Nalo - Ministry of Power
Nalo - Ministry of Power Nalo - Ministry of Power
50 000 MW HYDROELECTRIC INITIATIVE Government of India Ministry of Power Central Electricity Authority 360MW NALO H.E. PROJECT ARUNACHAL PRADESH Preliminary Feasibility Report April 2004 Consultant : uS'kuy gkbMªksbySfDVªd ikoj dkjiksjs'ku fyfeVsM National Hydroelectric Power Corporation Ltd. (A Government of India Enterprise)
- Page 3 and 4: PRELIMINARY FEASIBILITY REPORT NALO
- Page 5 and 6: CHAPTER PLATE LIST OF PLATES (iii)
- Page 7 and 8: (v) Preliminary Feasibility Report
- Page 9 and 10: Preliminary Feasibility Report Nalo
- Page 11 and 12: RESERVOIR Full reservoir level (FRL
- Page 13 and 14: PRESSURE SHAFT Number : 2 Size : 6.
- Page 15 and 16: Preliminary Feasibility Report Nalo
- Page 17 and 18: Preliminary Feasibility Report Nalo
- Page 19 and 20: 2.0 GENERAL CHAPTER-II BACKGROUND I
- Page 21 and 22: Preliminary Feasibility Report Nalo
- Page 23 and 24: Preliminary Feasibility Report Nalo
- Page 25 and 26: Table 2.2 Preliminary Feasibility R
- Page 27 and 28: 3.2 LOCATION AND ACCESSIBILITY Prel
- Page 29 and 30: Table 3.1 Preliminary Feasibility R
- Page 31 and 32: CHAPTER-IV Preliminary Feasibility
- Page 33 and 34: Maza Granites Preliminary Feasibili
- Page 35 and 36: 4.3.2 Water Conductor System Prelim
- Page 37 and 38: - Rock mass classification for unde
- Page 39 and 40: Preliminary Feasibility Report Nalo
- Page 41 and 42: Preliminary Feasibility Report Nalo
- Page 43 and 44: 5.1.3 Precipitation Characteristics
- Page 45 and 46: TABLE-5.1 DATA AVAILABILITY STATUS
- Page 47 and 48: 5.2 WATER AVAILABILITY STUDY 5.2.1
- Page 49 and 50: Preliminary Feasibility Report Nalo
- Page 51 and 52: (iii) Empirical Methods Preliminary
50 000 MW HYDROELECTRIC INITIATIVE<br />
Government <strong>of</strong> India<br />
<strong>Ministry</strong> <strong>of</strong> <strong>Power</strong><br />
Central Electricity Authority<br />
360MW NALO H.E. PROJECT<br />
ARUNACHAL PRADESH<br />
Preliminary Feasibility Report<br />
April 2004<br />
Consultant :<br />
uS'kuy gkbMªksbySfDVªd ikoj dkjiksjs'ku fyfeVsM<br />
National Hydroelectric <strong>Power</strong> Corporation Ltd.<br />
(A Government <strong>of</strong> India Enterprise)
PRELIMINARY FEASIBILITY REPORT<br />
NALO H. E. PROJECT<br />
(4 x 90 MW)<br />
TABLE OF CONTENTS<br />
(i)<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
CHAPTER TITLE PAGE<br />
I EXECUTIVE SUMMARY 1-11<br />
II BACKGROUND INFORMATION 12-18<br />
III PROJECT AREA 19-23<br />
IV TOPOGRAPHIC & GEO- TECHNICAL<br />
ASPECTS<br />
24-30<br />
V HYDROLOGY 31-49<br />
VI CONCEPTUAL LAYOUT & PLANNING 50-63<br />
VII POWER POTENTIAL STUDIES 64-92<br />
VIII POWER EVACUATION 93-94<br />
IX ENVIRONMENTAL ASPECTS 95-109<br />
X INFRASTRUCTURE 110-113<br />
XI CONSTRUCTION PLANNING &<br />
SCHEDULE<br />
114-119<br />
XII COST ESTIMATES 120-149<br />
XIII ECONOMIC EVALUATION 150-157<br />
PLATES 158-173<br />
ANNEXURES 174-253
LIST OF TABLES<br />
(ii)<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
CHAPTER TABLE TITLE PAGE<br />
II 2.1 <strong>Power</strong> Supply Position <strong>of</strong> North Eastern Region 17<br />
2.2 <strong>Power</strong> Supply Position <strong>of</strong> All India 18<br />
III 3.1 Circle wise number <strong>of</strong> villages, household and<br />
population in Upper Subansiri District as per<br />
1991 Census<br />
IV 4.1 Generalised Geological Succession 25<br />
V 5.1 Data Availability status 38<br />
5.2 Average Monthly Rainfall Near <strong>Nalo</strong> Sub-Basin 39<br />
5.3 Flood Computed by various methods 46<br />
VII 7.1 10- daily Discharge Data (cumecs) 69<br />
7.2 90% Dependable Year Flows for <strong>Power</strong><br />
Generation<br />
70<br />
7.3 Summary Sheet 71<br />
7.3A Availability <strong>of</strong> Units in KWH/KW for<br />
Incremental Installation in 90% Dependable<br />
Year<br />
72<br />
7.4 <strong>Power</strong> Potential in 90% Dependable Year with<br />
95% m/c availability<br />
73<br />
7.5 <strong>Power</strong> Potential in 90% Dependable Year 74<br />
IX 9.1 Landuse-landcover Information within the<br />
Submergence Area<br />
99<br />
9.2 Landuse-landcover Information within the 7 km<br />
Radius from the Dam site at <strong>Nalo</strong><br />
100<br />
X 10.1 Status <strong>of</strong> Road Network Connecting Project site 111<br />
XI 11.1 Construction Schedule <strong>of</strong> <strong>Nalo</strong> HE Project 119<br />
XIII 13.1 IDC Calculation at Present Day Cost 153<br />
13.2 Unit Cost <strong>of</strong> Energy at Bus Bar at Current Price<br />
Level with 12 % Free <strong>Power</strong> to Home State<br />
154<br />
13.2 A Unit Cost <strong>of</strong> Energy at Bus Bar at Current Price<br />
Level without Free <strong>Power</strong> to Home State<br />
155<br />
13.3 Calculation <strong>of</strong> Energy Rate with Present Day<br />
Cost with 12 % Free <strong>Power</strong> to Home State<br />
156<br />
13.3 A Calculation <strong>of</strong> Energy Rate with Present Day<br />
Cost without Free <strong>Power</strong> to Home State<br />
157<br />
22
CHAPTER PLATE<br />
LIST OF PLATES<br />
(iii)<br />
TITLE<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
PAGE<br />
II 2.1 Proposed Cascade Development over River<br />
Subansiri<br />
158<br />
2.2 Vicinity Map 159<br />
IV 4.1 Geological Plan 160<br />
4.2 Geological X- section near Dam site 161<br />
V 5.1 Catchment Plan <strong>of</strong> Subansiri Basin 162<br />
5.2 Catchment Plan <strong>of</strong> <strong>Nalo</strong> HE Project 163<br />
VI 6.1 General Layout Plan 164<br />
6.2 General Layout - Longitudinal Section 165<br />
6.3 Layout Plan- Dam area 166<br />
6.4 Dam- Upstream Elevation 167<br />
6.5 Dam- Cross Sections 168<br />
6.6 Water Conductor System- Cross Sections 169<br />
6.7 Layout Plan- <strong>Power</strong> House Area 170<br />
6.8 <strong>Power</strong> House- Cross Section 171<br />
VIII 8.1 Single Line Diagram – <strong>Power</strong> Evacuation 172<br />
8.2 Subansiri Basin- <strong>Power</strong> Evacuation System 173
CHAPTER FIGURE<br />
LIST OF FIGURES<br />
(iv)<br />
TITLE<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
PAGE<br />
V 5.1 Reservoir Elevation-Area-Capacity Curve 49<br />
LIST OF ANNEXURES<br />
CHAPTER ANNEXURE TITLE PAGE<br />
I 1.1 Salient Features<br />
II 2.1 CEA’s letter regarding Preparation <strong>of</strong> PFR-<br />
Replacement Schemes (dated 29.01.2004)<br />
2.2 Record note <strong>of</strong> Discussion with CEA regarding<br />
vetting <strong>of</strong> Layout (dated 24.02.2004)<br />
2.3 Comments <strong>of</strong> HP&I Division, CEA vide<br />
letter No. 7/9/NHPC/HP&I/2004/695 dated<br />
05.04.2004 and Reply <strong>of</strong> NHPC.<br />
IV 4.1 Preliminary Appraisal for PFR by Geological<br />
Survey <strong>of</strong> India, New Delhi<br />
V 5.1A Monthly Rainfall (mm) at Taliha 195<br />
5.1B Monthly Rainfall (mm) at Siyum 196<br />
5.1C<br />
Monthly Rainfall (mm) at Limeking<br />
197<br />
5.1D<br />
Monthly Rainfall (mm) at Nacho<br />
5.2 Synthetic 10-Daily Flow Series at Menga<br />
(NHPC)<br />
5.3 Synthetic Average 10-Daily Discharge Series<br />
at Dam Site<br />
5.4 Observation <strong>of</strong> CWC Received vide letter No.<br />
7/9/NHPC/2004/HP&I/1014 dated<br />
13.05.2004 and Reply <strong>of</strong> NHPC.<br />
174<br />
177<br />
179<br />
181<br />
186<br />
198<br />
199<br />
201<br />
203
(v)<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
CHAPTER ANNEXURE TITLE PAGE<br />
VI 6.1 Observation <strong>of</strong> CMDD Division, CEA vide<br />
letter No. 7/9/NHPC/2003/HP&I/872 dated<br />
21.04.2004 and Reply <strong>of</strong> NHPC.<br />
6.2 Comments <strong>of</strong> HCD (E&NE) Division, CEA<br />
vide letter No. 3/5/2000-HCD (E&NE)/875<br />
dated 08/04/2004 and Reply <strong>of</strong> NHPC.<br />
VII 7.1 Record note <strong>of</strong> Discussion with CEA<br />
Regarding Vetting <strong>of</strong> <strong>Power</strong> Potential dated<br />
16.03.2004.<br />
7.2 Comments <strong>of</strong> SP&PA Division, CEA vide<br />
letter No.-7/9/NHPC/2004/HP&I/892 dated<br />
22.04.2004 and Reply <strong>of</strong> NHPC.<br />
7.3 Comments <strong>of</strong> SP & PA Division on Cost<br />
Aspects, CEA vide letter No. 7/1/2004/<br />
SP&PA(C)/239 dated 13.05.2004 and Reply<br />
<strong>of</strong> NHPC.<br />
IX 9.1 Report from NRSA, Hyderabad on Satellite<br />
Remote Sensing Based Inputs for Initial<br />
Environmental Studies for <strong>Nalo</strong> Project Site<br />
