.31 51.30 12.31 51.30 12.31<br />

33.25 7.98 33.25 7.98 33.25 7.98<br />

26.60 7.02 26.60 7.02 26.60 7.02<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 4.01 15.20 4.01 15.20 4.01<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

14.25 3.76 14.25 3.76 14.25 3.76<br />

14.25 3.42 14.25 3.42 14.25 3.42<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 4.51 17.10 4.51 17.10 4.51<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

24.70 5.93 24.70 5.93 24.70 5.93<br />

35.15 8.44 35.15 8.44 35.15 8.44<br />

124.45 29.87 124.45 29.87 124.45 29.87<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

126.00 33.26 129.00 34.06 132.00 34.85<br />

545.94 554.79 563.65<br />

0.49 0.49 0.49<br />

9.20 8.86 8.86<br />

4.33 4.30 4.27<br />

60.68 61.67 62.65<br />

0.12 0.12 0.12


POWER & ENERGY GENERATION IN TABLE 7.6<br />

50% MEAN YEAR (1980-81)<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

Restricted Restrict Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

135 138 141<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

135.00 35.64 138.00 36.43 141.00 37.22<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

135.00 35.64 138.00 36.43 141.00 37.22<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

94.05 22.57 94.05 22.57 94.05 22.57<br />

65.55 15.73 65.55 15.73 65.55 15.73<br />

51.30 12.31 51.30 12.31 51.30 12.31<br />

33.25 7.98 33.25 7.98 33.25 7.98<br />

26.60 7.02 26.60 7.02 26.60 7.02<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 4.01 15.20 4.01 15.20 4.01<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

14.25 3.76 14.25 3.76 14.25 3.76<br />

14.25 3.42 14.25 3.42 14.25 3.42<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 4.51 17.10 4.51 17.10 4.51<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

24.70 5.93 24.70 5.93 24.70 5.93<br />

35.15 8.44 35.15 8.44 35.15 8.44<br />

124.45 29.87 124.45 29.87 124.45 29.87<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

135.00 35.64 138.00 36.43 141.00 37.22<br />

572.50 581.36 590.22<br />

0.48 0.48 0.48<br />

8.86 8.86 8.86<br />

4.24 4.21 4.19<br />

63.63 64.62 65.60<br />

0.12 0.11 0.11


POWER & ENERGY GENERATION IN TABLE 7.6<br />

50% MEAN YEAR (1980-81)<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

Restricted Restrict Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

144 147 150<br />

144.00 34.56 147.00 35.28 150.00 36.00<br />

144.00 34.56 147.00 35.28 150.00 36.00<br />

144.00 34.56 147.00 35.28 150.00 36.00<br />

144.00 34.56 147.00 35.28 150.00 36.00<br />

144.00 34.56 147.00 35.28 150.00 36.00<br />

144.00 38.02 147.00 38.81 150.00 39.60<br />

144.00 34.56 147.00 35.28 150.00 36.00<br />

144.00 34.56 147.00 35.28 150.00 36.00<br />

144.00 38.02 147.00 38.81 150.00 39.60<br />

144.00 34.56 147.00 35.28 149.15 35.80<br />

94.05 22.57 94.05 22.57 94.05 22.57<br />

65.55 15.73 65.55 15.73 65.55 15.73<br />

51.30 12.31 51.30 12.31 51.30 12.31<br />

33.25 7.98 33.25 7.98 33.25 7.98<br />

26.60 7.02 26.60 7.02 26.60 7.02<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 4.01 15.20 4.01 15.20 4.01<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

14.25 3.76 14.25 3.76 14.25 3.76<br />

14.25 3.42 14.25 3.42 14.25 3.42<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 4.51 17.10 4.51 17.10 4.51<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

24.70 5.93 24.70 5.93 24.70 5.93<br />

35.15 8.44 35.15 8.44 35.15 8.44<br />

124.45 29.87 124.45 29.87 124.45 29.87<br />

144.00 34.56 147.00 35.28 150.00 36.00<br />

144.00 38.02 147.00 38.81 150.00 39.60<br />

599.07 607.93 616.58<br />

0.47 0.47 0.47<br />

8.86 8.86 8.65<br />

4.16 4.14 4.11<br />

66.59 67.57 68.53<br />

0.11 0.11 0.10


POWER & ENERGY GENERATION IN TABLE 7.6<br />

50% MEAN YEAR (1980-81)<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

Restricted Restrict Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

153 156 159<br />

153.00 36.72 156.00 37.44 159.00 38.16<br />

153.00 36.72 156.00 37.44 159.00 38.16<br />

153.00 36.72 156.00 37.44 159.00 38.16<br />

153.00 36.72 156.00 37.44 159.00 38.16<br />

153.00 36.72 156.00 37.44 159.00 38.16<br />

153.00 40.39 156.00 41.18 159.00 41.98<br />

153.00 36.72 156.00 37.44 159.00 38.16<br />

153.00 36.72 156.00 37.44 159.00 38.16<br />

153.00 40.39 156.00 41.18 159.00 41.98<br />

149.15 35.80 149.15 35.80 149.15 35.80<br />

94.05 22.57 94.05 22.57 94.05 22.57<br />

65.55 15.73 65.55 15.73 65.55 15.73<br />

51.30 12.31 51.30 12.31 51.30 12.31<br />

33.25 7.98 33.25 7.98 33.25 7.98<br />

26.60 7.02 26.60 7.02 26.60 7.02<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 4.01 15.20 4.01 15.20 4.01<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

14.25 3.76 14.25 3.76 14.25 3.76<br />

14.25 3.42 14.25 3.42 14.25 3.42<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 4.51 17.10 4.51 17.10 4.51<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

