04.08.2013 Views

Rangyong - Ministry of Power

Rangyong - Ministry of Power

Rangyong - Ministry of Power

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

CHAPTER<br />

I<br />

TABLE OF CONTENTS<br />

DESCRIPTION<br />

Executive Summary<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

PAGE NO.<br />

1-11<br />

II Background Information 12-19<br />

III Project Area 20-27<br />

IV Topographical & Geo-technical Aspects 28-33<br />

V Hydrology 34-58<br />

VI Conceptual Layout and Planning 59-71<br />

VII <strong>Power</strong> Potential Studies 72-102<br />

VIII <strong>Power</strong> Evacuation 103<br />

IX Environmental Aspects 104-124<br />

X Infrastructure 125-128<br />

XI Construction Planning & Schedule 129-134<br />

XII Cost Estimate 135-174<br />

XIII Economic Evaluation 175-182<br />

Plates<br />

Annexures


TITLE<br />

LIST OF PLATES<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

PLATE<br />

No.<br />

Preliminary Ranking Study Layout 1<br />

Cascade Development <strong>of</strong> Teesta River Basin 2<br />

Layout Plan <strong>of</strong> Schemes in Upper Part <strong>of</strong> Teesta Basin 3<br />

Cascade Development <strong>of</strong> Tolung River Basin 4<br />

Geological Plan <strong>of</strong> The Project Area 4.1<br />

Vicinity Map 6.1<br />

Project Layout Plan 6.2<br />

Dam Area Layout Plan 6.3<br />

<strong>Power</strong> House Area Layout Plan 6.4<br />

Water Conductor System L-Section 6.5<br />

Upper Dam Upstream Elevation 6.6<br />

Lower Dam Upstream Elevation 6.7<br />

Dam: Spillway & Non-Overflow Cross Section 6.8<br />

Typical Cross Section Of Constituents Of Water<br />

Conductor System & Diversion Tunnel<br />

Single Line Diagram – <strong>Power</strong> Evacuation 8.1<br />

6.9


TITLE<br />

ANNEXURES<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

No.<br />

Geology <strong>of</strong> the Area Around the Project- By G SI 4.1<br />

Technical Report on Seismic History and<br />

Seismicity- By IMD<br />

4.2<br />

Preliminary Ranking Study Report- By CEA 6.1<br />

Reply on CEA/CWC Comments on Draft PFR 6.2


Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

CHAPTER – I<br />

EXECUTIVE SUMMARY


1.0 INTRODUCTION<br />

CHAPTER-I<br />

EXECUTIVE SUMMARY<br />

1<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

The <strong>Rangyong</strong> Hydroelectric Project located in North Sikkim district <strong>of</strong> Sikkim<br />

envisages utilization <strong>of</strong> the waters <strong>of</strong> the river <strong>Rangyong</strong> Chu a tributary <strong>of</strong> river Teesta<br />

for power generation on a run <strong>of</strong> river type development, harnessing a head <strong>of</strong> about<br />

738m by constructing two dams, one at downstream <strong>of</strong> confluence <strong>of</strong> Passaram Chu and<br />

Umram Chu tributaries <strong>of</strong> <strong>Rangyong</strong> Chu (Upper Dam) and other at <strong>Rangyong</strong> Chu<br />

(Lower dam).<br />

The project with a proposed installation <strong>of</strong> 141 MW (3 x 47MW) would afford an annual<br />

energy generation <strong>of</strong> 639.52 GWh in a 90% dependable year. The tariff from the project<br />

at present day cost would be Rs2.49 per KWh(levellised).<br />

The diversion sites are located at Latitude 27º36’00” North, Longitude 88º22’26” East<br />

(Upper Dam) and Latitude 27º35’00” North, Longitude 88º26’00” East (Lower Dam).<br />

The upper dam site is located just downstream <strong>of</strong> the confluence <strong>of</strong> Passaram Chu and<br />

Umram Chu and lower dam site on <strong>Rangyong</strong> chu . Presently lower dam site is not<br />

approachable while the upper dam site is approachable by a difficult foot path via<br />

Phontong from road ending at Lingza. The nearest road end is at Lingdem/ Lingza,<br />

which is about 15km from Mangan, the head quarters <strong>of</strong> North Sikkim District <strong>of</strong> Sikkim.<br />

The nearest railhead is at New Jalpaiguri and airport at Bagdogra.<br />

1.1 GENERAL PROJECT FEATURES<br />

The <strong>Rangyong</strong> HE Project envisages construction <strong>of</strong> :<br />

1. Two concrete dams, both 65 m high, one across river <strong>Rangyong</strong> Chu (Lower<br />

dam) and other at downstream <strong>of</strong> the confluence <strong>of</strong> Passaram Chu and Umram


2<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Chu to provide a total live storage <strong>of</strong> 1.97mcum. with FRL at 1845m and MDDL<br />

at 1825m;<br />

2. one link tunnel <strong>of</strong> 2.0km length and 3.3m diameter connecting upper dam with<br />

lower dam<br />

3. two intakes and two desilting chambers <strong>of</strong> size 125m(L)x 6 m(W)x 9m(H) to<br />

remove silt particles <strong>of</strong> size 0.2mm and above;<br />

4. a 7.5km long , 3.3m diameter head race tunnel terminating in a surge shaft;<br />

5. a 75m high, 10m dia surge shaft;<br />

6. 1000m long, 2.5m dia one pressure shaft;<br />

7. an underground power house having an installation <strong>of</strong> 3 Pelton turbine generating<br />

units <strong>of</strong> 47 MW each operating under a net head <strong>of</strong> about 723m; and<br />

8. a 300m long, 3.3m diameter tailrace tunnel to carry the power house release back<br />

to the river;<br />

The power generated from the project would be evacuated through one number 220KV<br />

double circuit lines to a proposed pooling station near Teesta II HE Project to feed power<br />

to the national grid.<br />

The salient features <strong>of</strong> the project are as under.<br />

LOCATION<br />

SALIENT FEATURES<br />

State Sikkim<br />

District North Sikkim<br />

Location <strong>of</strong> Upper Dam Just D/S <strong>of</strong> confluence <strong>of</strong> Umram<br />

chu and Passaram chu<br />

Location <strong>of</strong> Lower Dam On <strong>Rangyong</strong> Chu<br />

Location <strong>of</strong> <strong>Power</strong> House Just u/s <strong>of</strong> Reservoir <strong>of</strong> Panan H.E.<br />

project<br />

Nearest Rail head New Jalpaiguri


Nearest Airport Bagdogra<br />

Latitude upper dam & <strong>Power</strong> house 27º36’00’’& 27º33’14’’<br />

Latitude lower dam & <strong>Power</strong> house 27º35’00’’& 27º33’14’’<br />

Longitude <strong>of</strong> upper dam & <strong>Power</strong> house 88º22’26’’& 88º26’00’’<br />

Longitude <strong>of</strong> lower dam & <strong>Power</strong> house 88º21’48’’& 88º26’00’’<br />

HYDROLOGY<br />

Catchment area upper dam 146 km 2<br />

Catchment area Lower dam 127 km 2<br />

Design Flood for upper dam 750 m 3 /sec<br />

Design Flood for lower dam 675 m 3 /sec<br />

DIVERSION TUNNEL (for both dams)<br />

Diameter & Shape 3.3 m, Horse-shoe shaped<br />

Length 300 m<br />

Diversion Discharge ± 100 m 3 /sec<br />

Diversion Tunnel Gate 1 No. Vertical lift gate<br />

Size <strong>of</strong> Gate<br />

COFFER DAMS (for both dams)<br />

3<br />

3.3 m × 4 m<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Type Rockfill with central clay core.<br />

Maximum height <strong>of</strong> upstream c<strong>of</strong>fer dam ± 15.0 m<br />

Maximum height <strong>of</strong> downstream c<strong>of</strong>fer dam ± 8.0 m<br />

UPPER DAM<br />

Type Concrete Gravity<br />

Dam Top EL. 1850 m<br />

Length at Dam top 300 m


River bed level at dam site EL.1795m<br />

Maximum Dam height (above deepest<br />

foundation level)<br />

Dam height (above River bed level)<br />

LOWER DAM<br />

4<br />

65 m<br />

55 m<br />

Type Concrete Gravity<br />

Dam Top EL. 1850 m<br />

Length at Dam top 250 m<br />

River bed level at dam site EL.1795m<br />

Maximum Dam height (above deepest<br />

foundation level)<br />

65 m<br />

Dam height (above River bed level) 55 m<br />

SPILLWAY (For both the dams)<br />

Type Orifice Type<br />

No. <strong>of</strong> bays 3<br />

Crest level <strong>of</strong> spillway EL. 1805 m<br />

Size <strong>of</strong> the opening 3m(w) X 6m(H)<br />

Design flood (PMF) 750 / 675 m 3 /sec<br />

RESERVOIR<br />

UPPER DAM<br />

Full Reservoir Level (FRL) EL.1845 m<br />

Minimum draw down level (MDDL) EL.1825 m<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)


Area under submergence at FRL 15.62 Ha<br />

Gross Storage 3.05 MCM<br />

Live Storage 1.67 MCM<br />

LOWER DAM<br />

Full Reservoir Level (FRL) EL.1845 m<br />

Minimum draw down level (MDDL) EL.1825 m<br />

Area under submergence at FRL 2.5 Ha<br />

Gross Storage 0.525 MCM<br />

Live Storage 0.30 MCM<br />

LINK TUNNEL<br />

Invert level EL.1815 m<br />

Size 3.3 m diameter<br />

Size <strong>of</strong> Gate 3.3 m × 3.3 m<br />

5<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Trash Rack Steel Trash Racks with Raking<br />

Machine<br />

Length 1 Km<br />

INTAKE<br />

Number Two<br />

Invert level EL.1815 m<br />

Size <strong>of</strong> each Gate 3 m × 3 m<br />

Trash Rack Steel Trash Racks with Raking<br />

2<br />

Machine<br />

Design discharge 13.38 m 3 /sec in each intake


DESILTING ARRANGEMENT<br />

6<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

No., Type & size <strong>of</strong> desilting chamber 2 Nos.,Dufour type chambers each<br />

Total Design Discharge in each chamber 13.38 m 3 /sec<br />

125 m long, 6 m wide, ht.9 m<br />

Particle size to be removed ≥ 0.2 mm (90% efficiency)<br />

SILT FLUSHING TUNNEL<br />

Size & shape 1.5 m x 3.0 m, D-shaped<br />

HEADRACE TUNNEL<br />

Size & type 3.3 m Dia, Horse –shoe shaped,<br />

concrete lined<br />

Design discharge 22.30 m 3 /sec<br />

Length 7.5 Km<br />

Adits 3 No.; 3.3 m D-shaped<br />

SURGE SHAFT<br />

Size & type 10m diameter<br />

Vertical Shaft height ± 75 m<br />

PRESSURE SHAFT<br />

Type Steel Lined; one, Inclined<br />

Diameter<br />

Length<br />

Adits to Pressure Shaft<br />

2.5 m<br />

1000 m<br />

2 Nos., 3.3 m dia


POWER HOUSE COMPLEX<br />

Type Under ground<br />

Tail water level at outlet 1098 m<br />

Turbine Axis Elevation 1100.15 m<br />

Type <strong>of</strong> Turbine Vertical Pelton<br />

Generating Capacity 3X47 MW<br />

Gross head 738.18 m<br />

Rated Net head 723.18 m<br />

Design Discharge 22.30 m 3 /sec<br />

<strong>Power</strong> House Size 100m X 22.5m X 40m<br />

TRT<br />

Diameter and type 3.3m dia, Horse-shoe<br />

Tail Water level at outlet 1098m<br />

Length 300 m<br />

SWITCH YARD<br />

Size 155 M X 100M<br />

COST ESTIMATES & FIANANCIAL ASPECTS ( Rs. Crores)<br />

Civil Works 672.71<br />

Electro Mechanical Works 113.11<br />

Sub Total (Generation) 785.82<br />

Transmission Works 13.68<br />

7<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Total (Hard Cost) 799.50 at June,2003 Price Level<br />

Interest During Construction 91.32<br />

Grand Total 890.82<br />

Tariff for first year per KWh<br />

a. with 12% free power<br />

Rs. 3.07


. without 12% free power Rs. 2.70<br />

Levellised Tariff per KWh<br />

a. with 12% free power<br />

b. without free power<br />

8<br />

Rs. 2.49<br />

Rs. 2.19<br />

COSTRUCTION PERIOD 4 years<br />

1.2 STUDIES/INVESTIGATIONS UNDERTAKEN<br />

• Study <strong>of</strong> topographic maps and remote sensing imageries<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

• Reconnaissance <strong>of</strong> area for identifying probable alternative sites <strong>of</strong> projects<br />

components.<br />

• Study <strong>of</strong> regional geotechnical features/ seimotectonic aspects.<br />

• Geological appraisal <strong>of</strong> proposed project components.<br />

• Water availability design flood studies based on available meteorological/<br />

hydrological data.<br />

• Conceptual layout and project planning.<br />

• <strong>Power</strong> potential studies.<br />

• Study <strong>of</strong> biotic environment, socio-economic environment for prediction <strong>of</strong><br />

environmental impacts <strong>of</strong> the projects.<br />

• Study <strong>of</strong> existing infrastructure.<br />

• Cost benefit and economic evaluation.<br />

1.3 RESULTS OF STUDIES AND INVESTIGATIONS<br />

1.3.1 Geology<br />

The preliminary geological survey <strong>of</strong> the locations <strong>of</strong> all the structures on the ground was<br />

carried out after site visits. The site-specific geological data were got collected and<br />

utilized in the design <strong>of</strong> various component <strong>of</strong> the project. The survey <strong>of</strong> the near by area<br />

was also carried out to co-relate the geology <strong>of</strong> the project area. The underground<br />

powerhouse has been fixed after observing the competency <strong>of</strong> rock and its cover.


1.3.2 Hydrology<br />

9<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

The rivers <strong>Rangyong</strong> Chu, Umram Chu and Passaram Chu drain a total catchment area <strong>of</strong><br />

about 273sq.km at the proposed dam sites. The water availability for the project has been<br />

considered on the basis <strong>of</strong> 10-daily discharge series at Lachen for the period from 1976-<br />

1997. The water availability at the upper/lower dam sites has been derived from the<br />

above data on the basis <strong>of</strong> catchment area proportion and applying an overall reduction<br />

factor <strong>of</strong> 16 % and 17.8% respectively. The computed inflow series works out has been<br />

utilized for <strong>Power</strong> Potential Studies. The design flood has been assessed as 750 and 675<br />

cumecs for upper and lower dam sites respectively.<br />

1.3.3 <strong>Power</strong> Potential Studies<br />

The computed inflow series for 22 years viz Jan 1976 to Dec 97 has been considered in<br />

the assessment <strong>of</strong> a power benefits from the project. As per GOI notification for tariff the<br />

year 1976-77 corresponds to 90% dependable year. An installation <strong>of</strong> 141MW<br />

comprising 3 generating units <strong>of</strong> 47MW has been proposed. The energy availability from<br />

the project in a 90%dependable and an average year has been summarized below:<br />

Annual Energy Generation<br />

Annual Energy Generation (GWh) 639.52<br />

Annual Load Factor (%) 51.78<br />

Generation during Lean Flow Season<br />

Energy Output (GWh) 343.76<br />

Load Factor (%) 37.21<br />

The design energy for tariff at 95% availability in a 90% dependable year has been<br />

worked out at 639.52 GWh.<br />

A pondage <strong>of</strong> 1.97 mcum has been provided in the diversion dams, which would enable<br />

the station to operate as peaking station. The pondage is equivalent to 3460 MWh which<br />

sufficient to operate the station for 4 hours.


1.3.4 <strong>Power</strong> Evacuation Aspects<br />

10<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

The power generated from the project would be evacuated through 220KV, double circuit<br />

lines to a proposed pooling station near Teesta Stage-II project to feed into the Grid<br />

which in turn connected to National Grid.<br />

1.3.5 Environmental Aspects<br />

The project is located in north district <strong>of</strong> Sikkim. The total land requirement for the<br />

construction <strong>of</strong> various components is about 144ha. Most <strong>of</strong> the land falls under the<br />

category <strong>of</strong> private land. Based on assessment <strong>of</strong> environmental impacts, management<br />

plans have to be formulated for Catchment Area Treatment, compensatory afforestation<br />

and other environmental issues. These issues would be addressed during the investigation<br />

for DPR.<br />

1.3.6 Estimates Of The Cost<br />

The project is estimated to cost Rs. 890.82 crores including IDC at June,2003 price<br />

levels. The preliminary cost estimate <strong>of</strong> the project has been prepared as per guidelines <strong>of</strong><br />

CEA/CWC. The break down <strong>of</strong> the cost estimate (Rs. Crores) is given below:<br />

Civil works : 672.71<br />

Electro Mechanical Works : 113.11<br />

Sub Total (Generation) : 785.82<br />

Transmission Works : 13.68<br />

Total (Hard Cost) : 799.50<br />

Interest During Construction : 91.32<br />

Grand Total : 890.82<br />

1.3.7 Financial Aspects<br />

As indicated above, the <strong>Rangyong</strong>l HE project with an estimated cost <strong>of</strong> Rs. 890.82<br />

crores (including IDC <strong>of</strong> Rs. 91.32 crores) and design energy <strong>of</strong> 639.52GWh in a 90%<br />

dependable year is proposed to be completed in a period <strong>of</strong> 4 years. The tariff has been


11<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

worked out considering a debt-equity ratio <strong>of</strong> 70:30, 16% return on equity, annual interest<br />

rate on loan at 10% and 12% <strong>of</strong> energy as free power to Home State available after<br />

losses. The tariff for the first year and levellised tariff has been worked out Rs. 3.07/KWh<br />

& Rs. 2.49/KWh respectively.<br />

1.3.8 Conclusion<br />

The <strong>Rangyong</strong> HE project involves simple civil works and could be completed in 4 years.<br />

The project would afford a design energy <strong>of</strong> 639.52 GWh in a 90% dependable year. The<br />

cost per MW installed work out Rs.5.57 crores. The Preliminary Feasibility Report<br />

indicates that the scheme merit consideration for taking up for Survey & Investigation<br />

and preparation <strong>of</strong> DPR.


Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

CHAPTER – II<br />

BACKGROUND INFORMATION


2.1 GENERAL Information<br />

2.1.1 Introduction<br />

CHAPTER –II<br />

BACKGROUND INFORMATION<br />

12<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Sikkim has become 22 nd state <strong>of</strong> India in 1975. It is one <strong>of</strong> the most picturesque regions<br />

<strong>of</strong> Asia. The bowl like, mountain –girdled state in the eastern Himalayas bordered on the<br />

west by Nepal, on the north by Tibet, on the east by Bhutan and the south by Darjeeling<br />

district <strong>of</strong> the West Bengal, lies between 27 0 to 28 0 north latitude and 88 0 to 89 0 east<br />

longitudes. The Sikkim is the youngest and small hill state <strong>of</strong> India having an area <strong>of</strong><br />

7096 Sqkm. Sikkim is surrounded by important mountain ranges. The chola range <strong>of</strong><br />

mountains on its east forms the watershed between it and Bhutan on one side and chumbi<br />

valley <strong>of</strong> Tibet on the other. The well-known singalila ridge is <strong>of</strong> the great Himalayas<br />

peaks.<br />

Sikkim is divided into four districts. The most populated area is the Eastern district,<br />

which contains the capital town Gangtok followed by Southern and Western districts.<br />

The northern district is sparsely populated because <strong>of</strong> its inhospitable climate and steep<br />

ridges. Lying along the slopes <strong>of</strong> Himalayas between Tibet and plain <strong>of</strong> India, cut <strong>of</strong>f<br />

from the rest <strong>of</strong> the world by mighty mountains, Sikkim’s scenic beauty has no parallel in<br />

the East Sikkim’s historic past, mystic religion, sublime monasteries and age old rituals<br />

have an attraction hardly to be found anywhere else in the world.<br />

Sikkim is mountainous terrain with cliffs and valleys. Dominating both legend and<br />

landscape is the mighty massif <strong>of</strong> Kanchendzonga known to the outside world as<br />

Kanchenjunga, it is the third highest peak in the world, towering at 8550 meters. Sikkim<br />

is drained by number <strong>of</strong> Perennial Rivers. However, the two main river systems are<br />

Teesta and Rangit. The other entire stream eventually joins one or the other. Rangit also<br />

joins the Teesta just near the broader between Sikkim and West Bengal at Melli. Besides


13<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

the river, there are number <strong>of</strong> lakes and hot springs which add to the beauty <strong>of</strong> the region.<br />

The important hot springs are Phut sachu, Raeong sachu, Yumthang and Momay.<br />

2.1.2 Topography<br />

Geographical area <strong>of</strong> Sikkim State is about 7300 sq. km. The maximum horizontal length<br />

from north to south is about 112 Km. whereas the maximum width from east to west is 90<br />

Km. The Tibetan Plateau on the north, Nathula and other passes on the north east, Bhutan<br />

on the south east, Darjeeling district <strong>of</strong> West Bengal on the south and Singalila range <strong>of</strong><br />

Nepal from the boundaries <strong>of</strong> this picturesque Himalayan State. It is a hill state having no<br />

plain area. The altitude above mean sea level varies from 213m in the south to over<br />

8500m in the northwest. The Khangchedzonga, the third highest peak in the world at an<br />

elevation <strong>of</strong> about 8550m adorns the state with its beautiful range covered with shining<br />

snow. Gangtok, the capital is about 1677m above mean sea level. The northern part <strong>of</strong> the<br />

state is cut into deep escarpments. The northern part is not populated except in Lachung<br />

and Lachen valleys. Southern Sikkim is, however, more open and fairly well cultivated.<br />

2.1.3 Rivers<br />

The river Teesta is one <strong>of</strong> the main Himalayan Rivers, which originates in the glaciers <strong>of</strong><br />

Sikkim at an elevation <strong>of</strong> over 8500m above mean sea level. River rises in mountainous<br />

terrain and is formed mainly by the union <strong>of</strong> two hill streams Lachen Chu and Lachung<br />

Chu at Chungthang in North Sikkim. After the confluence <strong>of</strong> Lachen Chu and Lachung<br />

chu at Chungthang, the river gradually increases in width and takes a wide flowing down<br />

to Singhik, dropping in elevation from 1550m to 750m. At Singhik, the river receives one<br />

<strong>of</strong> the its major tributaries, the Talung chu on its right. Tolung Chu originates from the<br />

Talung glaciers, which are the part <strong>of</strong> the Khangchendzonga range. From Singhik, the<br />

rivers flow towards Dikchu in a very deep valley and drops from 750mto 550m. From<br />

Dikchu the river flows in a big curve again down to the Singtam with a drop <strong>of</strong> about<br />

200m. The Rongnichu, which drains the Changu lake area joins Teesta from left at<br />

Singtam and the river receives Rangpo Chu at Rangpo. After Rangpo, Teesta start


14<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

widening rapidly and is joined by the great Rangit at Melli bazar on Sikkim – West<br />

Bengal border.<br />

2.1.4 Communication<br />

By Air<br />

Bagdogra is the nearest airport <strong>of</strong> Sikkim. There are regular scheduled flights operated by<br />

the Indian airlines and other private airlines between Calcutta, the capital <strong>of</strong> West Bengal<br />

and Bagdogra and also between New Delhi and Bagdogra. Jeep taxis are available<br />

outsides Bagdogra airport for Gangtok. Gangtok is 124 kms from Bagdogra and the<br />

journey takes about 4 hours by jeep and 5 hours by bus.<br />

By Rail /Road<br />

The two closest railway stations to Gangtok are Siliguri junction, (Meter Gauge) which is<br />

114km away and New Jailpaiguri (Broad Gauge), which is 125km away. A number <strong>of</strong><br />

trains are available for Calcutta, Delhi, Guwhati and other important cities <strong>of</strong> India.<br />

Besides jeep taxis, Sikkim National Transport and other private buses ply regularly<br />

between Sikkim and Siliguri.<br />

2.1.5 The Project<br />

2.1.5.1 Background<br />

In order to exploit vast hydro potential in the country and to achieve the ideal hydro<br />

thermal mix <strong>of</strong> 40:60, the Honourable Prime Minister <strong>of</strong> India had launched a hydro-<br />

electric initiative on 24th May 2003 to develop 50,000MW hydro power potential in the<br />

country. Accordingly, based on the results <strong>of</strong> the preliminary ranking studies <strong>of</strong> Central<br />

Electricity Authority, 162 hydroelectric power schemes with estimated installed capacity<br />

<strong>of</strong> 50,560MW were selected in 16 states for preparation <strong>of</strong> Pre Feasibility Reports. The<br />

work <strong>of</strong> preparation <strong>of</strong> PFR’s was entrusted by <strong>Ministry</strong> <strong>of</strong> <strong>Power</strong> under overall<br />

coordination <strong>of</strong> CEA to NHPC Ltd, SJVN Ltd, NEEPCO, WAPCOS, KPCL, HPSEB and<br />

UJVN Ltd as consultancy work. NHPC was entrusted a total number <strong>of</strong> 43 schemes <strong>of</strong>


15<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

21345 MW comprising <strong>of</strong> 7 schemes in Indus-Jhelam Basin J&K, 25 schemes in Dihang-<br />

Dibang-Subansiri Basins Arunachal Pradesh, 1 scheme in Narmada Basin Madhya<br />

Pradesh and 10 schemes in Teesta Basin Sikkim. The <strong>Rangyong</strong> is one <strong>of</strong> the such<br />

scheme for PFR.<br />

2.1.5.2 About The Project<br />

The project is located on the river <strong>Rangyong</strong> chu in Dzongu area <strong>of</strong> North district <strong>of</strong><br />

Sikkim. The headquarter <strong>of</strong> the district North Sikkim is at Mangan. The project involves<br />

construction <strong>of</strong> two 65m high concrete dams, a 2.0 Km link tunnel, a 7.5 Km long<br />

headrace tunnel and an underground powerhouse with an installed capacity <strong>of</strong> 141 MW.<br />

The project shall generate 639.52 MU <strong>of</strong> energy in a 90% dependable year. The<br />

upperdam is located just downstream <strong>of</strong> the confluence <strong>of</strong> Umram Chu and Passaram<br />

Chu. The lowerdam is located on the river <strong>Rangyong</strong> Chu near by the place called<br />

Singnok.The underground powerhouse is located just u/s <strong>of</strong> the confluence <strong>of</strong> <strong>Rangyong</strong><br />

Chu and Ringyong Chu. The place Singnok nearest to Dam site, is connected from<br />

Mangan by 18 km long state PWD road upto Lavan and a footpath <strong>of</strong> about 12km via<br />

Phontong. The underground power house is located just u/s <strong>of</strong> confluence <strong>of</strong> Ringyong<br />

Chu and <strong>Rangyong</strong> Chu.<br />

2.2 POWER SCENARIO AND EXISTING INSTALLATION<br />

2.2.1 <strong>Power</strong> System In India<br />

The <strong>Power</strong> System in India has grown from small, isolated stations, serving limited<br />

consumers in and around large cities, into large regional <strong>Power</strong> Grids. The generating<br />

capacity installed in the country has already grown to 107903.53 MW by March 2003.<br />

For the purpose <strong>of</strong> system planning and operation the country has been divided into<br />

following five geopolitical regions: Northern, Western, Southern, Eastern and North-<br />

Eastern regional power grids and the transmission system are being progressively inter-<br />

connected for efficient operation <strong>of</strong> these five regional grids.


16<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

The objective <strong>of</strong> the system development is to evolve self-sufficient regional grid catering<br />

to the individual regional power demands. It is also aimed at achieving the maximum<br />

benefits from integrated operation, through a proper mix <strong>of</strong> thermal and hydro generation<br />

and ultimately to tie the five regional grids together to form a strong National <strong>Power</strong><br />

Gird, providing even greater reliability.<br />

2.2.2 <strong>Power</strong> Position in North Sikkim Region<br />

The total installed capacity in Eastern Region is 16696.68 MW. Out <strong>of</strong> this only 2459.51<br />

MW is hydel installation. Thus the Hydro-thermal mix is 15:85, which is well below the<br />

national average <strong>of</strong> 25:75 and desirable ratio <strong>of</strong> 40:60.<br />

The power supply position for Eastern region during 10th and 11th Five Year Plans is<br />

summarised in Table2.1. The power and energy availability and requirements during and<br />

after 10th Plan period in the Eastern Region is shown in Tables as projected in the 16th<br />

Electric <strong>Power</strong> Survey, published by CEA.<br />

Even considering the coordinated operation <strong>of</strong> existing hydro and thermal stations, as<br />

well as benefits from ongoing projects and also from the schemes cleared by CEA, the<br />

Eastern region is expected to face peak power and energy deficits during most <strong>of</strong> the 10th<br />

five Year Plan. The power situation in the region is dynamic and it is expected that the<br />

power generated from this project shall be cheap and helpful to the region as compared to<br />

thermal and other expensive power in the region.<br />

2.2.3 Existing <strong>Power</strong> Installations In Sikkim<br />

First time, a micro hydel station was established in Sikkim on the bank <strong>of</strong> Ranikhola at<br />

Lower Sichey Busty with an installed capacity <strong>of</strong> 10 KW on 27 th May 1927 for the needs<br />

<strong>of</strong> the members <strong>of</strong> the Royal family and Gangtok. Later, Lower Lagyap Hydel Project with<br />

an installed capacity <strong>of</strong> 12MW was constructed by Govt. <strong>of</strong> Sikkim and this was a big


17<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

boom. Presently following hydel schemes totaling 95.70MW are under operation in the<br />

state.<br />

Sl.<br />

Hydel Schemes Year <strong>of</strong><br />

Installed<br />

Firm<br />

No. 1 2 Completion 3 Capacities 4 Capacity 5<br />

1 Jali <strong>Power</strong> House 1966 2.10 1.20<br />

2 Rothak Micro Hydel 1971-72 0.20 0.10<br />

3 Rimbi Micro Hydel, Stage-I 1970-71 0.60 0.30<br />

4 Lower Lagyap HEP 1979-80 12.00 5.50<br />

5 Lachen Micro Hydel 1989-90 0.10 0.05<br />

6 Rimbi Stage-II 1989-90 1.00 0.50<br />

7 Rongnichu Micro Hydel-II 1988-89 2.50 1.20<br />

8 Lachung Micro Hydel 1991-92 0.20 0.10<br />

9 Mayongchu 1993-94 4.00 2.00<br />

10 Upper Rongnichu HEP 1994-95 8.00 4.00<br />

11 Kalej Khola 1995-96 2.00 1.00<br />

12 Rangit Hydel Project 1999-00 60.00 20.00<br />

13 Robom Micro Hydel 2003-04 3.0 1.00<br />

I - Total Hydel <strong>Power</strong> 95.70 36.95<br />

II - Total Diesel <strong>Power</strong> 2.70 2.70<br />

Total Generation Capacity 98.40 39.65<br />

2.2.4 Load Demand & <strong>Power</strong> Position <strong>of</strong> Eastern Grid<br />

Table-2.1 shows the power supply position <strong>of</strong> Eastern grid up to 2011-12.


18<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

2.2.5 NECESSITY OF THE PROJECT AND RELATED ASPECTS<br />

The need for <strong>Rangyong</strong> H.E. Project has been considered in the context <strong>of</strong> increasing<br />

demand <strong>of</strong> power in the eastern region. It has been assumed that eastern region will have<br />

energy requirements at the rate 10% per annum rise <strong>of</strong> each year. This is a run <strong>of</strong> the<br />

river scheme with little pondage in Teesta basin in North Sikkim District, Sikkim. It will<br />

generate 639.52 MU in 90% dependable year (1976-77) with 95% machine availability.<br />

The power generated at <strong>Rangyong</strong> HEP (3 X 47MW) would be evacuated through one<br />

number 220KV double circuit lines to a proposed pooling station near Teesta II HE<br />

Project to feed power to the national grid.


Table 2.1<br />

POWER SUPPLY POSITION OF EASTERN REGION<br />

WITHOUT RANGYONG HE PROJECT, (141MW)<br />

10th Plan 11th Plan<br />

19<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project, (3 x 47 MW)<br />

Eastern Region 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12<br />

1 2 3 4 5 6 7 8 9 10<br />

Installed Capacity MW 16697 17197 18327 20077 21237 22369 23269 24769 25429 26749<br />

Peak availability MW 7676 7906 8425 9230 9763 10284 10697 11387 11690 12297<br />

Peak requirement MW 8076 8527 9002 9505 10035 10586 11167 11780 12427 13109<br />

Peak Surplus(Deficit) MW -400 -621 -577 -275 -272 -302 -470 -393 -737 -812<br />

Peak Surplus(Deficit) % -4.95% -7.28% -6.41% -2.89% -2.71% -2.86% -4.21% -3.34% -5.93% -6.19%<br />

Energy availability MU 50260 51765 55167 60434 63926 67334 70043 74558 76545 80518<br />

Energy requirement MU 51653 54484 57469 60619 63941 67400 71046 74890 78941 83212<br />

Energy Surplus (Deficit) MU -1393 -2718 -2303 -184 -14 -66 -1003 -331 -2396 -2694<br />

Energy Surplus (Deficit) % -2.70% -4.99% -4.01% -0.30% -0.02% -0.10% -1.41% -0.44% -3.04% -3.24%<br />

1. All the data for the year 2002-2003 has been taken from the website www.cea.nic.in.<br />

2. Energy availability for the year 2002-2003 onwards have been estimated on the basis <strong>of</strong> ratio <strong>of</strong> Energy availability to Installed capacity for the year 2002-<br />

2003.<br />

3. Peak availability for the year 2002-2003 onwards have been estimated on the basis <strong>of</strong> ratio <strong>of</strong> Peak availability to installed capacity for the year 2002-2003.<br />

4. Energy requirement & peak requirement for the year 2002-2003 onwards is based on the annual increments given at page -117 & 118 <strong>of</strong> "Sixteenth Electric<br />

<strong>Power</strong> Survey Of India".<br />

5. Micro/mini projects have not been considered for the study.<br />

Note:- This is a statistical analysis based on various publications mentioned above and are meant for study and planning purposes.


Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

CHAPTER – III<br />

PROJECT AREA


CHAPTER –III<br />

PROJECT AREA<br />

3.1 DESCRIPTION OF PROJECT INCLUDING RIVER SYSTEM<br />

20<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

<strong>Rangyong</strong> H.E. Project is situated in the Dzongu area <strong>of</strong> north district <strong>of</strong> Sikkim .The<br />

project envisages construction <strong>of</strong> 65 m high two concrete gravity dams one just<br />

downstream <strong>of</strong> the confluence <strong>of</strong> Umram Chu and Passaram Chu and another on the river<br />

<strong>Rangyong</strong> Chu nearby the place called Singnok. The under ground powerhouse is just<br />

upstream <strong>of</strong> the Confluence <strong>of</strong> <strong>Rangyong</strong> Chu and Ringyong Chu . The rivers water shall<br />

be diverted through a diversion tunnels <strong>of</strong> 300 m long each and 3.3 m dia for construction<br />

<strong>of</strong> dams. A 2.0Km long link tunnel shall connect both the dams and a 7.5 km length<br />

headrace tunnel <strong>of</strong> 3.3m dia shall carry a discharge <strong>of</strong> 22.30 cumecs <strong>of</strong> water to the<br />

powerhouse. Two number <strong>of</strong> desilting chambers <strong>of</strong> 175m x 10m x 12 m size shall be<br />

constructed to separate the silt particles <strong>of</strong> 0.2mm size and above from the water. A surge<br />

shaft <strong>of</strong> 10 m dia and 75 m high along with one pressure shaft <strong>of</strong> 2.5m dia & 1000 m<br />

length shall be constructed. A tailrace tunnel <strong>of</strong> 300m length and 3.3 m dia shall<br />

discharge the water back into the river. A switchyard <strong>of</strong> 155m x 100m size shall also be<br />

constructed. The powerhouse shall have installed capacity <strong>of</strong> 141 MW to generate 639.52<br />

MU <strong>of</strong> energy in a 90% dependable year.<br />

The river Umram Chu and Pasaram Chu are the tributaries <strong>of</strong> the <strong>Rangyong</strong> Chu<br />

originating in the glaciers <strong>of</strong> North Sikkim at an elevation <strong>of</strong> about 5000 m above mean<br />

sea level and meets <strong>Rangyong</strong> Chu upstream <strong>of</strong> the confluence <strong>of</strong> Ravingrum Chu .The<br />

other tributaries <strong>of</strong> the <strong>Rangyong</strong> Chu /Tolung Chu are Rukel Chu, Pokhram Chu, Ringpi<br />

Chu, Ringyang Chu, Rangli Chu and Rahi Chu. Both the rivers Rahi Chu and <strong>Rangyong</strong><br />

Chu meets Teesta river near village Singhik . After running about 14 Km from the<br />

confluence, the Dikchu River joins the Teesta River near the village Dikchu. In the<br />

downstream the Rongni Chu joins Teesta River at Singtam, Rangpo Chu at Rangpo and<br />

Rangit at Melli.


3.2 SOCIO-ECONOMIC AND OTHER ASPECTS<br />

3.2.1 Demographic Features<br />

21<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

As per the 2001 census <strong>of</strong> India, the total population <strong>of</strong> the State is 540,493. The overall<br />

density <strong>of</strong> population in the State is 57 per sq. Km. East district is the most populated<br />

where as North's density is only 7 and is the least populated. Sex ratio (females per<br />

thousand male) in 1981 was 835, where as it had improved in 1991 to 878 and in 2001<br />

has shown a declining trend with a value <strong>of</strong> 875. There are only eight urban towns and<br />

constitutes only 9.10% <strong>of</strong> total population. Literacy rate was 56.94% (19th position) in<br />

1991 and has increased to 70.65% in 2001. The rural literacy rate in 2001 is 68.59%<br />

whereas the urban literacy rate is 85.80%.<br />

The economy <strong>of</strong> Sikkim is mainly based on agricultural and animal husbandry.<br />

Approximately 11% <strong>of</strong> the total geographical area is under agriculture. The work force<br />

participation rate as per 1991 census is 40.44%. The female participation rate in Sikkim is<br />

also much higher than the national average. This is an important aspect in the hill<br />

economy, as productivity is low and hence the people are engaged in agriculture and<br />

other activities. Cultivators account for the greater majority <strong>of</strong> the people in the State.<br />

Animal husbandry is an integral part <strong>of</strong> the house holds economy <strong>of</strong> the region. There are<br />

certain household industries also which substantially adds to household incomes. The<br />

past one and half decade has witnessed a tremendous upward swing in various<br />

development programme giving a new thrust to the Sikkim economy. This process has<br />

increased wage employment opportunities. There is very little human habitation in the<br />

vicinity <strong>of</strong> the proposed project site. Only a few small villages, comprised <strong>of</strong> few hamlets<br />

only, viz. Sakyong, Phontong, Singnak, Myong and Shabrung under Sakyong Pentong<br />

Revenue Block fall within 10km radius <strong>of</strong> the project area. The human population as per<br />

the 1991 census up to different aerial distances from the project are given below.<br />

Up to 2 km Up to 2-5 km Up to 5-10 km<br />

Population Nil 199 694<br />

Households Nil 49 145


3.2.2 Ethnographic details (Details <strong>of</strong> the tribals in the area)<br />

22<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

In Sikkim various communities with their own customs, religion and culture intermingle<br />

freely to constitute a homogeneous blend. The predominant communities are the<br />

Lepchas, Bhutias and Sherpas. Lepchas, Bhutias, Sherpas are categorized as Scheduled<br />

Tribes. The Lepchas are the original inhabitants <strong>of</strong> the State. Compared to other ethnic<br />

groups, the Lepchas still maintain many <strong>of</strong> their traditional ways. The Bhutias comprise,<br />

the Sikkimese Bhutia and Bhutia from Bhutan and Tibet. The Sherpas are a marginal<br />

ethnic group in the State. Over 80% population consists <strong>of</strong> Nepalese. Many people from<br />

the plains have also settled, especially in the urban areas and they are almost always<br />

engaged in business or Government services. A small part <strong>of</strong> the population consists <strong>of</strong><br />

migrant labourers from Bihar, West Bengal, Eastern UP and Nepal. The population near<br />

the dam site is quite thin dominated by yak and sheep grazers. Some marginal<br />

agricultural farmers also live nearby. Crops like cardamom, ginger, potato, millet, wheat<br />

and maize are grown in the area.<br />

3.2.3 Health & Education<br />

There are 4 district hospitals, Gyalshing, Namchi, Singtam & Mangan and one Central<br />

Referral Hospital at Gangtok, besides 25 Primary health centers 150 Primary health sub-<br />

centre, 9 Veterinary hospitals and 25 Veterinary dispensaries. There is a blood bank at<br />

Gangtok. There are 1234 doctors. Small pox and Kalzor have been eliminated from the<br />

state and many schemes for the provision <strong>of</strong> safe drinking water to the villages and<br />

bazars have been implemented. Sikkim has 700 Pre-nursery schools, 531Primary schools,<br />

122 Middle schools, 64 Secondary schools, and 28 Higher secondary schools 2 Public<br />

schools. There is a Training Institute for primary teachers, a Law college, a B.Ed. college,<br />

2 Degree colleges, one Industrial Training Institution, a Medical and an Engineering<br />

college.


3.2.4 Religion<br />

23<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Hinduism and Buddhism are the two main religions prevalent in Sikkim. Hindus and<br />

Buddhists constitute 99 percent <strong>of</strong> the population; Christians, Muslims, Jains and Sikhs<br />

together are less than one per cent.<br />

3.2.5 Trade & Industry<br />

Sikkim has a State Industrial Development Investment Corporation, which is encouraging<br />

establishment <strong>of</strong> industrial units in Sikkim. The Industrial Training Institute located at<br />

Rangpo is providing necessary expertise to the younger people for self-independence in<br />

the trade and the know-how. Sikkim has two distilleries , one tannery, and other ancillary<br />

units. Rangpo area has been declared as an industrial Zone. A Brewery is located at<br />

Melli, South Sikkim. and another at Rangpo, East Sikkim. There is also a fruit<br />

preservation factory at Singtam. The Sikkim Mining Corporation mines copper, zinc, lead<br />

etc in the state. The Sikkim Time Corporation a watch-manufacturing factory is located at<br />

Gangtok, which is producing one <strong>of</strong> the latest watches in India. There is a jewel factory<br />

located at Gangtok. Besides the above a good number <strong>of</strong> entrepreneurs have recently<br />

proposed to set up new factories. Some <strong>of</strong> the units are manufacturing leather goods,<br />

safety matches, local crafts, carpet weaving, handmade paper, woodcarving and similar<br />

works. The Sikkim State Tea Board has also been established for quality tea production.<br />

3.2.6 Natural Resources<br />

Sikkim is gifted with abundant natural resources. The resources can be grouped into a<br />

biotic & biotic both <strong>of</strong> which can be renewable and non-renewable. Biotic resources<br />

include agricultural crops, forests etc. The entire Himalayan region is endowed with<br />

natural flora and fauna and is a natural paradise for nature lovers, conservationists,<br />

botanists, zoo lists and environmentalists. There are 4500 species <strong>of</strong> flowering plants, 300<br />

species <strong>of</strong> primulas, 20 species <strong>of</strong> bamboos etc., 45 species <strong>of</strong> rhododendrons and around<br />

450 species <strong>of</strong> orchids.


24<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

The State is very rich in fauna also. There are 144 species <strong>of</strong> mammals, 500-600 species<br />

<strong>of</strong> birds, over 400 species <strong>of</strong> butterflies and moths and many species <strong>of</strong> reptiles are<br />

available. Sikkim is rich in medicinal plants/herbs and also important shrubs are found in<br />

low and high altitude areas. The State is endowed with water resources, tourism,<br />

hydroelectric potential etc. Under economic geology minerals like copper, iron, lime,<br />

dolomite, limestone, coal, quartzite, silicate & graphite are available in the state. As per<br />

the available data around 60% <strong>of</strong> cardamom production in India is from Sikkim. There is<br />

a vast potential for hydroelectric power generation. Tourism development deserves<br />

considerable attention to add to the economy <strong>of</strong> the region.<br />

3.2.7 Hydropower Potential<br />

The Teesta and Rangit are the two main rivers <strong>of</strong> Sikkim where considerable hydro<br />

potential is available. Sikkim have developed 95.7 MW <strong>of</strong> hydropower potential so far by<br />

constructing mini & micro hydel projects and about 600 MW hydel potential is under<br />

development in different stages. The details <strong>of</strong> hydropower potential identified is as<br />

under:<br />

Teesta Basin :<br />

According to the preliminary reconnaissance survey, the river could be harnessed under a<br />

cascade development for hydropower generation is six stages as under :<br />

i) Teesta Stage-I<br />

It is possible to diver the water <strong>of</strong> Teesta river d/s <strong>of</strong> confluence Chento chu near<br />

Shacham and d/s <strong>of</strong> confluence Lhonak chu and Poke chu by constructing diversion<br />

structures at EL ± 3330 and interconnecting tunnels discharging the Tail water at an EL ±<br />

2623 near the place Zema. The scheme will have installed capacity <strong>of</strong> about 320 MW.<br />

ii) Teesta Stage-II<br />

Under this scheme, a diversion dam <strong>of</strong> 83 m high is proposed near Bonsoi to divert the<br />

tail water <strong>of</strong> Teesta Stage-I and the power house at Chungthang. The scheme shall<br />

generate 330 MW.


iii) Teesta Stage-III<br />

25<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

The schemes involve construction <strong>of</strong> Teesta River and Lachung chu near Chungthang and<br />

a <strong>Power</strong> house near Singhik. The scheme shall have the installed capacity <strong>of</strong> 1200 MW .<br />

iv) Teesta Stage-IV<br />

A diversion dam is proposed just d/s <strong>of</strong> confluence <strong>of</strong> Teesta and Tolung chu near the<br />

place called Sanklan and power house near the village Dikchu. The scheme shall have<br />

installed capacity <strong>of</strong> 495 MW.<br />

v) Teesta Stage-V<br />

A diversion dam has been proposed d/s <strong>of</strong> confluence <strong>of</strong> Dikchu chu and Teesta river and<br />

a power house near the village Sherwani. The scheme shall have installed capacity <strong>of</strong> 510<br />

MW.<br />

vi)Teesta Stage-VI<br />

<strong>Power</strong> Potential <strong>of</strong> Rangit Basin It envisages construction <strong>of</strong> a 76 m high concrete dam<br />

near Khanitar d/s <strong>of</strong> the confluence <strong>of</strong> the Teesta and Rongni chu in East Sikkim and the<br />

power house near the village Namthang/Tarkhola in South Sikkim with installed capacity<br />

<strong>of</strong> 360 MW.<br />

Rangit Basin<br />

The hydropower development <strong>of</strong> Rangit river was identified in four stages as under :<br />

i) Rangit HE Project Stage –I<br />

The Rathong chu, a major perennial tributary <strong>of</strong> Rangit river has a very steep bad slop.<br />

The river takes a big loop near Yoksum. It is proposed to divert the water <strong>of</strong> Rathong chu<br />

at an elevation <strong>of</strong> about 2300 m U/S <strong>of</strong> Yoksum to elevation <strong>of</strong> 100 m near village<br />

Thingtom. The scheme shall generate 47 MW <strong>of</strong> power at 60 % load factor.<br />

ii) Rangit HE Project Stage-II<br />

It is proposed to divert the water <strong>of</strong> Rimbhi chu near Sigglitem and allow the water to<br />

drop through 425 m near Lingchum on Kalet chu to generate 10 MW <strong>of</strong> power at 60%<br />

load factor.


iii) Rangit HE Project Stage –III<br />

26<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

A dam has been constructed just d/s <strong>of</strong> confluence <strong>of</strong> Rathong chu and Rangit river and a<br />

power house near the village Mongbru. The installed capacity <strong>of</strong> the scheme is 60 MW.<br />

The project has been commissioned by NHPC in the year 1999 and is in operation.<br />

iv) Rangit HE Project Stage-IV<br />

The scheme shall utilize a drop <strong>of</strong> 110 m from an elevation <strong>of</strong> 440 m to 355 m in Reshi<br />

loop. The scheme shall generate 18 MW <strong>of</strong> power at 60 % load factor.<br />

Schemes For PFR in Teesta Basin<br />

The Cenrtral Elecrtricity authority entrusted 10 schemes with total installed capacity <strong>of</strong><br />

1569 MW for preparation <strong>of</strong> prefeasibility reports as per details given below:<br />

Sl. Name <strong>of</strong> Scheme Installed Name <strong>of</strong><br />

District<br />

No.<br />

Capacity (MW) River<br />

1. Dikchu 105 Bakchachu/Dikchu chu East<br />

2. Rongni 195 Rongni chu East<br />

3. Namlum 160 Rangit South<br />

4. Panan 200 Tolung chu North<br />

5. Lingza 160 Ringpi North<br />

6. <strong>Rangyong</strong> 141 <strong>Rangyong</strong>/ Umramchu North<br />

7. Ringpi 70 Ringpi North<br />

8. Rukel 33 Rukel/<strong>Rangyong</strong> North<br />

9. Jedang 185 Jhonak chu North<br />

10. Teesta Stage-I 320 Teesta & Zemu chu North<br />

OTHER SCHEMES IDENTIFIED BY CEA AND SIKKIM<br />

The CEA in the preliminary ranking studies and Sikkim in the preliminary studies<br />

identified the fallowing schemes:<br />

Sl. Name <strong>of</strong> Scheme Installed Capacity Name <strong>of</strong> River<br />

No.<br />

(MW)<br />

1. KalepHE Project 40 Teesta<br />

2. Talem HE Scheme 65 Teesta<br />

3. Serum HE Scheme 50 Lachung Chu<br />

4. Lachung HE Scheme 30 Lachung<br />

5. Chhota Pathing/Rolep 55 Chu/Sebokong Rangpo Chu<br />

Chu


27<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

6. Chuzachen 13 Rangpo Chu<br />

7. Suntalitar HE Scheme 25 Rangpo Chu<br />

8. Mana 37 Rangit<br />

9. Gompa 46 Rangit<br />

10. Rammam Stage-I 70 Rammam<br />

11. Rammam Stage-II 85 Rammam<br />

12. Rammam Stage-III 100 Rammam<br />

13 Chakhung Chu hydel 30 Chakhung Chu<br />

In addition to above schemes, the Govt. <strong>of</strong> Sikkim have identified about 40 mini/micro/<br />

small schemes for hydropower development in the region.


Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

CHAPTER – IV<br />

TOPOGRAPHICAL &<br />

GEO-TECHNICAL ASPECTS


CHAPTER-IV<br />

28<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

TOPOGRAPHIC AND GEOTECHNICAL ASPECTS<br />

4.1 INTRODUCTION<br />

The <strong>Rangyong</strong> Scheme envisages construction <strong>of</strong> a diversion scheme on <strong>Rangyong</strong> Chhu<br />

about 1.2Km upstream <strong>of</strong> its confluence with Umram Chhu, a water conductor system in<br />

the right bank and a <strong>Power</strong> House downstream <strong>of</strong> confluence <strong>of</strong> <strong>Rangyong</strong> Chhu and<br />

Ringpi Chhu. The scheme has been proposed by Central Electricity Authority in order to<br />

tap the water potential <strong>of</strong> <strong>Rangyong</strong> Chhu. Another scheme namely Rukel scheme has<br />

been proposed with the tail water discharging upstream <strong>of</strong> the diversion structure <strong>of</strong><br />

<strong>Rangyong</strong> Chhu. However, in order to augment the water potential <strong>of</strong> <strong>Rangyong</strong> Chhu<br />

the water from Umram Chhu, a left bank tributary <strong>of</strong> <strong>Rangyong</strong> Chhu shall be discharged<br />

into the reservoir <strong>of</strong> the proposed scheme through a 2km long link tunnel. The scheme is<br />

expected to generate approximately 141MW <strong>of</strong> power. The present appraisal is based on<br />

study <strong>of</strong> topographic sheet 78 A/6 and a report <strong>of</strong> GSI titled “Geology <strong>of</strong> the Area<br />

Around the Proposed <strong>Rangyong</strong> Hydroelectric Project” which is enclosed a Annexure –<br />

4.1.<br />

As a part <strong>of</strong> MOU between NHPC and CEA preparation <strong>of</strong> pre-feasibility report has been<br />

assigned to NHPC. Attempts were made to visit the area however, the same could not be<br />

matured since the footpath from Lingza to Sakkyong was damaged. As a result the<br />

present appraisal is based on regional geological data and geological assessment <strong>of</strong> the<br />

area made during the visits to Pannan, Lingza and Ringpi schemes.<br />

4.2 REGIONAL TOPOGRAPHIC AND GEOTECHNICAL FEATURES<br />

River Teesta in Sikkim is a major river originating from Zemeu glaciers and generally<br />

flows in north-south direction, at a steeper gradient. The river is joined by several<br />

tributaries major amongst them being Yumthang Chu, Zemu Chu, Talung Chu, Dik Chu,<br />

Rangpo Chu and Rangit Chu, apart from others join the river. The river valleys in this


29<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

region are U-shaped while, as the tributaries had developed deep gorges, which are bound<br />

by steep slopes. A thick vegetal cover occupies the hill slopes. These hill slopes are<br />

generally used for cultivation <strong>of</strong> cardamom.<br />

A brief <strong>of</strong> regional geological aspect <strong>of</strong> this area has been provided. The Eastern<br />

Himalaya covers the Sikkim-Darjeeling-Bhutan and Arunachal Pradesh sectors,<br />

extending from the Eastern Nepal to Western Burma. The higher Himalaya is a zone <strong>of</strong><br />

crystalline rocks dividing two distinct lith<strong>of</strong>acies association in the South and North. It is<br />

designed as the Axial belt. The Northern zone comprising the Tethyan Palaeo-Mesozoic<br />

sedimentary sequence forms the Trans-Axial belt. To the South <strong>of</strong> the Axial belt occurs<br />

the Inner belt, comprising thrust sheets <strong>of</strong> Proterozoic-Upper Palaeozoic formations,<br />

while the foothill belt is represented by para-autochthonous Siwaliks. This scheme is<br />

valid for the entire Eastern Himalaya, upto the Lohit District <strong>of</strong> Arunachal Pradesh,<br />

where the geological picture does not conform to this general scheme. The stratigraphic<br />

sequence provided by GSI report on <strong>Rangyong</strong> Hydroelectric Scheme has been brought<br />

out hereunder for the purpose <strong>of</strong> regional geological set-up <strong>of</strong> the area. According to this<br />

report the region from South to North is occupied by Gondwana, Daling, Chungthang and<br />

Central Crystalline Geneissic group <strong>of</strong> rocks.<br />

Group Lithology<br />

Gondwana Grits, pebble cum boulder beds and carbonaccous shale with<br />

occasional coal seams, pegmatite, quartzite(Tourmaline<br />

bearing)<br />

Daling • Interbedded quartzite and chlorite sericite<br />

phyllite/schist.<br />

• Lingza Granite.<br />

• Quartzite/Biotite schist.<br />

Chungthang • Interbedded quartzite and garnetiferous quart biotite<br />

schist.


Central Crystalline<br />

Geneissic Complex<br />

• Cale-silicate rock/marble.<br />

30<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

• Garnet-Kyanite-sillimanite-biotite-quartz-schist.<br />

Banded gneiss with augen gneiss and quart-biotite gneiss.<br />

Augen gneiss.<br />

Rock types belonging to Central Crystallines <strong>of</strong> Higher Himalaya occupy the area. The<br />

rock types are represented mainly by high-grade gneiss with interbands <strong>of</strong><br />

metasedimentaries represented by cale-silicate/quartzite and high-grade schist. As<br />

reported by GSI, the metasedimentaries occur as enclaves in the high-grade gneiss. All<br />

the rock types have discordant intrusions tourmaline bearing quartz veins and pegmatite.<br />

4.3 TOPOGRAPHIC AND GEOTECHNICAL ASPECTS OF COMPONENT<br />

STRUCTURES<br />

The region is moderately to thickly vegetated and falls within Sakkyong (upstream) and<br />

Tolung Reserve Forest (left bank area). The right bank area falls within Sakkyong reserve<br />

forest. Rukel Chhu, which originates from a glacier flows SE and takes an easterly swing<br />

and meets Umram Chhu near Lam. Umram Chhu also originates from a glacier and meets<br />

SW flowing nala Pasram Chhu before these confluence with Rukel/<strong>Rangyong</strong> Chhu near<br />

Lam <strong>Rangyong</strong> swings SE and then takes an easterly bend till it meets Ravingam Chhu.<br />

Further downstream <strong>Rangyong</strong> Chhu flows SE upto its confluence with Ringyong Chhu.<br />

In the right bank <strong>Rangyong</strong> Chhu is joined by few nalas major being Pokram Chhu. The<br />

area is bound by ridges, which trend N-S and NE-SW. The river flows in moderate to<br />

steep gradient <strong>Rangyong</strong> Chhu from the proposed diversion location upto Sakkyong<br />

flows across the strike <strong>of</strong> formations, however beyond, it flows almost parallel to the<br />

strike <strong>of</strong> formations. Entire area has a highly rugged terrain with elevation in vicinity<br />

varying from 2000M to 6000M.


31<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

The area is approachable by a fair weather road upto Lingza beyond which a foot track<br />

reaches Sakkyong. In general the valley slopes are occupied by slope wash material with<br />

few rock exposures. Rock formations are also exposed as steep ridges.<br />

4.3.1 Diversion Structure<br />

Near the proposed diversion structure <strong>Rangyong</strong> Chhu flows easterly till its confluence<br />

with Umram Chhu at Lam. The other diversion proposed on Umram Chhu shall be<br />

located below the confluence <strong>of</strong> Umram Chhu and Pasram Chhu. Water from Umram<br />

Chhu shall be diverted into the reservoir <strong>of</strong> <strong>Rangyong</strong> Chhu. In vicinity <strong>of</strong> the proposed<br />

structure on Umram Chhu the nala flows SE. The area is bound by steep ridges, which<br />

trend N-S and NE-SW. The hill ridge separating Umram Chhu and <strong>Rangyong</strong> Chhu<br />

trends NW-SE. Both the nalas flow in moderate to steep gradient. The proposed diversion<br />

structures are expected to be located within gneisses and augen gneisses. Quartzites and<br />

quartz biotite schists/biotite gneisses are also reported in the area. These rock types<br />

belong to Central Crystallines <strong>of</strong> higher Himalaya. The rocks are foliated and jointed.<br />

The gneisses <strong>of</strong> the area as studied at other locations namely Lingza, Ishana and Tolung<br />

are strong to very strong and are expected to provide good abutment conditions.<br />

Nevertheless, abutment conditions are required to be studied during the future course <strong>of</strong><br />

investigations. Also, depth <strong>of</strong> overburden at the proposed diversion locations shall be<br />

ascertained. Prima facie it appears that overburden depths may not be <strong>of</strong> higher order as<br />

has been found during the course <strong>of</strong> studies in this region.<br />

4.3.2 Water Conductor System<br />

A7.5km long water conductor system has been proposed in the right hill. This area is<br />

bound by steep ridges, which trend N-S and NE-SW. In the stretch between the proposed<br />

diversion structure and confluence <strong>of</strong> <strong>Rangyong</strong> Chhu with Ringyong Chhu the proposed<br />

water conductor system area is dissected by several drainages. A major drainage namely<br />

Pokram Chhu is located above the tunnel alignment, however the other drainages do not<br />

appear to have deeply incised the area. Accordingly, availability <strong>of</strong> rock cover above


32<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

water conductor system, here, shall be ascertained during future investigations. Prima<br />

facie sufficient superincumbent cover is available above the alignment. The water<br />

conductor system is expected to negotiate high grade gneisses with few intermittent<br />

stretches <strong>of</strong> quartz biotite schist. Few patches <strong>of</strong> Ligtse gneiss have been reported in the<br />

area. Fair to good tunneling media is expected however, few stretches especially contact<br />

zones and shear zones may provide poor rock media. Generally the area is thickly<br />

vegetated. A detailed assessment <strong>of</strong> the area shall however, be made during the further<br />

course <strong>of</strong> investigations.<br />

4.3.3. <strong>Power</strong> House<br />

The proposed <strong>Power</strong> House is located upstream <strong>of</strong> the confluence <strong>of</strong> <strong>Rangyong</strong> Chhu and<br />

Ringyong Chhu in the right bank <strong>of</strong> <strong>Rangyong</strong> Chhu. At present an underground <strong>Power</strong><br />

House has been contemplated on the basis <strong>of</strong> topographic conditions. The area is bound<br />

by steep ridges and occupied by a thick vegetal cover. The proposed <strong>Power</strong> House cavern<br />

is expected to lie within quartzite and quartz biotite schists and/or gneisses. The rock<br />

types are expected to <strong>of</strong>fer fair to good tunneling media. At the proposed <strong>Power</strong> House<br />

location the formation are exposed as steep rocky escarpments. Sufficient<br />

superincumbent cover is available above the proposed <strong>Power</strong> House cavern. The<br />

orientation <strong>of</strong> <strong>Power</strong> House shall be suitably aligned with respect to principal<br />

discontinuity. Towards the tailrace portion the area appears to be occupied by a veneer <strong>of</strong><br />

slope wash material as was observed during the investigation <strong>of</strong> Lingza scheme.<br />

4.4 SEISMICITY<br />

The site lies within Zone-IV <strong>of</strong> seismic zoning map <strong>of</strong> India IS 1893 (Part-I) 2002. IMD<br />

data <strong>of</strong> the region covering longitude 86-90 0 and 25-29 0 has been places at Annexure 4.2<br />

, which gives a list <strong>of</strong> earthquake events also that have occurred within the region. The<br />

probable intensity <strong>of</strong> earthquake within seismic zone–IV corresponds to intensity VIII on<br />

Modified Mercali Scale. Notable earthquakes that have occurred close to this area are<br />

Cachar 1869 (M 7.5), Great Assam Earthquake 1897(M 8.7), Dhubri 1930 (M 7.1) Bihar-


33<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Nepal Earthquake 1934 (M 8.3), Assam Earthquake 1950 (M 8.5) and Nepal-India border<br />

earthquake 1988 (M 6.4). The maximum intensity experienced in Sikkim region during<br />

Great Assam Earthquake 1897 was VIII(MMI) and during Bihar-Nepal border<br />

earthquake 1934 was VII(MMI).<br />

Two major tectonic features occurs in the area namely MBT (Main Boundary Thrust) and<br />

MCT (Main Central Thrust) besides other minor features. Many past occurrences <strong>of</strong><br />

earthquake have been associated with these major lineaments.<br />

4.5 GEO-PHYSICAL SURVEY<br />

The dam sites are located in remote area, where proper approaches are not available due<br />

which Geo-Physical survey was not feasible. However the powerhouse site is having rock<br />

exposures, hence the Geophysical survey is not required.<br />

4.6 CONSTRUCTION MATERIAL SURVEY<br />

Although, the riverbed is full <strong>of</strong> boulders, which may not be sufficient for requirement <strong>of</strong><br />

construction materials. However, the area is bounded by steep rocky ridges, therefore<br />

quarries for construction material can be developed.<br />

4.7 RECOMMENDATIONS<br />

• The foundation for structures are required to be investigated by subsurface<br />

explorations to assess overburden thickness and its amenability for construction <strong>of</strong><br />

various structures.<br />

• Detailed geological mapping <strong>of</strong> the project components need to be carried out.<br />

• Suitability <strong>of</strong> construction material may be assessed after conducting required<br />

tests.


Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

CHAPTER – V<br />

HYDROLOGY


5.1 GENERAL<br />

CHAPTER –V<br />

HYDROLOGY<br />

34<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

<strong>Rangyong</strong> H.E project is a run <strong>of</strong> the river scheme, in which two dams have been<br />

proposed to utilize the discharge <strong>of</strong> <strong>Rangyong</strong> Chu, a major right bank tributary <strong>of</strong> river<br />

Teesta. One dam is proposed on <strong>Rangyong</strong> Chu and another downstream <strong>of</strong> the<br />

confluence <strong>of</strong> Umram Chu and Passaram Chu, both tributaries <strong>of</strong> <strong>Rangyong</strong> Chu. The<br />

project envisages construction <strong>of</strong> two diversion structures, a 65 m high dam on <strong>Rangyong</strong><br />

Chu with a gross storage capacity <strong>of</strong> about 0.525 Mcum and area <strong>of</strong> submergence as 2.5<br />

Ha at EL 1845 m and another 65m high dam, d/s <strong>of</strong> confluence <strong>of</strong> Umram Chu and<br />

Passaram Chu with a gross storage capacity <strong>of</strong> about 3.05 Mcum and area <strong>of</strong><br />

submergence as 15.62 Ha at EL 1845 m.<br />

The hydrological investigations and analysis have been carried out for <strong>Rangyong</strong> Project<br />

with a view to:<br />

• Assess the availability <strong>of</strong> water for power generation by establishing a series <strong>of</strong><br />

average 10-daily discharges for the project site.<br />

• Establish the spillway design flood<br />

• Determine the capacity <strong>of</strong> the reservoir and the area <strong>of</strong> submergence at different<br />

levels including FRL and MDDL.<br />

• Reservoir sedimentation.<br />

5.2 RIVER SYSTEM AND BASIN CHARACTERISTICS<br />

<strong>Rangyong</strong> Chu is one <strong>of</strong> the major tributary <strong>of</strong> river Teesta which meets river Teesta at<br />

Singhik on its right bank. <strong>Rangyong</strong> Chu originates from the Talung glacier, which is a<br />

part <strong>of</strong> the Kanchanjunga range. The river is known by different names in different<br />

reaches. In the upper reach it is known as Rukel Chu, further downstream it is called<br />

<strong>Rangyong</strong> Chu and in the lower reaches it is known as Tolung Chu. <strong>Rangyong</strong> Chu is fed


35<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

by a number <strong>of</strong> tributaries having large drainage areas at their confluence. Umram Chu<br />

and Passaram Chu are also major tributaries <strong>of</strong> <strong>Rangyong</strong> Chu and intercept large<br />

drainage areas.<br />

The river Teesta is one <strong>of</strong> the main Himalayan Rivers, which originates in the glaciers <strong>of</strong><br />

Sikkim at an elevation <strong>of</strong> over 8500m above mean sea level. It is being snow fed by the<br />

glaciers Zemu, Changame Khanpu, Talung etc. It is an international river, which flows<br />

through the states <strong>of</strong> Sikkim and West Bengal in Indian Territory and then to Bangladesh.<br />

The river rises in mountainous terrain and is formed mainly by the union <strong>of</strong> two hill<br />

streams Lachen Chu and Lachung Chu at Chunthang in North Sikkim. The river upto this<br />

reach generally flows in a very steep gradient and the slope <strong>of</strong> the Teesta river upto the<br />

confluence <strong>of</strong> Lachen chu and Lachung chu is about 1 in 20. After the confluence <strong>of</strong><br />

Lachen chu and Lachung chu at Chungthang the river gradually increases in width and<br />

takes a wide loop flowing down to Singhik dropping in elevation from EL 1550 m to EL<br />

750 m. It is here after traversing about 20 Km that the river confluences with Tolung<br />

Chu.<br />

The area has a rugged terrain with the surrounding peaks reaching a maximum elevation<br />

<strong>of</strong> approximately 4000m. The minimum river bed elevation at both the proposed dam<br />

sites is about 1795m. Tolung Chu joins Teesta river almost perpendicularly. The terrain<br />

hosts a rich growth <strong>of</strong> vegetation. In general the river flows in southeasterly direction.<br />

Numerous valleys are seen in the area, which are occupied by cultivated terraces. Few<br />

high level terraces have been observed in this area especially in vicinity <strong>of</strong> Lingza and<br />

Kayem village.<br />

5.2.1 CASCADE DEVELOPMENT IN TEESTA BASIN<br />

The river Teesta has tremendous potential for development <strong>of</strong> hydro power, as the river<br />

descends from an elevation <strong>of</strong> about 3600m to about 300m over a distance <strong>of</strong> about 175<br />

Km. According to the preliminary reconnaissance survey by Central water and power


36<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Commission in 1974, the river could be harnessed under a cascade development for<br />

hydro power generation. The cascade development proposed at that stage consisted <strong>of</strong><br />

power generation in six stages on river Teesta. Out <strong>of</strong> these schemes, NHPC had<br />

submitted a DPR for Teesta H.E project, Stage-III in 1990. The diversion structure for<br />

Teesta-III was proposed to be constructed at Chungthang, which lies downstream <strong>of</strong> the<br />

confluence <strong>of</strong> Lachen Chu and Lachung Chu. Another project under Teesta Basin<br />

development, which is under execution by NHPC, is Teesta Stage-V having an installed<br />

capacity <strong>of</strong> 510 MW, where a diversion structure is being built at Dikchu, about 2 Km<br />

downstream <strong>of</strong> confluence <strong>of</strong> Dikchu with Teesta. About 70km downstream <strong>of</strong> Teesta-V,<br />

NHPC has been entrusted two projects namely, Teesta Low Dam H.E projects, Stage-III<br />

& IV, having an installed capacity <strong>of</strong> 132 MW and 160 MW respectively.<br />

The proposed <strong>Rangyong</strong> H.E project on <strong>Rangyong</strong> Chu, lies downstream <strong>of</strong> Chungthang<br />

on Teesta river, which was the proposed damsite <strong>of</strong> Teesta-III H.E project.<br />

5.2.2 CATCHMENT AREA<br />

The catchment area <strong>of</strong> the proposed scheme lies between Longitude 88 o 11′00” E to<br />

88 o 25′00” E and Latitude 27 o 30′00” N to 27 o 45’00” N. The catchment area upto the<br />

proposed dam site on <strong>Rangyong</strong> Chu is about 127 Sq.km and upto the proposed dam site<br />

d/s <strong>of</strong> Umram Chu and Passaram Chu is about 146 Sq.km. Both the catchments are<br />

snowfed as well as rainfed. The proposed diversion structure on <strong>Rangyong</strong> Chu lies at<br />

Longitude 88 o 21′48” E and latitude 27 o 35′00” N and that d/s <strong>of</strong> Umram Chu and<br />

Passaram Chu lies at Longitude 88 o 22′26” E and latitude 27 o 36′00” N. The catchment<br />

Plan showing both the proposed dam sites is shown in Plate-5.1.<br />

The catchment plan has been prepared from 1:50000, Survey <strong>of</strong> India toposheets. The<br />

entire catchment is covered in toposheets no. 78A/6, and 78A/2. The area above<br />

EL4600m for dam on <strong>Rangyong</strong> Chu is about 25 Sq.km and for dam d/s <strong>of</strong> Umram Chu<br />

and Passaram Chu is about 54 Sq.km and the same has been assumed to be the snowfed


37<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

area in the catchment. Thus the rainfed and snowfed area in the catchments <strong>of</strong> both dams<br />

are 102 Sq.km and 25 Sq.km respectively and 92 Sq.km and 54 Sq.km respectively.<br />

5.2.3 Temperature And Humidity<br />

The climate in the region is fairly humid and moist. The abrupt variation in altitude is<br />

chiefly responsible for abrupt changes in the climatic conditions and aided by the<br />

complex orography, the area experiences frequent rainfall <strong>of</strong> varying intensity and<br />

duration. The maximum and minimum temperature varies from 39 0 C in summer to 6 0 C<br />

in winter and the relative humidity varies from 80% to 100%. Temperature and relative<br />

humidity observations are being made in the basin at Dikchu site where Teesta-V H.E<br />

project is being constructed by NHPC and at TLDP-III and TLDP-IV sites, as a part <strong>of</strong><br />

cascade development on Teesta river. The monthly maximum, minimum temperatutre<br />

and relative humidity at Dikchu from Jan 1998 to Dec 2001 is enclosed as Annexure-5.1<br />

and annual maximum and minimum temperature from 1998 to 2001 is given in Table 5-<br />

1.<br />

Year<br />

TABLE 5-1<br />

Temperature And Humidity Data At Dikchu<br />

Maximum<br />

Temp o C<br />

Minimum Temp<br />

o C<br />

Max. Relative<br />

Humidity %<br />

Min.<br />

Relative<br />

Humidity<br />

1998 38.0 7.0 99.0 89.0<br />

1999 39.0 6.0 99.0 90.0<br />

2000 39.0 7.0 97.0 85.0<br />

2001 31.0 11.0 97.0 90.0<br />

Overall 39.0 6.0 99.0 85.0<br />

%


5.2.4 Precipitation Characterstics<br />

38<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

In the Teesta basin the southwest monsoon normally sets in the third week <strong>of</strong> May and<br />

withdraws in the second week <strong>of</strong> October. The major portion <strong>of</strong> the catchment being hilly<br />

and the river flowing in steep gradient, heavy rains in the upper and middle catchments<br />

has an immediate effect <strong>of</strong> rendering the plains to flash floods.<br />

Sh. B.Biswas and C.V.V Bhadram in their paper titled “A study <strong>of</strong> major rainstorms <strong>of</strong><br />

Teesta Basin” and published in Mausam (1984), have studied the rainfall distribution,<br />

major rainstorms and their associated synoptic situations over the catchment based on 22<br />

years data (1960-81). The entire Teesta catchment extending from its origin in north upto<br />

the Indo Bangladesh border has been considered. On the basis <strong>of</strong> the rainfall distribution,<br />

the Teesta catchment has been divided into three parts viz. upper, middle & lower. The<br />

average annual rainfall is 1328 mm, 2619 mm & 3289 mm for the upper, middle and<br />

lower parts respectively. The monthly breakup <strong>of</strong> the annual rainfall <strong>of</strong> the basin is given<br />

in Table 5-2 .<br />

Table 5-2<br />

Average Monthly Rainfall (mm) <strong>of</strong> Teesta Basin<br />

Month<br />

Catchment<br />

Upper Middle Lower<br />

Jan 21 23 6<br />

Feb 41 32 16<br />

Mar 73 66 30<br />

Apr 72 147 144<br />

May 142 274 315<br />

Jun 245 463 547<br />

Jul 236 621 866<br />

Aug 222 512 645<br />

Sep 171 338 495


Oct 77 112 191<br />

Nov 15 19 21<br />

Dec 13 12 13<br />

Annual 1328 2619 3289<br />

39<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

From the table it is clear that July is the wettest month followed by August and June. The<br />

upper, middle and lower catchments receive 71.6%, 78.1% and 83.4% <strong>of</strong> the annual<br />

rainfall respectively due to southwest monsoon. The catchment area upto the present<br />

proposed scheme comprises the upper and middle portions only.<br />

The authors have considered 53 rainstorms <strong>of</strong> duration ranging from one to three days in<br />

the study. The selection <strong>of</strong> storms is based on isohyetal analysis <strong>of</strong> daily rainfall values.<br />

Out <strong>of</strong> the 53 rain storms 40 were <strong>of</strong> 1 day, 11 were <strong>of</strong> 2 day and only 2 were <strong>of</strong> 3-day<br />

duration. It was concluded that 1-day duration storm are more frequent, a fact which is<br />

also supported by the narrow width <strong>of</strong> the catchment for which the effect <strong>of</strong> any system<br />

lasts for a shorter duration. No storm <strong>of</strong> longer duration than 3 day is reported. Majority<br />

<strong>of</strong> the storms have been reported in July & August. It has also been concluded that rain<br />

storms over this catchment occur in association with any <strong>of</strong> the following synoptic<br />

situations:<br />

(i) Break monsoon conditions i.e. shifting <strong>of</strong> the axis <strong>of</strong> trough close to the<br />

foothills <strong>of</strong> the Himalayas.<br />

(ii) Eastern end <strong>of</strong> monsoon trough lying north <strong>of</strong> Latitude 24 0 N.<br />

(iii) Movement <strong>of</strong> trough in west lies across the eastern Himalayas ; and<br />

(iv) Low pressure system lying over or to the west <strong>of</strong> the catchment.<br />

Many <strong>of</strong> the rainstorms studied by the authors were seen to occur due to either <strong>of</strong> the first<br />

two synoptic situations in July & August. A combination <strong>of</strong> first three synoptic situations<br />

is also a common feature over the area, giving rise to heavy precipitation.


5.2.4.1 Rain Gauge Network<br />

40<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

As per the paper <strong>of</strong> Sh. B.Biswas and C.V.V Bhadram, the network density <strong>of</strong> rain<br />

gauges in the basin works out to be one raingauge per 300 Sq.km <strong>of</strong> the basin area. The<br />

data used by them is <strong>of</strong> 42 raingauge stations working under Indian Meteorology<br />

Department (IMD) and Central Water Commision (CWC), 24 <strong>of</strong> which are equipped with<br />

self recording raingauges. The rainfall data availability status <strong>of</strong> the raingauge stations in<br />

the catchment upto Teesta-V H.E project, with NHPC, is shown in Table 5-3.<br />

Table 5-3<br />

Data Availability Status Of Raingauge Stations Upto Teesta-V<br />

S.No Name <strong>of</strong> station Period <strong>of</strong> data availability<br />

1. Lachung Jul 57 to Dec 58, 1960 to 1964,1970 to 1981,<br />

Feb 91 to Dec 97<br />

2. Chunthang Apr 57 to Dec 58, 1960 to 1964,1970 to Jul 85,<br />

1991 to 1997<br />

3. Lachen Jan 57 to Dec 58, Jan 60 to Apr64, 1971, Sep<br />

77 to Jan 78, Jun 92 to Dec 97<br />

4. Yumthang Jul 57 to Oct 57, 1958, 1960 to 1964, Jan 70 to<br />

Sep 82, Jan 83 to Apr 85<br />

5. Singhik Sep 75 to Sep 85, 1991 to 1993<br />

6. Thangu Jan 57 to Dec 58, 1960 to 1964, 1970 to 1974,<br />

7. Dikchu (near Teesta-<br />

V dam site)<br />

Jan to Apr 83<br />

8. Gayzing 1978 to 1988<br />

9. Yoksam 1978 to 1988<br />

10 Rangit dam site 1991 to 1997<br />

1992 to 1997, 2001 to Oct 03<br />

11. Pelling May 93 to Dec 96


41<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

At all the above raingauge sites, data for few months is missing in between. Raingauge<br />

sites have also been established near Teesta Low dam projects, Stage-III & IV and are<br />

operational since August 2000. Lot <strong>of</strong> efforts has been made to collect all available<br />

rainfall data in the basin but only rainfall data <strong>of</strong> 11 stations mentioned above is available<br />

at present. None <strong>of</strong> the above rainfall stations lie in the catchment <strong>of</strong> the proposed project<br />

so this data has not been used in the hydrological analysis.<br />

5.3 WATER AVAILABILITY STUDY<br />

5.3.1 Stream flow and River gauges<br />

Since Teesta River <strong>of</strong>fers ideal conditions for cascade development <strong>of</strong> hydroelectric<br />

schemes, the discharge passing through the river is measured at various sites by CWC.<br />

Recently NHPC has also established its various G&D sites on Teesta river since a<br />

number <strong>of</strong> projects have been entrusted to NHPC as a part <strong>of</strong> cascade development on the<br />

river. These include Teesta-V, and Teesta Low Dam projects, Stage-III & IV. However,<br />

no G&D data is available in the catchment <strong>of</strong> <strong>Rangyong</strong> H.E project. The various G&D<br />

sites and period <strong>of</strong> data availability in Teesta Basin is shown in Table 5-4.<br />

Table 5-4<br />

Data Availability Status Of G&D Sites In Teesta Basin<br />

S.No Name <strong>of</strong> site River Period <strong>of</strong> availabilty Catchment<br />

1. Chunthang (before<br />

confluence <strong>of</strong> Lachung<br />

& Lachung Chu)<br />

2. Chungthang (after<br />

3.<br />

confluence <strong>of</strong> Lachung<br />

& Lachung Chu)<br />

Lachen<br />

Chu<br />

Third Mile Tolung<br />

Area<br />

(Sq.km)<br />

Jan 75 to Aug 85 1919.25<br />

Teesta Jan 75 to Jun 86 2786.8<br />

Chu<br />

Jan 75 to Aug 85, Apr<br />

90 to Apr 98<br />

731.25


4. Lachung Lachung<br />

5. Chuba<br />

Chu<br />

Yumtha<br />

6. Zema<br />

ng Chu<br />

Zema<br />

Chu<br />

42<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

May 76 to Aug 85 634.50<br />

Jan 78 to Aug 85 355.5<br />

Jan 79 to Aug 85 900.0<br />

7. Sankalang Teesta Dec 89 to May 98<br />

8. Dikchu (near Teesta-V<br />

damsite)<br />

9. Sirwani (<strong>Power</strong> house<br />

site-TeestaV)<br />

10. Legship (near Rangit<br />

damsite)<br />

Teesta Jan 84 to Oct 96, Jan<br />

97 to Oct 03<br />

Teesta May 84 to Mar 97,<br />

2000<br />

Rangit Jan 77 to Dec 79, Apr<br />

87 to Dec 87, Jan 90<br />

to Dec 91<br />

11. Teesta Bazar Teesta 1972 to 1994<br />

4307<br />

12. Samco Ropeway Teesta Aug 2000 till date 7755<br />

13. Coronation Bridge Teesta 1972 to 1994, Aug<br />

2000 till date<br />

14. Domohoni Teesta 1972 to 2000<br />

.<br />

5.3.2 Present Study<br />

8065<br />

No daily G&D data was available on Umram Chu and Passaram Chu, on which one <strong>of</strong><br />

the dam sites for the present project is proposed. For the pre feasibility study, water<br />

availability for the proposed project has been computed based on the following<br />

methodologies:


43<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

(i) Based on observed discharges at Tolung Chu (Jan 75 to Aug 85, Apr 90 to Apr<br />

98)<br />

The two proposed diversion structures for <strong>Rangyong</strong> project are located on <strong>Rangyong</strong><br />

Chu and another d/s <strong>of</strong> confluence <strong>of</strong> Umram chu and Passaram Chu, both <strong>of</strong> which are<br />

tributaries <strong>of</strong> <strong>Rangyong</strong> Chu/Tolung Chu. Daily G&D data is available on Tolung Chu<br />

from Jan 75 to Aug 85 and Apr 90 to Apr 98. The G&D site lies downstream <strong>of</strong> the<br />

proposed project on Tolung Chu, having a catchment area <strong>of</strong> 731 Sq.km. Average 10-<br />

daily series has been prepared based on this observed data and reduced to the proposed<br />

dam sites using catchment area proportion, using a reduction factor <strong>of</strong> 0.175 and 0.158.<br />

(ii) Based on discharge series <strong>of</strong> Teesta-III H.E project (1976-1984)<br />

Average10-daily series recommended for Teesta-III H.E project by CWC at Chungthang<br />

has been converted at both the proposed sites using catchment area reduction (catchment<br />

reduction factor – 0.12 and 0.11). Thus a series for the period 1976 to 1984 has been<br />

obtained.<br />

(iii) Based on observed G&D data at Lachen (1976-1997)<br />

G&D data observed at Lachen has been converted at both the proposed sites using<br />

catchment area reduction (catchment reduction factor – 0.178 and 0.16). Thus a series for<br />

the period 1976 to 1997 has been obtained. Data at Lachen is missing for the years 1986-<br />

1988, i.e for 3 years. This missing data has been filled from the observed data at Dikchu<br />

G&D site (Teesta-V) using catchment area reduction.<br />

(iv) Based on discharge series <strong>of</strong> Teesta-V H.E project (1976-Feb 2003)<br />

The 10-daily series at Teesta-V H.E project for the period 1976- Feb 2003 has been<br />

converted at both the proposed dam sites using catchment area reduction (catchment<br />

reduction factor – 0.05 and 0.045). The series from 1976-1996 is the approved series by


44<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

CWC for Teesa-V and from 1997 to Feb 2003 is the observed data at Dikchu G&D site,<br />

where observations are being taken by NHPC.<br />

Average 10-daily discharge for all the above four series developed is worked out and<br />

compared at both the proposed dam sites. The plots showing this comparison <strong>of</strong> average<br />

10-daily discharge is enclosed at Figure-5.1 and Figure-5.2. From the plots it is obvious<br />

that the average 10-daily <strong>of</strong> the series obtained on the basis <strong>of</strong> G&D data observed on<br />

Tolung Chu is on a much higher side as compared to other three series. Rainfall-run<strong>of</strong>f<br />

relationship for consistency check could not be established for the observed data on<br />

Tolung Chu as no rainfall data in the catchment <strong>of</strong> the proposed project was available.<br />

Hence, for pre-feasibility study, the series so obtained on the basis <strong>of</strong> Tolung Chu data<br />

cannot be adopted as such, it comparatively being on a higher side. Average 10-daily<br />

obtained from other three approaches are almost comparable so need for further statistical<br />

checks is not felt necessary. For pre-feasibility stage, the average 10-daily obtained from<br />

G&D data at Lachen is recommended for both the dams proposed for <strong>Rangyong</strong> H.E<br />

project. Though the catchment area reduction factor is very low for all three series, this<br />

series has been adopted as Lachen G&D site has a smaller catchment area as compared to<br />

Chungthang and Teesta-V. After estabilishing G&D site near proposed dam axis and<br />

obtaining more rainfall data in the catchment, detailed water availability study need be<br />

done during feasibility/DPR stage. The final 10-daily series at both the proposed dam<br />

sites is enclosed as Annexure-5.2 and 5.3.<br />

5.4 RESERVOIR ELEVATION AREA CAPACITY CURVE<br />

The reservoir elevation-area-capacity curve for both the proposed dam sites <strong>of</strong> <strong>Rangyong</strong><br />

H.E project has been prepared from 1:50000 Survey <strong>of</strong> India toposheets. The contours are<br />

available at an interval <strong>of</strong> 40m the minimum contour being <strong>of</strong> 1840m. The area enclosed<br />

within the contours has been found using Autocad. Area has been found from elevation<br />

1840m to 1960m at an interval <strong>of</strong> 40m. The volume between any two elevations is<br />

calculated using the conical formula :


V = H/3 * (A1+A2+√A1A2)<br />

Where<br />

V = Volume between two contours<br />

H = Contour interval<br />

A1 = Area at level <strong>of</strong> first contour<br />

A2 = Area at level <strong>of</strong> second contour<br />

45<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

The incremental volumes thus computed are added up to obtain cumulative volume. The<br />

resultant area capacity curve for both the dams is enclosed as Figure-5.3 and Figure-5.4.<br />

The curve may be improved after receiving toposheets in scale <strong>of</strong> 1:25000. The gross<br />

storage capacity for dam on <strong>Rangyong</strong> Chu at FRL 1845m is 0.525 Mcum and<br />

submergence area is 2.5 Ha and for dam d/s <strong>of</strong> confluence <strong>of</strong> Umram Chu and Passaram<br />

Chu, the gross storage capacity at FRL 1845m is 3.05 Mcum and submergence area is<br />

15.62 Ha.<br />

5.5 DESIGN FLOOD<br />

Design Flood for a project can be estimated by following approaches:<br />

(i) Deterministic approach using Unit Hydrograph technique.<br />

(ii) Statistical approach using Flood frequency analysis<br />

(iii) Empirical methods<br />

• Unit Hydrograph technique<br />

Due to non-availability <strong>of</strong> G&D data and hourly gauges, design storm values in the<br />

proposed catchment, rating curves and observed flood hydrographs could not be<br />

developed for computing the Unit Hydrograph and Design Flood hydrograph.<br />

• Flood Frequency analysis<br />

Due to non-availability <strong>of</strong> long term, consistent G&D data near the proposed scheme,<br />

frequency analysis could not be done to estimate the design flood.


• Empirical Methods<br />

46<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

The following empirical relationships have been used to estimate the design flood peak:<br />

(i) Dicken’s formula<br />

Q = CA 3/4<br />

Where C = Dickens constant with value between 11-14 for North- Indian Hilly<br />

catchment. A value <strong>of</strong> 14 has been adopted in present study.<br />

A = Catchment area in sq.km<br />

Therefore, Q 1 = 14 x 127 3/4<br />

= 530 cumec<br />

Q 2 = 14 x 146 3/4<br />

= 588 cumec<br />

where subscript 1 and 2 stand for the two proposed dams, first on <strong>Rangyong</strong> Chu and<br />

second d/s <strong>of</strong> confluence <strong>of</strong> Umram Chu and Passaram Chu respectively.<br />

(ii) Ali Nawab Jung formula<br />

Q = C(0.386A) (0.925-1/14logA)<br />

Where C = 49 to 60 (55 used)<br />

Q1 = 55* (0.386*127) (0.925-1/14log(127))<br />

= 1259 cumec<br />

Q2 = 55* (0.386*146) (0.925-1/14log(146))<br />

= 1384 cumec<br />

where subscript 1 and 2 stand for the two proposed dams as explained above.<br />

(iii) Computation <strong>of</strong> Design Flood from Design Flood at Teetsa-III using Dicken’s<br />

formula<br />

The design flood recommended for Teesta H.E project, Stage-III was 4572 cumec. The<br />

total catchment area upto Stage-III dam site is 2786 Sq.km. <strong>Rangyong</strong> H.E project is<br />

located on <strong>Rangyong</strong> Chu, which is a major tributary <strong>of</strong> Teesta river and both the<br />

catchments can be assumed to be hydrologically and hydro-meteorologically similar.<br />

Therefore, it seems logical to transpose the design flood value <strong>of</strong> Teesta-III to proposed


47<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

dam sites on <strong>Rangyong</strong> Chu and d/s <strong>of</strong> confluence <strong>of</strong> Umram Chu and Passaram Chu.<br />

This transposition has been done by Dicken’s formula using a conversion factor <strong>of</strong> 0.099<br />

and 0.11 respectively.<br />

Q 1 = CA 1 n<br />

Q 2 = CA 2 n<br />

Where, A 1 = Catchment area <strong>of</strong> <strong>Rangyong</strong> project<br />

A 2 = Catchment area <strong>of</strong> Teesta-III project<br />

Q 1 = Design Flood for <strong>Rangyong</strong> project<br />

Q 2 = Design Flood for Teesta-III project<br />

C = Dicken’s constant<br />

n= 0.75<br />

Q <strong>Rangyong</strong> I = Q Teesta-III * (A <strong>Rangyong</strong> I/A Teesta-III) 0.75<br />

= 451 cumec<br />

Q <strong>Rangyong</strong> II = Q Teesta-III * (A <strong>Rangyong</strong> II/A Teesta-III) 0.75<br />

= 501 cumec<br />

(iv) Computation <strong>of</strong> Design Flood from Design Flood at Teetsa-V using Dicken’s<br />

formula<br />

The design flood for <strong>Rangyong</strong> project has also been estimated by transposing the design<br />

flood at Teesta-V H.E project using Dicken’s formula. The design flood recommended<br />

for Teesta-V H.E project, having a catchment area <strong>of</strong> 4307 Sq.km is 9500 cumec. The<br />

conversion factor for converting it at proposed dam sites for <strong>Rangyong</strong> project, having a<br />

catchment area <strong>of</strong> 127 Sq.km and 146 Sq.km, comes out to be 0.071 and 0.079<br />

respectively.<br />

Q <strong>Rangyong</strong> I = Q Teesta-V * (A <strong>Rangyong</strong> I/A Teesta-V) 0.75<br />

= 676 cumec<br />

Q <strong>Rangyong</strong> II = Q Teesta-V * (A <strong>Rangyong</strong> II/A Teesta-V) 0.75<br />

= 751 cumec<br />

A comparative study <strong>of</strong> flood peak computed from various methods at both the proposed<br />

dam sites is placed as Table 5-5.


Sl.No<br />

TABLE 5- 5<br />

Comparison Of Various Flood Values<br />

Method Used<br />

Design Flood-<br />

48<br />

Dam on<br />

<strong>Rangyong</strong> Chu<br />

(cumec)<br />

1. Dickens Formula 530 588<br />

2. Ali Nawaz Jung<br />

Formula<br />

3. Transposition <strong>of</strong> Teesta-<br />

III Flood peak on the<br />

basis <strong>of</strong> Dickens<br />

formula.<br />

4. Transposition <strong>of</strong> Teesta-<br />

V Flood peak on the<br />

basis <strong>of</strong> Dickens<br />

formula.<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Design Flood-Dam d/s <strong>of</strong><br />

confluence <strong>of</strong> Umram Chu<br />

& Passaram Chu (cumec)<br />

1259 1384<br />

451 501<br />

676 751<br />

For pre-feasibility stage study, a design flood <strong>of</strong> 675 cumec and 750 cumec has been<br />

recommended for the proposed dam sites, one on <strong>Rangyong</strong> Chu and second d/s <strong>of</strong><br />

confluence <strong>of</strong> Umram Chu and Passaram Chu respectively. It is worth to mention here<br />

that one <strong>of</strong> the methods <strong>of</strong> working out the design flood is on the basis <strong>of</strong> design flood at<br />

Teesta-III and Teesta-V, which has been computed using both unit hydrograph technique<br />

and flood frequency analysis<br />

On availability <strong>of</strong> more data/information, design flood will have to be estimated by<br />

deterministic approach using unit hydrograph technique and probabilistic approach using<br />

flood frequency analysis in feasibility stage.


5.6 SEDIMENTATION<br />

49<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

A rate <strong>of</strong> sedimentation <strong>of</strong> 0.1385 Ham/Sq.km/Year has been worked out for Teesta-V<br />

H.E project based on suspended sediment observations at Dikchu. In the absence <strong>of</strong><br />

sediment data at or near the proposed dam site, the same silt rate <strong>of</strong> Dikchu may be<br />

adopted for <strong>Rangyong</strong> H.E project too.<br />

The necessity <strong>of</strong> Detailed sedimentation study is not felt during PFR stage and the same<br />

need be done during feasibility/DPR stage with more observed data at the proposed site<br />

using a suitable method.


50<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>l HE Project, (3x 47 MW)<br />

TEESTA BASIN PROJECTS Annexure 5.1<br />

Maximum, Minimum monthly temperature and Relative humidity at Dikchu (Teesta-V dam site)<br />

Month 1998 1999 2000 2001<br />

TEMPERATURE RELATIVE<br />

RELATIVE<br />

RELATIVE TEMPERATURE<br />

HUMIDITY TEMPERATURE HUMIDITY TEMPERATURE HUMIDITY<br />

(%)<br />

(%)<br />

(%)<br />

Max O C Min O C<br />

Max O C Min O C<br />

Max O C Min O C<br />

Max O C Min O C<br />

RELATIVE<br />

HUMIDITY<br />

(%)<br />

Jan 25 7 92 23 6 90 22 9 90 20 11 96<br />

Feb 27 8 90 24 7 92 24 7 92 22 14 93<br />

Mar 30 10 92 28 9 91 N.A N.A N.A 24 15 91<br />

Apr 36 12 89 34 16 94 32 22 90 29 20 92<br />

May 38 14 91 35 18 93 36 17 87 29 19 91<br />

Jun 36 20 98 37 20 99 38 20 89 31 22 93<br />

Jul 35 20 99 39 21 96 39 22 90 31 20 90<br />

Aug 36 21 93 38 20 96 36 21 89 30 22 97<br />

Sep 35 20 93 34 16 97 35 20 89 28 22 95<br />

Oct 31 16 93 30 15 96 35 16 85 27 19 96<br />

Nov 29 14 92 28 13 91 31 14 90 25 16 95<br />

Dec 24 9 92 23 9 91 25 10 97 N.A N.A N.A


AVERAGE 10-DAILY DISCHARGE FOR DAM ON RANGYONG CHU<br />

51<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>l HE Project, (3x 47 MW)<br />

Annexure-5.2<br />

YEAR/MONTH JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC AVG<br />

I 3.99 3.71 4.34 5.88 6.96 11.06 20.02 16.92 17.97 6.41 5.08 3.06<br />

1976 II 3.82 3.64 4.65 6.44 5.51 21.58 19.07 18.45 10.36 5.06 4.21 2.62 8.54<br />

III 3.63 3.80 5.04 7.53 7.73 15.66 14.52 19.72 7.56 5.11 3.76 2.42<br />

I 2.16 3.61 2.00 3.83 4.18 11.89 17.53 20.18 13.84 11.52 6.02 3.75<br />

1977 II 2.05 3.52 2.85 3.60 5.16 21.10 20.63 16.98 11.32 7.26 5.49 3.96 8.50<br />

III 1.96 2.11 2.64 3.82 7.36 15.34 24.71 19.82 9.44 5.80 4.14 4.48<br />

I 3.08 2.85 2.60 3.70 6.40 17.57 20.46 25.05 13.18 12.41 6.61 4.68<br />

1978 II 2.76 2.79 2.78 4.74 13.11 18.43 21.93 21.17 17.17 9.68 4.93 3.96 10.04<br />

III 2.82 2.57 3.08 5.62 15.31 23.30 21.17 15.89 12.90 8.25 4.85 3.56<br />

I 3.29 2.71 3.02 5.75 10.77 12.51 22.30 22.08 18.19 19.40 9.90 7.23<br />

1979 II 3.03 2.71 3.17 5.72 13.73 14.97 21.33 17.43 15.87 13.24 8.06 5.95 10.79<br />

III 2.98 2.94 3.90 7.18 10.50 21.47 23.89 18.49 11.64 9.93 7.59 5.73<br />

I 5.40 4.95 5.68 8.84 12.32 17.23 27.15 29.43 25.71 12.76 8.63 6.72<br />

1980 II 5.20 5.18 5.83 11.34 10.54 22.93 27.80 32.31 20.15 10.97 7.86 6.11 13.74<br />

III 5.15 5.53 7.87 12.92 11.23 25.66 29.12 26.91 16.31 10.22 7.23 5.55<br />

I 5.35 4.60 5.66 7.08 12.97 14.96 31.03 24.41 23.96 15.01 10.35 6.28<br />

1981 II 5.01 4.73 5.99 8.97 14.01 17.89 26.61 25.75 20.54 13.89 8.26 5.65 13.19<br />

III 4.95 5.72 7.07 10.56 13.59 24.29 25.03 25.04 16.37 12.14 6.84 4.42<br />

I 4.06 4.42 4.65 7.80 10.82 20.85 22.29 19.79 16.91 11.36 7.20 5.37<br />

1982 II 4.52 4.59 5.21 7.78 12.15 22.96 24.97 18.73 24.46 9.54 6.28 4.95 11.95<br />

III 4.46 4.47 6.20 8.63 11.81 25.38 29.45 21.99 16.05 9.19 6.08 4.69<br />

I 4.65 2.64 3.92 6.67 10.99 22.04 34.18 23.61 23.51 21.44 11.78 7.44<br />

1983 II 4.14 2.62 5.03 5.46 13.17 21.39 29.08 25.04 26.44 21.14 10.82 6.97 14.66<br />

III 2.90 3.65 4.53 6.83 17.53 29.85 28.85 29.25 30.50 14.41 8.91 6.25


52<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>l HE Project, (3x 47 MW)<br />

YEAR/MONTH JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC AVG<br />

I 5.58 4.71 10.36 11.96 14.48 31.23 38.82 37.13 40.14 25.60 18.64 9.18<br />

1984 II 5.49 4.89 11.58 12.75 21.16 37.56 38.95 37.23 38.31 32.47 16.11 9.03 21.38<br />

III 4.88 4.69 11.38 12.76 30.05 33.73 41.17 38.98 30.39 25.01 14.32 9.07<br />

I 9.14 8.22 11.55 14.02 14.38 14.92 41.60 36.89 19.43 13.37 7.84 5.14<br />

1985 II 8.69 7.51 12.51 16.92 16.69 18.62 54.29 38.91 18.56 11.72 6.81 4.65 18.49<br />

III 7.52 9.09 11.65 19.98 23.25 52.77 45.65 47.64 15.55 9.66 6.03 4.28<br />

I 4.05 3.86 4.84 5.32 7.24 9.86 21.46 21.40 17.88 14.58 7.83 5.38<br />

1986 II 4.03 3.97 5.27 6.88 7.70 16.72 26.81 18.40 22.21 10.90 6.96 4.96 10.93<br />

III 3.82 4.54 5.41 7.72 8.11 24.77 24.11 20.36 18.08 8.51 6.01 3.66<br />

I 3.19 2.67 2.71 7.37 7.69 16.65 23.29 23.57 30.92 14.09 7.28 3.68<br />

1987 II 3.00 2.65 3.22 5.15 8.55 24.19 22.26 25.72 16.54 10.49 4.44 3.37 11.12<br />

III 2.82 2.90 4.04 6.80 10.04 20.30 24.89 17.19 22.69 8.97 3.90 3.08<br />

I 3.00 2.91 3.51 6.12 8.22 13.16 32.42 27.86 18.52 11.80 5.19 4.15<br />

1988 II 3.00 3.05 5.21 6.91 12.32 19.05 25.47 25.57 12.49 7.83 4.69 3.93 11.63<br />

III 2.97 3.39 5.35 8.04 16.32 20.86 28.07 38.80 13.97 6.30 4.37 3.72<br />

I 2.28 2.44 2.70 2.94 7.42 16.58 29.58 23.50 17.53 12.46 5.37 3.45<br />

1989 II 2.22 2.23 2.75 3.52 7.66 27.47 29.09 18.44 15.88 10.61 4.35 3.00 10.81<br />

III 2.20 2.38 2.83 4.23 18.68 29.05 27.08 18.09 15.78 8.63 3.96 2.62<br />

I 2.39 1.98 1.64 1.41 4.25 18.17 22.88 21.26 18.40 10.28 5.27 3.01<br />

1990 II 2.22 1.86 1.34 2.32 7.48 17.75 29.17 21.60 17.62 10.47 3.94 2.49 9.36<br />

III 2.01 1.79 1.36 2.88 8.61 20.76 24.96 19.17 12.27 8.61 3.29 2.14<br />

I 2.17 2.04 2.09 6.60 6.69 9.65 16.00 19.48 18.69 12.21 6.58 3.73<br />

1991 II 2.13 1.94 2.39 3.76 8.15 15.23 15.59 22.45 19.74 9.68 5.82 2.86 8.75<br />

III 2.11 1.96 2.52 3.98 9.01 14.01 16.99 18.55 15.29 7.94 4.44 2.52<br />

I 2.29 2.05 2.03 2.49 3.13 4.05 9.61 12.09 11.58 7.12 3.21 2.57<br />

1992 II 1.90 1.98 2.05 3.50 3.65 5.77 9.73 12.14 11.40 5.11 2.85 2.23 5.31<br />

III 1.94 1.90 2.11 3.20 3.67 11.19 11.05 13.20 9.43 4.35 2.60 2.06<br />

I 2.09 1.92 3.21 3.41 5.66 6.63 22.82 30.01 28.67 20.29 10.71 8.44<br />

1993 II 2.11 2.04 3.21 3.73 5.10 8.47 22.82 28.45 24.15 15.06 9.44 7.76 11.36<br />

III 1.98 1.97 3.36 4.46 5.17 10.90 26.76 27.25 22.83 12.90 8.65 6.37


53<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>l HE Project, (3x 47 MW)<br />

YEAR/MONTH JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC AVG<br />

I 6.00 5.57 5.26 5.83 7.50 13.73 18.05 17.92 15.97 10.81 7.24 4.81<br />

1994 II 5.59 5.33 4.75 7.30 7.73 18.18 19.14 17.51 15.99 9.61 5.97 4.40 10.14<br />

III 5.65 5.71 6.01 6.70 9.51 21.11 19.50 18.83 13.82 8.80 4.99 4.16<br />

I 3.95 3.91 3.56 4.55 11.99 20.77 28.56 20.12 16.27 10.35 5.12 4.40<br />

1995 II 3.99 3.89 3.37 5.63 18.51 22.22 23.96 20.30 14.57 10.08 5.85 3.92 11.08<br />

III 3.94 3.92 4.65 8.22 17.89 22.51 18.42 18.03 14.02 7.87 5.88 3.64<br />

I 3.14 3.41 3.38 3.83 10.10 11.49 19.31 17.69 16.60 12.11 9.03 5.14<br />

1996 II 3.12 3.04 3.91 3.72 8.85 9.73 20.79 16.50 15.84 11.10 8.39 4.65 9.56<br />

III 3.30 3.33 4.17 8.28 12.25 17.38 18.51 16.63 13.78 9.92 7.46 4.28<br />

I 4.84 4.67 4.71 5.17 6.17 8.10 17.78 14.73 12.63 9.11 4.32 3.26<br />

1997 II 4.60 4.65 4.94 5.14 7.10 11.55 15.39 17.97 14.30 5.97 3.99 3.18 7.87<br />

III 4.68 4.60 5.39 5.29 7.33 14.22 12.85 11.81 11.58 4.71 3.61 3.00<br />

I 3.99 3.71 4.34 5.88 8.80 14.92 24.21 22.75 19.43 13.37 7.84 5.14<br />

AVG II 3.82 3.64 4.65 6.44 10.50 18.62 24.75 22.49 18.56 11.72 6.81 4.65 11.34<br />

III 3.63 3.80 5.04 7.53 12.66 22.56 24.19 22.38 15.55 9.66 6.03 4.28<br />

Note : 1) All discharge data is in cumec.<br />

2) Total no. <strong>of</strong> years -22


AVERAGE 10-DAILY DISCHARGE FOR THE DAM D/S OF CONFLUENCE OF UMRAM CHU & PASSARAM CHU<br />

54<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>l HE Project, (3x 47 MW)<br />

Annexure-5.3<br />

YEAR/MONTH JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC AVG<br />

I 3.53 3.27 3.83 5.36 6.28 9.97 18.05 15.26 16.21 5.78 4.58 2.76<br />

1976 II 3.38 3.23 4.18 5.79 4.97 19.46 17.20 16.64 9.35 4.57 3.80 2.36 7.69<br />

III 3.22 3.40 4.53 6.79 6.97 14.12 13.09 17.79 6.82 4.61 3.39 2.18<br />

I 1.94 3.26 1.80 3.46 3.77 10.73 15.81 18.20 12.49 10.39 5.43 3.38<br />

1977 II 1.85 3.18 2.57 3.25 4.66 19.03 18.61 15.31 10.21 6.55 4.95 3.57 7.67<br />

III 1.77 1.90 2.38 3.45 6.64 13.84 22.29 17.88 8.51 5.23 3.74 4.04<br />

I 2.78 2.57 2.34 3.34 5.77 15.84 18.45 22.60 11.89 11.20 5.96 4.22<br />

1978 II 2.49 2.52 2.51 4.27 11.83 16.62 19.78 19.09 15.48 8.73 4.45 3.58 9.05<br />

III 2.54 2.31 2.78 5.06 13.81 21.02 19.09 14.34 11.64 7.44 4.38 3.21<br />

I 2.96 2.45 2.73 5.19 9.71 11.29 20.11 19.91 16.40 17.50 8.93 6.52<br />

1979 II 2.73 2.44 2.86 5.16 12.38 13.51 19.24 15.72 14.31 11.94 7.27 5.37 9.74<br />

III 2.69 2.66 3.51 6.47 9.47 19.36 21.55 16.68 10.50 8.96 6.84 5.17<br />

I 4.87 4.46 5.13 7.97 11.11 15.54 24.49 26.54 23.19 11.51 7.78 6.06<br />

1980 II 4.69 4.68 5.26 10.23 9.50 20.68 25.07 29.15 18.18 9.89 7.09 5.51 12.40<br />

III 4.65 4.98 7.10 11.65 10.13 23.14 26.27 24.27 14.71 9.21 6.52 5.00<br />

I 4.82 4.15 5.10 6.39 11.70 13.49 27.99 22.01 21.62 13.54 9.33 5.66<br />

1981 II 4.52 4.27 5.40 8.09 12.64 16.14 24.00 23.23 18.53 12.53 7.45 5.09 11.90<br />

III 4.46 5.16 6.38 9.53 12.26 21.91 22.57 22.58 14.76 10.95 6.17 3.99<br />

I 3.67 3.99 4.20 7.03 9.76 18.80 20.10 17.85 15.26 10.25 6.49 4.85<br />

1982 II 4.08 4.14 4.70 7.02 10.96 20.71 22.52 16.90 22.06 8.61 5.66 4.47 10.78<br />

III 4.02 4.03 5.60 7.79 10.65 22.89 26.56 19.83 14.48 8.29 5.48 4.23<br />

I 4.19 2.38 3.54 6.02 9.91 19.88 30.83 21.30 21.21 19.34 10.62 6.71<br />

1983 II 3.73 2.37 4.54 4.92 11.88 19.29 26.23 22.58 23.84 19.07 9.76 6.29 13.22<br />

III 2.62 3.29 4.09 6.16 15.81 26.92 26.02 26.39 27.51 13.00 8.04 5.64


55<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>l HE Project, (3x 47 MW)<br />

YEAR/MONTH JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC AVG<br />

I 5.03 4.24 9.35 10.79 13.06 28.17 35.01 33.49 36.21 23.09 16.81 8.28<br />

1984 II 4.95 4.41 10.45 11.50 19.08 33.87 35.13 33.58 34.55 29.28 14.53 8.15 19.29<br />

III 4.40 4.23 10.26 11.50 27.11 30.42 37.14 35.15 27.41 22.56 12.91 8.18<br />

I 8.25 7.41 10.42 12.65 12.97 13.24 37.52 33.27 17.91 12.07 6.93 4.54<br />

1985 II 7.83 6.77 11.28 15.26 15.05 16.97 48.97 35.10 16.55 10.31 5.96 4.12 16.65<br />

III 6.78 8.20 10.51 18.02 20.97 47.59 41.17 42.97 14.38 8.49 5.28 3.75<br />

I 3.66 3.48 4.37 4.80 6.53 8.89 19.35 19.30 16.13 13.15 7.06 4.86<br />

1986 II 3.64 3.58 4.75 6.21 6.94 15.08 24.18 16.59 20.03 9.83 6.28 4.47 9.86<br />

III 3.44 4.10 4.88 6.96 7.31 22.34 21.75 18.37 16.30 7.68 5.42 3.30<br />

I 2.88 2.41 2.45 6.64 6.94 15.02 21.01 21.26 27.89 12.71 6.57 3.32<br />

1987 II 2.71 2.39 2.90 4.64 7.72 21.82 20.08 23.20 14.92 9.46 4.01 3.04 10.03<br />

III 2.54 2.62 3.64 6.13 9.05 18.31 22.45 15.50 20.46 8.09 3.52 2.78<br />

I 2.71 2.63 3.17 5.52 7.41 11.87 29.24 25.13 16.71 10.64 4.68 3.74<br />

1988 II 2.71 2.75 4.70 6.24 11.11 17.18 22.97 23.06 11.27 7.06 4.23 3.55 10.49<br />

III 2.68 3.06 4.83 7.25 14.72 18.82 25.32 34.99 12.60 5.68 3.94 3.36<br />

I 2.05 2.20 2.44 2.65 6.69 14.96 26.68 21.20 15.81 11.24 4.84 3.12<br />

1989 II 2.00 2.01 2.48 3.18 6.91 24.78 26.24 16.63 14.32 9.57 3.93 2.70 9.75<br />

III 1.98 2.14 2.55 3.81 16.84 26.20 24.43 16.32 14.23 7.78 3.57 2.37<br />

I 2.16 1.78 1.48 1.27 3.83 16.39 20.64 19.18 16.59 9.27 4.76 2.72<br />

1990 II 2.00 1.67 1.21 2.09 6.75 16.01 26.31 19.48 15.89 9.45 3.55 2.24 8.44<br />

III 1.81 1.62 1.23 2.60 7.76 18.72 22.52 17.29 11.07 7.77 2.97 1.93<br />

I 1.96 1.84 1.89 5.96 6.03 8.70 14.43 17.57 16.85 11.01 5.94 3.37<br />

1991 II 1.92 1.75 2.15 3.40 7.35 13.74 14.06 20.25 17.81 8.73 5.25 2.58 7.89<br />

III 1.90 1.77 2.27 3.59 8.13 12.64 15.33 16.73 13.79 7.17 4.01 2.27<br />

I 2.07 1.85 1.84 2.24 2.83 3.65 8.67 10.91 10.44 6.43 2.90 2.32<br />

1992 II 1.72 1.79 1.85 3.15 3.29 5.21 8.77 10.95 10.28 4.61 2.57 2.01 4.79<br />

III 1.75 1.71 1.90 2.88 3.31 10.09 9.97 11.91 8.51 3.92 2.35 1.85<br />

I 1.88 1.73 2.90 3.08 5.11 5.98 20.58 27.07 25.86 18.30 9.66 7.61<br />

1993 II 1.90 1.84 2.89 3.36 4.60 7.64 20.58 25.66 21.78 13.58 8.51 7.00 10.24<br />

III 1.79 1.77 3.03 4.03 4.66 9.83 24.14 24.58 20.59 11.64 7.80 5.75


56<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>l HE Project, (3x 47 MW)<br />

YEAR/MONTH JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC AVG<br />

I 5.42 5.02 4.74 5.26 6.77 12.39 16.28 16.17 14.40 9.75 6.53 4.34<br />

1994 II 5.04 4.80 4.28 6.58 6.98 16.40 17.26 15.79 14.43 8.67 5.38 3.97 9.14<br />

III 5.09 5.15 5.42 6.04 8.58 19.04 17.59 16.98 12.46 7.94 4.50 3.75<br />

I 3.56 3.52 3.21 4.10 10.82 18.74 25.76 18.15 14.68 9.34 4.62 3.97<br />

1995 II 3.60 3.51 3.04 5.08 16.70 20.04 21.61 18.31 13.14 9.09 5.28 3.53 9.99<br />

III 3.55 3.53 4.19 7.42 16.14 20.30 16.61 16.27 12.64 7.10 5.30 3.28<br />

I 2.83 3.08 3.05 3.46 9.11 10.36 17.42 15.96 14.97 10.92 8.14 4.54<br />

1996 II 2.81 2.74 3.53 3.36 7.98 8.78 18.75 14.88 14.29 10.01 7.57 4.12 8.61<br />

III 2.97 3.00 3.76 7.47 11.05 15.67 16.69 15.00 12.43 8.95 6.73 3.75<br />

I 4.36 4.21 4.25 4.66 5.56 7.31 16.04 13.29 11.39 8.21 3.89 2.94<br />

1997 II 4.15 4.20 4.46 4.64 6.40 10.42 13.88 16.21 12.90 5.38 3.60 2.87 7.10<br />

III 4.22 4.15 4.86 4.77 6.61 12.83 11.59 10.65 10.44 4.25 3.26 2.71<br />

I 3.53 3.27 3.83 5.36 7.80 13.24 22.02 20.71 17.91 12.07 6.93 4.54<br />

AVG II 3.38 3.23 4.18 5.79 9.35 16.97 22.34 20.38 16.55 10.31 5.96 4.12 10.21<br />

III 3.22 3.40 4.53 6.79 11.27 20.27 22.01 20.57 14.38 8.49 5.28 3.75<br />

Note: 1. All discharge data in cumec.<br />

2. Total no. <strong>of</strong> years -22


Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

CHAPTER – VI<br />

CONCEPTUAL LAYOUT &<br />

PLANNING


6.1 INTRODUCTION<br />

CHPAPER-VI<br />

CONCEPTUAL PLANNING AND LAYOUT<br />

59<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

The <strong>Rangyong</strong> H.E. project is located in the North district <strong>of</strong> Sikkim state. It is a run <strong>of</strong><br />

the river scheme proposed to harness hydel potential <strong>of</strong> the <strong>Rangyong</strong> Chu, a Sub-<br />

tributary <strong>of</strong> river Teesta. The available gross head <strong>of</strong> 737 m is proposed to be utilised for<br />

generating 141 MW <strong>of</strong> <strong>Power</strong>. Two small reservoirs <strong>of</strong> adequate capacity have been<br />

provided as operating pools to meet diurnal peaking load demands.<br />

6.2 PROJECT COMPONENTS<br />

• Two 3.3 m diameter, 300 m long Diversion Tunnel with u/s & d/s c<strong>of</strong>fer dams.<br />

• Upper concrete Dam 65 m high above deepest level & 300m long with a central<br />

spillway.<br />

• Lower concrete Dam 65 m high high above deepest level & 250m long with a<br />

central spillway.<br />

• One 3.3m diameter horseshoe shaped concrete lined and 2 kms long link tunnel.<br />

• <strong>Power</strong> Intake Structure leading to 2 Nos. 3 m dia D-shaped intake tunnels.<br />

• Two Nos. Underground Desilting Chambers <strong>of</strong> size 125m (L) X 6 m (W) X 9 m<br />

(H).<br />

• One 3.3m diameter horseshoe shaped concrete lined and 7.5 kms long Head Race<br />

Tunnel with three adits.<br />

• One 10 m diameter & approx. 75 m high semi-Underground Surge Shaft.<br />

• One circular inclined Pressure Shaft <strong>of</strong> 2.5m diameters, 1000 m long with<br />

mainfold to feed three Pelton wheel turbines.<br />

• Underground <strong>Power</strong> House <strong>of</strong> size 100m x 22.5m x 40m consisting <strong>of</strong> 3 Pelton<br />

units <strong>of</strong> 47 MW each.<br />

• One no.3.3m diameter Horseshoe shaped tailrace tunnel <strong>of</strong> about 300 m length.


60<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

The conceptual planning and lay-out <strong>of</strong> project components have been worked out based<br />

on S.O.I topo sheets no.78A/6 <strong>of</strong> 1:50000 scale with contour intervals 40 m.<br />

6.2.1 Conceptual Layout<br />

The choice <strong>of</strong> location <strong>of</strong> the dams has been made keeping in view the topography,<br />

geology and maximum water availability at the prospective sites. Two reservoirs have<br />

been created in two basins and connected with a link tunnel to fulfill peaking<br />

requirement. The location <strong>of</strong> power house has been fixed keeping the tailrace outlet at<br />

El.1098.00m taking into consideration the FRL <strong>of</strong> upcoming Panan H E project.<br />

The location <strong>of</strong> major components <strong>of</strong> the project, riverbed levels at dam sites, TRT outlet<br />

site and generation capacity <strong>of</strong> the project as identified in the ranking study undertaken<br />

by CEA in 1990 have been considered during the preparation <strong>of</strong> this report.The upcoming<br />

hydroelectric projects on <strong>Rangyong</strong>/Tolung Chu have been taken into consideration in<br />

the conceptual planning <strong>of</strong> the project.<br />

The layout plan <strong>of</strong> the project and brief write up as envisaged by CEA have been<br />

enclosed as plate-1 and annexure 6.1 respectively. The cascade development schemes<br />

on the Teesta River as prepared by CEA is enclosed as plate-2 and <strong>of</strong> Tolung River basin<br />

as plate 3 and 4.<br />

Based on the hydrological and topographical study, reconnaissance survey <strong>of</strong> the site and<br />

input data <strong>of</strong> ranking study, a conceptual layout plan <strong>of</strong> the project was prepared and<br />

discussed in CEA for vetting during Nov’03.<br />

6.2.2 Dam and River Diversion Works<br />

Construction <strong>of</strong> two 65m high concrete Dams have been proposed keeping in view the<br />

topography, geology and availability <strong>of</strong> construction material.The availability <strong>of</strong>


61<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

construction material for the dam, c<strong>of</strong>ferdam and its suitability has been discussed<br />

elsewhere in the report.<br />

Upper Dam<br />

Upper Dam is proposed on d/s <strong>of</strong> confluence <strong>of</strong> Umram Chu and Passaram Chu. Width<br />

<strong>of</strong> the valley at this Dam site varies from 50 m at riverbed level to 300 m at EL 1850 m,<br />

which is suitable for a concrete dam. Average bed level at Dam site is EL 1795 m. The<br />

overflow section <strong>of</strong> this dam is 27 m long and Non –overflow section is 273 m consisting<br />

166 m on right abutment and 107 m on left abutment.<br />

Lower dam<br />

Lower Dam is proposed across the river rangyong Chu. Width <strong>of</strong> the valley at this Dam<br />

site varies from 50 m at riverbed level to 250 m at EL 1850 m., which is suitable for a<br />

concrete dam. FRL is proposed to be fixed at EL 1845 and MDDL at El.1825 m. keeping<br />

in view the pondage requirement and inflow <strong>of</strong> water in <strong>Rangyong</strong> Chu and Umram chu<br />

and Passaram chu during lean period The overflow section <strong>of</strong> lower dam is 27 m long and<br />

Non overflow section is 223 m consisting 105 m on right abutment and 118 m on left<br />

abutment.<br />

The top <strong>of</strong> both the dams has been proposed to be kept at EL 1850 m and foundation <strong>of</strong><br />

the dam at EL 1785 m after removal <strong>of</strong> approx. 10.0 m thick overburden.Both the<br />

spillways have three bays each <strong>of</strong> size 3 m X 6 m with 3.0 m wide piers for both the<br />

dams. The spillway is designed to pass a probable maximum flood <strong>of</strong> 750 cumecs and<br />

675 cumecs for upper and lower dams respectively with one gate inoperative. The crest<br />

<strong>of</strong> spillways has been kept at EL1805 m. The low-level orifice type spillway has been<br />

provided to flush out the sediment accumulated in the reservoir to maintain the live<br />

storage capacity <strong>of</strong> the reservoir. The top width <strong>of</strong> non-overflow has been fixed as 8 m.<br />

The d/s slope <strong>of</strong> the Non-overflow section has been proposed as 0.8H: 1V and u/s slope<br />

as 0.1H: 1V. The project area falls within Zone-IV <strong>of</strong> seismic zoning map.