9.2 Excerpts from Preliminary Floristic Report <strong>of</strong><br />
Botanical Survey <strong>of</strong> India, Itanagar<br />
9.3 Brief Report on Faunal Diversity <strong>of</strong><br />
Zoological Survey <strong>of</strong> India, Itanagar<br />
9.4 Report <strong>of</strong> Fishery Department, Govt. <strong>of</strong><br />
Arunachal Pradesh.<br />
210<br />
215<br />
218<br />
220<br />
229<br />
233<br />
249<br />
250<br />
253
1.0 INTRODUCTION<br />
CHAPTER – I<br />
EXECUTIVE SUMMARY<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
<strong>Nalo</strong> H.E. Project is located in a remote area up-stream <strong>of</strong> Ledi Ishi Nallah<br />
in Upper Subansiri District <strong>of</strong> Arunachal Pradesh. This project envisages<br />
utilisation <strong>of</strong> water <strong>of</strong> river Subansiri (called Si Ngit in upper reaches).<br />
Subansiri is a tributary <strong>of</strong> river Brahmaputra. Three scheme viz.,<br />
Subansiri lower (2000 MW), Subansiri Middle (1600MW) and Subansiri<br />
Upper (2000MW) have been planned to harness power potential <strong>of</strong> river<br />
Subansiri. CEA has identified eight additional projects totalling about 4900<br />
MW in Subansiri Basin (Arunachal Pradesh) in their ranking studies, as a<br />
part <strong>of</strong> exercise for development <strong>of</strong> balance hydroelectric potential in the<br />
country and accorded priority for preparation <strong>of</strong> Preliminary Feasibility<br />
Report (PFR) so that these could be taken up for preparation <strong>of</strong> Detailed<br />
Project Report (DPR) and further development during the XI and XII Five<br />
Year Plans.<br />
While preparing PFRs <strong>of</strong> Naba, Niare, Oju-II and Oju-I projects it was<br />
noticed that about 300 m head between Naba and Subansiri Upper<br />
Project is unutilised. In CEA’s Ranking study and Reassessment study<br />
report there is no proposal to develop this head. Accordingly, it was<br />
considered prudent to explore possibilities <strong>of</strong> exploring potential <strong>of</strong> the<br />
river in this stretch between Naba and Ebiya villages. In this reach the<br />
river travels about 31 km descending from EL 770 m to EL 470 m<br />
providing a gross head <strong>of</strong> 300 m.<br />
As gradient <strong>of</strong> river in this stretch is gentle, developing this head through<br />
one scheme, would have involved construction <strong>of</strong> about a 25 km long HRT<br />
1
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
as water conductor system. Hence, it was considered prudent to go for<br />
two schemes in cascade. As a result, concept <strong>of</strong> <strong>Nalo</strong> and Dengser<br />
projects emerged. Various alternative layouts were developed on<br />
toposheets and proposed sites were inspected by NHPC <strong>of</strong>ficers. Based<br />
on the data/ information collected during site visits and study <strong>of</strong><br />
topographical and geological inputs as collected, the parameters <strong>of</strong> <strong>Nalo</strong><br />
Project are proposed taking into account Naba HE Project on upstream<br />
and Dengser HE Project on downstream. A few alternatives <strong>of</strong> scheme<br />
were studied, discussed with CEA and it is proposed to have the dam site<br />
where River Bed Level is 660 m, tail race outfall at EL 635 m and 2.5/2.6<br />
km long head race tunnel as water conductor system. Installed capacity <strong>of</strong><br />
this project would be 360 MW ( 4x 90 MW).<br />
1.1 GENERAL PROJECT FEATURES<br />
The <strong>Nalo</strong> HE Project envisages construction <strong>of</strong><br />
River diversion works comprising <strong>of</strong> 2 nos <strong>of</strong> 10.75 m diameter<br />
horseshoe shaped diversion tunnels with u/s and d/s c<strong>of</strong>ferdams.<br />
A 125 m high concrete gravity dam from deepest foundation level to<br />
provide a gross storage <strong>of</strong> 163.37 mcm at FRL <strong>of</strong> EL 765 m and a<br />
storage <strong>of</strong> 113 mcm at MDDL <strong>of</strong> EL 745 m .<br />
Spillway comprising <strong>of</strong> (a) low level orifice spillway - 5 nos <strong>of</strong> opening<br />
size 9.75 m X 11.5 m with crest elevation at EL 715 m and (b) upper<br />
level crest type spillway - 2 nos <strong>of</strong> opening size 9.75 m X 11.5 m with<br />
crest elevation at EL 753.5 m.<br />
4 nos <strong>of</strong> Desilting chambers <strong>of</strong> size 300m (L) x 17m (W) x 25 m (H) to<br />
remove silt particle <strong>of</strong> size 0.2 mm and above.<br />
2 nos 2.5 / 2.6 km long 7.5 m diameter horseshoe shaped headrace<br />
tunnels.<br />
2
2 nos 90 m high 20 m diameter surge shaft.<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
2 nos 6.25 m diameter steel lined pressure shafts (vertical height 82m).<br />
A surface power house with 4 units <strong>of</strong> 90 MW each<br />
A tail race channel having bed width <strong>of</strong> 60 m.<br />
The power generated from the project will be evacuated at 400 KV level<br />
and will be pooled at Daporijo through one double circuit transmission line.<br />
Daporijo pooling point will be ultimately linked through HVDC line to the<br />
National Grid.<br />
The salient features <strong>of</strong> the project are as under :<br />
SALIENT FEATURES<br />
LOCATION<br />
State : Arunachal Pradesh<br />
District : Upper Subansiri<br />
River : Subansiri/Si Ngit<br />
Dam site : 1.6 km u/s <strong>of</strong> Ledi Ishi Nallah<br />
Nearest BG rail head : Nagaon<br />
Nearest airport : Lilabari (North Lakhimpur)<br />
HYDROLOGY<br />
Catchment area<br />
Location <strong>of</strong> catchment<br />
: 14500 sq.km.<br />
Latitude : 27 o 50’ N to 29 o 00’ N<br />
Longitude : 91 o 45' E to 93 o 49' E<br />
Average annual rainfall : 2810 mm<br />
3
RESERVOIR<br />
Full reservoir level (FRL) : EL 765 m<br />
Min. Draw Down Level (MDDL)<br />
Gross storage<br />
: EL 745 m<br />
-at FRL : 163.37 mcm<br />
-at MDDL : 113 mcm<br />
Area under submergence at FRL : 283.8 ha<br />
DIVERSION TUNNEL<br />
Number : 2<br />
Size : 10.75 m<br />
Shape : Horse shoe<br />
Length : 650/800 m<br />
Diversion capacity (assumed) : 2600 cumec<br />
U/s c<strong>of</strong>fer dam : 28 m<br />
D/s c<strong>of</strong>fer dam : 14 m<br />
DAM<br />
Type : Concrete<br />
Top elevation <strong>of</strong> dam : EL 770 m<br />
Height <strong>of</strong> dam above deepest<br />
foundation level<br />
: 125 m<br />
Length <strong>of</strong> dam at top : 366 m<br />
River Bed level : EL 660 m<br />
SPILLWAY<br />
Design flood : 12300 cumec<br />
Lower spillway<br />
Crest elevation : EL 715 m<br />
Type : Orifice<br />
Number : 5<br />
Size <strong>of</strong> opening<br />
: 9.75 m x11.5 m<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
4
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Upper spillway<br />
Crest elevation : EL 753.5 m<br />
Type : Crest<br />
Number : 2<br />
Size <strong>of</strong> opening : 9.75 m x 11.5 m<br />
Energy dissipation : Ski jump with preformed plunge<br />
pool<br />
Length <strong>of</strong> spillway : 120 m<br />
INTAKE<br />
Invert level : EL 725 m<br />
Number : 2<br />
Size <strong>of</strong> gate opening : 7.5 m x 8.5 m<br />
Trash rack : 18 m x 20 m<br />
Intake tunnel : 8.5 m<br />
Intake tunnel length : 250/350 m<br />
DESILTING CHAMBERS<br />
Number : 4<br />
Size : 17 m x 25 m<br />
Length : 300 m<br />
Design discharge per chamber : 111.8 cum<br />
Particle size to be removed : 0.2 mm and above<br />
HEAD RACE TUNNEL<br />
Number : 2<br />
Size : 7.5 m<br />
Shape : Horse shoe<br />
Length : 2.5 /2.6 km<br />
Design discharge per tunnel : 186.4 cumec<br />
SURGE SHAFT<br />
Number : 2<br />
Size : 20 m<br />
Height : 90 m<br />
5
PRESSURE SHAFT<br />
Number : 2<br />
Size : 6.25 m<br />
Vertical height : 82 m<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
POWER HOUSE<br />
Type : Surface<br />
Installed capacity : 360 MW<br />
Number <strong>of</strong> units : 4 ( 90 MW each )<br />
<strong>Power</strong> house size<br />
(machine hall + service bay)<br />
: 103 (L)x 22 (W) x 47 (H)<br />
Type <strong>of</strong> turbine : Vertical Shaft Francis<br />
C.L <strong>of</strong> turbine : EL 633 m<br />
Draft tube opening for each unit : 2 nos , 5 m (W) X 4.3 m (H)<br />
Net Operating Head : 221 m<br />
TAIL RACE CHANNEL<br />
Bed Width : 60 m<br />
Side Slope : 1V:1.5H<br />
Length : 50 m<br />
Design discharge : 372.8 cumec<br />
River Bed level : EL 635 m<br />
Maximum TWL : EL 645 m<br />