24.70 5.93 24.70 5.93 24.70 5.93<br />

35.15 8.44 35.15 8.44 35.15 8.44<br />

124.45 29.87 124.45 29.87 124.45 29.87<br />

153.00 36.72 156.00 37.44 157.70 37.85<br />

153.00 40.39 156.00 41.18 159.00 41.98<br />

624.72 632.85 640.68<br />

0.47 0.46 0.46<br />

8.14 8.14 7.82<br />

4.08 4.06 4.03<br />

69.44 70.34 71.21<br />

0.10 0.10 0.10


CHHATRU HYDRO- ELECTRIC PROJECT TABLE-7.7<br />

50% Dep. <strong>Power</strong> Energy Energy<br />

Discharges MW GWH GWH<br />

MONTH PERIOD 1980-81 108 at 95%m/c Availability<br />

I 132.89 108.00 25.92 25.92<br />

JUN II 154.60 108.00 25.92 24.62<br />

III 219.73 108.00 25.92 24.62<br />

I 231.57 108.00 25.92 24.62<br />

JUL II 223.68 108.00 25.92 24.62<br />

III 205.91 108.00 28.51 27.09<br />

I 223.02 108.00 25.92 24.62<br />

AUG II 146.71 108.00 25.92 24.62<br />

III 165.13 108.00 28.51 27.09<br />

I 103.29 108.00 25.92 24.62<br />

SEP II 65.13 94.05 22.57 21.44<br />

III 45.39 65.55 15.73 15.73<br />

I 35.52 51.30 12.31 12.31<br />

OCT II 23.03 33.25 7.98 7.98<br />

III 18.42 26.60 7.02 7.02<br />

I 13.82 19.95 4.79 4.79<br />

NOV II 13.16 19.00 4.56 4.56<br />

III 13.16 19.00 4.56 4.56<br />

I 11.84 17.10 4.10 4.10<br />

DEC II 11.18 16.15 3.88 3.88<br />

III 10.53 15.20 4.01 4.01<br />

I 11.18 16.15 3.88 3.88<br />

JAN II 10.53 15.20 3.65 3.65<br />

III 9.87 14.25 3.76 3.76<br />

I 9.87 14.25 3.42 3.42<br />

FEB II 10.53 15.20 3.65 3.65<br />

III 11.84 17.10 3.28 3.28<br />

I 11.18 16.15 3.88 3.88<br />

MAR II 11.18 16.15 3.88 3.88<br />

III 11.84 17.10 4.51 4.51<br />

I 12.50 18.05 4.33 4.33<br />

APR II 17.10 24.70 5.93 5.93<br />

III 24.34 35.15 8.44 8.44<br />

I 86.18 108.00 25.92 25.92<br />

MAY II 109.21 108.00 25.92 25.92<br />

III 128.28 108.00 28.51 28.51<br />

TOTAL ENERGY= 488.85 475.80<br />

GWH GWH


CHHATRU HYDRO- ELECTRIC PROJECT<br />

SUMMARY TABLE 7.10<br />

50% MEAN YEAR<br />

Installed Cap. Total Energy Inc. Increase Gwh/ Mw PLF PLF<br />

Mw Gwh Gwh Total Year Dec. - Feb.<br />

78 389.24 0.00 4.99 0.57 0.20<br />

81 399.54 10.30 4.93 0.56 0.19<br />

84 409.83 10.30 4.88 0.56 0.19<br />

87 420.13 10.30 4.83 0.55 0.18<br />

90 430.42 10.30 4.78 0.55 0.17<br />

93 440.72 10.30 4.74 0.54 0.17<br />

96 450.55 9.83 4.69 0.54 0.16<br />

99 460.12 9.58 4.65 0.53 0.16<br />

102 469.70 9.58 4.60 0.53 0.15<br />

105 479.28 9.58 4.56 0.52 0.15<br />

108 488.85 9.58 4.53 0.52 0.14<br />

111 498.43 9.58 4.49 0.51 0.14<br />

114 508.00 9.58 4.46 0.51 0.14<br />

117 517.58 9.58 4.42 0.50 0.13<br />

120 527.16 9.58 4.39 0.50 0.13<br />

123 536.73 9.58 4.36 0.50 0.13<br />

126 545.94 9.20 4.33 0.49 0.12<br />

129 554.79 8.86 4.30 0.49 0.12<br />

132 563.65 8.86 4.27 0.49 0.12<br />

135 572.50 8.86 4.24 0.48 0.12<br />

138 581.36 8.86 4.21 0.48 0.11<br />

141 590.22 8.86 4.19 0.48 0.11<br />

144 599.07 8.86 4.16 0.47 0.11<br />

147 607.93 8.86 4.14 0.47 0.11<br />

150 616.58 8.65 4.11 0.47 0.10<br />

153 624.72 8.14 4.08 0.47 0.10<br />

156 632.85 8.14 4.06 0.46 0.10<br />

159 640.68 7.82 4.03 0.46 0.10


DISCH. IN CUMECS<br />

400.00<br />

300.00<br />

200.00<br />

100.00<br />

0.00<br />

0.00<br />

CHHATRU HEP FLOW DURATION CURVE(OVER-ALL)<br />

10.00<br />

20.00<br />

30.00<br />

40.00<br />

50.00<br />

60.00<br />

% OCCURR.<br />

70.00<br />

80.00<br />

90.00<br />

100.00<br />

PLATE 5.1<br />

%Cumm.occ. Disch.(m3/sec)<br />

0.31 300.00<br />

10.49 200.00<br />

19.03 150.00<br />

28.40 100.00<br />

29.53 90.00<br />

31.38 80.00<br />

32.92 70.00<br />

34.88 60.00<br />

37.04 50.00<br />

41.26 40.00<br />

46.50 30.00<br />

51.23 25.00<br />

59.67 20.00<br />

72.53 15.00<br />

91.56 10.00<br />

100.00 5.00<br />

90% Dep. Discharge = 10.41 cumecs<br />

50% Dep. Discharge = 26.30 cumecs<br />

Design discharge <strong>of</strong> 75 Cumec 32.15 % availability


DISCH.(CUMECS)<br />

40<br />

35<br />

30<br />

25<br />

20<br />

15<br />

10<br />

5<br />

0<br />

0.00<br />

CHHATRU HEP FLOW DURATION CURVE (LEAN SEASON)<br />

10.00<br />

20.00<br />

30.00<br />

40.00<br />

50.00<br />

60.00<br />

% OCCURR.<br />

70.00<br />

80.00<br />

90.00<br />

100.00<br />

PLATE 5.2<br />

Series1<br />

%Cumm.occ. Disch.<br />

2.06 35<br />

2.47 30<br />

4.94 25<br />

13.58 20<br />

32.92 15<br />

74.49 10<br />

100.00 5<br />

90% Dep. Discharge = 6.96 Cumecs<br />

50% Dep. Discharge = 12.95 Cumecs


TEN DAILY AVERAGE DISCHARGE DATA OF RIVER CHANDRA AT GHOUSA<br />

Year Period 1973-74 1974-75 1975-76 1976-77 1977-78 1978-79 1979-80<br />

I 279 98 196 208 135 237 101<br />

June II 464 163 271 163 93 215 205<br />

III 402 110 306 139 281 411 403<br />

I 383 154 228 269 370 443 359<br />

July II 403 289 403 352 347 369 431<br />

III 330 238 278 372 294 360 346<br />

I 323 262 329 262 349 368 386<br />

Aug. II 229 222 357 233 249 289 322<br />

III 266 205 236 184 221 259 236<br />

I 217 136 183 156 189 126 213<br />

Sept. II 198 100 127 84 109 105 112<br />

III 136 66 80 69 71 83 51<br />

I 48 35 61 49 50 56 48<br />

Oct. II 31 27 51 31 34 44 39<br />

III 26 22 33 23 29 38 34<br />

I 22 18 23 21 26 28 31<br />

Nov. II 19 17 20 19 22 25 27<br />

III 18 16 18 17 21 25 26<br />

I 18 15 16 16 20 23 25<br />

Dec. II 17 13 14 14 17 22 23<br />

III 17 14 13 13 15 22 23<br />

I 16 14 12 12 13 22 20<br />

Jan. II 14 14 12 11 15 19 19<br />

III 17 12 11 9 14 18 18<br />

I 14 14 12 13 13 20 23<br />

Feb. II 17 14 8 12 12 18 20<br />

III 15 14 10 12 18 16 22<br />

I 14 11 12 12 12 17 20<br />

March II 15 12 11 12 12 22 22<br />

III 19 16 10 17 15 28 24<br />

I 21 18 10 20 16 31 26<br />

April II 26 25 16 19 26 38 29<br />

III 43 35 40 24 33 63 32<br />

I 66 51 57 24 102 88 66<br />

May II 57 111 88 36 159 77 90<br />

III 64 143 122 88 181 76 122<br />

TEN DAILY AVERAGE DISCHARGE DATA OF RIVER CHENAB AT UDAIPUR<br />

Month Period 1973-74 1974-75 1975-76 1976-77 1977-78 1978-79 1979-80<br />

I 195 361 477 258 456 197<br />

June II 318 558 351 184 424 401<br />

III 203 651 287 633 845 806<br />

I 299 513 574 828 904 736<br />

July II 636 887 721 754 700 927


III 504 618 755 601 700 698<br />

I 524 731 569 724 725 817<br />

Aug. II 430 856 518 501 619 666<br />

III 417 535 381 468 528 437<br />

I 293 718 326 396 253 423<br />

Sept. II 205 288 178 226 221 216<br />

III 144 177 159 151 164 130<br />

I 82 148 118 109 121 127<br />

Oct. II 67 121 70 80 96 108<br />

III 55 79 56 69 79 91<br />

I 46 58 52 57 59 83<br />

Nov. II 40 49 44 49 49 70<br />

III 36 42 37 44 44 65<br />

I 36 39 34 38 40 59<br />

Dec. II 35 33 31 35 38 57<br />

III 35 32 31 33 35 57<br />

I 24 32 33 30 32 41 57<br />

Jan. II 22 31 33 29 33 42 56<br />

III 23 26 32 155 32 40 52<br />

I 21 27 31 33 32 39 58<br />

Feb. II 23 31 25 27 27 38 57<br />

III 21 32 28 26 32 - 54<br />

I 23 30 31 28 31 - 51<br />

March II 23 31 29 29 31 - 51<br />

III 35 31 28 37 36 - 51<br />

I 42 38 34 40 38 - 58<br />

April II 53 54 42 39 66 91 71<br />

III 75 71 101 47 82 144 95<br />

I 137 108 131 50 197 179 155<br />

May II 106 228 189 75 290 163 182<br />

III 125 277 276 168 336 145 240


AL (in cu.M/Sec.) FROM 1973-74 Nov.2000.<br />

1980-81 1981-82 1982-83 1983-84 1984-85 1985-86 1986-87 1987-88 1988-89<br />

202 151 122 133 256 186 95 165 155<br />

235 152 232 148 248 220 228 170 199<br />

334 315 213 219 299 255 391 224 392<br />

352 277 283 269 289 294 331 386 393<br />

340 357 314 224 220 340 382 414 375<br />

313 376 353 337 267 271 417 451 378<br />

339 324 379 397 300 286 374 359 328<br />

223 296 335 358 321 283 338 335 333<br />

251 216 247 354 262 250 228 345 238<br />

157 169 163 288 166 200 207 259 198<br />

99 94 151 202 121 112 105 168 167<br />

69 86 115 108 60 81 80 129 168<br />

54 47 80 76 37 65 49 74 79<br />

35 39 70 51 38 42 37 52 57<br />

28 25 39 33 37 34 27 45 48<br />

21 23 26 27 34 29 23 43 43<br />

20 20 25 25 31 22 23 40 39<br />

20 18 22 23 26 21 20 37 37<br />

18 17 18 20 25 20 19 29 31<br />

17 15 15 19 34 18 19 24 29<br />

16 14 14 18 23 16 18 20 25<br />

17 14 15 19 19 15 19 19 23<br />

16 14 15 19 18 15 19 18 20<br />

15 12 15 18 17 15 20 17 19<br />

15 13 14 17 15 15 19 17 18<br />

16 14 14 17 18 14 18 17 17<br />

18 13 14 16 18 14 17 16 15<br />

17 15 18 16 21 14 18 17 17<br />

17 15 20 18 22 14 17 24 17<br />

18 14 18 19 23 15 17 34 18<br />

19 16 18 20 24 16 18 28 18<br />

26 17 18 20 29 18 19 54 20<br />

37 25 21 26 45 21 44 97 21<br />

131 49 37 45 56 45 64 94 25<br />

166 44 56 74 71 121 55 118 51<br />

195 76 83 125 159 69 74 122 132<br />

(in cu.M/Sec.) FROM Jan.1973-74 May.2001.<br />

1980-81 1981-82 1982-83 1983-84 1984-85 1985-86 1986-87 1987-88 1988-89<br />

395 292 320 264 615 379 207 330 420<br />

481 311 537 310 555 469 499 383 535<br />

696 738 519 555 643 511 810 546 958<br />

731 582 582 497 576 579 685 717 950<br />

762 779 705 350 437 666 797 709 811


635 818 903 725 556 535 819 863 920<br />

750 694 861 903 598 585 697 624 710<br />

423 628 664 686 639 564 648 577 704<br />

473 467 425 697 536 520 482 631 493<br />

301 370 338 597 362 392 424 532 416<br />

213 221 339 406 239 240 197 352 306<br />

165 211 136 195 112 165 181 273 274<br />

150 125 84 142 78 127 109 132 170<br />

116 108 71 99 65 80 78 100 132<br />

95 92 63 62 60 63 64 80 98<br />

84 76 53 50 48 54 53 78 85<br />

77 57 48 48 43 49 49 75 75<br />

72 53 44 44 41 46 45 71 64<br />

68 49 42 42 38 41 40 68 57<br />

67 45 42 39 37 38 37 64 52<br />

65 44 39 36 36 36 34 62 47<br />

65 36 31 35 36 37 34 57 39<br />

62 35 29 35 34 35 33 55 36<br />

65 33 28 32 31 34 32 52 36<br />

59 36 27 30 31 34 31 51 34<br />

64 35 26 28 30 34 36 49 35<br />

64 37 24 22 31 35 38 48 32<br />

61 37 26 33 33 35 42 57 33<br />

60 37 30 33 31 49 52 77 34<br />

65 38 32 36 36 35 54 70 43<br />

70 45 44 42 36 37 65 100 36<br />

100 56 45 51 42 65 82 143 40<br />

149 80 45 69 63 103 102 187 44<br />

304 138 100 128 93 143 110 243 51<br />

321 109 173 180 120 245 111 350 73<br />

405 179 167 353 386 170 156 377 181


1989-90 1990-91 1991-92 1992-93 1993-94 1994-95 1995-96 1996-97 1997-98<br />

292 176 213 90 156 215 156 169 67<br />

215 174 301 205 220 220 328 299 174<br />

257 449 352 263 260 311 273 351 230<br />

240 402 448 202 289 379 415 263 257<br />

356 285 433 299 326 402 365 290 319<br />

456 284 397 332 192 362 262 323 344<br />

209 335 326 247 245 329 254 345 272<br />

290 283 253 236 184 265 256 343 249<br />

266 266 247 248 204 370 237 249 216<br />

133 200 226 212 163 195 263 186 161<br />

126 148 178 104 190 140 181 120 161<br />

106 112 103 67 75 74 117 103 121<br />

64 69 72 60 58 63 78 77 67<br />

43 53 54 49 45 46 59 60 50<br />

37 42 44 44 34 38 45 52 44<br />

33 38 38 34 30 38 36 46 41<br />

30 37 30 28 25 36 32 44 38<br />

27 34 26 25 23 34 31 41 36<br />

28 27 23 24 23 33 32 40 34<br />

26 23 21 23 22 31 25 39 33<br />

24 21 20 23 20 30 25 37 32<br />

24 19 19 21 19 29 25 36 30<br />

23 19 19 20 18 27 25 34 30<br />

23 17 18 19 17 24 26 32 29<br />

22 16 18 18 17 23 22 34 27<br />

23 14 18 17 17 23 23 34 27<br />

22 14 17 18 17 24 21 33 30<br />

23 12 18 18 19 24 23 33 30<br />

25 16 19 19 21 26 23 34 31<br />

26 17 18 19 23 27 27 39 32<br />

26 20 19 21 23 28 27 37 34<br />

28 18 23 23 28 29 27 39 37<br />

33 30 29 31 33 28 29 39 40<br />

62 61 34 50 52 32 33 43 46<br />

140 97 48 45 58 90 31 43 53<br />

184 90 70 85 150 105 74 52 154<br />

1989-90 1990-91 1991-92 1992-93 1993-94 1994-95 1995-96 1996-97 1997-98<br />

497 503 589 490 305 388 409 253 251<br />

445 459 775 700 471 362 831 542 211<br />