62<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

The reservoir capacity formed by construction <strong>of</strong> both the dams has a gross storage pre-<br />

sedimentation capacity <strong>of</strong> 3.57 M.cum and live storage capacity <strong>of</strong> 1.97 M cum out <strong>of</strong><br />

which the upper reservoir has the gross storage pre-sedimentation capacity <strong>of</strong> 3.05<br />

M.cum and live storage capacity <strong>of</strong> 1.67 M while lower reservoir has the gross storage<br />

pre-sedimentation capacity <strong>of</strong> 0.525 M.cum and live storage capacity <strong>of</strong> 0.3 M<br />

respectively. After sedimentation, the reservoir is likely to have an adequate live storage<br />

capacity <strong>of</strong> more than what is adequate for running the power station at full capacity for<br />

3-4 hours in a day during the period <strong>of</strong> lean flows. Both the reservoirs have been<br />

connected by one 3.3m diameter horseshoe shaped concrete lined and 2 kms long link<br />

tunnel. The invert level <strong>of</strong> the link tunnel has been kept at EL1815 taking into<br />

consideration the water seal requirement to prevent the vortex formation and air<br />

entrainment. The intake structure shall be provided with the trash racks to prevent the<br />

entry <strong>of</strong> trash in the link tunnel.<br />

Two no. Concrete lined 3.3 m dia 300 m long diversion tunnels have been proposed for<br />

both the dams on the left banks <strong>of</strong> the river to divert a flood <strong>of</strong> approx. 100 cumecs The<br />

design diversion discharge has been decided based on the experience <strong>of</strong> various ongoing<br />

NHPC projects in Teesta valley. This data shall however needs to be firmed up during the<br />

preparation <strong>of</strong> detailed project report with the availability <strong>of</strong> more hydrological data &<br />

experience gained in the basin e.g.: during the construction <strong>of</strong> Teesta-V project. In order<br />

to divert the river during construction <strong>of</strong> the dams, an u/s c<strong>of</strong>ferdam <strong>of</strong> approx. height<br />

15m and d/s c<strong>of</strong>ferdam <strong>of</strong> 8 m height is proposed for both the dams.<br />

6.2.3 <strong>Power</strong> Intake & Desilting Chambers<br />

The proposed power intake is on the right bank <strong>of</strong> the <strong>Rangyong</strong> Chu and consists <strong>of</strong> two<br />

no. intake and two no. D-shaped intake tunnels <strong>of</strong> dia 3 m each. Two no intakes are<br />

proposed to keep the desilting chambers dimension within the manageable limits and to<br />

put either <strong>of</strong> the desilting chambers to inspection and maintenance while the other is in<br />

operation. The intake structures are designed to pass 26.76 cumecs, which includes


63<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

flushing discharge i.e. about 20% <strong>of</strong> turbine discharge (22.30 cumecs). The invert level <strong>of</strong><br />

the intake structure has been kept at 10m higher than the spillway crest to check the<br />

sediments entry in the water conductor system. The intake structure shall be provided<br />

with the trash racks to prevent the entry <strong>of</strong> trash into the water conductor system. The<br />

gross area <strong>of</strong> the trash racks shall be determined to give a velocity <strong>of</strong> not more than<br />

1.5m/s. A mechanical raking machine operated from El.1850m shall clean the racks.<br />

For the efficient, trouble free and continuous operation <strong>of</strong> turbines with least possible<br />

wearing and erosion damages due to silt, it is necessary to remove 90% <strong>of</strong> the sediments<br />

larger than 0.2 mm-particle size. Two nos. 6 m wide Dufour type Desilting chambers<br />

with height 9 m shall be provided to remove 90% <strong>of</strong> particles having size greater than or<br />

equal to 0.2 mm. Two separate intakes lead the water to two independent desilting<br />

chambers 125 m long spaced at 30 m c/c, through 25 m long upstream transition which<br />

will gradually reduce the velocity <strong>of</strong> water in the chamber to less than 0.25m /sec. The<br />

chambers have been provided with central gutter with holes to facilitate the flushing <strong>of</strong><br />

settled silt particles through the flushing tunnel. A silt flushing conduit at the bottom <strong>of</strong><br />

each chamber runs along the length and two flushing tunnels join to form a single silt<br />

flushing tunnel <strong>of</strong> size 1.5 m x 3.0 m d-shaped and 500 m length which will discharge the<br />

sediment back into the river d/s <strong>of</strong> the dam. Thus practically silt free water will be led<br />

into the headrace tunnel. The requirement <strong>of</strong> desilting chambers is being foreseen, on the<br />

lines <strong>of</strong> Teesta-V project, which is located d/s <strong>of</strong> this project.<br />

6.2.4 Head Race Tunnel, Surge Shaft, and Pressure Shaft<br />

The proposed 3.3 m diameter concrete lined horse- shoe shaped headrace tunnel <strong>of</strong> 7.5<br />

km length, and having a slope <strong>of</strong> 1 in 250 is designed to carry a design discharge <strong>of</strong> 26.76<br />

cumec. The diameter <strong>of</strong> the headrace tunnel has been fixed from the minimum working<br />

area requirements. The Invert level <strong>of</strong> headrace tunnel is fixed at EL. 1815 m near intake.<br />

The rock cover above headrace tunnel generally varies from +25 m to +600 m. The low<br />

cover reaches are confined to prominent nalla crossings. Three nos. construction Adits <strong>of</strong>


64<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

3.3m dia are proposed to facilitate excavation <strong>of</strong> headrace tunnel within the scheduled<br />

completion time. The length <strong>of</strong> tunnel between 250 m long adit-1 & 500 m long adit-2 is<br />

3 Km and the length <strong>of</strong> tunnel between 500 m long adit-2 & 600 m long adit-3 is 3 Km.<br />

The location <strong>of</strong> the adits and portals are indicative and the actual lengths may vary. The<br />

tunnel is proposed to be concrete lined with 250 mm thick plain M-20 concrete. The rock<br />

support treatment shall consist <strong>of</strong> grouted rock bolts/anchors and shotcrete with or<br />

without wire mesh. In rock class <strong>of</strong> IV & V steel ribs supports is envisaged.<br />

A vertical, restricted orifice type semi-underground surge shaft <strong>of</strong> 10 m finished dia and<br />

about 75 m height has been proposed with its top opening into a platform at elevation EL<br />

+1860 m. Surge shaft is proposed to be concrete lined with 0.75 m thick R.C.C. Its<br />

bottom is kept at EL 1785 m at the HRT and surge shaft junction. The transient studies<br />

shall be required to be done to work out the maximum and minimum levels for the worst<br />

operation conditions.<br />

One no. Steel lined inclined circular Pressure Shaft <strong>of</strong> 2.5m diameter and 1000 m length<br />

takes <strong>of</strong>f from the surge shaft, which further bifurcates at two points to feed water to<br />

three units <strong>of</strong> Pelton turbines each <strong>of</strong> 47 MW.<br />

6.2.5 <strong>Power</strong> House Complex & Tail Race Channel<br />

The underground <strong>Power</strong> House is located on the Right bank <strong>of</strong> rangyong Chu u/s <strong>of</strong><br />

Panan dam. It will have an installed capacity <strong>of</strong> 141 MW (3 generating units <strong>of</strong> 47 MW<br />

each). The support system shall comprise <strong>of</strong> rock bolts and shotcrete. The centerline <strong>of</strong><br />

the turbines is proposed at EL 1100.15 m. One number electrically operated overhead<br />

traveling crane (E.O.T) shall be provided for handling the electrical and mechanical<br />

equipment. A lift shall be provided near the service bay for approaching the lower parts<br />

<strong>of</strong> powerhouse. The overall dimensions <strong>of</strong> the <strong>Power</strong> House are 100m x 22.5m x 40m. A


65<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Control block area shall be located on one end <strong>of</strong> machine hall. The transformer cavern<br />

cum gate shaft is proposed 30m d/s <strong>of</strong> powerhouse cavern.<br />

A cable tunnel <strong>of</strong> size 2.0 m x 3.0 m will take <strong>of</strong>f from transformer area and shall carry<br />

cables to a surface switchyard. The Switchyard measuring approx. 155 m x 100 m shall<br />

be formed in cutting/filling.<br />

Water from the turbines is discharged through three lined tailrace tunnels, which merge<br />

into a single tailrace tunnel <strong>of</strong> diameter 3.3 m near Tolung Chu. This tunnel is 3.3 m<br />

diameter horseshoe and about 300m long with invert at EL.1097 at tailrace outlet. The<br />

tailrace outlet level has been kept at El. 1098 m in conformity with the FRL <strong>of</strong> proposed<br />

Panan H E Project to maintain an open channel flow in the TRT.<br />

6.3 Further Studies<br />

6.3.1 Topographical Studies<br />

1. Topographical contour Survey <strong>of</strong> the dam area and <strong>Power</strong> House area in 1:5000<br />

scales with 5m contour intervals.<br />

2. Survey in 1:1000 scale for locating the adits <strong>of</strong> the HRT.<br />

3. The riverbed survey including the cross sections at Dam axis and tailrace outlet shall<br />

be undertaken to firm up the power potential <strong>of</strong> the project.<br />

6.3.2 Geological and Geo-technical investigations<br />

1. Geological/ geotechnical investigations including surface mapping and subsurface<br />

explorations like exploratory drilling and seismic pr<strong>of</strong>iling at the dam and<br />

powerhouse area.<br />

2. Rock mechanic lab tests shall be required for finding out the properties <strong>of</strong> the rock<br />

material.<br />

3. Construction material survey shall be required to be undertaken involving drifts, pits,<br />

and topographical surveys <strong>of</strong> the borrow/quarry areas.


66<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

4. Site-specific studies for earthquake design parameters shall also be required to be<br />

undertaken.<br />

6.3.3 Design Studies<br />

1. Hydraulic design <strong>of</strong> various structures like spillway, power intake, desilting<br />

chambers, transient studies <strong>of</strong> surge shaft shall be required for firming up the<br />

dimensions.<br />

2. Stability analysis <strong>of</strong> non-overflow and overflow sections shall have to be done taking<br />

into account the approved seismic parameters.<br />

3. Hydraulic model studies for reservoir and Dam spillway shall be required for the<br />

confirmation <strong>of</strong> design parameters.<br />

4. Structural design <strong>of</strong> various components <strong>of</strong> the project.<br />

5. Sedimentation analysis for working out the post sedimentation storage capacity <strong>of</strong> the<br />

reservoir.<br />

6. Alternative studies for location, type and layout <strong>of</strong> main components based on<br />

detailed topographical and geological studies.<br />

6.4 HYDRO- MECHENICAL EQUIPMENT<br />

6.4.1 Diversion Tunnel Gates And Hoists-Upper Reservoir<br />

For the diversion <strong>of</strong> water during construction stage, one number horseshoe shaped<br />

diversion tunnel <strong>of</strong> 3.3m diameter has been proposed.After the construction <strong>of</strong> the dam,<br />

for the purpose <strong>of</strong> plugging the diversion tunnels, one number fixed wheel type gate will<br />

be provided at the inlet <strong>of</strong> the tunnel. The gate shall be operated by means <strong>of</strong> electrically<br />

operated rope drum hoist located on the hoist platform installed over the trestle above<br />

deck level. The gate is meant for one time closure, just before plugging <strong>of</strong> the tunnel.<br />

Height <strong>of</strong> the c<strong>of</strong>ferdam is 15m and gate is to be designed for operation against water<br />

height corresponding to 19.0m.


67<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

6.4.2 Spillway Radial Gates, Hoists, Spillway Bulkhead Gate And Gantry Crane-<br />

Upper Reservoir<br />

Three submerged type radial gates shall be provided to control the discharge through the<br />

gated portion <strong>of</strong> the spillway. Each gate shall be operated by means <strong>of</strong> suitable capacity<br />

hydraulic hoist from a power pack and two double acting cylinders having a provision <strong>of</strong><br />

25% pushing force (one on each end <strong>of</strong> the gate).<br />

One trolley mounted mobile gasoline engines operated power pack capable <strong>of</strong> operating<br />

two gates at 25% <strong>of</strong> the normal rated speed are envisaged for emergency operation <strong>of</strong><br />

spillway radial gates.<br />

One portable oil filter unit for filtration, dehydration and degasification <strong>of</strong> hydraulic oil is<br />

also being provided.<br />

One set <strong>of</strong> spillway bulkhead gate has been envisaged to cater to the maintenance<br />

requirement <strong>of</strong> three nos. spillway radial gates. The spillway bulkhead gate shall be<br />

lowered / raised under balanced head condition by means <strong>of</strong> a suitable capacity <strong>of</strong> Gantry<br />

Crane.<br />

6.4.2.1 Instrument And Remote Control<br />

Gates shall be provided with PLC based remote control system for Control and operation<br />

<strong>of</strong> gates and automatic control <strong>of</strong> the reservoir level.<br />

6.4.2.2 Diesel Generating Set<br />

One diesel generating set complete with all accessories, equipment, instrument and<br />

wiring for making the equipment complete and for warranting a trouble free safe<br />

operation including its design, manufacturing, testing and commissioning will be<br />

provided for emergency operation <strong>of</strong> gates and hoists.


68<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

6.4.3 Trash Rack And Trash Rack Cleaning Machine At Link Tunnel- Upper<br />

Reservoir<br />

Upstream face <strong>of</strong> the link tunnel shall be provided with the trash rack screen, which will<br />

be cleaned by means <strong>of</strong> a trash rack-cleaning machine.<br />

6.4.4 Link Tunnel Gate, Bulkhead Gate And Hoists-Upper Reservoir<br />

One number fixed wheel type gate shall be provided just downstream <strong>of</strong> the bell mouth <strong>of</strong><br />

the link tunnel. The link tunnel gate is to be designed for self-lowering against upstream<br />

water level corresponding to FRL. The gate shall be operated by means <strong>of</strong> electrically<br />

operated rope drum hoist <strong>of</strong> suitable capacity.<br />

For maintenance and inspection <strong>of</strong> link tunnel gate and embedded parts, one number<br />

vertical slide type bulkhead gate has been proposed on the upstream <strong>of</strong> the link tunnel<br />

gate. The bulkhead gate shall be operated by means <strong>of</strong> a electrically operated rope drum<br />

hoist under balance head condition.<br />

6.4.5 Diversion Tunnel Gate And Hoist- Lower Reservoir<br />

For the diversion <strong>of</strong> water during construction stage, one number horseshoe shaped<br />

diversion tunnel <strong>of</strong> 3.3m diameter has been proposed. After the construction <strong>of</strong> the dam,<br />

for the purpose <strong>of</strong> plugging the diversion tunnels, one number fixed wheel type gate will<br />

be provided at the inlet <strong>of</strong> the tunnel. The gate shall be operated by means <strong>of</strong> electrically<br />

operated rope drum hoist located on the hoist platform installed over the trestle above<br />

deck level. The gate is meant for one time closure, just before plugging <strong>of</strong> the tunnel.<br />

Height <strong>of</strong> the c<strong>of</strong>ferdam is 15m and gate is to be designed for operation against water<br />

height corresponding to 19.0m.


69<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

6.4.6 Spillway Radial Gates, Hoists, Spillway Bulkhead Gate And Gantry Crane-<br />

Lower Reservoir<br />

Three submerged type radial gates shall be provided to control the discharge through the<br />

gated portion <strong>of</strong> the spillway. Each gate shall be operated by means <strong>of</strong> suitable capacity<br />

hydraulic hoist from a power pack and two double acting cylinders having a provision <strong>of</strong><br />

25% pushing force (one on each end <strong>of</strong> the gate).<br />

One trolley mounted mobile gasoline engines operated power pack capable <strong>of</strong> operating<br />

two gates at 25% <strong>of</strong> the normal rated speed are envisaged for emergency operation <strong>of</strong><br />

spillway radial gates.<br />

One set <strong>of</strong> spillway bulkhead gate has been envisaged to cater to the maintenance<br />

requirement <strong>of</strong> three nos. spillway radial gates. The spillway bulkhead gate shall be<br />

lowered / raised under balanced head condition by means <strong>of</strong> a suitable capacity <strong>of</strong> Gantry<br />

Crane.<br />

6.4.6.1 Instruments And Remote Control<br />

Gates shall be provided with PLC based remote control system for Control and operation<br />

<strong>of</strong> gates and automatic control <strong>of</strong> the reservoir level.<br />

Remote control system <strong>of</strong> both the reservoirs shall be interconnected together with the<br />

help <strong>of</strong> optical fibre cable, which will be routed through the link tunnel.<br />

6.4.6.2 Diesel Generating Set<br />

One diesel generating set complete with all accessories, equipment, instrument and<br />

wiring for making the equipment complete and for warranting a trouble free safe<br />

operation including its design, manufacturing, testing and commissioning will be<br />

provided for emergency operation <strong>of</strong> gates and hoists.


6.4.7 Link Tunnel Bulkhead Gate And Hoist-Lower Reservoir<br />

70<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

For maintenance and inspection <strong>of</strong> link tunnel, one number vertical slide gate has been<br />

proposed. The slide gate shall be operated by means <strong>of</strong> an electrically operated rope drum<br />

hoist under balance head condition.<br />

6.4.8 Intake Trash Rack And Trash Rack Cleaning Machine-Lower Reservoir<br />

Upstream face <strong>of</strong> the link tunnel shall be provided with the trash rack screen, which will<br />

be cleaned by means <strong>of</strong> a trash rack-cleaning machine.<br />

6.4.9 Intake Gates, Bulkhead Gates And Hoists<br />

Two number fixed wheel type gates shall be provided just downstream <strong>of</strong> the bell mouth<br />

<strong>of</strong> the intake. The intake gates are to be designed for self-lowering against upstream<br />

water level corresponding to FRL. The gates shall be operated by means <strong>of</strong> electrically<br />

operated rope drum hoist <strong>of</strong> suitable capacity.<br />

For maintenance and inspection <strong>of</strong> intake gates and embedded parts, two numbers<br />

vertical slide gates have been proposed on the upstream <strong>of</strong> the intake gates. The slide<br />

gates shall be operated by means <strong>of</strong> a electrically operated rope drum hoist under balance<br />

head condition.<br />

6.4.10 Desilting Chamber Gate<br />

One set <strong>of</strong> slide type gate has been envisaged to cater to the maintenance requirement <strong>of</strong><br />

two nos. desilting chambers. The gate shall be lowered / raised under balanced head<br />

condition by means <strong>of</strong> a suitable Capacity EOT Crane.<br />

6.4.11 Silt Flushing Tunnel Gates And Hoists<br />

In two silt-flushing tunnels, each tunnel is provided with a set <strong>of</strong> two slide (emergency &<br />

service) gates for regulating the discharge through flushing tunnels. Both the (emergency<br />

& service) gates shall be operated by means <strong>of</strong> hydraulic hoists. The gate grooves are


71<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

provided with bonnet structures embedded in the concrete & a watertight bonnet cover at<br />

the top <strong>of</strong> the groove.<br />

6.4.12 Surge Shaft Gate And Hoist<br />

The intake <strong>of</strong> pressure shaft is provided with a slide type gate. The gate shall be operated<br />

under balanced head condition by means <strong>of</strong> an electrically operated rope drum hoist.<br />

6.4.13 Tailrace Gate And Hoist<br />

To isolate powerhouse from the river during flood, one number <strong>of</strong> fixed wheel type gate<br />

has been envisaged. The fixed wheel gate shall be operated under unbalanced head<br />

condition by a suitable capacity electrically operated monorail hoist placed in the<br />

transformer cavern.<br />

6.4.14 Adit Inspection Gates<br />

Three nos. adits shall be provided with manually operated hinged type gates in the<br />

concrete plug at the HRT construction to give access to the head race tunnel in the event<br />

<strong>of</strong> any inspection, repair and maintenance.<br />

6.4.15 Pressure Shaft Steel Liner<br />

One no. Pressure Shaft <strong>of</strong> dia. 2500 mm fully steel lined will take <strong>of</strong>f from d/s <strong>of</strong> steel<br />

transition <strong>of</strong> Surge Shaft to feed the turbine placed in the power house. It comprises<br />

horizontal & inclined ferrules, 2 nos. vertical bends, 2 nos. plan bends, 2 nos.<br />

bifurcations and branch pipes for feeding three turbines.<br />

The material <strong>of</strong> Pressure Shaft liner shall conform to ASTM A537 Class 1. However<br />

bifurcation material shall conform to ASTM A517 Gr. F.


Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

CHAPTER – VII<br />

POWER POTENTIAL STUDIES


7.1 GENERAL<br />

CHAPTER-VII<br />

POWER POTENTIAL STUDIES<br />

68<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

The <strong>Power</strong> potential studies <strong>of</strong> <strong>Rangyong</strong> HE Project has been made for 90% dependable<br />

year based on 21 hydrological years, from 1976-77 (June) to 1996-97 (May) as given in<br />

table 7.1. The salient features <strong>of</strong> the project are as follows:<br />

FRL (EL) =1845 m<br />

MDDL (EL) =1825 m<br />

TWL = EL 1098 m<br />

Centre line <strong>of</strong> M/C = EL 1100.15 m<br />

Rated net head = 723.18 m<br />

Type <strong>of</strong> turbine = Vertical Pelton<br />

Rated Discharge <strong>of</strong> Plant =22.30 cumecs<br />

Proposed Plant Capacity =141 MW (3 x 47MW)<br />

Generation voltage = 11KV<br />

Design Energy = 639.52 MU in the 90% dependable year with 95%<br />

machine availability<br />

Minimum Peaking (Hrs) = 4.01hrs (approx.)<br />

7.2 Available Flow<br />

The discharge data for the 90% dependable hydrological year is given in Table 7.3. For<br />

carrying out the power potential and optimisation studies, the following statistics have<br />

been computed.<br />

Year:<br />

Each 10-daily period <strong>of</strong> the year represents the average <strong>of</strong> the flow recorded for the<br />

corresponding period <strong>of</strong> each year.


90% Dependable Year:<br />

69<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

This is the lower decile <strong>of</strong> the series <strong>of</strong> the corresponding 10-daily period <strong>of</strong> the record<br />

i.e. (N+1) x 0.9th year where N is the years for which continuous hydrological data are<br />

available. The 90% dependable year comes out to be 1976-77 whose calculations are<br />

shown in table 7.2.<br />

7.3 DEFINITION OF TERMS<br />

Annual Energy<br />

This is the yearly energy provided during the 90% dependable hydrological year with<br />

95% machine availability.<br />

Firm <strong>Power</strong><br />

This is the power capacity, which can be guaranteed continuously during the lean period<br />

in 90% dependable year. During lean inflow period the firm power comes out to be 23.58<br />

MW.<br />

7.4 FULL RESERVOIR LEVEL (FRL) AND MINIMUM DRAW DOWN<br />

LEVEL (MDDL)<br />

FRL and MDDL have been fixed at EL 1845 m & EL 1825 m respectively based on civil<br />

consideration. This project is envisaged as a run <strong>of</strong> the river scheme with small pondage.<br />

7.5 OPERATING HEAD AND HEAD LOSSES<br />

The net operating head for turbines has been derived from the following formula where<br />

head losses are taken as 15 m.<br />

Net operating head =MDDL+2/3 (FRL-MDDL)-TCL-Head losses<br />

The net operating head comes out to 723.18 m.<br />

7.6 INSTALLED CAPACITY<br />

The studies for power output and annual energy generation for the 90% dependable year<br />

has been given in Table 7.4 (A). Considering water availability the total installed capacity<br />

has been selected as 141 MW.


7.7 SIZE OF GENERATING UNITS<br />

70<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

The power load demand in India is increasing at a very rapid rate and both hydroelectric<br />

and thermal (including nuclear) <strong>Power</strong> potential in the country are being developed not<br />

only to meet the overall requirements, but stimulatingly also to provide a proper mix <strong>of</strong><br />

hydro and thermal power for optimum operation <strong>of</strong> the system. Keeping this in view<br />

current practice is to opt for largest size hydro units permissible within the parameters <strong>of</strong><br />

economy, operating efficiency, maintenance, optimum utilization <strong>of</strong> available water,<br />

transport limitation etc. It is therefore proposed to install 3 units each <strong>of</strong> 47 MW capacity<br />

with Pelton turbine as prime mover.<br />

7.8 ENERGY GENERATION<br />

The energy generation in the 90% dependable year (1976-77) indicating lean inflow<br />

period and high inflow period is shown in Table 7.4 (B). It may be seen from Table 7.4<br />

(A) that the total unrestricted energy generation is 826.686 MU. Annual energy<br />

generation at 141 MW comes out to be 639.52 MU. Annual load factor for lean and<br />

monsoon periods <strong>of</strong> all years have been shown in Table 7.4 (C). Incremental benefits<br />

have been shown in Table 7.6 which comes out to be 2.63 for this year. Also annual<br />

energy generation unrestricted has been indicated in table 7.7(A) to 7.7(U) for 21<br />

hydrological years. Energy available at bus bar shall be 631.87 MU after allowing<br />

auxiliary consumption <strong>of</strong> 0.7% and transformer losses <strong>of</strong> 0.5% respectively.


Table-7.1<br />

DISCHARGE DATA<br />

75<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project, (3 x 47 MW)<br />

1976- 1977- 1978- 1979- 1980- 1981- 1982- 1983- 1984- 1985- 1986- 1987- 1988- 1989- 1990- 1991- 1992- 1993- 1994- 1995- 1996-<br />

PERIOD 1977 1978 1979 1980 1981 1982 1983 1984 1985 1986 1987 1988 1989 1990 1991 1992 1993 1994 1995 1996 1997<br />

I 21.03 22.62 33.41 23.80 32.76 28.45 39.65 41.91 59.40 28.15 18.75 31.67 25.04 31.54 34.57 18.35 7.70 12.61 26.12 39.51 21.85<br />

JUN II 41.04 40.12 35.06 28.48 43.60 34.03 43.67 40.68 71.43 35.59 31.80 46.00 36.23 52.24 33.77 28.98 10.98 16.11 34.58 42.26 18.51<br />

III 29.78 29.18 44.32 40.83 48.80 46.20 48.27 56.77 64.15 100.36 47.12 38.61 39.68 55.25 39.48 26.65 21.28 20.73 40.14 42.80 33.05<br />

I 38.07 33.35 38.91 42.41 51.64 59.02 42.39 65.01 73.83 79.13 40.81 44.29 61.67 56.26 43.52 30.43 18.28 43.40 34.33 54.32 36.73<br />

JUL II 36.28 39.24 41.71 40.56 52.87 50.61 47.49 55.31 74.07 103.26 50.99 42.34 48.44 55.34 55.48 29.65 18.50 43.40 36.40 45.57 39.54<br />

III 27.61 46.99 40.26 45.44 55.39 47.60 56.02 54.87 78.31 86.82 45.86 47.35 53.39 51.51 47.48 32.32 21.01 50.90 37.09 35.03 35.20<br />

I 32.19 38.37 47.65 41.99 55.97 46.42 37.64 44.91 70.62 70.16 40.70 44.83 52.99 44.70 40.44 37.06 23.00 57.09 34.09 38.27 33.65<br />

AUG II 35.09 32.29 40.26 33.16 61.46 48.98 35.63 47.62 70.81 74.01 34.99 48.91 48.63 35.07 41.09 42.69 23.09 54.12 33.30 38.61 31.38<br />

III 37.51 37.70 30.23 35.17 51.19 47.62 41.82 55.64 74.13 90.61 38.73 32.69 73.79 34.40 36.46 35.28 25.11 51.83 35.81 34.30 31.63<br />

I 34.17 26.33 25.07 34.59 48.90 45.58 32.17 44.72 76.35 37.35 34.01 58.81 35.23 33.35 34.99 35.54 22.02 54.53 30.37 30.95 31.57<br />

SEP II 19.71 21.53 32.65 30.18 38.33 39.06 46.52 50.28 72.86 35.11 42.24 31.46 23.76 30.21 33.51 37.55 21.67 45.93 30.42 27.71 30.13<br />

III 14.39 17.95 24.54 22.14 31.03 31.13 30.53 58.00 57.80 29.93 34.38 43.15 26.57 30.01 23.34 29.08 17.94 43.43 26.28 26.66 26.20<br />

I 12.19 21.91 23.61 36.90 24.27 28.55 21.61 40.78 48.68 25.44 27.73 26.80 22.43 23.70 19.55 23.22 13.55 38.59 20.56 19.69 23.04<br />

OCT II 9.63 13.82 18.41 25.18 20.86 26.42 18.15 40.20 61.75 22.03 20.73 19.96 14.89 20.17 19.92 18.41 9.72 28.63 18.28 19.17 21.11<br />

III 9.72 11.04 15.69 18.89 19.43 23.09 17.48 27.40 47.57 18.14 16.19 17.07 11.98 16.41 16.38 15.11 8.27 24.54 16.73 14.98 18.87<br />

I 9.67 11.44 12.57 18.83 16.42 19.68 13.69 22.40 35.45 14.77 14.89 13.85 9.87 10.21 10.03 12.52 6.11 20.36 13.77 9.74 17.17<br />

NOV II 8.00 10.44 9.38 15.33 14.95 15.70 11.94 20.58 30.64 12.77 13.24 8.45 8.91 8.28 7.50 11.07 5.43 17.95 11.35 11.12 15.96<br />

III 7.16 7.88 9.23 14.43 13.76 13.01 11.56 16.95 27.23 11.31 11.44 7.42 8.31 7.53 6.26 8.45 4.95 16.45 9.49 11.19 14.20<br />

I 5.82 7.12 8.90 13.75 12.78 11.94 10.22 14.14 17.46 9.68 10.24 7.00 7.88 6.57 5.73 7.10 4.89 16.06 9.15 8.37 9.68<br />

DEC II 4.98 7.53 7.54 11.32 11.62 10.74 9.42 13.26 17.18 8.77 9.43 6.41 7.48 5.70 4.73 5.45 4.23 14.75 8.37 7.45 8.77<br />

III 4.60 8.52 6.77 10.90 10.55 8.42 8.92 11.88 17.24 8.02 6.95 5.86 7.08 4.99 4.08 4.79 3.91 12.12 7.92 6.92 8.02<br />

I 4.10 5.86 6.25 10.27 10.17 7.73 8.84 10.61 17.39 7.71 6.07 5.71 4.33 4.55 4.13 4.36 3.97 11.42 7.50 5.96 9.20<br />

JAN II 3.90 5.25 5.77 9.89 9.53 8.60 7.87 10.44 16.52 7.67 5.71 5.71 4.22 4.22 4.05 3.62 4.01 10.63 7.59 5.93 8.75<br />

III 3.73 5.36 5.67 9.80 9.41 8.48 5.52 9.29 14.30 7.26 5.36 5.65 4.18 3.82 4.01 3.70 3.77 10.74 7.49 6.27 8.90<br />

I 6.87 5.42 5.16 9.41 8.75 8.41 5.02 8.95 15.63 7.34 5.08 5.54 4.65 3.76 3.88 3.91 3.65 10.59 7.43 6.49 8.88<br />

FEB II 6.70 5.31 5.15 9.86 9.00 8.74 4.99 9.29 14.29 7.55 5.03 5.80 4.25 3.53 3.69 3.77 3.87 10.13 7.41 5.78 8.85<br />

III 4.01 4.88 5.60 10.51 10.88 8.49 6.94 8.93 17.29 8.64 5.52 6.44 4.52 3.41 3.73 3.61 3.74 10.86 7.45 6.33 8.75<br />

I 3.80 4.94 5.75 10.81 10.76 8.85 7.46 19.71 21.97 9.21 5.16 6.68 5.14 3.11 3.98 3.87 6.11 10.01 6.77 6.42 8.95<br />

MAR II 5.42 5.28 6.02 11.09 11.39 9.91 9.56 22.03 23.79 10.03 6.12 9.90 5.24 2.54 4.54 3.90 6.10 9.03 6.42 7.44 9.40<br />

III 5.03 5.86 7.41 14.97 13.45 11.80 8.63 21.64 22.16 10.30 7.68 10.18 5.38 2.59 4.79 4.01 6.39 11.42 8.84 7.93 10.25<br />

I 7.29 7.04 10.94 16.81 13.47 14.83 12.69 22.75 26.67 10.12 14.01 11.64 5.60 2.68 12.56 4.73 6.49 11.09 8.65 7.29 9.83<br />

APR II 6.84 9.01 10.88 21.57 17.05 14.80 10.38 24.25 32.19 13.09 9.79 13.15 6.70 4.42 7.16 6.65 7.09 13.88 10.71 7.08 9.78<br />

III 7.27 10.68 13.65 24.57 20.09 16.42 12.99 24.26 38.01 14.68 12.94 15.29 8.04 5.47 7.58 6.08 8.49 12.73 15.64 15.75 10.06<br />

I 7.95 12.17 20.48 23.43 24.68 20.58 20.90 27.53 27.35 13.76 14.63 15.64 14.11 8.08 12.72 5.96 10.77 14.27 22.81 19.20 11.73<br />

MAY II 9.82 24.94 26.11 20.04 26.65 23.12 25.05 40.24 31.75 14.64 16.27 23.42 14.58 14.23 15.50 6.94 9.70 14.71 35.21 16.84 13.50<br />

III 14.00 29.12 19.97 21.36 25.85 22.46 33.33 57.16 44.22 15.42 19.09 31.04 35.52 16.37 17.15 6.97 9.82 18.09 34.03 23.30 13.94


YEAR<br />

Table-7.2<br />

UNRESTRICTED ENERGY GENERATION<br />

UNRESTRICTED<br />

ENERGY ARRANGED IN<br />

DESCENDING ORDER<br />

76<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

RANK OF THE YEAR<br />

1984-1985 2332.049 1<br />

1983-1984 1765.222 2<br />

1985-1986 1639.993 3<br />

1980-1981 1447.736 4<br />

1981-1982 1351.618 5<br />

1993-1994 1333.717 6<br />

1979-1980 1249.271 7<br />

1982-1983 1245.435 8<br />

1987-1988 1227.705 9<br />

1988-1989 1166.822 10<br />

1986-1987 1126.798 11<br />

1995-1996 1099.951 12<br />

1994-1995 1095.294 13<br />

1978-1979 1081.120 14<br />

1989-1990 1075.182 15<br />

1990-1991 1031.968 16<br />

1996-1997 1013.595 17<br />

1977-1978 971.124 18<br />

1991-1992 867.428 19<br />

1976-1977 826.686 20<br />

1992-1993 595.886 21<br />

90% dependable year<br />

=(N+1) x 0.9th year (where N=no. <strong>of</strong> years)<br />

=(21+1)*0.9th year<br />

=20<br />

1976-77 is 90% dependable year<br />

1986-87 is 50% dependable year<br />

Unrestricted energy <strong>of</strong> 90% dependable year is 826.686 MU<br />

90% dependable energy when power restricted to 141 MW is 639.52 MU


Table-7.3<br />

90% DEPENDABLE FLOWS FOR POWER GENERATION<br />

77<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

MONTH/PERIOD 90% dependable year 1976-77 inflow (cumecs)<br />

10- daily series for the dam<br />

d/s <strong>of</strong> confluence <strong>of</strong> Umram<br />

Chu & Passaram Chu.<br />

10- daily series for the dam<br />

on <strong>Rangyong</strong> Chu.<br />

I 11.06 9.97<br />

JUN II 21.58 19.46<br />

III 15.66 14.12<br />

I 20.02 18.05<br />

JUL II 19.07 17.20<br />

III 14.52 13.09<br />

I 16.92 15.26<br />

AUG II 18.45 16.64<br />

III 19.72 17.79<br />

I 17.97 16.21<br />

SEP II 10.36 9.35<br />

III 7.56 6.82<br />

I 6.41 5.78<br />

OCT II 5.06 4.57<br />

III 5.11 4.61<br />

I 5.08 4.58<br />

NOV II 4.21 3.80<br />

III 3.76 3.39<br />

I 3.06 2.76<br />

DEC II 2.62 2.36<br />

III 2.42 2.18<br />

I 2.16 1.94<br />

JAN II 2.05 1.85<br />

III 1.96 1.77<br />

I 3.61 3.26<br />

FEB II 3.52 3.18<br />

III 2.11 1.90<br />

I 2.00 1.80<br />

MAR II 2.85 2.57<br />

III 2.64 2.38<br />

I 3.83 3.46<br />

APR II 3.60 3.25<br />

III 3.82 3.45<br />

I 4.18 3.77<br />

MAY II 5.16 4.66<br />

III 7.36 6.64


PERIOD INFLO<br />

W<br />

HEAD POWE<br />

R<br />

UNRES<br />

ENERGY<br />

Table-7.4 (A)<br />

POWER POTENTIAL STUDY OF 90% DEPENDABLE YEAR 1976-1977<br />

78<br />

ENERGY AT DIFFERENT RESTRICTED CAPACITIES<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project, (3 x 47 MW)<br />

CUME<br />

(M) IN MW (MU) 114 MW 117 MW 120 MW 123 MW 126 MW 129 MW 132 MW 135 MW 138 MW 141 MW 144 MW 147 MW 150 MW 153 MW 156 MW 159 MW 162 MW<br />

C<br />

JUNE I 21.03 723.18 132.966 31.912 25.992 26.676 27.360 28.044 28.728 29.412 30.096 30.316 30.316 31.912 31.912 31.912 31.912 31.912 31.912 31.912 31.912<br />

II 41.04 723.18 259.483 62.276 25.992 26.676 27.360 28.044 28.728 29.412 30.096 30.780 31.464 32.148 32.832 33.516 34.200 34.884 35.568 36.252 36.936<br />

III 29.78 723.18 188.290 45.190 25.992 26.676 27.360 28.044 28.728 29.412 30.096 30.780 31.464 32.148 32.832 33.516 34.200 34.884 35.568 36.252 36.936<br />

JULY I 38.07 723.18 240.705 57.769 25.992 26.676 27.360 28.044 28.728 29.412 30.096 30.780 31.464 32.148 32.832 33.516 34.200 34.884 35.568 36.252 36.936<br />

II 36.28 723.18 229.387 55.053 25.992 26.676 27.360 28.044 28.728 29.412 30.096 30.780 31.464 32.148 32.832 33.516 34.200 34.884 35.568 36.252 36.936<br />

5 III 27.61 723.18 174.570 46.086 28.591 29.344 30.096 30.848 31.601 32.353 33.106 33.858 34.610 35.363 36.115 36.868 37.620 38.372 39.125 39.877 40.630<br />

AUG I 32.19 723.18 203.527 48.847 25.992 26.676 27.360 28.044 28.728 29.412 30.096 30.780 31.464 32.148 32.832 33.516 34.200 34.884 35.568 36.252 36.936<br />

II 35.09 723.18 221.863 53.247 25.992 26.676 27.360 28.044 28.728 29.412 30.096 30.780 31.464 32.148 32.832 33.516 34.200 34.884 35.568 36.252 36.936<br />

III 37.51 723.18 237.164 62.611 28.591 29.344 30.096 30.848 31.601 32.353 33.106 33.858 34.610 35.363 36.115 36.868 37.620 38.372 39.125 39.877 40.630<br />

SEPT I 34.17 723.18 216.046 51.851 25.992 26.676 27.360 28.044 28.728 29.412 30.096 30.780 31.464 32.148 32.832 33.516 34.200 34.884 35.568 36.252 36.936<br />

II 19.71 723.18 124.620 29.909 25.992 26.676 27.360 28.044 28.413 28.413 29.909 29.909 29.909 29.909 29.909 29.909 29.909 29.909 29.909 29.909 29.909<br />

III 14.39 723.18 90.984 21.836 21.836 21.836 21.836 21.836 21.836 21.836 21.836 21.836 21.836 21.836 21.836 21.836 21.836 21.836 21.836 21.836 21.836<br />

OCT I 12.19 723.18 77.074 18.498 18.498 18.498 18.498 18.498 18.498 18.498 18.498 18.498 18.498 18.498 18.498 18.498 18.498 18.498 18.498 18.498 18.498<br />

II 9.63 723.18 60.888 14.613 14.613 14.613 14.613 14.613 14.613 14.613 14.613 14.613 14.613 14.613 14.613 14.613 14.613 14.613 14.613 14.613 14.613<br />

III 9.72 723.18 61.457 16.225 16.225 16.225 16.225 16.225 16.225 16.225 16.225 16.225 16.225 16.225 16.225 16.225 16.225 16.225 16.225 16.225 16.225<br />

NOV I 9.67 723.18 61.140 14.674 14.674 14.674 14.674 14.674 14.674 14.674 14.674 14.674 14.674 14.674 14.674 14.674 14.674 14.674 14.674 14.674 14.674<br />

II 8.00 723.18 50.582 12.140 12.140 12.140 12.140 12.140 12.140 12.140 12.140 12.140 12.140 12.140 12.140 12.140 12.140 12.140 12.140 12.140 12.140<br />

III 7.16 723.18 45.270 10.865 10.865 10.865 10.865 10.865 10.865 10.865 10.865 10.865 10.865 10.865 10.865 10.865 10.865 10.865 10.865 10.865 10.865<br />

DEC I 5.82 723.18 36.798 8.832 8.832 8.832 8.832 8.832 8.832 8.832 8.832 8.832 8.832 8.832 8.832 8.832 8.832 8.832 8.832 8.832 8.832<br />

II 4.98 723.18 31.487 7.557 7.557 7.557 7.557 7.557 7.557 7.557 7.557 7.557 7.557 7.557 7.557 7.557 7.557 7.557 7.557 7.557 7.557<br />

III 4.60 723.18 29.084 7.678 7.678 7.678 7.678 7.678 7.678 7.678 7.678 7.678 7.678 7.678 7.678 7.678 7.678 7.678 7.678 7.678 7.678<br />

JAN I 4.10 723.18 25.923 6.222 6.222 6.222 6.222 6.222 6.222 6.222 6.222 6.222 6.222 6.222 6.222 6.222 6.222 6.222 6.222 6.222 6.222<br />

II 3.90 723.18 24.658 5.918 5.918 5.918 5.918 5.918 5.918 5.918 5.918 5.918 5.918 5.918 5.918 5.918 5.918 5.918 5.918 5.918 5.918<br />

III 3.73 723.18 23.584 6.226 6.226 6.226 6.226 6.226 6.226 6.226 6.226 6.226 6.226 6.226 6.226 6.226 6.226 6.226 6.226 6.226 6.226<br />

FEB I 6.87 723.18 43.437 10.425 10.425 10.425 10.425 10.425 10.425 10.425 10.425 10.425 10.425 10.425 10.425 10.425 10.425 10.425 10.425 10.425 10.425<br />

II 6.70 723.18 42.362 10.167 10.167 10.167 10.167 10.167 10.167 10.167 10.167 10.167 10.167 10.167 10.167 10.167 10.167 10.167 10.167 10.167 10.167<br />

III 4.01 723.18 25.354 4.868 4.868 4.868 4.868 4.868 4.868 4.868 4.868 4.868 4.868 4.868 4.868 4.868 4.868 4.868 4.868 4.868 4.868<br />

MAR I 3.80 723.18 24.026 5.766 5.766 5.766 5.766 5.766 5.766 5.766 5.766 5.766 5.766 5.766 5.766 5.766 5.766 5.766 5.766 5.766 5.766<br />

II 5.42 723.18 34.269 8.225 8.225 8.225 8.225 8.225 8.225 8.225 8.225 8.225 8.225 8.225 8.225 8.225 8.225 8.225 8.225 8.225 8.225<br />

III 5.03 723.18 31.803 8.396 8.396 8.396 8.396 8.396 8.396 8.396 8.396 8.396 8.396 8.396 8.396 8.396 8.396 8.396 8.396 8.396 8.396<br />

APR I 7.29 723.18 46.092 11.062 11.062 11.062 11.062 11.062 11.062 11.062 11.062 11.062 11.062 11.062 11.062 11.062 11.062 11.062 11.062 11.062 11.062<br />

II 6.84 723.18 43.247 10.379 10.379 10.379 10.379 10.379 10.379 10.379 10.379 10.379 10.379 10.379 10.379 10.379 10.379 10.379 10.379 10.379 10.379<br />

III 7.27 723.18 45.966 11.032 11.032 11.032 11.032 11.032 11.032 11.032 11.032 11.032 11.032 11.032 11.032 11.032 11.032 11.032 11.032 11.032 11.032<br />

MAY I 7.95 723.18 50.265 12.064 12.064 12.064 12.064 12.064 12.064 12.064 12.064 12.064 12.064 12.064 12.064 12.064 12.064 12.064 12.064 12.064 12.064<br />

II 9.82 723.18 62.089 14.901 14.901 14.901 14.901 14.901 14.901 14.901 14.901 14.901 14.901 14.901 14.901 14.901 14.901 14.901 14.901 14.901 14.901<br />

III 14.00 723.18 88.518 23.369 23.369 23.369 23.369 23.369 23.369 23.369 23.369 23.369 23.369 23.369 23.369 23.369 23.369 23.369 23.369 23.369 23.369<br />

ENERGY OBTAINED ON 95% M/C AVAILABILITY 826.686 573.05 580.71 588.37 596.03 603.37 610.35 618.82 625.34 631.63 639.52 645.81 652.10 658.40 664.69 670.98 677.27 683.57<br />

FRL= EL 1845<br />

MDDL= EL 1825<br />

TWL= 1098<br />

LOSSES= 15<br />

OVERALL EFFICIENCY= 89.30%


Table-7.4 (B)<br />

79<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>HE Project (3 x 47 MW)<br />

POWER POTENTIAL STUDY OF 90% DEPENDABLE YEAR 1976-1977 WITH<br />

95% MACHINE AVAILABILITY<br />

Net Head 723.18 m Design Discharge 22.30 Overall efficiency 89.30%<br />

Period<br />

Inflow Head Unrestri Unrestrict <strong>Power</strong> Energy (Mu) Energy Energy<br />

(Cumecs) (M) cted ed Restrict At 141 Mw During During<br />

<strong>Power</strong> In Energy ed To With 95% High Lean<br />

Mw (Mu) 141 Mw Machine Inflow Inflow<br />

Availability Period Period<br />

JUNE<br />

JULY<br />

AUG<br />

SEPT<br />

OCT<br />

NOV<br />

DEC<br />

JAN<br />

FEB<br />

MAR<br />

APR<br />

MAY<br />

10 1-10 21.03 723.18 132.97 31.912 132.97 31.912 0.000 31.912<br />

10 11-20 41.04 723.18 259.48 62.276 141.00 32.148 32.148 0.000<br />

10 21-30 29.78 723.18 188.29 45.190 141.00 32.148 32.148 0.000<br />

10 1-10 38.07 723.18 240.70 57.769 141.00 32.148 32.148 0.000<br />

10 11-20 36.28 723.18 229.39 55.053 141.00 32.148 32.148 0.000<br />

11 21-31 27.61 723.18 174.57 46.086 141.00 35.363 35.363 0.000<br />

10 1-10 32.19 723.18 203.53 48.847 141.00 32.148 32.148 0.000<br />

10 11-20 35.09 723.18 221.86 53.247 141.00 32.148 32.148 0.000<br />

11 21-31 37.51 723.18 237.16 62.611 141.00 35.363 35.363 0.000<br />

10 1-10 34.17 723.18 216.05 51.851 141.00 32.148 32.148 0.000<br />

10 11-20 19.71 723.18 124.62 29.909 124.62 29.909 0.000 29.909<br />

10 21-30 14.39 723.18 90.98 21.836 90.98 21.836 0.000 21.836<br />

10 1-10 12.19 723.18 77.07 18.498 77.07 18.498 0.000 18.498<br />

10 11-20 9.63 723.18 60.89 14.613 60.89 14.613 0.000 14.613<br />

11 21-31 9.72 723.18 61.46 16.225 61.46 16.225 0.000 16.225<br />

10 1-10 9.67 723.18 61.14 14.674 61.14 14.674 0.000 14.674<br />

10 11-20 8.00 723.18 50.58 12.140 50.58 12.140 0.000 12.140<br />

10 21-30 7.16 723.18 45.27 10.865 45.27 10.865 0.000 10.865<br />

10 1-10 5.82 723.18 36.80 8.832 36.80 8.832 0.000 8.832<br />

10 11-20 4.98 723.18 31.49 7.557 31.49 7.557 0.000 7.557<br />

11 21-31 4.60 723.18 29.08 7.678 29.08 7.678 0.000 7.678<br />

10 1-10 4.10 723.18 25.92 6.222 25.92 6.222 0.000 6.222<br />

10 11-20 3.90 723.18 24.66 5.918 24.66 5.918 0.000 5.918<br />

11 21-31 3.73 723.18 23.58 6.226 23.58 6.226 0.000 6.226<br />

10 1-10 6.87 723.18 43.44 10.425 43.44 10.425 0.000 10.425<br />

10 11-20 6.70 723.18 42.36 10.167 42.36 10.167 0.000 10.167<br />

8 21-28 4.01 723.18 25.35 4.868 25.35 4.868 0.000 4.868<br />

10 1-10 3.80 723.18 24.03 5.766 24.03 5.766 0.000 5.766<br />

10 11-20 5.42 723.18 34.27 8.225 34.27 8.225 0.000 8.225<br />

11 21-31 5.03 723.18 31.80 8.396 31.80 8.396 0.000 8.396<br />

10 1-10 7.29 723.18 46.09 11.062 46.09 11.062 0.000 11.062<br />

10 11-20 6.84 723.18 43.25 10.379 43.25 10.379 0.000 10.379<br />

10 21-30 7.27 723.18 45.97 11.032 45.97 11.032 0.000 11.032<br />

10 1-10 7.95 723.18 50.27 12.064 50.27 12.064 0.000 12.064<br />

10 11-20 9.82 723.18 62.09 14.901 62.09 14.901 0.000 14.901<br />

11 21-31 14.00 723.18 88.52 23.369 88.52 23.369 0.000 23.369<br />

Energy obtained on 95% machine availability 639.52 295.76 343.76<br />

LOAD FACTOR 51.78 95.00 37.21


Period<br />

Yearly<br />

inflow<br />

(M Cum)<br />

Annual Energy<br />

Generation<br />

(MU)<br />

Table 7.4 (C)<br />

80<br />

Annual<br />

Load<br />

Factor<br />

(%)<br />

Load Factor<br />

during high in<br />

flow period<br />

(%)<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>HE Project (3 x 47 MW)<br />

Load Factor<br />

during lean<br />

inflow period<br />

(%)<br />

1976-1977 535.37 639.52 51.78% 95.00% 37.21%<br />

1977-1978 626.49 738.62 59.80% 95.00% 47.94%<br />

1978-1979 700.98 792.80 64.19% 95.00% 53.80%<br />

1979-1980 808.67 951.71 77.05% 95.00% 71.00%<br />

1980-1981 937.71 929.82 75.28% 95.00% 68.63%<br />

1981-1982 875.47 905.81 73.34% 95.00% 66.03%<br />

1982-1983 804.96 833.56 67.49% 95.00% 58.21%<br />

1983-1984 1140.39 1021.78 82.72% 95.00% 78.59%<br />

1984-1985 1510.49 1106.43 89.58% 95.00% 87.75%<br />

1985-1986 1058.83 827.99 67.03% 95.00% 57.61%<br />

1986-1987 729.68 793.94 64.28% 95.00% 53.93%<br />

1987-1988 794.72 805.34 65.20% 95.00% 55.16%<br />

1988-1989 750.71 716.62 58.02% 95.00% 45.56%<br />

1989-1990 696.22 676.82 54.80% 95.00% 41.25%<br />

1990-1991 667.78 707.14 57.25% 95.00% 44.53%<br />

1991-1992 561.78 659.92 53.43% 95.00% 39.42%<br />

1992-1993 385.61 578.76 46.86% 86.60% 33.46%<br />

1993-1994 863.13 895.88 72.53% 92.30% 65.87%<br />

1994-1995 708.50 825.90 66.87% 95.00% 57.38%<br />

1995-1996 712.63 786.17 63.65% 95.00% 53.08%<br />

1996-1997 657.03 827.53 67.00% 93.70% 58.00%


Period<br />

Table-7.5<br />

POWER GENERATION IN 90% DEPENDABLE YEAR 1976-77<br />

90%<br />

Dependable<br />

Flow<br />

(Cumecs)<br />

81<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>HE Project (3 x 47 MW)<br />

<strong>Power</strong> In Mw Energy In Gwh Monthly<br />

Energy<br />

In Gwh<br />

Un Restricted<br />

Restricted To Installed<br />

Capacity Of<br />

141 Mw<br />

Un Restricted Restricted To<br />

Installed<br />

Capacity Of<br />

141 Mw<br />

1 2 3 4 5 6 7<br />

JUN<br />

1-10<br />

11-20<br />

21.03<br />

41.04<br />

132.966<br />

259.483<br />

132.97<br />

141.00<br />

31.912<br />

62.276<br />

31.912<br />

32.148 96.21<br />

21-30 29.78 188.290 141.00 45.190 32.148<br />

1-10 38.07 240.705 141.00 57.769 32.148<br />

JULY 11-20 36.28 229.387 141.00 55.053 32.148 99.66<br />

21-31 27.61 174.570 141.00 46.086 35.363<br />

1-10 32.19 203.527 141.00 48.847 32.148<br />

AUG 11-20 35.09 221.863 141.00 53.247 32.148 99.66<br />

21-31 37.51 237.164 141.00 62.611 35.363<br />

1-10 34.17 216.046 141.00 51.851 32.148<br />

SEPT 11-20 19.71 124.620 124.62 29.909 29.909 83.89<br />

21-30 14.39 90.984 90.98 21.836 21.836<br />

1-10 12.19 77.074 77.07 18.498 18.498<br />

OCT 11-20 9.63 60.888 60.89 14.613 14.613 49.34<br />

21-31 9.72 61.457 61.46 16.225 16.225<br />

1-10 9.67 61.140 61.14 14.674 14.674<br />

NOV 11-20 8.00 50.582 50.58 12.140 12.140 37.68<br />

21-30 7.16 45.270 45.27 10.865 10.865<br />

1-10 5.82 36.798 36.80 8.832 8.832<br />

DEC 11-20 4.98 31.487 31.49 7.557 7.557 24.07<br />

21-31 4.60 29.084 29.08 7.678 7.678<br />

1-10 4.10 25.923 25.92 6.222 6.222<br />

JAN 11-20 3.90 24.658 24.66 5.918 5.918 18.37<br />

21-31 3.73 23.584 23.58 6.226 6.226<br />

1-10 6.87 43.437 43.44 10.425 10.425<br />

FEB 11-20 6.70 42.362 42.36 10.167 10.167 25.46<br />

21-28 4.01 25.354 25.35 4.868 4.868<br />

1-10 3.80 24.026 24.03 5.766 5.766<br />

MAR 11-20 5.42 34.269 34.27 8.225 8.225 22.39<br />

21-31 5.03 31.803 31.80 8.396 8.396<br />

1-10 7.29 46.092 46.09 11.062 11.062<br />

APR 11-20 6.84 43.247 43.25 10.379 10.379 32.47<br />

21-30 7.27 45.966 45.97 11.032 11.032<br />

1-10 7.95 50.265 50.27 12.064 12.064<br />

MAY 11-20 9.82 62.089 62.09 14.901 14.901 50.33<br />

21-31 14.00 88.518 88.52 23.369 23.369<br />

ENERGY OBTAINED ON 95% M/C AVAILABILITY 639.52


Table-7.6<br />

82<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>HE Project (3 x 47 MW)<br />

INCREMENTAL BENEFIT IN 90% DEPENDABLE YEAR 1976-77<br />

MW MU ? MU/? MW<br />

Load Factor<br />

(%)<br />

Annual Load Factor<br />

for additional capacity<br />

(%)<br />

120 588.37 55.97% 29.15%<br />

2.55<br />

123 596.03 55.32% 29.15%<br />

2.45<br />

126 603.37 54.67% 27.95%<br />

2.33<br />

129 610.35 54.01% 26.55%<br />

2.82<br />

132 618.82 53.52% 32.24%<br />

2.17<br />

135 625.34 52.88% 24.78%<br />

2.10<br />

138 631.63 52.25% 23.95%<br />

2.63<br />

141 639.52 51.78% 30.02%<br />

2.10<br />

144 645.81 51.20% 23.95%<br />

2.10<br />

147 652.10 50.64% 23.95%<br />

2.10<br />

150 658.40 50.11% 23.95%<br />

2.10<br />

153 664.69 49.59% 23.95%<br />

2.10<br />

156 670.98 49.10% 23.95%<br />

2.10<br />

159 677.27 48.63% 23.95%<br />

2.10<br />

162 683.567 48.17% 23.95%


Table-7.7 (A)<br />

83<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>HE Project (3 x 47 MW)<br />

UNRESTRICTED ENERGY GENERATION IN YEAR 1976-77<br />

PERIOD INFLOW HEAD POWER UNRESTRICTED<br />

ENERGY<br />

CUMEC (M) (MW) (MU)<br />

JUNE I 21.03 723.18 132.966 31.912<br />

II 41.04 723.18 259.483 62.276<br />

III 29.78 723.18 188.290 45.190<br />

JULY I 38.07 723.18 240.705 57.769<br />

II 36.28 723.18 229.387 55.053<br />

III 27.61 723.18 174.570 46.086<br />

AUG I 32.19 723.18 203.527 48.847<br />

II 35.09 723.18 221.863 53.247<br />

III 37.51 723.18 237.164 62.611<br />

SEPT I 34.17 723.18 216.046 51.851<br />

II 19.71 723.18 124.620 29.909<br />

III 14.39 723.18 90.984 21.836<br />

OCT I 12.19 723.18 77.074 18.498<br />

II 9.63 723.18 60.888 14.613<br />

III 9.72 723.18 61.457 16.225<br />

NOV I 9.67 723.18 61.140 14.674<br />

II 8.00 723.18 50.582 12.140<br />

III 7.16 723.18 45.270 10.865<br />

DEC I 5.82 723.18 36.798 8.832<br />

II 4.98 723.18 31.487 7.557<br />

III 4.60 723.18 29.084 7.678<br />

JAN I 4.10 723.18 25.923 6.222<br />

II 3.90 723.18 24.658 5.918<br />

III 3.73 723.18 23.584 6.226<br />

FEB I 6.87 723.18 43.437 10.425<br />

II 6.70 723.18 42.362 10.167<br />

III 4.01 723.18 25.354 4.868<br />

MAR I 3.80 723.18 24.026 5.766<br />

II 5.42 723.18 34.269 8.225<br />

III 5.03 723.18 31.803 8.396<br />

APR I 7.29 723.18 46.092 11.062<br />

II 6.84 723.18 43.247 10.379<br />

III 7.27 723.18 45.966 11.032<br />

MAY I 7.95 723.18 50.265 12.064<br />

II 9.82 723.18 62.089 14.901<br />

III 14.00 723.18 88.518 23.369<br />

ENERGY OBTAINED 826.686


84<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>HE Project (3 x 47 MW)<br />

Table-7.7 (B)<br />

UNRESTRICTED ENERGY GENERATION IN YEAR 1977-78<br />

PERIOD INFLOW HEAD POWER UNRESTRICTED<br />

ENERGY<br />

CUMEC (M) (MW) (MU)<br />

JUNE I 22.62 723.18 143.019 34.325<br />

II 40.12 723.18 253.666 60.880<br />

III 29.18 723.18 184.496 44.279<br />

JULY I 33.35 723.18 210.862 50.607<br />

II 39.24 723.18 248.102 59.545<br />

III 46.99 723.18 297.103 78.435<br />

AUG I 38.37 723.18 242.602 58.224<br />

II 32.29 723.18 204.160 48.998<br />

III 37.70 723.18 238.365 62.928<br />

SEPT I 26.33 723.18 166.476 39.954<br />

II 21.53 723.18 136.128 32.671<br />

III 17.95 723.18 113.492 27.238<br />

OCT I 21.91 723.18 138.530 33.247<br />

II 13.82 723.18 87.380 20.971<br />

III 11.04 723.18 69.803 18.428<br />

NOV I 11.44 723.18 72.332 17.360<br />

II 10.44 723.18 66.009 15.842<br />

III 7.88 723.18 49.823 11.957<br />

DEC I 7.12 723.18 45.018 10.804<br />

II 7.53 723.18 47.610 11.426<br />

III 8.52 723.18 53.869 14.222<br />

JAN I 5.86 723.18 37.051 8.892<br />

II 5.25 723.18 33.194 7.967<br />

III 5.36 723.18 33.890 8.947<br />

FEB I 5.42 723.18 34.269 8.225<br />

II 5.31 723.18 33.573 8.058<br />

III 4.88 723.18 30.855 5.924<br />

MAR I 4.94 723.18 31.234 7.496<br />

II 5.28 723.18 33.384 8.012<br />

III 5.86 723.18 37.051 9.781<br />

APR I 7.04 723.18 44.512 10.683<br />

II 9.01 723.18 56.967 13.672<br />

III 10.68 723.18 67.526 16.206<br />

MAY I 12.17 723.18 76.947 18.467<br />

II 24.94 723.18 157.688 37.845<br />

III 29.12 723.18 184.117 48.607<br />

ENERGY OBTAINED 971.124


85<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>HE Project (3 x 47 MW)<br />