SWITCH YARD<br />
Size : 80m (W) X160m(L)<br />
POWER GENERATED<br />
Installed capacity<br />
Annual energy generation<br />
: 360 MW<br />
in 90% dependable year : 1732.99 MU<br />
6
1.2 STUDIES/INVESTIGATIONS UNDERTAKEN<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Study <strong>of</strong> topographic maps and remote sensing imageries.<br />
Reconnaissance <strong>of</strong> area for identifying probable alternative<br />
sites <strong>of</strong> project components.<br />
Study <strong>of</strong> regional geotechnical features/ seismotectonic<br />
aspects.<br />
Geological appraisal <strong>of</strong> proposed project components.<br />
Water availability/ design flood studies based on available<br />
meteorological / hydrological data.<br />
Conceptual layout and project planning.<br />
<strong>Power</strong> potential studies.<br />
Study <strong>of</strong> biotic environment, socio-economic environment for<br />
prediction <strong>of</strong> environmental impacts <strong>of</strong> the project.<br />
Study <strong>of</strong> existing infrastructure.<br />
Cost benefit and Economic evaluation.<br />
Geophysical investigations are not expected to provide reliable<br />
results because <strong>of</strong> steep topography. Accordingly,<br />
geophysical methods are not attempted.<br />
1.3 RESULTS OF STUDIES AND INVESTIGATIONS<br />
1.3.1 Geology<br />
The entire project is located in broadly two rock types i.e. Biotite gneiss<br />
and Biotite Schist. The dam site has been chosen in a relatively straight<br />
stretch <strong>of</strong> the river where rock is exposed on left bank as steep rocky<br />
7
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
escarpment but right bank is covered under overburden and vegetation.<br />
From regional geological assessment it is expected that dam, diversion<br />
tunnel & desilting chambers will be housed in biotite gneiss <strong>of</strong> Gelensiniak<br />
formation whereas powerhouse complex and most <strong>of</strong> the part <strong>of</strong> HRT will<br />
be housed in Biotite Schist <strong>of</strong> Nacho formation.<br />
1.3.2 Hydrology<br />
The river Subansiri/ Si Ngit drains a catchment area <strong>of</strong> about 14500 sq.<br />
km at the proposed damsite. The water availability for the project has<br />
been considered on the basis <strong>of</strong> 10-daily discharge series for 20 year<br />
synthetic flow series at Subansiri Upper dam site, located d/s <strong>of</strong> this<br />
project on the Subansiri river itself, on the basis <strong>of</strong> catchment proportion.<br />
The computed inflow series worked out has been utilised for <strong>Power</strong><br />
Potential studies. The design flood is assessed as 12300 cumec at dam<br />
site.<br />
1.3.3 Infrastructure<br />
In order to complete the project in 6 years, broad Infrastructure<br />
requirements such as road network (including upgradation <strong>of</strong> roads)<br />
project <strong>of</strong>fice, residential colonies, arrangement for construction power,<br />
explosive magazine, telecommunication etc. have been identified and<br />
provision has been made in the cost estimate <strong>of</strong> the project.<br />
The project area is located in a remote corner <strong>of</strong> Arunachal Pradesh. It is<br />
connected by a 410 km long single lane road from Pahumara in Assam<br />
(take-<strong>of</strong>f point from NH-52) to <strong>Nalo</strong> Project. Provision for<br />
widening/strengthening <strong>of</strong> road sections /bridges has been kept in<br />
estimates <strong>of</strong> hydroelectric projects viz., Subansiri Middle, Subansiri Upper,<br />
and Dengser located downstream <strong>of</strong> this project. Cost <strong>of</strong> upgradation <strong>of</strong><br />
road for Dengser-<strong>Nalo</strong> segment has been kept in estimate <strong>of</strong> <strong>Nalo</strong> Project<br />
8
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
to avoid duplication. Therefore, in case, <strong>Nalo</strong> H.E. Project is to be taken<br />
up before construction <strong>of</strong> downstream projects, provision for R-<br />
Communication in the estimate shall need to be revised, resulting in<br />
higher tariff.<br />
1.3.4 <strong>Power</strong> Potential Studies<br />
The computed inflow series for 19 years has been considered in the<br />
assessment <strong>of</strong> power benefits from the project.<br />
The design energy for tariff at 95 % availability in a 90% dependable year<br />
has been worked out 1732.99 MU.<br />
A live storage <strong>of</strong> 50.37 mcm has been provided in the dam which would<br />
enable the station to operate as peaking station. The live storage is<br />
equivalent to 13511.70 MWh, which is sufficient to operate the station for<br />
37.53 hour.<br />
1.3.5 <strong>Power</strong> Evacuation Aspects<br />
The power generated from the project would be evacuated at 400 KV level<br />
through one number double circuit transmission line with Twin moose<br />
conductor to pooling station proposed at Daporijo which in turn will be<br />
connected to National Grid.<br />
1.3.6 Environmental Aspects<br />
The project is located in a remote area in the Subansiri Basin. To<br />
appreciate landuse-landcover around the proposed project area, Initial<br />
Environmental Studies have been carried out through National Remote<br />
Sensing Agency (NRSA). The total land requirement for the construction<br />
<strong>of</strong> various components is 740 ha. Out <strong>of</strong> which 285 ha. is private land<br />
and remaining is forest land. Based on assessment <strong>of</strong> environmental<br />
impacts, management plans have to be formulated for catchment area<br />
treatment, Compensatory afforestation and other environmental issues.<br />
9
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
These issues would be addressed during the investigation <strong>of</strong> DPR. No<br />
major township will be submerged or affected due to construction <strong>of</strong><br />
project.<br />
It is also stated that <strong>Ministry</strong> <strong>of</strong> Environment and Forest (MOEF) has<br />
imposed a condition that “There would be no construction <strong>of</strong> dam<br />
upstream <strong>of</strong> Subansiri river in future” while according clearance for<br />
construction <strong>of</strong> Subansiri Lower HE Project. As this project is located<br />
upstream <strong>of</strong> Subansiri Lower Project on Subansiri River, this condition is<br />
required to be considered while taking up the project for preparation <strong>of</strong><br />
DPR.<br />
1.3.7 Estimate <strong>of</strong> Cost<br />
The project is estimated to cost Rs. 2609.66 crores excluding IDC at June,<br />
2003 price level. The preliminary cost estimate <strong>of</strong> the project has been<br />
prepared as per guidelines <strong>of</strong> CEA/CWC. The break up <strong>of</strong> the cost<br />
estimate is given below:<br />
Civil Works : Rs. 2212.47 Crores<br />
Electro Mechanical Works : Rs. 334.89 Crores<br />
Transmission Works : Rs. 62.31 Crores<br />
Interest During Construction : Rs. 312.48 Crores<br />
Grand Total : Rs.2922.14 Crores<br />
1.3.8 Financial Aspects<br />
The <strong>Nalo</strong> HE Project, with an estimated cost <strong>of</strong> Rs.2922.14 Crores<br />
(including IDC <strong>of</strong> Rs.312.48 Cr) and design energy <strong>of</strong> 1732.99 MU in a<br />
90% dependable year is proposed to be completed in 6 years. The tariff<br />
has been worked out considering a debt-equity ratio <strong>of</strong> 70:30; 16% return<br />
on equity, annual interest rate on loan at 10% and twelve percent free<br />
power to home state. The tariff for first year and levellised tariff (with free<br />
10
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
power to home state) is Rs.3.71 per unit and Rs.3.01 per unit respectively.<br />
However, levellised tariff at present day cost without free power to home<br />
state works out to be Rs.2.65 per unit.<br />
1.3.9 Construction Schedule<br />
The main infrastructure development is proposed to be initiated<br />
simultaneously with preparation <strong>of</strong> DPR for which a provision <strong>of</strong> 18 months<br />
will be kept in programme <strong>of</strong> stage-II activity and completed in initial 12<br />
months after taking up construction (Stage-III activity) <strong>of</strong> the project. Main<br />
construction activity is planned to be completed in 6 years.<br />
