04.08.2013 Views

Untitled - Ministry of Power

Untitled - Ministry of Power

Untitled - Ministry of Power

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

106<br />

identified for R&M/LE and PHS Unit # II and<br />

PHS Unit # I.<br />

The RM&U work <strong>of</strong> MHS Unit # II by ALSTOM<br />

– BHEL consortium is in advanced stage <strong>of</strong><br />

completion. A portion <strong>of</strong> additional imported<br />

items have reached site. Balance materials<br />

are yet to be delivered by Consortium.<br />

Completion date has been further extended<br />

upto 30.06.2004.<br />

For RLA study <strong>of</strong> PHS Unit # I, re-tendering<br />

has been done after inclusion <strong>of</strong> additional<br />

vendors, as suggested by the consultant.<br />

Action for R&M/LE <strong>of</strong> MHS units # I & III will<br />

be taken after observing the performance <strong>of</strong><br />

MHS unit # II.<br />

Capacity Addition Programme during 10th Plan<br />

DVC has taken up capacity addition <strong>of</strong> 2210 MW during 10th Plan, brief status <strong>of</strong> which is indicated<br />

below:<br />

Sl No Project Capacity Target COD Brief Status<br />

1 Mejia TPS Extn. 1x210 MW Sept 2004 EPC Contractor: M/s BHEL. Major activities<br />

Unit # IV completed: Lifting <strong>of</strong> Boiler Drum, Hydro test<br />

(drainable), TG Casting etc. Activities in<br />

progress: Boiler, TG erection etc. BHEL is<br />

being pursued for supply <strong>of</strong> balance plant &<br />

equipment, which are delayed.<br />

2 Mejia TPS Extn. 2x250 MW 2006-07 All clearances obtained. EPC contract through<br />

Unit # V & VI negotiation with BHEL & PPA with beneficiaries<br />

under finalisation.<br />

3 Chandrapura TPS 2x250 MW 2006-07 MOEF clearance awaited.Engagement <strong>of</strong><br />

Extn. Unit # VII Consultant for EPC contract through ICB route:<br />

& VIII Techno-commercial bids opened on 27.01.04 are<br />

under scrutiny. COD is likely to slip.<br />

4 Maithon Right 4x250 MW 2006-07 Land acquisition in progress. The consultant is<br />

Bank TPS* being appointed for finalization <strong>of</strong> EPC contract<br />

through ICB route.<br />

* Implementation through Maithon <strong>Power</strong> Ltd (MPL), presently a wholly owned subsidiary <strong>of</strong> DVC after<br />

exit <strong>of</strong> erstwhile partner BSES (presently Reliance Energy). DVC is currently on the look out for<br />

another strategic joint venture partner for MPL.<br />

TRANSMISSION & DISTRIBUTION<br />

Matching with generation capacity addition,<br />

expansion <strong>of</strong> existing T&D network <strong>of</strong> DVC during<br />

10th Plan has been taken up as per the<br />

programme detailed below.<br />

T&D addition programme during 10th Plan<br />

220 KV Sub-stations 11 nos<br />

220 KV Lines 1686 ckt km<br />

132 KV Sub-stations 4 nos<br />

132 KV Lines 74 ckt km<br />

FLOOD CONTROL & WATER RESOURCE<br />

MANAGEMENT<br />

FLOOD CONTROL<br />

As per the unified development scheme <strong>of</strong><br />

Damodar basin submitted by Mr. W.A. Voorduin<br />

in August 1944, eight Storage Reservoirs viz,<br />

Maithon, Deolbari (near Balpahari), Tilaiya, Aiyar<br />

(near Tenughat), Bermo, Bokaro, Konar and<br />

Solanpur (near Panchet) were to be built on river<br />

Damodar and its tributaries with the main<br />

objectives <strong>of</strong> flood control, irrigation, domestic<br />

and industrial water supply and hydel power<br />

generation.<br />

At the first stage <strong>of</strong> implementation, four multipurpose<br />

Dams at Maithon, Panchet, Tilaiya and<br />

Konar have been constructed. But the designed<br />

storage levels could not be achieved due to<br />

constraint in acquiring the required land from the<br />

State Governments in respect <strong>of</strong> Maithon and<br />

Panchet reservoirs. In the first phase, total flood<br />

reserve capacity <strong>of</strong> 1.05 million acre-ft. could be<br />

arranged.<br />

However, even with the partial implementation <strong>of</strong><br />

the scheme, DVC over the years has been able<br />

to play a vital role in moderation <strong>of</strong> the floods to<br />

a great extent.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!