Table-7.7 (C)<br />

UNRESTRICTED ENERGY GENERATION IN YEAR 1978-79<br />

PERIOD INFLOW HEAD POWER UNRESTRICTED<br />

ENERGY<br />

CUMEC (M) (MW) (MU)<br />

JUNE I 33.41 723.18 211.241 50.698<br />

II 35.06 723.18 221.674 53.202<br />

III 44.32 723.18 280.222 67.253<br />

JULY I 38.91 723.18 246.016 59.044<br />

II 41.71 723.18 263.719 63.293<br />

III 40.26 723.18 254.552 67.202<br />

AUG I 47.65 723.18 301.276 72.306<br />

II 40.26 723.18 254.552 61.092<br />

III 30.23 723.18 191.135 50.460<br />

SEPT I 25.07 723.18 158.510 38.042<br />

II 32.65 723.18 206.436 49.545<br />

III 24.54 723.18 155.159 37.238<br />

OCT I 23.61 723.18 149.279 35.827<br />

II 18.41 723.18 116.401 27.936<br />

III 15.69 723.18 99.203 26.190<br />

NOV I 12.57 723.18 79.476 19.074<br />

II 9.38 723.18 59.307 14.234<br />

III 9.23 723.18 58.358 14.006<br />

DEC I 8.90 723.18 56.272 13.505<br />

II 7.54 723.18 47.673 11.442<br />

III 6.77 723.18 42.805 11.300<br />

JAN I 6.25 723.18 39.517 9.484<br />

II 5.77 723.18 36.482 8.756<br />

III 5.67 723.18 35.850 9.464<br />

FEB I 5.16 723.18 32.625 7.830<br />

II 5.15 723.18 32.562 7.815<br />

III 5.60 723.18 35.407 6.798<br />

MAR I 5.75 723.18 36.355 8.725<br />

II 6.02 723.18 38.063 9.135<br />

III 7.41 723.18 46.851 12.369<br />

APR I 10.94 723.18 69.170 16.601<br />

II 10.88 723.18 68.791 16.510<br />

III 13.65 723.18 86.305 20.713<br />

MAY I 20.48 723.18 129.489 31.077<br />

II 26.11 723.18 165.085 39.621<br />

III 19.97 723.18 126.264 33.334<br />

ENERGY OBTAINED 1081.120


86<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>HE Project (3 x 47 MW)<br />

Table-7.7 (D)<br />

UNRESTRICTED ENERGY GENERATION IN YEAR 1979-80<br />

PERIOD INFLOW HEAD POWER UNRESTRICTED<br />

ENERGY<br />

CUMEC (M) (MW) (MU)<br />

JUNE I 23.80 723.18 150.480 36.115<br />

II 28.48 723.18 180.070 43.217<br />

III 40.83 723.18 258.155 61.957<br />

JULY I 42.41 723.18 268.145 64.355<br />

II 40.56 723.18 256.448 61.548<br />

III 45.44 723.18 287.303 75.848<br />

AUG I 41.99 723.18 265.490 63.718<br />

II 33.16 723.18 209.660 50.319<br />

III 35.17 723.18 222.369 58.705<br />

SEPT I 34.59 723.18 218.702 52.488<br />

II 30.18 723.18 190.819 45.797<br />

III 22.14 723.18 139.984 33.596<br />

OCT I 36.90 723.18 233.307 55.994<br />

II 25.18 723.18 159.205 38.209<br />

III 18.89 723.18 119.436 31.531<br />

NOV I 18.83 723.18 119.056 28.574<br />

II 15.33 723.18 96.927 23.262<br />

III 14.43 723.18 91.236 21.897<br />

DEC I 13.75 723.18 86.937 20.865<br />

II 11.32 723.18 71.573 17.177<br />

III 10.90 723.18 68.917 18.194<br />

JAN I 10.27 723.18 64.934 15.584<br />

II 9.89 723.18 62.531 15.008<br />

III 9.80 723.18 61.962 16.358<br />

FEB I 9.41 723.18 59.497 14.279<br />

II 9.86 723.18 62.342 14.962<br />

III 10.51 723.18 66.451 14.354<br />

MAR I 10.81 723.18 68.348 16.404<br />

II 11.09 723.18 70.119 16.828<br />

III 14.97 723.18 94.651 24.988<br />

APR I 16.81 723.18 106.284 25.508<br />

II 21.57 723.18 136.380 32.731<br />

III 24.57 723.18 155.349 37.284<br />

MAY I 23.43 723.18 148.141 35.554<br />

II 20.04 723.18 126.707 30.410<br />

III 21.36 723.18 135.053 35.654<br />

ENERGY OBTAINED 1249.271


87<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>HE Project (3 x 47 MW)<br />

Table-7.7 (E)<br />

UNRESTRICTED ENERGY GENERATION IN YEAR 1980-81<br />

PERIOD INFLOW HEAD POWER UNRESTRICTED<br />

ENERGY<br />

CUMEC (M) (MW) (MU)<br />

JUNE I 32.76 723.18 207.131 49.712<br />

II 43.60 723.18 275.669 66.161<br />

III 48.80 723.18 308.547 74.051<br />

JULY I 51.64 723.18 326.504 78.361<br />

II 52.87 723.18 334.281 80.227<br />

III 55.39 723.18 350.214 92.456<br />

AUG I 55.97 723.18 353.881 84.931<br />

II 61.46 723.18 388.593 93.262<br />

III 51.19 723.18 323.659 85.446<br />

SEPT I 48.90 723.18 309.180 74.203<br />

II 38.33 723.18 242.349 58.164<br />

III 31.03 723.18 196.193 47.086<br />

OCT I 24.27 723.18 153.452 36.828<br />

II 20.86 723.18 131.891 31.654<br />

III 19.43 723.18 122.850 32.432<br />

NOV I 16.42 723.18 103.819 24.916<br />

II 14.95 723.18 94.524 22.686<br />

III 13.76 723.18 87.000 20.880<br />

DEC I 12.78 723.18 80.804 19.393<br />

II 11.62 723.18 73.470 17.633<br />

III 10.55 723.18 66.704 17.610<br />

JAN I 10.17 723.18 64.302 15.432<br />

II 9.53 723.18 60.255 14.461<br />

III 9.41 723.18 59.497 15.707<br />

FEB I 8.75 723.18 55.324 13.278<br />

II 9.00 723.18 56.904 13.657<br />

III 10.88 723.18 68.791 13.208<br />

MAR I 10.76 723.18 68.032 16.328<br />

II 11.39 723.18 72.015 17.284<br />

III 13.45 723.18 85.040 22.451<br />

APR I 13.47 723.18 85.167 20.440<br />

II 17.05 723.18 107.802 25.872<br />

III 20.09 723.18 127.023 30.485<br />

MAY I 24.68 723.18 156.044 37.451<br />

II 26.65 723.18 168.500 40.440<br />

III 25.85 723.18 163.442 43.149<br />

ENERGY OBTAINED 1447.736


88<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>HE Project (3 x 47 MW)<br />

Table-7.7 (F)<br />

UNRESTRICTED ENERGY GENERATION IN YEAR 1981-82<br />

PERIOD INFLOW HEAD POWER UNRESTRICTED<br />

ENERGY<br />

CUMEC (M) (MW) (MU)<br />

JUNE I 28.45 723.18 179.881 43.171<br />

II 34.03 723.18 215.161 51.639<br />

III 46.20 723.18 292.108 70.106<br />

JULY I 59.02 723.18 373.165 89.560<br />

II 50.61 723.18 319.991 76.798<br />

III 47.60 723.18 300.960 79.453<br />

AUG I 46.42 723.18 293.499 70.440<br />

II 48.98 723.18 309.685 74.325<br />

III 47.62 723.18 301.087 79.487<br />

SEPT I 45.58 723.18 288.188 69.165<br />

II 39.06 723.18 246.964 59.271<br />

III 31.13 723.18 196.825 47.238<br />

OCT I 28.55 723.18 180.513 43.323<br />

II 26.42 723.18 167.046 40.091<br />

III 23.09 723.18 145.991 38.542<br />

NOV I 19.68 723.18 124.431 29.863<br />

II 15.70 723.18 99.266 23.824<br />

III 13.01 723.18 82.258 19.742<br />

DEC I 11.94 723.18 75.493 18.118<br />

II 10.74 723.18 67.906 16.297<br />

III 8.42 723.18 53.237 14.055<br />

JAN I 7.73 723.18 48.874 11.730<br />

II 8.60 723.18 54.375 13.050<br />

III 8.48 723.18 53.616 14.155<br />

FEB I 8.41 723.18 53.174 12.762<br />

II 8.74 723.18 55.260 13.262<br />

III 8.49 723.18 53.680 10.306<br />

MAR I 8.85 723.18 55.956 13.429<br />

II 9.91 723.18 62.658 15.038<br />

III 11.80 723.18 74.608 19.696<br />

APR I 14.83 723.18 93.766 22.504<br />

II 14.80 723.18 93.576 22.458<br />

III 16.42 723.18 103.819 24.916<br />

MAY I 20.58 723.18 130.121 31.229<br />

II 23.12 723.18 146.181 35.083<br />

III 22.46 723.18 142.008 37.490<br />

ENERGY OBTAINED 1351.618


89<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>HE Project (3 x 47 MW)<br />

Table-7.7 (G)<br />

UNRESTRICTED ENERGY GENERATION IN YEAR 1982-83<br />

PERIOD INFLOW HEAD POWER UNRESTRICTED<br />

ENERGY<br />

CUMEC (M) (MW) (MU)<br />

JUNE I 39.65 723.18 250.695 60.167<br />

II 43.67 723.18 276.112 66.267<br />

III 48.27 723.18 305.196 73.247<br />

JULY I 42.39 723.18 268.019 64.325<br />

II 47.49 723.18 300.265 72.064<br />

III 56.02 723.18 354.197 93.508<br />

AUG I 37.64 723.18 237.986 57.117<br />

II 35.63 723.18 225.277 54.067<br />

III 41.82 723.18 264.415 69.806<br />

SEPT I 32.17 723.18 203.401 48.816<br />

II 46.52 723.18 294.132 70.592<br />

III 30.53 723.18 193.032 46.328<br />

OCT I 21.61 723.18 136.633 32.792<br />

II 18.15 723.18 114.757 27.542<br />

III 17.48 723.18 110.521 29.177<br />

NOV I 13.69 723.18 86.558 20.774<br />

II 11.94 723.18 75.493 18.118<br />

III 11.56 723.18 73.090 17.542<br />

DEC I 10.22 723.18 64.618 15.508<br />

II 9.42 723.18 59.560 14.294<br />

III 8.92 723.18 56.398 14.889<br />

JAN I 8.84 723.18 55.893 13.414<br />

II 7.87 723.18 49.760 11.942<br />

III 5.52 723.18 34.901 9.214<br />

FEB I 5.02 723.18 31.740 7.618<br />

II 4.99 723.18 31.550 7.572<br />

III 6.94 723.18 43.879 8.425<br />

MAR I 7.46 723.18 47.167 11.320<br />

II 9.56 723.18 60.445 14.507<br />

III 8.63 723.18 54.565 14.405<br />

APR I 12.69 723.18 80.235 19.256<br />

II 10.38 723.18 65.630 15.751<br />

III 12.99 723.18 82.132 19.712<br />

MAY I 20.90 723.18 132.144 31.715<br />

II 25.05 723.18 158.383 38.012<br />

III 33.33 723.18 210.735 55.634<br />

ENERGY OBTAINED 1245.435


90<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>HE Project (3 x 47 MW)<br />

Table-7.7 (H)<br />

UNRESTRICTED ENERGY GENERATION IN YEAR 1983-84<br />

PERIOD INFLOW HEAD POWER UNRESTRICTED<br />

ENERGY<br />

CUMEC (M) (MW) (MU)<br />

JUNE I 41.91 723.18 264.984 63.596<br />

II 40.68 723.18 257.207 61.730<br />

III 56.77 723.18 358.939 86.145<br />

JULY I 65.01 723.18 411.038 98.649<br />

II 55.31 723.18 349.708 83.930<br />

III 54.87 723.18 346.926 91.588<br />

AUG I 44.91 723.18 283.952 68.148<br />

II 47.62 723.18 301.087 72.261<br />

III 55.64 723.18 351.795 92.874<br />

SEPT I 44.72 723.18 282.751 67.860<br />

II 50.28 723.18 317.905 76.297<br />

III 58.00 723.18 366.716 88.012<br />

OCT I 40.78 723.18 257.839 61.881<br />

II 40.20 723.18 254.172 61.001<br />

III 27.40 723.18 173.242 45.736<br />

NOV I 22.40 723.18 141.628 33.991<br />

II 20.58 723.18 130.121 31.229<br />

III 16.95 723.18 107.170 25.721<br />

DEC I 14.14 723.18 89.403 21.457<br />

II 13.26 723.18 83.839 20.121<br />

III 11.88 723.18 75.114 19.830<br />

JAN I 10.61 723.18 67.084 16.100<br />

II 10.44 723.18 66.009 15.842<br />

III 9.29 723.18 58.738 15.507<br />

FEB I 8.95 723.18 56.588 13.581<br />

II 9.29 723.18 58.738 14.097<br />

III 8.93 723.18 56.462 12.196<br />

MAR I 19.71 723.18 124.620 29.909<br />

II 22.03 723.18 139.289 33.429<br />

III 21.64 723.18 136.823 36.121<br />

APR I 22.75 723.18 143.841 34.522<br />

II 24.25 723.18 153.325 36.798<br />

III 24.26 723.18 153.388 36.813<br />

MAY I 27.53 723.18 174.064 41.775<br />

II 40.24 723.18 254.425 61.062<br />

III 57.16 723.18 361.405 95.411<br />

ENERGY OBTAINED 1765.222


91<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>HE Project (3 x 47 MW)<br />

Table-7.7 (I)<br />

UNRESTRICTED ENERGY GENERATION IN YEAR 1984-85<br />

PERIOD INFLOW HEAD POWER UNRESTRICTED<br />

ENERGY<br />

CUMEC (M) (MW) (MU)<br />

JUNE I 59.40 723.18 375.568 90.136<br />

II 71.43 723.18 451.630 108.391<br />

III 64.15 723.18 405.601 97.344<br />

JULY I 73.83 723.18 466.804 112.033<br />

II 74.07 723.18 468.322 112.397<br />

III 78.31 723.18 495.130 130.714<br />

AUG I 70.62 723.18 446.508 107.162<br />

II 70.81 723.18 447.710 107.450<br />

III 74.13 723.18 468.701 123.737<br />

SEPT I 76.35 723.18 482.737 115.857<br />

II 72.86 723.18 460.671 110.561<br />

III 57.80 723.18 365.452 87.708<br />

OCT I 48.68 723.18 307.789 73.869<br />

II 61.75 723.18 390.426 93.702<br />

III 47.57 723.18 300.770 79.403<br />

NOV I 35.45 723.18 224.139 53.793<br />

II 30.64 723.18 193.727 46.495<br />

III 27.23 723.18 172.167 41.320<br />

DEC I 17.46 723.18 110.394 26.495<br />

II 17.18 723.18 108.624 26.070<br />

III 17.24 723.18 109.003 28.777<br />

JAN I 17.39 723.18 109.952 26.388<br />

II 16.52 723.18 104.451 25.068<br />

III 14.30 723.18 90.414 23.869<br />

FEB I 15.63 723.18 98.824 23.718<br />

II 14.29 723.18 90.351 21.684<br />

III 17.29 723.18 109.319 20.989<br />

MAR I 21.97 723.18 138.910 33.338<br />

II 23.79 723.18 150.417 36.100<br />

III 22.16 723.18 140.111 36.989<br />

APR I 26.67 723.18 168.626 40.470<br />

II 32.19 723.18 203.527 48.847<br />

III 38.01 723.18 240.326 57.678<br />

MAY I 27.35 723.18 172.926 41.502<br />

II 31.75 723.18 200.745 48.179<br />

III 44.22 723.18 279.589 73.812<br />

ENERGY OBTAINED 2332.049


92<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>HE Project (3 x 47 MW)<br />

Table-7.7 (J)<br />

UNRESTRICTED ENERGY GENERATION IN YEAR 1985-86<br />

PERIOD INFLOW HEAD POWER UNRESTRICTED<br />

ENERGY<br />

CUMEC (M) (MW) (MU)<br />

JUNE I 28.15 723.18 177.984 42.716<br />

II 35.59 723.18 225.025 54.006<br />

III 100.36 723.18 634.545 152.291<br />

JULY I 79.13 723.18 500.315 120.075<br />

II 103.26 723.18 652.881 156.691<br />

III 86.82 723.18 548.936 144.919<br />

AUG I 70.16 723.18 443.600 106.464<br />

II 74.01 723.18 467.942 112.306<br />

III 90.61 723.18 572.899 151.245<br />

SEPT I 37.35 723.18 236.153 56.677<br />

II 35.11 723.18 221.990 53.278<br />

III 29.93 723.18 189.238 45.417<br />

OCT I 25.44 723.18 160.849 38.604<br />

II 22.03 723.18 139.289 33.429<br />

III 18.14 723.18 114.694 30.279<br />

NOV I 14.77 723.18 93.386 22.413<br />

II 12.77 723.18 80.741 19.378<br />

III 11.31 723.18 71.510 17.162<br />

DEC I 9.68 723.18 61.204 14.689<br />

II 8.77 723.18 55.450 13.308<br />

III 8.02 723.18 50.708 13.387<br />

JAN I 7.71 723.18 48.748 11.700<br />

II 7.67 723.18 48.495 11.639<br />

III 7.26 723.18 45.903 12.118<br />

FEB I 7.34 723.18 46.409 11.138<br />

II 7.55 723.18 47.736 11.457<br />

III 8.64 723.18 54.628 10.489<br />

MAR I 9.21 723.18 58.232 13.976<br />

II 10.03 723.18 63.417 15.220<br />

III 10.30 723.18 65.124 17.193<br />

APR I 10.12 723.18 63.986 15.357<br />

II 13.09 723.18 82.764 19.863<br />

III 14.68 723.18 92.817 22.276<br />

MAY I 13.76 723.18 87.000 20.880<br />

II 14.64 723.18 92.564 22.215<br />

III 15.42 723.18 97.496 25.739<br />

ENERGY OBTAINED 1639.993


93<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>HE Project (3 x 47 MW)<br />

Table-7.7 (K)<br />

UNRESTRICTED ENERGY GENERATION IN YEAR 1986-87<br />

PERIOD INFLOW HEAD POWER UNRESTRICTED<br />

ENERGY<br />

CUMEC (M) (MW) (MU)<br />

JUNE I 18.75 723.18 118.550 28.452<br />

II 31.80 723.18 201.062 48.255<br />

III 47.12 723.18 297.925 71.502<br />

JULY I 40.81 723.18 258.029 61.927<br />

II 50.99 723.18 322.394 77.375<br />

III 45.86 723.18 289.959 76.549<br />

AUG I 40.70 723.18 257.334 61.760<br />

II 34.99 723.18 221.231 53.095<br />

III 38.73 723.18 244.878 64.648<br />

SEPT I 34.01 723.18 215.035 51.608<br />

II 42.24 723.18 267.070 64.097<br />

III 34.38 723.18 217.374 52.170<br />

OCT I 27.73 723.18 175.328 42.079<br />

II 20.73 723.18 131.069 31.457<br />

III 16.19 723.18 102.364 27.024<br />

NOV I 14.89 723.18 94.145 22.595<br />

II 13.24 723.18 83.712 20.091<br />

III 11.44 723.18 72.332 17.360<br />

DEC I 10.24 723.18 64.744 15.539<br />

II 9.43 723.18 59.623 14.310<br />

III 6.95 723.18 43.943 11.601<br />

JAN I 6.07 723.18 38.379 9.211<br />

II 5.71 723.18 36.103 8.665<br />

III 5.36 723.18 33.890 8.947<br />

FEB I 5.08 723.18 32.119 7.709<br />

II 5.03 723.18 31.803 7.633<br />

III 5.52 723.18 34.901 6.701<br />

MAR I 5.16 723.18 32.625 7.830<br />

II 6.12 723.18 38.695 9.287<br />

III 7.68 723.18 48.558 12.819<br />

APR I 14.01 723.18 88.581 21.259<br />

II 9.79 723.18 61.899 14.856<br />

III 12.94 723.18 81.816 19.636<br />

MAY I 14.63 723.18 92.501 22.200<br />

II 16.27 723.18 102.870 24.689<br />

III 19.09 723.18 120.700 31.865<br />

ENERGY OBTAINED 1126.798


94<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>HE Project (3 x 47 MW)<br />

Table-7.7 (L)<br />

UNRESTRICTED ENERGY GENERATION IN YEAR 1987-88<br />

PERIOD INFLOW HEAD POWER UNRESTRICTED<br />

ENERGY<br />

CUMEC (M) (MW) (MU)<br />

JUNE I 31.67 723.18 200.240 48.058<br />

II 46.00 723.18 290.844 69.803<br />

III 38.61 723.18 244.119 58.589<br />

JULY I 44.29 723.18 280.032 67.208<br />

II 42.34 723.18 267.703 64.249<br />

III 47.35 723.18 299.379 79.036<br />

AUG I 44.83 723.18 283.446 68.027<br />

II 48.91 723.18 309.243 74.218<br />

III 32.69 723.18 206.689 54.566<br />

SEPT I 58.81 723.18 371.837 89.241<br />

II 31.46 723.18 198.912 47.739<br />

III 43.15 723.18 272.824 65.478<br />

OCT I 26.80 723.18 169.448 40.668<br />

II 19.96 723.18 126.201 30.288<br />

III 17.07 723.18 107.928 28.493<br />

NOV I 13.85 723.18 87.569 21.017<br />

II 8.45 723.18 53.427 12.822<br />

III 7.42 723.18 46.914 11.259<br />

DEC I 7.00 723.18 44.259 10.622<br />

II 6.41 723.18 40.528 9.727<br />

III 5.86 723.18 37.051 9.781<br />

JAN I 5.71 723.18 36.103 8.665<br />

II 5.71 723.18 36.103 8.665<br />

III 5.65 723.18 35.723 9.431<br />

FEB I 5.54 723.18 35.028 8.407<br />

II 5.80 723.18 36.672 8.801<br />

III 6.44 723.18 40.718 8.795<br />

MAR I 6.68 723.18 42.236 10.137<br />

II 9.90 723.18 62.595 15.023<br />

III 10.18 723.18 64.365 16.992<br />

APR I 11.64 723.18 73.596 17.663<br />

II 13.15 723.18 83.143 19.954<br />

III 15.29 723.18 96.674 23.202<br />

MAY I 15.64 723.18 98.887 23.733<br />

II 23.42 723.18 148.077 35.539<br />

III 31.04 723.18 196.256 51.812<br />

ENERGY OBTAINED 1227.705


95<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>HE Project (3 x 47 MW)<br />

Table-7.7 (M)<br />

UNRESTRICTED ENERGY GENERATION IN YEAR 1988-89<br />

PERIOD INFLOW HEAD POWER UNRESTRICTED<br />

ENERGY<br />

CUMEC (M) (MW) (MU)<br />

JUNE I 25.04 723.18 158.320 37.997<br />

II 36.23 723.18 229.071 54.977<br />

III 39.68 723.18 250.884 60.212<br />

JULY I 61.67 723.18 389.920 93.581<br />

II 48.44 723.18 306.271 73.505<br />

III 53.39 723.18 337.568 89.118<br />

AUG I 52.99 723.18 335.039 80.409<br />

II 48.63 723.18 307.472 73.793<br />

III 73.79 723.18 466.551 123.170<br />

SEPT I 35.23 723.18 222.748 53.460<br />

II 23.76 723.18 150.227 36.055<br />

III 26.57 723.18 167.994 40.319<br />

OCT I 22.43 723.18 141.818 34.036<br />

II 14.89 723.18 94.145 22.595<br />

III 11.98 723.18 75.746 19.997<br />

NOV I 9.87 723.18 62.405 14.977<br />

II 8.91 723.18 56.335 13.520<br />

III 8.31 723.18 52.542 12.610<br />

DEC I 7.88 723.18 49.823 11.957<br />

II 7.48 723.18 47.294 11.350<br />

III 7.08 723.18 44.765 11.818<br />

JAN I 4.33 723.18 27.377 6.571<br />

II 4.22 723.18 26.682 6.404<br />

III 4.18 723.18 26.429 6.977<br />

FEB I 4.65 723.18 29.401 7.056<br />

II 4.25 723.18 26.871 6.449<br />

III 4.52 723.18 28.579 5.487<br />

MAR I 5.14 723.18 32.499 7.800<br />

II 5.24 723.18 33.131 7.951<br />

III 5.38 723.18 34.016 8.980<br />

APR I 5.60 723.18 35.407 8.498<br />

II 6.70 723.18 42.362 10.167<br />

III 8.04 723.18 50.834 12.200<br />

MAY I 14.11 723.18 89.213 21.411<br />

II 14.58 723.18 92.185 22.124<br />

III 35.52 723.18 224.582 59.290<br />

ENERGY OBTAINED 1166.822


96<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>HE Project (3 x 47 MW)<br />

Table-7.7 (N)<br />

UNRESTRICTED ENERGY GENERATION IN YEAR 1989-90<br />

PERIOD INFLOW HEAD POWER UNRESTRICTED<br />

ENERGY<br />

CUMEC (M) (MW) (MU)<br />

JUNE I 31.54 723.18 199.418 47.860<br />

II 52.24 723.18 330.297 79.271<br />

III 55.25 723.18 349.329 83.839<br />

JULY I 56.26 723.18 355.715 85.372<br />

II 55.34 723.18 349.898 83.975<br />

III 51.51 723.18 325.682 85.980<br />

AUG I 44.70 723.18 282.624 67.830<br />

II 35.07 723.18 221.737 53.217<br />

III 34.40 723.18 217.501 57.420<br />

SEPT I 33.35 723.18 210.862 50.607<br />

II 30.21 723.18 191.009 45.842<br />

III 30.01 723.18 189.744 45.539<br />

OCT I 23.70 723.18 149.848 35.963<br />

II 20.17 723.18 127.529 30.607<br />

III 16.41 723.18 103.755 27.391<br />

NOV I 10.21 723.18 64.555 15.493<br />

II 8.28 723.18 52.352 12.564<br />

III 7.53 723.18 47.610 11.426<br />

DEC I 6.57 723.18 41.540 9.970<br />

II 5.70 723.18 36.039 8.649<br />

III 4.99 723.18 31.550 8.329<br />

JAN I 4.55 723.18 28.768 6.904<br />

II 4.22 723.18 26.682 6.404<br />

III 3.82 723.18 24.153 6.376<br />

FEB I 3.76 723.18 23.773 5.706<br />

II 3.53 723.18 22.319 5.357<br />

III 3.41 723.18 21.560 4.140<br />

MAR I 3.11 723.18 19.664 4.719<br />

II 2.54 723.18 16.060 3.854<br />

III 2.59 723.18 16.376 4.323<br />

APR I 2.68 723.18 16.945 4.067<br />

II 4.42 723.18 27.946 6.707<br />

III 5.47 723.18 34.585 8.300<br />

MAY I 8.08 723.18 51.087 12.261<br />

II 14.23 723.18 89.972 21.593<br />

III 16.37 723.18 103.502 27.325<br />

ENERGY OBTAINED 1075.182


Table-7.7 (O)<br />

97<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>HE Project (3 x 47 MW)<br />

UNRESTRICTED ENERGY GENERATION IN YEAR 1990-91<br />

PERIOD INFLOW HEAD POWER UNRESTRICTED<br />

ENERGY<br />

CUMEC (M) (MW) (MU)<br />

JUNE I 34.57 723.18 218.575 52.458<br />

II 33.77 723.18 213.517 51.244<br />

III 39.48 723.18 249.620 59.909<br />

JULY I 43.52 723.18 275.164 66.039<br />

II 55.48 723.18 350.783 84.188<br />

III 47.48 723.18 300.201 79.253<br />

AUG I 40.44 723.18 255.690 61.366<br />

II 41.09 723.18 259.799 62.352<br />

III 36.46 723.18 230.525 60.859<br />

SEPT I 34.99 723.18 221.231 53.095<br />

II 33.51 723.18 211.873 50.850<br />

III 23.34 723.18 147.572 35.417<br />

OCT I 19.55 723.18 123.609 29.666<br />

II 19.92 723.18 125.948 30.228<br />

III 16.38 723.18 103.566 27.341<br />

NOV I 10.03 723.18 63.417 15.220<br />

II 7.50 723.18 47.420 11.381<br />

III 6.26 723.18 39.580 9.499<br />

DEC I 5.73 723.18 36.229 8.695<br />

II 4.73 723.18 29.906 7.178<br />

III 4.08 723.18 25.797 6.810<br />

JAN I 4.13 723.18 26.113 6.267<br />

II 4.05 723.18 25.607 6.146<br />

III 4.01 723.18 25.354 6.693<br />

FEB I 3.88 723.18 24.532 5.888<br />

II 3.69 723.18 23.331 5.599<br />

III 3.73 723.18 23.584 4.528<br />

MAR I 3.98 723.18 25.164 6.039<br />

II 4.54 723.18 28.705 6.889<br />

III 4.79 723.18 30.286 7.995<br />

APR I 12.56 723.18 79.413 19.059<br />

II 7.16 723.18 45.270 10.865<br />

III 7.58 723.18 47.926 11.502<br />

MAY I 12.72 723.18 80.425 19.302<br />

II 15.50 723.18 98.002 23.520<br />

III 17.15 723.18 108.434 28.627<br />

ENERGY OBTAINED 1031.968


98<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>HE Project (3 x 47 MW)<br />

Table-7.7 (P)<br />

UNRESTRICTED ENERGY GENERATION IN YEAR 1991-92<br />

PERIOD INFLOW HEAD POWER UNRESTRICTED<br />

ENERGY<br />

CUMEC (M) (MW) (MU)<br />

JUNE I 18.35 723.18 116.021 27.845<br />

II 28.98 723.18 183.232 43.976<br />

III 26.65 723.18 168.500 40.440<br />

JULY I 30.43 723.18 192.400 46.176<br />

II 29.65 723.18 187.468 44.992<br />

III 32.32 723.18 204.349 53.948<br />

AUG I 37.06 723.18 234.319 56.237<br />

II 42.69 723.18 269.916 64.780<br />

III 35.28 723.18 223.065 58.889<br />

SEPT I 35.54 723.18 224.708 53.930<br />

II 37.55 723.18 237.417 56.980<br />

III 29.08 723.18 183.864 44.127<br />

OCT I 23.22 723.18 146.813 35.235<br />

II 18.41 723.18 116.401 27.936<br />

III 15.11 723.18 95.536 25.221<br />

NOV I 12.52 723.18 79.160 18.998<br />

II 11.07 723.18 69.992 16.798<br />

III 8.45 723.18 53.427 12.822<br />

DEC I 7.10 723.18 44.891 10.774<br />

II 5.45 723.18 34.459 8.270<br />

III 4.79 723.18 30.286 7.995<br />

JAN I 4.36 723.18 27.567 6.616<br />

II 3.62 723.18 22.888 5.493<br />

III 3.70 723.18 23.394 6.176<br />

FEB I 3.91 723.18 24.722 5.933<br />

II 3.77 723.18 23.837 5.721<br />

III 3.61 723.18 22.825 4.930<br />

MAR I 3.87 723.18 24.469 5.873<br />

II 3.90 723.18 24.658 5.918<br />

III 4.01 723.18 25.354 6.693<br />

APR I 4.73 723.18 29.906 7.178<br />

II 6.65 723.18 42.046 10.091<br />

III 6.08 723.18 38.442 9.226<br />

MAY I 5.96 723.18 37.683 9.044<br />

II 6.94 723.18 43.879 10.531<br />

III 6.97 723.18 44.069 11.634<br />

ENERGY OBTAINED 867.428


99<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>HE Project (3 x 47 MW)<br />

Table-7.7 (Q)<br />

UNRESTRICTED ENERGY GENERATION IN YEAR 1992-93<br />

PERIOD INFLOW HEAD POWER UNRESTRICTED<br />

ENERGY<br />

CUMEC (M) (MW) (MU)<br />

JUNE I 7.70 723.18 48.685 11.684<br />

II 10.98 723.18 69.423 16.662<br />

III 21.28 723.18 134.547 32.291<br />

JULY I 18.28 723.18 115.579 27.739<br />

II 18.50 723.18 116.970 28.073<br />

III 21.01 723.18 132.840 35.070<br />

AUG I 23.00 723.18 145.422 34.901<br />

II 23.09 723.18 145.991 35.038<br />

III 25.11 723.18 158.763 41.913<br />

SEPT I 22.02 723.18 139.226 33.414<br />

II 21.67 723.18 137.013 32.883<br />

III 17.94 723.18 113.429 27.223<br />

OCT I 13.55 723.18 85.672 20.561<br />

II 9.72 723.18 61.457 14.750<br />

III 8.27 723.18 52.289 13.804<br />

NOV I 6.11 723.18 38.632 9.272<br />

II 5.43 723.18 34.332 8.240<br />

III 4.95 723.18 31.297 7.511<br />

DEC I 4.89 723.18 30.918 7.420<br />

II 4.23 723.18 26.745 6.419<br />

III 3.91 723.18 24.722 6.527<br />

JAN I 3.97 723.18 25.101 6.024<br />

II 4.01 723.18 25.354 6.085<br />

III 3.77 723.18 23.837 6.293<br />

FEB I 3.65 723.18 23.078 5.539<br />

II 3.87 723.18 24.469 5.873<br />

III 3.74 723.18 23.647 4.540<br />

MAR I 6.11 723.18 38.632 9.272<br />

II 6.10 723.18 38.568 9.256<br />

III 6.39 723.18 40.402 10.666<br />

APR I 6.49 723.18 41.034 9.848<br />

II 7.09 723.18 44.828 10.759<br />

III 8.49 723.18 53.680 12.883<br />

MAY I 10.77 723.18 68.095 16.343<br />

II 9.70 723.18 61.330 14.719<br />

III 9.82 723.18 62.089 16.391<br />

ENERGY OBTAINED 595.886


100<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>HE Project (3 x 47 MW)<br />

Table-7.7 (R)<br />

UNRESTRICTED ENERGY GENERATION IN YEAR 1993-94<br />

PERIOD INFLOW HEAD POWER UNRESTRICTED<br />

ENERGY<br />

CUMEC (M) (MW) (MU)<br />

JUNE I 12.61 723.18 79.729 19.135<br />

II 16.11 723.18 101.859 24.446<br />

III 20.73 723.18 131.069 31.457<br />

JULY I 43.40 723.18 274.405 65.857<br />

II 43.40 723.18 274.405 65.857<br />

III 50.90 723.18 321.825 84.962<br />

AUG I 57.09 723.18 360.962 86.631<br />

II 54.12 723.18 342.184 82.124<br />

III 51.83 723.18 327.705 86.514<br />

SEPT I 54.53 723.18 344.776 82.746<br />

II 45.93 723.18 290.401 69.696<br />

III 43.43 723.18 274.594 65.903<br />

OCT I 38.59 723.18 243.993 58.558<br />

II 28.63 723.18 181.019 43.444<br />

III 24.54 723.18 155.159 40.962<br />

NOV I 20.36 723.18 128.730 30.895<br />

II 17.95 723.18 113.492 27.238<br />

III 16.45 723.18 104.008 24.962<br />

DEC I 16.06 723.18 101.542 24.370<br />

II 14.75 723.18 93.260 22.382<br />

III 12.12 723.18 76.631 20.231<br />

JAN I 11.42 723.18 72.205 17.329<br />

II 10.63 723.18 67.210 16.130<br />

III 10.74 723.18 67.906 17.927<br />

FEB I 10.59 723.18 66.957 16.070<br />

II 10.13 723.18 64.049 15.372<br />

III 10.86 723.18 68.664 13.184<br />

MAR I 10.01 723.18 63.290 15.190<br />

II 9.03 723.18 57.094 13.703<br />

III 11.42 723.18 72.205 19.062<br />

APR I 11.09 723.18 70.119 16.828<br />

II 13.88 723.18 87.759 21.062<br />

III 12.73 723.18 80.488 19.317<br />

MAY I 14.27 723.18 90.225 21.654<br />

II 14.71 723.18 93.007 22.322<br />

III 18.09 723.18 114.377 30.196<br />

ENERGY OBTAINED 1333.717


101<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>HE Project (3 x 47 MW)<br />

Table-7.7 (S)<br />

UNRESTRICTED ENERGY GENERATION IN YEAR 1994-95<br />

PERIOD INFLOW HEAD POWER UNRESTRICTED<br />

ENERGY<br />

CUMEC (M) (MW) (MU)<br />

JUNE I 26.12 723.18 165.149 39.636<br />

II 34.58 723.18 218.639 52.473<br />

III 40.14 723.18 253.793 60.910<br />

JULY I 34.33 723.18 217.058 52.094<br />

II 36.40 723.18 230.146 55.235<br />

III 37.09 723.18 234.509 61.910<br />

AUG I 34.09 723.18 215.541 51.730<br />

II 33.30 723.18 210.546 50.531<br />

III 35.81 723.18 226.416 59.774<br />

SEPT I 30.37 723.18 192.020 46.085<br />

II 30.42 723.18 192.336 46.161<br />

III 26.28 723.18 166.160 39.878<br />

OCT I 20.56 723.18 129.995 31.199<br />

II 18.28 723.18 115.579 27.739<br />

III 16.73 723.18 105.779 27.926<br />

NOV I 13.77 723.18 87.063 20.895<br />

II 11.35 723.18 71.763 17.223<br />

III 9.49 723.18 60.002 14.401<br />

DEC I 9.15 723.18 57.853 13.885<br />

II 8.37 723.18 52.921 12.701<br />

III 7.92 723.18 50.076 13.220<br />

JAN I 7.50 723.18 47.420 11.381<br />

II 7.59 723.18 47.989 11.517<br />

III 7.49 723.18 47.357 12.502<br />

FEB I 7.43 723.18 46.978 11.275<br />

II 7.41 723.18 46.851 11.244<br />

III 7.45 723.18 47.104 9.044<br />

MAR I 6.77 723.18 42.805 10.273<br />

II 6.42 723.18 40.592 9.742<br />

III 8.84 723.18 55.893 14.756<br />

APR I 8.65 723.18 54.691 13.126<br />

II 10.71 723.18 67.716 16.252<br />

III 15.64 723.18 98.887 23.733<br />

MAY I 22.81 723.18 144.221 34.613<br />

II 35.21 723.18 222.622 53.429<br />

III 34.03 723.18 215.161 56.803<br />

ENERGY OBTAINED 1095.294


102<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>HE Project (3 x 47 MW)<br />

Table-7.7 (T)<br />

UNRESTRICTED ENERGY GENERATION IN YEAR 1995-96<br />

PERIOD INFLOW HEAD POWER UNRESTRICTED<br />

ENERGY<br />

CUMEC (M) (MW) (MU)<br />

JUNE I 39.51 723.18 249.810 59.954<br />

II 42.26 723.18 267.197 64.127<br />

III 42.80 723.18 270.611 64.947<br />

JULY I 54.32 723.18 343.449 82.428<br />

II 45.57 723.18 288.125 69.150<br />

III 35.03 723.18 221.484 58.472<br />

AUG I 38.27 723.18 241.969 58.073<br />

II 38.61 723.18 244.119 58.589<br />

III 34.30 723.18 216.868 57.253<br />

SEPT I 30.95 723.18 195.687 46.965<br />

II 27.71 723.18 175.202 42.048<br />

III 26.66 723.18 168.563 40.455<br />

OCT I 19.69 723.18 124.494 29.879<br />

II 19.17 723.18 121.206 29.089<br />

III 14.98 723.18 94.714 25.004<br />

NOV I 9.74 723.18 61.583 14.780<br />

II 11.12 723.18 70.308 16.874<br />

III 11.19 723.18 70.751 16.980<br />

DEC I 8.37 723.18 52.921 12.701<br />

II 7.45 723.18 47.104 11.305<br />

III 6.92 723.18 43.753 11.551<br />

JAN I 5.96 723.18 37.683 9.044<br />

II 5.93 723.18 37.494 8.998<br />

III 6.27 723.18 39.643 10.466<br />

FEB I 6.49 723.18 41.034 9.848<br />

II 5.78 723.18 36.545 8.771<br />

III 6.33 723.18 40.023 8.645<br />

MAR I 6.42 723.18 40.592 9.742<br />

II 7.44 723.18 47.041 11.290<br />

III 7.93 723.18 50.139 13.237<br />

APR I 7.29 723.18 46.092 11.062<br />

II 7.08 723.18 44.765 10.744<br />

III 15.75 723.18 99.582 23.900<br />

MAY I 19.20 723.18 121.396 29.135<br />

II 16.84 723.18 106.474 25.554<br />

III 23.30 723.18 147.319 38.892<br />

ENERGY OBTAINED 1099.951


103<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong>HE Project (3 x 47 MW)<br />

Table-7.7 (U)<br />

UNRESTRICTED ENERGY GENERATION IN YEAR 1996-97<br />

PERIOD INFLOW HEAD POWER UNRESTRICTED<br />

ENERGY<br />

CUMEC (M) (MW) (MU)<br />

JUNE I 21.85 723.18 138.151 33.156<br />

II 18.51 723.18 117.033 28.088<br />

III 33.05 723.18 208.965 50.152<br />

JULY I 36.73 723.18 232.232 55.736<br />

II 39.54 723.18 249.999 60.000<br />

III 35.20 723.18 222.559 58.756<br />

AUG I 33.65 723.18 212.759 51.062<br />

II 31.38 723.18 198.406 47.617<br />

III 31.63 723.18 199.987 52.796<br />

SEPT I 31.57 723.18 199.607 47.906<br />

II 30.13 723.18 190.503 45.721<br />

III 26.20 723.18 165.655 39.757<br />

OCT I 23.04 723.18 145.675 34.962<br />

II 21.11 723.18 133.472 32.033<br />

III 18.87 723.18 119.309 31.498<br />

NOV I 17.17 723.18 108.561 26.055<br />

II 15.96 723.18 100.910 24.218<br />

III 14.20 723.18 89.782 21.548<br />

DEC I 9.68 723.18 61.204 14.689<br />

II 8.77 723.18 55.450 13.308<br />

III 8.02 723.18 50.708 13.387<br />

JAN I 9.20 723.18 58.169 13.961<br />

II 8.75 723.18 55.324 13.278<br />

III 8.90 723.18 56.272 14.856<br />

FEB I 8.88 723.18 56.146 13.475<br />

II 8.85 723.18 55.956 13.429<br />

III 8.75 723.18 55.324 10.622<br />

MAR I 8.95 723.18 56.588 13.581<br />

II 9.40 723.18 59.433 14.264<br />

III 10.25 723.18 64.808 17.109<br />

APR I 9.83 723.18 62.152 14.916<br />

II 9.78 723.18 61.836 14.841<br />

III 10.06 723.18 63.606 15.266<br />

MAY I 11.73 723.18 74.165 17.800<br />

II 13.50 723.18 85.356 20.486<br />

III 13.94 723.18 88.138 23.269<br />

ENERGY OBTAINED 1013.595


Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

CHAPTER – VIII<br />

POWER EVACUATION


8.1 GENERAL<br />

CHAPTER-VIII<br />

POWER EVACUATION<br />

103<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

This chapter contains data regarding existing <strong>Power</strong> network <strong>of</strong> the Eastern region and<br />

the power evacuation arrangement required, consequent upon power generation at the<br />

proposed <strong>Rangyong</strong> Hydro Electric Project.<br />

8.2 APPRAISAL OF EXISTING POWER EVACUATION FACILITIES<br />

The nearest pooling point being proposed is a new 400/220 KV substation at Siliguri<br />

(New Jalpaiguri) where power from Tala H.E.P and Teesta stages is expected to be<br />

pooled. Adjoining to this is also a new substation <strong>of</strong> 220/132 KV level being created by<br />

WBSEB. Hence power evacuation with respect to development <strong>of</strong> national grid and<br />

consumption by the state can be considered as assured for the present project. Underlying<br />

220/132 KV 200 MVA PGCIL and 132 KV network in the entire area is available to<br />

cater for local loads.<br />

8.3 PROPOSED EVACUATION ARRANGEMENT TO THE NEAREST<br />

FACILITY<br />

After study <strong>of</strong> existing power evacuation facilities, it emerges that evacuation <strong>of</strong> power<br />

generated at <strong>Rangyong</strong> Hydro Electric Project can be done through one no. 220 kV<br />

double circuit line to be connected at the pooling point which can be assumed to come up<br />

near Teesta II H.E.P (2 km from Teesta –II H E Project). The length <strong>of</strong> this 220 kV<br />

double circuit line would be approximately 30 km.


Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

CHAPTER – IX<br />

ENVIRONMENTAL ASPECTS


CHAPTER - IX<br />

ENVIRONMENTAL ASPECTS<br />

104<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

9.1 INTRODUCTION<br />

9.1.1 General<br />

The proposed <strong>Rangyong</strong> H. E. Scheme is one <strong>of</strong> the various projects proposed in Teesta<br />

river basin in Sikkim (Fig 9.1). The project envisages construction <strong>of</strong> two dams, i.e. upper<br />

dam to be located immediately downstream to the confluence <strong>of</strong> Umram chu and Passaram<br />

chu in North district <strong>of</strong> Sikkim and lower dam on <strong>Rangyong</strong> chu, upstream to the confluence<br />

<strong>of</strong> Umram chu with <strong>Rangyong</strong> chu (Fig. 9.2). The upper dam is located between longitude<br />

88 o 22’26’’ & 88 o 26’00’’E and latitude 27 o 36’00’’ & 27 o 33’14’’N while the lower dam is<br />

located between longitude 88 o 21’48’’ & 88 o 26’00’’E and latitude 27 o 35’00’’ &<br />

27 o 33’14’’N. The project involves construction <strong>of</strong> 55m high upper dam and diversion <strong>of</strong><br />

water to the lower dam reservoir through a 2 km long link tunnel. The water from the 55m<br />

high lower dam is proposed to be diverted through a 7.5 km long headrace tunnel (Fig. 9.2).<br />

An underground powerhouse is proposed immediately upstream to the reservoir <strong>of</strong> Panan<br />

H.E. Scheme. The proposed project envisages power generation <strong>of</strong> 141 (3 x 47) MW.<br />

9.1.2 Location<br />

Town : Singnok<br />

Revenue Block : Sakyong Pentong<br />

Sub-division : Mangan<br />

District : North Sikkim<br />

State : Sikkim<br />

New Jalpaiguri is the nearest railhead and Bagdogra is the nearest airport.


9.2 PHYSICAL ENVIRONMENT<br />

9.2.1 Climate/Meteorology<br />

105<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

For most <strong>of</strong> the period in the year, the climate is cold and humid. The region experiences<br />

a cold winter from November to February and monsoons from May to mid- October. The<br />

rainfall in the project area varies from 300-360 cm in most parts <strong>of</strong> valley. Snowfall is<br />

seen at higher altitudes <strong>of</strong> the catchment area from November to April. The area enjoys<br />

sub tropical to alpine conditions. Temperature varies with altitude and slope. Fog is a<br />

common feature in the area especially from September to February.<br />

9.2.2 Topography<br />

Sikkim encompasses the Lesser Himalaya, Central Himalaya, and the Tethys Himalaya.<br />

It is essentially a mountainous State without flat piece <strong>of</strong> land <strong>of</strong> any extent anywhere.<br />

The mountains rise in elevation northward. The northern portion <strong>of</strong> the State is deeply cut<br />

into steep escarpments. South Sikkim is lower, more open, and fairly well cultivated.<br />

This configuration <strong>of</strong> the State is partly due to the direction <strong>of</strong> the main drainage, which<br />

is towards the south. The trend <strong>of</strong> the mountain system is generally in east-west direction.<br />

The Rangit and the Teesta, which form the main channels <strong>of</strong> drainage, run nearly north<br />

south. The valleys cut by these rivers and their feeders are very deep and are rather open<br />

towards the top, but usually attain a steep gorge like structure as they approach the bed <strong>of</strong><br />

the rivers.<br />

9.2.3 Soils<br />

The soil depth varies from 100- 150 cm deep in most areas. There are also certain rock<br />

outcrops in the soil. The soil is mainly coarse to fine loam in texture. Some soils have a<br />

gray tint <strong>of</strong> color and rich in humus in most places. The State <strong>of</strong> Sikkim enjoys a wide<br />

range <strong>of</strong> climate, physiography, geology and vegetation which have further influenced<br />

formation <strong>of</strong> different kinds <strong>of</strong> soils that are classified under 5 broad physiographic units.<br />

Table 9.1 gives area wise details <strong>of</strong> these soils. The light textured soil and rocky areas are<br />

prone to sliding. Topsoil in most area is rich in humus and organic matter. The water


106<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

holding capacity in most area is low and has low cohesiveness. The soil in general is<br />

loamy sand to silty clay loam with a depth <strong>of</strong> 30 cm to 100 cm and in some cases even<br />

more than 120 cm. Based on the soil survey conducted by the National Bureau <strong>of</strong> Soil<br />

Survey <strong>of</strong> India & Landuse Planning; the State has been classified into 3 main soil<br />

groups:<br />

Udalf: High base status soil <strong>of</strong> humid region.<br />

Orthants: Recently formed soil.<br />

Odhepts: Shallow blocks, brown and alluvial soil.<br />

No<br />

.<br />

Table 9.1: Major physiographic units <strong>of</strong> soil in Sikkim<br />

Physiographic units Area (ha) % <strong>of</strong> total geographic<br />

area<br />

1 Summit & Ridge (>30%) 31459.45 4.43<br />

2<br />

2.1<br />

2.2<br />

2.3<br />

2.4<br />

Slide slope <strong>of</strong> hills<br />

Very steep slope (>50%)<br />

Escarpments (>50%)<br />

Steeply sloping (30-50%)<br />

Moderately sloping (15-30%)<br />

213100.01<br />

30480.73<br />

214641.28<br />

16024.82<br />

30.03<br />

4.3<br />

30.24<br />

2.26<br />

3 Valleys (


9.2.4 Geomorphology and Geology<br />

The stratigraphic sequence <strong>of</strong> the proposed project site is given below:<br />

GROUP LITHOLOGY<br />

107<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Gondwana Grits, pebble cum boulder beds and carbonaceous<br />

shales with occasional coal seam, pegmatite and<br />

quartzite (tourmaline bearing)<br />

Daling Inter-bedded quartzite and chlorite sericite<br />

phyllite/schist<br />

Lingza granite.<br />

Quartzite/Biotite schist.<br />

Chungthang Interbedded quartzite and garnetiferous quartz biotite<br />

Central Crystalline<br />

Gneissic complex<br />

(CCGC)<br />

schist.<br />

Calc-silicate rock/marble.<br />

Garnet-kyanite-silimanite-biotite-quartz-schist<br />

Banded gneiss with augen gneiss and quartz-biotite<br />

gneiss.<br />

Augen gneiss<br />

The area falls within axial belt <strong>of</strong> Central Crystalline Zone <strong>of</strong> the North Sikkim<br />

Himalayas where the rock types are mainly high grade gneisses (CCGC) having inter-<br />

bands <strong>of</strong> meta-sedimentaries represented by calc-silicate/quartzite, high-grade schist and<br />

their fine inter laminations. The meta-sedimentaies occur as enclaves in the high-grade<br />

gneisses in the area around the proposed project. Discordant tourmaline bearing quartz<br />

veins and pegmatite <strong>of</strong>ten intrudes all these rock types.<br />

9.2.5 Seismicity<br />

Sikkim is a part <strong>of</strong> active Himalayan belt, which is tectonically young. The area has<br />

experienced mild tremors in the recent past. One earthquake <strong>of</strong> magnitude 6.0 on Richter


108<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

scale was recorded on November 20 th , 1980. The project area falls in Zone IV <strong>of</strong> Seismic<br />

Zoning Map <strong>of</strong> India as per IS 1893 - 1984.<br />

9.2.6 Catchment Area<br />

The catchment area <strong>of</strong> the upper dam is 146 sq km while that <strong>of</strong> the lower dam is 127 sq<br />

km. The catchment is mountainous with rugged terrain. The tributaries are angular and<br />

have dendritic drainage patterns. Streams have moderate to steep slopes in upper reaches.<br />

The natural vegetation consists <strong>of</strong> shrubby to alpine in many places at upper reaches and<br />

mixed forest at lower elevations.<br />

9.2.7 River System<br />

<strong>Rangyong</strong> chu originates from Tingchen glacier and drains the slopes <strong>of</strong> Narsingh peak. It<br />

is joined by Rukel Chu on its left bank. Rukel Chu originates from Tongshiong and Talung<br />

glaciers at the base <strong>of</strong> South Kanchendzonga peak (8,476 m). Along its course Rukel Chu<br />

also receives drainage from South Simvo glacier on its left bank (Fig 9.3). Most <strong>of</strong> the<br />

Rukel Chu catchment is predominantly glaciated with a number <strong>of</strong> high peaks like South<br />

Kachendzonga peak, Talung (7,349m), Kabru Dome (6,545m) and a number <strong>of</strong> peaks<br />

above 7,000m marking the western boundary, Simvo (6,811m) lies on the northern<br />

boundary, while Gocha peak (6,115m), Pandim (6,691m) and Narsingh (5,825m) form the<br />

southern boundary. The catchment area up to upper dam site is 146 sq km and <strong>of</strong> lower<br />

dam is 127 sq km. Total length <strong>of</strong> Umram Chu from its origin up to the upper dam site is<br />

about 11 km and total length <strong>of</strong> <strong>Rangyong</strong> Chu from its origin up to the lower dam site is<br />

about 12 km.<br />

9.2.8 Submergence<br />

The project envisages construction <strong>of</strong> two dams each 55m high from the river bed level.<br />

The reservoir <strong>of</strong> upper dam would result in inundation <strong>of</strong> 15.62 ha <strong>of</strong> land whereas the<br />

lower dam reservoir is likely to submerge only 2.5 ha <strong>of</strong> land. Therefore, <strong>Rangyong</strong> H.E.<br />

project would inundate 18.12 ha <strong>of</strong> land. The spread <strong>of</strong> the two reservoirs is indicated in


109<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Figure 9.8. The predominant landuse in the submergence area <strong>of</strong> upper dam is alpine<br />

open scrub forest (63%) and dense mixed forest (34%) and the rest <strong>of</strong> the area is<br />

characterized by rockyland. The area likely to be submerged by the lower dam reservoir<br />

is comprised only <strong>of</strong> dense mixed forests (89%) and alpine scrub (11%). The proposed<br />

project, however, does not involve inundation <strong>of</strong> any village or human habitation.<br />

9.2.9 Landuse pattern<br />

The landuse/landcover pattern within the 7 km radius <strong>of</strong> the proposed <strong>Rangyong</strong> H.E.<br />

project was interpreted and generated from LISS-III scene <strong>of</strong> Path/Row 107/051 <strong>of</strong> 19th<br />

January, 2000 and PAN D scene <strong>of</strong> Path/Row 107/051 <strong>of</strong> 13th January, 2002. LISS and<br />

Pan scenes <strong>of</strong> area covering 7 km radius <strong>of</strong> the project site are given in Figures 9.4 &<br />

9.5. The first level classified landuse/landcover map generated from these two scenes<br />

coupled with ground truthing is given in Figure 9.6. Area covered by various<br />

landuse/lancover categories is given in Table 9.1 and the percent representation <strong>of</strong> each<br />

<strong>of</strong> the landuse/landcover type is shown in Figure 9.7. From the studies it is clear that the<br />

vegetation <strong>of</strong> the area concerned is typically that <strong>of</strong> high altitude Himalayan region. The<br />

predominant landuse <strong>of</strong> the area is a mixture <strong>of</strong> forests, alpine scrub, rockfalls, rockyland,<br />

snow and ice cover. The dense mixed forests, which occupy the lower altitudes <strong>of</strong> the<br />

catchment along river slopes constitute about 47% <strong>of</strong> the land area while alpine open<br />

scrubs constitute 29% <strong>of</strong> the total land area. Rockylands and rockfall areas in the<br />

catchment constitute the important landuse/landcover <strong>of</strong> the area covering about 1890 ha<br />

(10%) <strong>of</strong> the land. Similarly, large areas in the catchment are either under permanent ice<br />

cover/glaciers (5%) or snow cover (8%). In addition a small part <strong>of</strong> the catchment is<br />

under settlements/ agriculture which constitutes about 1% <strong>of</strong> the land area. These sparse<br />

human habitation sites and managed ecosystems like agricultural fields, etc. are restricted<br />

to areas downstream <strong>of</strong> the proposed power house site. These areas are around Lingza,<br />

Nung, Namprik and Lingdem on the two banks <strong>of</strong> the <strong>Rangyong</strong> Chhu. Majority <strong>of</strong> the<br />

area is covered by natural ecosystems and the landscape conditions in the area are also<br />

quite natural without any human disturbance. The dense forests are present along the


110<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Passaram Chhu and Umram Chhu in the north and northwest, respectively. The western<br />

forests are represented by Sakkyong Reserve Forest mostly along right bank <strong>of</strong> <strong>Rangyong</strong><br />

Chhu. The forests in the north and northeast and northwest are represented by Tolung<br />

Reserve Forest. In the southern part these forests are represented by Lingdem Reserve<br />

Forest. These forests are mostly broad-leaf forests with occasional representation <strong>of</strong><br />

bamboo in them, particularly in the warmer areas. The areas above these dense mixed<br />

forests are represented by alpine/open scrub type <strong>of</strong> vegetation.<br />

Table 9.2. Area (ha) under different landuse/landcover categories in 7 km radius <strong>of</strong><br />

<strong>Rangyong</strong> H.E. Project<br />

Landuse/landcover Area (ha)<br />

Dense Mixed Forest 9443.86<br />

Open Scrub 5768.01<br />

Rockyland 1541.61<br />

Rockfalls 348.48<br />

Cultivation/settlements 43.32<br />

Ice/Glacier 917.51<br />

Snow 1627.89


8%<br />

1%<br />

2%<br />

29%<br />

5%<br />

8%<br />

Dense Mixed Forest Open Scrub Rockyland Rockfalls<br />

Cultivation/Settlements Ice/Glacier Snow<br />

111<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Figure 9.7: Percent area under various landuse/landcover categories in 7 km radius<br />

<strong>of</strong> the proposed <strong>Rangyong</strong> H.E. Project<br />

9.3. BIOTIC ENVIRONMENT<br />

Sikkim stretches from the low lands in the south with tropical climate to the mountainous<br />

regions in the north. The altitude varies right from sea level to mountain peaks covering a<br />

wide spectrum <strong>of</strong> flora and fauna. Nowhere in the world in such a small area can one find<br />

flora and fauna <strong>of</strong> all varieties - Tropical to the Alpines. Sikkim's botanical and<br />

zoological richness is awe- inspiring, boasting <strong>of</strong> more than 4500 species <strong>of</strong> flowering<br />

plants. 30% <strong>of</strong> all the birds in the country are found in Sikkim.<br />

9.3.1 Flora<br />

The two dam sites are located in temperate and alpine montane terrain and the area <strong>of</strong> in<br />

the vicinity <strong>of</strong> the project is comprised <strong>of</strong> dense mixed forests along the river course and<br />

alpine and open scrub higher up on the slopes. This area experiences cool and humid<br />

47%


112<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

summers and severe cold winters. Owing to good moisture conditions and cool<br />

temperatures throughout the year at these altitudes the vegetation is constituted mostly by<br />

the cold temperate evergreen plant species. The forests are mostly confined to lower<br />

slopes in the river valley and are represented by all the physiognomic forms – trees,<br />

shrubs and herbs. The woody elements in these mixed forests are represented by Alnus<br />

nepalensis, Engelhardtia spicata, Litsea doshia, Neolitsea sp., Prunus cerasoides and<br />

Quercus lineata. In addition Euonymous pendulus, Lyonia ovalifolia, Macaranga<br />

denticulata and Rhamnus virgatus are commonly met with in these riverine dense forests.<br />

A few patches <strong>of</strong> bamboo were also seen interspersed within these forests. In the higher<br />

slopes where scrub vegetation dominates species <strong>of</strong> Rhododendron, Salix, Viburnum and<br />

several members <strong>of</strong> Rosaceae and Ericaceae are seen growing predominantly in the<br />

region. The alpine meadows harbour several species <strong>of</strong> Primulaceae, Gentianaceae,<br />

Papavaraceae, Brassicaceae, Poaceae and Juncaceae. The catchment area harbour some<br />

<strong>of</strong> the important endemic and endangered medicinal plant species <strong>of</strong> Himalaya. Among<br />

these species Artemisia vulgaris, Podophyllum hexandrum, Aconitum spp., Saussurea<br />

spp., Nardostachys jatamansi, Picrorrhiza kurroa and Meconopsis spp. are noteworthy.<br />

9.3.2 Fauna and Wildlife<br />

As the area represents a rich diversity <strong>of</strong> wildlife it forms a part <strong>of</strong> Kanchendzonga<br />

National Park. The upper parts <strong>of</strong> catchments <strong>of</strong> Ringpi Chhu and Tolung (<strong>Rangyong</strong>)<br />

Chhu harbour several faunal species like Himalayan brown bear (Selenarctos thibetanus),<br />

Great Tibetan sheep, Snow leopard (Panthera uncia), Bharal, Himalayan tahr<br />

(Hemitragus jemlahicus), Hoary-bellied squirrel (Callossciurus pygerithrus), Orange-<br />

bellied squirrel (Dremomys lokhriah), Assamese macaque (Macaca assamensis),<br />

Himalayan palm civet (Paguma larvata), Stone marten (Martes foina) and jackals (Canis<br />

aureus). Some <strong>of</strong> these animals are generally found in the vicinity <strong>of</strong> agricultural crops<br />

particularly in southern parts <strong>of</strong> the catchment. In addition there are also species like<br />

Civets (Viverra zibetha), porcupines (Hystrix brachyura), Grey musk shrew (Suncus


113<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

murinus), the house mouse (Mus musculus) and Bandicoot rat (Bandicota bengalensis).<br />

The upper reaches, i.e. the alpine areas <strong>of</strong> the catchment harbour mammalian species,<br />

which include Nayan, Bharal, Snow leopard, bear, Himalayan tahr, Barking Deer,<br />

Himalayan marmot and pikas. These animals however are not known to come down to<br />

lower altitudes i.e. 2,200 m or below. The avifauna <strong>of</strong> the catchments is represented by<br />

bird species like bulbuls, thrushes, eagles, partridges, pigeons, doves, koels, owls,<br />

kingfishers, nightjars, woodpeckers, orioles, drongos, mynas, flycatchers, babblers,<br />

robins, etc. The invertebrates are represented by many species <strong>of</strong> butterflies and<br />

dragonflies in the surrounding area.<br />

Among the various faunal species present in the catchment Panthera uncia, P. pardus,<br />

Ne<strong>of</strong>elis nebulosa, Felis bengalensis, Macaca assemensis and Cervus duvaucelli are<br />

Scheduled as threatened animals <strong>of</strong> India while Panthera tigris, Selenarctos thibetanus<br />

and Cervus duvaucelli are considered as globally threatened species.<br />

9.3.3 Aquatic life<br />

The rivers in Sikkim harbour a variety <strong>of</strong> fish species. Ichthy<strong>of</strong>auna in the river<br />

comprised mainly <strong>of</strong> Balm, Asala, Chepti, Gadela, etc. Snow trouts and other minor<br />

trouts are found at higher elevations. Some <strong>of</strong> the identified fish species found in the area<br />

are Schizothorax richardsonii, Salmo trutta fario, Labeo pangusia, Noemacheilus<br />

kanjupkhulens, Bagarius bagarius, etc.<br />

9.4. EXISTENCE OF ANY PROTECTED AREA/ARCHAEOLOGICAL SITES<br />

The proposed project area lies entirely within the boundary <strong>of</strong> Kachendzonga National<br />

Park. However, except the National Park there are no sites or monuments <strong>of</strong><br />

archaeological or national importance, which would be affected by the project activities<br />

directly or indirectly.