1.4 CONCLUSION<br />
<strong>Nalo</strong> HE Project works can be completed in 6 years. The project would<br />
afford a design energy <strong>of</strong> 1732.99 MU in a 90% dependable year. The<br />
tariff for first year and levellised tariff have been worked out as Rs.3.71 per<br />
unit and Rs.3.01 per unit respectively (with provision <strong>of</strong> 12% free power to<br />
home state).<br />
The Preliminary Feasibility Report indicates that the scheme merits<br />
consideration for taking up for survey and Investigation and preparation <strong>of</strong><br />
DPR. Nevertheless, it may be mentioned that MOEF has imposed ban<br />
on construction <strong>of</strong> dam on Subansiri River upstream <strong>of</strong> Subansiri<br />
Lower Project. Accordingly, matter needs to be taken up with MOEF for<br />
review and lifting <strong>of</strong> ban before taking up investigation work leading to<br />
preparation <strong>of</strong> DPR.<br />
11
2.0 GENERAL<br />
CHAPTER-II<br />
BACKGROUND INFORMATION<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Subansiri River is a major tributary <strong>of</strong> Brahmaputra contributing about 10%<br />
<strong>of</strong> its total discharge. It has its origin in the Central Himalayas in Tibet at<br />
an approximate altitude <strong>of</strong> 5340 m. Traversing through the snow clad<br />
mountains <strong>of</strong> Great Himalayas, it enters India in its North-East corner in<br />
Arunachal Pradesh. The river bed level drops from more than 4000 m<br />
height in the mountainous region to less than 100 m in the foothills before<br />
it enters the plains <strong>of</strong> Assam promising stupendous hydropower potential<br />
with snowmelt combining with heavy rainfall it receives in its catchment<br />
ensuring significant discharge in the river throughout the year.<br />
2.1. PROPOSALS FOR HARNESSING HYDRO-POWER POTENTIAL<br />
OF SUBANSIRI BASIN<br />
To harness hydro-power potential <strong>of</strong> Subansiri river and to derive benefits<br />
<strong>of</strong> flood moderation, DPR <strong>of</strong> Subansiri dam project (4800 MW) was<br />
prepared by Brahmaputra Board during April 1983. But the project could<br />
not be taken up for execution because <strong>of</strong> objections from Arunachal<br />
Pradesh Govt. on account <strong>of</strong> large submergence <strong>of</strong> its land and<br />
consequent displacement <strong>of</strong> inhabitants. Subsequently, cascade<br />
development over river Subansiri was planned considering three projects<br />
namely Subansiri Lower HE Project at Gerukamukh over river Subansiri<br />
(2,000 MW), Subansiri Middle project at Tamen over river Kamla<br />
(1,600 MW) and Subansiri Upper Project at Menga over river Subansiri<br />
(2,000 MW).<br />
12
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
The Subansiri Lower HE Project is now under construction by NHPC. The<br />
feasibility reports <strong>of</strong> Subansiri Upper and Subansiri Middle project(s) have<br />
already been prepared and detailed investigations leading to preparation<br />
<strong>of</strong> DPR for these two projects are in progress.<br />
In addition to the above 3 mega projects, 8 additional projects have been<br />
taken up in Subansiri basin for preliminary feasibility study on priority basis<br />
under “ 50,000 MW Hydro-electric Initiative ” launched by Hon’ble Prime<br />
Minister <strong>of</strong> India launched in May, 2003. In fact, CEA has conducted<br />
Ranking Study for harnessing the balance Hydropower potential available<br />
in the country and identified 399 Schemes to add further 1,07,000 MW to<br />
narrow the gap between supply and demand <strong>of</strong> power in the interest <strong>of</strong><br />
sustained economic growth <strong>of</strong> the country. In its first phase, 162 projects<br />
are taken up for preliminary feasibility study to be completed within 10-18<br />
months with a projected capacity addition <strong>of</strong> 50,560 MW. These projects<br />
are expected to be developed expeditiously within next 10 years.<br />
The eight new projects identified for preparation <strong>of</strong> PFR (Preliminary<br />
Feasibility Report) in Subansiri basin under 50,000 MW Hydroelectric<br />
Initiative were - Naba, Niare, Oju-I & II, Kurung - I & II , Hegio and<br />
Duimukh.<br />
Kurung-I & II projects have been clubbed and named as Kurung HE<br />
Project. Further, Heigo project has been found to be located within<br />
submergence <strong>of</strong> proposed Subansiri Middle Project. As such, in lieu <strong>of</strong><br />
these two projects, two schemes namely <strong>Nalo</strong> & Dengser located in<br />
between Naba project and Subansiri Upper Project have been added to<br />
list <strong>of</strong> PFR projects in Subansiri Basin (Annexure 2.1). Proposed cascade<br />
development over river Subansiri is enclosed as Plate 2.1.<br />
13
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
<strong>Nalo</strong> HE Project is located at about 120 km upstream <strong>of</strong> Daporijo town in<br />
Upper Subansiri District <strong>of</strong> Arunachal Pradesh. It has been envisaged as<br />
a run-<strong>of</strong>-the-river Scheme on (Subansiri) river with generating capacity <strong>of</strong><br />
360 MW. Location <strong>of</strong> the project is indicated in the vicinity map enclosed<br />
as Plate-2.2.<br />
2.2 EVOLUTION OF CONCEPTUAL LAYOUT OF NALO HE SCHEME<br />
While preparing PFRs <strong>of</strong> Naba, Niare, Oju-II and Oju-I projects it was<br />
noticed that about 300 m head between Naba and Subansiri Upper<br />
Project is unutilised. In CEA’s Ranking study or Reassessment study<br />
report there is no proposal to develop this head. Accordingly, it was<br />
considered prudent to explore possibilities <strong>of</strong> exploring potential <strong>of</strong> the<br />
river in this stretch between Naba and Ebiya villages. In this reach the<br />
river travels about 31 km descending from EL 770 m to EL 470 m<br />
providing a gross head <strong>of</strong> 300 m.<br />
As gradient <strong>of</strong> river in this stretch is gentle, developing this head through<br />
one scheme, would have involved construction <strong>of</strong> about a 25 km long HRT<br />
as water conductor system. Hence, it was considered prudent to go for<br />
two schemes in cascade. As a result, concept <strong>of</strong> <strong>Nalo</strong> and Dengser<br />
projects emerged. Various alternative layouts were developed on<br />
toposheets and proposed sites were inspected by NHPC <strong>of</strong>ficers. Based<br />
on the data/ information collected during site visits and study <strong>of</strong><br />
topographical and geological inputs as collected, the parameters <strong>of</strong> <strong>Nalo</strong><br />
Project are proposed taking into account Naba HE Project on upstream<br />
and Dengser HE Project on downstream. A few alternatives <strong>of</strong> scheme<br />
were studied and discussed with CEA and it is proposed to have the dam<br />
site where River Bed Level is 660 m and tailrace outfall at EL 635 m.<br />
Maximum TWL will be at EL 645 M. Summary record <strong>of</strong> the discussion<br />
held with CEA is enclosed as Annexure –2.2. Further, details <strong>of</strong> various<br />
14
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
alternative locations considered for finalising layout <strong>of</strong> <strong>Nalo</strong> HE Project are<br />
given in chapter-VI.<br />
Based on the limited available hydro meteorological data, hydrological<br />
studies have been carried out and a synthetic 90 % dependable water<br />
availability series developed for undertaking power potential studies. As<br />
per power potential studies the installed capacity works out to 360 MW.<br />
The design energy on a 90% dependable year works out to 1732.99 MU.<br />
Preliminary observations and study <strong>of</strong> available information reveal that, no<br />
major area <strong>of</strong> cultivable land is available around the proposed project area<br />
needing irrigation. As such, there is no scope for development <strong>of</strong> irrigation<br />
in this project. However, this aspect needs to be examined during<br />
feasibility stage investigations.<br />
PFR <strong>of</strong> <strong>Nalo</strong> HE Project has been made in accordance with the scope <strong>of</strong><br />
work and keeping in view observations/ comments <strong>of</strong> CEA (Annexure 2.3)<br />
