Untitled - Ministry of Power
Untitled - Ministry of Power
Untitled - Ministry of Power
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
- Diversion tunnel<br />
civil works are in<br />
progress as per<br />
schedule.<br />
Vindhyachal-III (2x500 MW), Madhya Pradesh<br />
Commissioning Schedule : Unit-IX (February<br />
2007)<br />
Unit-X (August<br />
2007). Efforts are<br />
on to commission<br />
both the units in<br />
the Tenth plan.<br />
Present Status : Main Plant contract<br />
awarded to BHEL<br />
in March 2003. Civil<br />
works for main<br />
plant and Boiler<br />
erection are in<br />
progress as per<br />
schedule.<br />
Kahalgaon Stage-II, Phase-I (2x500 MW), Bihar<br />
Commissioning Schedule : Unit-V (November<br />
2006)<br />
Unit-VI (May 2007)<br />
Efforts are on to<br />
commission all the<br />
units in the Tenth<br />
plan.<br />
Present Status – Phase-I : Investment approval<br />
(2x500 MW) accorded in July<br />
2003. Main Plant<br />
award to BHEL<br />
Phase-II (1x500 MW) :<br />
completed in August<br />
2003. Civil and<br />
Structural activities<br />
at site have been<br />
taken up.<br />
Unit-VII (Mar’2007)<br />
LOI has been<br />
placed on M/s<br />
BHEL in Dec’2003<br />
pending MoEF<br />
clearance, which is<br />
awaited.<br />
Sipat-II (2x500 MW), Chhatisgarh<br />
Commissioning Schedule : Unit-IV (June’2007)<br />
Unit-V (Dec’2007)<br />
Efforts are on to<br />
commission both<br />
the units in the<br />
Tenth plan.<br />
Present Status : LOI has been<br />
placed on M/s.<br />
BHEL in Dec’2003<br />
pending MOEF<br />
clearance which is<br />
a w a i t e d .<br />
Excavation work for<br />
Boiler foundations<br />
has been taken up.<br />
Unchahar-III (1x210 MW), Uttar Pradesh<br />
Commissioning Schedule : Unit-V (Sept’2006)<br />
Present Status : LOI was placed on<br />
M/s. BHEL in<br />
Dec’03. MOEF<br />
clearance received<br />
in Mar’2004 and<br />
LOA has been<br />
released to BHEL.<br />
Piling work has<br />
been started at site.<br />
B) NEW PROJECTS<br />
a NEW Project <strong>of</strong> total capacity 1980 MW<br />
have been accorded investment approval:<br />
Sl. Projects Capacity<br />
No. (Location) (MW)<br />
1. Sipat Stage-I<br />
(Chhattisgarh)<br />
1980 (3x660)<br />
Also the main plant award for Sipat Stage-<br />
I (3 X 660 MW) TG package has been<br />
placed on 6th April 2004 and award for SG<br />
package has been placed on 15th b.<br />
April<br />
2004.<br />
The following new projects with a total<br />
capacity <strong>of</strong> 4550 MW are under<br />
consideration and for which action for<br />
procurement <strong>of</strong> LNG / Natural Gas has been<br />
taken up on International Competitive Bidding<br />
basis. Implementation <strong>of</strong> these projects is,<br />
however, subject to availability <strong>of</strong> LNG / Gas<br />
in a suitable time frame, at reasonable price/<br />
terms also acceptable to the beneficiary<br />
states.<br />
Sl.No. Projects/ Capacity<br />
Location (MW)<br />
1. Kawas Stage-II/(Gujarat) 1300<br />
2. Gandhar Stage-II/(Gujarat) 1300<br />
3. Kayamkulam –II (Kerala) 1950<br />
Hydro <strong>Power</strong> Projects<br />
Construction <strong>of</strong> Koldam Hydroelectric <strong>Power</strong><br />
Project (4x200 MW) in Himachal Pradesh is<br />
progressing as per schedule. Award for Main<br />
Dam, Spillway & <strong>Power</strong> In-take Package for<br />
Koldam project (800 MW) placed in December<br />
67