9.5 PREDICTION OF ENVIRONMENTAL IMPACTS<br />

9.5.1. Impacts on Land Environment<br />

114<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Sufficient amount <strong>of</strong> land will be required for construction <strong>of</strong> the proposed dam,<br />

powerhouse, colonies & approach roads etc. The reservoir <strong>of</strong> upper dam would result in<br />

inundation <strong>of</strong> 15.62 ha <strong>of</strong> land whereas the lower dam reservoir is likely to submerge<br />

only 2.5 ha <strong>of</strong> land. Therefore, <strong>Rangyong</strong> H.E. project would inundate 18.12 ha <strong>of</strong> land.<br />

All these activities would mean some disturbance and change in the landscape. There<br />

will be changes in the Landuse <strong>of</strong> the area and in its physical composition.<br />

9.5.2 Impacts on Water Environment<br />

The construction <strong>of</strong> a reservoir replaces the river eco-system by a lacustrine ecosystem.<br />

The vector <strong>of</strong> various diseases breeds in shallow areas not very far from reservoir<br />

margins. The breeding site for mosquitoes and other vectors in impounded water is in<br />

direct proportion to the length <strong>of</strong> the shoreline. The construction <strong>of</strong> the reservoir would<br />

increase the shoreline many times as compared to the pre-project shoreline <strong>of</strong> various<br />

rivers and tributaries under submergence. Thus the construction <strong>of</strong> the proposed<br />

reservoir may enhance the potential breeding sites for various disease vectors.<br />

9.5.3 Impacts on Air Environment<br />

The construction <strong>of</strong> the proposed dam would increase dust generation in the area and<br />

some vehicular pollution. However, these would only be limited to the construction<br />

period.<br />

9.5.4 Impacts on Flora/Fauna<br />

9.5.4.1 Impacts on terrestrial flora<br />

About 18.12 ha <strong>of</strong> land will be inundated due to construction <strong>of</strong> the proposed dam. The<br />

direct impact <strong>of</strong> construction activity <strong>of</strong> a water resources project in a hilly terrain is<br />

generally limited to the vicinity <strong>of</strong> the construction sites. A large number <strong>of</strong> labourers<br />

and technical staff and other groups <strong>of</strong> people are likely to aggregate in the area during


115<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

construction phase. In this area majority <strong>of</strong> forest dwelling rural community depends on<br />

forest for food, fodder and timber. Submergence <strong>of</strong> forest area in primary impact zone<br />

may reduce the availability <strong>of</strong> resources for the local people. This would also result in<br />

significant changes at the structural resource level in forest. The acquisition <strong>of</strong> land for<br />

various project activities would also lead to cutting <strong>of</strong> vegetation on these lands.<br />

9.5.4.2 Impacts on terrestrial fauna<br />

During the construction phase, a large number <strong>of</strong> machinery and construction labour will<br />

have to be mobilized. This activity may cause some disturbance to the wildlife<br />

population. The operation <strong>of</strong> various construction equipments is likely to generate<br />

significant noise. Likewise blasting too is likely to generate noise level and vibration<br />

intermittently. The noise may scare the fauna in the region and force them to migrate to<br />

other areas. There might be some impacts due to increased human interference.<br />

9.5.4.3 Impacts on avi-fauna<br />

The construction <strong>of</strong> the proposed dam will lead to formation <strong>of</strong> a reservoir, which will<br />

have a fluctuation in the water level, which precisely means the reservoir bank will<br />

remain wet throughout the year. Due to such reasons grasses may grow along the<br />

reservoir banks. Such conditions are generally ideal for various kinds <strong>of</strong> birds, especially<br />

water birds. However, because <strong>of</strong> the presence <strong>of</strong> a good habitat, it is quite likely that<br />

water birds will flock in this area in a large number. The birds from cold climatic areas<br />

could also use this area during the winter season.<br />

9.5.4.4 Impacts on aquatic ecology<br />

The major physical change upstream <strong>of</strong> the proposed dam will be formation <strong>of</strong> a<br />

lacustrine habitat from a riverine habitat. Whereas below the damsite, there will be<br />

regulated water or very little water in river course. As such there will be some changes in<br />

the aquatic environment in this stretch. For this the water quality analysis shall be<br />

conducted regularly. Moreover, some migratory fish species may get affected due to


116<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

construction <strong>of</strong> the dam. Also some fish species, which are riverine and are not<br />

accustomed to deep lake environment, may also get replaced.<br />

9.5.5 Impacts on Socio-Economic Environment<br />

Since the submergence area is small and is confined to the river valley, no village will be<br />

submerged. Thus displacement is not anticipated. At present, there are small business<br />

and little employment facilities in the project area. However, with the construction <strong>of</strong> the<br />

project new business and employment opportunities will open up for the local people<br />

which are likely to improve the economic conditions <strong>of</strong> the local people. Further, there<br />

will be development <strong>of</strong> infrastructure facilities as housing, water supply, medical<br />

facilities, schools, transportation and communications. These factors are expected to<br />

bring about positive impact on the socio-economic status <strong>of</strong> the people living in the<br />

project area. There is possibility <strong>of</strong> changes in lifestyle and cultural values <strong>of</strong> local<br />

people due to migrant worker population. However, the impact is expected to be low as<br />

the number <strong>of</strong> immigrant people will be small for the small project and most <strong>of</strong> the<br />

labourers employed in the project will be local people.<br />

As a part <strong>of</strong> the Environmental Impact Assessment Study, a detailed socio-economic<br />

survey would be carried out to determine the following:<br />

Information on various aspects <strong>of</strong> the affected population viz;<br />

demographic details, socio-economic and cultural characteristics,<br />

enumeration <strong>of</strong> personal properties <strong>of</strong> the affected population, education<br />

level and occupational pr<strong>of</strong>ile etc.<br />

Enumeration <strong>of</strong> social infrastructure and community property resources in<br />

the submergence area.<br />

Ethnographic assessment <strong>of</strong> PAFs.


9.6 ENVIRONMENTAL MANAGEMENT PLANS<br />

117<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

The objective <strong>of</strong> the Environmental Management Plan (EMP) is to ameliorate the<br />

negative impacts <strong>of</strong> a developmental project. The most reliable way to ensure proper<br />

implementation <strong>of</strong> these management plans is to integrate the same with various<br />

processes involved during project planning, designing, construction and operation phases.<br />

Based on the assessment <strong>of</strong> environmental impacts, following management plans will be<br />

formulated:<br />

Catchment Area Treatment<br />

Compensatory Afforestation<br />

Wildlife Conservation<br />

Resettlement and Rehabilitation<br />

Public Health Management System<br />

Muck Disposal<br />

Fishery Management<br />

Restoration <strong>of</strong> Construction Area<br />

Green Belt Development<br />

Free Fuel Provision<br />

Disaster Management


Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

CHAPTER – X<br />

INFRASTRUCTURE


CHAPTER – X<br />

INFRASTRUCTURE<br />

10.1 EXISTING ACCESS AND INFRASTRUCTURE FACILITIES<br />

10.1.1 Road Communication<br />

125<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

The upper dam site is located just downstream <strong>of</strong> the confluence <strong>of</strong> Passaram Chu and<br />

Umram Chu and lower dam site is on river <strong>Rangyong</strong> Chu nearby the place Singnok. The<br />

lower dam site is presently not approachable, while the upper dam site is approachable by<br />

a diffcult path via Phontang from road head at Lingza. The <strong>Power</strong> house is located on the<br />

right bank <strong>of</strong> <strong>Rangyong</strong> Chu just upstream <strong>of</strong> confluence <strong>of</strong> Ringyong Chu and<br />

<strong>Rangyong</strong> Chu. The nearest road end is at Lingza/Lingdem which is 15Km from<br />

Mangan, the head quater <strong>of</strong> North Sikkim District <strong>of</strong> Sikkim, about 60 Km from Singtam<br />

(NH31A), about 160 Km from NJP railway station and about 161 Km from Bagdogra<br />

airport. The Lingza/Lingdem village is connected form Mangan by a PWD road. The<br />

Siliguri-Gangtok (NH-31A) and Singtam-Mangan-Sanklan state highways are being<br />

maintained by BRO.<br />

10.1.2 Housing And Community Facilities<br />

Singnok is the name <strong>of</strong> the place near the Dam sites where even basic facilities <strong>of</strong> health<br />

care, schooling, market, postal and telephone etc. are not available. It is therefore<br />

necessary to plan housing, <strong>of</strong>fice, recreation, store etc. for meeting the requirement <strong>of</strong> the<br />

project.<br />

10.1.3 <strong>Power</strong> Availability<br />

Sikkim, at present, is dependent mainly its mini and micro hydel power stations for<br />

meeting its power demand. The total installed capacity <strong>of</strong> state at present is about 95<br />

MW. The state gets some share <strong>of</strong> power from Chukha Hydel Electric Project in Bhutan,<br />

Farakka Thermal <strong>Power</strong> Station, West Bengal and Rangit Hydel <strong>Power</strong> Project <strong>of</strong> NHPC<br />

Ltd. Teesta (V) HE Project, 510 MW being executed by NHPC in central sector is also


126<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

under advance stage <strong>of</strong> construction. The existing transmission system <strong>of</strong> this state<br />

comprises <strong>of</strong> mainly 66 KV and 11 KV transmission lines. A 132 KV S/C transmission<br />

line is being constructed from Melli border town <strong>of</strong> Sikkim-West Bengal to Ranipool. A<br />

132 KV sub station is being constructed at Melli. A substation <strong>of</strong> 2.5MVA, 66/11KV is<br />

located at Phodong near Mangan. Therefore , the necessary construction power shall be<br />

available for the execution <strong>of</strong> <strong>Rangyong</strong> H.E. Project from some where nearby Mangan<br />

but the exact location may be decided at the time <strong>of</strong> FR/DPR.<br />

10.2 PROPOSED ACCESS AND INFRASTRUCTURE FACILITIES<br />

Keeping in view the available infrastructure facilities <strong>of</strong> communication,, housing and<br />

power, the requirement <strong>of</strong> the same for <strong>Rangyong</strong> H.E. Project has been worked out.<br />

10.2.1 Improvement Of Existing Road And Bridges<br />

The <strong>Power</strong>house is located on just u/s <strong>of</strong> confluence <strong>of</strong> <strong>Rangyong</strong> Chu and Ringyong<br />

Chu. The approach roads from Mangan are available upto Lingza/ Lingdem. Further the<br />

power house and upper dam site are approachable by a difficult footpath. While there is<br />

no approach is available to lower dam site. Since the <strong>Rangyong</strong> H.E. Project is on u/s <strong>of</strong><br />

the Panan project, therefore it has been presumed that all the roads and bridges shall be<br />

ready upto dam site <strong>of</strong> Panan H.E. Project.<br />

10.2.2 Construction Of Roads & Bridges<br />

The power house shall be approached from Mangan – Lingza road from right bank for<br />

which a new project roads shall be constructed from the dam site <strong>of</strong> Panan H.E. Project.<br />

The Dam sites shall be approached from powerhouse on right bank and bridges across the<br />

rivers Pokharam Chu and <strong>Rangyong</strong> Chu are proposed.<br />

10.2.3 Accommodation For Residential Purpose<br />

To accommodate the project employees and contractors, land would be required for<br />

construction <strong>of</strong> suitable residential complexes. The residential colony has been proposed


127<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

at Sakkyong. The project colony would have accommodation for all categories <strong>of</strong><br />

<strong>of</strong>ficials deployed for the construction. The strength <strong>of</strong> the <strong>of</strong>ficials and staff <strong>of</strong> various<br />

categories required for the project has been worked out. Each personal would be provided<br />

with the accommodation as per the entitlement. Keeping in view the construction period<br />

and subsequent operation and maintenance <strong>of</strong> the project, it is proposed to construct<br />

about 50% <strong>of</strong> the buildings as the permanent and the remaining as temporary. This<br />

conclusion has been drawn on the basis that 50% <strong>of</strong> the staff strength would be required<br />

for maintenance and operation after the completion <strong>of</strong> the project.<br />

Requirement <strong>of</strong> built up accommodation has been worked out to 4138Sq.m <strong>of</strong> permanent<br />

built up area and 4514 Sq.m <strong>of</strong> temporary builtup area would be required. Total plinth<br />

area for residential accommodation worked out to be 8648Sq.m,<br />

10.2.4 Accommodation For Non-Residential Purposes<br />

The <strong>of</strong>fice complexes are proposed to be located at Sakkyong. Workshops, laboratories,<br />

stores, water supply, fire stations, electrical substations etc would be accommodated in<br />

the project area. One stockyard is proposed at railhead near new Jalpaiguri Railway<br />

station where construction materials like cement, steel and machinery and equipments<br />

would be store for further transportation to the project site, Batching and mixing plants<br />

are to be commissioned, one near dam site and the other near power house site.<br />

Accommodation required for non residential purposes have been worked out to be<br />

9630Sq.m <strong>of</strong> which about 50% would be permanent and rest will be temporary.<br />

10.3 TELECOMMUNICATION FACILITIES<br />

The different work sites <strong>of</strong> the project, <strong>of</strong>fices, stores, laboratories, workshop and<br />

residences would be connected through a telecommunication network. The<br />

telecommunication facilities would also be provided between the projects and outside.<br />

Therefore, an internal telephone exchange would be provided at the project for


128<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

communication within and outside the project. Most parts <strong>of</strong> Sikkim are presently<br />

connected with different parts <strong>of</strong> the world through satellite telecommunication network<br />

for which an earth satellite station with electronic exchange exists. The same network<br />

would be extended to the project area for telecommunication with outstation agencies.<br />

10.4 CONSTRUCTION POWER<br />

The construction power for the project shall be available at the time <strong>of</strong> construction <strong>of</strong> the<br />

project and it is presumed that till that time some mega projects in the d/s i.e. Teesta<br />

(V), Teesta(III) and Teesta(IV) would have been commissioned and a transmission line<br />

<strong>of</strong> about 10Km may be required for arranging construction power.


Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

CHAPTER – XI<br />

CONSRUCTION PLANNING &<br />

SCHEDULE


11.1 INTRODUCTION<br />

CHAPTER –XI<br />

CONSTRUCTION PLANNING & SCHEDULE<br />

129<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

The Equipment Planning & Construction Methodology <strong>of</strong> <strong>Rangyong</strong> H.E. Project (3x47<br />

MW) in Teesta Basin Sikkim has been developed on following consideration.<br />

1. The project construction period has been considered as four years after<br />

completion <strong>of</strong> Stage I & II activities.<br />

2. Available Geological Data at PFR stage.<br />

3. Requirement <strong>of</strong> Construction Equipment has been planned to handle the quantities<br />

worked out on the basis <strong>of</strong> preliminary layout.<br />

4. Five months (May to September) rainy season has been considered while<br />

planning surface works.<br />

11.2 CONSTRUCTION METHODOLOGY:<br />

11.2.1 Infrastructure Works:<br />

The main infrastructure development is proposed to be carried out in period <strong>of</strong> 12<br />

months. During infrastructure period Land Acquisition, construction <strong>of</strong> approach roads,<br />

bridges& culverts, arrangement <strong>of</strong> construction power will be undertaken. Critical<br />

component <strong>of</strong> project would be started from 5 th month after construction <strong>of</strong> approach<br />

roads. Platform to accommodate batching plant, stores for construction material, site<br />

workshop, <strong>of</strong>fices and other buildings (residential/ non residential) colonies will also be<br />

developed in infrastructure period. Crawler Dozer, Loader cum Excavator, Air<br />

compressor, Road Roller etc. are proposed for deployment during infrastructure stage.<br />

11.2.2 Diversion <strong>of</strong> River<br />

The construction <strong>of</strong> two diversion tunnels 3.3 m finished dia., Horse shoe shaped 300 m<br />

long each, for both Dams would be carried out by full face method. Excavation <strong>of</strong>


130<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Diversion Tunnel will be carried out by deploying separate set <strong>of</strong> equipment i.e single<br />

Boom drill jumbo, Jack hammers, 1.0 cum Conway mucker & 10 T Tippers.. Excavation<br />

& concreting <strong>of</strong> both diversion tunnel would be completed in 9 months. The concreting<br />

equipment proposed are two set <strong>of</strong> 38 cum Concrete pump, Transit mixer, shotcrete<br />

machine, Grout pump, shutters etc. Concreting requirement would be catered by the same<br />

batching & mixing Plant and Aggregate processing Plant, being proposed for each Dam .<br />

U/s & D/s C<strong>of</strong>fer dam would be constructed immediately after construction <strong>of</strong> diversion<br />

tunnel in 3 months to divert the river. River bed excavation would be taken up after<br />

completion <strong>of</strong> c<strong>of</strong>fer dam.<br />

11.2.3 Upper Concrete Dam<br />

Dam abutment stripping is proposed to be carried out in 13 months. The excavation <strong>of</strong><br />

river bed & foundation treatment would be carried out in 3 months. Excavated material<br />

will be handled by 1.0 cum Hyd. Excavator and 10T Tippers/20 T Dumpers. Concreting<br />

<strong>of</strong> Dam & HM work would be carried out in further 23 months. Concreting would be<br />

done by deploying 2 nos. Travelling Tower cranes (4.5 T at 60 m radius), 1 No. 120<br />

cum/hr Batching& Mixing plant and 250TPH Aggregate Processing plant.<br />

11.2.4 Lower Concrete Dam<br />

Dam abutment stripping <strong>of</strong> lower Dam is proposed to be carried out in 13 months.<br />

Thereafter excavation <strong>of</strong> river bed & foundation treatment would be carried out in 4<br />

months. Excavated material will be handled by 1.0 cum Hyd. Excavator and 10T<br />

Tippers/20 T Dumpers. Concreting <strong>of</strong> Dam & HM work would be carried out in further<br />

22 months. Concreting would be done by deploying 2 nos. Travelling Tower crane (4.5<br />

T at 60 m radius), 1 No. 120 cum/hr Batching& Mixing plant and 250TPH Aggregate<br />

Processing plant.


11.2.5 Link Tunnel<br />

131<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Initially construction <strong>of</strong> approaches for link tunnel would be carried out in four months.<br />

Thereafter excavation <strong>of</strong> 3.3m dia 2.0 km long link tunnel would be carried out in the<br />

same way as diversion tunnels in 20 months. Concreting & HM works <strong>of</strong> tunnel would be<br />

carried in further 15 months. Concreting would be carried out by deploying concrete<br />

pump, Transit Mixer etc.<br />

11.2.6 Intake Structure, Desilting Chamber , Silt Flushing tunnel & HRT<br />

Initially excavation <strong>of</strong> adits & approaches would be carried out in 4 months.<br />

Thereafter,2 Nos. Intake structure having gate size <strong>of</strong> 3 m x3m, 2 Nos. Dufour type<br />

Desilting chambers <strong>of</strong> size 175m X10mX12m each and HRT <strong>of</strong> 3.3 m dia. would be<br />

excavated in 24 months . After excavation <strong>of</strong> intake structure, 2 nos. intake tunnel 3m<br />

dia. each would be excavated by full face method. Excavation <strong>of</strong> Desilting Chamber<br />

would be taken up from intake tunnel. Intake tunnel would be extended upto full length<br />

<strong>of</strong> Desilting Chamber. Thereafter it will be expanded side wise to the full width <strong>of</strong><br />

desilting chamber resulting in desilting chamber dome. Mucking <strong>of</strong> excavated material<br />

would be done through the tunnel. After the excavation <strong>of</strong> desilting chamber, concreting<br />

will be carried out. Excavation <strong>of</strong> silt flushing tunnel & gate operation chamber would be<br />

a parallel activity. The equipment to be deployed are Jack hammers, wagon drills, air<br />

compressors, skid steer loader, tippers, concrete pump, transit mixers etc.<br />

Excavation <strong>of</strong> 7.5 km long, 3.3 m finished diameter horse shoe shaped Head Race Tunnel<br />

is proposed by full face drilling & blasting method. It will be excavated through 3 nos<br />

adits. Excavation would be carried out by deploying three set <strong>of</strong> equipment i.e single<br />

boom drill jumbo, 1.0 cum Conway mucker and 10 T tipper. Concreting will be carried<br />

out by deploying concreting equipment i.e. Concrete pump, Transit Mixer etc. Concreting<br />

requirement would be catered by Batching & Mixing Plant & aggregate processing plant<br />

installed at dam site.


11.2.7 Surge Shaft :<br />

132<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

For Construction <strong>of</strong> 10m diameter, 75 m high Surge Shaft, an approach to surge shaft top<br />

would be constructed in four months. After the completion <strong>of</strong> approach, Excavation <strong>of</strong><br />

surge shaft would be carried out manually in 15 months. Excavation would be carried out<br />

with the help <strong>of</strong> Jack hammers, motorized winch 10 T capacity etc.. Mucking will be<br />

done from the top. Concreting would be completed employing 2 m shutter, concrete<br />

pump, Transit Mixer & 30 cum/hr batching &mixing plant . Construction <strong>of</strong> surge shaft<br />

would be completed in 27 months.<br />

11.2.8 Pressure Shaft:<br />

Initially construction <strong>of</strong> approaches & adit would be done in 4 months. One no. 1000 m<br />

long 2.5 m dia. inclined pressure shaft, will be excavated in the same way as surge shaft<br />

by deploying Jack hammer, Motorized winch etc. However two nos. intermediate adit<br />

can be used to handle the muck. Steel liner erection & concreting will be carried out by<br />

deploying 10/20 t winches, Slipform liner etc. Construction <strong>of</strong> Pressure shaft would take<br />

around 30 months.<br />

11.2.9 <strong>Power</strong> House<br />

3 X 47 MW (141MW) underground power house (110 m X 22 m X 40 m size),<br />

Transformer Cavern & MIV would be excavated in 16 months. For excavation <strong>of</strong> <strong>Power</strong><br />

House a construction adit would be excavated up to the crown <strong>of</strong> power house. Main<br />

access tunnel would also be excavated simultaneously. Construction adit would be<br />

extended up to full length <strong>of</strong> power House. Thereafter it will be expanded side wise to<br />

the full width <strong>of</strong> power house resulting in <strong>Power</strong> House Cavern. Mucking <strong>of</strong> excavated<br />

material would be done through the Construction adit. From <strong>Power</strong> House Cavern 3<br />

shafts <strong>of</strong> 2.0 m diameter would be excavated up to the bottom level <strong>of</strong> draft tube followed<br />

by benching <strong>of</strong> <strong>Power</strong> House cavern up to the bottom <strong>of</strong> <strong>Power</strong> House. Mucking will be<br />

carried out through Main access Tunnel/TRT. The equipment to be deployed for<br />

excavation are jack hammers, wagon drills, air compressors, loader, excavators, tippers,


133<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

winches etc. Concreting <strong>of</strong> <strong>Power</strong>house would be carried out in 20 months with the help<br />

<strong>of</strong> concrete pump, transit mixer etc. Concreting requirement would be catered by<br />

deploying 60 cum/hr batching & mixing plant and 100 TPH aggregate processing plant.<br />

<strong>Power</strong> house Installation & Testing <strong>of</strong> Machine would be undertaken in such a manner<br />

that Project get commissioned in 48 th month from the start <strong>of</strong> Project construction.<br />

11.2.10 Tail Race Tunnel:<br />

1 Nos. 300m long horse shoe shaped Tail Race Tunnel having 3.3 m finished diameter<br />

will be excavated by full face method. Excavation <strong>of</strong> Tail Race Tunnel would be carried<br />

out with single boom Drill Jumbo, Wagon drill, Conway mucker , 10 t tipper etc. The<br />

TRT will be excavated from 5th month & will be completed in further 6 month. After the<br />

excavation <strong>of</strong> power house the TRT will be concreted with the help <strong>of</strong> concrete pump,<br />

Transit mixer, Batching & mixing plant & aggregate processing plant ( installed at <strong>Power</strong><br />

house).<br />

11.3 CONSTRUCTION SCHEDULE<br />

The schedule for stage I & II activities upto CCEA clearance and construction schedule<br />

has been prepared in the form <strong>of</strong> bar chart and placed as annexure –11.1 & 11.2<br />

respectively.


S. No.<br />

Details <strong>of</strong> works<br />

1 Preparation <strong>of</strong> stage-I activity estimates 1<br />

2 Data collec./ application for clearance from MOEF<br />

3 MOEF clearance 1<br />

4 Essent. Temp. infra./access 6<br />

5 Estab. <strong>of</strong> G&D sites, Metrological<br />

obser. And Hydrological measurement<br />

6 Essential Geological & Geo-physical<br />

exploration, Topographical surveys<br />

7 Formulation <strong>of</strong> Feasibility Report,<br />

preparation <strong>of</strong> estimate for st-II activities<br />

8 EIA / EMP studies 15<br />

9 Commercial viability from CEA 1<br />

10 Vetting & sanction <strong>of</strong> st-II activity estimates 1<br />

11 Detailed Topogr./Geological/Hydro<br />

metero. & Construction material survey<br />

12 MOEF clearance 3<br />

13 Const. <strong>of</strong> resid./non resid. buildings,roads<br />

bridges and arrangement <strong>of</strong> const. <strong>Power</strong><br />

14 Preparation <strong>of</strong> Detailed Project Report<br />

and its submission<br />

Duration<br />

15 Techno Economic Clearance 3<br />

16 Pre PIB delibrations 1<br />

17 PIB Clearance 1<br />

18 CCEA Clearance (Investment Sanction) 1<br />

2<br />

24<br />

11<br />

14<br />

14<br />

19<br />

14<br />

SCHEDULE FOR STAGE-I&II ACTIVITIES (UP TO CCEA CLEARANCE)<br />

MONTHS<br />

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40<br />

*This schedule is in accordances with three stage clearance policy <strong>of</strong> <strong>Ministry</strong> <strong>of</strong> <strong>Power</strong> ,Govt. <strong>of</strong> India vide no. 16/31/2000-DO(NHPC) dated 8/6/2001<br />

133<br />

Annexure-11.1<br />

Contd.<br />

Contd.<br />

Zero date for<br />

Construction


Sl.<br />

No.<br />

CCEA Clearance 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48<br />

1 INFRASTRUCTURE DEVELOPMENT<br />

a Acquisition <strong>of</strong> private & forest land Ha 8<br />

b Construction <strong>of</strong> roads & buildings LS 12<br />

2 AWARD OF CONTRACTS<br />

a Tendering , award and mobilization LS 4<br />

3 DIVERSION TUNNELS ( 2nos., 300 m<br />

long 3.3 m dia horse shoe)<br />

a<br />

Excavation m 3 40,000 5<br />

b Erection <strong>of</strong> shutters & Conc. Lining m 3 6,500 4<br />

c HM Works Job LS 4<br />

d Plugging <strong>of</strong> tunnels Job LS 2<br />

4 COFFER DAMS (U/s & D/s)<br />

Name <strong>of</strong> Work Unit Quantity Duration<br />

(months)<br />

a Const.<strong>of</strong> C<strong>of</strong>fer Dams & River Diversion m 3 75,000 3<br />

5 UPPER CONCRETE DAM<br />

(65 m High & 300 m Long at top )<br />

a<br />

b<br />

Dam abutments stripping<br />

Excavation and foundation treatment<br />

m 2,10,000<br />

13<br />

3<br />

3<br />

c Mass Concreting m 3 3,76,000 19<br />

d Hyromechanical Works Job LS 12<br />

e Reservoir filling Job 2<br />

6 LOWER CONCRETE DAM<br />

( 65 m high & 250m long at top)<br />

a<br />

b<br />

Dam abutments stripping<br />

Excavation and foundation treatment<br />

m 1,55,000<br />

13<br />

4<br />

3<br />

c Mass Concreting m 3 3,24,000 18<br />

d Hyromechanical Works Job LS 12<br />

e Reservoir filling Job 2<br />

7 LINK TUNNEL (3.3m dia. 2000m long)<br />

a Construction <strong>of</strong> approaches Job LS 4<br />

b Excavation m 3 35,000 20<br />

c Concreting & HM Works m 3 12,000 15<br />

7 INTAKE, DESILTING CHAMBERS &<br />

HRT ( 7.5 Km <strong>of</strong> dia 3.3m horse shoe)<br />

a Excavation <strong>of</strong> adits(3 Nos. 3.3m <strong>of</strong> D-Shaped) &<br />

approches<br />

Job LS 4<br />

b Excavation m 3 1,94,100 24<br />

c Concrete Lining m 3 59,400 18<br />

d Grouting Job LS 12<br />

e HM Works Job LS 14<br />

f Cleanning, Adit pluggings etc. Job LS 2<br />

g Water conductor charging Job LS 1<br />

8 POWER HOUSE COMPLEX<br />

(3 Caverns i.e MIV, PH & TG)<br />

a Const. <strong>of</strong> Adits Job LS 4<br />

b Excavation <strong>of</strong> PH, MIV & TG m 3 2,30,000 16<br />

c Concreting in sub & super structures m 3 104,500 20<br />

d Erection <strong>of</strong> EOT crane Job LS 2<br />

9 SURGE SHAFT<br />

( 10 m dia.<strong>of</strong> 75 m height)<br />

a Const. <strong>of</strong> approches Job LS 4<br />

b Excavation m 3<br />

70,200 15<br />

c Concreting & HM Works m 3<br />

6,000 12<br />

10 STEEL LINED PRESSURE SHAFT<br />

( approx.2.5m dia ,1000 m long ) and<br />

penstocks<br />

a Const.<strong>of</strong> approaches & adit Job LS 4<br />

b Excavation m 3<br />

17,500 18<br />

c Erection <strong>of</strong> steel liners & Concreting m 3<br />

12,000 12<br />

11 TAILRACE TUNNEL<br />

( 3.3 m dia ,300 m length )<br />

a Excavation m 3<br />

5,200 6<br />

b Concreting & HM Works m 3<br />

1,800 4<br />

12 POT HEAD YARD Job<br />

Exc 79000,<br />

Conc 3000<br />

12<br />

13 ELECTRO-MECHANICAL WORKS<br />

a Erection, Testing & Commisioning <strong>of</strong> all three Units<br />

Job 26<br />

Note: Since the date <strong>of</strong> CCEA clearance cannot be anticipated at this stage, the time assumed for various activities is inclusive <strong>of</strong> the effect <strong>of</strong> monsoon.<br />

CONSTRUCTION SCHEDULE OF RANGYONG HE PROJECT (3X47=141 MW), SIKKIM<br />

Ist year IInd year<br />

Schedule <strong>of</strong> Constructiom<br />

IIIrd year IVth year<br />

134<br />

Annexure 11.2


Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

CHAPTER – XII<br />

COST ESTIMATE


CHAPTER -XII<br />

COST ESTIMATES<br />

135<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

PRELIMINARY COST ESTIMATES FOR CIVIL, HYDRO-MECHANICAL,<br />

ELECTRO-MECHANICAL AND TRANSMISSION WORKS<br />

The estimate has been prepared to arrive at the capital cost <strong>of</strong> <strong>Rangyong</strong> H.E. Project and<br />

is <strong>of</strong> Pre-feasibility level <strong>of</strong> accuracy. The base date <strong>of</strong> the estimate is June 2003 Price<br />

Level and the cost is expressed in Indian Rupees. The Cost Estimate is divided into<br />

Civil, Electrical and Transmission Works. For Civil Works, the sub heads are as under: -<br />

12.1 I-WORKS<br />

Under this head, provision has been made for various components <strong>of</strong> the Project as<br />

detailed hereunder.<br />

A-Preliminary<br />

Under this head, provision has been made for all surveys and investigations to be<br />

conducted to arrive at the optimum <strong>of</strong> the project components.<br />

B-Land<br />

This covers the provision for acquisition <strong>of</strong> land for construction <strong>of</strong> the project colonies,<br />

<strong>of</strong>fices and stores and compensation for trees and standing crops etc.<br />

C-Works<br />

This covers the cost <strong>of</strong> Diversion Tunnel and C<strong>of</strong>fer and Concrete Dam and Spillway<br />

along with associated hydro-mechanical equipment.


J-<strong>Power</strong> Plant Civil Works<br />

136<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

This covers the cost <strong>of</strong> project components viz. Intake Structure, Headrace Tunnel, <strong>Power</strong><br />

House and Transformer Cavern, Pressure Shaft, Surge Shaft, Tail Race Tunnel and other<br />

appurtenant works.<br />

The quantities indicated in the estimates for C - Works & J-<strong>Power</strong> Plant Civil Works<br />

(Civil & HM) are calculated from the Preliminary Engineering Drawings and as per<br />

experience <strong>of</strong> other on-going or commissioned projects. A provision has been made for<br />

contingencies.<br />

The unit rates for various items are taken as per the Guidelines issued by CEA for<br />

preparation <strong>of</strong> PFRs. It has been assumed that the quarry is available at a distance <strong>of</strong> 10<br />

Kms from the work site.<br />

K-Buildings<br />

Under this head provision for both residential and non-residential have been provided.<br />

Under the permanent category only those structures are included which will be<br />

subsequently utilized during the operation and maintenance <strong>of</strong> the project utilities. The<br />

costs are worked out on plinth area basis prevalent in the area for the type <strong>of</strong> construction<br />

involved.<br />

O-Miscellaneous<br />

Provision under this head has been made for C & J works for the Capital & running cost<br />

<strong>of</strong> Electrification, Water Supply, Sewage disposal, Fire fighting equipments, Medical<br />

assistance, Recreation, Post Office, Telephone and Telegraph Office, etc. also the<br />

Provisions are made for the Security arrangements, inspection vehicles, schools, transport<br />

<strong>of</strong> labour, Laboratory testing, R&M <strong>of</strong> Guest House and transit camps, Community<br />

center, Retrenchment compensation, photographic instruments as well as their R&M<br />

charges etc.


P-Maintenance During Construction And Y-Losses On Stock<br />

137<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

A provision <strong>of</strong> 1% and 0.25% <strong>of</strong> C-Civil works, J-<strong>Power</strong> Plants, K-Buildings & R-<br />

Communications has been made for maintenance <strong>of</strong> works during construction period<br />

and losses on stock respectively.<br />

Q-Special Tools And Plant<br />

It is assumed that the work will be carried out through contracts and not through<br />

departmental construction. Accordingly, provision for general purpose equipment and<br />

inspection vehicles only has been made as per CWC Guidelines.<br />

R-Communication<br />

Provision under this head covers the cost <strong>of</strong> new roads, Widening/Improvement <strong>of</strong> roads<br />

and strengthening <strong>of</strong> bridges. The cost <strong>of</strong> roads and bridges are based on the prevalent<br />

rate structure prevalent in the area <strong>of</strong> the Project, for the type <strong>of</strong> construction involved.<br />

X-Environment And Ecology<br />

Provision under this head has been taken as 2% <strong>of</strong> I Works towards Bio-diversity<br />

Conservation, Creation <strong>of</strong> Green belt, Restoration <strong>of</strong> Construction Area, Catchment Area<br />

Treatment, Compensatory Afforestation etc<br />

12.2 II-ESTABLISHMENT<br />

Provision for establishment has been made at 8% <strong>of</strong> I-works minus B-Land for civil<br />

works.<br />

12.3 III-TOOLS AND PLANTS<br />

This provision is distinct from that under Q-Special T&P and is meant to cover cost <strong>of</strong><br />

survey instruments, camp equipment and other small tools and plants. The outlay is<br />

provided at 1% <strong>of</strong> cost <strong>of</strong> I-works.


12.4 IV-SUSPENSE<br />

138<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

No provision has been made under this head as all the outstanding suspense are expected<br />

to be cleared by adjustment to appropriate heads at completion <strong>of</strong> the project.<br />

12.5 V-RECEIPTS AND RECOVERIES<br />

Under this provision, estimated recoveries by way <strong>of</strong> resale or transfer <strong>of</strong> equipment used<br />

in infrastructure works are provided for @ 75% <strong>of</strong> value booked under head Q-Special<br />

Tools and Plants. Also, the provision for recoveries on account <strong>of</strong> resale <strong>of</strong> DG Set and<br />

temporary buildings has been considered<br />

12.6 ELECTRICAL WORKS AND GENERATING PLANT<br />

The cost <strong>of</strong> generating plant and equipment is based on indigenous sources. The prices <strong>of</strong><br />

auxiliary equipment and services are based on prevailing market prices/costs incurred at<br />

other ongoing or commissioned projects.


ABSTRACT OF COST OF WORKS<br />

139<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

S.No Description Amount<br />

(Rs. in Crores)<br />

( June 2003 P.L.)<br />

A CIVIL WORKS<br />

1. DIRECT CHARGES<br />

I - Works<br />

A - Preliminary 5.78<br />

B - Land 13.47<br />

C - Works 299.44<br />

J - <strong>Power</strong> Plant Civil Works 217.77<br />

K - Buildings 15.07<br />

O - Miscellaneous 8.78<br />

P - Maintenance 5.64<br />

Q-Special Tools & Plants 4.07<br />

R - Communication 31.62<br />

X - Environment & Ecology 12.31<br />

Y - Losses on Stock 1.41<br />

Total <strong>of</strong> I-Works 615.36<br />

II - Establishment @ 8% <strong>of</strong> cost <strong>of</strong> I-Works less B-Land 48.15<br />

III - Tools and Plants @ 1% <strong>of</strong> cost <strong>of</strong> I-Works 6.15<br />

IV - Suspense 0.00<br />

V - Receipt & Recoveries (-) -3.27<br />

TOTAL DIRECT CHARGES 666.40<br />

2. INDIRECT CHARGES<br />

a) Capitalised Value <strong>of</strong> Abatement <strong>of</strong> Land Revenue 0.17<br />

b) Audit and Account Charges @1% <strong>of</strong> cost <strong>of</strong> I-Works 6.15<br />

TOTAL INDIRECT CHARGES 6.32<br />

TOTAL OF DIRECT & INDIRECT CHARGES 672.71<br />

ABSTRACT :<br />

A Civil Works 672.71<br />

B Electrical Works 113.11<br />

C Transmission Works 13.68<br />

TOTAL COST 799.50<br />

C IDC 91.32<br />

D Total Cost With IDC 890.82


Sl<br />

No.<br />

A- Preliminary<br />

140<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Description <strong>of</strong> Work Unit Qty Rate<br />

Rs. In lakhs<br />

Amount<br />

1 Prefeasibility<br />

1.1 Preparation <strong>of</strong> Prefeasibility Report LS 14.00<br />

2.0 Preparation <strong>of</strong> Detailed Project Report<br />

2.1 Detail survey for final location <strong>of</strong> project<br />

componenets<br />

2.2 Aerial survey, contour survey for reservoir<br />

basin including establishment <strong>of</strong> permanent<br />

benchmarks.<br />

2.3 Geological and geophyical surveys and<br />

investigation<br />

LS 25.00<br />

LS 10.00<br />

I) Drifting m 800 0.10 80.00<br />

ii) Geophysical LS 30.00<br />

iii) Core drilling m 450 0.10 45.00<br />

2.4 Hydrological and Metrological surveys<br />

including establishment <strong>of</strong> rain gauges/<br />

river gauges and discharge, sedimentation<br />

stations and their running charge for 1 year<br />

LS 16.00<br />

2.5 Investigations for foundation and rock<br />

testing<br />

2.6 Investigation for availability <strong>of</strong> construction<br />

materials.<br />

2.7 Construction <strong>of</strong> access roads to facilitate<br />

investigations<br />

LS 6.00<br />

LS 3.50<br />

LS 7.00<br />

2.8 Model experiment. LS 12.00<br />

2.9 Computer and telecommunication facilities. LS 3.00<br />

2.10 Vehicles for inspecting <strong>of</strong>ficers for site<br />

investigations<br />

LS 25.00<br />

2.11 Camping equipment LS 2.00<br />

2.12 Preliminary soil test, establishing soil<br />

testing laboratory.<br />

LS 6.00<br />

2.13 Consultant’s fees including charges for<br />

preliminary design work or device<br />

2.14 Training <strong>of</strong> engineers during investigation<br />

and preparation <strong>of</strong> project reports<br />

LS 15.00<br />

LS 6.00<br />

2.15 Ground water studies. LS 6.00<br />

2.16 Environment and ecological studies. LS 10.00


141<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

2.17 Preparation and printing <strong>of</strong> DPR LS 10.00<br />

Total( I+II) 331.50<br />

3.0 Pre-Construction Stage Investigations<br />

3.1 Topographical Surveys LS<br />

3.2 Geological Investigation<br />

15.00<br />

I) Diamond Core Drilling m 200.00 0.1 20.00<br />

ii) Exploratory Drift m 200.00 0.1 20.00<br />

iii) Excavation in trenches & pits<br />

LS<br />

iv) Testing <strong>of</strong> Samples<br />

LS<br />

3.3 Hydrological and Silt data collection - 3<br />

sites for 4 years<br />

3.4 Meteorological Data Collection 3 sites for 4<br />

years Year<br />

3.5 Construction material survey<br />

I) Topographical Survey<br />

LS<br />

ii) Collection and Transportation <strong>of</strong> samples<br />

iii) Laboratory Testing <strong>of</strong> Samples including<br />

LS<br />

charges for all T&P and Machineries LS<br />

3.6 Model studies<br />

LS<br />

3.7 Seismological data collection for 4 years<br />

Year<br />

3.8 Survey for layout <strong>of</strong> colonies and roads<br />

0.75<br />

4.00<br />

12.00 2.00 24.00<br />

12.00 0.40 4.80<br />

5.00 0.05 0.25<br />

3.00<br />

6.00<br />

15.00<br />

4.00 1 4<br />

I) Residential-cum-Office accomodation<br />

Sqm.<br />

2.00 0.5 1.00<br />

ii) Batching Mixing Plant and Workshop Sqm. 1.00 0.5 0.50<br />

iii) Project and quarry site road Sqm. 0.50 0.5 0.25<br />

3.9 Workcharged establishment for unforseen<br />

works Year<br />

4.0 Design & Consultancy<br />

4.1 Cost <strong>of</strong> Design Establishement including<br />

procurement <strong>of</strong> printing stationery and<br />

preparation <strong>of</strong> completion report, History <strong>of</strong><br />

Project etc. LS<br />

4.2 Cost <strong>of</strong> Special Studies and Designs<br />

LS<br />

4.3 Fees for Consultant and specialists<br />

LS<br />

4.4 Training <strong>of</strong> Engineers<br />

LS<br />

4.00 2 8.00<br />

25.00<br />

15.00<br />

15.00<br />

5.00


142<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

5.0 Equipment LS<br />

5.1 Drawing and Mathematical Instruments LS 10.00<br />

5.3 Survey Instruments LS 30.00<br />

5.4 Office instruments<br />

LS<br />

20.00<br />

Grand Total :( I+II+III) 578.05


Sl.<br />

No.<br />

1.0 Private land Requirement<br />

B-LAND<br />

143<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Rs. In lakhs<br />

Description Qty. Rate Unit Amount<br />

Permanent residential and non residential<br />

buildings<br />

3.00 5.50 Ha 16.50<br />

Diversion tunnel 2.00 5.50 Ha 11.00<br />

Submerged in the reservoir area 27.00 5.50 Ha 148.50<br />

Construction <strong>of</strong> dam/ weir 8.00 5.50 Ha 44.00<br />

Construction material 2.00 5.50 Ha 11.00<br />

Construction <strong>of</strong> approach Roads 70.00 5.50 Ha 385.00<br />

<strong>Power</strong> house 2.00 5.50 Ha 11.00<br />

Construction <strong>of</strong> adits 3.00 5.50 Ha 16.50<br />

Switch Yard 1.00 5.50 Ha 5.50<br />

Surge Shaft 1.00 5.50 Ha 5.50<br />

Land for Misc Purpose 1.00 5.50 Ha 5.50<br />

Sub Total (1) 120.00 660.00<br />

2.0 Forest land<br />

River bed 10.00 0.00 Ha 0.00<br />

Underground 4.00 0.00 Ha 0.00<br />

Sub total (2) 14.00 0.00 0.00<br />

3.0 Other Compensation<br />

Cost <strong>of</strong> crops standing on cultivated land<br />

required @30% <strong>of</strong> cultivated land<br />

80 1.65 Ha 132.00<br />

Compensation for trees LS 10.00<br />

Compensation for relocating electric and<br />

telephone poles<br />

2.00<br />

Crop Compensation for submergence LS 200.00<br />

Total 344.00<br />

4 Land on lease/ hire for 4 Years<br />

Dumping area 0.50 2.40 Ha 1.20<br />

Dumping area for batching and mixing 0.50 2.40 Ha 1.20<br />

plant<br />

Temporary Residential and Non-<br />

Residential buildings<br />

2.00 2.40 Ha 4.80<br />

Contractors Colony 2.00 2.40 Ha 4.80<br />

Contractors Construction facilities 2.00 2.40 Ha 4.80<br />

Railway Siding Facilities 1.00 2.40 Ha 2.40


144<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Electro - Mechanical Works 1.00 2.40 Ha 2.40<br />

Hydro -Mechanical Works 1.00 2.40 Ha 2.40<br />

Total 24.00<br />

Total (1+2+3+4) 1028.00<br />

Interest charges on account <strong>of</strong> award for<br />

the period taking over possession <strong>of</strong> land<br />

and date <strong>of</strong> award @ 12% per year <strong>of</strong><br />

25% cost <strong>of</strong> land acquisition for two years<br />

39.60<br />

Solatium charges for compulsory<br />

acquisition <strong>of</strong> land @ 30% <strong>of</strong> the cost <strong>of</strong><br />

private land<br />

Provision for legal charges @1% on total<br />

compensation<br />

Labour and material required for<br />

measurement and demarcation <strong>of</strong> land and<br />

properties @ 1% <strong>of</strong> land acquisition<br />

Establishment charges @ 6.25% <strong>of</strong> cost<br />

<strong>of</strong> total compensation<br />

198.00<br />

10.28<br />

6.60<br />

64.25<br />

Total 1346.73


ABSTRACT OF COST OF C - WORKS<br />

145<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

S. N. Description Amount (Rs. In Lakhs)<br />

Civil HM Total<br />

1. River Diversion Works 635.60 72.66 708.26<br />

2. C<strong>of</strong>fer Dam 1289.40 1289.40<br />

3. Upper Concrete Dam 10301.94 10301.94<br />

3. Lower Concrete Dam 8513.11 8513.11<br />

4. Spillway & Plunge Pool 7677.89 866.36 8544.25<br />

Total 28417.95 939.02 29356.96<br />

Add works tax @ 2% 568.36 18.78 587.14<br />

GRAND TOTAL 28986.30 957.80 29944.10


S.<br />

No.<br />

HYDRO MECHANICAL EQUIPMENT<br />

Detail <strong>of</strong> Items Unit Qnty. Rate in<br />

Rs.<br />

UPPER DAM<br />

1 Diversion tunnel gate<br />

Gate(Fixed wheel type)including ballast<br />

(3.3m x 4m)- 1 No.<br />

146<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Amount<br />

in Lakh<br />

Ton 16 60000 9.60<br />

Embedded Parts - 1 Set Ton 5 50000 2.50<br />

Ropedrum hoist 55 T Capacity Ton 17 100000 17.00<br />

Hoist Supporting structure and trestle Ton 11 50000 5.50<br />

2 Spillway structure<br />

a) Radial Gates (3m x 6.0m) - 3 Nos. Ton 114 100000 114.00<br />

Embedded Parts (including anchorages,<br />

hoist structure) including breast wall<br />

liners - 3 Set<br />

Ton 69 50000 34.50<br />

Hydraulic Hoist 50.0T capacity (One<br />

power pack + Two 50T cap. hydraulic<br />

cylinders with provision <strong>of</strong> 25%<br />

pushing force)<br />

Set 3 3500000 105.00<br />

Portable oil filter unit along with<br />

Contamination checking kit & Low<br />

vacuum dehydration and degassification<br />

unit<br />

Set 1 500000 5.00<br />

Portable trolley mounted gasoline<br />

engine operated power pack<br />

Set 1 750000 7.50<br />

b) Bulkhead Gate ( Slide type) 3.0m x<br />

7.5m - 1 Set<br />

Ton 18 60000 10.80<br />

Embedded Parts - 3 Set Ton 18 50000 9.00<br />

Gantry crane 40 T capacity Set 1 4000000 40.00<br />

3 Instruments and Remote Control Set 1 7000000 70.00<br />

4 D G Set 250 KVA Set 1 1250000 12.50<br />

5 Link Tunnel structure<br />

a) TrashRacks and Embedded parts (5m<br />

x14m) - 1 No.<br />

Ton 25 50000 12.50<br />

Trash rack cleaning machine Set 1 10000000 100.00<br />

b) Fixed wheel Gate including ballast<br />

(3.3m x 3.3m) - 1 No.<br />

Ton 27 60000 16.20


147<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Embedded Parts - 1 Set Ton 6 50000 3.00<br />