2.3 POWER SCENARIO & EXISTING INSTALLATIONS<br />
The power system in India has grown from small, isolated stations, serving<br />
limited consumers in and around large cities, into large regional Grids. The<br />
generating capacity installed in the country has already grown to<br />
107643.70 MW by March 2003.<br />
The objective <strong>of</strong> the system development is to evolve self-sufficient<br />
regional grid catering to the individual regional power demands. It is also<br />
aimed at achieving the maximum benefits from integrated operation,<br />
through a proper mix <strong>of</strong> thermal and hydro generation and ultimately to tie<br />
the five regional grids together to form a robust National <strong>Power</strong> Grid,<br />
providing even greater reliability.<br />
15
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
At present, Arunachal Pradesh Electricity Board has its own hydel<br />
generation <strong>of</strong> 32.52 MW and diesel generation <strong>of</strong> 23.64 MW. Share <strong>of</strong><br />
Arunachal Pradesh in Central Sector <strong>Power</strong> Generation is around 117.0<br />
MW (includes gas based <strong>Power</strong> projects).<br />
2.4 NECESSITY OF THE PROJECT & RELATED ASPECTS<br />
The power position in the North Eastern region and all India power supply<br />
position have been summarized in Table-2.1 and Table-2.2. The benefits<br />
from all schemes that have been cleared by CEA have been included.<br />
Even after considering the co-ordinated operation <strong>of</strong> existing hydro,<br />
nuclear and thermal stations as well as benefits from ongoing projects and<br />
also from the scheme cleared by CEA and programmed for<br />
implementation in 10th Plan, the all India regions are expected to face<br />
power deficit in 10th five year plan. The regions will continue to remain in<br />
deficit in 11th Five year plan also except in North-Eastern region as it is<br />
evident from Table-2.1 even if all the cleared projects till date are<br />
implemented. The surplus in North-Eastern region is planned to be<br />
exported to regions having deficit. However, energy requirement and peak<br />
requirement in the country will remain in deficit even by the end <strong>of</strong> 11 th<br />
plan as shown in Table-2.2. Construction <strong>of</strong> <strong>Nalo</strong> HE Project will reduce<br />
this deficit.<br />
16
Table 2.1<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
17
Table 2.2<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
18
3.0 THE PROJECT<br />
CHAPTER- III<br />
PROJECT AREA<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
The <strong>Nalo</strong> HE Project is located in upper reaches <strong>of</strong> Subansiri River near<br />
<strong>Nalo</strong> village. It is about 120 km from Daporijo town. Hydropower potential<br />
<strong>of</strong> the river Subansiri is proposed to be harnessed through cascade <strong>of</strong><br />
several projects, viz.-Oju-I, Oju-II, Niare, Naba, <strong>Nalo</strong>, Dengser, Subansiri<br />
Upper Project and Subansiri Lower Project. The proposed dam site <strong>of</strong><br />
<strong>Nalo</strong> project is accessible through Daporijo-Limeking road.<br />
3.1 RIVER SYSTEM<br />
River Subansiri originates in Tibet at an altitude <strong>of</strong> around 5340 m<br />
beyond the Great Himalayan Range (Central Himalayas) and after<br />
traversing about 375 km joins the Brahmaputra river. The river flows<br />
through narrow gorge in most part <strong>of</strong> its length and generally follows an<br />
easterly direction up to Siyum, and, thereafter it takes a south-easterly<br />
course upto its confluence with Kamla. Then, it flows in a southerly<br />
direction upto Kherkatiasuti and after flowing for another 60 km (approx.)<br />
in south-westerly direction it confluences with the mighty Brahmaputra<br />
River. It is one <strong>of</strong> the largest right bank tributary <strong>of</strong> Brahmaputra and<br />
contributes about 10% <strong>of</strong> its total discharge. Major tributaries joining the<br />
Subansiri river in the project area are Ledi Ishi, Kyo Ishi, Kodap & Kojap<br />
nallah. These tributaries exhibit trellis and dendritic pattern <strong>of</strong> drainage.<br />
Major villages/ towns located in the vicinity are <strong>Nalo</strong>, Jiba-Aying,<br />
Doginalo & Nacho.<br />
19
3.2 LOCATION AND ACCESSIBILITY<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
The project area is located near <strong>Nalo</strong> village. <strong>Power</strong>house as well as<br />
dam site can be accessed by all weather Daporijo- Limeking road<br />
running on right bank <strong>of</strong> the river. The dam site <strong>of</strong> <strong>Nalo</strong> project is located<br />
about 10 km upstream <strong>of</strong> Nacho. Major villages/towns present along the<br />
Daporijo – Limeking road are Taliha, Kodak, Siyum, Ayingmoring, Nacho<br />
& Limeking. Left bank <strong>of</strong> the river at proposed dam site can be<br />
approached by a bamboo bridge located about 1 km upstream <strong>of</strong> dam<br />
site. It is connected by a foot track. Proposed powerhouse site is located<br />
on right bank <strong>of</strong> the river near Jiba-Aying village.<br />
The nearest meter gauge and broadgauge railhead is North Lakhimpur<br />
and Nagaon respectively. Nearest airport is at North Lakhimpur<br />
(Lilabari) in Assam. Besides, there are helipads at Daporijo, Nacho,<br />
Limeking near the project area.<br />
3.3 CLIMATIC CONDITION<br />
The area experiences a subtropical climate with temperatures ranging<br />
from 11.5 0 to 39.5 0 C at Menga. However, from local enquiries it is learnt<br />
that temperature falls to 0 0 C around the project area in winters. Ice-cold<br />
winds blow during the morning and evening hours <strong>of</strong> the winter season.<br />
Monsoon commences during May and lasts till the end <strong>of</strong> September.<br />
Nevertheless, scanty rains are also common during winter season.<br />
Average annual rainfall in and around project area is about 2810 mm.<br />
The relative humidity as observed ranges from maximum 94% to<br />
minimum 62%.<br />
20
3.4 SOCIO- ECONOMIC ASPECTS<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
The project area is located in the Upper Subansiri District in Arunachal<br />
Pradesh sharing the International Boundary with China in the North.<br />
Upper catchment <strong>of</strong> Subansiri Basin in Indian territory falls in this district.<br />
The area is inhabited mainly by the people from the Nyshis, Tagin<br />
community, Galos and Hill Miris. The main livelihood <strong>of</strong> the population is<br />
cultivation. They commonly practice terrace and jhoom cultivation.<br />
3.4.1 Demography<br />
The district is divided into 11(eleven) circles. The district has a diverse<br />
terrain extending over valleys <strong>of</strong> lower altitude to heights upto 18000 ft.<br />
Taksing is the remotest Circle bordering Tibet. It has snow bound peaks<br />
where no habitation exists.<br />
The Upper Subansiri District has an area <strong>of</strong> 7032 sqkm. The total<br />
population <strong>of</strong> the district is 50,086 (1991 census). The population density<br />
is approximately 8 persons per sq.km in the district. The male population<br />
is 26,823 and the female population is 23,263. There is no educational<br />
institution above higher secondary level. There are 3 nos. <strong>of</strong> Higher<br />
Secondary Schools and 6 nos. <strong>of</strong> High Schools in the district. Population<br />
<strong>of</strong> Nacho circle is 3404 persons where the project is located.<br />
Circle wise population pattern <strong>of</strong> the Upper Subansiri District is<br />
presented in tabulated form (Table 3.1) below.<br />
21
Table 3.1<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Circle wise population in Upper Subansiri District as per 1991 census.<br />
(Statistical Hand Book <strong>of</strong> Upper Subansiri District - 2000 )<br />
Sl No. Name <strong>of</strong> Circles<br />
Total No. <strong>of</strong><br />
Villages<br />
Total No. <strong>of</strong><br />
House hold<br />
Total<br />
Population<br />
01. Daporijo 56 2948 17425<br />
02. Dumporijo 57 4299 7457<br />
03. Baririjo 24 620 3292<br />
04. Giba 62 980 5052<br />
05. Taliha 89 1666 8057<br />
06. Taksing 12 168 733<br />
07. Nacho 42 827 3404<br />
08. Limeking 18 209 863<br />