530 989 826 909 458 996 589 703 362<br />

501 886 905 825 648 954 776 140 344<br />

694 721 975 864 650 758 837 298 524


992 634 1025 950 451 747 677 312 561<br />

525 820 820 816 496 753 548 216 569<br />

639 582 487 631 398 612 658 182 604<br />

569 590 510 650 469 653 605 163 523<br />

314 424 473 472 356 511 452 407 437<br />

326 215 415 218 246 220 276 366 294<br />

257 125 234 163 200 129 204 295 169<br />

175 88 163 136 130 117 170 187 95<br />

131 72 125 104 108 96 145 158 57<br />

101 64 96 89 80 73 167 132 59<br />

90 58 88 82 77 73 100 85 62<br />

85 43 82 80 80 70 74 69 62<br />

81 31 78 75 74 67 61 62 57<br />

78 39 72 68 68 64 59 67 53<br />

70 37 68 61 67 60 56 64 50<br />

64 38 63 56 56 60 53 62 54<br />

61 34 56 48 50 63 56 60 48<br />

56 29 54 46 48 63 58 57 47<br />

53 29 54 44 44 61 56 57 45<br />

50 38 59 41 46 60 58 60 42<br />

47 28 54 41 45 63 63 59 43<br />

44 30 52 41 53 62 61 67 46<br />

43 31 52 45 44 60 65 85 56<br />

43 45 61 44 53 63 62 106 58<br />

49 69 72 42 64 64 30 96 76<br />

50 98 73 42 68 69 80 67 86<br />

59 136 84 50 69 77 98 64 114<br />

82 162 110 74 88 88 111 72 172<br />

133 178 152 118 115 97 125 78 202<br />

348 220 233 124 134 101 131 54 244<br />

545 246 326 168 194 128 121 109 398


1998-99 1999-2000 2000-01<br />

221 147 130<br />

175 278 187<br />

286 384 245<br />

485 429 236<br />

520 435 248<br />

453 344 292<br />

442 371 278<br />

426 293 248<br />

351 321 263<br />

296 240 200<br />

227 221 135<br />

128 197 92<br />

105 118 58<br />

75 72 53<br />

69 67 50<br />

66 67 51<br />

57 66 45<br />

45 61 41<br />

40 59<br />

38 57<br />

36 57<br />

35 43<br />

34 42<br />

32 41<br />

31 55<br />

30 55<br />

29 46<br />

30 50<br />

30 46<br />

33 43<br />

34 42<br />

40 42<br />

124 45<br />

164 86<br />

193 197<br />

218 187<br />

1998-99 1999-2000 2000-01<br />

466 273 290<br />

333 590 451<br />

717 777 675<br />

968 1032 655<br />

815 908 725


610 712 944<br />

708 881 674<br />

709 588 670<br />

564 591 641<br />

504 470 500<br />

322 427 336<br />

264 319 207<br />

152 202 166<br />

132 121 143<br />

110 109 135<br />

91 96 130<br />

81 85 104<br />

70 72 91<br />

61 66 85<br />

55 63 83<br />

48 61 80<br />

49 53 77<br />

47 49 67<br />

45 49 71<br />

57 48 65<br />

58 46 65<br />

55 48 65<br />

55 47 66<br />

55 47 71<br />

60 52 75<br />

72 69 72<br />

118 97 86<br />

281 117 98<br />

255 193 152<br />

360 411 257<br />

397 430 293


Table-5.3(1)<br />

REGRESSION ANALYSIS BETWEEN DISCHARGES OF TANDI AND GHOUSAL JUNE- JULY<br />

TANDI GHOUSAL DEVIATION FROM MEAN<br />

D/SITE D/SITE X Y X^2 X*Y<br />

YEAR MONTH Qx Qy LOG x LOG y LOGx-LOGX' LOGy-LOGy'<br />

(Cumecs) (Cumecs)<br />

I 54.28 98.00 1.7346 1.9912 -0.3652 -0.3987 0.1334 0.1456<br />

1974 JUN II 85.59 163.00 1.9324 2.2122 -0.1674 -0.1777 0.0280 0.0298<br />

III 57.44 110.00 1.7592 2.0414 -0.3406 -0.3485 0.1160 0.1187<br />

I 92.61 154.00 1.9667 2.1875 -0.1332 -0.2024 0.0177 0.0270<br />

JUL II 163.53 289.00 2.2136 2.4609 0.1138 0.0710 0.0129 0.0081<br />

III 136.12 238.00 2.1339 2.3766 0.0341 -0.0133 0.0012 -0.0005<br />

I 86.44 196.00 1.9367 2.2923 -0.1631 -0.0977 0.0266 0.0159<br />

1975 JUN II 127.51 271.00 2.1055 2.4330 0.0057 0.0430 0.0000 0.0002<br />

III 162.02 306.00 2.2096 2.4857 0.1098 0.0958 0.0120 0.0105<br />

I 132.00 228.00 2.1206 2.3579 0.0208 -0.0320 0.0004 -0.0007<br />

JUL II 210.91 403.00 2.3241 2.6053 0.2243 0.2154 0.0503 0.0483<br />

III 151.52 278.00 2.1805 2.4440 0.0807 0.0541 0.0065 0.0044<br />

I 109.18 208.00 2.0381 2.3181 -0.0617 -0.0719 0.0038 0.0044<br />

1976 JUN II 84.79 163.00 1.9283 2.2122 -0.1715 -0.1777 0.0294 0.0305<br />

III 63.81 139.00 1.8049 2.1430 -0.2949 -0.2469 0.0870 0.0728<br />

I 146.59 269.00 2.1661 2.4298 0.0663 0.0398 0.0044 0.0026<br />

JUL II 208.80 352.00 2.3197 2.5465 0.2199 0.1566 0.0484 0.0344<br />

III 208.87 372.00 2.3199 2.5705 0.2201 0.1806 0.0484 0.0397<br />

I 61.59 135.00 1.7895 2.1303 -0.3103 -0.2596 0.0963 0.0806<br />

1977 JUN II 48.04 93.00 1.6816 1.9685 -0.4182 -0.4214 0.1749 0.1763<br />

III 155.71 281.00 2.1923 2.4487 0.0925 0.0588 0.0086 0.0054<br />

I 209.09 370.00 2.3203 2.5682 0.2205 0.1783 0.0486 0.0393<br />

JUL II 185.87 347.00 2.2692 2.5403 0.1694 0.1504 0.0287 0.0255<br />

III 156.26 294.00 2.1938 2.4683 0.0940 0.0784 0.0088 0.0074<br />

I 116.06 237.00 2.0647 2.3747 -0.0351 -0.0152 0.0012 0.0005<br />

1978 JUN II 97.95 215.00 1.9910 2.3324 -0.1088 -0.0575 0.0118 0.0063<br />

III 229.03 411.00 2.3599 2.6138 0.2601 0.2239 0.0676 0.0582<br />

I 204.43 443.00 2.3105 2.6464 0.2107 0.2565 0.0444 0.0540<br />

JUL II 171.15 369.00 2.2334 2.5670 0.1336 0.1771 0.0178 0.0237<br />

III 176.99 360.00 2.2479 2.5563 0.1481 0.1664 0.0219 0.0246<br />

I 40.70 101.00 1.6096 2.0043 -0.4902 -0.3856 0.2403 0.1890<br />

1979 JUN II 90.39 205.00 1.9561 2.3118 -0.1437 -0.0782 0.0206 0.0112<br />

III 194.47 403.00 2.2889 2.6053 0.1890 0.2154 0.0357 0.0407<br />

I 182.98 359.00 2.2624 2.5551 0.1626 0.1652 0.0264 0.0269<br />

JUL II 229.97 431.00 2.3617 2.6345 0.2619 0.2446 0.0686 0.0640<br />

III 173.08 346.00 2.2382 2.5391 0.1384 0.1492 0.0192 0.0206<br />

I 99.89 202.00 1.9995 2.3054 -0.1003 -0.0846 0.0101 0.0085<br />

1980 JUN II 121.45 235.00 2.0844 2.3711 -0.0154 -0.0189 0.0002 0.0003<br />

III 173.78 334.00 2.2400 2.5237 0.1402 0.1338 0.0197 0.0188<br />

I 184.27 352.00 2.2655 2.5465 0.1656 0.1566 0.0274 0.0259<br />

JUL II 184.29 340.00 2.2655 2.5315 0.1657 0.1416 0.0275 0.0235<br />

III 161.10 313.00 2.2071 2.4955 0.1073 0.1056 0.0115 0.0113<br />

I 70.07 151.00 1.8455 2.1790 -0.2543 -0.2109 0.0647 0.0536<br />

1981 JUN II 77.57 152.00 1.8897 2.1818 -0.2101 -0.2081 0.0442 0.0437<br />

III 186.01 315.00 2.2695 2.4983 0.1697 0.1084 0.0288 0.0184<br />

I 141.26 277.00 2.1500 2.4425 0.0502 0.0526 0.0025 0.0026<br />

JUL II 169.95 357.00 2.2303 2.5527 0.1305 0.1627 0.0170 0.0212<br />

III 196.92 376.00 2.2943 2.5752 0.1945 0.1853 0.0378 0.0360<br />

I 60.53 122.00 1.7820 2.0864 -0.3178 -0.3036 0.1010 0.0965<br />

1982 JUN II 100.83 232.00 2.0036 2.3655 -0.0962 -0.0244 0.0093 0.0024<br />

III 115.64 213.00 2.0631 2.3284 -0.0367 -0.0615 0.0013 0.0023<br />

I 156.48 283.00 2.1945 2.4518 0.0946 0.0619 0.0090 0.0059<br />

JUL II 150.71 314.00 2.1781 2.4969 0.0783 0.1070 0.0061 0.0084<br />

III 186.55 353.00 2.2708 2.5478 0.1710 0.1579 0.0292 0.0270<br />

I 71.20 133.00 1.8525 2.1239 -0.2473 -0.2661 0.0612 0.0658<br />

1983 JUN II 83.29 148.00 1.9206 2.1703 -0.1792 -0.2197 0.0321 0.0394<br />

III 108.14 219.00 2.0340 2.3404 -0.0658 -0.0495 0.0043 0.0033<br />

I 133.41 269.00 2.1252 2.4298 0.0254 0.0398 0.0006 0.0010<br />

JUL II 89.79 224.00 1.9532 2.3502 -0.1466 -0.0397 0.0215 0.0058<br />

III 201.52 337.00 2.3043 2.5276 0.2045 0.1377 0.0418 0.0282<br />

G.TOTAL 125.99 143.40 0.00 0.00 2.18 2.00<br />

NO. OF PERIOD 60 LOG x' LOG y'<br />

AVERAGE<br />

Co-efficient <strong>of</strong> Corelation<br />

2.0998 2.3899<br />

b = SIGMA X*Y = 0.9168<br />

SIGMA X^2


REGRESSION ANALYSIS BETWEEN DISCHARGES OF TANDI AND GHOUSAL AUG.- SEPT.<br />

TANDI GHOUSAL DEVIATION FROM MEAN<br />

D/SITE D/SITE X Y X^2 X*Y<br />

YEAR MONTH Qx Qy LOG x LOG y LOGx-LOGX' LOGy-LOGy'<br />

(Cumecs) (Cumecs)<br />

I 140.96 262.00 2.1491 2.4183 0.1890 0.1610 0.0357 0.0304<br />

1974 AUG II 108.22 222.00 2.0343 2.3464 0.0742 0.0890 0.0055 0.0066<br />

III 106.99 205.00 2.0293 2.3118 0.0693 0.0544 0.0048 0.0038<br />

I 75.23 136.00 1.8764 2.1335 -0.0837 -0.1238 0.0070 0.0104<br />

SEPT II 60.48 100.00 1.7816 2.0000 -0.1785 -0.2573 0.0318 0.0459<br />

III 41.41 66.00 1.6171 1.8195 -0.3430 -0.4378 0.1176 0.1501<br />

I 182.62 329.00 2.2615 2.5172 0.3015 0.2599 0.0909 0.0784<br />

1975 AUG II 218.79 357.00 2.3400 2.5527 0.3800 0.2954 0.1444 0.1122<br />

III 134.86 236.00 2.1299 2.3729 0.1698 0.1156 0.0288 0.0196<br />

I 101.37 183.00 2.0059 2.2625 0.0458 0.0051 0.0021 0.0002<br />

SEPT II 73.70 127.00 1.8675 2.1038 -0.0926 -0.1535 0.0086 0.0142<br />

III 44.74 80.00 1.6507 1.9031 -0.3094 -0.3542 0.0957 0.1096<br />

I 146.32 262.00 2.1653 2.4183 0.2052 0.1610 0.0421 0.0330<br />

1976 AUG II 127.47 233.00 2.1054 2.3674 0.1453 0.1100 0.0211 0.0160<br />

III 98.12 184.00 1.9918 2.2648 0.0317 0.0075 0.0010 0.0002<br />

I 84.73 156.00 1.9280 2.1931 -0.0320 -0.0642 0.0010 0.0021<br />

SEPT II 54.96 84.00 1.7400 1.9243 -0.2200 -0.3330 0.0484 0.0733<br />

III 44.35 69.00 1.6469 1.8388 -0.3132 -0.4185 0.0981 0.1310<br />

I 181.88 349.00 2.2598 2.5428 0.2997 0.2855 0.0898 0.0856<br />

1977 AUG II 119 249.00 2.0755 2.3962 0.1155 0.1389 0.0133 0.0160<br />

III 109.56 221.00 2.0397 2.3444 0.0796 0.0871 0.0063 0.0069<br />

I 92.03 189.00 1.9639 2.2765 0.0039 0.0192 0.0000 0.0001<br />

SEPT II 61.94 109.00 1.7920 2.0374 -0.1681 -0.2199 0.0283 0.0370<br />

III 43.63 71.00 1.6398 1.8513 -0.3203 -0.4061 0.1026 0.1300<br />

I 182.35 368.00 2.2609 2.5658 0.3008 0.3085 0.0905 0.0928<br />

1978 AUG II 146.17 289.00 2.1649 2.4609 0.2048 0.2036 0.0419 0.0417<br />

III 119.00 259.00 2.0755 2.4133 0.1155 0.1560 0.0133 0.0180<br />

I 60.00 126.00 1.7782 2.1004 -0.1819 -0.1569 0.0331 0.0285<br />

SEPT II 37.98 105.00 1.5796 2.0212 -0.3805 -0.2361 0.1448 0.0898<br />

III 53.28 83.00 1.7266 1.9191 -0.2335 -0.3382 0.0545 0.0790<br />

I 188.89 386.00 2.2762 2.5866 0.3161 0.3293 0.0999 0.1041<br />

1979 AUG II 156.29 322.00 2.1939 2.5079 0.2339 0.2505 0.0547 0.0586<br />

III 99.16 236.00 1.9963 2.3729 0.0363 0.1156 0.0013 0.0042<br />

I 98.36 213.00 1.9928 2.3284 0.0328 0.0711 0.0011 0.0023<br />

SEPT II 52.16 112.00 1.7173 2.0492 -0.2427 -0.2081 0.0589 0.0505<br />

III 23.60 51.00 1.3729 1.7076 -0.5872 -0.5497 0.3447 0.3228<br />

I 176.94 339.00 2.2478 2.5302 0.2878 0.2729 0.0828 0.0785<br />

1980 AUG II 95.18 223.00 1.9785 2.3483 0.0185 0.0910 0.0003 0.0017<br />

III 105.30 251.00 2.0224 2.3997 0.0624 0.1424 0.0039 0.0089<br />

I 68.52 157.00 1.8358 2.1959 -0.1242 -0.0614 0.0154 0.0076<br />

SEPT II 45.10 99.00 1.6542 1.9956 -0.3059 -0.2617 0.0936 0.0800<br />

III 30.36 69.00 1.4823 1.8388 -0.4778 -0.4185 0.2283 0.1999<br />

I 163.37 324.00 2.2132 2.5105 0.2531 0.2532 0.0641 0.0641<br />

1981 AUG II 145.32 296.00 2.1623 2.4713 0.2023 0.2140 0.0409 0.0433<br />

III 87.76 216.00 1.9433 2.3345 -0.0168 0.0771 0.0003 -0.0013<br />

I 81.66 169.00 1.9120 2.2279 -0.0481 -0.0294 0.0023 0.0014<br />

SEPT II 47.39 94.00 1.6757 1.9731 -0.2844 -0.2842 0.0809 0.0808<br />

III 39.77 86.00 1.5996 1.9345 -0.3605 -0.3228 0.1300 0.1164<br />

I 199.82 379.00 2.3006 2.5786 0.3406 0.3213 0.1160 0.1094<br />

1982 AUG II 151.72 335.00 2.1810 2.5250 0.2210 0.2677 0.0488 0.0592<br />

III 97.35 247.00 1.9883 2.3927 0.0283 0.1354 0.0008 0.0038<br />

I 88.49 163.00 1.9469 2.2122 -0.0132 -0.0451 0.0002 0.0006<br />

SEPT II 68.20 151.00 1.8338 2.1790 -0.1263 -0.0783 0.0159 0.0099<br />

III 37.19 115.00 1.5704 2.0607 -0.3896 -0.1966 0.1518 0.0766<br />

I 246.85 397.00 2.3924 2.5988 0.4324 0.3415 0.1869 0.1476<br />

1983 AUG II 188.24 358.00 2.2747 2.5539 0.3146 0.2966 0.0990 0.0933<br />

III 185.17 354.00 2.2676 2.5490 0.3075 0.2917 0.0946 0.0897<br />

I 149.26 288.00 2.1739 2.4594 0.2139 0.2021 0.0457 0.0432<br />

SEPT II 97.29 202.00 1.9881 2.3054 0.0280 0.0480 0.0008 0.0013<br />

III 53.98 108.00 1.7322 2.0334 -0.2278 -0.2239 0.0519 0.0510<br />

G.TOTAL 117.60 135.44 0.00 0.00 3.52 3.37<br />

NO. OF PERIOD 60 LOG x' LOG y'<br />

AVERAGE 1.9601 2.2573<br />

Co-efficient <strong>of</strong> Corelation<br />

b = SIGMA X*Y = 0.9583<br />

SIGMA X^2<br />

Table-5.3(2)