Rope drum hoist 50T Capacity Ton 17 100000 17.00<br />

Hoist platform and trestle Ton 11 50000 5.50<br />

C) Bulkhead Gate (Slide Type) 3.3m Ton 10 60000 6.00<br />

x3.3m - 1 No.<br />

Embedded Parts - 1 Set Ton 4 50000 2.00<br />

Rope drum hoist 20T Capacity Ton 6 100000 6.00<br />

Hoist platform and trestle Ton 4 50000 2.00<br />

LOWER DAM<br />

6 Diversion tunnel gate<br />

Gate(Fixed wheel type)including ballast<br />

(3.3m x 4m)- 1 No.<br />

Ton 16 60000 9.60<br />

Embedded Parts - 1 Set Ton 5 50000 2.50<br />

Ropedrum hoist 55 T Capacity Ton 17 100000 17.00<br />

Hoist Supporting structure and trestle Ton 11 50000 5.50<br />

7 Spillway structure<br />

a) Radial Gates (3m x 6.0m) - 3 Nos. Ton 114 100000 114.00<br />

Embedded Parts (including anchorages,<br />

hoist structure) including breast wall<br />

liners - 3 Set<br />

Ton 66 50000 33.00<br />

Hydraulic Hoist 50.0T capacity (One<br />

power pack + Two 50T cap. hydraulic<br />

cylinders with provision <strong>of</strong> 25%<br />

pushing force)<br />

Set 3 3500000 105.00<br />

Portable oil filter unit along with<br />

Contamination checking kit & Low<br />

vacuum dehydration and degassification<br />

unit<br />

Set 1 500000 5.00<br />

Portable trolley mounted gasoline<br />

engine operated power pack<br />

Set 1 750000 7.50<br />

b) Bulkhead Gate ( Slide type) 3.0m x<br />

7.5m - 1 Set<br />

Ton 18 60000 10.80<br />

Embedded Parts - 3 Set Ton 18 50000 9.00<br />

Gantry crane 40 T capacity Set 1 4000000 40.00<br />

8 Instruments and Remote Control Set 1 7000000 70.00<br />

9 Optical Fibre cables 3.0km<br />

(approx.)long for connecting upper<br />

dam & lower dam control systems.<br />

Set 1 1000000 10.00<br />

10 D G Set 250 KVA Set 1 1250000 12.50


11 Link Tunnel structure<br />

a) Bulkhead Gate (Slide Type) 3.3m<br />

x3.3m - 1 No.<br />

148<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Ton 10 60000 6.00<br />

Embedded Parts - 1 Set Ton 4 50000 2.00<br />

Rope drum hoist 20T Capacity Ton 6 100000 6.00<br />

Hoist platform and trestle Ton 4 50000 2.00<br />

12 Intake structure<br />

a) TrashRacks and Embedded parts (5m x<br />

14m) - 2 No.<br />

Ton 60 50000 30.00<br />

Trash rack cleaning machine Set 1 10000000 100.00<br />

b) Intake gate(fixed wheel type) including<br />

ballast (3m x 3m) - 2Nos.<br />

Ton 48 60000 28.80<br />

Embedded Parts - 2 Set Ton 12 50000 6.00<br />

Rope drum hoist 50T Cap.-2set Ton 27 100000 27.00<br />

Hoist platform and trestle-2set Ton 18 50000 9.00<br />

C) Bulkhead Gate (Slide Type) 3m x3m - 2 Ton 16 60000 9.60<br />

No.<br />

Embedded Parts - 2 Set Ton 6 50000 3.00<br />

Rope drum hoist 15T Cap.-2set Ton 9 100000 9.00<br />

Hoist platform and trestle-2set Ton 6 50000 3.00<br />

13 Desilting Chamber Gates 0.00<br />

Desilting Chamber Gate (Slide Type)<br />

3.3m x3.3m - 1 No.<br />

Ton 10 60000 6.00<br />

Embedded parts - 2 Set Ton 8 50000 4.00<br />

EOT crane with 20T Cap. Set 1 1500000 15.00<br />

14 Silt Flushing Gates (Slide Type)<br />

Gates (Service & Emergency) 1.5m<br />

x1.5m - 4 Nos.<br />

Embedded parts (including bonnet,<br />

bonnet cover,gate body liner etc.)-4Set<br />

Hydraulic Hoist 130T Cap. (Two<br />

Double acting cylinder and one power<br />

pack)<br />

Ton 10 100000 10.00<br />

Ton 70 50000 35.00<br />

Set 2 4800000 96.00<br />

15 Surge shaft gate<br />

Gate(Slide Type) 2.5m x4.5m - 1 No. Ton 14 60000 8.40<br />

Embedded parts - 1 Set Ton 15 50000 7.50<br />

Rope drum hoist 25T Cap. Ton 8 100000 8.00<br />

Hoist platform and trestle Ton 5 50000 2.50


16 Tailrace channel gate<br />

Gate (Fixed Wheel type) 3.3m x 3.3m -<br />

1 No.<br />

149<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Ton 4 60000 2.40<br />

Embedded Parts - 1 Set Ton 2 50000 1.00<br />

Monorail hoist 10T Cap. Set 1 1000000 10.00<br />

17 Pressure shaft steel Liner<br />

Steel Liner - 1 No. (ASTM A 537 Cl. 1<br />

)<br />

Bifurcation (ASTM A 517 Gr. F ) - 2<br />

Nos.<br />

Ton 2750 70000 1925.00<br />

Ton 200 77000 154.00<br />

18 Adit Gates<br />

Adit gates (2.5m x2.5m) - 3 Nos. Ton 21 60000 12.60<br />

Embedded Parts - 3 Set Ton 10 50000 5.00<br />

19 contingency @ 5% for spares air<br />

vent by pass etc<br />

Sub Total 3608.30<br />

5% 180.42<br />

Total 3788.72


S.<br />

No.<br />

DIVERSION TUNNEL<br />

Description Unit Quantity Rate<br />

(in<br />

Rs.)<br />

150<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Amount<br />

( Rs. in<br />

Lakhs)<br />

1.0 Surface Excavation<br />

1.1 Common excavation Cum 25,000 125 31.25<br />

1.2 Rock excavation Cum 5,000 300 15.00<br />

2.0 Underground excavation Cum 10,000 1000 100.00<br />

3.0 Rock Support System<br />

3.1 Rock bolts M 7,000 400 28.00<br />

3.2 Steel Supports T 50 42000 21.00<br />

3.3 Shotcreting Cum 700 4000 28.00<br />

3.4 Concrete lagging (if required) Cum 150 7000 10.50<br />

4.0 Concrete<br />

4.1 Cement concrete lining M-20 Cum 2,000 4000 80.00<br />

4.2 M15 Cum 1,400 2930 41.02<br />

4.3 M20 Cum 100 3390 3.39<br />

4.4 M25 Cum 3,000 3610 108.30<br />

5.0 Reinforcement Steel T 300 27000 81.00<br />

Sub Total (A) 547.46<br />

6.0 Miscellaneous and Ancillary<br />

Works<br />

6.1 Various Miscellaneous works like<br />

wire mesh/steel fibre<br />

reinforcement, drilling & grouting,<br />

PVC pipes for drainage, slope<br />

protection works etc.(7% - 8% <strong>of</strong><br />

Sub Total (A) depending upon the<br />

site conditions & type <strong>of</strong> structure)<br />

7.50% 41.06<br />

Sub Total (B) 588.52<br />

7.0 Instrumentation (1% <strong>of</strong> Sub -Total<br />

(B)<br />

1% 5.89<br />

8.0 Dewatering (2% <strong>of</strong> Sub -Total (B) 2% 11.77<br />

9.0 Contingencies (3% <strong>of</strong> Sub -Total 3% 17.66<br />

(B)<br />

10.0 Work Charged Establishment(2%<br />

<strong>of</strong> Sub -Total (B)<br />

2% 11.77<br />

Total 635.60


S.<br />

No.<br />

COFFER DAMS<br />

DESCRIPTION UNIT QTY. RATE(in<br />

Rs.)<br />

151<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Amount<br />

(Rs. in<br />

Lakhs)<br />

1.0 Surface Excavation<br />

1.1 Common Excavation Cum 70,000 125 87.50<br />

2.0 Embankment Construction<br />

2.1 Earth/rock fill Cum 50000 518 259.00<br />

2.2 Impervious core Cum 20000 354 70.80<br />

2.3 Filter Cum 5000 901 45.05<br />

3.0 Concrete<br />

3.1 M10 Cum 1,000 2560 25.60<br />

3.2 Concrete cut-<strong>of</strong>f wall Sqm 3,500 20000 700.00<br />

Sub Total (A) 1187.95<br />

4.0 Miscellaneous<br />

4.1 Various Miscellaneous works<br />

like, drilling & grouting<br />

etc.(0.0% - 0.5% <strong>of</strong> Sub Total<br />

(A) depending upon the site<br />

conditions & type <strong>of</strong><br />

structure)<br />

0.50% 5.94<br />

Sub Total (B) 1193.89<br />

5.0 Dewatering 3% <strong>of</strong> Sub -Total<br />

(B)<br />

6.0 Contingencies 3% <strong>of</strong> Sub -<br />

Total (B)<br />

7.0 Work Charged Establishment<br />

2% <strong>of</strong> Sub -Total (B)<br />

3% 35.82<br />

3% 35.82<br />

2% 23.88<br />

Total <strong>of</strong> 1 to 7 1289.40


S.<br />

No.<br />

UPPER CONCRETE DAM<br />

DESCRIPTION UNIT QTY. RATE(in<br />

Rs.)<br />

152<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Amount<br />

(Rs. in<br />

Lakhs)<br />

1.0 Surface Excavation<br />

1.1 Common Excavation Cum 150,000 125 187.50<br />

1.2 Rock Excavation Cum 30,000 300 90.00<br />

2.0 Rock Support System<br />

2.1 Rock bolts M 1,500 400 6.00<br />

2.2 Shot Crete Cum 500 4000 20.00<br />

3.0 Concrete<br />

3.1 M10 Cum 500 2560 12.80<br />

3.2 M15 Cum 270,000 2930 7911.00<br />

3.3 M20 Cum 20,000 3390 678.00<br />

3.4 M25 Cum 5,000 3610 180.50<br />

4.0 Reinforcement Steel MT 500 27000 135.00<br />

Sub Total (A) 9220.80<br />

5.0 Miscellaneous and Ancillary<br />

Works<br />

5.1 Various Miscellaneous works<br />

like wire mesh/steel fibre<br />

reinforcement, drilling &<br />

grouting, PVC pipes, water<br />

stops, other steel works, slope<br />

protection works, road works,<br />

architectural works for dam<br />

etc.(2% - 3% <strong>of</strong> Sub Total (A)<br />

depending upon the site<br />

conditions & type <strong>of</strong><br />

structure)<br />

2.50% 230.52<br />

Sub Total (B) <strong>of</strong> 1 to 5 9451.32<br />

6.0 Instrumentation 1% <strong>of</strong> Sub -<br />

Total (B)<br />

1% 94.51<br />

7.0 Dewatering 2% <strong>of</strong> Sub -Total<br />

(B)<br />

3% 283.54<br />

8.0 Contingencies 3% <strong>of</strong> Sub - 3% 283.54<br />

Total (B)<br />

9.0 Work Charged Establishment<br />

2% <strong>of</strong> Sub -Total (B)<br />

2% 189.03<br />

Total 10301.94


S.<br />

No.<br />

LOWER CONCRETE DAM<br />

DESCRIPTION UNIT QTY. RATE(in<br />

Rs.)<br />

153<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Amount<br />

(Rs. in<br />

Lakhs)<br />

1.0 Surface Excavation<br />

1.1 Common Excavation Cum 100,000 125 125.00<br />

1.2 Rock Excavation Cum 25,000 300 75.00<br />

2.0 Rock Support System<br />

2.1 Rock bolts M 1,500 400 6.00<br />

2.2 Shot Crete Cum 500 4000 20.00<br />

3.0 Concrete<br />

3.1 M10 Cum 500 2560 12.80<br />

3.2 M15 Cum 218,000 2930 6387.40<br />

3.3 M20 Cum 20,000 3390 678.00<br />

3.4 M25 Cum 5,000 3610 180.50<br />

4.0 Reinforcement Steel MT 500 27000 135.00<br />

Sub Total (A) 7619.70<br />

5.0 Miscellaneous and Ancillary<br />

Works<br />

5.1 Various Miscellaneous works<br />

like wire mesh/steel fibre<br />

reinforcement, drilling &<br />

grouting, PVC pipes, water<br />

stops, other steel works, slope<br />

protection works, road works,<br />

architectural works for dam<br />

etc.(2% - 3% <strong>of</strong> Sub Total (A)<br />

depending upon the site<br />

conditions & type <strong>of</strong><br />

structure)<br />

2.50% 190.49<br />

Sub Total (B) 7810.19<br />

6.0 Instrumentation 1% <strong>of</strong> Sub -<br />

Total (B)<br />

1% 78.10<br />

7.0 Dewatering 2% <strong>of</strong> Sub -Total<br />

(B)<br />

3% 234.31<br />

8.0 Contingencies 3% <strong>of</strong> Sub - 3% 234.31<br />

Total (B)<br />

9.0 Work Charged Establishment<br />

2% <strong>of</strong> Sub -Total (B)<br />

2% 156.20<br />

Total 8513.11


S.<br />

No.<br />

SPILLWAY (Upper & Lower Dam)<br />

DESCRIPTION UNIT QTY. RATE(in<br />

Rs.)<br />

154<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Amount<br />

(Rs. in<br />

Lakhs)<br />

1.0 Surface Excavation<br />

1.1 Common Excavation Cum 50,000 125 62.50<br />

1.2 Rock Excavation Cum 10,000 300 30.00<br />

2.0 Concrete<br />

2.1 M10 Cum 2,000 2560 51.20<br />

2.2 M15 Cum 96,000 2930 2812.80<br />

2.3 M20 Cum 4,000 3390 135.60<br />

2.4 M25 Cum 60,000 3610 2166.00<br />

3.0 Reinforcement Steel T 6,000 27000 1620.00<br />

4.0 Structural Steel T 300 42000 126.00<br />

Sub Total (A) <strong>of</strong> 1 to 4 7004.10<br />

5.0 Miscellaneous and Ancillary<br />

Works<br />

5.1 Various Miscellaneous works<br />

like drilling & grouting, PVC<br />

pipes, water stops, other steel<br />

works, slope protection works,<br />

bridge etc.(1% - 2% <strong>of</strong> Sub<br />

Total (A) depending upon the<br />

site conditions & type <strong>of</strong><br />

structure)<br />

1.50% 105.06<br />

Sub Total (B) <strong>of</strong> 1 to 5 7109.16<br />

6.0 Instrumentation 1% <strong>of</strong> Sub -<br />

Total (B)<br />

7.0 Dewatering 2% <strong>of</strong> Sub -Total<br />

(B)<br />

8.0 Contingencies 3% <strong>of</strong> Sub -Total<br />

(B)<br />

9.0 Work Charged Establishment<br />

2% <strong>of</strong> Sub -Total (B)<br />

1% 71.09<br />

2% 142.18<br />

3% 213.27<br />

2% 142.18<br />

Total 7677.89


155<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

J -POWER PLANT APPURTENANCES (CIVIL WORKS)<br />

S. Description Amount (Rs. in Lakhs)<br />

NO. Civil HM Total<br />

1 POWER INTAKE STRUCTURE 720.97 236.67 957.64<br />

2<br />

DESILTING CHAMBERS<br />

(INCLUDING S.F.T.) 680.40<br />

174.30 854.70<br />

3 ADITS 1403.17 18.48 1421.65<br />

4<br />

HEAD RACE, LINK TUNNEL<br />

AND TAIL RACE TUNNEL<br />

6314.91 209.58 6524.49<br />

5 SURGE SHAFT 742.57 27.72 770.29<br />

6<br />

PRESSURE SHAFTS AND<br />

PENSTOCKS 778.25<br />

2182.95 2961.20<br />

7 POWER HOUSE COMPLEX 7491.99 7491.99<br />

8 SWITCHYARD 368.49 368.49<br />

Total 18500.76 2849.70 21350.46<br />

Add works tax @ 2% 370.02 56.99 427.01<br />

GRAND TOTAL 18870.77 2906.69 21777.47


S.<br />

No.<br />

POWER INTAKE STRUCTURE<br />

156<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

DESCRIPTION UNIT QTY. RATE(in<br />

Rs.)<br />

Amount<br />

(Rs. in<br />

Lakhs)<br />

1.0 Surface Excavation<br />

1.1 Common excavation Cum 25,000 125 31.25<br />

1.2 Rock excavation Cum 7,000 300 21.00<br />

2.0 Underground excavation Cum 5,000 1000 50.00<br />

3.0 Supports System<br />

3.1 Rock bolts M 1,500 400 6.00<br />

3.2 Steel ribs Support T 25 42000 10.50<br />

3.3 Shotcreting Cum 100 4000 4.00<br />

3.4 Concrete Lagging if required Cum 100 7000 7.00<br />

4.0 Concrete<br />

4.1 M15 Cum 1,000 2930 29.30<br />

4.2 M25 Cum 8,000 3610 288.80<br />

5.0 Reinforcement Steel T 800 27000 216.00<br />

6.0 Miscellaneous and Ancillary<br />

Works<br />

6.1 Various Miscellaneous works like<br />

drilling & grouting,<br />

wiremeshreinforcement, slope<br />

protection works, other steel works,<br />

etc.(1% - 2% <strong>of</strong> Sub Total (A)<br />

depending upon the site conditions &<br />

type <strong>of</strong> structure)<br />

Sub Total (A) 663.85<br />

1.50% 9.96<br />

Sub Total (B) 673.81<br />

7.0 Instrumentation 1% <strong>of</strong> Sub -Total (B) 1% 6.74<br />

8.0 Dewatering 1% <strong>of</strong> Sub -Total (B) 1% 6.74<br />

9.0 Contingencies 3% <strong>of</strong> Sub -Total (B) 3% 20.21<br />

10.0 Work Charged Establishment 2% <strong>of</strong><br />

Sub -Total (B)<br />

2% 13.48<br />

Total 720.97


S.<br />

No.<br />

DESILTING CHAMBERS (INCLUDING S.F.T.)<br />

DESCRIPTION UNIT QTY. RATE(in<br />

Rs.)<br />

157<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Amount<br />

(Rs. in<br />

Lakhs)<br />

1.0 Surface Excavation<br />

1.1 Common excavation Cum 5,000 125 6.25<br />

1.2 Rock excavation Cum 2,000 300 6.00<br />

2.0 Underground excavation Cum 20,000 1000 200.00<br />

3.0 Rock Support System<br />

3.1 Rock bolts M 11,000 400 44.00<br />

3.2 Steel Supports T 75 42000 31.50<br />

3.3 Shotcreting Cum 700 4000 28.00<br />

3.4 Concrete Lagging Cum 225 7000 15.75<br />

4.0 Concrete<br />

4.1 M15 Cum 3,000 2930 87.90<br />

4.2 M25 Cum 3,000 3610 108.30<br />

5.0 Reinforcement Steel T 300 27000 81.00<br />

Sub Total (A) <strong>of</strong> 1 to 5 608.70<br />

6.0 Miscellaneous and Ancillary<br />

Works<br />

6.1 Various Miscellaneous works<br />

like wiremesh/steel<br />

reinforcement, drilling &<br />

grouting works, etc.(3% - 4%<br />

<strong>of</strong> Sub Total (A) depending<br />

upon the site conditions & type<br />

<strong>of</strong> structure)<br />

3.50% 21.30<br />

Sub Total (B) <strong>of</strong> 1 to 6 630.00<br />

7.0 Instrumentation (1% <strong>of</strong> Sub -<br />

Total (B)<br />

1% 6.30<br />

8.0 Dewatering (2% <strong>of</strong> Sub -Total 2% 12.60<br />

(B)<br />

9.0 Contingencies (3% <strong>of</strong> Sub -<br />

Total (B) except on L.S. items)<br />

10.0 Work Charged<br />

Establishment(2% <strong>of</strong> Sub -Total<br />

(B) except on L.S. items)<br />

3% 18.90<br />

2% 12.60<br />

Total 680.40


S.<br />

No.<br />

ADITS<br />

DESCRIPTION UNIT QTY. RATE<br />

(in<br />

Rs.)<br />

158<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Amount<br />

(Rs. in<br />

Lakhs)<br />

1.0 Surface Excavation<br />

1.1 Common excavation Cum 30,000 125 37.50<br />

1.2 Rock excavation Cum 5,000 300 15.00<br />

2.0 Underground excavation<br />

2.1 Excavation <strong>of</strong> adits Cum 50,000 1000 500.00<br />

3.0 Supports System<br />

3.1 Rock bolts M 30,000 400 120.00<br />

3.2 Steel ribs Support T 200 42000 84.00<br />

3.3 Shotcreting Cum 2,600 4000 104.00<br />

3.4 Concrete lagging if required Cum 800 7000 56.00<br />

4.0 Concrete<br />

4.1 Cement concrete lining M-20 Cum 1,500 4000 60.00<br />

4.2 M10 Cum 500 2560 12.80<br />

4.3 M15 Cum 7,000 2930 205.10<br />

4.4 M20 Cum 1,000 3390 33.90<br />

5.0 Reinforcement Steel T 100 27000 27.00<br />

Sub Total (A) <strong>of</strong> 1 to 5 1255.30<br />

6.0 Miscellaneous and Ancillary<br />

Works<br />

6.1 Various Miscellaneous works like<br />

wiremesh/steel reinforcement,<br />

drilling & grouting, PVC pipes<br />

for drainage etc.(3% -4% <strong>of</strong> Sub<br />

Total (A) depending upon the site<br />

conditions & type <strong>of</strong> structure)<br />

3.50% 43.94<br />

Sub Total (B) <strong>of</strong> 1 to 6 1299.24<br />

7.0 Instrumentation (1% <strong>of</strong> Sub -<br />

Total (B)<br />

1% 12.99<br />

8.0 Dewatering (2% <strong>of</strong> Sub -Total 2% 25.98<br />

(B)<br />

9.0 Contingencies (3% <strong>of</strong> Sub -Total<br />

(B) except on L.S. items)<br />

10.0 Work Charged Establishment(2%<br />

<strong>of</strong> Sub -Total (B) except on L.S.<br />

items)<br />

3% 38.98<br />

2% 25.98<br />

Total 1403.17


S.<br />

No.<br />

HEAD RACE, LINK TUNNEL AND TAIL RACE TUNNEL<br />

DESCRIPTION UNIT QTY. RATE<br />

(in<br />

Rs.)<br />

159<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Amount<br />

(Rs. in<br />

Lakhs)<br />

1.0 Surface Excavation<br />

1.1 Common excavation Cum 4,000 125 5.00<br />

1.2 Rock excavation Cum 1,000 300 3.00<br />

2.0 Underground excavation Cum 165,000 1000 1650.00<br />

3.0 Rock Support System<br />

3.1 Rock bolts M 90,000 400 360.00<br />

3.2 Steel Supports T 900 42000 378.00<br />

3.3 Shotcreting Cum 10,000 4000 400.00<br />

3.4 Concrete lagging Cum 6,000 7000 420.00<br />

4.0 Concrete<br />

4.1 Cement concrete lining M-20 Cum 30,000 4000 1200.00<br />

4.2 M15 Cum 22,000 2930 644.60<br />

4.3 M25 Cum 6,000 3610 216.60<br />

5.0 Reinforcement Steel T 600 27000 162.00<br />

Sub Total (A) <strong>of</strong> 1 to 5 5439.20<br />

6.0 Miscellaneous and Ancillary<br />

Works<br />

6.1 Various Miscellaneous works like<br />

wiremesh/steel reinforcement,<br />

drilling & grouting, PVC pipes<br />

for drainage etc.(7% - 8% <strong>of</strong> Sub<br />

Total (A) depending upon the site<br />

conditions & type <strong>of</strong> structure)<br />

7.50% 407.94<br />

Sub Total (B) <strong>of</strong> 1 to 6 5847.14<br />

7.0 Instrumentation (1% <strong>of</strong> Sub -<br />

Total (B)<br />

1% 58.47<br />

8.0 Dewatering (2% <strong>of</strong> Sub -Total (B) 2% 116.94<br />

9.0 Contingencies (3% <strong>of</strong> Sub -Total<br />

(B) except on L.S. items)<br />

3% 175.41<br />

10.0 Work Charged Establishment(2%<br />

<strong>of</strong> Sub -Total (B) except on L.S.<br />

items)<br />

2% 116.94<br />

Total 6314.91


S.<br />

No.<br />

SURGE SHAFT<br />

DESCRIPTION UNIT QTY. RATE<br />

(in<br />

Rs.)<br />

160<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Amount<br />

(Rs. in<br />

Lakhs)<br />

1.0 Surface Excavation<br />

1.1 Common Excavation Cum 50000 125 62.50<br />

1.2 Rock excavation Cum 10000 300 30.00<br />

2.0 Underground excavation<br />

2.1 Surge shaft excavation Cum 10000 1,200 120.00<br />

2.2 Surge shaft excavation with raise Cum 200 1,500 3.00<br />

borer<br />

2.3 Concrete Lagging if required Cum 100 7,000 7.00<br />

3.0 Support System<br />

3.1 Rock bolts M 25000 400 100.00<br />

3.2 Steel ribs Support T 50 42,000 21.00<br />

3.3 Shotcreting Cum 1000 4,000 40.00<br />

4.0 Concrete<br />

4.1 M-20 Cum 3500 3,390 118.65<br />

4.2 M-25 Cum 2500 3,610 90.25<br />

5.0 Steel Works<br />

5.1 Deformed Reinforcement Steel T 250 27,000 67.50<br />

5.2 Steel liner T 25 70,000 17.50<br />

Sub Total (A) <strong>of</strong> 1 to 5 677.40<br />

6.0 Miscellaneous<br />

6.1 Various Miscellaneous works like<br />

drilling & grouting,wiremesh<br />

reinforcement, airvent pipe, lift<br />

arrangement, other steel works etc.(1-<br />

2% <strong>of</strong> Sub Total (A) depending upon<br />

the site conditions & type <strong>of</strong><br />

structure)<br />

1.50% 10.16<br />

Sub Total (B) <strong>of</strong> 1 to 6 687.56<br />

7.0 Instrumentation (1% <strong>of</strong> Sub -Total<br />

(B)<br />

1% 6.88<br />

8.0 Dewatering (2% <strong>of</strong> Sub -Total (B) 2% 13.75<br />

9.0 Contingencies (3% <strong>of</strong> Sub -Total (B)<br />

except on L.S. items)<br />

10.0 Work Charged Establishment(2% <strong>of</strong><br />

Sub -Total (B) except on L.S. items)<br />

3% 20.63<br />

2% 13.75<br />

Total 742.57


S.<br />

No.<br />

PRESSURE SHAFTS AND PENSTOCKS<br />

DESCRIPTION UNIT QTY. RATE<br />

(in<br />

Rs.)<br />

161<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Amount<br />

(Rs. in<br />

Lakhs)<br />

1.0 Underground excavation Cum 17500 1200 210.00<br />

2.0 Supports System<br />

2.1 Rock bolts M 12,500 400 50.00<br />

2.2 Steel ribs Support T 100 42000 42.00<br />

2.3 Shotcreting Cum 1,400 4000 56.00<br />

3.0 Concrete<br />

3.1 M15 backfill concrete Cum 12,000 2930 351.60<br />

Sub Total (A) <strong>of</strong> 1 to 3 709.60<br />

4.0 Miscellaneous and Ancillary<br />

works<br />

4.1 Various Miscellaneous works<br />

like drilling &<br />

grouting,wiremesh<br />

reinforcement, swellex anchors<br />

etc.(2-3% <strong>of</strong> Sub Total (A)<br />

depending upon the site<br />

conditions & type <strong>of</strong> structure)<br />

2.50% 17.74<br />

Sub Total (B) <strong>of</strong> 1 to 4 727.34<br />

5.0 Instrumentation (1% <strong>of</strong> Sub -<br />

Total (B)<br />

1% 7.27<br />

6.0 Dewatering (1% <strong>of</strong> Sub -Total 1% 7.27<br />

(B)<br />

7.0 Contingencies (3% <strong>of</strong> Sub -<br />

Total (B) except on L.S. items)<br />

8.0 Work Charged<br />

Establishment(2% <strong>of</strong> Sub -Total<br />

(B) except on L.S. items)<br />

3% 21.82<br />

2% 14.55<br />

Total 778.25


S.<br />

No.<br />

POWER HOUSE COMPLEX<br />

162<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

DESCRIPTION UNIT QTY. RATE<br />

(in<br />

Rs.)<br />

1.0 Under Ground Excavation<br />

1.1 Excavation <strong>of</strong> PH cavern, transformer<br />

cum MIV cavern and draft tube gate<br />

Amount<br />

(Rs. in<br />

Lakhs)<br />

Cum 160,000 1000 1600.00<br />

2.0 Supports System<br />

2.1 Rock bolts M 70,000 400 280.00<br />

2.2 Steel ribs Support T 100 42000 42.00<br />

2.3 Shotcreting Cum 7,000 4000 280.00<br />

3.0 Concrete<br />

3.1 M15 backfill concrete Cum 5,000 2930 146.50<br />

3.2 Concrete lining M20 Cum 2,000 3390 67.80<br />

3.3 M25 Cum 60,000 3610 2166.00<br />

4.0 Reinforcement steel T 7,000 27000 1890.00<br />

5.0 Structural Steel for ro<strong>of</strong> trusses T 300 42000 126.00<br />

6.0 Masonry<br />

6.1 Stone Cum 1500 2000 30.00<br />

6.2 Brick Cum 500 2000 10.00<br />

Sub Total (A) <strong>of</strong> 1 to 7 6638.30<br />

7.0 Miscellaneous<br />

7.1 Various Miscellaneous works like site<br />

clearance, drilling &<br />

grouting,wiremesh/steel reinforcement,<br />

flooring, water fp<strong>of</strong>fing system,<br />

swellex anchor, doors, window,<br />

painting, lift arrangement, architectural<br />

works , other metal works etc.(4-5% <strong>of</strong><br />

Sub Total (A) depending upon the site<br />

4.50% 298.72<br />

conditions & type <strong>of</strong> structure)<br />

Sub Total (B) <strong>of</strong> 1 to 8 6937.02<br />

8.0 Instrumentation (1% <strong>of</strong> Sub -Total (B) 1% 69.370235<br />

9.0 Dewatering (2% <strong>of</strong> Sub -Total (B) 2% 138.74047<br />

10.0 Contingencies (3% <strong>of</strong> Sub -Total (B)<br />

except on L.S. items)<br />

3% 208.110705<br />

11.0 Work Charged Establishment(2% <strong>of</strong><br />

Sub -Total (B) except on L.S. items)<br />

2% 138.74047<br />

Total 7491.99


S.<br />

No.<br />

SWITCHYARD<br />

DESCRIPTION UNIT QTY. RATE<br />

(in<br />

Rs.)<br />

163<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Amount<br />

(Rs. in<br />

Lakhs)<br />

1.0 Surface Excavation<br />

1.1 Common excavation Cum 75,000 125 93.75<br />

1.1 Rock excavation Cum 4,000 300 12.00<br />

2.0 Supports System<br />

2.1 Rock bolts M 1,000 400 4.00<br />

2.2 Shotcreting Cum 50 4000 2.00<br />

3.0 Earthwork in filling Cum 25,000 342 85.50<br />

4.0 Concrete<br />

4.1 M15 Cum 1,000 2930 29.30<br />

4.2 M20 Cum 1,000 3390 33.90<br />

4.2 M25 Cum 1,000 3610 36.10<br />

5.0 Deformed Reinforcement Steel T 100 27000 27.00<br />

6.0 Stone/Brick Masonry Cum 300 2000 6.00<br />

Sub Total (A) <strong>of</strong> 1 to 6 329.55<br />

7.0 Miscellaneous<br />

7.1 Various Miscellaneous works like<br />

site clearance, PVC pipes, control<br />

block building works like flooring,<br />

doors, windowsets including water<br />

supply and sewerage, boulder<br />

pitching, metal works, etc.(4-5% <strong>of</strong><br />

Sub Total (A) depending upon the<br />

site conditions & type <strong>of</strong> structure)<br />

4.50% 14.83<br />

Sub Total (B) <strong>of</strong> 1 to 8 344.38<br />

8.0 Dewatering (2% <strong>of</strong> Sub -Total (B) 2% 6.887595<br />

9.0 Contingencies (3% <strong>of</strong> Sub -Total<br />

(B) except on L.S. items)<br />

3% 10.3313925<br />

10.0 Work Charged Establishment(2%<br />

<strong>of</strong> Sub -Total (B) except on L.S.<br />

items)<br />

2% 6.887595<br />

Total 368.49


Sl<br />

No<br />

1.0 Residential Buildings<br />

K-BUILDINGS<br />

Description Plinth<br />

Area(Sqm).<br />

164<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Rs. In lakhs<br />

Rate Unit Amount<br />

1.1 Residential permanent buildings 4134 0.075 Sqm 310.05<br />

Service Charges @31%<br />

1.2 Residential temporary buildings<br />

96.12<br />

4514 0.065 Sqm 293.41<br />

Service Charges @27%<br />

79.22<br />

Total (Residential) 8648 778.80<br />

2.0 Non-Residential Buildings<br />

2.1 Non residential permanent<br />

buildings<br />

4540 0.065 Sqm 295.10<br />

Service Charges @22.5% 66.40<br />

2.2 Non residential and other<br />

purposes temporary buildings<br />

(Sl No. 1,3&4)<br />

5090 0.055 Sqm 279.95<br />

Service Charges @20.5% 57.39<br />

Total( Non-Residential) 9630 698.84<br />

Total(1+2) 18278 1477.63<br />

Add works tax @ 2% 2% 29.55<br />

Total 1507.19


Sl No<br />

Description<br />

1 CAPITAL COST<br />

1.1 Purchase <strong>of</strong> Diesel Generator<br />

Sets (25 KVA) including<br />

anciliary equipments etc.<br />

1.2 Cost <strong>of</strong> transmission line for<br />

construction power<br />

1.2 Water Supply, purification &<br />

distribution arrangements<br />

including purchase <strong>of</strong> water<br />

tankers,filters, cost <strong>of</strong> tanks &<br />

chlorination.<br />

1.4 Providing sewage disposal<br />

and storm water drains in<br />

<strong>of</strong>fice and residential<br />

1.5<br />

complexes.<br />

Providing & fixing <strong>of</strong> fire<br />

fighting equipments.<br />

1.6 Providing telephone,<br />

Telegraph <strong>of</strong>fice, Post <strong>of</strong>fice<br />

and Wireless equipments.<br />

1.7 Providing hospital<br />

equipments.<br />

1.8 Construction <strong>of</strong> children park<br />

and welfare centres for<br />

<strong>of</strong>ficials and labourers.<br />

1.9 Furnishing and equipping <strong>of</strong><br />

rest houses and field hostels<br />

<strong>of</strong> <strong>of</strong>ficers and staff.<br />

1.1 Purchase <strong>of</strong> furniture and<br />

other articles for labour<br />

welfare centres and clubs and<br />

schools.<br />

1.11 Purchase <strong>of</strong> equipment for<br />

quality control/field<br />

Laboratories<br />

165<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

O-MISCELLANEOUS<br />

Rs. In lakhs<br />

Quantity Rate Unit Amount<br />

5.00 2.50 Nos 12.50<br />

10.00 10.00 km 100.00<br />

LS 25.00<br />

LS 25.00<br />

LS 15.00<br />

LS 20.00<br />

LS 15.00<br />

LS 8.00<br />

LS 5.00<br />

LS 5.00<br />

LS 15.00<br />

Sub Total Item 1 245.50<br />

2.0 MAINTENANCE &<br />

SERVICE CHARGES OF<br />

2.1 R&M <strong>of</strong> Diesel Generator sets<br />

4 Nos. for four years.<br />

16.00 4.00 Nos 64.00


R&M <strong>of</strong> Transmission line for<br />

four years.<br />

2.2 R&M <strong>of</strong> water supply<br />

facilities to the staff and<br />

labour colonies for four years<br />

2.3 R&M <strong>of</strong> sanitation and<br />

drainage facilities for <strong>of</strong>fice<br />

and residential compllex and<br />

labour colonies.<br />

2.4 R&M <strong>of</strong> fire fighting<br />

2.5<br />

equipments.<br />

Maint. Of telecommunication<br />

system and post <strong>of</strong>fices.<br />

166<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

10.00 4.00 km 40.00<br />

LS 10.00<br />

LS 8.00<br />

LS 4.00<br />

LS 20.00<br />

2,6 R&M <strong>of</strong> hospitals. LS 16.00<br />

2.7 Maint. <strong>of</strong> parks and welfare<br />

centres, clubs and school.<br />

LS 10.00<br />

2.8 R&M <strong>of</strong> Rest houses and field<br />

hostels.<br />

2.9 R&M <strong>of</strong> research & quality<br />

control laboratories<br />

2.1 Labour welfare compensation<br />

and retrenchment benefits.<br />

LS 8.00<br />

LS 8.00<br />

LS 30.00<br />

2.11 Providing Security & Policing LS 10.00<br />

2.12 R&M <strong>of</strong> Inspection vehicles<br />

and staff cars (25 nos) for four<br />

year<br />

25*4 2.50 year 250.00<br />

2.13 R&M <strong>of</strong> school buses, 4*4 1.80 year 28.80<br />

Ambulance Car etc. (4 nos)<br />

for for four year<br />

Sub Total Item 2 506.80<br />

3 MISCELLANEOUS<br />

3.1 Foundation stone laying<br />

LS 10.00<br />

ceremony, inaguration and<br />

3.2<br />

visit <strong>of</strong> Dignitaries.<br />

Railway siding LS 20.00<br />

3.3 Installation and maintenance<br />

<strong>of</strong> Petrol/Diesel Pumps<br />

LS 16.00<br />

3.4 Providing<br />

measures<br />

anti malarial<br />

LS 2.00<br />

3.5 Procurement<br />

leterature.<br />

<strong>of</strong> technical<br />

LS 2.00<br />

3.6 Model Exhibits LS 4.00<br />

3.7 Canteen facilities and cooperative<br />

stores.<br />

LS 20.00


3.8 Photographic and<br />

Cinemagraphic equipment<br />

and their maintenance<br />

167<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

LS 8.00<br />

3.9 Group insurance LS 15.00<br />

3.1 Publication and pamplets LS 2.00<br />

3.11 Creches LS 2.00<br />

3.12 Compensation for accident LS 8.00<br />

3.13 Training <strong>of</strong> personnels aboard<br />

includig study course and visit<br />

LS 15.00<br />

3.14 Award to workers LS 1.5<br />

Sub Total Item 3 125.50<br />

Grand Total Item (1+2+3) 877.80


SI<br />

NO.<br />

R - COMMUNUCATION<br />

168<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Rs. In lakhs<br />

Description Quantity Rate Unit Amount<br />

1 Proposed new roads<br />

Approach road to Lower dam site,<br />

DT, Top <strong>of</strong> Dam<br />

Approach road to Upper dam site,<br />

DT, Top <strong>of</strong> Dam<br />

15.0 80.00 Km 1200.00<br />

6.0 80.00 Km 480.00<br />

Approach road to power house site 2.0 80.00 Km 160.00<br />

Switch yard 1.0 80.00 Km 80.00<br />

Surgeshaft,Adit I,II,III 9.0 80.00 Km 720.00<br />

Colony Roads 2.0 75.00 Km 150.00<br />

3 Proposed new bailey bridges Cl 30<br />

At Upper dam site 30.0 2.25 m 67.50<br />

At Upper dam site 30.0 2.25 m 67.50<br />

On Pokhram Chu (2 no) 40.0 2.25 m 90.00<br />

On <strong>Rangyong</strong> Chu 20.0 2.25 m 45.00<br />

4 Proposed Culverts<br />

Culverts( 4nos) 40.0 1.00 m 40.00<br />

Grand Total 3100.00<br />

Add works tax @ 2% 2% 62.00<br />

Total 3162.00


Q-Spl T&P for Infrastructure Development<br />

S.No. Description <strong>of</strong> equipment Quantity<br />

(Nos.)<br />

169<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Cost<br />

(Rs in<br />

Lacs)<br />

Total<br />

Cost (Rs<br />

in Lacs)<br />

1 Hydraulic Excavator, 1.0 cum. 1 50.00 50.00<br />

2 Loader cum Excavator, 1.0/0.25<br />

cum.<br />

1 18.00 18.00<br />

3 Mini excavator 0.3 cum 1 25.00 25.00<br />

4 Multi utility (Skid Steer loader) 1 40.00 40.00<br />

5 Front End loader 2 cum 1 24.00 24.00<br />

6 Crawler Dozer, 100 FHP 2 50.00 100.00<br />

7 Crawler Dozer, 200 FHP 1 85.00 85.00<br />

8 Wheel Dozer, 130 FHP 1 95.00 95.00<br />

9 Motor Grader, 145 FHP 1 60.00 60.00<br />

10 Diamond Core Drill (Mechanical) 2 15.00 30.00<br />

11 Diamond Core Drill (Hyd) 1 60.00 60.00<br />

12 Air Track/Wagon Drill 2 15.00 30.00<br />

13 Jack Hammer/Pavement Breaker 5 0.35 1.75<br />

14 Compressed Air(cfm) 2000 0.0125 25.00<br />

15 Mobile Crane, 10 t Pick & Carry 2 10.00 20.00<br />

16 Mobile Crane, 20 t (rough Terrain) 1 70.00 70.00<br />

17 Road Roller, 8/10 t 1 10.00 10.00<br />

18 Dewatering Pump L.S 10.00 10.00<br />

19 Tipper 4.5/6.0 cum. 10 9.50 95.00<br />

20 Truck, 8/10 t 4 7.50 30.00<br />

21 Low Bed Tractor Trailor, 20 t 1 30.00 30.00<br />

22 Concrete Mixer, 14/10 cft 2 1.50 3.00<br />

23 Explosive Van, 5/7 t 1 10.00 10.00<br />

24 Water Tanker/Sprinkler, 10 KL 1 12.00 12.00<br />

25 Petrol/Diesel Tanker, 10 KL 1 12.00 12.00<br />

26 Bus/Mini Bus 5 8.00 40.00<br />

27 Car/MUV 2 4.00 8.00<br />

28 Jeep (Petrol/Diesel) 20 4.00 80.00<br />

29 Ambulance 2 8.00 16.00<br />

30 Workshop Equipt. L.S 20.00 20.00<br />

31 Fire Tender 1 15.00 15.00<br />

32 Recovery Van 1 5.00 5.00<br />

33 Pick up Van/L.C.V 2 5.00 10.00<br />

34 Motor Boat 2 5.00 10.00<br />

Total 1149.75


170<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

DISTRIBUTION OF COST UNDER HEAD Q - SPECIAL T & P AND V -<br />

RECEIPT & RECOVERIES<br />

Cost <strong>of</strong> equipments excluding inspection<br />

vehicles<br />

(Rs. In lakhs)<br />

Cost Q R&R<br />

990.75 247.69 185.77<br />

Cost <strong>of</strong> inspection vehicles 159.00 159.00 31.80<br />

Provision under head Q - Spl. T&P 1149.75 406.69<br />

Recoveries to be shown under V- Receipt and<br />

Recoveries<br />

217.57


V - RECEIPT & RECOVERIES<br />

171<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

S. No. Item Amount<br />

(Rs. In Lakhs)<br />

1. Recovery from the Sale <strong>of</strong> Equipments 217.57<br />

2 Recovery from the DG sets 2.50<br />

3 Recovery from Temporary Buildings 106.50<br />

Total 326.56


COST ESTIMATE OF E&M WORKS<br />

Generator, Turbine and Accessories<br />

S.No. Item Particulars Qty Unit Rate Amount Excise<br />

Duty*<br />

172<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Annex-I (page 1 <strong>of</strong> 2)<br />

Total<br />

(Rs % Amou (Rs<br />

Lakh)<br />

nt Lakh)<br />

1 2 3 3(a) 4 5 6 7 5+7<br />

1 (a) Generating units and<br />

Bus Ducts 3 X 47 MW,<br />

500 rpm, Head 723.18<br />

meters<br />

2 Step up transformer<br />

11/220 KV, 20MVA,<br />

single phase bank<br />

3 Auxiliary Electrical<br />

Equipment for <strong>Power</strong><br />

Stations (Except<br />

Transformer) (5% <strong>of</strong><br />

item 1)<br />

3 no. 3500<br />

Rs/KW<br />

10 no. 250<br />

Rs/KVA<br />

4 Auxiliary Equipment &<br />

Services for <strong>Power</strong><br />

stations (5% <strong>of</strong> Item 1)<br />

5 Switchyard (220KV) 6 bays 120<br />

6 Spares (5% <strong>of</strong> item 1<br />

and 3% <strong>of</strong> item 2 to 5 )<br />

4935.00 16 789.60 5724.60<br />

500 16 80 580<br />

246.75 16 39.48 286.23<br />

246.75 16 39.48 286.23<br />

720.00 16 115.20 835.20<br />

247<br />

lacs/bay<br />

51.41 298.16 16 47.70 345.86<br />

7 Subtotal(1-6) 8058.12<br />

8 Central Sales tax** 4%<br />

<strong>of</strong> item 7<br />

9 Transportation &<br />

Insurance 6% <strong>of</strong> item 7<br />

10 Erection &<br />

commissioning 8% <strong>of</strong><br />

item 7 except spares<br />

277.87 322.32<br />

483.49<br />

616.98<br />

11 Subtotal (7-10) 9480.91<br />

12<br />

13<br />

14<br />

15<br />

16<br />

17<br />

Total <strong>of</strong> FC (XLPE<br />

Cable and Termination<br />

kit) in INR (As per<br />

Annexure-II)<br />

Custom Duty @22% <strong>of</strong><br />

item 12<br />

Marine frieght and<br />

insurance @6% Approx<br />

<strong>of</strong> 12<br />

Inland Frieght and<br />

insurance 6% <strong>of</strong> item 12<br />

Erection &<br />

commissioning 8% <strong>of</strong><br />

item 12 excluding spares<br />

Subtotal <strong>of</strong> FC ( item<br />

12-16 in INR)<br />

included in above item 12<br />

826.73<br />

49.60<br />

49.60<br />

65.12<br />

991.06


18<br />

Subtotal <strong>of</strong> item no<br />

11+17(Foreign plus<br />

indian component)<br />

19 Establishment,<br />

Contingency, other<br />

charges 11% <strong>of</strong> Item 18<br />

Excluding duties<br />

GRAND TOTAL (In<br />

Lakh)<br />

S.No.<br />

173<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

10471.98<br />

838.70<br />

11310.67<br />

Annex-II<br />

Dec 2003 price level<br />

Item Particulars Qty Rate Amount<br />

Custom<br />

Duty*<br />

Amou<br />

nt(<br />

Total<br />

( Lakh<br />

Lakh (Lakh<br />

( USD) USD) Rate% USD) USD)<br />

1<br />

2 3 4 5 6 7 5+7<br />

2<br />

XLPE Cable (220 kV) 2750 m<br />

280<br />

USD/m 7.70 22 1.69 9.39<br />

3<br />

XLPE Cable termination<br />

Kit 20 no. 35000 7.00 22 1.54 8.54<br />

4<br />

Spares for above @ 3%<br />

<strong>of</strong> 2 0.23 22 0.05 0.28<br />

Total 18.21<br />

*Custom duty in case <strong>of</strong> imported Items<br />

**Not applicable for Imported Items<br />

1 USD conversion rate as on 23/12/03= Rs. 45.400


S.No. Item Particulars Qty Un<br />

it<br />

<strong>Power</strong> Evacuation system<br />

Rate Amount E xcise<br />

Duty*<br />

(Rs<br />

Lakh)<br />

174<br />

(Rs<br />

Lakh)<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Annex-III (page 1 <strong>of</strong> 1)<br />

Rate Amou<br />

nt<br />

Total<br />

(Rs<br />

Lakh)<br />

1 2 3 4 5 6 7 5+7<br />

1 1 no 220kV Double<br />

Circuit line (<strong>of</strong><br />

approximately 30 kms)<br />

30 km 30<br />

lacs/km<br />

900.00 16 144.00 1044.00<br />

2 Spares ( 3% <strong>of</strong> 1) 27 16 4.32 31.32<br />

3 Subtotal(1) 1075.32<br />

4 Central Sales tax 4% <strong>of</strong><br />

item 3<br />

5 Transportation &<br />

Insurance 6% <strong>of</strong> item 3<br />

7 Erection &<br />

commissioning 8% <strong>of</strong><br />

item 3 except spares<br />

37.08 43.01<br />

64.52<br />

83.52<br />

8 Subtotal(2) 1266.37<br />

9 Establishment,<br />

Contingency, other<br />

charges 11% <strong>of</strong> Item 3<br />

excluding duties<br />

GRAND TOTAL (In<br />

Lakh)<br />

101.97<br />

1368.34


Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

CHAPTER – XIII<br />

ECONOMIC EVALUATION


13.1 GENERAL<br />

CHAPTER – XIII<br />

ECONOMIC EVALUATION<br />

175<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

The Project has been contemplated as a run-<strong>of</strong>f the river scheme on river <strong>Rangyong</strong><br />

Chu. The project is estimated to cost Rs. 799.50 crores excluding IDC at June 2003<br />

Price Level. Sale price <strong>of</strong> energy generated at powerhouse bus bars has been worked<br />

out as 3.07 Rs. per unit with free power to home state (Table 13.2) & Rs. 2.70 per unit<br />

without free power to home state (Table 13.2-A).<br />

13.2 ECONOMIC JUSTIFICATION<br />

The energy generation <strong>of</strong> the project with an installed capacity <strong>of</strong> 3X47 MW has been<br />

estimated at 639.52 MU in a 90% dependable year.<br />

13.3 COST ESTIMATES AND PHASING OF EXPENDITURES<br />

The cost <strong>of</strong> construction <strong>of</strong> the project has been estimated at June 2003 price level with a<br />

construction schedule <strong>of</strong> 5.5 years including 1.5 years for Infrastructure works.<br />

The estimated Present Day Cost <strong>of</strong> the project is Rs. 799.50 Crores without IDC at June<br />

2003 Price level.<br />

13.4 PHASING OF EXPENDITURE<br />

The phasing <strong>of</strong> expenditure has been worked out on the basis <strong>of</strong> anticipated construction<br />

programme.


176<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

The phasing <strong>of</strong> expenditure without IDC for present day cost is shown as below:<br />

Year Estimated Cost at June 2003 P.L.<br />

(Rs. in Crores)<br />

1 st 79.95<br />

2 nd 111.93<br />

3 rd<br />

159.90<br />

4 th 223.86<br />

5 th 159.90<br />

5.5 th 63.96<br />

Net Cost 799.50<br />

13.5 INTEREST DURING CONSTRUCTION (IDC)<br />

Based upon above phasing <strong>of</strong> expenditure the interest during construction (IDC) have<br />

been calculated with 70:30 debt equity ratio and 10.0% interest on loan for estimated<br />

Present Day cost <strong>of</strong> the project.<br />

The estimated IDC with estimated present cost is Rs. 91.32 Crores<br />

13.6 COST OF ENERGY GENERATION<br />

The cost <strong>of</strong> energy generation has been calculated for the annual energy generation in a<br />

90% dependable year based upon following assumptions.<br />

1. Debt-equity ratio 70 : 30<br />

2. Annual interest rate on loan 10.0%<br />

3. Return on equity 16%<br />

4. Annual interest rate on working capital 10.0%<br />

5. O&M Charges 1.5% <strong>of</strong> Project Cost<br />

6. Free power to Home State 12% <strong>of</strong> the energy<br />

available after losses


177<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

7. Depreciation considered 1/12 th <strong>of</strong> loan amount<br />

during loan repayment<br />

period.<br />

The levellised tariff <strong>of</strong> the Project at present day cost works out to be Rs. 2.49 Per Unit<br />

with free power to home state (Table 13.3) & Rs 2.19 per unit without free power to<br />

home state. (Table 13.3-A).


178<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47MW)<br />

STATEMENT SHOWING IDC CALCULATION AT PRESENT DAY COST (APRIL 2003 LEVEL)<br />

Table-13.1<br />

PRESENT DAY COST 799.50 Crs. Transmission Works 13.68 Crores<br />

Civil Works 672.71 Crs. Electrical Works 113.11 Crs.<br />

INTEREST RATE PER ANNUM 10% Transmission cost 13.68 Crs.<br />

(Rs. in Crs.)<br />

Present Day Amount Receivable I.D.C Loan Outstanding Amount Receivable<br />

Year Cost Equity Loan at the end <strong>of</strong> Equity Loan<br />

year (for the year)<br />

1 2 3 4 5 6 7 8<br />

1 79.95 79.95 79.95<br />

2 111.93 111.93 111.93<br />

3 159.90 75.37 84.53 2.23 86.77 75.37 86.77<br />

4 223.86 223.86 19.87 330.50 243.73<br />

5 159.90 159.90 41.05 531.45 200.95<br />

5.5 63.96 63.96 28.17 623.58 92.13<br />

Total 799.50 267.25 532.26 91.32 267.25 623.58<br />

IDC 91.32 Crs. Equity 267.25 Crs.<br />

Net cost <strong>of</strong> the project 890.82 Crs. Loan 623.58 Crs.


179<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

TABLE-13.2<br />

UNIT COST OF ENERGY AT BUS BAR AT CURRENT PRICE LEVEL<br />

(June 2003 P.L.)<br />

(Based on 16% return on equity & 10% interest on loan, 10% interest on working capital)<br />

1 Installed capacity 141 MW<br />

2 Cost <strong>of</strong> the Project (Net) Rs. 799.50 Crores<br />

3 Interest During Construction Rs. 91.32 Crores<br />

4 Total Cost <strong>of</strong> Project Rs. 890.82 Crores<br />

(Including IDC)<br />

a) Equity 30% Rs. 267.25 Crores<br />

b) Loan 70% Rs. 623.58 Crores<br />

5 Annual Energy Generation 639.52 MU<br />

6 0.7% As Auxiliary Consumption <strong>of</strong> No. 5 0.70% 4.48 MU<br />

7 Energy Available After Auxiliary Consumption 635.04 MU<br />

8 0.5% As Transformer Loss <strong>of</strong> No. 7 0.50% 3.18 MU<br />

9 Energy Available After Transformer Loss 631.87 MU<br />

10 Free <strong>Power</strong> to Home State 12% 75.82 MU<br />

11<br />

Energy Available After Allowing Free<br />

<strong>Power</strong> 556.04 MU<br />

12 Fixed and Running Charges<br />

A) Capacity Charges<br />

a) Interest on Loan 10.00% 59.76 Crores<br />

b) Depreciation Charges<br />

(Limited to 1/12 th <strong>of</strong> Loan Amount)<br />

51.96 Crores<br />

SUB-<br />

TOTAL 111.72 Crores<br />

B) Energy Charges<br />

a) O&M Charges 1.50% 13.36 Crores<br />

b) Return on Equity 16.00% 42.76 Crores<br />

SUB-TOTAL 56.12 Crores<br />

c) Interest on Working Capital 10.00% 2.96 Crores<br />

I) O&M Charges for 1 month 1.11<br />

II) 2 Months Average Billing 28.47<br />

TOTAL Rs. 170.80 Crores<br />

13 Sale Price at Bus Bar/Unit 3.07 Rs.<br />

14 Cost <strong>of</strong> Generation at Bus Bar/Unit 2.03 Rs.<br />

(Without Allowing Free <strong>Power</strong> to Home State and Return on Equity)<br />

Note : This unit rate is excluding water cess, income tax incentive, penalties etc.


180<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

TABLE-13.2 A<br />

UNIT COST OF ENERGY AT BUS BAR AT CURRENT PRICE LEVEL<br />

(June 2003 P.L.)WITHOUT FREE POWER TO HOME STATE<br />

(Based on 16% return on equity & 10% interest on loan, 10% interest on working capital)<br />

1 Installed capacity 141 MW<br />

2 Cost <strong>of</strong> the Project (Net) Rs. 799.50 Crores<br />

3 Interest During Construction Rs. 91.32 Crores<br />

4 Total Cost <strong>of</strong> Project Rs. 890.82 Crores<br />

(Including IDC)<br />

a) Equity 30% Rs. 267.25 Crores<br />

b) Loan 70% Rs. 623.58 Crores<br />

5 Annual Energy Generation 639.52 MU<br />

6 0.7% As Auxiliary Consumption <strong>of</strong> No. 5 0.70% 4.48 MU<br />

7 Energy Available After Auxiliary Consumption 635.04 MU<br />

8 0.5% As Transformer Loss <strong>of</strong> No. 7 0.50% 3.18 MU<br />

9 Energy Available After Transformer Loss 631.87 MU<br />

10 Free <strong>Power</strong> to Home State 0% 0.00 MU<br />

11<br />

Energy Available After Allowing Free<br />

<strong>Power</strong> 631.87 MU<br />

12 Fixed and Running Charges<br />

A) Capacity Charges<br />

a) Interest on Loan 10.00% 59.76 Crores<br />

b) Depreciation Charges<br />

(Limited to 1/12 th <strong>of</strong> Loan Amount)<br />

51.96 Crores<br />

SUB-<br />

TOTAL 111.72 Crores<br />

B) Energy Charges<br />

a) O&M Charges 1.50% 13.36 Crores<br />

b) Return on Equity 16.00% 42.76 Crores<br />

SUB-TOTAL 56.12 Crores<br />

c) Interest on Working Capital 10.00% 2.96 Crores<br />

I) O&M Charges for 1 month 1.11<br />

II) 2 Months Average Billing 28.47<br />

TOTAL Rs. 170.80 Crores<br />

13 Sale Price at Bus Bar/Unit 2.70 Rs.<br />

14 Cost <strong>of</strong> Generation at Bus Bar/Unit 2.03 Rs.<br />

(Without Allowing Free <strong>Power</strong> to Home State and Return on Equity)<br />

Note : This unit rate is excluding water cess, income tax incentive, penalties etc.


181<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Table 13.3<br />

CALCULATION OF ENERGY RATE WITH PRESENT COST (JUNE 2003 PRICE LEVEL) AS PER TARIFF NOTIFICATION<br />

Annual Generation in a 90% dependable 639.52 MU O&M Charges 1.50%<br />

Annual Generation after allowing losses & free Rate <strong>of</strong> increase <strong>of</strong> O&M Charges after 1st Year (Compounded) 6%<br />

power to home state in a 90% dependable year 556.04 MU Interest rate on Loan 10.0%<br />

Total cost including IDC Rs. 890.82 Crores Interest rate on Working Capital 10.00%<br />

Equity 30% Rs. 267.25 Crores Return on Equity 16%<br />

Loan 70% Rs. 623.58 Crores Discounting rate 12%<br />

Year Capacity Charges Charges Per Unit Discounting Discounted<br />

Out- (Rs.in Cr.) (Rs.in Cr.) (Rs. per Unit) Factor Tariff<br />

standing<br />

Loan<br />

(Rs.in Cr.)<br />

Interest on<br />

loan<br />

Depre-<br />

ciation<br />

Total Return on<br />

equity<br />

O&M<br />

Charges<br />

O&M<br />

for1<br />

month<br />

Interest on<br />

Working<br />

Capital<br />

Interest Total Capacity<br />

charges<br />

Energy<br />

charges<br />

Total (Paisa per<br />

Unit)<br />

2 months<br />

Average<br />

Billing<br />

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16<br />

1 623.58 59.76 51.96 111.72 42.76 13.36 1.11 28.47 2.96 59.08 2.01 1.06 3.07 1.0000 3.07<br />

2 571.61 54.56 51.96 106.53 42.76 14.16 1.18 27.72 2.89 59.81 1.92 1.08 2.99 0.8929 2.67<br />

3 519.65 49.37 51.96 101.33 42.76 15.01 1.25 26.99 2.82 60.60 1.82 1.09 2.91 0.7972 2.32<br />

4 467.68 44.17 51.96 96.13 42.76 15.91 1.33 26.26 2.76 61.43 1.73 1.10 2.83 0.7118 2.02<br />

5 415.72 38.97 51.96 90.94 42.76 16.87 1.41 25.54 2.69 62.32 1.64 1.12 2.76 0.6355 1.75<br />

6 363.75 33.78 51.96 85.74 42.76 17.88 1.49 24.84 2.63 63.27 1.54 1.14 2.68 0.5674 1.52<br />

7 311.79 28.58 51.96 80.55 42.76 18.95 1.58 24.14 2.57 64.29 1.45 1.16 2.60 0.5066 1.32<br />

8 259.82 23.38 51.96 75.35 42.76 20.09 1.67 23.45 2.51 65.36 1.36 1.18 2.53 0.4523 1.14<br />

9 207.86 18.19 51.96 70.15 42.76 21.30 1.77 22.78 2.46 66.51 1.26 1.20 2.46 0.4039 0.99<br />

10 155.89 12.99 51.96 64.96 42.76 22.58 1.88 22.12 2.40 67.73 1.17 1.22 2.39 0.3606 0.86<br />

11 103.93 7.79 51.96 59.76 42.76 23.93 1.99 21.47 2.35 69.04 1.07 1.24 2.32 0.3220 0.75<br />

12 51.96 2.60 51.96 54.56 42.76 25.37 2.11 20.83 2.29 70.42 0.98 1.27 2.25 0.2875 0.65<br />

13 0.00 0.00 7.75 7.75 42.76 26.89 2.24 13.16 1.54 71.19 0.14 1.28 1.42 0.2567 0.36<br />

14 0.00 0.00 7.75 7.75 42.76 28.50 2.38 13.43 1.58 72.84 0.14 1.31 1.45 0.2292 0.33<br />

15 0.00 0.00 7.75 7.75 42.76 30.21 2.52 13.72 1.62 74.59 0.14 1.34 1.48 0.2046 0.30<br />

16 0.00 0.00 7.75 7.75 42.76 32.02 2.67 14.03 1.67 76.45 0.14 1.37 1.51 0.1827 0.28<br />

17 0.00 0.00 7.75 7.75 42.76 33.95 2.83 14.36 1.72 78.42 0.14 1.41 1.55 0.1631 0.25<br />

18 0.00 0.00 7.75 7.75 42.76 35.98 3.00 14.71 1.77 80.51 0.14 1.45 1.59 0.1456 0.23<br />

19 0.00 0.00 7.75 7.75 42.76 38.14 3.18 15.08 1.83 82.73 0.14 1.49 1.63 0.1300 0.21<br />

20 0.00 0.00 7.75 7.75 42.76 40.43 3.37 15.47 1.88 85.07 0.14 1.53 1.67 0.1161 0.19<br />

21 0.00 0.00 7.75 7.75 42.76 42.85 3.57 15.88 1.95 87.56 0.14 1.57 1.71 0.1037 0.18<br />

22 0.00 0.00 7.75 7.75 42.76 45.43 3.79 16.32 2.01 90.20 0.14 1.62 1.76 0.0926 0.16<br />

23 0.00 0.00 7.75 7.75 42.76 48.15 4.01 16.79 2.08 92.99 0.14 1.67 1.81 0.0826 0.15<br />

24 0.00 0.00 7.75 7.75 42.76 51.04 4.25 17.28 2.15 95.95 0.14 1.73 1.86 0.0738 0.14<br />

25 0.00 0.00 7.75 7.75 42.76 54.10 4.51 17.81 2.23 99.09 0.14 1.78 1.92 0.0659 0.13<br />

26 0.00 0.00 7.75 7.75 42.76 57.35 4.78 18.36 2.31 102.42 0.14 1.84 1.98 0.0588 0.12<br />

27 0.00 0.00 7.75 7.75 42.76 60.79 5.07 18.95 2.40 105.95 0.14 1.91 2.04 0.0525 0.11<br />

28 0.00 0.00 7.75 7.75 42.76 64.44 5.37 19.57 2.49 109.69 0.14 1.97 2.11 0.0469 0.10<br />

29 0.00 0.00 7.75 7.75 42.76 68.30 5.69 20.23 2.59 113.66 0.14 2.04 2.18 0.0419 0.09<br />

30 0.00 0.00 7.75 7.75 42.76 72.40 6.03 20.93 2.70 117.86 0.14 2.12 2.26 0.0374 0.08<br />

31 0.00 0.00 7.75 7.75 42.76 76.75 6.40 21.68 2.81 122.31 0.14 2.20 2.34 0.0334 0.08<br />

32 0.00 0.00 7.75 7.75 42.76 81.35 6.78 22.46 2.92 127.04 0.14 2.28 2.42 0.0298 0.07<br />

33 0.00 0.00 7.75 7.75 42.76 86.23 7.19 23.30 3.05 132.04 0.14 2.37 2.51 0.0266 0.07<br />

34 0.00 0.00 7.75 7.75 42.76 91.41 7.62 24.18 3.18 137.35 0.14 2.47 2.61 0.0238 0.06<br />

35 0.00 0.00 7.75 7.75 42.76 96.89 8.07 25.12 3.32 142.97 0.14 2.57 2.71 0.0212 0.06<br />

TOTAL 9.1566 22.82<br />

(A) (B)<br />

Note: The charges per unit is exclusive <strong>of</strong> water cess, spares, incentive & Income Tax etc. Levellised Tariff =(B)/(A) 2.49


CALCULATION OF ENERGY RATE WITH PRESENT COST (JUNE 2003 PRICE LEVEL) AS PER TARIFF NOTIFICATION<br />

182<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

Table 13.3A<br />

WITHOUT FREE POWER TO HOME STATE<br />

Annual Generation in a 90% dependable year 639.52 MU O&M Charges 1.50%<br />

Annual Generation after allowing losses Rate <strong>of</strong> increase <strong>of</strong> O&M Charges after 1st Year (Compounded) 6%<br />

in a 90% dependable year 631.87 MU Interest rate on Loan 10.0%<br />

Total cost including IDC Rs. 890.82 Crores Interest rate on Working Capital 10.00%<br />

Equity 30% Rs. 267.25 Crores Return on Equity 16%<br />

Loan 70% Rs. 623.58 Crores Discounting rate 12%<br />

Year Capacity Charges(Rs.in Cr.) (Rs.in Cr.) Charges Per Unit (Rs. per Unit) Discounting Discounted<br />

Out- standing<br />

Loan(Rs.in<br />

Cr.)<br />

Interest on<br />

loan<br />

Depre-<br />

ciation Total<br />

Return<br />

on<br />

equity<br />

O&M<br />

Charges<br />

O&M<br />

for1<br />

month<br />

Interest on<br />

Working<br />

Capital Interest Total<br />

Capacity<br />

charges<br />

Energy<br />

charges Total Factor<br />

(Paisa<br />

Tariff per<br />

Unit)<br />

2 months<br />

Average<br />

Billing<br />

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16<br />

1 623.58 59.76 51.96 111.72 42.76 13.36 1.11 28.47 2.96 59.08 1.77 0.94 2.70 1.0000 2.70<br />

2 571.61 54.56 51.96 106.53 42.76 14.16 1.18 27.72 2.89 59.81 1.69 0.95 2.63 0.8929 2.35<br />

3 519.65 49.37 51.96 101.33 42.76 15.01 1.25 26.99 2.82 60.60 1.60 0.96 2.56 0.7972 2.04<br />

4 467.68 44.17 51.96 96.13 42.76 15.91 1.33 26.26 2.76 61.43 1.52 0.97 2.49 0.7118 1.77<br />

5 415.72 38.97 51.96 90.94 42.76 16.87 1.41 25.54 2.69 62.32 1.44 0.99 2.43 0.6355 1.54<br />

6 363.75 33.78 51.96 85.74 42.76 17.88 1.49 24.84 2.63 63.27 1.36 1.00 2.36 0.5674 1.34<br />

7 311.79 28.58 51.96 80.55 42.76 18.95 1.58 24.14 2.57 64.29 1.27 1.02 2.29 0.5066 1.16<br />

8 259.82 23.38 51.96 75.35 42.76 20.09 1.67 23.45 2.51 65.36 1.19 1.03 2.23 0.4523 1.01<br />

9 207.86 18.19 51.96 70.15 42.76 21.30 1.77 22.78 2.46 66.51 1.11 1.05 2.16 0.4039 0.87<br />

10 155.89 12.99 51.96 64.96 42.76 22.58 1.88 22.12 2.40 67.73 1.03 1.07 2.10 0.3606 0.76<br />

11 103.93 7.79 51.96 59.76 42.76 23.93 1.99 21.47 2.35 69.04 0.95 1.09 2.04 0.3220 0.66<br />

12 51.96 2.60 51.96 54.56 42.76 25.37 2.11 20.83 2.29 70.42 0.86 1.11 1.98 0.2875 0.57<br />

13 0.00 0.00 7.75 7.75 42.76 26.89 2.24 13.16 1.54 71.19 0.12 1.13 1.25 0.2567 0.32<br />

14 0.00 0.00 7.75 7.75 42.76 28.50 2.38 13.43 1.58 72.84 0.12 1.15 1.28 0.2292 0.29<br />

15 0.00 0.00 7.75 7.75 42.76 30.21 2.52 13.72 1.62 74.59 0.12 1.18 1.30 0.2046 0.27<br />

16 0.00 0.00 7.75 7.75 42.76 32.02 2.67 14.03 1.67 76.45 0.12 1.21 1.33 0.1827 0.24<br />

17 0.00 0.00 7.75 7.75 42.76 33.95 2.83 14.36 1.72 78.42 0.12 1.24 1.36 0.1631 0.22<br />

18 0.00 0.00 7.75 7.75 42.76 35.98 3.00 14.71 1.77 80.51 0.12 1.27 1.40 0.1456 0.20<br />

19 0.00 0.00 7.75 7.75 42.76 38.14 3.18 15.08 1.83 82.73 0.12 1.31 1.43 0.1300 0.19<br />

20 0.00 0.00 7.75 7.75 42.76 40.43 3.37 15.47 1.88 85.07 0.12 1.35 1.47 0.1161 0.17<br />

21 0.00 0.00 7.75 7.75 42.76 42.85 3.57 15.88 1.95 87.56 0.12 1.39 1.51 0.1037 0.16<br />

22 0.00 0.00 7.75 7.75 42.76 45.43 3.79 16.32 2.01 90.20 0.12 1.43 1.55 0.0926 0.14<br />