09. Siyum 45 835 3803<br />
Total 405 12552 50086<br />
3.4.2 Ethnography<br />
Race: The people <strong>of</strong> Arunachal Pradesh have been generally described<br />
as descendants <strong>of</strong> Mongoloid, Paleo mongoloid and Proto-mongoloid<br />
race. The distinctive characteristics <strong>of</strong> the tribes in their language, dress,<br />
customs and food habits are direct reflection <strong>of</strong> the type <strong>of</strong> environment<br />
they live in - in geographical isolation over a long period <strong>of</strong> time.<br />
22
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Tribes: The major tribes found in the project area belong to “Tagin”<br />
community and “Nyishi”. These ethnic population usually live in different<br />
groups called ‘busthi’ in the local language. Each ‘busthi’ generally<br />
comprises <strong>of</strong> 15-25 homesteads. The houses (constructed <strong>of</strong> wood,<br />
bamboo and thatches) are usually raised over a platform <strong>of</strong> logs about 3-<br />
4 feet above the ground.<br />
Social structure: The tribals <strong>of</strong> Arunachal Pradesh have highly ordered<br />
and organised system <strong>of</strong> functioning in their villages. All matters relating<br />
to the community as a whole are decided at the village level. The socioadministrative<br />
structure <strong>of</strong> the society, as evolved over centuries,<br />
recognises democratic participation right down to the village level.<br />
Several self-governing institutions exist among these tribes. Such a<br />
structure <strong>of</strong> ‘Nyshis’ in the area is locally known as ‘Nyele’.<br />
Agriculture: Jhum cultivation is one <strong>of</strong> the predominant forms <strong>of</strong><br />
agriculture even today. Efforts are on to control this form <strong>of</strong> practice as<br />
this results in cutting <strong>of</strong> forest trees & degradation <strong>of</strong> slopes. Most <strong>of</strong> the<br />
people are dependent on agriculture. Only a few are working as traders,<br />
daily wage labourers or salaried employees. Wet Rice Cultivation (WRC)<br />
and Terrace Rice Cultivation (TRC) is also practiced in areas where flat<br />
ground /river terraces are available.<br />
Festival: Four main festivals are observed by the various communities<br />
<strong>of</strong> the district. These are, (i) Si-Donyi, (ii) Boori-Yullo, (iii) Boori- Boot<br />
and (iv) Mopin. The Tagin community celebrates the festival <strong>of</strong> Si-Donyi<br />
in the month <strong>of</strong> January. Nyishis celebrates the Boori-Yullo festival<br />
during the month <strong>of</strong> January. The Hill Miris community observes Boori-<br />
Boot festival during the month <strong>of</strong> February. The Galo community<br />
celebrates the Mopin festival during the month <strong>of</strong> April. There is another<br />
festival known as Losar observed by the people <strong>of</strong> Taksing area in the<br />
month <strong>of</strong> February.<br />
23
CHAPTER-IV<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
TOPOGRAPHIC AND GEOTECHNICAL ASPECTS<br />
4.0 INTRODUCTION<br />
The Geological Survey <strong>of</strong> India has prepared a Preliminary Appraisal<br />
Report entitled “Geology <strong>of</strong> Area Around the Proposed <strong>Nalo</strong> Hydroelectric<br />
Project, Subansiri Basin, Arunachal Pradesh (March ’04)”. This appraisal<br />
(Annexure 4.1) is the main source <strong>of</strong> geological inputs for evaluating<br />
geotechnical aspects <strong>of</strong> the project. Nevertheless, proposed sites were<br />
visited by NHPC geologists to collect site specific geotechnical details.<br />
Topographic and geological aspects <strong>of</strong> the area have been used while<br />
finalizing conceptual layout <strong>of</strong> the project (Plate-4.1).<br />
4.1 REGIONAL TOPOGRAPHY AND GEOLOGY<br />
The river Subansiri originates from Tibet and after traversing 375 km joins<br />
the Brahmaputra River. At the project site river flows in an almost W-E<br />
direction carving out a very narrow valley.<br />
Project area in general is characterised by rugged topography typical <strong>of</strong><br />
Himalayan terrain. Geomorphologically, the area is composed <strong>of</strong> high<br />
mountain ridges with steep slopes and deep incised valleys carved by<br />
Subansiri river and perennial nallahs joining Subansiri river.<br />
The Project area falls within higher Himalayas. At the proposed dam site<br />
river valley is about 60 m wide with steep rocky slope at left bank and a<br />
predominantly gentle slope on right bank. Right bank is covered by<br />
overburden material and has a thick vegetation cover. Rock present at the<br />
dam site is dark grey coloured slightly weathered to almost fresh biotite<br />
gneiss. Geologists <strong>of</strong> G.S.I. (Surendra Singh, K.V.S Reddy, C.M.Bindal,<br />
24
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
B.V.Ganesh and K.K. Rao, 1985-86) have carried out regional geological<br />
mapping in this area.<br />
4.2 REGIONAL GEOLOGY<br />
The tectono-stratigraphic sequence <strong>of</strong> Upper Subansiri area as given<br />
by Singh et al (1986) is reproduced below from GSI (March,2004) report.<br />
(Table-4.1)<br />
Table- 4.1<br />
Generalised Geological Succession<br />
Group Formation Litho-assemblages<br />
S<br />
U<br />
B<br />
A<br />
N<br />
S<br />
I<br />
R<br />
I<br />
G<br />
R<br />
O<br />
U<br />
P<br />
Maza Granite Tourmaline leucogranite with biotite<br />
gneiss and hornblende gneiss<br />
Taksing Formation Schistose quartzite interbanded with<br />
staurolite-garnet-biotite schists, calsilicate,<br />
marble, meta-amphibolites<br />
Gelensiniak Formation Kyanite-sillimanite-garnet gneiss,<br />
migmatite gneiss, garnetiferous<br />
biotite gneiss, biotite gneiss,<br />
calc-silicate rock, marble with<br />
graphitic<br />
graphitic schists.<br />
disseminations,<br />
Nacho Formation Schistose Quartzite intercalated and<br />
interbanded with biotite schist.<br />
-----------------------------------------Kobaso Thrust-------------------------------------<br />
Tali Massive quartzite, limestone/dolomite, phyllite and slate<br />
Group<br />
25
Maza Granites<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Tourmaline leucogranites, extensively exposed at Maza and further north<br />
towards International Border with China have been designated as ‘Maza<br />
Granites’. It is light grey fine grained and pr<strong>of</strong>usely jointed. Maza Granites<br />
show hypidiomorphic granitar texure. Orthoclase, plagioclase and quartz<br />
are its main mineral constituents. These are <strong>of</strong> intrusive igneous origin.<br />
Taksing Formation<br />
The metasedimentaries <strong>of</strong> Subansiri Valley constituting the Taksing<br />
Formation are exposed in a NE-SW trending belt and are encountered<br />
between Reddi and Taksing in Subansiri valley and also between Gelmo<br />
and Ridding in the Tsari-Chu. White to light grey and fine quartzite<br />
constitute the dominant lithounit <strong>of</strong> the Taksing Formation. Interbands <strong>of</strong><br />
staurolite – garnet –biotite- schist are common in the quartzite.<br />
Gelensiniak Formation<br />
The Gelensiniak Formation is most extensively developed in the<br />
Subansiri Valley. Various types <strong>of</strong> gneisses belonging to this formation<br />
are biotite gneiss, garnetiferrous biotite gneiss and kyanite- sillimanite<br />
gneiss. These can be distinguished in the field on the basis <strong>of</strong> appearance<br />
<strong>of</strong> index minerals such as Garnet, Kyanite, Sillimanite etc. Each type <strong>of</strong><br />
gneiss forms a distinct belt and have gradational contacts with one<br />
another.<br />
In the project area dark grey colured fine to medium grained well foliated<br />
biotite gneiss is exposed.<br />
Nacho Formation<br />
It constitutes a litho-assemblage <strong>of</strong> white to light brown coloured<br />
schistose-quartzite, intercalated as well as interbanded with dark biotite<br />
schist. At Nacho the biotite schist bands show preponderence over the<br />
26
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
quartzite. Further west dark grey biotite schist is well exposed. Near Dogi<br />
<strong>Nalo</strong>, the Nacho Formation grades into overlying Gelensiniak Formation.<br />
The quartzite, phyllite, limestone representing Tali Group are exposed<br />