Table-5.3(3)<br />

REGRESSION ANALYSIS BETWEEN DISCHARGES OF TANDI AND GHOUSAL ( NON-MONSOON PERIOD)<br />

TANDI GHOUSAL DEVIATION FROM MEAN<br />

D/SITE D/SITE X Y X^2 X*Y<br />

YEAR MONTH Qx Qy LOG x LOG y LOGx-LOGX' LOGy-LOGy'<br />

(Cumecs) (Cumecs)<br />

I 24.62 35.00 1.3913 1.5441 0.2877 0.1687 0.0828 0.0485<br />

1974-75 OCT II 21.58 27.00 1.3341 1.4314 0.2305 0.0560 0.0531 0.0129<br />

III 17.31 22.00 1.2383 1.3424 0.1347 -0.0329 0.0181 -0.0044<br />

I 14.92 18.00 1.1738 1.2553 0.0702 -0.1201 0.0049 -0.0084<br />

NOV II 18.83 17.00 1.2749 1.2304 0.1713 -0.1449 0.0293 -0.0248<br />

III 11.45 16.00 1.0588 1.2041 -0.0448 -0.1712 0.0020 0.0077<br />

I 10.69 15.00 1.0290 1.1761 -0.0746 -0.1992 0.0056 0.0149<br />

DEC II 10.43 13.00 1.0183 1.1139 -0.0853 -0.2614 0.0073 0.0223<br />

III 10.42 14.00 1.0179 1.1461 -0.0857 -0.2292 0.0073 0.0196<br />

I 8.38 14.00 0.9232 1.1461 -0.1803 -0.2292 0.0325 0.0413<br />

JAN II 8.07 14.00 0.9069 1.1461 -0.1967 -0.2292 0.0387 0.0451<br />

III 7.60 12.00 0.8808 1.0792 -0.2228 -0.2961 0.0496 0.0660<br />

I 8.19 14.00 0.9133 1.1461 -0.1903 -0.2292 0.0362 0.0436<br />

FEB II 7.59 14.00 0.8802 1.1461 -0.2233 -0.2292 0.0499 0.0512<br />

III 9.12 14.00 0.9600 1.1461 -0.1436 -0.2292 0.0206 0.0329<br />

I 7.30 11.00 0.8633 1.0414 -0.2403 -0.3339 0.0577 0.0802<br />

MAR II 6.43 12.00 0.8082 1.0792 -0.2954 -0.2961 0.0872 0.0875<br />

III 7.26 16.00 0.8609 1.2041 -0.2427 -0.1712 0.0589 0.0415<br />

I 8.42 18.00 0.9253 1.2553 -0.1783 -0.1201 0.0318 0.0214<br />

APR II 10.38 25.00 1.0162 1.3979 -0.0874 0.0226 0.0076 -0.0020<br />

III 13.70 35.00 1.1367 1.5441 0.0331 0.1687 0.0011 0.0056<br />

I 23.16 51.00 1.3647 1.7076 0.2612 0.3322 0.0682 0.0868<br />

MAY II 47.15 111.00 1.6735 2.0453 0.5699 0.6700 0.3248 0.3818<br />

III 62.11 143.00 1.7932 2.1553 0.6896 0.7800 0.4755 0.5379<br />

I 36.47 61.00 1.5619 1.7853 0.4583 0.4100 0.2101 0.1879<br />

1975-76 OCT II 30.99 51.00 1.4912 1.7076 0.3876 0.3322 0.1503 0.1288<br />

III 21.50 33.00 1.3324 1.5185 0.2289 0.1432 0.0524 0.0328<br />

I 16.53 23.00 1.2183 1.3617 0.1147 -0.0136 0.0132 -0.0016<br />

NOV II 14.42 20.00 1.1590 1.3010 0.0554 -0.0743 0.0031 -0.0041<br />

III 13.23 18.00 1.1216 1.2553 0.0180 -0.1201 0.0003 -0.0022<br />

I 13.32 16.00 1.1245 1.2041 0.0209 -0.1712 0.0004 -0.0036<br />

DEC II 12.02 14.00 1.0799 1.1461 -0.0237 -0.2292 0.0006 0.0054<br />

III 11.75 13.00 1.0700 1.1139 -0.0336 -0.2614 0.0011 0.0088<br />

I 12.16 12.00 1.0849 1.0792 -0.0187 -0.2961 0.0003 0.0055<br />

JAN II 11.46 12.00 1.0592 1.0792 -0.0444 -0.2961 0.0020 0.0131<br />

III 10.84 11.00 1.0350 1.0414 -0.0686 -0.3339 0.0047 0.0229<br />

I 10.41 12.00 1.0175 1.0792 -0.0861 -0.2961 0.0074 0.0255<br />

FEB II 10.21 8.00 1.0090 0.9031 -0.0946 -0.4722 0.0089 0.0447<br />

III 10.03 10.00 1.0013 1.0000 -0.1023 -0.3753 0.0105 0.0384<br />

I 10.49 12.00 1.0208 1.0792 -0.0828 -0.2961 0.0069 0.0245<br />

MAR II 10.10 11.00 1.0043 1.0414 -0.0993 -0.3339 0.0099 0.0331<br />

III 10.13 10.00 1.0056 1.0000 -0.0980 -0.3753 0.0096 0.0368<br />

I 10.08 10.00 1.0035 1.0000 -0.1001 -0.3753 0.0100 0.0376<br />

APR II 10.91 16.00 1.0378 1.2041 -0.0658 -0.1712 0.0043 0.0113<br />

III 20.08 40.00 1.3028 1.6021 0.1992 0.2267 0.0397 0.0452<br />

I 26.13 57.00 1.4171 1.7559 0.3136 0.3805 0.0983 0.1193<br />

MAY II 39.74 88.00 1.5992 1.9445 0.4956 0.5692 0.2457 0.2821<br />

III 62.72 122.00 1.7974 2.0864 0.6938 0.7110 0.4814 0.4933<br />

I 31.29 49.00 1.4954 1.6902 0.3918 0.3149 0.1535 0.1234<br />

1976-77 OCT II 20.19 31.00 1.3051 1.4914 0.2015 0.1160 0.0406 0.0234<br />

III 16.71 23.00 1.2230 1.3617 0.1194 -0.0136 0.0143 -0.0016<br />

I 14.45 21.00 1.1599 1.3222 0.0563 -0.0531 0.0032 -0.0030<br />

NOV II 13.17 19.00 1.1196 1.2788 0.0160 -0.0966 0.0003 -0.0015<br />

III 11.95 17.00 1.0774 1.2304 -0.0262 -0.1449 0.0007 0.0038<br />

I 10.40 16.00 1.0170 1.2041 -0.0866 -0.1712 0.0075 0.0148<br />

DEC II 9.24 14.00 0.9657 1.1461 -0.1379 -0.2292 0.0190 0.0316<br />

III 8.93 13.00 0.9509 1.1139 -0.1527 -0.2614 0.0233 0.0399<br />

I 8.07 12.00 0.9069 1.0792 -0.1967 -0.2961 0.0387 0.0583<br />

JAN II 7.97 11.00 0.9015 1.0414 -0.2021 -0.3339 0.0409 0.0675<br />

III 7.18 9.00 0.8561 0.9542 -0.2475 -0.4211 0.0612 0.1042<br />

I 9.47 13.00 0.9763 1.1139 -0.1272 -0.2614 0.0162 0.0333<br />

FEB II 7.22 12.00 0.8585 1.0792 -0.2451 -0.2961 0.0600 0.0726<br />

III 7.26 12.00 0.8609 1.0792 -0.2427 -0.2961 0.0589 0.0719<br />

I 7.12 12.00 0.8525 1.0792 -0.2511 -0.2961 0.0631 0.0744<br />

MAR II 7.33 12.00 0.8651 1.0792 -0.2385 -0.2961 0.0569 0.0706<br />

III 9.05 17.00 0.9566 1.2304 -0.1469 -0.1449 0.0216 0.0213<br />

I 9.91 20.00 0.9961 1.3010 -0.1075 -0.0743 0.0116 0.0080<br />

APR II 9.31 19.00 0.9689 1.2788 -0.1346 -0.0966 0.0181 0.0130<br />

III 10.28 24.00 1.0120 1.3802 -0.0916 0.0049 0.0084 -0.0004<br />

I 11.33 24.00 1.0542 1.3802 -0.0494 0.0049 0.0024 -0.0002<br />

MAY II 15.18 36.00 1.1813 1.5563 0.0777 0.1810 0.0060 0.0141<br />

III 36.42 88.00 1.5613 1.9445 0.4578 0.5692 0.2095 0.2605<br />

I 30.11 50.00 1.4787 1.6990 0.3751 0.3236 0.1407 0.1214<br />

1977-78 OCT II 23.55 34.00 1.3720 1.5315 0.2684 0.1562 0.0720 0.0419


Table-5.3(4)<br />

TANDI GHOUSAL DEVIATION FROM MEAN<br />

D/SITE D/SITE X Y X^2 X*Y<br />

YEAR MONTH Qx Qy LOG x LOG y LOGx-LOGX' LOGy-LOGy'<br />

(Cumecs) (Cumecs)<br />

III 18.45 29.00 1.2660 1.4624 0.1624 0.0871 0.0264 0.0141<br />

I 15.74 26.00 1.1970 1.4150 0.0934 0.0396 0.0087 0.0037<br />

NOV II 14.3 22.00 1.1553 1.3424 0.0517 -0.0329 0.0027 -0.0017<br />

III 13.85 21.00 1.1414 1.3222 0.0379 -0.0531 0.0014 -0.0020<br />

I 12.17 20.00 1.0853 1.3010 -0.0183 -0.0743 0.0003 0.0014<br />

DEC II 10.86 17.00 1.0358 1.2304 -0.0678 -0.1449 0.0046 0.0098<br />

III 10.35 15.00 1.0149 1.1761 -0.0886 -0.1992 0.0079 0.0177<br />

I 9.94 13.00 0.9974 1.1139 -0.1062 -0.2614 0.0113 0.0278<br />

JAN II 11.57 15.00 1.0633 1.1761 -0.0403 -0.1992 0.0016 0.0080<br />

III 10.35 14.00 1.0149 1.1461 -0.0886 -0.2292 0.0079 0.0203<br />

I 9.16 13.00 0.9619 1.1139 -0.1417 -0.2614 0.0201 0.0370<br />

FEB II 10.57 12.00 1.0241 1.0792 -0.0795 -0.2961 0.0063 0.0235<br />

III 9.02 18.00 0.9552 1.2553 -0.1484 -0.1201 0.0220 0.0178<br />

I 8.6 12.00 0.9345 1.0792 -0.1691 -0.2961 0.0286 0.0501<br />

MAR II 8.1 12.00 0.9085 1.0792 -0.1951 -0.2961 0.0381 0.0578<br />

III 8.41 15.00 0.9248 1.1761 -0.1788 -0.1992 0.0320 0.0356<br />

I 9.1 16.00 0.9590 1.2041 -0.1445 -0.1712 0.0209 0.0247<br />

APR II 14.41 26.00 1.1587 1.4150 0.0551 0.0396 0.0030 0.0022<br />

III 19.48 33.00 1.2896 1.5185 0.1860 0.1432 0.0346 0.0266<br />

I 44.66 102.00 1.6499 2.0086 0.5463 0.6333 0.2985 0.3460<br />

MAY II 70.87 159.00 1.8505 2.2014 0.7469 0.8261 0.5578 0.6170<br />

III 86.93 181.00 1.9392 2.2577 0.8356 0.8824 0.6982 0.7373<br />

I 24.94 56.00 1.3969 1.7482 0.2933 0.3729 0.0860 0.1094<br />

1978-79 OCT II 17.61 44.00 1.2458 1.6435 0.1422 0.2681 0.0202 0.0381<br />

III 21.49 38.00 1.3322 1.5798 0.2286 0.2045 0.0523 0.0467<br />

I 12.26 28.00 1.0885 1.4472 -0.0151 0.0718 0.0002 -0.0011<br />

NOV II 10.70 25.00 1.0294 1.3979 -0.0742 0.0226 0.0055 -0.0017<br />

III 11.17 25.00 1.0481 1.3979 -0.0555 0.0226 0.0031 -0.0013<br />

I 10.02 23.00 1.0009 1.3617 -0.1027 -0.0136 0.0106 0.0014<br />

DEC II 9.29 22.00 0.9680 1.3424 -0.1356 -0.0329 0.0184 0.0045<br />

III 9.17 22.00 0.9624 1.3424 -0.1412 -0.0329 0.0199 0.0046<br />

I 8.52 22.00 0.9304 1.3424 -0.1731 -0.0329 0.0300 0.0057<br />

JAN II 7.92 19.00 0.8987 1.2788 -0.2049 -0.0966 0.0420 0.0198<br />

III 8.07 18.00 0.9069 1.2553 -0.1967 -0.1201 0.0387 0.0236<br />

I 7.86 20.00 0.8954 1.3010 -0.2082 -0.0743 0.0433 0.0155<br />

FEB II 7.12 18.00 0.8525 1.2553 -0.2511 -0.1201 0.0631 0.0301<br />

III 9.41 16.00 0.9736 1.2041 -0.1300 -0.1712 0.0169 0.0223<br />

I 8.35 17.00 0.9217 1.2304 -0.1819 -0.1449 0.0331 0.0264<br />

MAR II 18.35 22.00 1.2636 1.3424 0.1600 -0.0329 0.0256 -0.0053<br />

III 28.50 28.00 1.4548 1.4472 0.3513 0.0718 0.1234 0.0252<br />

I 20.00 31.00 1.3010 1.4914 0.1974 0.1160 0.0390 0.0229<br />

APR II 16.00 38.00 1.2041 1.5798 0.1005 0.2045 0.0101 0.0206<br />

III 25.02 63.00 1.3983 1.7993 0.2947 0.4240 0.0868 0.1250<br />

I 30.02 88.00 1.4774 1.9445 0.3738 0.5692 0.1397 0.2128<br />

MAY II 25.58 77.00 1.4079 1.8865 0.3043 0.5112 0.0926 0.1556<br />

III 24.78 76.00 1.3941 1.8808 0.2905 0.5055 0.0844 0.1469<br />

I 20.72 48.00 1.3164 1.6812 0.2128 0.3059 0.0453 0.0651<br />

1979-80 OCT II 17.94 39.00 1.2538 1.5911 0.1502 0.2157 0.0226 0.0324<br />

III 14.83 34.00 1.1711 1.5315 0.0676 0.1562 0.0046 0.0105<br />

I 13.23 31.00 1.1216 1.4914 0.0180 0.1160 0.0003 0.0021<br />

NOV II 10.74 27.00 1.0310 1.4314 -0.0726 0.0560 0.0053 -0.0041<br />