23 0.00 0.00 7.75 7.75 42.76 48.15 4.01 16.79 2.08 92.99 0.12 1.47 1.59 0.0826 0.13<br />

24 0.00 0.00 7.75 7.75 42.76 51.04 4.25 17.28 2.15 95.95 0.12 1.52 1.64 0.0738 0.12<br />

25 0.00 0.00 7.75 7.75 42.76 54.10 4.51 17.81 2.23 99.09 0.12 1.57 1.69 0.0659 0.11<br />

26 0.00 0.00 7.75 7.75 42.76 57.35 4.78 18.36 2.31 102.42 0.12 1.62 1.74 0.0588 0.10<br />

27 0.00 0.00 7.75 7.75 42.76 60.79 5.07 18.95 2.40 105.95 0.12 1.68 1.80 0.0525 0.09<br />

28 0.00 0.00 7.75 7.75 42.76 64.44 5.37 19.57 2.49 109.69 0.12 1.74 1.86 0.0469 0.09<br />

29 0.00 0.00 7.75 7.75 42.76 68.30 5.69 20.23 2.59 113.66 0.12 1.80 1.92 0.0419 0.08<br />

30 0.00 0.00 7.75 7.75 42.76 72.40 6.03 20.93 2.70 117.86 0.12 1.87 1.99 0.0374 0.07<br />

31 0.00 0.00 7.75 7.75 42.76 76.75 6.40 21.68 2.81 122.31 0.12 1.94 2.06 0.0334 0.07<br />

32 0.00 0.00 7.75 7.75 42.76 81.35 6.78 22.46 2.92 127.04 0.12 2.01 2.13 0.0298 0.06<br />

33 0.00 0.00 7.75 7.75 42.76 86.23 7.19 23.30 3.05 132.04 0.12 2.09 2.21 0.0266 0.06<br />

34 0.00 0.00 7.75 7.75 42.76 91.41 7.62 24.18 3.18 137.35 0.12 2.17 2.30 0.0238 0.05<br />

35 0.00 0.00 7.75 7.75 42.76 96.89 8.07 25.12 3.32 142.97 0.12 2.26 2.39 0.0212 0.05<br />

TOTAL 9.1566 20.08<br />

(A) (B)<br />

Note: The charges per unit is exclusive <strong>of</strong> water cess, spares, incentive & Income Tax etc. Levellised Tariff =(B)/(A) 2.19


Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

PLATES


ELEVATION IN METERS<br />

SCHEMATIC DIAGRAM SHOWING CASCADE DEVELOPMENT OF TEESTA RIVER BASIN (SIKKIM)<br />

3500<br />

3000<br />

2500<br />

2000<br />

1500<br />

1000<br />

500<br />

000<br />

TEESTA PROJECT<br />

STAGE -VI<br />

SALENTFEATURES:-<br />

1. CATCHMENT AREA 4874sqkm<br />

2. DISCHARGE(Dependable) 93CUMECS<br />

3. F.R.L. 341m.<br />

4. TYPE OF DAM(Conc.GravityDam)<br />

5. T.W.L. 253.5om.<br />

6. AVERAGE GROSS HEAD 84.50m.<br />

7. LENGTH OF TUNNEL 3.50km.<br />

8. FIRM POWER 55.50MW.<br />

9. PROPOSED INSTALLED<br />

CAPACITY 360MW.<br />

11O<br />

UNDER CONST.BY NHPC<br />

TEESTA PROJECT<br />

STAGE -V<br />

SALENTFEATURES:-<br />

1. CATCHMENT AREA 4336sqkm<br />

2. DISCHARGE(Dependable) 60cumecs<br />

3. F.R.L. 579m.<br />

4. TYPE OF DAM-Conc.GravityDam<br />

5. T.W.L. 359.5m.<br />

6. AVERAGE GROSS HEAD 216.73m.<br />

7. LENGTH OF TUNNEL 18km.<br />

8. FIRM POWER 100mw.<br />

9. PROPOSED INSTALLED<br />

CAPACITY 510mw.<br />

100 90 80 70<br />

TEESTA PROJECT<br />

STAGE -II<br />

SALENTFEATURES:-<br />

1. CATCHMENT AREA 1772sqkms<br />

2. DISCHARGE(Dependable)9.29cumecs.<br />

3. F.R.L. 2287m.<br />

4. TYPE OF DAM-Conc.GravityDam<br />

5. T.W.L. 1592m.<br />

6. AVERAGE GROSS HEAD 683m.<br />

7. LENGTH OF TUNNEL 11.60km.<br />

8. FIRM POWER 57.38mw.<br />

9. PROPOSED INSTALLED<br />

CAPACITY 330mw.<br />

TEESTA PROJECT<br />

STAGE -III<br />

SALENTFEATURES:-<br />

1. CATCHMENT AREA 2787sqkm.<br />

2. DISCHARGE(Dependable)31cumecs<br />

3. F.R.L. 1585m.<br />

4. TYPE OF DAM(Conc.GravityDam)<br />

5. HEIGHT OF DAM 103m.<br />

6. T.W.L. 779m.<br />

7. AVERAGE GROSS HEAD 800m.<br />

8. LENGTH OF TUNNEL 12.93m.<br />

9. FIRM POWER 180mw.<br />

10. PROPOSED INSTALLED<br />

CAPACITY 1200mw.<br />

60 50<br />

DISTANCE IN KILOMETER<br />

TEESTA PROJECT<br />

STAGE-IV<br />

SALENTFEATURES:-<br />

1. CATCHMENT AREA 3859sqkms<br />

2. DISCHARGE(Dependable)56cumecs.<br />

3. F.R.L. 722m.<br />

4. TYPE OF DAM-Conc.GravityDam<br />

5. T.W.L. 589m.<br />

6. AVERAGE GROSS HEAD 183m.<br />

7. LENGTH OF TUNNEL 11km.<br />

8. FIRM POWER 82.5mw.<br />

9. PROPOSED INSTALLED<br />

CAPACITY 495mw.<br />

40<br />

LACHEN PROJECT<br />

SALENTFEATURES:-<br />

1. CATCHMENT AREA 1604sq.km.<br />

2. DISCHARGE(Dependable)9.25 cumecs.<br />

3. F.R.L. 2650m.<br />

4. TYPE OF DAM-Conc.GravityDam<br />

5. T.W.L. 2290m.<br />

6. AVERAGE GROSS HEAD 355m.<br />

7. LENGTH OF TUNNEL 4.5km.<br />

8. FIRM POWER 38.44mw.<br />

9. PROPOSED INSTALLED<br />

CAPACITY 210mw.<br />

30 20<br />

TEESTA PROJECT<br />

STAGE -I<br />

10 0<br />

3500<br />

3000<br />

2500<br />

SALENTFEATURES:-<br />

1. CATCHMENT AREA 1461sq.km.<br />

2. DISCHARGE(Dependable)10.8 cumecs.<br />

3. F.R.L. 3258m.<br />

4. TYPE OF DAM(Conc.GravityDam) 2Nos.<br />

5. T.W.L. 2675m.<br />

6. AVERAGE GROSS HEAD 730m.<br />

7. LENGTH OF TUNNEL 7.75km.<br />

8. FIRM POWER 43.03mw.<br />

9. PROPOSED INSTALLED<br />

CAPACITY 320mw.<br />

500<br />

000<br />

2000<br />

1500<br />

1000<br />

PLATE-2


27°<br />

45'<br />

40'<br />

35'<br />

27°<br />

30'<br />

88° 15'<br />

6200<br />

6200<br />

6400<br />

5200<br />

4200<br />

5000<br />

4600<br />

88° 15'<br />

6539<br />

4800<br />

4000<br />

6671<br />

3720<br />

4850<br />

4600<br />

4400<br />

4000<br />

4400<br />

4800<br />

5485<br />

4000<br />

5000<br />

RUKEL CHHU<br />

4000<br />

3690<br />

4565<br />

4600<br />

5215<br />

5508<br />

4400<br />

4890<br />

4600<br />

5000<br />

4600<br />

5000<br />

4340<br />

3400<br />

3200<br />

4200<br />

4600<br />

4440<br />

4200<br />

4425<br />

3000<br />

3600<br />

3800<br />

4000<br />

RUKEL H.E PROJECT<br />

F R L 2395<br />

R B L 2355<br />

M D D L 2385<br />

3800<br />

4525<br />

5288<br />

4600<br />

3190<br />

3400<br />

3800<br />

4000<br />

4400<br />

4200<br />

4400<br />

3000<br />

6888<br />

2810<br />

2600<br />

3000<br />

DAM AXIS<br />

4000<br />

6345<br />

5259<br />

8425<br />

2800<br />

3200<br />

20' 25'<br />

UMRAM CHHU<br />

RANGYONG H.E PROJECT<br />

F R L 1845<br />

R B L1795<br />

M D D L1825<br />

RANGYONG CHHU<br />

T W L 1845<br />

AVG. GROSS HEAD 541.1<br />

P.H. CAPACITY 3 X 11<br />

4200<br />

4600<br />

2600<br />

2800<br />

6065 5643<br />

3800<br />

3000<br />

5600<br />

5718<br />

3800<br />

3600<br />

3400<br />

3200<br />

3000<br />

3580<br />

5200<br />

4800<br />

5000<br />

5200<br />

4600<br />

4800<br />

3775<br />

2600<br />

4934<br />

4000<br />

3200<br />

4180<br />

4000 4200<br />

3400<br />

4400<br />

3800<br />

5070<br />

4200<br />

4600<br />

4800<br />

4390<br />

4885<br />

DAM AXIS<br />

3200<br />

4200<br />

5200<br />

4000<br />

4925<br />

4600<br />

PASSAM CHHU<br />

CANE BRIDGE<br />

T W L 1098<br />

JUMTHUL CHU<br />

F R L 1845<br />

R B L1795<br />

M D D L1825<br />

DAM AXIS<br />

2200<br />

2400<br />

2800<br />

4200<br />

2000<br />

4000<br />

4400<br />

POKHRAM CHU<br />

AVG GROSS HEAD 738.2<br />

P.H. CAPACITY 3 X 47<br />

3800<br />

4660<br />

3400<br />

2600<br />

4800<br />

4600<br />

2800<br />

3600<br />

3000<br />

4800<br />

3580<br />

2600<br />

2400<br />

5000<br />

4135<br />

5000<br />

4115<br />

1800<br />

2800<br />

3000<br />

3200<br />

3400<br />

RINGPI H.E PROJECT<br />

F R L 2966<br />

R B L 2940<br />

M D D L2933<br />

4640<br />

LINGZA H.E PROJECT<br />

F R L 1850<br />

M D D L 1830<br />

R B L 1795<br />

RINGYONG CHU<br />

3370<br />

2600<br />

2400<br />

2600<br />

RGVINGRUM CHU<br />

2000<br />

2400<br />

4940<br />

1400<br />

2800<br />

2200<br />

2400<br />

3000<br />

1800<br />

3200<br />

3355<br />

2900<br />

2600<br />

2800<br />

2600<br />

2800<br />

3000<br />

4060<br />

KISHONG CHU<br />

DAM AXIS<br />

1600<br />

2200<br />

DAM AXIS<br />

PANAN H.E PROJECT<br />

F R L 1095<br />

R B L 1050<br />

M D D L 1085<br />

3000<br />

2800<br />

2600<br />

2400<br />

4000<br />

4235<br />

DAWATHANG CHHU<br />

RINGPI CHHU<br />

RANGYONG CHHU<br />

LUDUI CHHU<br />

PEGAR CHHU<br />

T W L 1095<br />

AVG. GROSS HEAD 746<br />

P.H. CAPACITY 3 X 40<br />

DAM AXIS<br />

1200<br />

1800<br />

4200<br />

4200<br />

2000<br />

1600<br />

4400<br />

3000<br />

1400<br />

2200<br />

4400<br />

1200<br />

2200<br />

2400<br />

4600<br />

4600<br />

2725<br />

1800<br />

1600<br />

2800<br />

4800<br />

5000<br />

3200<br />

KONGCHA CHU<br />

ZONG CHHU<br />

2600<br />

2800<br />

3000<br />

3200<br />

1200<br />

1000<br />

4965<br />

2400<br />

2503 3065<br />

5060<br />

3000<br />

3400<br />

88° 30'<br />

3600<br />

4600<br />

4800<br />

3000<br />

3200<br />

SUSPENSION BRIDGE<br />

1800<br />

2600<br />

2400<br />

5615<br />

4400<br />

4460<br />

4195<br />

2200<br />

2000<br />

TW L 770<br />

27°<br />

30'<br />

3400<br />

3800<br />

2008<br />

88° 30'<br />

1800<br />

4600<br />

3400<br />

3600<br />

3400<br />

3200<br />

3800<br />

3400<br />

3200<br />

2800<br />

2600<br />

2200<br />

1400<br />

1600<br />

27°<br />

45'<br />

TW L 1853<br />

AVG GROSS HEAD 1110<br />

P.H. CAPACITY 2 X 35<br />

2400<br />

1600<br />

1400<br />

1400<br />

1000<br />

1600<br />

AVG. GROSS HEAD 322<br />

1200<br />

2400<br />

TOLUNG CHU<br />

1000<br />

2485<br />

1000<br />

1200<br />

800<br />

800<br />

2000<br />

1000<br />

RAHI CHU<br />

1000<br />

1400<br />

TEESTA RIVER<br />

TEESTA H.E. PROJECT<br />

(STAGE-IV)<br />

1200<br />

DAM AXIS<br />

1400<br />

1600<br />

1430<br />

1800<br />

2845<br />

2000<br />

3200<br />

3400<br />

3000<br />

2800<br />

2600<br />

2400<br />

2200<br />

1800<br />

1800<br />

1600<br />

1400<br />

1200<br />

1000<br />

1000<br />

1200<br />

1400<br />

1600<br />

1800<br />

2000<br />

NOTES<br />

1. NO DIMENSION SHALL BE MEASURED FROM<br />

THIS DRAWING .<br />

2. CONTOURS AND OTHER FEATURES HAVE<br />

BEEN TRACED FROM THE S.O.I. TOPO-SHEET<br />

NO. 78A/6 & 78A/10 (SCALE:- 1:50000).<br />

FEB.2004<br />

PLATE-3<br />

F/DCE730/01/02


SCHEMATIC DIAGRAM SHOWING CASCADE DEVELOPMENT<br />

OF TOLUNG RIVER BASIN (SIKKIM)<br />

ELEVATION IN METERS<br />

3000<br />

2750<br />

2500<br />

2250<br />

2000<br />

1750<br />

1500<br />

1250<br />

PANAN HE PROJECT<br />

LINGZA HE PROJECT<br />

o 2 4 6 8<br />

RANGYONG HE PROJECT<br />

DISTANSE IN KILOMETER<br />

RINGPI HE PROJECT<br />

RUKEL HE PROJECT<br />

10 12 14 16 18 20 22<br />

3000<br />

2750<br />

2500<br />

2250<br />

2000<br />

1750<br />

1500<br />

1250<br />

PLATE-4


Hot spring<br />

LEGEND:-<br />

Falls 85m<br />

Rukel chhu<br />

S A K K Y O N G RF<br />

Dense mixed jungle<br />

QUARTZITE<br />

GNEISS<br />

Indragram<br />

DAM<br />

Open scrub<br />

Sing Gamringa<br />

88°20'<br />

Falls 150m<br />

Riyot Potam<br />

SCALE:- 1:50,000<br />

Open scrub<br />

Falls 90m<br />

falls<br />

Shophyak<br />

2440 Payongchu<br />

(Lingmlum)<br />

<strong>Rangyong</strong><br />

Dense mixed jungle<br />

0 1 2 3 Kilometres<br />

Umram chhu<br />

chhu<br />

27°35' 27°35'<br />

RUKEL HE SCHEME<br />

88°20'<br />

Passamphyaku<br />

1795<br />

Singnok<br />

Dense mixed jungle<br />

Date:<br />

Passaram chhu<br />

DAM<br />

DAM<br />

Lam<br />

RANGYONG HE SCHEME<br />

Pokhram Chhu<br />

Cune bridge<br />

Sakkyong<br />

S A K K Y O N G R F<br />

Ravingrum chhu<br />

Falls 71m<br />

Falls 25m<br />

88°25'<br />

88°25'<br />

Phontong<br />

Log bridge<br />

?<br />

Ringyong Chhu<br />

?<br />

?<br />

40<br />

? ?<br />

Ringpi chhu<br />

Falls 40m Log bridge<br />

? ?<br />

?<br />

45<br />

45<br />

45 65<br />

80<br />

50<br />

45<br />

70<br />

65<br />

40<br />

?<br />

? ?


TALAM HYDRO ELECTRIC PROJECT<br />

( 2 X 35 MW )<br />

RINGPI HYDRO ELECTRIC PROJECT<br />

( 2 X 35 MW )<br />

RANGYONG HYDRO ELECTRIC PROJECT<br />

( 3 X 47 MW )<br />

RUKEL HYDRO ELECTRIC PROJECT<br />

( 3 X 11 MW )<br />

N E P A L<br />

LINGZA HYDRO ELECTRIC PROJECT<br />

( 3 X 40 MW)<br />

YANGSS CHHU<br />

RAMAM OR<br />

RANGBONG KHOLA<br />

C H I N A<br />

CHAUNRIKHIANG<br />

TIKIPCHHU<br />

RIYONG KHOLA<br />

RIMBI CHHU<br />

T I B E T<br />

PHUTHUNG CHHU<br />

TONGSHIONG GLACIER<br />

TALUNG GLACIER<br />

CHOKCHURANG CHHU<br />

PREK CHHU<br />

LAMBI<br />

KHUNGME<br />

RATHANG CHHU<br />

KALEJ KHOLA<br />

TINGCHEN KHANG<br />

REFLI CHHU<br />

RISHI KHOLA<br />

GOMA CHHU<br />

RUKEL CHHU<br />

RONGDUNG CHHU<br />

GEZING<br />

REATHOK KHOLA<br />

SOMBARE NAYA BAZAR<br />

KHORA CHHU<br />

LUNGMA CHHU<br />

UMMRAM CHHU<br />

RANGYONG CHHU<br />

RANGIT RIVER<br />

KAYAM CHHU<br />

NAMCHI<br />

RINGYONG CHHU<br />

RANGPO CHHU<br />

GREAT RANGIT RIVER<br />

NACHUNGTHANGKHA<br />

THANG CHHO<br />

NAKU CHHU<br />

LANGBO CHHU<br />

THOMPHYAK CHHU<br />

POKE CHHU<br />

LHONAK CHHU<br />

RINGPI CHHU<br />

MONMU CHHU<br />

RANGPHAP CHHU<br />

ZEMU CHHU<br />

TOLUNG CHHU<br />

RUN CHHU<br />

SINGTAM<br />

TEESTA RIVER<br />

MANGKHA<br />

SIRWANI<br />

RONGNI CHHU OR RANI K<br />

TEESTA RIVER<br />

RAHI CHHU<br />

LASHA CHHU<br />

KALEP<br />

MANGAN<br />

DIKCHU<br />

TEESTA RIVER<br />

GYAMTHANG CHHU<br />

BURUM CHHU<br />

GEY CHHU<br />

TEESTA RIVER<br />

RANGPO CHHU<br />

RANGPO<br />

CHHU<br />

TARUM CHHU<br />

RABOM CHHU<br />

RI CHHU<br />

RISHI KHOLA<br />

BAKCHA<br />

DIK CHHU<br />

YUMRHANG CHHU<br />

CHUNGTHANG<br />

GANGTOK<br />

CHAKUNG CHHU<br />

CHHU<br />

RORA CHHU<br />

TAKCHOM CHHU<br />

RANGLI KHOLA<br />

W E S T B E N G A L<br />

DONGKYA CHHU<br />

TOKLUNG CHHU<br />

RATE CHHU<br />

BYU CHHU<br />

SEBOZANG CHHU<br />

LUNGZE CHHU<br />

RANGPO CHHU<br />

C H I N A<br />

T I B E T<br />

B H U T A N<br />

PANAN HYDRO ELECTRIC PROJECT<br />

(4 X 50MW)<br />

RONGNI STORAGE PROJECT<br />

( 3 X 65 MW)<br />

NOTES<br />

1. NO DIMENSION SHALL BE MEASURED FROM THIS DRAWING.<br />

PRE- FEASIBILITY REPORT DRAWING<br />

VICINITY MAP<br />

PLATE NO.- 6.1<br />

TEESTA HYDRO ELECTRIC PROJECT(STAGE-I)<br />

( 4 X 80 MW )<br />

LACHEN HYDRO ELECTRIC PROJECT<br />

( 3 X 70 MW )<br />

TEESTA HYDRO ELECTRIC PROJECT(STAGE-V)<br />

( 3 X 170 MW )<br />

DIKCHU HYDRO ELECTRIC PROJECT<br />

( 3 X 35 MW )<br />

LEGEND<br />

INTERNATIONAL BOUNDARY<br />

STATE BOUNDARY<br />

RIVER<br />

TRIBUTARY<br />

ROAD<br />

DAM SITE<br />

F/DCE730/01/02


27°<br />

35'<br />

2600<br />

2200<br />

2400<br />

2600<br />

2800<br />

3000<br />

3200<br />

2400<br />

OPEN SCRUB<br />

RANGYONG CHU<br />

2000<br />

UMRAM CHHU<br />

3400 PAYONGCHU<br />

3600<br />

(LINGMIUM)<br />

INTAKE TUNNEL<br />

3MØ<br />

DESILTING<br />

CHAMBER<br />

3400<br />

LINK TUNNEL<br />

3.3MØ<br />

DAM AXIS<br />

1800<br />

3200<br />

3600<br />

2200<br />

2400<br />

1800<br />

PASSARAM CHHU<br />

SINGNAK<br />

2000<br />

2000<br />

DAM AXIS<br />

DIVERSION TUNNEL<br />

3.3MØ H.S.<br />

DIVERSION TUNNEL<br />

3.3 MØ H.S.<br />

SILT FLUSHING TUNNEL<br />

ADIT-1<br />

3400<br />

2200<br />

2400<br />

3200<br />

1600<br />

2400<br />

2600<br />

2800<br />

RANGYONG CHU<br />

ADIT-2<br />

2000<br />

2200<br />

1800<br />

3000<br />

1600<br />

1400<br />

CANE BRIDGE<br />

SOKKYONG<br />

HEADRACE TUNNEL 3.3MØ H.S.<br />

PAKHRAM CHHU<br />

LOG BRIDGE<br />

ADIT-3<br />

2800<br />

RAVINGRUM CHHU<br />

2800<br />

2600<br />

88°<br />

25'<br />

2600<br />

2400<br />

88°<br />

25'<br />

FARD<br />

2000<br />

2400<br />

2200<br />

1400<br />

1800<br />

PHANTONG<br />

1200<br />

SWITCH YARD<br />

LOG BRIDGE<br />

POWER HOUSE<br />

INCLINED PRESSURE<br />

SHAFT 2.5M Ø<br />

1600<br />

SURGE SHAFT 10M Ø<br />

2200<br />

2000<br />

1800<br />

RINGYONG CHHU<br />

1400<br />

TRANSFORMER<br />

CAVERN<br />

1600<br />

VAWL<br />

SHABRUNG<br />

RINGPI CHHU<br />

1600<br />

1800<br />

T.R.T. 3.3 M Ø<br />

M.A.T.<br />

1800<br />

ISHANA<br />

FORD<br />

LOG BRIDGE<br />

MYONG<br />

2200<br />

RANGYONG CHU<br />

LOG BRIDGE<br />

1600<br />

1800<br />

2000<br />

2200<br />

2000<br />

1800<br />

1600<br />

1400<br />

1200<br />

1200<br />

1400<br />

1600<br />

27°<br />

35'<br />

NOTES<br />

1. NO DIMENSION SHALL BE MEASURED FROM THIS DRAWING.<br />

2. CONTOURS AND OTHER FEATURES HAVE BEEN TRACED<br />

FROM THE S.O.I. TOPO- SHEET NO. 78A/6 (SCALE 1:50000) .<br />

PRE- FEASIBILITY REPORT DRAWING<br />

PROJECT LAY-OUT PLAN<br />

PLATE NO.-6.2<br />

F/DCE730/01/02


2000<br />

1800<br />

2600<br />

SINGNAK<br />

2400<br />

SILT FLUSHING TUNNEL<br />

2M.X 3M. D- SHAPE<br />

1600<br />

D/S COFFERDAM<br />

H.R.T. 3.3M.Ø H.S.SHAPE<br />

RANGYONG CHHU<br />

2200<br />

1800<br />

27°<br />

35'<br />

2000<br />

1600<br />

RANGYONG CHU<br />

DESILTING CHAMBER<br />

( 125 X 6 X 9M.)<br />

INTAKE TUNNEL<br />

3MØ<br />

U/S COFFERDAM<br />

DIVERSION TUNNEL<br />

3.3 MØ H.S.SHAPE<br />

(LINGMIUM)<br />

3400 PAYONGCHU<br />

LINK TUNNEL<br />

3.3MØ H.S. SHAPE<br />

D/S COFFERDAM<br />

DIVERSION TUNNEL<br />

3.3MØ H.S.SHAPE<br />

2400<br />

DAM AXIS( UPPER )<br />

1800<br />

2200<br />

2400<br />

2000<br />

UMRAM CHHU<br />

U/S COFFERDAM<br />

PASSARAM CHHU<br />

NOTES<br />

1. NO DIMENSION SHALL BE MEASURED FROM THIS DRAWING.<br />

2. CONTOURS AND OTHER FEATURES HAVE BEEN TRACED<br />

FROM THE S.O.I. TOPO-SHEET NO. 78A/6 (SCALE 1:50000) .<br />

PRE- FEASIBILITY REPORT DRAWING<br />

DAM AREA<br />

LAY-OUT PLAN<br />

PLATE NO.- 6.3<br />

F/DCE730/01/02


H.R.T. 3.3M Ø H.S.SHAPE<br />

1600<br />

1800<br />

SURGE SHAFT 10M Ø<br />

2000<br />

1800<br />

CABLE TUNNEL<br />

1400<br />

POWER HOUSE<br />

(100M. X 22.5M. X 40 M.)<br />

INCLINED PRESSURE<br />

SHAFT 2.5M Ø<br />

TRANSFORMER<br />

CAVERN<br />

SWITCH YARD<br />

(100M. X 155M.)<br />

1200<br />

1600<br />

RINGYONG CHHU<br />

T.R.T. 3.3 M Ø H.S. SHAPE<br />

M.A.T.<br />

RANGYONG CHHU<br />

1200<br />

1400<br />

1200<br />

NOTES<br />

1. NO DIMENSION SHALL BE MEASURED FROM THIS DRAWING.<br />

2. CONTOURS AND OTHER FEATURES HAVE BEEN TRACED<br />

FROM THE S.O.I. TOPO-SHEET NO. 78A/6 (SCALE 1:50000) .<br />

PRE- FEASIBILITY REPORT DRAWING<br />

POWER HOUSE AREA<br />

LAY-OUT PLAN<br />

PLATE NO.- 6.4<br />

F/DCE730/01/02


FRL 1845.00<br />

MDDL 1825.00<br />

EL 1815.00<br />

EL 1810.00<br />

TRESTLE<br />

EL 1850.00<br />

?<br />

?<br />

DESILTING CHAMBER<br />

(125M. X 6M.X 9M.)<br />

SILT FLUSHING TUNNEL<br />

(2M.X 3M. D-SHAPED)<br />

?<br />

?<br />

GATE OPERATION ?<br />

CHAMBER<br />

EL 1850.00<br />

EL1860<br />

1<br />

? ?<br />

250<br />

HRT 3.3M. Ø H.S. SHAPE<br />

STEEL LINED PRESSURE SHAFT 2.5M. Ø<br />

SURGE SHAFT<br />

10M. Ø<br />

ADIT TO P.S.<br />

3.3M.Ø D-SHAPE<br />

EL 1783.85<br />

EL. 1100.15<br />

C L - OF MACHINE<br />

?<br />

?<br />

ADIT TO P.S.<br />

3.3M.Ø D-SHAPE<br />

22500<br />

EL.1132.00<br />

BUS DUCT<br />

30000<br />

?<br />

POWER HOUSE CAVERN<br />

14000<br />

TRANSFORMER CAVERN<br />

CABLE TUNNEL<br />

EL.1114.55<br />

?<br />

T.R.T. 3.3M.Ø H.S.SHAPE<br />

NOTES:<br />

MAR.2004<br />

C.C. BLOCKS<br />

TWL1098.00<br />

COFFERWALL<br />

1 ALL DIMENSIONS ARE IN MILLIMETERS AND LEVELS IN METERS.<br />

WATER CONDUCTOR SYSTEM<br />

L-SECTION<br />

PLATE NO.-6.5<br />

2 NO DIMENSION SHALL BE MEASURED FROM THIS DRAWING.<br />

F/DCE730/01/02


L6<br />

?<br />

L5<br />

?<br />

L4<br />

107000 27000 166000<br />

3000 (TYP.)<br />

3000(TYP.)<br />

DAM TOP EL 1850.00<br />

L3<br />

?<br />

L2<br />

L1<br />

S3<br />

S2<br />

S1<br />

UPSTREAM ELEVATION<br />

?<br />

300000<br />

R1 R2 R3 R4 R5 R6<br />

RADIAL GATE 3000 X 6000<br />

?<br />

N.S.L.<br />

ANTICIPATED ROCK PROFILE<br />

?<br />

R7<br />

NOTES:<br />

1 ALL DIMENSIONS ARE IN MM AND LEVELS IN METRES.<br />

PRE- FEASIBILITY REPORT DRAWING<br />

MAR.2004<br />

RAILING<br />

R8<br />

R9<br />

UPPER DAM<br />

UPSTREAM ELEVATION<br />

PLATE NO.- 6.6<br />

R10<br />

2. NO DIMENSION SHALL BE MEASURED FROM THIS DRAWING.<br />

?<br />

F/DCE730/01/02


L6<br />

?<br />

L5<br />

?<br />

L4<br />

118000<br />

L3<br />

?<br />

DAM TOP EL 1850.00<br />

L2<br />

250000<br />

27000<br />

3000(TYP.) 3000(TYP.)<br />

L1<br />

RADIAL GATE 3000 X 6000<br />

105000<br />

S3 S2 S1 R1 R2 R3 R4<br />

?<br />

?<br />

RAILING<br />

NSL<br />

ANTICIPATED ROCK PROFILE<br />

?<br />

NOTES:<br />

1 ALL DIMENSIONS ARE IN MM AND LEVELS IN METRES.<br />

PRE- FEASIBILITY REPORT DRAWING<br />

MAR.2004<br />

LOWER DAM<br />

UPSTREAM ELEVATION<br />

PLATE NO.- 6.7<br />

2. NO DIMENSION SHALL BE MEASURED FROM THIS DRAWING.<br />

R5<br />

F/DCE730/01/02


STOPLOG GATE GROOVE<br />

1<br />

STOPLOG GANTRY<br />

CRANE<br />

DAM TOP EL 1850.00<br />

FRL EL. 1845.00<br />

MDDL EL. 1825.00<br />

1<br />

CREST EL 1805.00<br />

RBL ±EL 1795.00<br />

EL ±1785.00<br />

STEEL LINER<br />

GROUT CURTAIN HOLES<br />

?<br />

3500<br />

DAM AXIS<br />

8000<br />

ROAD<br />

BREAST WALL<br />

AIR VENT PIPE<br />

EL. 1811.00<br />

R9600<br />

FOUNDATION<br />

GALLERY<br />

DRAINAGE HOLE<br />

RADIAL GATE(3M. X 6M.)<br />

TRUNION BEAM<br />

HIGH PERFORMENCE CONC.<br />

70000<br />

FLIP BUCKET<br />

BUCKET INVERT EL 2353.00<br />

? ? ? ? ? ?<br />

SPILLWAY- MAXIMUM SECTION<br />

15°<br />

R25000<br />

30°<br />

1<br />

1<br />

1 1<br />

12250<br />

7000 LONG ROCK ANCHORS<br />

@1500 c/c STAGGERED<br />

MAX. T W L<br />

NORMAL T W L<br />

CONCRETE APRON<br />

DAM TOP EL 1850.00<br />

FRL EL 1845.00<br />

MDDL EL 1825.00<br />

0.1<br />

1<br />

EL. VARIES ?<br />

DAM AXIS<br />

8000<br />

NON- OVERFLOW SECTION<br />

COMPACTED BACKFILL<br />

NOTES:<br />

? ?<br />

1 ALL DIMENSIONS ARE IN MM AND LEVELS IN METRES.<br />

2 NO DIMENSION SHALL BE MEASURED FROM THIS<br />

DRAWING.<br />

PRE- FEASIBILITY REPORT DRAWING<br />

MAR.2004<br />

0.8<br />

1<br />

DAM<br />

SPILLWAY & NON-OVER FLOW<br />

CROSS-SECTION<br />

PLATE NO.-6.8<br />

F/DCE730/01/02


HRT3.3 M. Ø<br />

Ø3300<br />

Ø10000<br />

TYP. SECTION - SURGE SHAFT<br />

2000 LONG 25 Ø ROCK BOLTS/<br />

ANCHORS 1000 c/c<br />

Ø1650<br />

Ø3300<br />

TYP. SECTION - HRT<br />

CONC. LINING 225 THK.<br />

50 THK.<br />

SHOTCRETE<br />

4M LONG 25 Ø ROCK BOLTS/<br />

ANCHORS 1500 c/c<br />

100 THK. SHOTCRETE<br />

WITH WIREMESH<br />

CONC.LINING 750 THK.<br />

PRESSURE SHAFT<br />

Ø3300<br />

TYP. SECTION - DIVERSION TUNNEL<br />

12000<br />

2000 LONG 25 Ø ROCK BOLTS/<br />

ANCHORS 1000 c/c<br />

Ø1650<br />

Ø3300<br />

CONC. LINING 225 THK.<br />

50 THK.<br />

SHOTCRETE<br />

10000<br />

1.5<br />

1<br />

SECTION - DESILTING CHAMBER<br />

Ø2500<br />

32Ø 5000 LONG ROCK BOLTS /<br />

ANCHORS @ 2000 c/c<br />

2000 LONG 25 Ø ROCK BOLTS/<br />

ANCHORS 1000 c/c(IF REQUIRED)<br />

BACK FILL 750 THK.<br />

STEEL LINER<br />

50THK.<br />

SHOTCRETE<br />

TYP. SECTION - PRESSURE SHAFT<br />

100 THK. SHOTCRETE<br />

WITH WIREMESH<br />

R.C.C. LINING 300 THK.<br />

32Ø 5000 LNG ROCK BOLTS/<br />

ANCHORS @ 1500 c/c<br />

NOTE :-<br />

1 ALL DIMENSIONS AREIN MILIMETRES AND LEVELS<br />

IN METRE UNLESS OTHERWISE SPECIFIED.<br />

2 NO DIMENSION SHALL BE MEASURED FROM THIS<br />

DRAWING.<br />

PRE-FEASIBILITY REPORT DRAWING<br />

TYPICAL CROSS SECTION<br />

OF CONSTITUENTS OF WATER<br />

CONDUCTOR SYSTEM & DIVERSION TUNNEL<br />

MAR.2004<br />

PLATE NO.- 6.9<br />

00<br />

F/DCE/730/01/02


220KV<br />

BUS1<br />

BUS CVT-1<br />

220kV<br />

BUS-II<br />

BUS CVT-2<br />

EX. Tr.<br />

NGT<br />

S.A.<br />

XLPE CABLE<br />

GSU Tr.<br />

G-III<br />

UNIT -III<br />

SC<br />

SA<br />

PT<br />

PT<br />

UAT<br />

64G1<br />

64G2<br />

PTSP<br />

FUTURE<br />

CVT<br />

EX. Tr.<br />

NGT<br />

UNIT -II<br />

S.A.<br />

XLPE CABLE<br />

GSU Tr.<br />

SC<br />

SA<br />

G-II<br />

PT<br />

PT<br />

UAT<br />

64G1<br />

64G2<br />

TO 220KV<br />

FEEDER-1<br />

PTSP<br />

CVT<br />

BUS<br />

COUPLER<br />

EX. Tr.<br />

NGT<br />

UNIT -I<br />

S.A.<br />

XLPE CABLE<br />

GSU Tr.1Ø,20 MVA<br />

11/ 220/ 3 KV<br />

SA<br />

PT<br />

PT<br />

G-I<br />

47 MW,11 KV<br />

64G1<br />

64G2<br />

FOR<br />

TO 220KV<br />

FEEDER-2<br />

UAT<br />

11 / 0.415KV,800KVA<br />

SC PTSP<br />

FOR<br />

METERING &<br />

PROTECTION<br />

DVR DUPLICATE<br />

PROTECTION<br />

CVT<br />

AUTO Tr. 14 MVA<br />

132/220 KV, 1Ø CVT<br />

SA<br />

S.A.<br />

VED PAL<br />

MAR, 2004<br />

FROM RUKEL<br />

SINGLE LINE DIAGRAM<br />

BHU DEV<br />

V.K.SINGH<br />

NH/DEM/RYG/SLD/01<br />

PLATE-8.1<br />

00


Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

ANNEXURES


GEOLOGY OF THE AREA AROUND THE PROPOSED<br />

Annexure 4.1<br />

RANGYONG HYDROELECTRIC PROJECT, TEESTA BASIN,<br />

INTRODUCTION<br />

SIKKIM<br />

The Central Electricity Authority (CEA), as a part <strong>of</strong> an exercise to assess the<br />

balance hydroelectric potential in the county have identified 399 schemes with installed<br />

capacity <strong>of</strong> 1,50,000 MW in various river basins. The schemes thus identified were<br />

subjected to ranking studies based on different parameters. As a resulted <strong>of</strong> ranking<br />

studies, 162 schemes located in the different river basins in 16 states were selected to<br />

be taken up for preparation <strong>of</strong> Pre-Feasibility Reports (PFR’s) in first phase. The<br />

schemes thus found feasible are proposed to be taken up for further development during<br />

X and XI Five Year Plans. Out <strong>of</strong> 162 schemes selected to be taken up for preparation<br />

<strong>of</strong> PFR’s in first phase, 10 are located in Teesta Basin in Sikkim. The proposed<br />

<strong>Rangyong</strong> Hydroelectric Project located in north Sikkim is one <strong>of</strong> the ten schemes that<br />

are being taken up for preparation <strong>of</strong> PFR’s in first phase. As per the layout provided by<br />

NHPC Ltd. the scheme envisages construction <strong>of</strong> two diversion dams, one across<br />

Umram Chhu just downstream <strong>of</strong> its confluence with Passaram Chhu (27 O 36’ 00” N: 88 O<br />

22’ 24” E, 78 0/6 ) with a view <strong>of</strong> diverting its water to <strong>Rangyong</strong> Chhu through 2 km long<br />

diversion tunnel and another across Rangong Chhu just downstream <strong>of</strong> powerhouse <strong>of</strong><br />

upstream Rukel Hydroelectric Project (27 O 35’ N: 88 O 21’ E, 78 0/6 ). The water<br />

conductor system includes approximately 7.5 km. long headrace tunnel aligned on right<br />

bank <strong>of</strong> <strong>Rangyong</strong> Chhu and underground powerhouse with probable installed capacity<br />

<strong>of</strong> 175 MW just upstream <strong>of</strong> powerhouse <strong>of</strong> the proposed Lingza Hydroelectric Project<br />

(27 O 33’ 00” N: 88 O 26’ 00” E, 78 0/6 ).<br />

REGIONAL GEOLOGY<br />

The area around the proposed project is located in North Sikkim in Central<br />

Crystalline axial region and is characterised by sharp crested snow bound mountains.


The ridges trend both in E-W and N-S directions. Teesta River, main draining agency <strong>of</strong><br />

Sikkim flows almost N-S in the area. The important tributaries <strong>of</strong> Teesta are Lach Chhu,<br />

Toloung Chhu Chakung Chu, Ringpi Chu and their numerous tributaries. The valleys <strong>of</strong><br />

rivers are U-shaped and small streams have formed deep gorges. Vegetation is<br />

observed up to EI . 3.900 m and many lakes are present at high altitudes.<br />

The area around the proposed project has been mapped by Raina (1966)<br />

Chakraborti and Banerjee (1982), Kumar et al (1984), Neogi et al (1984) and Neogi et al<br />

(1986). The stratigraphic sequence established by the <strong>of</strong>ficers <strong>of</strong> GSI on the basis <strong>of</strong><br />

geological mapping is given below:<br />

GROUP LITHOLOGY<br />

Gondwana Grits, pebble cum boulder beds and<br />

2<br />

carbonaceous shales with occasional<br />

coal seams, pegmatite, quartzite<br />

(Tourmaline bearing)<br />

Daling Inter bedded quartzite and chlorite<br />

sericite phyllite / schist.<br />

Lingza Granite<br />

Quartzite/Biotite schist<br />

Chungthang Interbedded quartzite and<br />

Central Crystalline Gneissic<br />

Complex<br />

garnetiferous quartz biotite schist .<br />

Calc – silicate rock / marble.<br />

Garnet – kyanite – sillimanite – biotite<br />

– quartz – schist.<br />

Banded gneiss with augen gneiss and<br />

quartz – biotite gneiss.<br />

Augen gneiss


The area falls within axial belt <strong>of</strong> Central Crystalline Zone <strong>of</strong> the North Sikkim<br />

Himalayas where the rock types are mainly high grade gneisses (CCGC) having<br />

interbands <strong>of</strong> metasedimentaries represented by calc – silicate / quartzite, high grade<br />

schists and their fine inter laminations. The metasedimentaries occur as enclaves in the<br />

high-grade gneisses in the area around the proposed project. All these rock types are<br />

<strong>of</strong>ten intruded by discordant tourmaline bearing quartz veins and pegmatite.<br />

The higher grade gneisses belonging to the Central Crystalline Gneissic<br />

Complex (CCGC) Group vary in composition from a gneiss in which feldspar is<br />

predominant with respect to quartz to quartz biotite gneiss in which feldspar is almost<br />

absent (Chakraborti & Banerjee, 1982 and Neogi et al, 1986) with frequent association<br />

<strong>of</strong> garnet, tourmaline and sillimanite / kyanite depending up on bulk chemical<br />

composition. While the former type is well foliated with streaks <strong>of</strong> biotite, the latter is<br />

compact and poorly foliated. The different types <strong>of</strong> these gneisses occurring at different<br />

structural levels are banded gneiss, augen gneiss and streaky gneiss. A gradual<br />

passage from one type to other type, both vertically and laterally, is rather common.<br />

The banded type is characterized by alternate bands <strong>of</strong> quartz feldspar and biotite.<br />

These bands are at places stretched giving rise to augens which are composed<br />

predominantly <strong>of</strong> single grains <strong>of</strong> feldspar or occasionally quartz or their aggregate. The<br />

latter may be the result <strong>of</strong> metamorphic differentiation. The augens are both deformed<br />

or undeformed and are invariably warped around by biotite flakes defining the gneissic –<br />

foliation. The augens are stretched in the direction <strong>of</strong> regional schistosity. The high<br />

grade gneisses are <strong>of</strong>ten intruded by tourmaline granite at places and are associated<br />

with interbands <strong>of</strong> calc silicate – quartzite and garnetiferous biotite schist and various<br />

other schists belonging to Chungthang Group. These have locally been mapped as<br />

Kanchendzonga Gneiss, Chungthang Gneiss and Darjeeling Gneiss by various workers<br />

earlier. According to Neogi et al (1986), there exists a complete gradation both laterally<br />

and in down dip direction amongst above mentioned gneisses. Their repetition is due to<br />

normal morphological variation and unlinked with folding and thrusting. Various<br />

structural/textural types <strong>of</strong> these gneisses stated above have also been observed in all<br />

the so called gneissic groups <strong>of</strong> Central Crystalline axial region and have been referred<br />

as “High Grade Gneisses” <strong>of</strong> Central Crystalline Belt which are also comparable to<br />

Darjeeling Gneisses <strong>of</strong> Lesser Himalayas.<br />

3


The metasedimentaries <strong>of</strong> the area belonging to the Chungthang Group are<br />

represented by a sequence <strong>of</strong> lithounits varying from calcareous to arenaceous and<br />

argillaceous lith<strong>of</strong>acies. These comprise calc silicate rocks, quartzite, high grade<br />

micaceous schists occasional amphibolites and their fine grained interlaminations.<br />

Neogi et al (1986) have clubbed together calc silicate rocks and quartzites as<br />

these invariably occur together. Prominent bands <strong>of</strong> these rocks have been observed<br />

near Be and Myong, north <strong>of</strong> Talung gompa and near Phygn and south <strong>of</strong> Kishong.<br />

These have NE-SW trend are locally folded. Calcareous bands are easily identified by<br />

their greenish colour within banded calc silicate / quartzite assemblage. Apart from<br />

carbonates and quartz, stumpy diopside and needle shaped tremolite have also been<br />

observed in these. Garnet is generally leached giving rise to ferruginous staining. The<br />

quartzite is sericite quartzite. Thin laminations <strong>of</strong> biotite are observed in quartzite at<br />

places. The rocks are occasionally boudinaged. Carbonaceous biotite schist is found<br />

associated with southern west calc silicate / quartzite band. Tourmaline bearing silica<br />

veins and pegmatites have been observed occasionally intruding these rock types.<br />

Daling Series <strong>of</strong> Raina (1966) having two zones viz phyllite zone and schistose<br />

zone has been mapped as low grade metamorphites <strong>of</strong> Daling Group by Kumar et al<br />

(1984). Daling Group comprises quartz – chlorite – sericite schist phyllite, quartz –<br />

sericite schist, quartz chlorite phyllite <strong>of</strong>ten associated with thin interbands <strong>of</strong> quartzite.<br />

The low grade sedimentaries belonging to Daling Series from southern part <strong>of</strong> the area<br />

structurally underlie the Lingtze Granite Gneiss. Near Gyathang and at some other<br />

places, the frequency <strong>of</strong> presence <strong>of</strong> garnet is slightly higher and its grain size is<br />

controlled by the original bulk composition <strong>of</strong> the rock. According to Kumar et al (1984)<br />

these metasedimentaries typically resemble the Gorubathan Formation <strong>of</strong> Daling Group<br />

and hence been named “low Grade Daling” .<br />

The granite gneiss which crops out near north <strong>of</strong> Senkhalang with an E-W trend<br />

and northerly dips is also observed NW <strong>of</strong> Kendong and north <strong>of</strong> Karsang to form the<br />

western limb <strong>of</strong> major antiformal closure. It occupies a unique position between low-<br />

grade and high-grade metasedimentaries and is conformable to both. This granite is a<br />

well foliated, coarse grained, sheared streaky biotite gneiss and occasionally contains<br />

4


garnets. At places, augens <strong>of</strong> quartz and feldspar stretched parallel to the foliation plane<br />

are recorded within this unit.<br />

Tourmaline and biotite bearing granites are the younger granites having<br />

discordant relationship with high-grade gneisses and high-grade metasedimentaries.<br />

Compositionally, these are mainly quartz-feldspar rich leucogranite varying from coarse<br />

grained to fine grained aplitic variety and shows disseminated flakes <strong>of</strong> biotite.<br />

Tourmaline grains are observed generally in structural highs.<br />

Gondwanas, according to Raina (1966) include grits, pebble cum boulder beds<br />

and carbonaceous shales with occasional coal seams. Pebble cum boulder bed forms<br />

the marker horizon for Gondwana. Arkosic sandstone (feldspathic grit) forms the other<br />

main rock type. It is light yellow to dark grey coloured and is infolded within pebble<br />

beds.<br />

STRUCTURE AND TECTONICS<br />

The area exposes a sequence <strong>of</strong> gneissic rocks and associated<br />

metasedimentary rocks <strong>of</strong> Central Crystalline Belt <strong>of</strong> North Sikkim and the structural<br />

fabric elements observed pertain to features in the area predominated by high grade<br />

litho-facies which have undergone polyphase deformation and metamorphism. The<br />

primary structures include compositional banding. The gneisses show lithological<br />

banding which can be attributed to metamorphic differentiation. Bedded characters are<br />

observed only in calc silicate – quartzite multilayers. The high-grade schists also show<br />

compositional banding <strong>of</strong> alternate quartz rich and calc silicate rich bands. There is no<br />

evidence however to indicate that these bandings are relict <strong>of</strong> primary sedimentary<br />

banding. However, broad parallelism <strong>of</strong> the bandings and later imposed pervasive<br />

planes, S2, indicates that these could be transposed.<br />

The secondary structures include planar surfaces like gneisses foliation,<br />

schistosity which include bedding schistosity (S1), regional schistosity (S2) and fracture<br />

cleavage (S3). Bed Gneissic foliation forms the most prominent fabric element <strong>of</strong> high<br />

grade metamorphic tectonics. These ‘S’ surfaces are marked by parallel lithological<br />

5


layering and preferred dimensional orientation <strong>of</strong> minerals. The gneissic foliation in the<br />

area generally trends NE-SW with moderate NW dips.<br />

The metasedimentaries associated with the gneisses show a pervasive<br />

schistosity where lithological layering is absent. The fabric is defined by preferred<br />

orientation <strong>of</strong> tabular mica crystals. Bedding schistosity (S1) is incipient and is parallel to<br />

the compositional banding in metasedimentaries. This ‘S’ surface could not be related to<br />

any tectonic structure in the area and could be described as another inherited fabric<br />

element along with bedding. The regional schistosity (S2) is most pervasive structural<br />

element in metasedimentaries. The axial plane schistosity is symmetrically oriented with<br />

respect to axial planes <strong>of</strong> folds (F1). The trend <strong>of</strong> regional schistosity is parallel to the<br />

gneissic foliation. The fracture cleavage (S3) is defined by discrete parallel fractures<br />

and are also axial plane cleavages related to F2 crenulation. Due to varying styles <strong>of</strong> the<br />

F2 folds the orientation <strong>of</strong> the S3 surfaces varies with respect to regional schistosity ‘S2’.<br />

The linear structures include striping lineation, pucker axis lineation and mineral<br />

lineation.<br />

The area comprises a sequence <strong>of</strong> high-grade metasedimentaries and gneisses<br />

that show evidence <strong>of</strong> having undergone polyphase deformation with complex pattern <strong>of</strong><br />

folds due to repeated super-imposition <strong>of</strong> successive fold forms. Grouping <strong>of</strong> different<br />

generations <strong>of</strong> folds on the basis <strong>of</strong> styles and spatial attitudes has not been possible<br />

due to their complex forms. Broadly three generations <strong>of</strong> fold movement could be<br />

deciphered. F1 folds, the earliest recognizable folds have compositional banding and<br />

bedding schistosity as their form surface and are <strong>of</strong> tight isoclinal reclined to inclined<br />

folds. Their style and spatial orientation as observed in the area is comparable to these<br />

observed in Daling Group <strong>of</strong> rocks exposed south <strong>of</strong> present area. The F2 folds have<br />

involved all the above mentioned surfaces. These show a variety <strong>of</strong> styles ranging from<br />

appressed isoclinal folds to open warps, small-scale chevron folds or multi-hinged<br />

disharmonic folds. The calc silicate / marble quartzite bands show regional warps along<br />

NW-SE axis due to this phase <strong>of</strong> folding. The effects <strong>of</strong> F3 folds have been observed<br />

mainly on regional scale. On macro scale they are <strong>of</strong> the nature <strong>of</strong> minor broad warps<br />

that have folded the weakly developed S3 planes. No planar surface related to this<br />

phase <strong>of</strong> folding are apparent. F3 warps are only locally developed in high-grade<br />

metasedimentaries and have N-S oriented axis.<br />

6


Zones <strong>of</strong> intense mylonitisation have been observed in the gneisses but there is<br />

no basis to conclude that these could represent planes <strong>of</strong> thrusting on the basis <strong>of</strong><br />

evidence like distinct truncation <strong>of</strong> lithounits reorientation <strong>of</strong> major folds (F2),<br />

development <strong>of</strong> small scale faults etc.. Chakraborty and Banerjee (1982) have marked<br />

NNW-SSE trending thrust near Manual and NW-SE trending thrust near Naga. Neogi et<br />

al (1984) observed minor slips and faults occurring commonly within gneisses and<br />

metasedimentaries along S3 planes near hinge zone <strong>of</strong> F2 folds. The slips are more<br />

common where folds are tight. A meso scale normal vertical fault trending N-S has been<br />

found with in low grade metasedimentaries about 2 km north <strong>of</strong> Brang village.<br />

Silicification, chloritization and mylonitization are found along this fault plane.<br />

SEISMOTECTONICS AND SEISMICITY<br />

Seismotectonically the area under reference is located in Axial Belt <strong>of</strong> Central<br />

Crystalline Zones <strong>of</strong> North Sikkim. According to Narula at al (2000) the northern part <strong>of</strong><br />

the area is occupied by poorly metamorphosed sequence (Tethyan) folded during<br />

Himalayan Orogeny. Similar tectonic pockets representing Gondwana sequence crop<br />

out within Rangit Window as well as lenticular tectonic wedge along the Main Boundary<br />

Thrust (MBT). The northern Tethyan Belt is followed successively to the south by high-<br />

grade complex <strong>of</strong> Central Crystallines and low-grade complex <strong>of</strong> Lesser Himalayan rock<br />

worked during Himalayan Orogeny. The latter packet is exposed within tectonic<br />

windows as well as linear belt between Main Central Thrust (MCT) and MBT. South <strong>of</strong><br />

MBT the foot hill region is occupied by sequence <strong>of</strong> frontal belt affected by the terminal<br />

phase <strong>of</strong> the Himalayan Orogeny. Adjacent Peninsular tract is covered by Quaternary<br />

alluvial fill along the foredeep. In the southwestern part, Peninsular element is<br />

represented by small inliers <strong>of</strong> gneissic complex and Rajmahal Trap. The basement<br />

gneissic complex, representing a part <strong>of</strong> Shillong massif along with marine transgressive<br />

cover are present in south eastern part. Like other parts <strong>of</strong> Himalayas, this area is the<br />

high grade Central Crystallines from comparatively lower grade Lesser Himalayan<br />

packages which are separated from the Siwalik Belt by MBT. At places, particularly<br />

towards east, several subsidiary thrust are presented between MCT and MBT. Besides<br />

these, several approximately N-S trending gravity faults are present particularly within<br />

northern Tethyan Belt and the southern foot hill belt. Within northern Tethyan Belt these<br />

7


N-S faults define some well knows graben structures, viz. Pum Qu Graben and Yadong<br />

Gulu Graben. In the former, the faults affecting the Quaternary glacial deposits are<br />

clearly evident. The latter graben is considered to be longest one in Tibetan Plateau and<br />

is segmented into several N-S smaller grabens. The foredeep tract east <strong>of</strong> Munger –<br />

Saharsha Ridge is known as Purnia Basin where Gondwana sequence has developed<br />

over the rifted basement. The structural configuration <strong>of</strong> this foredeep region is<br />

architectured by a set <strong>of</strong> almost N-S trending faults resulting in development <strong>of</strong> alternate<br />

horst and graben structures. The westernmost is the Munger – Saharsha Ridge which<br />

alternates towards east by Purnia Basin. The western and eastern boundaries <strong>of</strong> Purnia<br />

Basin are defined by the Munger - Saharsha Ridge Morginal Fault (MSRF) and Malda<br />

Kishanganj Fault (MKF). The former fault known as Sainthia – Brahmani Fault further<br />

south, along which cluster <strong>of</strong> earthquakes have been recorded by the Geological Survey<br />

<strong>of</strong> India, has been found seismically active. Further east the prominent tectonic feature<br />

is the Rangpur Ridge bound by MKF and Jangipur – Goribandha Fault, Teesta Fault and<br />

Katihar – Nailphamari Fault. Several subsidiary faults, parallel to Teesta Fault forming<br />

grabens are reported from ridge. Gondwana sequence is found to have developed<br />

within these grabens. Along with transverse faults, several lineaments cutting across the<br />

Himalayan belt are also present. These exhibit NE and NW trends. The NE trending<br />

Azun Lineament considered to be trace <strong>of</strong> northern extension <strong>of</strong> East Patna Fault,<br />

Kanchanjunga Lineament and NW-SE trending Teesta and Purnia lineaments are other<br />

prominent transverse lineaments. The basement contours corroborate the presence <strong>of</strong><br />

Purnia Saddle and Rangpur Ridge.<br />

Most <strong>of</strong> the earthquakes in this area are shallow focus (40 km. The depth <strong>of</strong> focus for one event, that <strong>of</strong><br />

21.05.1935, has been interpreted to be 140 km. As such observed seismic events are<br />

mostly concentrated in Main Himalayan Belt. Keeping in view the seismotectonic set up<br />

8


and seismicity, the area has been kept in Zone – IV as per Map <strong>of</strong> India Showing<br />

Seismic Zones (IS - 1893 (part –I) : 2002).<br />

GEOTECHNICAL APPRAISAL<br />

The proposed <strong>Rangyong</strong> Hydroelectric Project is located downstream <strong>of</strong> Rukel<br />

Hydroelectric Project in valley <strong>of</strong> <strong>Rangyong</strong> Chhu. This scheme involves diversion <strong>of</strong><br />

discharges <strong>of</strong> Umram Chhu and Passasam Chu with a view to augment discharge <strong>of</strong><br />

<strong>Rangyong</strong> Chhu through a diversion structure proposed to be located just downstream<br />

<strong>of</strong> confluence <strong>of</strong> both the tributaries near Pussamphyaku. The site <strong>of</strong> the diversion<br />

structure exposes banded and augen gneisses and quartzite – biotite gneisses<br />

belonging to CCGC. The rocks are foliated and jointed. It is suggested that thickness <strong>of</strong><br />

overburden in the river bed and on the abutments be assessed and availability <strong>of</strong> bed<br />

rock on the abutments be assured before finalizing the type <strong>of</strong> structure and location.<br />

The discharge is proposed to be diverted to the main diversion structure through a 2 km<br />

long diversion tunnel. This diversion tunnel is expected to encounter the gneisses <strong>of</strong><br />

CCGC. These are expected to provide good tunneling media. The main diversion<br />

structure on <strong>Rangyong</strong> Chhu is proposed just downstream <strong>of</strong> powerhouse <strong>of</strong> upstream<br />

Rukel Hydroelectric Project. Similar studies are suggested for the diversion structure.<br />

The water conductor system comprising about 7.5 km long HRT for conveying<br />

combined discharge to powerhouse is proposed on the right bank <strong>of</strong> <strong>Rangyong</strong> Chhu.<br />

The proposed HRT is expected to encounter the high grade gneisses belonging to<br />

CCGC on major portion and garnet – kyanite – sillimanite – biotite quartz schist and<br />

interbedded quartzite and garnetiferous quartz biotite schist belonging to Chhungthang<br />

Group. The rocks belonging to CCGC and Chhunghang Group are interbanded and are<br />

expected to provide good to fair tunneling media in general except for reaches where<br />

local faults and shears are encountered where poor rock conditions can be expected.<br />

The preliminary layout <strong>of</strong> the project indicates that no intermediate construction adit has<br />

been included along this 7.5 km long HRT. It is suggested that tunnel be shifted towards<br />

river in the middle reaches and a kink be provided so that at least one construction adit<br />

is provided to facilitate construction. However, adequate lateral and top covered be<br />

ensured so that structure is safe. Patches <strong>of</strong> Lingtse Granite may also be encountered<br />

9


in HRT. The proposed underground powerhouse with installed capacity <strong>of</strong> 175 MW is<br />

envisaged on the right bank <strong>of</strong> <strong>Rangyong</strong> Chhu just upstream <strong>of</strong> powerhouse <strong>of</strong> the<br />

proposed Lingza Hydroelectric Project near Lingza. It is expected to encounter<br />

interbedded quartzite and garnetiferous quartz biotite schist. The rock conditions are<br />

expected to be fair in general. The tailrace may also encounter high grade schists which<br />

are kyanite – sillimanite schist. The Project is located in zone-IV as per Map <strong>of</strong> India<br />

Showing Seismic Zones (BIS : 1893 (Part-I) : 2002). Therefore proper seismic<br />

coefficient be incorporated in the designs <strong>of</strong> appurtenant structures <strong>of</strong> the project. This<br />

preliminary geotechnical appraisal is without field visit to the project site.<br />

REFERENCE<br />

Chakraborti, B., and Banerjee, H., (1982). Geology and Structure <strong>of</strong> the Area around<br />

Chungthang - Mangan – Tolung, North Sikkim. Unpubl. Prog. Rep. Geological Survey <strong>of</strong><br />

India, F.S. 1980-81.<br />

Kumar, J.P., and Mitra, P.K. (1984). Geology and Structure <strong>of</strong> the Area Around<br />

Sakkyong, Mangan, Dikchu, Lingi and Mangka Covering Parts <strong>of</strong> North South and East<br />

Sikkim. Unpubl. Prog. Rep. Geological Survey <strong>of</strong> India, F.S. 1982-83.<br />