around Mara in southeastern corner. These are overridden by the medium<br />
to high grade metamorphics and crystallines <strong>of</strong> the Subansiri Group along<br />
the Kabaso Thrust.<br />
4.3 TOPOGRAPHIC AND GEOTECHNICAL ASPECTS OF<br />
COMPONENT STRUCTURES<br />
To substantiate topographic/geological data, entire area has been<br />
traversed and site specific information has been collected. A geological<br />
section has been developed across the river near proposed dam site<br />
(Plate-4.2), based on surface observations.<br />
4.3.1 Dam<br />
At the proposed site river flows through a wide valley. Width <strong>of</strong> the river<br />
channel is about 60 m and width <strong>of</strong> the valley at the dam top is about 350<br />
m. Left abutment is a steep rocky slope. Right abutment has a gentle<br />
slope and is covered by overburden and thick vegetation. Nevertheless,<br />
on right bank small rock outcrops are seen downstream <strong>of</strong> dam axis<br />
indicating availability <strong>of</strong> rock at reasonable depth. Thickness <strong>of</strong><br />
overburden and quality <strong>of</strong> bedrock needs to be ascertained during<br />
feasibility stage investigations. Dark grey coloured almost fresh to slightly<br />
weathered biotite gneiss <strong>of</strong> Gelensiniak Formation is exposed in the<br />
area. Rock is well foliated and moderate to closely jointed, dissected by<br />
three to four prominent joint sets. Overburden on left abutment is very thin<br />
but on right abutment it is comparatively thicker.<br />
Depth <strong>of</strong> overburden in the river channel is not known at this stage. This<br />
needs to be ascertained through exploratory drilling during feasibility /<br />
DPR stage Investigations.<br />
27
4.3.2 Water Conductor System<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Topography, geomorphology and geology are favorable for laying a tunnel<br />
on the right bank. Proposed head race tunnel would be laid in puckered<br />
biotite schist <strong>of</strong> Nacho Formation. However, intake tunnels and desilting<br />
chambers will be housed in biotite gneiss <strong>of</strong> Gelensiniak Formation.<br />
Engineering classification <strong>of</strong> rockmass expected to be negotiated in<br />
various underground components <strong>of</strong> water conductor system needs to be<br />
done during FR/DPR stage for estimating rock support requirement during<br />
excavation.<br />
4.3.3 <strong>Power</strong> House<br />
The surface powerhouse is proposed on right bank <strong>of</strong> Subansiri river near<br />
Jiba-Aying village. It will be located in moderate to closely jointed biotiteschist<br />
belonging to Nacho Formation. Although, valley slope on right bank<br />
are relatively gentler near proposed location, but some amount <strong>of</strong> slope<br />
cutting will be required to create sufficient space for surface power house.<br />
Therefore, depth <strong>of</strong> overburden and quality <strong>of</strong> bedrock at the back slope <strong>of</strong><br />
powerhouse needs to be studied during FR/DPR stage. If after detailed<br />
study, surface powerhouse does not find favour option <strong>of</strong> underground<br />
powerhouse may also be studied during FR/DPR stage.<br />
Location <strong>of</strong> proposed surge shaft and pressure shaft needs to be studied<br />
with a backup <strong>of</strong> detailed geological mapping and exploratory drilling/<br />
drifting, during FR/DPR stage.<br />
4.4 SEISMICITY<br />
Seismotectonically, the area falls in the seismic zone –V <strong>of</strong> seismic zoning<br />
map <strong>of</strong> India (IS-1893: Part- I :2002). Site specific design parameters need<br />
to be worked out during Feasibility stage Investigations <strong>of</strong> the project.<br />
28
4.5 CONSTRUCTION MATERIAL<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
The Subansiri River flows through a narrow valley. There are very few<br />
river shoals or small terraces <strong>of</strong> riverine material, seen along course <strong>of</strong> the<br />
river. Hence, very limited quantities <strong>of</strong> natural aggregates are expected to<br />
be available from riverine shoals / terraces. Therefore, samples from rock<br />
exposed around dam site and in reservoir area may be tested for using<br />
this material as coarse and fine aggregates for production <strong>of</strong> concrete.<br />
Biotite gneiss rock is present at dam site and upstream <strong>of</strong> it whereas<br />
schistose quartzite intercalated with biotite schist is present downstream<br />
<strong>of</strong> dam site. Desilting chambers and HRT would be laid in biotite gneiss<br />
and biotite schist. Excavated rock from biotite gneiss is expected to be<br />
useful as concrete aggregates (non- wearing surface only). Accordingly,<br />
samples <strong>of</strong> rocks expected to be available in underground excavations<br />
may also be tested during FR/DPR stage, if found suitable after testing.<br />
Detailed construction material surveys may be conducted to identify<br />
borrow areas and rock quarries. Quality and quantity <strong>of</strong> material for each<br />
borrow area and rock quarry may also be ascertained during FR/DPR<br />
stage investigations.<br />
4.6 RECOMMENDATIONS<br />
INVESTIGATIONS<br />
FOR FURTHER STUDIES/<br />
4.6.1 Topographic Surveys<br />
- Detailed contour plans for Dam, Water Conductor System,<br />
powerhouse and reservoir areas as per CWC guidelines.<br />
- Cross- section <strong>of</strong> river at dam site and along other main<br />
components <strong>of</strong> the project.<br />
4.6.2 Geological Geotechnical Studies<br />
- Detailed geological mapping <strong>of</strong> project components.<br />
- Petrographic studies on rock samples.<br />
29
- Rock mass classification for underground excavations.<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
- Drill holes and exploratory drifts at dam axis, water conductor<br />
system and various components in the powerhouse area.<br />
- Permeability / water pressure testing in drill holes.<br />
- One or two sets <strong>of</strong> Groutability tests should also be done.<br />
- Lab / In-situ rock mechanic testing for evaluation <strong>of</strong> physical<br />
properties and engineering properties <strong>of</strong> the rock mass.<br />
- Geophysical surveys for estimation <strong>of</strong> overburden at main civil<br />
structures.<br />
4.6.3 Remote Sensing Studies<br />
- Regional geological appraisal <strong>of</strong> the area using remote sensing<br />
data and aerial photographs.<br />
- Preparation <strong>of</strong> lineament/ tectonic map <strong>of</strong> the area.<br />
- Landuse classification using toposheets and Satellite imageries.<br />
4.6.4 Construction Material Surveys<br />
- Identification <strong>of</strong> borrow areas/ rock quarries.<br />
- Survey <strong>of</strong> borrow areas / rock quarries for quantity estimation.<br />
- Testing <strong>of</strong> representative samples for determination <strong>of</strong> physical<br />
properties and alkali- aggregate reactivity potential.<br />
30
5.0 GENERAL<br />
CHAPTER – V<br />
HYDROLOGY<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
<strong>Nalo</strong> H.E. Project is proposed on river Subansiri a tributary <strong>of</strong> Brahmaputra<br />
river, near <strong>Nalo</strong> village in Upper Subansiri district <strong>of</strong> Arunachal Pradesh.<br />
The proposed dam site is located around 1.6 km upstream <strong>of</strong> confluence <strong>of</strong><br />
Ledi Ishi, with Subansiri, a right bank tributary <strong>of</strong> Subansiri river. The project<br />
envisages construction <strong>of</strong> 125 m high dam above river bed on Singit or<br />
Subansiri River with a gross storage capacity <strong>of</strong> 163.37 mcm at FRL i.e EL<br />
765 m. The submergence area is estimated as 283.8 Ha at FRL whereas<br />
the reservoir length is measured as around 9.7 km.<br />
The hydrological investigations and analysis have been carried out with a<br />
view to:<br />
• Assess the availability <strong>of</strong> water for power generation by<br />
establishing a long-term series <strong>of</strong> average 10-daily discharges<br />
at the project site.<br />
• Estimate the spillway design flood.<br />
• Determine the capacity <strong>of</strong> the reservoir and the area <strong>of</strong><br />
submergence at different levels including FRL and MDDL.<br />