III 10.24 26.00 1.0103 1.4150 -0.0933 0.0396 0.0087 -0.0037<br />

I 9.74 25.00 0.9886 1.3979 -0.1150 0.0226 0.0132 -0.0026<br />

DEC II 8.93 23.00 0.9509 1.3617 -0.1527 -0.0136 0.0233 0.0021<br />

III 8.86 23.00 0.9474 1.3617 -0.1562 -0.0136 0.0244 0.0021<br />

I 7.68 20.00 0.8854 1.3010 -0.2182 -0.0743 0.0476 0.0162<br />

JAN II 7.76 19.00 0.8899 1.2788 -0.2137 -0.0966 0.0457 0.0206<br />

III 6.08 18.00 0.7839 1.2553 -0.3197 -0.1201 0.1022 0.0384<br />

I 6.54 23.00 0.8156 1.3617 -0.2880 -0.0136 0.0829 0.0039<br />

FEB II 6.83 20.00 0.8344 1.3010 -0.2692 -0.0743 0.0725 0.0200<br />

III 6.79 22.00 0.8319 1.3424 -0.2717 -0.0329 0.0738 0.0089<br />

I 5.5 20.00 0.7404 1.3010 -0.3632 -0.0743 0.1319 0.0270<br />

MAR II 5.55 22.00 0.7443 1.3424 -0.3593 -0.0329 0.1291 0.0118<br />

III 6.63 24.00 0.8215 1.3802 -0.2821 0.0049 0.0796 -0.0014<br />

I 7.9 26.00 0.8976 1.4150 -0.2060 0.0396 0.0424 -0.0082<br />

APR II 9.03 29.00 0.9557 1.4624 -0.1479 0.0871 0.0219 -0.0129<br />

III 10.98 32.00 1.0406 1.5051 -0.0630 0.1298 0.0040 -0.0082<br />

I 25.76 66.00 1.4109 1.8195 0.3074 0.4442 0.0945 0.1365<br />

MAY II 33.09 90.00 1.5197 1.9542 0.4161 0.5789 0.1731 0.2409<br />

III 55.23 122.00 1.7422 2.0864 0.6386 0.7110 0.4078 0.4541


Table-5.3(5)<br />

TANDI GHOUSAL DEVIATION FROM MEAN<br />

D/SITE D/SITE X Y X^2 X*Y<br />

YEAR MONTH Qx Qy LOG x LOG y LOGx-LOGX' LOGy-LOGy'<br />

(Cumecs) (Cumecs)<br />

I 30.26 54.00 1.4809 1.7324 0.3773 0.3571 0.1423 0.1347<br />

1980-81 OCT II 21.63 35.00 1.3351 1.5441 0.2315 0.1687 0.0536 0.0391<br />

III 17.26 28.00 1.2370 1.4472 0.1335 0.0718 0.0178 0.0096<br />

I 12.35 21.00 1.0917 1.3222 -0.0119 -0.0531 0.0001 0.0006<br />

NOV II 9.02 20.00 0.9552 1.3010 -0.1484 -0.0743 0.0220 0.0110<br />

III 8.62 20.00 0.9355 1.3010 -0.1681 -0.0743 0.0283 0.0125<br />

I 8.16 18.00 0.9117 1.2553 -0.1919 -0.1201 0.0368 0.0230<br />

DEC II 7.82 17.00 0.8932 1.2304 -0.2104 -0.1449 0.0443 0.0305<br />

III 7.64 16.00 0.8831 1.2041 -0.2205 -0.1712 0.0486 0.0378<br />

I 7.71 17.00 0.8871 1.2304 -0.2165 -0.1449 0.0469 0.0314<br />

JAN II 7.35 16.00 0.8663 1.2041 -0.2373 -0.1712 0.0563 0.0406<br />

III 7.36 15.00 0.8669 1.1761 -0.2367 -0.1992 0.0560 0.0472<br />

I 7.46 15.00 0.8727 1.1761 -0.2308 -0.1992 0.0533 0.0460<br />

FEB II 7.07 16.00 0.8494 1.2041 -0.2542 -0.1712 0.0646 0.0435<br />

III 6.76 18.00 0.8299 1.2553 -0.2736 -0.1201 0.0749 0.0329<br />

I 6.76 17.00 0.8299 1.2304 -0.2736 -0.1449 0.0749 0.0396<br />

MAR II 6.60 17.00 0.8195 1.2304 -0.2840 -0.1449 0.0807 0.0412<br />

III 6.80 18.00 0.8325 1.2553 -0.2711 -0.1201 0.0735 0.0325<br />

I 7.44 19.00 0.8716 1.2788 -0.2320 -0.0966 0.0538 0.0224<br />

APR II 9.34 26.00 0.9703 1.4150 -0.1332 0.0396 0.0178 -0.0053<br />

III 33.52 37.00 1.5253 1.5682 0.4217 0.1929 0.1778 0.0813<br />

I 70.93 131.00 1.8508 2.1173 0.7472 0.7419 0.5584 0.5544<br />

MAY II 77.63 166.00 1.8900 2.2201 0.7864 0.8448 0.6185 0.6644<br />

III 92.76 195.00 1.9674 2.2900 0.8638 0.9147 0.7461 0.7901<br />

I 15.05 47.00 1.1775 1.6721 0.0739 0.2968 0.0055 0.0219<br />

1981-82 OCT II 12.80 39.00 1.1072 1.5911 0.0036 0.2157 0.0000 0.0008<br />

III 12.24 25.00 1.0878 1.3979 -0.0158 0.0226 0.0002 -0.0004<br />

I 10.72 23.00 1.0302 1.3617 -0.0734 -0.0136 0.0054 0.0010<br />

NOV II 8.67 20.00 0.9380 1.3010 -0.1656 -0.0743 0.0274 0.0123<br />

III 7.31 18.00 0.8639 1.2553 -0.2397 -0.1201 0.0574 0.0288<br />

I 6.42 17.00 0.8075 1.2304 -0.2961 -0.1449 0.0876 0.0429<br />

DEC II 5.94 15.00 0.7738 1.1761 -0.3298 -0.1992 0.1088 0.0657<br />

III 5.72 14.00 0.7574 1.1461 -0.3462 -0.2292 0.1198 0.0793<br />

I 8.34 14.00 0.9212 1.1461 -0.1824 -0.2292 0.0333 0.0418<br />

JAN II 8.20 14.00 0.9138 1.1461 -0.1898 -0.2292 0.0360 0.0435<br />

III 9.41 12.00 0.9736 1.0792 -0.1300 -0.2961 0.0169 0.0385<br />

I 9.32 13.00 0.9694 1.1139 -0.1342 -0.2614 0.0180 0.0351<br />

FEB II 8.70 14.00 0.9395 1.1461 -0.1641 -0.2292 0.0269 0.0376<br />

III 8.76 13.00 0.9425 1.1139 -0.1611 -0.2614 0.0259 0.0421<br />

I 8.37 15.00 0.9227 1.1761 -0.1809 -0.1992 0.0327 0.0360<br />

MAR II 7.92 15.00 0.8987 1.1761 -0.2049 -0.1992 0.0420 0.0408<br />

III 8.09 14.00 0.9079 1.1461 -0.1956 -0.2292 0.0383 0.0448<br />

I 8.50 16.00 0.9294 1.2041 -0.1742 -0.1712 0.0303 0.0298<br />

APR II 9.13 17.00 0.9605 1.2304 -0.1431 -0.1449 0.0205 0.0207<br />

III 11.40 25.00 1.0569 1.3979 -0.0467 0.0226 0.0022 -0.0011<br />

I 21.96 49.00 1.3416 1.6902 0.2380 0.3149 0.0567 0.0750<br />

MAY II 20.11 44.00 1.3034 1.6435 0.1998 0.2681 0.0399 0.0536<br />

III 30.79 76.00 1.4884 1.8808 0.3848 0.5055 0.1481 0.1945<br />

I 20.84 80.00 1.3189 1.9031 0.2153 0.5278 0.0464 0.1136<br />

1982-83 OCT II 18.58 70.00 1.2690 1.8451 0.1655 0.4698 0.0274 0.0777<br />

III 16.79 39.00 1.2251 1.5911 0.1215 0.2157 0.0148 0.0262<br />

I 15.31 26.00 1.1850 1.4150 0.0814 0.0396 0.0066 0.0032<br />

NOV II 13.77 25.00 1.1389 1.3979 0.0353 0.0226 0.0012 0.0008<br />

III 12.27 22.00 1.0888 1.3424 -0.0147 -0.0329 0.0002 0.0005<br />

I 11.40 18.00 1.0569 1.2553 -0.0467 -0.1201 0.0022 0.0056<br />

DEC II 10.54 15.00 1.0228 1.1761 -0.0807 -0.1992 0.0065 0.0161<br />

III 12.22 14.00 1.0871 1.1461 -0.0165 -0.2292 0.0003 0.0038<br />

I 7.36 15.00 0.8667 1.1761 -0.2369 -0.1992 0.0561 0.0472<br />

JAN II 7.40 15.00 0.8692 1.1761 -0.2344 -0.1992 0.0549 0.0467<br />

III 7.62 15.00 0.8820 1.1761 -0.2216 -0.1992 0.0491 0.0442<br />

I 7.39 14.00 0.8686 1.1461 -0.2349 -0.2292 0.0552 0.0538<br />

FEB II 7.20 14.00 0.8573 1.1461 -0.2463 -0.2292 0.0606 0.0564<br />

III 7.45 14.00 0.8722 1.1461 -0.2314 -0.2292 0.0536 0.0530<br />

I 11.99 18.00 1.0788 1.2553 -0.0248 -0.1201 0.0006 0.0030<br />

MAR II 12.42 20.00 1.0941 1.3010 -0.0095 -0.0743 0.0001 0.0007<br />

III 11.44 18.00 1.0584 1.2553 -0.0452 -0.1201 0.0020 0.0054<br />

I 11.41 18.00 1.0573 1.2553 -0.0463 -0.1201 0.0021 0.0056<br />

APR II 10.28 18.00 1.0120 1.2553 -0.0916 -0.1201 0.0084 0.0110<br />

III 12.42 21.00 1.0941 1.3222 -0.0095 -0.0531 0.0001 0.0005<br />

I 20.45 37.00 1.3107 1.5682 0.2071 0.1929 0.0429 0.0399<br />

MAY II 35.11 56.00 1.5454 1.7482 0.4418 0.3729 0.1952 0.1647<br />

III 56.24 83.00 1.7500 1.9191 0.6465 0.5438 0.4179 0.3515


Table-5.3(6)<br />

TANDI GHOUSAL DEVIATION FROM MEAN<br />

D/SITE D/SITE X Y X^2 X*Y<br />

YEAR MONTH Qx Qy LOG x LOG y LOGx-LOGX' LOGy-LOGy'<br />

(Cumecs) (Cumecs)<br />

1983-84 I 45.51 76.00 1.6581 1.8808 0.5545 0.5055 0.3075 0.2803<br />

OCT II 27.07 51.00 1.4325 1.7076 0.3289 0.3322 0.1082 0.1093<br />

III 17.04 33.00 1.2315 1.5185 0.1279 0.1432 0.0164 0.0183<br />

I 12.42 27.00 1.0941 1.4314 -0.0095 0.0560 0.0001 -0.0005<br />

NOV II 11.67 25.00 1.0671 1.3979 -0.0365 0.0226 0.0013 -0.0008<br />

III 11.10 23.00 1.0453 1.3617 -0.0583 -0.0136 0.0034 0.0008<br />

I 10.40 20.00 1.0168 1.3010 -0.0868 -0.0743 0.0075 0.0064<br />

DEC II 9.55 19.00 0.9801 1.2788 -0.1234 -0.0966 0.0152 0.0119<br />

III 3.42 18.00 0.5340 1.2553 -0.5696 -0.1201 0.3244 0.0684<br />

I 11.03 19.00 1.0426 1.2788 -0.0610 -0.0966 0.0037 0.0059<br />

JAN II 10.59 19.00 1.0249 1.2788 -0.0787 -0.0966 0.0062 0.0076<br />

III 10.06 18.00 1.0026 1.2553 -0.1010 -0.1201 0.0102 0.0121<br />

I 9.62 17.00 0.9829 1.2304 -0.1206 -0.1449 0.0146 0.0175<br />

FEB II 9.07 17.00 0.9576 1.2304 -0.1460 -0.1449 0.0213 0.0211<br />

III 8.73 16.00 0.9410 1.2041 -0.1626 -0.1712 0.0264 0.0278<br />

I 9.65 16.00 0.9845 1.2041 -0.1191 -0.1712 0.0142 0.0204<br />

MAR II 11.19 18.00 1.0488 1.2553 -0.0548 -0.1201 0.0030 0.0066<br />

III 11.48 19.00 1.0599 1.2788 -0.0436 -0.0966 0.0019 0.0042<br />

I 11.91 20.00 1.0759 1.3010 -0.0277 -0.0743 0.0008 0.0021<br />

APR II 10.85 20.00 1.0354 1.3010 -0.0682 -0.0743 0.0046 0.0051<br />

III 15.00 26.00 1.1761 1.4150 0.0725 0.0396 0.0053 0.0029<br />

I 28.03 45.00 1.4476 1.6532 0.3440 0.2779 0.1184 0.0956<br />

MAY II 33.90 74.00 1.5302 1.8692 0.4266 0.4939 0.1820 0.2107<br />

III 72.58 125.00 1.8608 2.0969 0.7572 0.7216 0.5734 0.5464<br />

G.TOTAL 264.86 330.08 0.00 0.00 15.65 14.99<br />

NO. OF PERIOD 240 LOG x' LOG y'<br />

AVERAGE<br />

Co-efficient <strong>of</strong> Corelation<br />

1.1036 1.3753<br />

b = SIGMA X*Y = 0.9580<br />

SIGMA X^2


REGRESSION ANALYSIS BETWEEN DISCHARGES OF TANDI PLUS GHOUSAL AND UDAIPUR JUNE- JULY<br />

UDAIPUR TDI.+GSL DEVIATION FROM MEAN<br />

D/SITE D/SITE X Y X^2 X*Y<br />

YEAR MONTH Qx Qy LOG x LOG y LOGx-LOGX' LOGy-LOGy'<br />

(Cumecs) (Cumecs)<br />

I 195.00 152.28 2.2900 2.1826 -0.4193 -0.3874 0.1758 0.1625<br />

1974 JUN II 318.00 248.59 2.5024 2.3955 -0.2069 -0.1746 0.0428 0.0361<br />

III 203.00 167.44 2.3075 2.2239 -0.4018 -0.3462 0.1615 0.1391<br />

I 299.00 246.61 2.4757 2.3920 -0.2337 -0.1781 0.0546 0.0416<br />