Narula, P.L. Acharayya, S.K., and Banerjee, J., (Eds) (2000). Seismotectonic Atlas <strong>of</strong><br />

India and its Environs, GSI Publication.<br />

Neogi S., Purkaint, B. and Samaddar, A.K. (1984). Geology <strong>of</strong> the Area Around<br />

Tashiding – Lapdang – Maidang La-Karshang – Lampokhari – Khungre, West District,<br />

Sikkim. Unpubl. Prog. Rep. Geological Survey <strong>of</strong> India, F.S. 1982-83.<br />

Neogi, S., Kumar, J.P., Mitra, N.D., Samaddar, A.K. and Dawande, A.K. (1986).<br />

Geology <strong>of</strong> the Area Around Tolung – Thijp, - Kishong, North Sikkim District, Sikkim.<br />

Unpubl. Geological Survey <strong>of</strong> India Prog. Preg., F.S. 1983-84.<br />

Raina, U.K. (1966). Geological Mapping in the western part <strong>of</strong> Sikkim. Unpubl.<br />

Geological Survey <strong>of</strong> India, Rep., F.S. 1965-66.<br />

10


1<br />

Annexure-4.2<br />

TECHNICAL REPORT ON SEISMIC HISTORY AND SEISMICITY OF THE<br />

TEESTA BASIN OF SIKXKIM COVERING PROPOSED SITES FOR<br />

HYDROELECTRIC SCHEMES<br />

Historical and instrumentally recorded data on earthquakes show that the whole area <strong>of</strong><br />

the proposed sites for hydroelectric schemes at Dikchu, Rongni Storage, Panan,<br />

Namlum, Zedang, Teesta St-I, Ringpi, Lingza, Rukel and <strong>Rangyong</strong> in Sikkim lies in a<br />

region liable to damage due to moderate to great earthquakes. Noteworthy earthquakes<br />

which affected the region in the past are (i) the Cachar earthquake <strong>of</strong> 10.01.1869<br />

(Magnitude= 7.5 on Richter scale), (ii) the Shillong plateau earthquake <strong>of</strong> 12.06.1897<br />

(Magnitude= 8.7), (iii) the Dhubri earthquake <strong>of</strong> 02.07.1930 (Magnitude= 7.1), (iv) the<br />

Bihar-Nepal Border earthquake <strong>of</strong> 15.01.1934 (Magnitude= 8.3), (v) the Assam<br />

earthquake <strong>of</strong> 15.08.1950 (Magnitude= 8.5) and (vi) the Nepal-India Border earthquake<br />

<strong>of</strong> 21.08.1988 (Magnitude= 6.4). The 1897 earthquake had its epicentral tract in and<br />

around Shillong where there was considerable damage to lives and property, in addition<br />

to other effects <strong>of</strong> very strong ground shaking. One <strong>of</strong> the significant observations made<br />

on this earthquake was that boulders were thrown out vertically upwards from their<br />

original places showing that the force <strong>of</strong> earthquake motion exceeded the force due to<br />

gravity, at least momentarily. The earthquake was followed by a large number <strong>of</strong><br />

aftershocks.<br />

In addition to the above significant earthquakes, the region has experienced<br />

several earthquakes <strong>of</strong> lesser intensity originating within a radius <strong>of</strong> 450 km around<br />

Shillong and neighbouring regions. A list <strong>of</strong> important earthquakes from I.M.D.<br />

catalogue occurred in the region bounded by Lat. 25.00 to 30.00°N and Long. 86.00 to<br />

91.00°E for the period 1505 to 2001 is enclosed.<br />

The occurrence <strong>of</strong> earthquakes in Sikkim region is broadly associated with the<br />

tectonic activity along the well-known faults in the Himalayas such as the Main<br />

Boundary Thrust (MBT) and the Main Central Thrust (MCT). Besides, earthquakes<br />

occurring along some other faults namely Malda-Kishanganj Fault, Tista Fault, Purnia-<br />

Everest Lineament, Katihar-Nailphamani Fault, Dhubri Fault etc. have also affected the<br />

region.<br />

In the seismic zoning map <strong>of</strong> India prepared by a committee <strong>of</strong> experts under the<br />

auspices <strong>of</strong> Bureau <strong>of</strong> Indian Standards (BIS: 1893: Part I 2002), the entire area <strong>of</strong><br />

Sikkim has been placed in the zone IV. The seismic zone IV is broadly associated with<br />

a seismic intensity VIII on Modified Mercalli (MM) scale. It may be mentioned that the<br />

seismic intensity VIII corresponds to a horizontal ground acceleration range <strong>of</strong> 51-<br />

350cm/sec 2 or an average acceleration <strong>of</strong> 172cm/sec 2 in any direction. The ground<br />

acceleration and hence the intensity <strong>of</strong> an earthquake at a place depends on magnitude<br />

<strong>of</strong> earthquake, distance from the focus, duration <strong>of</strong> earthquake, type <strong>of</strong> underlying soil<br />

and its damping characteristics and liquefaction potential. The damage to the buildings


founded on sandy soil is higher than that in the similar type <strong>of</strong> buildings having their<br />

foundation on hard bedrock. Also, the damage will be higher for higher magnitude and<br />

long duration earthquakes, less epicentral distance s<strong>of</strong>t soil conditions and area with<br />

high liquefaction potential.<br />

Presently, there is no scientific technique available anywhere in the world to predict<br />

occurrence <strong>of</strong> earthquakes with reasonable degree <strong>of</strong> accuracy with regard to space,<br />

time and magnitude. It is, therefore suggested that appropriate steps may be taken to<br />

ensure that the dwellings and other structures in the region are designed and constructed<br />

as per guidelines laid down by Bureau <strong>of</strong> Indian Standards (BIS) to minimize the losses<br />

caused by earthquakes. Suitable seismic design parameters may be adopted as per<br />

recommendations <strong>of</strong> National Committee on Seismic Design Parameters (NCSDP)<br />

for designing and engineering Hydroelectric Projects.<br />

EXPLANATION OF COMPUTER OUTPUT (IMD CATALOGUE)<br />

1. “O” – Time means time <strong>of</strong> Origin <strong>of</strong> Earthquake in UTC.<br />

2. “Depth” means Focal Depth in Kilometers. If depth is reported as 33, it means<br />

that the earthquake is located in the crust but its focal depth could not be<br />

determined.<br />

3. “MAG” means magnitude on Richter scale.<br />

4. “Zero” under any column means that the parameters have not been determined.<br />

2


MODIFIED MERCALLI INTENSITY SCALE (ABRIDGED)<br />

CLASS OF REMARKS<br />

EARTHQUAKE<br />

I Not felt except by a very few under specially favourable circumstances.<br />

II Felt only by a few persons at rest, specially on upper floors <strong>of</strong> buildings; and<br />

delicately suspended objects may swing.<br />

III Felt quite noticeably indoors, specially on upper floors <strong>of</strong> buildings but many<br />

people do not recognize it as an earthquake; standing motor cars may rock<br />

slightly; and vibration may be felt like the passing <strong>of</strong> a truck.<br />

IV During the day felt indoors by many, outdoors by a few, at night some<br />

awakened; dishes, windows, doors disturbed; walls make creaking sound,<br />

sensation like heavy truck striking the building; and standing motor cars rocked<br />

noticeably.<br />

V Felt by nearly everyone; many awakened; some dishes, windows, etc. broken; a<br />

few instances <strong>of</strong> cracked plaster; unstable object overturned; disturbance <strong>of</strong><br />

trees; polls and other tall objects notices sometimes; and pendulum clocks may<br />

stop.<br />

VI Felt by all, many frightened and run outdoors; some heavy furniture moved; a<br />

few instances <strong>of</strong> fallen plaster or damaged chimneys and damaged slight.<br />

VII Everybody runs outdoors, damage negligible in buildings <strong>of</strong> good design and<br />

construction; slight to moderate in well built ordinary structures; considerable<br />

in poorly built or badly designed structures; and some chimneys broken, noticed<br />

by person driving motor cars.<br />

VIII Damage slight in specially design structures; considerable in ordinary but<br />

substantial buildings with partial collapse; very heavy in poorly build structures;<br />

panel walls thrown out <strong>of</strong> framed structured; falling <strong>of</strong> chimney, factory stacks,<br />

columns, monuments and walls; heavy furniture overturned, sand and mud<br />

ejected in small amounts; changes in well water; and disturbs person driving<br />

motor cars.<br />

IX Damage considerable in specially designed structures: well designed framed<br />

structures thrown out <strong>of</strong> plumb; very heavy in substantial buildings with partial<br />

collapse; buildings shifted <strong>of</strong>f foundations; ground cracked conspicuously; and<br />

underground pipes broken.<br />

3


X Some well built wooden structures destroyed; most masonry and framed<br />

structures with foundations destroyed; ground badly cracks; rails bent;<br />

landslides considerable from river banks and steep slopes; shifted sand and mud;<br />

and water splashed over banks.<br />

XI Few, if any, masonry structures remain standing; bridges destroyed; broad<br />

fissures in ground, underground pipelines completely out <strong>of</strong> services; earth<br />

slumps and landslips in s<strong>of</strong>t ground; and rails bent greatly.<br />

XII Total damage; waves seen on ground surfaces; lines <strong>of</strong> sight and levels distorted;<br />

and objects thrown upward<br />

4


LIST OF EARTHQUAKES FROM IMD CATALOGUE OCCURING BETWEEN LAT25 . 00 TO 30 . 00<br />

DEG. AND LONG 86 . 00 TO 91 . 00DEG. E FOR THE PERIOD 1505 TO 2001<br />

DATE<br />

O-TIME LAT LONG DEPTH MAG<br />

Y M D Hr Mn Sec Deg-N Deg-E Km<br />

1833 8 26 0 0 . 0 27 . 50 86 . 50 0 . 7 . 5<br />

1834 7 8 0 0 . 0 25 . 80 89 . 40 0 . 6 . 3<br />

1834 7 21 0 0 . 0 25 . 80 89 . 40 0 . 6 . 0<br />

1842 2 5 21 15 . 0 25 . 00 87 . 00 0 . 5 . 5<br />

1842 11 11 0 0 . 0 25 . 00 90 . 00 0 . 6 . 5<br />

1843 8 10 0 0 . 0 27 . 00 88 . 30 0 . 5 . 5<br />

1849 2 27 0 0 . 0 27 . 00 88 . 30 0 . 6 . 0<br />

1852 5 0 0 0 . 0 27 . 00 88 . 00 0 . 6 . 5<br />

1897 6 12 11 6 . 0 25 . 90 91 . 00 0 . 8 . 7<br />

1899 9 25 0 0 . 0 27 . 00 88 . 30 0 . 6 . 0<br />

1909 2 17 0 0 . 0 27 . 00 87 . 00 0 . 5 . 0<br />

1918 2 4 17 54 49 . 0 29 . 60 87 . 80 0 . 6 . 0<br />

1923 4 24 22 3 6 . 0 29 . 60 87 . 80 0 . 5 . 5<br />

1923 9 9 22 3 42 . 0 25 . 30 91 . 00 0 . 7 . 1<br />

1926 12 4 11 15 23 . 0 29 . 60 87 . 80 0 . 6 . 0<br />

1930 7 2 21 3 34 . 0 25 . 80 90 . 20 0 . 7 . 1<br />

1930 7 3 0 19 5 . 0 25 . 80 90. 20 0 . 5 . 5<br />

1930 7 4 18 54 44 . 0 25 . 80 90 . 20 0 . 5 . 5<br />

1930 7 4 21 34 . 0 25 . 80 90. 80 0 . 5 . 5<br />

1930 7 8 4 32 24 . 0 25 . 80 90 . 80 0 . 5 . 5<br />

1930 7 8 9 43 . 0 25 . 80 90. 80 0 . 5 . 5<br />

1930 7 13 14 0 12 . 0 25 . 80 90 . 80 0 . 5 . 5<br />

1932 3 24 16 8 44 . 0 25 . 80 90 . 20 0 . 5 . 5<br />

1932 3 25 4 29 32 . 0 30 . 00 89 . 20 0 . 5 . 5<br />

1933 3 6 13 5 38 . 0 25 . 70 90 . 50 0 . 5 . 8<br />

1934 1 15 8 43 25 . 0 26 . 60 86. 80 0 . 8 . 3<br />

1934 1 16 4 59 22 . 0 28 . 00 86 . 00 0 . 5 . 6<br />

1934 7 21 0 0 . 0 25 . 80 89 . 40 0 . 5 . 5<br />

1935 5 21 4 22 31 . 0 28 . 80 89 . 30 140 . 6 . 3<br />

1936 5 30 7 8 38 . 0 25 . 70 90 . 50 0 . 5 . 3<br />

1936 6 9 0 2 42 . 0 27 . 50 87 . 00 0 . 5 . 5<br />

1936 6 18 14 56 27 . 0 26 . 60 90 . 30 0 . 5 . 8<br />

1936 9 7 2 30 49 . 0 27 . 50 87 . 00 0 . 5 . 7<br />

1937 8 15 11 36 48 . 0 30 . 00 90 . 00 0 . 5 . 8<br />

1938 1 29 4 13 8 . 0 27 . 50 87 . 00 0 . 5 . 8<br />

1938 2 26 12 10 43 . 0 28 . 00 90 . 50 0 . 5 . 7<br />

1938 4 13 1 10 17 . 0 26 . 00 91 . 00 0 . 5 . 2<br />

1939 6 4 22 36 . 0 28 . 50 86 . 50 0 . 5 . 7<br />

5


1940 8 2 3 3 59 . 0 28 . 00 90 . 50 0 . 5 . 2<br />

1945 5 19 5 2 53 . 0 25 . 10 90 . 90 0 . 6 . 1<br />

1949 12 10 19 37 14 . 0 26 . 00 89 . 00 0 . 6 . 0<br />

1950 2 26 3 35 48 . 0 28 . 00 90 . 50 0 . 6 . 0<br />

1951 4 7 20 29 12 . 0 25 . 90 90 . 50 0 . 6 . 8<br />

1951. 5 28 15 59 19 . 0 29 . 00 87 . 00 0 . 6 . 0<br />

1952 3 6 9 11 23 . 0 29 . 60 90 . 80 0 . 5 . 5<br />

1952 11 19 10 23 28 . 0 29 . 80 86 . 60 0 . 6 . 0<br />

1955 3 27 14 38 43 . 0 29 . 90 90 . 20 0 . 6 . 3<br />

1958 11 23 20 15 48 . 0 28 . 79 86 . 94 0 . 5 . 5<br />

1959 6 10 4 25 15 . 0 30 . 00 91 . 00 0 . 5 . 7<br />

1960 7 29 10 42 44 . 6 26 . 90 90 . 30 11 . 6 . 5<br />

1960 8 21 3 29 4 . 9 27 . 00 88 . 50 29 . 5 . 5<br />

1961 9 29 22 36 30 . 0 28 . 00 87 . 00 0 . 5 . 5<br />

1961 12 25 11 19 10 . 0 27 . 00 90 . 00 0 . 5 . 5<br />

1963 2 22 1 32 30 . 0 27 . 20 87 . 10 0 . 5 . 2<br />

1964 2 1 11 28 19 . 2 27 . 30 87 . 78 33 . 4 . 8<br />

1964 3 27 23 3 41 . 1 27 . 13 89 . 36 29 . 5 . 0<br />

1964 4 13 3 19 57 . 3 27 . 52 90 . 17 1 . 5 . 2<br />

1964 8 30 2 35 7 . 3 27 . 36 88 . 21 21 . 5 . 1<br />

1964 11 9 16 12 51 . 9 29 . 53 86 . 04 33 . 5 . 0<br />

1965 1 12 13 32 24 . 1 27 . 40 87 . 84 23 . 5 . 8<br />

1965 1 12 13 55 18 . 1 27 . 31 87 . 68 18 . 5 . 2<br />

1967 3 2 11 47 13 . 0 28 . 70 86 . 38 20 . 4 . 8<br />

1968 8 18 14 18 58 . 0 26 . 42 90 . 62 22 . 5 . 1<br />

1968 10 28 17 48 30 . 1 27 . 57 86 . 03 37 . 4 . 9<br />

1969 11 5 20 25 13 . 7 27 . 66 90 . 24 13 . 5 . 0<br />

1970 7 25 1 35 26 . 0 25 . 72 88 . 58 32 . 5 . 1<br />

1971 10 24 8 59 6 . 3 28 . 30 87 . 19 57 . 4 . 8<br />

1971 10 31 15 54 48 . 2 26 . 18 90 . 65 33 . 4 . 7<br />

1971 12 4 8 38 . 2 27 . 92 87 . 95 29 . 5 . 2<br />

1972 8 21 14 4 34 . 2 27 . 33 88 . 01 33 . 4 . 5<br />

1972 11 6 10 56 13 . 5 26 . 88 88 . 43 59 . 4 . 4<br />

1973 3 22 1 6 57 . 4 28 . 12 87 . 15 33 . 5 . 0<br />

1973 8 1 14 5 15 . 5 29 . 59 89 . 17 63 . 4 . 9<br />

1974 3 24 14 16 1 . 1 27 . 66 86 . 00 0 . 5 . 4<br />

1974 3 24 16 17 35 . 3 27 . 63 86 . 01 3 . 4 . 7<br />

1975 1 23 1 37 42 . 6 27 . 44 88 . 37 33 . 4 . 5<br />

1975 2 6 6 39 48 . 7 27 . 95 87 . 67 63 . 4 . 7<br />

1975 4 24 1 35 51 . 2 27 . 44 87 . 04 26 . 4 . 9<br />

1975 6 24 15 38 28 . 1 27 . 74 87 . 50 33 . 4 . 8<br />

1975 11 21 13 49 27 . 9 26 . 96 86 . 54 0 . 4 . 9<br />

1975 11 26 15 2 31 . 1 28 . 15 87 . 80 33 . 5 . 0<br />

1976 9 14 6 43 51 . 6 29 . 81 89 . 57 75 . 5 . 4<br />

1977 6 5 19 21 37 . 4 26 . 07 88 . 43 0 . 4 . 7<br />

1978 10 14 18 48 48 . 9 27 . 66 87 . 33 0 . 4 . 8<br />

1978 10 23 14 36 50 . 4 28 . 56 86 . 78 33 . 4 . 4<br />

1979 4 2 1 16 46 . 5 26 . 46 90 . 68 33 . 4 . 4<br />

1979 4 11 16 8 12 . 6 25 . 98 88 . 84 33 . 4 . 7<br />

1979 6 19 16 29 8 . 4 26 . 74 87 . 48 1 . 5 . 2<br />

6


1979 10 17 1 44 22 . 2 27 . 97 87 . 62 33 . 4 . 6<br />

1979 11 16 19 17 27 . 4 27 . 95 88 . 69 39 . 4 . 6<br />

1980 6 11 5 25 15 . 4 25 . 79 90 . 31 68 . 4 . 9<br />

1980 11 19 19 0 44 . 5 27 . 40 88 . 80 1 . 6. 0<br />

1980 12 22 4 36 8 . 0 26 . 67 89 . 59 33 . 4 . 4<br />

1980 12 26 5 19 44 . 9 29 . 08 88 . 88 66 . 4 . 5<br />

1981 2 9 15 49 21 . 6 27 . 20 89 . 76 16 . 4 . 9<br />

1981 11 21 4 25 5 . 6 29 . 52 89 . 12 50 . 4 . 8<br />

1982 1 28 7 18 7 . 6 25 . 47 90 . 89 33 . 4 . 4<br />

1982 2 26 0 5 47 . 5 25 . 79 90 . 62 48 . 4 . 6<br />

1982 4 5 2 19 41 . 1 27 . 38 88 . 84 9 . 5 . 0<br />

1982 6 20 15 29 19 . 8 26 . 24 89 . 97 33 . 4 . 5<br />

1982 7 6 6 13 32 . 0 25 . 88 90 . 31 8 . 5 . 0<br />

1982 8 18 18 1 7 . 6 27 . 04 89 . 26 51 . 4 . 6<br />

1983 10 16 22 3 14 . 5 29 . 51 90 . 31 33 . 4 . 5<br />

1983 12 16 15 15 40 . 1 28 . 37 86 . 65 116 . 4 . 2<br />

1983 12 23 19 35 44 . 2 25 . 87 87 . 91 33 . 4 . 3<br />

1984 1 25 23 49 44 . 6 27 . 49 86 . 10 11 . 4 . 6<br />

1985 5 25 0 28 18 . 7 27 . 60 88 . 48 33 . 4 . 6<br />

1985 6 7 18 23 59 . 0 26 . 87 90 . 21 33 . 4 . 8<br />

1985 6 17 21 52 49 . 0 25 . 65 90 . 20 22 . 4 . 6<br />

1985 10 2 16 33 50 . 3 27 . 19 89 . 73 45 . 4 . 4<br />

1986 1 7 20 20 . 4 27 . 40 88 . 43 41 . 4 . 7<br />

1986 1 10 3 46 30 . 9 28 . 65 86 . 56 63 . 5 . 5<br />

1986 2 2 0 13 50 . 7 27 . 92 86 . 45 33 . 4 . 5<br />

1986 2 10 12 56 23 . 0 28 . 15 87 . 86 87 . 4 . 7<br />

1986 4 12 12 44 2 . 2 28 . 63 86 . 57 33 . 4 . 8<br />

1986 10 25 21 25 30 . 4 26 . 12 88 . 26 33 . . 0<br />

1986 12 1 19 14 29 . 0 28 . 30 87 . 80 10 . . 0<br />

1987 4 23 9 5 56 . 8 27 . 93 87 . 01 48 . 4 . 7<br />

1987 4 25 22 13 47 . 0 25 . 30 88 . 46 10 . . 0<br />

1987 5 10 5 10 42 . 3 28 . 99 87 . 26 33 . 4 . 5<br />

1987 6 22 23 6 53 . 5 28 . 40 87 . 17 33 . 4 . 1<br />

1987 9 25 23 16 29 . 0 29 . 84 90 . 37 19 . 5 . 1<br />

1987 9 26 1 3 3 . 0 29 . 82 90 . 45 33 . 4 . 4<br />

1987 9 29 17 30 28 . 3 29 . 91 90 . 41 33 . 4 . 6<br />

1987 9 29 21 12 30 . 0 29 . 70 90 . 41 46 . 4 . 5<br />

1987 10 6 22 18 17 . 2 29 . 90 90 . 42 10 . 4 . 7<br />

1987 10 22 21 23 56 . 0 27 . 07 89 . 06 19 . 4 . 2<br />

1987 11 25 19 20 40 . 0 27 . 70 86 . 17 33 . 4 . 5<br />

1987 12 6 23 29 44 . 0 27 . 00 88 . 52 42 . . 0<br />

1987 12 11 6 39 40 . 0 26 . 04 90 . 92 57 . 4 . 6<br />

1987 12 12 5 49 . 0 29 . 80 90 . 40 45 . 4 . 8<br />

1988 1 10 6 18 35 . 0 29 . 75 90 . 29 50 . 4 . 7<br />

1988 1 10 6 31 42 . 7 29 . 89 90 . 44 10 . 4 . 7<br />

1988 1 19 11 23 51 . 0 27 . 80 88 . 80 33 . 4 . 3<br />

1988 3 27 5 56 30 . 0 27 . 10 88 . 42 70 . 4 . 1<br />

1988 4 9 12 57 55 . 7 29 . 84 86 . 87 33 . 4 . 4<br />

1988 4 20 6 40 25 . 8 27 . 02 86 . 72 55 . 5 . 4<br />

1988 4 25 16 4 3 . 7 26 . 90 86 . 54 79 . 4 . 7<br />

7


1988 5 10 7 16 16 . 1 25 . 32 90 . 88 33 . 4 . 4<br />

1988 5 26 16 30 5 . 5 27 . 45 88 . 61 42 . 4 . 7<br />

1988 5 28 23 13 12 . 0 28 . 00 89 . 70 33 . . 0<br />

1988 8 20 23 9 10 . 1 26 . 72 86 . 63 65 . 6 . 4<br />

1988 8 20 23 38 56 . 0 26 . 90 86 . 70 38 . . 0<br />

1988 8 22 11 34 34 . 7 26 . 61 86 . 74 33 . 4 . 3<br />

1988 8 24 9 55 34 . 3 26 . 77 86 . 44 41 . 4 . 7<br />

1988 8 29 12 12 17 . 0 26 . 39 87 . 50 33 . 4 . 5<br />

1988 9 1 22 4 11 . 3 26 . 80 86 . 53 33 . 4 . 5<br />

1988 9 2 6 35 34 . 3 26 . 56 86 . 48 33 . 4 . 3<br />

1988 9 27 19 10 10 . 0 27 . 19 88 . 37 28 . 5 . 0<br />

1988 12 10 15 24 31 . 4 26 . 38 86 . 68 33 . . 0<br />

1988 12 13 6 29 17 . 3 27 . 14 87 . 97 52 . 4 . 4<br />

1988 12 24 13 32 22 . 0 26 . 90 88 . 00 41 . 4 . 4<br />

1988 12 27 2 56 1 . 8 27 . 98 87 . 86 38 . 4 . 6<br />

1989 2 12 23 44 57 . 0 30 . 00 89 . 86 53 . . 0<br />

1989 4 9 2 31 36 . 3 29 . 11 90 . 02 10 . 5 . 1<br />

1989 4 16 0 2 33 . 0 29 . 20 89 . 70 33 . . 0<br />

1989 5 10 23 20 34 . 0 27 . 70 87 . 20 33 . . 0<br />

1989 5 22 19 24 31 . 0 27 . 38 87 . 86 4 . 5 .0<br />

1989 6 11 13 42 45 . 7 26 . 39 90 . 70 50 . 4 . 5<br />

1989 7 30 21 4 44 . 0 30 . 00 90 . 50 33 . . 0<br />

1989 10 10 4 10 56 . 0 28 . 36 87 . 49 38 . 4 . 7<br />

1989 11 19 22 11 34 . 0 29 . 00 89 . 70 33 . 4 . 4<br />

1990 1 9 2 29 21 . 8 28 . 15 88 . 11 35 . 5 . 7<br />

1990 1 10 23 1 21 . 7 26 . 52 86 . 67 66 . 4 . 4<br />

1990 2 18 18 12 48 . 3 29 . 39 89 . 95 10 . 4 . 5<br />

1990 2 22 13 33 16 . 6 29 . 14 90 . 02 54 . 4 . 9<br />

1990 2 23 14 25 19 . 3 29 . 38 90 . 02 10 . 4 . 3<br />

1990 3 1 18 47 28 . 0 28 . 70 88 . 40 33 . 4 . 2<br />

1990 5 6 10 30 9 . 0 29 . 99 89 . 98 33 . 4 . 2<br />

1990 5 19 2 18 57 . 0 25 . 40 90 . 93 33 . . 0<br />

1990 7 13 11 50 11 . 0 28 . 20 86 . 90 33 . 4 . 5<br />

1990 10 29 12 6 28 . 0 27 . 60 89 . 10 33 . . 0<br />

1991 1 5 14 50 8 . 0 28 . 90 87 . 92 33 . . 0<br />

1991 3 4 0 55 38 . 0 28 . 10 89 . 20 33 . . 0<br />

1991 3 15 4 28 18 . 2 28 . 34 87 . 55 64 . 4 . 7<br />

1991 6 8 18 59 57 . 8 26 . 30 90 . 37 33 . 4 . 0<br />

1991 8 7 11 36 29 . 1 25 . 27 88 . 66 10 . 4 . 7<br />

1991 8 19 22 28 41 . 0 26 . 80 90 . 70 10 . . 0<br />

1991 9 25 19 26 49 . 3 26 . 70 88 . 40 33 . . 0<br />

1991 9 27 11 56 40 . 8 29 . 90 90 . 40 33 . . 0<br />

1991 10 30 13 13 57 . 0 26 . 00 88 . 60 33 . . 0<br />

1991 12 21 19 52 45 . 1 27 . 79 87 . 96 65 . 4 . 7<br />

1992 3 7 22 41 50 . 8 29 . 40 89 . 40 113 . 4 . 3<br />

1992 4 1 13 41 3 . 9 27 . 40 87 . 10 33 . 4 . 3<br />

1992 4 4 17 43 20 . 7 28 . 10 88 . 00 33 . 4 . 9<br />

1992 4 20 19 22 59 . 7 25 . 80 90 . 60 55 . 4 . 2<br />

1992 7 24 6 24 17 . 6 29 . 30 90 . 20 33 . 4 . 8<br />

1992 7 30 8 24 46 . 6 29 .60 90 . 20 14 . 5 . 9<br />

8


1992 7 30 9 7 39 . 1 29 . 90 90 . 30 33 . 4 . 2<br />

1992 7 30 13 36 42 . 0 29 . 80 90 . 30 33 . 4 . 4<br />

1992 7 30 17 28 53 . 9 30 . 00 90 . 40 33 . 4 . 5<br />

1992 7 30 19 6 13 . 3 29 . 80 90 . 20 33 . 4 . 3<br />

1992 8 4 22 50 3 . 0 29 . 90 90 . 40 10 . 4 . 2<br />

1992 8 8 19 50 42 . 6 29 . 90 90 . 30 33 . 4 . 3<br />

1992 8 9 22 34 46 . 4 28 . 70 86 . 50 37 . 4 . 3<br />

1993 2 15 14 29 40 . 8 25 . 90 87 . 50 30 . 5 . 0<br />

1993 3 3 5 17 31 . 0 25 . 40 90 . 20 33 . 4 . 5<br />

1993 3 20 14 51 59 . 7 29 . 10 87 . 30 12 . 5 . 8<br />

1993 3 20 21 26 39 . 4 29 . 00 87 . 40 21 . 5 . 0<br />

1993 3 31 13 44 10 . 1 29 . 10 87 . 30 20 . 5 . 1<br />

1993 7 3 2 0 22 . 2 28 . 30 86 . 60 33 . 4 . 7<br />

1993 7 9 16 23 17 . 3 26 . 80 86 . 00 33 . 4 . 6<br />

1993 9 5 6 5 54 . 6 27 . 20 87 . 30 33 . 4 . 5<br />

1993 12 14 2 27 44 . 4 28 . 40 86 . 80 33 . 4 . 8<br />

1993 12 14 2 27 44 . 4 28 . 40 86 . 80 33 . 4 . 8<br />

1994 1 16 14 22 38 . 3 26 . 40 89 . 10 33 . 3 . 9<br />

1994 4 15 14 28 48 . 7 25 . 90 90 . 50 33 . 4 . 2<br />

1994 5 25 7 38 53 . 7 26 . 60 87 . 80 48 . 4 . 6<br />

1995 1 1 19 36 13 . 6 27 . 80 87 . 60 33 . 4 . 9<br />

1995 1 12 23 39 51 . 0 29 . 40 88 . 20 33 . 4 . 9<br />

1995 8 8 16 52 48 . 8 26 . 40 90 . 40 33 . 4 . 4<br />

1995 12 6 0 50 33 . 0 25 . 20 91 . 00 33 . 4 . 5<br />

1995 12 11 9 49 36 . 0 27 . 60 87 . 50 33 . 4 . 0<br />

1996 1 25 7 15 19 . 3 28 . 00 87 . 00 33 . 5 . 2<br />

1996 1 25 7 15 13 . 0 28 . 40 86 . 90 33 . 4 . 4<br />

1996 3 23 16 7 34 . 2 27 . 20 88 . 30 33 . 4 . 0<br />

1996 4 26 16 31 3 . 0 27 . 80 87 . 60 33 . 5 . 2<br />

1996 5 10 9 7 1 . 8 30 . 00 88 . 10 0 . 4 . 8<br />

1996 5 11 3 58 50 . 2 29 . 90 88 . 10 0 . 4 . 8<br />

1996 5 11 7 27 11 . 2 29 . 90 88 . 10 0 . 4 . 3<br />

1996 5 14 5 41 8 . 9 29 . 70 87 . 90 0 . 4 . 1<br />

1996 7 3 7 0 28 . 9 29 . 90 88 . 10 0 . 4 . 1<br />

1996 7 3 10 10 33 . 8 29 . 90 88 . 20 0 . 5 . 0<br />

1996 7 3 10 19 42 . 9 30 .00 88 . 20 0 . 4 . 3<br />

1996 7 3 10 49 50 . 5 29 . 90 87 . 80 0 . 4 . 1<br />

1996 7 4 18 11 4 . 6 30 . 00 88 . 10 0 . 4 . 9<br />

1996 7 6 8 12 39 . 4 29 . 90 87 . 90 0 . 3 . 8<br />

1996 7 13 8 29 4 . 0 29 . 90 88 . 10 0 . 4 . 3<br />

1996 7 22 15 54 7 . 0 30 . 00 88 . 00 0 . 4 . 5<br />

1996 8 3 7 12 6 . 0 30 . 00 88 . 20 0 . 4 . 1<br />

1996 8 18 2 48 . 0 25 . 80 90 . 10 0 . 4 . 4<br />

1996 9 13 3 41 8 . 6 27 . 00 88 . 20 33 . 4 . 5<br />

1996 9 25 17 41 17 . 2 27 . 40 88 . 50 33 . 5 . 0<br />

1996 10 3 1 29 3 . 1 28 . 20 87 . 50 33 . 4 . 5<br />

1996 10 14 14 49 12 . 7 29 . 90 88 . 20 33 . 4 . 4<br />

1996 12 30 11 8 18 . 9 27 . 43 86 . 63 37 . 5 . 0<br />

1996 12 30 15 16 29 . 5 27 . 23 86 . 50 33 . 3 . 6<br />

1997 1 22 11 12 4 . 4 25 . 60 90 . 30 33 . . 0<br />

9


1997 1 25 20 8 28 . 7 30 . 00 88 . 00 33 . 4 . 4<br />

1997 3 3 9 29 40 . 0 27 . 24 86 . 00 45 . 4 . 7<br />

1997 3 22 21 16 4 . 8 29 . 89 88 . 15 33 . 4 . 4<br />

1997 4 4 10 8 41 . 0 25 . 50 90 . 80 33 . 3 . 8<br />

1997 4 7 13 0 42 . 0 27 . 40 86 . 50 33 . 4 . 4<br />

1997 5 26 0 45 32 . 1 27 . 70 86 . 90 33 . . 0<br />

1997 7 5 6 22 53 . 5 28 . 80 86 . 86 33 . 4 . 8<br />

1997 7 8 21 16 49 . 8 29 . 83 88 . 31 33 . 3 . 7<br />

1997 7 9 7 18 52 . 9 29 . 90 88 . 40 33 . 4 . 1<br />

1997 7 12 23 41 9 . 7 29 . 90 88 . 40 33 . . 0<br />

1997 8 10 11 53 17 . 2 29 . 16 89 . 49 33 . 3 . 4<br />

1997 8 17 20 3 32 . 8 28 . 13 87 . 56 33 . . 0<br />

1997 9 18 7 37 10 . 0 28 . 87 86 . 15 33 . 4 . 6<br />

1997 10 11 10 11 10 . 3 27 . 70 86 . 40 33 . 4 . 3<br />

1997 10 12 19 45 25 . 8 30 . 00 88 . 00 33 . . 0<br />

1997 10 30 2 2 52 . 0 29 . 50 89 . 70 33 . 5 . 3<br />

1997 10 30 20 3 . 0 29 . 20 89 . 40 0. 4 . 9<br />

1997 11 14 12 30 23 . 9 25 . 30 87 . 70 33 . . 0<br />

1997 11 27 16 11 57 . 0 27 . 60 87 . 34 33 . 5 . 1<br />

1997 11 27 16 55 52 . 1 27 . 70 87 . 76 33 . 4 . 2<br />

1997 12 8 2 3 55 . 8 27 . 48 87 . 17 33 . 5 . 0<br />

1997 12 8 6 37 57 . 8 27 . 48 87 . 16 33 . . 0<br />

1998 1 16 18 6 42 . 5 30 . 00 86 . 00 33 . 4 . 0<br />

1998 2 1 17 32 48 . 2 28 . 10 87 . 10 33 . 4 . 5<br />

1998 2 12 2 40 29 . 1 26 . 50 88 . 10 33 . 4 . 6<br />

1998 2 28 4 59 30 . 7 27 . 00 87 . 50 33 . 4 . 4<br />

1998 3 15 20 35 29 . 3 28 . 55 86 . 88 33 . 4 . 4<br />

1998 3 16 10 35 2 . 0 26 . 90 89 . 68 33 . 3 . 8<br />

1998 3 18 18 12 18 . 9 27 . 36 88 . 33 33 . 4 . 0<br />

1998 5 13 1 24 55 . 6 28 . 18 89 . 80 10 . 4 . 9<br />

1998 7 31 17 50 18 . 3 28 . 01 87 . 73 33 . 4 . 1<br />

1998 8 18 4 10 20 . 6 27 . 55 90 . 98 22 . 5 . 2<br />

1998 8 24 7 32 21 . 5 30 . 00 87 . 92 33 . . 0<br />

1998 8 25 9 43 6 . 0 29 . 99 88 . 09 33 . 4 . 1<br />

1998 8 25 9 56 44 . 0 29 . 83 87 . 91 33 . 4 . 4<br />

1998 8 25 10 25 6 . 0 29 . 98 88 . 10 33 . 4 . 4<br />

1998 8 25 12 43 4 . 3 29 . 96 88 . 09 33 . 4 . 4<br />

1998 8 25 13 39 49 . 5 29 . 92 88 . 12 33 . 3 . 8<br />

1998 8 25 15 16 2 . 7 29 . 97 88 . 10 33 . 4 . 4<br />

1998 8 30 3 49 48 . 1 29 . 90 87 . 98 33 . 4 . 0<br />

1998 9 3 18 15 56 . 5 27 . 85 86 . 94 33 . 5 . 6<br />

1998 9 3 18 22 19 . 2 27 . 97 87 . 04 33 . . 0<br />

1998 9 3 18 51 38 . 6 27 . 65 86 . 80 33 . 4 . 4<br />

1998 9 3 21 0 53 . 5 27 . 72 86 . 88 33 . 4 . 1<br />

1998 9 3 23 2 28 . 3 27 . 60 86 . 73 33 . 4 . 6<br />

1998 9 4 0 36 17 . 9 27 . 45 86 . 46 33 . 4 . 1<br />

1998 9 4 1 10 18 . 4 27 . 77 86 . 79 33 . 4 . 2<br />

1998 9 4 21 16 13 . 7 27 . 65 86 . 72 33 . . 0<br />

1998 9 6 21 35 49 . 4 27 . 86 86 . 89 33 . 4 . 6<br />

1998 9 10 22 57 16 . 9 27 . 20 88 . 34 33 . 4 . 7<br />

10


1998 9 12 5 8 52 . 1 27 . 85 86 . 90 33 . 4 . 2<br />

1998 9 21 23 24 40 . 6 29 . 94 88 . 00 33 . 4 . 1<br />

1998 9 26 20 48 44 . 1 27 . 52 86 . 13 33 . 3 . 9<br />

1998 9 30 2 29 55 . 1 29 . 94 88 . 11 33 . 5 . 1<br />

1998 10 11 22 0 49 . 9 26 . 35 86 . 40 90 . 4 . 4<br />

1998 10 13 14 47 51 . 9 29 . 74 87 . 88 33 . . 0<br />

1998 10 16 14 17 16 . 7 30 . 00 88 . 19 33 . . 0<br />

1998 11 26 10 14 27 . 6 27 . 75 87 . 89 73 . 5 . 1<br />

1998 12 1 5 35 9 . 2 27 . 93 87 . 64 33 . 4 . 8<br />

1999 1 28 16 10 33 . 9 28 . 22 87 . 31 41 . 4 . 0<br />

1999 3 25 5 4 54 . 3 28 . 51 88 . 28 33 . 3 . 8<br />

1999 3 25 20 47 57 . 4 28 . 50 87 . 63 13 . 4 . 2<br />

1999 3 31 22 32 57 . 8 28 . 57 86 . 81 21 . . 0<br />

1999 4 10 20 42 39 . 7 28 . 04 87 . 85 33 . 4 . 2<br />

1999 5 7 17 53 52 . 3 27 . 22 90 . 64 33 . . 0<br />

1999 5 9 8 8 57 . 7 27 . 40 89 . 45 15 . . 0<br />

1999 6 13 7 38 6 . 4 28 . 14 86 . 64 33 . 4 . 4<br />

1999 7 4 6 5 15 . 2 25 . 42 90 . 28 33 . 3 . 8<br />

1999 8 1 8 24 51 . 2 28 . 37 86 . 79 40 . 5. 0<br />

1999 9 5 2 28 22 . 8 28 . 07 87 . 53 33 . 4 . 5<br />

1999 9 8 18 8 27 . 9 27 . 90 87 . 91 19 . 3 . 7<br />

1999 9 16 12 20 9 . 8 27 . 55 87 . 71 33 . . 0<br />

1999 9 20 7 28 5 . 6 27 . 24 87 . 98 23 . 4 . 1<br />

1999 9 21 13 54 39 . 8 25 . 16 88 . 86 2 . 3 . 9<br />

1999 10 15 7 33 1 . 0 29 . 61 90 . 06 33 . 4 . 4<br />

1999 10 18 16 12 55 . 7 26 . 68 87 . 22 33 . . 0<br />

1999 11 5 15 57 21 . 4 28 . 59 87 . 08 23 . 3 . 7<br />

1999 11 17 5 27 14 . 0 28 . 09 89 . 18 33 . 3 . 6<br />

1999 1 28 16 10 33 . 9 28 . 22 87 . 31 41 . 4 . 0<br />

1999 3 25 5 4 54 . 3 28 . 51 88 . 28 33 . 3 . 8<br />

1999 3 25 20 47 57 . 4 28 . 50 87 . 63 12 . 4 . 2<br />

1999 4 10 20 42 39 . 7 28 . 04 87 . 85 33 . 4 . 2<br />

1999 6 13 7 38 6 . 4 28 . 14 86 . 64 33 . 4 . 4<br />

1999 7 4 6 5 15 . 2 25 . 42 90 . 28 33 . 3 . 8<br />

1999 8 1 8 24 51 . 2 28 . 37 86 . 79 40 . 5 . 0<br />

1999 9 5 2 28 22 . 8 28 . 07 87 . 53 33 . 4 . 5<br />

1999 9 8 18 8 27 . 9 27 . 90 87 . 91 19 . 3 . 7<br />

1999 9 20 7 28 5 . 6 27 . 24 87 . 98 22 . 4 . 2<br />

1999 9 21 13 54 39 . 8 25 . 16 88 . 86 2 . 3 . 9<br />

1999 10 15 7 33 1 . 0 29 . 61 90 . 06 33 . 4 . 4<br />

1999 11 5 15 57 21 . 4 28 . 59 87 . 08 23 . 3 . 7<br />

1999 11 7 5 11 57 . 6 27 . 10 89 . 13 14 . 3 . 8<br />

1999 11 17 5 27 13 . 8 28 . 04 89 . 22 33 . 3 . 3<br />

2000 1 20 12 54 27 . 5 27 . 78 86 . 02 33 . 5 . 0<br />

2000 1 25 12 7 33 . 3 29 . 94 89 . 72 0 . 5 . 0<br />

2000 2 21 18 21 43 . 2 28 . 36 86 . 56 33 . 4 . 7<br />

2000 3 13 20 44 38 . 3 27 . 43 87 . 85 108 . 4 . 1<br />

2000 4 18 7 53 45 . 2 26 . 55 90 . 26 33 . 3 . 3<br />

2000 6 20 7 16 43 . 8 26 . 04 90 . 31 33 . 4 . 3<br />

2000 9 6 7 19 8 . 9 28 . 52 86 . 86 33 . 4 . 2<br />

11


2000 10 3 17 8 22 . 4 26 . 88 89 . 8 33 . 2 . 8<br />

2001 1 16 8 6 57 . 4 26 . 42 90 . 24 33 . . 0<br />

2001 2 9 10 20 55 . 7 27 . 24 89 . 67 13 . 3 . 9<br />

2001 2 27 1 46 7 . 0 26 . 48 90 . 55 20 . 4 . 7<br />

2001 2 27 16 21 25 . 6 28 . 38 86 . 97 33 . 4 . 9<br />

2001 4 3 23 8 38 . 0 27 . 74 86 . 13 33 . 4 . 6<br />

2001 4 3 23 26 4 . 4 27 . 82 86 . 18 18 . 3 . 5<br />

2001 4 8 18 35 49 . 3 28 . 16 88 . 57 20 . 3 . 9<br />

2001 4 20 18 35 2 . 7 26 . 13 90 . 67 33 . 4 . 6<br />

2001 4 28 10 37 59 . 1 28 . 55 87 . 14 33 . 5 . 0<br />

2001 4 29 10 39 9 . 1 28 . 70 87 . 14 33 . 4 . 5<br />

2001 5 3 16 2 59 . 6 27 . 63 90 . 47 33 . 3 . 8<br />

2001 5 21 21 55 7 . 8 28 . 54 86 . 72 33 . 3 . 8<br />

2001 6 12 10 47 46 . 6 28 . 46 86 . 57 20 . 3 . 9<br />

2001 7 3 19 16 18 . 4 26 . 15 89 . 20 6 . 3 . 6<br />

2001 7 6 23 4 3 . 4 27 . 65 88 . 64 10 . 2 . 7<br />

2001 8 6 6 23 32 . 7 27 . 47 87 . 47 9 . 4 . 3<br />

2001 9 4 22 8 3 . 7 25 . 37 90 . 96 15 . 3 . 7<br />

2001 9 27 22 40 11 . 1 26 . 99 87 . 76 2 . 4 . 1<br />

2001 12 2 22 41 14 . 8 27 . 18 88 . 33 15 . 4 . 8<br />

NO. OF EARTHQUAKES = 358<br />

12


PRELIMINARY RANKING STUDY REPORT- BY CEA<br />

<strong>Rangyong</strong> Hydro Electric Scheme (Org. No. HEPR-PS-BHM-764)<br />

Annexure 6.1<br />

The water <strong>of</strong> Talung Chhu rivers and also its tributaries the Umaram and Passaram can<br />

possibly be utilized for power generation by constructing (i) two diversion structures one<br />

on the main Talung Chhu immediately downstream <strong>of</strong> confluence <strong>of</strong> Umaram and<br />

Passaram tributaries and the other across the Rukel Chhu (ii) a small tunnel connecting<br />

two diversions (iii) a tunnel diverting the waters <strong>of</strong> Talung Chhu and droping the same to<br />

a power house & (iv) a power house on the main Talung Chhu at a site where the river<br />

bed level is <strong>of</strong> the order <strong>of</strong> +1085 m. Between the diversion level as + 1795 m. and the<br />

tailrace level as +1085 m. a gross head <strong>of</strong> 710 m. would be available enabling a firm<br />

power output <strong>of</strong> about 22 MW. The schemes would have an installed capacity <strong>of</strong> about<br />

175 MW. And would enable annual energy generation <strong>of</strong> 785 GWH and 853 GWH<br />

respectively in 90% and 50% dependable years.


TITLE<br />

ANNEXURES 6.2<br />

Preliminary Feasibility Report<br />

<strong>Rangyong</strong> HE Project (3 x 47 MW)<br />

No.<br />

Reply on CWC’s Comments on Hydrology 1-3<br />

Summary <strong>of</strong> Discussions on <strong>Power</strong> Potential<br />

studies<br />

4-5<br />

Reply on Comments <strong>of</strong> SP&PA Division CEA 6-7<br />

Reply on comments on CMDD(E&NE), CWC 8


REPLY ON CWC’s COMMENTS ON HYDROLOGY OF<br />

RANGYONG HE PROJECT<br />

1<br />

Annexure 6.2<br />

In reference to your letter no. NH/CON-229 dt. 5-1-2004. Point wise reply to the CWC observations for the<br />

project is placed as below:<br />

CWC Observations Reply <strong>of</strong> NHPC<br />

Data availability Rainfall - The report has quoted the paper<br />

<strong>of</strong> Sh. Biswas and Bhadram in which data<br />

<strong>of</strong> 42 raingauge stations, 24 <strong>of</strong> which is<br />

equipped with SRRG have been stated to<br />

be available. However rainfall data has<br />

not been furnished in the report and only<br />

the period <strong>of</strong> data availability <strong>of</strong> 11<br />

raingauge stations located u/s <strong>of</strong> the<br />

Teesta-V HEP is given in the report.<br />

Though the rainfall data <strong>of</strong> 11 raingauge<br />

stations are lying in the project catchment<br />

area under consideration, the project<br />

authorities may put their efforts to verify<br />

whether any <strong>of</strong> the rain gauges out <strong>of</strong> the<br />

remaining 31 raingauges as mentioned in<br />

the report lies in the catchment area under<br />

consideration and to explore the<br />

possibilities <strong>of</strong> utilization <strong>of</strong> this data in<br />

the study.<br />

Discharge – It is stated in the report that<br />

discharge data is available for the period<br />

Jan 75 to Aug 85 and April 90 to Apr 98<br />

on Tolung Chu, which is located d/s <strong>of</strong><br />

the proposed project site having a<br />

catchment area <strong>of</strong> 731 Sq.km. But the<br />

discharge data and the methodology<br />

adopted for collection have not been<br />

furnished.<br />

Consistency <strong>of</strong><br />

data<br />

The project authorities may verify<br />

whether any <strong>of</strong> the rain gauges out <strong>of</strong> the<br />

remaining 31 raingauges as mentioned in<br />

the report <strong>of</strong> C.V.V Bhadram are located<br />

in the sub-basin under consideration and<br />

to collect the rainfall data <strong>of</strong> these sites<br />

None <strong>of</strong> the raingauge stations out <strong>of</strong> the<br />

remaining 31 raingauges as mentioned in the<br />

report <strong>of</strong> C.V.V Bhadram are located in the<br />

sub-basin under consideration.<br />

Similarly, the discharge data at on Tolung Chu<br />

has been used only for comparison purpose and<br />

not adopted finally for water availability, hence<br />

the basic data not given in report. However, the<br />

discharge data at Tolung Chu has been taken<br />

from the report <strong>of</strong> Teesta H.E Project Stage-III<br />

& VI submitted by CWC itself.<br />

None <strong>of</strong> the raingauge stations out <strong>of</strong> the<br />

remaining 31 raingauges as mentioned in the<br />

report <strong>of</strong> C.V.V Bhadram are located in the<br />

sub-basin under consideration.


Water<br />

availability<br />

studies<br />

and to utilize the same. The data and the<br />

consistency check done on it may be<br />

furnished.<br />

c) Before discarding the G&D data <strong>of</strong><br />

Tolung Chu site the project authorities are<br />

advised to verify whether any <strong>of</strong> the<br />

remaining 31 rain gauges mentioned in<br />

the report <strong>of</strong> the Bhadram are located in<br />

the sub-basin and to collect the data <strong>of</strong><br />

these sites and to utilize the same after<br />

applying consistency check.<br />

(d) The approved series <strong>of</strong> Lachen G&D<br />

used for converting to the present project<br />

may also be appended.<br />

(e) The basis <strong>of</strong> deriving the catchment<br />

reduction factor is not given.<br />

(f) Integrated studies on water availability<br />

may be done incorporating the likely<br />

releases from the u/s power house and<br />

independent catchment contributions.<br />

Design Flood (a) The design flood studies done by<br />

NHPC are too empirical to be relied<br />

upon.<br />

(b) In the absence <strong>of</strong> short interval<br />

concurrent rainfall run<strong>of</strong>f data the design<br />

flood may be calculated using relevant<br />

sub zonal report <strong>of</strong> CWC taking into<br />

account the recommendations <strong>of</strong> 1993<br />

workshop and by collecting PMP/SPS<br />

values from IMD. The results may be<br />

compared before recommending the<br />

design flood.<br />

Sedimentation Sedimentation rate for the projects in the<br />

region given in the compendium on<br />

siltation published by CWC is higher than<br />

the value adopted by the project<br />

authorities. The rate given in the<br />

2<br />

(c) As stated earlier also, none <strong>of</strong> the remaining<br />

31 rain gauges mentioned in the report <strong>of</strong> the<br />

Bhadram are located in the sub-basin <strong>of</strong> the<br />

proposed project.<br />

(d) The available average 10-daily series at<br />

Lachen is enclosed as Annexure (I).<br />

(e) The catchment reduction factor has been<br />

obtained on the basis <strong>of</strong> rainfed area at both the<br />

sites. Rainfed catchment <strong>of</strong> Lachen site is 574<br />

Sq.km and <strong>of</strong> <strong>Rangyong</strong> is 92 and 102 Sq.km<br />

for the two diversion structures.<br />

(f) Cascade development need to be done at a<br />

later stage.<br />

As already explained in our earlier reply also,<br />

for such detailed studies as suggested for this<br />

stage i.e PFR, neither the database is at all<br />

sufficient nor necessacity felt by us. During<br />

feasibility stage, deterministic/probabilistic<br />

approach will be used, based on more observed<br />

data.<br />

As per report <strong>of</strong> “Compendium on silting <strong>of</strong><br />

reservoirs in India”, the sediment rate varies<br />

from 0.05658 to 0.2785 Ham/Sq.km/year for<br />

Indus, Ganga and Brahmaputra basin. But the


compendium on siltation will be the most<br />

likely value after construction <strong>of</strong> projects<br />

and the same may be incorporated in the<br />

proposal stage. As stated in the report<br />

detailed study may be done.<br />

As per the terms <strong>of</strong> preparation <strong>of</strong> PFRs<br />

and as emphasized in the meetings<br />

conducted by CEA sedimentation studies<br />

are required to be carried out and<br />

incorporated in the PFRs. However such<br />

studies have not been given to HSO/CWC<br />

for vetting.<br />

General The PFR must bring out the limitations <strong>of</strong><br />

the hydrological studies carried out for<br />

the PFR and suggest improvements,<br />

specific recommendations for opening<br />

new hydrological stations, method <strong>of</strong><br />

observations, data to be collected etc.<br />

may be given which will help us as<br />

guidance to the agency taking up the<br />

detail investigations/DPR must review the<br />

network in consultation with HSO,<br />

CWC.The hydrological studies for the<br />

PFR may be revised incorporating the<br />

above observations and resubmitted.<br />

3<br />

silt rate adopted for this particular project has<br />

been calculated on the basis <strong>of</strong> observed<br />

sediment data at Dikchu and is more region<br />

specific than that given in the report. Also silt<br />

rate is usually calculated based on the observed<br />

sediment data at or near the proposed site. The<br />

necessity <strong>of</strong> detailed sedimentation study<br />

showing the new zero elevation, revised area<br />

capacity curve etc. is not felt during PFR stage.<br />

The PFR has pointed out the limitation <strong>of</strong> the<br />

studies after each study and establishment <strong>of</strong><br />

G&D site, rainfall stations etc. are also<br />

highlighted in the PFR.<br />

Moreover, all the CWC comments along with<br />

their replies are also being appended in the<br />

PFR’s for future reference.


SUMMARY RECORD OF DISCUSSIONS OF MEETING TAKEN BY<br />

DIRECTOR (HP&I), CEA WITH NHPC ON 24.12.2003 REGARDING<br />

POWER POTENTIAL STUDIES OF PFRS OF RINGPI & RANGYONG HE<br />

PROJECTS IN SIKKIM.<br />

(Letter no 7/9/2003/HP&I/1581-1582 dated 24.12.2003)<br />

<strong>Power</strong> potential studies <strong>of</strong> Ringpi & <strong>Rangyong</strong> H.E. Projects in Sikkim were<br />

discussed in detail and summarized as under :<br />

1 Ringpi HE Project :<br />

i. Only power potential studies without any write up was presented by NHPC<br />

<strong>of</strong>ficers and the same was discussed.<br />

ii. Hydrology may be got cleared by CWC.<br />

iii. NHPC have furnished studies considering FRL at +2940 m. and tail water<br />

level <strong>of</strong> +1853 m. (+3 m. above the FRL <strong>of</strong> proposed Lingza HE<br />

Project). NHPC Officers indicated that sufficient pondage is available<br />

for peaking operation. NHPC was advised to furnish basis <strong>of</strong> FRL,<br />

MDDL and tail water level in the concerned chapter <strong>of</strong> PFR.<br />

iv. Based on the studies presented by NHPC an installed capacity <strong>of</strong> 70 MW<br />

was considered to be in order subject to approval <strong>of</strong> hydrology by CWC.<br />

It was suggested that two units <strong>of</strong> 35 MW each could be installed in case<br />

there is no problem <strong>of</strong> transportation.<br />

v. NHPC may prepare summary <strong>of</strong> the studies indicating yearly inflow, annual<br />

energy generation, load factor <strong>of</strong> operation during monsoon and lean flow<br />

period.<br />

vi. NHPC may indicate recommendation for further studies at the time <strong>of</strong><br />

FR/DPR.<br />

2. <strong>Rangyong</strong> HE Project :<br />

i. Only power potential studies without any write up was presented by NHPC<br />

<strong>of</strong>ficers and the same was discussed.<br />

ii. Hydrology may be got cleared by CWC.<br />

4


iii. NHPC was advised to keep the tail water level <strong>of</strong> the project about 3 m.<br />

above FRL <strong>of</strong> the downstream project. NHPC Officers indicated that<br />

sufficient pondage is available for peaking operation. NHPC was advised<br />

to furnish basis <strong>of</strong> FRL, MDDL and tail water level in the concerned<br />

chapter <strong>of</strong> PFR.<br />

iv. NHPC has proposed an installation <strong>of</strong> 150 MW. The power potential studies<br />

presented by NHPC are generally in order subject to compliance <strong>of</strong> the above<br />

comment and approval <strong>of</strong> hydrology by CWC.<br />

v. NHPC may prepare summary <strong>of</strong> the studies indicating yearly inflow, annual<br />

energy generation, load factor <strong>of</strong> operation during monsoon and lean flow<br />

period.<br />

vi. NHPC may indicate recommendation for further studies at the time <strong>of</strong><br />

FR/DPR.<br />

5


REPLY ON COMMENTS OF SP&PA DIVISION ON DRAFT PFR OF<br />

RANGYONG HE PROJECT<br />

(CEA Letter No.7/9/(NHPC)/2003/HP&I/111 dated 20.01.2004 )<br />

Sr.No. Comments Reply<br />

7.1<br />

General<br />

<strong>Rangyong</strong> HEP is a run <strong>of</strong> the river<br />

scheme and situated in the Dzongu<br />

area <strong>of</strong> North district <strong>of</strong> Sikkim. The<br />

project envisages construction <strong>of</strong> 65m<br />

high two concrete gravity dam. The<br />

underground power house is just<br />

It is general description <strong>of</strong> the<br />

project and no reply is required.<br />

upstream <strong>of</strong> the confluence <strong>of</strong><br />

<strong>Rangyong</strong> chu and <strong>Rangyong</strong> chu.<br />

7.2<br />

7.3<br />

Construction <strong>Power</strong><br />

The construction power will get from<br />

existing 2X2.5 MVA 66/11 KV<br />

Phadong near Mangan.<br />

Switchyard<br />

No details <strong>of</strong> switchyard are given.<br />

7.4 <strong>Power</strong> Evacuation:<br />

<strong>Power</strong> will be generated at 11KV and<br />

stepped up to 220KV through 10no<br />

20MVA 11/220KV single phase unit<br />

transformer. Evacuation <strong>of</strong> power<br />

generated at <strong>Rangyong</strong> HEP can be<br />

done through 1 no 220KV double<br />

circuit 30km line to be connected at<br />

the pooling point which can be<br />

assumed to come up near Teesta-II<br />

6<br />

This is already discussed in Chapter<br />

–X <strong>of</strong> the PFR<br />

6 nos. <strong>of</strong> bays have been taken at<br />

switchyard which have been<br />

indicated in the cost estimate based<br />

on the tentative scheme envisaged at<br />

this stage. However, 8 nos <strong>of</strong> bays<br />

have been envisaged in dimension <strong>of</strong><br />

170 X 100m switchyard taking into<br />

account 132/220KV bay for power<br />

coming from Rukel HEP and a<br />

future bay. Further details <strong>of</strong><br />

switchyard are normally worked out<br />

during FR/DPR stage.<br />

No reply is required.


HEP, which is in order.<br />

7.5 Cost:<br />

According to PFR 6 no <strong>of</strong> 220KV line<br />

bays has been taken:<br />

Generator bays -3<br />

220KV line bays – 2<br />

Bus Coupler bays – 1<br />

Which is in order.<br />

7<br />

No reply is required.


REPLY ON COMMENTS OF CMDD DIRECTORATE, CWC ON PFR OF<br />

RANGYONG HE PROJECT<br />

(Letter No CWC P.U. No. 20/2/03-CMDD(E&NE)/136 dated 26.2.2004)<br />

Comments <strong>of</strong> CEA/CWC Replies <strong>of</strong> Design Division<br />

1. It should be mentioned in the report<br />

that the PMF value has been vetted by<br />

hydrology (NE)<br />

Dte. CWC.<br />

8<br />

Hydrology adopted is as per<br />

decisions taken in the progress<br />

review meeting with CEA.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!