JUL II 636.00 452.53 2.8035 2.6556 0.0941 0.0856 0.0089 0.0081<br />

III 504.00 374.12 2.7024 2.5730 -0.0069 0.0029 0.0000 0.0000<br />

I 361.00 282.44 2.5575 2.4509 -0.1518 -0.1192 0.0231 0.0181<br />

1975 JUN II 558.00 398.51 2.7466 2.6004 0.0373 0.0304 0.0014 0.0011<br />

III 651.00 468.02 2.8136 2.6703 0.1042 0.1002 0.0109 0.0104<br />

I 513.00 360.00 2.7101 2.5563 0.0008 -0.0138 0.0000 0.0000<br />

JUL II 887.00 613.91 2.9479 2.7881 0.2386 0.2180 0.0569 0.0520<br />

III 618.00 429.52 2.7910 2.6330 0.0816 0.0629 0.0067 0.0051<br />

I 477.00 317.18 2.6785 2.5013 -0.0308 -0.0688 0.0010 0.0021<br />

1976 JUN II 351.00 247.79 2.5453 2.3941 -0.1640 -0.1760 0.0269 0.0289<br />

III 287.00 202.81 2.4579 2.3071 -0.2515 -0.2630 0.0632 0.0661<br />

I 574.00 415.59 2.7589 2.6187 0.0496 0.0486 0.0025 0.0024<br />

JUL II 721.00 560.80 2.8579 2.7488 0.1486 0.1787 0.0221 0.0266<br />

III 755.00 580.87 2.8779 2.7641 0.1686 0.1940 0.0284 0.0327<br />

I 258.00 196.59 2.4116 2.2936 -0.2977 -0.2765 0.0886 0.0823<br />

1977 JUN II 184.00 141.04 2.2648 2.1493 -0.4445 -0.4207 0.1976 0.1870<br />

III 633.00 436.71 2.8014 2.6402 0.0921 0.0701 0.0085 0.0065<br />

I 828.00 579.09 2.9180 2.7627 0.2087 0.1927 0.0435 0.0402<br />

JUL II 754.00 532.87 2.8774 2.7266 0.1680 0.1565 0.0282 0.0263<br />

III 601.00 450.26 2.7789 2.6535 0.0695 0.0834 0.0048 0.0058<br />

I 456.00 353.06 2.6590 2.5478 -0.0504 -0.0222 0.0025 0.0011<br />

1978 JUN II 424.00 312.95 2.6274 2.4955 -0.0820 -0.0746 0.0067 0.0061<br />

III 845.00 640.03 2.9269 2.8062 0.2175 0.2361 0.0473 0.0514<br />

I 904.00 647.43 2.9562 2.8112 0.2468 0.2411 0.0609 0.0595<br />

JUL II 700.00 540.15 2.8451 2.7325 0.1358 0.1624 0.0184 0.0221<br />

III 700.00 536.99 2.8451 2.7300 0.1358 0.1599 0.0184 0.0217<br />

I 197.00 141.70 2.2945 2.1514 -0.4149 -0.4187 0.1721 0.1737<br />

1979 JUN II 401.00 295.39 2.6031 2.4704 -0.1062 -0.0997 0.0113 0.0106<br />

III 806.00 597.47 2.9063 2.7763 0.1970 0.2062 0.0388 0.0406<br />

I 736.00 541.98 2.8669 2.7340 0.1575 0.1639 0.0248 0.0258<br />

JUL II 927.00 660.97 2.9671 2.8202 0.2577 0.2501 0.0664 0.0645<br />

III 698.00 519.08 2.8439 2.7152 0.1345 0.1451 0.0181 0.0195<br />

I 395.00 301.89 2.5966 2.4798 -0.1127 -0.0902 0.0127 0.0102<br />

1980 JUN II 481.00 356.45 2.6821 2.5520 -0.0272 -0.0181 0.0007 0.0005<br />

III 696.00 507.78 2.8426 2.7057 0.1333 0.1356 0.0178 0.0181<br />

I 731.00 536.27 2.8639 2.7294 0.1546 0.1593 0.0239 0.0246<br />

JUL II 762.00 524.29 2.8820 2.7196 0.1726 0.1495 0.0298 0.0258<br />

III 635.00 474.10 2.8028 2.6759 0.0934 0.1058 0.0087 0.0099<br />

I 292.00 221.07 2.4654 2.3445 -0.2440 -0.2256 0.0595 0.0550<br />

1981 JUN II 311.00 229.57 2.4928 2.3609 -0.2166 -0.2092 0.0469 0.0453<br />

III 738.00 501.01 2.8681 2.6998 0.1587 0.1298 0.0252 0.0206<br />

I 582.00 418.26 2.7649 2.6214 0.0556 0.0514 0.0031 0.0029<br />

JUL II 779.00 526.95 2.8915 2.7218 0.1822 0.1517 0.0332 0.0276<br />

III 818.00 572.92 2.9128 2.7581 0.2034 0.1880 0.0414 0.0382<br />

I 320.00 182.53 2.5051 2.2613 -0.2042 -0.3088 0.0417 0.0630<br />

1982 JUN II 537.00 332.83 2.7300 2.5222 0.0206 -0.0479 0.0004 -0.0010<br />

III 519.00 328.64 2.7152 2.5167 0.0058 -0.0534 0.0000 -0.0003<br />

I 582.00 439.48 2.7649 2.6429 0.0556 0.0729 0.0031 0.0040<br />

JUL II 705.00 464.71 2.8482 2.6672 0.1388 0.0971 0.0193 0.0135<br />

III 903.00 539.55 2.9557 2.7320 0.2463 0.1619 0.0607 0.0399<br />

I 264.00 204.20 2.4216 2.3101 -0.2877 -0.2600 0.0828 0.0748<br />

1983 JUN II 310.00 231.29 2.4914 2.3642 -0.2180 -0.2059 0.0475 0.0449<br />

III 555.00 327.14 2.7443 2.5147 0.0349 -0.0554 0.0012 -0.0019<br />

I 497.00 402.41 2.6964 2.6047 -0.0130 0.0346 0.0002 -0.0004<br />

JUL II 350.00 313.79 2.5441 2.4966 -0.1653 -0.0734 0.0273 0.0121<br />

III 725.00 538.52 2.8603 2.7312 0.1510 0.1611 0.0228 0.0243<br />

G.TOTAL 162.56 154.21 0.00 0.00 2.15 2.03<br />

NO. OF PERIOD 60 LOG x' LOG y'<br />

AVERAGE 2.7093 2.5701<br />

Co-efficient <strong>of</strong> Corelation<br />

b = SIGMA X*Y = 0.9422<br />

SIGMA X^2<br />

Table-5.4(1)


REGRESSION ANALYSIS BETWEEN DISCHARGES OF TANDI PLUS GHOUSAL AND UDAIPUR AUG.- SEPT<br />

UDAIPUR TDI.+GSL DEVIATION FROM MEAN<br />

D/SITE D/SITE X Y X^2 X*Y<br />

YEAR MONTH Qx Qy LOG x LOG y LOGx-LOGX' LOGy-LOGy'<br />

(Cumecs) (Cumecs)<br />

I 524.00 402.96 2.7193 2.6053 0.1394 0.1697 0.0194 0.0237<br />

1974 AUG II 430.00 330.22 2.6335 2.5188 0.0535 0.0832 0.0029 0.0045<br />

III 417.00 311.99 2.6201 2.4941 0.0402 0.0586 0.0016 0.0024<br />

I 293.00 211.23 2.4669 2.3248 -0.1131 -0.1108 0.0128 0.0125<br />

SEPT II 205.00 160.48 2.3118 2.2054 -0.2682 -0.2302 0.0719 0.0617<br />

III 144.00 107.41 2.1584 2.0310 -0.4216 -0.4045 0.1777 0.1705<br />

I 731.00 511.62 2.8639 2.7089 0.2840 0.2734 0.0806 0.0776<br />

1975 AUG II 856.00 575.79 2.9325 2.7603 0.3525 0.3247 0.1243 0.1145<br />

III 535.00 370.86 2.7284 2.5692 0.1484 0.1336 0.0220 0.0198<br />

I 718.00 284.37 2.8561 2.4539 0.2762 0.0183 0.0763 0.0051<br />

SEPT II 288.00 200.70 2.4594 2.3025 -0.1205 -0.1330 0.0145 0.0160<br />

III 177.00 124.74 2.2480 2.0960 -0.3320 -0.3396 0.1102 0.1127<br />

I 569.00 408.32 2.7551 2.6110 0.1752 0.1754 0.0307 0.0307<br />

1976 AUG II 518.00 360.47 2.7143 2.5569 0.1344 0.1213 0.0181 0.0163<br />

III 381.00 282.12 2.5809 2.4504 0.0010 0.0148 0.0000 0.0000<br />

I 326.00 240.73 2.5132 2.3815 -0.0667 -0.0541 0.0045 0.0036<br />

SEPT II 178.00 138.96 2.2504 2.1429 -0.3295 -0.2927 0.1086 0.0964<br />

III 159.00 113.35 2.2014 2.0544 -0.3785 -0.3812 0.1433 0.1443<br />

I 724.00 530.88 2.8597 2.7250 0.2798 0.2894 0.0783 0.0810<br />

1977 AUG II 501.00 368.00 2.6998 2.5658 0.1199 0.1303 0.0144 0.0156<br />

III 468.00 330.56 2.6702 2.5193 0.0903 0.0837 0.0082 0.0076<br />

I 396.00 281.03 2.5977 2.4488 0.0178 0.0132 0.0003 0.0002<br />

SEPT II 226.00 170.94 2.3541 2.2328 -0.2258 -0.2027 0.0510 0.0458<br />

III 151.00 114.63 2.1790 2.0593 -0.4010 -0.3763 0.1608 0.1509<br />

I 725.00 550.35 2.8603 2.7406 0.2804 0.3050 0.0786 0.0855<br />

1978 AUG II 619.00 435.17 2.7917 2.6387 0.2118 0.2031 0.0448 0.0430<br />

III 528.00 378.00 2.7226 2.5775 0.1427 0.1419 0.0204 0.0202<br />

I 253.00 186.00 2.4031 2.2695 -0.1768 -0.1661 0.0313 0.0294<br />

SEPT II 221.00 142.98 2.3444 2.1553 -0.2355 -0.2803 0.0555 0.0660<br />

III 164.00 136.28 2.2148 2.1344 -0.3651 -0.3012 0.1333 0.1100<br />

I 817.00 574.89 2.9122 2.7596 0.3323 0.3240 0.1104 0.1077<br />

1979 AUG II 666.00 478.29 2.8235 2.6797 0.2435 0.2441 0.0593 0.0594<br />

III 437.00 335.16 2.6405 2.5253 0.0605 0.0897 0.0037 0.0054<br />

I 423.00 311.36 2.6263 2.4933 0.0464 0.0577 0.0022 0.0027<br />

SEPT II 216.00 164.16 2.3345 2.2153 -0.2455 -0.2203 0.0603 0.0541<br />

III 130.00 74.60 2.1139 1.8727 -0.4660 -0.5629 0.2172 0.2623<br />

I 750.00 515.94 2.8751 2.7126 0.2951 0.2770 0.0871 0.0818<br />

1980 AUG II 423.00 318.18 2.6263 2.5027 0.0464 0.0671 0.0022 0.0031<br />

III 473.00 356.30 2.6749 2.5518 0.0949 0.1162 0.0090 0.0110<br />

I 301.00 225.52 2.4786 2.3532 -0.1014 -0.0824 0.0103 0.0084<br />

SEPT II 213.00 144.10 2.3284 2.1587 -0.2516 -0.2769 0.0633 0.0697<br />

III 165.00 99.36 2.2175 1.9972 -0.3625 -0.4384 0.1314 0.1589<br />

I 694.00 487.37 2.8414 2.6879 0.2614 0.2523 0.0683 0.0659<br />

1981 AUG II 628.00 441.32 2.7980 2.6448 0.2180 0.2092 0.0475 0.0456<br />

III 467.00 303.76 2.6693 2.4825 0.0894 0.0469 0.0080 0.0042<br />

I 370.00 250.66 2.5682 2.3991 -0.0117 -0.0365 0.0001 0.0004<br />

SEPT II 221.00 141.39 2.3444 2.1504 -0.2355 -0.2852 0.0555 0.0672<br />

III 211.00 125.77 2.3243 2.0996 -0.2557 -0.3360 0.0654 0.0859<br />

I 861.00 578.82 2.9350 2.7625 0.3551 0.3270 0.1261 0.1161<br />

1982 AUG II 664.00 486.72 2.8222 2.6873 0.2422 0.2517 0.0587 0.0610<br />

III 425.00 344.35 2.6284 2.5370 0.0485 0.1014 0.0023 0.0049<br />

I 338.00 251.49 2.5289 2.4005 -0.0510 -0.0351 0.0026 0.0018<br />

SEPT II 339.00 219.20 2.5302 2.3408 -0.0497 -0.0947 0.0025 0.0047<br />

III 136.00 152.19 2.1335 2.1824 -0.4464 -0.2532 0.1993 0.1130<br />

I 903.00 643.85 2.9557 2.8088 0.3757 0.3732 0.1412 0.1402<br />

1983 AUG II 686.00 546.24 2.8363 2.7374 0.2564 0.3018 0.0657 0.0774<br />

III 697.00 539.17 2.8432 2.7317 0.2633 0.2961 0.0693 0.0780<br />

I 597.00 437.26 2.7760 2.6407 0.1960 0.2052 0.0384 0.0402<br />

SEPT II 406.00 299.29 2.6085 2.4761 0.0286 0.0405 0.0008 0.0012<br />

III 195.00 161.98 2.2900 2.2095 -0.2899 -0.2261 0.0840 0.0656<br />

G.TOTAL 154.80 146.14 0.00 0.00 3.49 3.37<br />

NO. OF PERIOD 60 LOG x' LOG y'<br />

AVERAGE 2.5799 2.4356<br />

Co-efficient <strong>of</strong> Corelation<br />

b = SIGMA X*Y = 0.9648<br />

SIGMA X^2<br />

Table-5.4(2)


REGRESSION ANALYSIS BETWEEN DISCHARGES OF TANDI PLUS GHOUSAL AND UDAIPUR ( N-MON )<br />

UDAIPUR TDI.+GSL DEVIATION FROM MEAN<br />

D/SITE D/SITE X Y X^2 X*Y<br />

YEAR MONTH Qx Qy LOG x LOG y LOGx-LOGX' LOGy-LOGy'<br />

(Cumecs) (Cumecs)<br />

I 82.00 59.62 1.9138 1.7754 0.1598 0.2095 0.0256 0.0335<br />

1974-75 OCT II 67.00 48.58 1.8261 1.6865 0.0721 0.1206 0.0052 0.0087<br />

III 55.00 39.31 1.7404 1.5945 -0.0136 0.0287 0.0002 -0.0004<br />

I 46.00 32.92 1.6628 1.5175 -0.0912 -0.0484 0.0083 0.0044<br />

NOV II 40.00 35.83 1.6021 1.5542 -0.1519 -0.0116 0.0231 0.0018<br />

III 36.00 27.45 1.5563 1.4385 -0.1977 -0.1273 0.0391 0.0252<br />

I 36.00 25.69 1.5563 1.4098 -0.1977 -0.1561 0.0391 0.0309<br />

DEC II 35.00 23.43 1.5441 1.3698 -0.2099 -0.1961 0.0441 0.0412<br />

III 35.00 24.42 1.5441 1.3877 -0.2099 -0.1781 0.0441 0.0374<br />

I 32.00 22.38 1.5051 1.3499 -0.2488 -0.2160 0.0619 0.0537<br />

JAN II 31.00 22.07 1.4914 1.3438 -0.2626 -0.2220 0.0690 0.0583<br />

III 26.00 19.60 1.4150 1.2923 -0.3390 -0.2736 0.1149 0.0927<br />

I 27.00 22.19 1.4314 1.3462 -0.3226 -0.2197 0.1041 0.0709<br />

FEB II 31.00 21.59 1.4914 1.3343 -0.2626 -0.2316 0.0690 0.0608<br />

III 32.00 23.12 1.5051 1.3640 -0.2488 -0.2019 0.0619 0.0502<br />

I 30.00 18.30 1.4771 1.2625 -0.2768 -0.3034 0.0766 0.0840<br />

MAR II 31.00 18.43 1.4914 1.2655 -0.2626 -0.3003 0.0690 0.0789<br />

III 31.00 23.26 1.4914 1.3666 -0.2626 -0.1992 0.0690 0.0523<br />

I 38.00 26.42 1.5798 1.4219 -0.1742 -0.1439 0.0303 0.0251<br />

APR II 54.00 35.38 1.7324 1.5488 -0.0216 -0.0171 0.0005 0.0004<br />

III 71.00 48.70 1.8513 1.6875 0.0973 0.1217 0.0095 0.0118<br />

I 108.00 74.16 2.0334 1.8702 0.2795 0.3043 0.0781 0.0850<br />

MAY II 228.00 158.15 2.3579 2.1991 0.6040 0.6332 0.3648 0.3824<br />

III 277.00 205.11 2.4425 2.3120 0.6885 0.7461 0.4740 0.5137<br />

I 148.00 97.47 2.1703 1.9889 0.4163 0.4230 0.1733 0.1761<br />

1975-76 OCT II 121.00 81.99 2.0828 1.9138 0.3288 0.3479 0.1081 0.1144<br />

III 79.00 54.50 1.8976 1.7364 0.1437 0.1706 0.0206 0.0245<br />

I 58.00 39.53 1.7634 1.5969 0.0095 0.0311 0.0001 0.0003<br />

NOV II 49.00 34.42 1.6902 1.5368 -0.0638 -0.0290 0.0041 0.0019<br />

III 42.00 31.23 1.6232 1.4946 -0.1307 -0.0713 0.0171 0.0093<br />

I 39.00 29.32 1.5911 1.4672 -0.1629 -0.0987 0.0265 0.0161<br />

DEC II 33.00 26.02 1.5185 1.4153 -0.2355 -0.1505 0.0554 0.0354<br />

III 32.00 24.75 1.5051 1.3936 -0.2488 -0.1723 0.0619 0.0429<br />

I 33.00 24.16 1.5185 1.3831 -0.2355 -0.1827 0.0554 0.0430<br />

JAN II 33.00 23.46 1.5185 1.3703 -0.2355 -0.1955 0.0554 0.0460<br />

III 32.00 21.84 1.5051 1.3393 -0.2488 -0.2266 0.0619 0.0564<br />

I 31.00 22.41 1.4914 1.3504 -0.2626 -0.2154 0.0690 0.0566<br />

FEB II 25.00 18.21 1.3979 1.2603 -0.3560 -0.3055 0.1268 0.1088<br />

III 28.00 20.03 1.4472 1.3017 -0.3068 -0.2642 0.0941 0.0810<br />

I 31.00 22.49 1.4914 1.3520 -0.2626 -0.2139 0.0690 0.0562<br />

MAR II 29.00 21.10 1.4624 1.3243 -0.2916 -0.2416 0.0850 0.0704<br />

III 28.00 20.13 1.4472 1.3038 -0.3068 -0.2620 0.0941 0.0804<br />

I 34.00 20.08 1.5315 1.3028 -0.2225 -0.2631 0.0495 0.0585<br />

APR II 42.00 26.91 1.6232 1.4299 -0.1307 -0.1359 0.0171 0.0178<br />

III 101.00 60.08 2.0043 1.7787 0.2504 0.2129 0.0627 0.0533<br />

I 131.00 83.13 2.1173 1.9198 0.3633 0.3539 0.1320 0.1286<br />

MAY II 189.00 127.74 2.2765 2.1063 0.5225 0.5405 0.2730 0.2824<br />

III 276.00 184.72 2.4409 2.2665 0.6869 0.7007 0.4719 0.4813<br />

I 118.00 80.29 2.0719 1.9047 0.3179 0.3388 0.1011 0.1077<br />

1976-77 OCT II 70.00 51.19 1.8451 1.7092 0.0911 0.1433 0.0083 0.0131<br />

III 56.00 39.71 1.7482 1.5989 -0.0058 0.0331 0.0000 -0.0002<br />

I 52.00 35.45 1.7160 1.5496 -0.0380 -0.0162 0.0014 0.0006<br />

NOV II 44.00 32.17 1.6435 1.5075 -0.1105 -0.0584 0.0122 0.0065<br />

III 37.00 28.95 1.5682 1.4616 -0.1858 -0.1042 0.0345 0.0194<br />

I 34.00 26.40 1.5315 1.4216 -0.2225 -0.1442 0.0495 0.0321<br />

DEC II 31.00 23.24 1.4914 1.3662 -0.2626 -0.1996 0.0690 0.0524<br />

III 31.00 21.93 1.4914 1.3410 -0.2626 -0.2248 0.0690 0.0590<br />

I 30.00 20.07 1.4771 1.3025 -0.2768 -0.2633 0.0766 0.0729<br />

JAN II 29.00 18.97 1.4624 1.2781 -0.2916 -0.2878 0.0850 0.0839<br />

III 155.00 16.18 2.1903 1.2090 0.4364 -0.3569 0.1904 -0.1557<br />

I 33.00 22.47 1.5185 1.3516 -0.2355 -0.2142 0.0554 0.0504<br />

FEB II 27.00 19.22 1.4314 1.2838 -0.3226 -0.2821 0.1041 0.0910<br />

III 26.00 19.26 1.4150 1.2847 -0.3390 -0.2812 0.1149 0.0953<br />

I 28.00 19.12 1.4472 1.2815 -0.3068 -0.2844 0.0941 0.0872<br />

MAR II 29.00 19.33 1.4624 1.2862 -0.2916 -0.2796 0.0850 0.0815<br />

III 37.00 26.05 1.5682 1.4158 -0.1858 -0.1500 0.0345 0.0279<br />

I 40.00 29.91 1.6021 1.4758 -0.1519 -0.0900 0.0231 0.0137<br />

APR II 39.00 28.31 1.5911 1.4519 -0.1629 -0.1139 0.0265 0.0186<br />

III 47.00 34.28 1.6721 1.5350 -0.0819 -0.0308 0.0067 0.0025<br />

I 50.00 35.33 1.6990 1.5481 -0.0550 -0.0177 0.0030 0.0010<br />

MAY II 75.00 51.18 1.8751 1.7091 0.1211 0.1433 0.0147 0.0173<br />

III 168.00 124.42 2.2253 2.0949 0.4713 0.5290 0.2222 0.2494<br />

Table-5.4(3)


UDAIPUR TDI.+GSL DEVIATION FROM MEAN<br />

D/SITE D/SITE X Y X^2 X*Y<br />

YEAR MONTH Qx Qy LOG x LOG y LOGx-LOGX' LOGy-LOGy'<br />

(Cumecs) (Cumecs)<br />

I 109.00 80.11 2.0374 1.9037 0.2835 0.3378 0.0803 0.0958<br />

1977-78 OCT II 80.00 57.55 1.9031 1.7600 0.1491 0.1942 0.0222 0.0290<br />

III 69.00 47.45 1.8388 1.6762 0.0849 0.1104 0.0072 0.0094<br />

I 57.00 41.74 1.7559 1.6206 0.0019 0.0547 0.0000 0.0001<br />

NOV II 49.00 36.30 1.6902 1.5599 -0.0638 -0.0059 0.0041 0.0004<br />

III 44.00 34.85 1.6435 1.5422 -0.1105 -0.0236 0.0122 0.0026<br />

I 38.00 32.17 1.5798 1.5075 -0.1742 -0.0584 0.0303 0.0102<br />

DEC II 35.00 27.86 1.5441 1.4450 -0.2099 -0.1209 0.0441 0.0254<br />

III 33.00 25.35 1.5185 1.4040 -0.2355 -0.1619 0.0554 0.0381<br />

I 32.00 22.94 1.5051 1.3606 -0.2488 -0.2053 0.0619 0.0511<br />

JAN II 33.00 26.57 1.5185 1.4244 -0.2355 -0.1415 0.0554 0.0333<br />

III 32.00 24.35 1.5051 1.3865 -0.2488 -0.1793 0.0619 0.0446<br />

I 32.00 22.16 1.5051 1.3456 -0.2488 -0.2203 0.0619 0.0548<br />

FEB II 27.00 22.57 1.4314 1.3535 -0.3226 -0.2123 0.1041 0.0685<br />

III 32.00 27.02 1.5051 1.4317 -0.2488 -0.1342 0.0619 0.0334<br />

I 31.00 20.60 1.4914 1.3139 -0.2626 -0.2520 0.0690 0.0662<br />

MAR II 31.00 20.10 1.4914 1.3032 -0.2626 -0.2626 0.0690 0.0690<br />

III 36.00 23.41 1.5563 1.3694 -0.1977 -0.1964 0.0391 0.0388<br />

I 38.00 25.10 1.5798 1.3997 -0.1742 -0.1662 0.0303 0.0289<br />

APR II 66.00 40.41 1.8195 1.6065 0.0656 0.0406 0.0043 0.0027<br />

III 82.00 52.48 1.9138 1.7200 0.1598 0.1541 0.0256 0.0246<br />

I 197.00 146.66 2.2945 2.1663 0.5405 0.6005 0.2921 0.3246<br />

MAY II 290.00 229.87 2.4624 2.3615 0.7084 0.7956 0.5019 0.5637<br />

III 336.00 267.93 2.5263 2.4280 0.7724 0.8622 0.5966 0.6659<br />

I 121.00 80.94 2.0828 1.9082 0.3288 0.3423 0.1081 0.1126<br />

1978-79 OCT II 96.00 61.61 1.9823 1.7897 0.2283 0.2238 0.0521 0.0511<br />

III 79.00 59.49 1.8976 1.7744 0.1437 0.2086 0.0206 0.0300<br />

I 59.00 40.26 1.7709 1.6049 0.0169 0.0390 0.0003 0.0007<br />

NOV II 49.00 35.70 1.6902 1.5527 -0.0638 -0.0132 0.0041 0.0008<br />

III 44.00 36.17 1.6435 1.5583 -0.1105 -0.0075 0.0122 0.0008<br />

I 40.00 33.02 1.6021 1.5188 -0.1519 -0.0471 0.0231 0.0071<br />

DEC II 38.00 31.29 1.5798 1.4954 -0.1742 -0.0704 0.0303 0.0123<br />

III 35.00 31.17 1.5441 1.4937 -0.2099 -0.0721 0.0441 0.0151<br />

I 41.00 30.52 1.6128 1.4846 -0.1412 -0.0813 0.0199 0.0115<br />

JAN II 42.00 26.92 1.6232 1.4301 -0.1307 -0.1358 0.0171 0.0177<br />

III 40.00 26.07 1.6021 1.4161 -0.1519 -0.1497 0.0231 0.0227<br />

I 39.00 27.86 1.5911 1.4450 -0.1629 -0.1209 0.0265 0.0197<br />

FEB II 38.00 25.12 1.5798 1.4000 -0.1742 -0.1658 0.0303 0.0289<br />

III 35.00 25.41 1.5441 1.4050 -0.2099 -0.1608 0.0441 0.0338<br />

I 41.00 25.35 1.6128 1.4040 -0.1412 -0.1619 0.0199 0.0229<br />

MAR II 40.00 40.35 1.6021 1.6058 -0.1519 0.0400 0.0231 -0.0061<br />

III 45.00 56.50 1.6532 1.7520 -0.1008 0.1862 0.0102 -0.0188<br />

I 64.00 51.00 1.8062 1.7076 0.0522 0.1417 0.0027 0.0074<br />

APR II 91.00 54.00 1.9590 1.7324 0.2051 0.1665 0.0421 0.0342<br />

III 144.00 88.02 2.1584 1.9446 0.4044 0.3787 0.1635 0.1532<br />

I 179.00 118.02 2.2529 2.0720 0.4989 0.5061 0.2489 0.2525<br />

MAY II 163.00 102.58 2.2122 2.0111 0.4582 0.4452 0.2100 0.2040<br />

III 145.00 100.78 2.1614 2.0034 0.4074 0.4375 0.1660 0.1783<br />

I 127.00 68.72 2.1038 1.8371 0.3498 0.2712 0.1224 0.0949<br />

1979-80 OCT II 108.00 56.94 2.0334 1.7554 0.2795 0.1896 0.0781 0.0530<br />

III 91.00 48.83 1.9590 1.6887 0.2051 0.1228 0.0421 0.0252<br />

I 83.00 44.23 1.9191 1.6457 0.1651 0.0799 0.0273 0.0132<br />

NOV II 70.00 37.74 1.8451 1.5768 0.0911 0.0110 0.0083 0.0010<br />

III 65.00 36.24 1.8129 1.5592 0.0589 -0.0067 0.0035 -0.0004<br />

I 59.00 34.74 1.7709 1.5408 0.0169 -0.0250 0.0003 -0.0004<br />

DEC II 57.00 31.93 1.7559 1.5042 0.0019 -0.0616 0.0000 -0.0001<br />

III 57.00 31.86 1.7559 1.5032 0.0019 -0.0626 0.0000 -0.0001<br />

I 57.00 27.68 1.7559 1.4422 0.0019 -0.1237 0.0000 -0.0002<br />

JAN II 56.00 26.76 1.7482 1.4275 -0.0058 -0.1384 0.0000 0.0008<br />

III 52.00 24.08 1.7160 1.3817 -0.0380 -0.1842 0.0014 0.0070<br />

I 58.00 29.54 1.7634 1.4704 0.0095 -0.0954 0.0001 -0.0009<br />

FEB II 57.00 26.83 1.7559 1.4286 0.0019 -0.1372 0.0000 -0.0003<br />

III 54.00 28.79 1.7324 1.4592 -0.0216 -0.1066 0.0005 0.0023<br />

I 51.00 25.50 1.7076 1.4065 -0.0464 -0.1593 0.0022 0.0074<br />

MAR II 51.00 27.55 1.7076 1.4401 -0.0464 -0.1257 0.0022 0.0058<br />

III 51.00 30.63 1.7076 1.4861 -0.0464 -0.0797 0.0022 0.0037<br />

I 58.00 33.90 1.7634 1.5302 0.0095 -0.0356 0.0001 -0.0003<br />

APR II 71.00 38.03 1.8513 1.5801 0.0973 0.0143 0.0095 0.0014<br />

III 95.00 42.98 1.9777 1.6333 0.2238 0.0674 0.0501 0.0151<br />

I 155.00 91.76 2.1903 1.9627 0.4364 0.3968 0.1904 0.1732<br />

MAY II 182.00 123.09 2.2601 2.0902 0.5061 0.5244 0.2561 0.2654<br />

III 240.00 177.23 2.3802 2.2485 0.6262 0.6827 0.3922 0.4275<br />

Table-5.4(4)


UDAIPUR TDI.+GSL DEVIATION FROM MEAN<br />

D/SITE D/SITE X Y X^2 X*Y<br />

YEAR MONTH Qx Qy LOG x LOG y LOGx-LOGX' LOGy-LOGy'<br />

(Cumecs) (Cumecs)<br />

I 150.00 84.26 2.1761 1.9256 0.4221 0.3598 0.1782 0.1519<br />

1980-81 OCT II 116.00 56.63 2.0645 1.7530 0.3105 0.1872 0.0964 0.0581<br />

III 95.00 45.26 1.9777 1.6557 0.2238 0.0899 0.0501 0.0201<br />

I 84.00 33.35 1.9243 1.5231 0.1703 -0.0427 0.0290 -0.0073<br />

NOV II 77.00 29.02 1.8865 1.4627 0.1325 -0.1031 0.0176 -0.0137<br />

III 72.00 28.62 1.8573 1.4567 0.1034 -0.1092 0.0107 -0.0113<br />

I 68.00 26.16 1.8325 1.4176 0.0785 -0.1482 0.0062 -0.0116<br />

DEC II 67.00 24.82 1.8261 1.3948 0.0721 -0.1710 0.0052 -0.0123<br />

III 65.00 23.64 1.8129 1.3736 0.0589 -0.1922 0.0035 -0.0113<br />

I 65.00 24.71 1.8129 1.3929 0.0589 -0.1730 0.0035 -0.0102<br />

JAN II 62.00 23.35 1.7924 1.3683 0.0384 -0.1976 0.0015 -0.0076<br />

III 65.00 22.36 1.8129 1.3495 0.0589 -0.2164 0.0035 -0.0128<br />

I 59.00 22.46 1.7709 1.3514 0.0169 -0.2144 0.0003 -0.0036<br />

FEB II 64.00 23.07 1.8062 1.3630 0.0522 -0.2028 0.0027 -0.0106<br />

III 64.00 24.76 1.8062 1.3938 0.0522 -0.1721 0.0027 -0.0090<br />

I 61.00 23.76 1.7853 1.3758 0.0314 -0.1900 0.0010 -0.0060<br />

MAR II 60.00 23.60 1.7782 1.3729 0.0242 -0.1929 0.0006 -0.0047<br />

III 65.00 24.80 1.8129 1.3945 0.0589 -0.1714 0.0035 -0.0101<br />

I 70.00 26.44 1.8451 1.4223 0.0911 -0.1436 0.0083 -0.0131<br />

APR II 100.00 35.34 2.0000 1.5483 0.2460 -0.0176 0.0605 -0.0043<br />

III 149.00 70.52 2.1732 1.8483 0.4192 0.2825 0.1757 0.1184<br />

I 304.00 201.93 2.4829 2.3052 0.7289 0.7394 0.5313 0.5389<br />

MAY II 321.00 243.63 2.5065 2.3867 0.7525 0.8209 0.5663 0.6177<br />

III 405.00 287.76 2.6075 2.4590 0.8535 0.8932 0.7284 0.7623<br />

I 125.00 62.05 2.0969 1.7927 0.3429 0.2269 0.1176 0.0778<br />

1981-82 OCT II 108.00 51.80 2.0334 1.7143 0.2795 0.1485 0.0781 0.0415<br />

III 92.00 37.24 1.9638 1.5710 0.2098 0.0052 0.0440 0.0011<br />

I 76.00 33.72 1.8808 1.5279 0.1268 -0.0380 0.0161 -0.0048<br />

NOV II 57.00 28.67 1.7559 1.4574 0.0019 -0.1084 0.0000 -0.0002<br />

III 53.00 25.31 1.7243 1.4033 -0.0297 -0.1626 0.0009 0.0048<br />

I 49.00 23.42 1.6902 1.3696 -0.0638 -0.1963 0.0041 0.0125<br />

DEC II 45.00 20.94 1.6532 1.3210 -0.1008 -0.2449 0.0102 0.0247<br />

III 44.00 19.72 1.6435 1.2949 -0.1105 -0.2709 0.0122 0.0299<br />

I 36.00 22.34 1.5563 1.3491 -0.1977 -0.2168 0.0391 0.0428<br />

JAN II 35.00 22.20 1.5441 1.3464 -0.2099 -0.2195 0.0441 0.0461<br />

III 33.00 21.41 1.5185 1.3306 -0.2355 -0.2352 0.0554 0.0554<br />

I 36.00 22.32 1.5563 1.3487 -0.1977 -0.2171 0.0391 0.0429<br />

FEB II 35.00 22.70 1.5441 1.3560 -0.2099 -0.2098 0.0441 0.0440<br />

III 37.00 21.76 1.5682 1.3377 -0.1858 -0.2282 0.0345 0.0424<br />

I 37.00 23.37 1.5682 1.3687 -0.1858 -0.1972 0.0345 0.0366<br />

MAR II 37.00 22.92 1.5682 1.3602 -0.1858 -0.2056 0.0345 0.0382<br />

III 38.00 22.09 1.5798 1.3442 -0.1742 -0.2216 0.0303 0.0386<br />

I 45.00 24.50 1.6532 1.3892 -0.1008 -0.1767 0.0102 0.0178<br />

APR II 56.00 26.13 1.7482 1.4171 -0.0058 -0.1487 0.0000 0.0009<br />

III 80.00 36.40 1.9031 1.5611 0.1491 -0.0047 0.0222 -0.0007<br />

I 138.00 70.96 2.1399 1.8510 0.3859 0.2852 0.1489 0.1101<br />

MAY II 109.00 64.11 2.0374 1.8069 0.2835 0.2411 0.0803 0.0683<br />

III 179.00 106.79 2.2529 2.0285 0.4989 0.4627 0.2489 0.2308<br />

I 84.00 100.84 1.9243 2.0036 0.1703 0.4378 0.0290 0.0746<br />

1982-83 OCT II 71.00 88.58 1.8513 1.9473 0.0973 0.3815 0.0095 0.0371<br />

III 63.00 55.79 1.7993 1.7466 0.0454 0.1807 0.0021 0.0082<br />

I 53.00 41.31 1.7243 1.6161 -0.0297 0.0502 0.0009 -0.0015<br />

NOV II 48.00 38.77 1.6812 1.5885 -0.0727 0.0227 0.0053 -0.0016<br />

III 44.00 34.27 1.6435 1.5349 -0.1105 -0.0309 0.0122 0.0034<br />

I 42.00 29.40 1.6232 1.4683 -0.1307 -0.0975 0.0171 0.0127<br />

DEC II 42.00 25.54 1.6232 1.4072 -0.1307 -0.1586 0.0171 0.0207<br />

III 39.00 26.22 1.5911 1.4186 -0.1629 -0.1472 0.0265 0.0240<br />

I 31.00 22.36 1.4914 1.3494 -0.2626 -0.2164 0.0690 0.0568<br />

JAN II 29.00 22.40 1.4624 1.3502 -0.2916 -0.2156 0.0850 0.0629<br />

III 28.00 22.62 1.4472 1.3545 -0.3068 -0.2114 0.0941 0.0648<br />

I 27.00 21.39 1.4314 1.3302 -0.3226 -0.2356 0.1041 0.0760<br />

FEB II 26.00 21.20 1.4150 1.3263 -0.3390 -0.2395 0.1149 0.0812<br />

III 24.00 21.45 1.3802 1.3314 -0.3738 -0.2344 0.1397 0.0876<br />

I 26.00 29.99 1.4150 1.4770 -0.3390 -0.0889 0.1149 0.0301<br />

MAR II 30.00 32.42 1.4771 1.5108 -0.2768 -0.0550 0.0766 0.0152<br />

III 32.00 29.44 1.5051 1.4689 -0.2488 -0.0969 0.0619 0.0241<br />

I 44.00 29.41 1.6435 1.4685 -0.1105 -0.0973 0.0122 0.0108<br />

APR II 45.00 28.28 1.6532 1.4515 -0.1008 -0.1144 0.0102 0.0115<br />

III 45.00 33.42 1.6532 1.5240 -0.1008 -0.0418 0.0102 0.0042<br />

I 100.00 57.45 2.0000 1.7593 0.2460 0.1934 0.0605 0.0476<br />

MAY II 173.00 91.11 2.2380 1.9596 0.4841 0.3937 0.2343 0.1906<br />

III 167.00 139.24 2.2227 2.1438 0.4687 0.5779 0.2197 0.2709<br />

1983-84 I 142.00 121.51 2.1523 2.0846 0.3983 0.5188 0.1587 0.2066<br />

OCT II 99.00 78.07 1.9956 1.8925 0.2417 0.3266 0.0584 0.0789<br />

III 62.00 50.04 1.7924 1.6993 0.0384 0.1335 0.0015 0.0051<br />

I 50.00 39.42 1.6990 1.5957 -0.0550 0.0299 0.0030 -0.0016<br />

NOV II 48.00 36.67 1.6812 1.5643 -0.0727 -0.0015 0.0053 0.0001<br />

III 44.00 34.10 1.6435 1.5328 -0.1105 -0.0331 0.0122 0.0037<br />

Table-5.4(5)


UDAIPUR TDI.+GSL DEVIATION FROM MEAN<br />

D/SITE D/SITE X Y X^2 X*Y<br />

YEAR MONTH Qx Qy LOG x LOG y LOGx-LOGX' LOGy-LOGy'<br />

(Cumecs) (Cumecs)<br />

I 42.00 30.40 1.6232 1.4828 -0.1307 -0.0830 0.0171 0.0109<br />

DEC II 39.00 28.55 1.5911 1.4557 -0.1629 -0.1102 0.0265 0.0180<br />

Table-5.4(6)


UDAIPUR TDI.+GSL DEVIATION FROM MEAN<br />

D/SITE D/SITE X Y X^2 X*Y<br />

YEAR MONTH Qx Qy LOG x LOG y LOGx-LOGX' LOGy-LOGy'<br />

(Cumecs) (Cumecs)<br />

III 36.00 21.42 1.5563 1.3308 -0.1977 -0.2350 0.0391 0.0465<br />

I 35.00 30.03 1.5441 1.4776 -0.2099 -0.0883 0.0441 0.0185<br />

JAN II 35.00 29.59 1.5441 1.4711 -0.2099 -0.0947 0.0441 0.0199<br />

III 32.00 28.06 1.5051 1.4481 -0.2488 -0.1178 0.0619 0.0293<br />

I 30.00 26.62 1.4771 1.4251 -0.2768 -0.1407 0.0766 0.0390<br />

FEB II 28.00 26.07 1.4472 1.4161 -0.3068 -0.1497 0.0941 0.0459<br />

III 22.00 24.73 1.3424 1.3932 -0.4115 -0.1726 0.1694 0.0710<br />

I 33.00 25.65 1.5185 1.4091 -0.2355 -0.1568 0.0554 0.0369<br />

MAR II 33.00 29.19 1.5185 1.4652 -0.2355 -0.1006 0.0554 0.0237<br />

III 36.00 30.48 1.5563 1.4840 -0.1977 -0.0818 0.0391 0.0162<br />

I 42.00 31.91 1.6232 1.5039 -0.1307 -0.0619 0.0171 0.0081<br />

APR II 51.00 30.85 1.7076 1.4893 -0.0464 -0.0766 0.0022 0.0036<br />

III 69.00 41.00 1.8388 1.6128 0.0849 0.0469 0.0072 0.0040<br />

I 128.00 73.03 2.1072 1.8635 0.3532 0.2977 0.1248 0.1051<br />

MAY II 180.00 107.90 2.2553 2.0330 0.5013 0.4672 0.2513 0.2342<br />

III 353.00 197.58 2.5478 2.2957 0.7938 0.7299 0.6301 0.5794<br />

G.TOTAL 420.95 375.80 0.00 0.00 17.53 15.36<br />

NO. OF PERIOD 240 LOG x' LOG y'<br />

AVERAGE 1.7540 1.5658<br />

Co-efficient <strong>of</strong> Corelation<br />

b = SIGMA X*Y = 0.8766<br />

SIGMA X^2<br />

Table-5.4(7)


Discharge in Cumecdays<br />

120000<br />

100000<br />

80000<br />

60000<br />

40000<br />

20000<br />

Graph showing the trend lines <strong>of</strong> two series blocks<br />

<strong>of</strong> annual discharge <strong>of</strong> river Chenab at Udaipur<br />

0<br />

19<br />

74-<br />

75<br />

19<br />

76-<br />

77<br />

19<br />

78-<br />

79<br />

19<br />

80-<br />

81<br />

19<br />

82-<br />

83<br />

19<br />

84-<br />

85<br />

19<br />

86-<br />

87<br />

19<br />

88-<br />

89<br />

19<br />

90-<br />

91<br />

19<br />

92-<br />

93<br />

19<br />

94-<br />

95<br />

19<br />

96-<br />

97<br />

combined s2 s1 Linear (combined) Linear (s2) Linear (s1)<br />

19<br />

98-<br />

99<br />

20<br />

00-<br />

01

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!