• Reservoir Sedimentation<br />
5.1 RIVER SYSTEM & BASIN CHARACTERISTICS<br />
Subansiri is a major right bank tributary <strong>of</strong> river Brahmaputra. The river<br />
originates beyond the Great Himalayan Range (Central Himalaya) at an<br />
31
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
altitude <strong>of</strong> around 5340 m. Near its source, several mountain torrents,<br />
rather a big “Chu” family <strong>of</strong> streams, drains into main valley. The principal<br />
stream belonging to this “Chu” group is the Nye Chu which may be<br />
considered as the main source <strong>of</strong> the river Subansiri originating from the<br />
snow clad peaks <strong>of</strong> Krakang, Shabota, Baru and Mata (El 5389 m) lying<br />
around 92 o and 93 o E longitudes and 28 o and 29 o N latitudes. The Nye Chu<br />
is then joined by another stream Laro Chu near Chayal and thereby taking<br />
the name <strong>of</strong> Chayal Chu. Another stream, the Char Chu, rising from the<br />
snow clad peaks in the North joins the main stream Chyal Chu near<br />
Karutra and crosses the international boundary soon after.<br />
A small distance from the boundary, Yume Chu flowing from the north<br />
merges with mainstream. After flowing further it receives the Tsari Chu and<br />
the combined water <strong>of</strong> these streams flow as the Subansiri for about 200<br />
km from this point finally outfalling into Kherkutia Suti, a spill channel <strong>of</strong> the<br />
Brahmaputra. In higher reaches, where it is known as Tsari chu, the<br />
Subansiri is flowing in an approximately easterly direction. The river cuts<br />
across the central Himalayan ridge, which has a series <strong>of</strong> high peaks <strong>of</strong><br />
5000 m and above. It follows a Southeasterly course along the lesser<br />
Himalayan zone with an average height <strong>of</strong> 3048 m and takes the name<br />
Subansiri.<br />
The river as it approaches the Miri hills in Arunachal Pradesh after crossing<br />
the international boundary runs in an unexplored valley and the course <strong>of</strong><br />
the main river and its tributaries are more or less marked on conjectural<br />
lines rather than by accurate mapping. In its early reaches as the river<br />
gathers more and more torrents in the Himalayas, it rushes through deep<br />
gorges, far below the snow tipped mountain peaks.<br />
The main course <strong>of</strong> the Subansiri after entering the Miri hills in Arunachal<br />
Pradesh runs between the Dafla hills and the Abor hills. Even in this reach,<br />
very little is known <strong>of</strong> the river and its valley as it is covered with dense<br />
32
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
vegetation and impenetrable forests. It is an enormous virgin terrain <strong>of</strong><br />
rugged mountains, covered by insatiable forest, fed by copious rains.<br />
After traversing through the Miri Hills <strong>of</strong> the outer Himalaya (Siwalik<br />
foothills), the Subansiri debouches into the plains <strong>of</strong> Assam near<br />
Dulangmukh. Before entering the plains, Subansiri cuts a steep gorge <strong>of</strong><br />
unique beauty through the Siwalik rocks <strong>of</strong> Arunachal Himalaya.<br />
Debouching from the hills near Dulangmukh the course <strong>of</strong> river lies in the<br />
fertile plains <strong>of</strong> North Lakhimpur Civil Sub-Division <strong>of</strong> Assam. In the broad<br />
and flat valley, the river flows in lazy and sinuous curves. The total length <strong>of</strong><br />
the river in the mountainous terrain is about 208 km. The riverbed falls from<br />
a height <strong>of</strong> 4206 m to 80 m near Dulangmukh in the foothills. After flowing<br />
for about 70 km from the hills, the river falls into the Kherkutia Suti and<br />
thereafter flowing for another 60 km it outfalls into the river Brahmaputra.<br />
Throughout its journey from the central Himalaya to the Arunachal foothills,<br />
the Subansiri receives the discharges <strong>of</strong> numerous mountainous big and<br />
small streams. The number <strong>of</strong> its tributaries is more in the Siwalik foothills<br />
than in other zones. The total length <strong>of</strong> the known and well-defined<br />
tributaries <strong>of</strong> Subansiri is 1960 km.<br />
The region may be divided into four parts; the distant Tibetan mountains<br />
beyond the international border, the reach lying between the international<br />
boundary and Miri hills <strong>of</strong> Arunachal Pradesh, the Arunachal Pradesh<br />
portion between the outskirt <strong>of</strong> Miri hills and the inter-state boundary <strong>of</strong><br />
Assam and Arunachal Pradesh and lastly the plains <strong>of</strong> Assam. The first two<br />
belongs to the great Himalayan range, the third belonging to the Sub-<br />
Himalayas and the fourth in the fertile plains <strong>of</strong> Assam.<br />
Tibet, the birthplace <strong>of</strong> Subansiri is a land to conjure with. In the mountains,<br />
blinding snow and ice build vast bewildering expanses. The streams flow<br />
beneath the ice in winter, which have their turn in summer when they melt<br />
and flow down the valleys lined up on either side with rows <strong>of</strong> white snow.<br />
33
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
In this region are found towns, highly inaccessible in their mountain<br />
retreats.<br />
Down below in the region between the Miri hills <strong>of</strong> Arunachal Pradesh and<br />
international boundary, the river passes through damp thick jungles and<br />
rocky terrain.<br />
The next reach is also in mountain terrain. These are the Sub-Himalayas,<br />
the pattern <strong>of</strong> the hills and valleys being the same imposition <strong>of</strong> the<br />
Himalayan range at a lower altitude. In the vastness <strong>of</strong> wild mountains,<br />
there are unbelievable settlements <strong>of</strong> human habitation.<br />
In the last lap <strong>of</strong> journey Subansiri passes through a broad fertile plain with<br />
gentle slopes. Debouched from the narrow confines <strong>of</strong> the gorge, it spreads<br />
and dissipates itself out in the plains <strong>of</strong> Lakhimpur District meandering and<br />
altering channels <strong>of</strong> flow. The topography <strong>of</strong> this region is almost flat formed<br />
<strong>of</strong> alluvial deposits. The river Subansiri in Arunachal Pradesh flows through<br />
Upper and Subansiri Lower districts and in Assam its catchment area falls<br />
in the North Lakhimpur and Dhemaji districts. The contribution <strong>of</strong> the river<br />
Subansiri is estimated to be about 10.66 percent <strong>of</strong> the total discharge <strong>of</strong><br />
the river Brahmaputra at Pandu near Guwahati.<br />
The snow line or limit <strong>of</strong> perpetual snow in the Himalaya varies depending<br />
upon various local factors. The present snow line varies in altitude from<br />
about 4267 m in the eastern part to about 5182 m in the western<br />
Himalayas.<br />
The catchment plan <strong>of</strong> Subansiri basin along with rainfall stations, G&D<br />
sites marked is shown in Plate–5.1.<br />
34
5.1.1 Catchment Area<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
The <strong>Nalo</strong> basin lies between Longitude 91 o 45′ E to 93 o 49′E and Latitude<br />
27 o 50’ N to 29 o 00’ N. The proposed dam site lies at Longitude 93 o 46’54”E<br />
and Latitude 28 o 24’27” N. The total catchment area up to the proposed dam<br />
site is about 14500 sq.km. The permanent snow cover has been assumed<br />
above an elevation <strong>of</strong> 4500 m. The snowfed area at proposed dam site has<br />
been estimated as 9484 sq.km. The rainfed area upto the proposed dam<br />
site is 5016 sq.km. The river bed level at the proposed dam site is around<br />
EL 660 m. Average slope <strong>of</strong> river upto proposed dam site is estimated as<br />
around 11 m per km.<br />
The catchment plan <strong>of</strong> Subansiri Upper basin upto <strong>Nalo</strong> dam site is given in<br />
Plate-5.2. This catchment plan has been prepared on the basis <strong>of</strong><br />
catchment plan prepared for the Subansiri basin by Brahmaputra Board and<br />
then by NHPC. Toposheets <strong>of</strong> 1:50000 scale covering the catchment area<br />
<strong>of</strong> the basin are not available and as most <strong>of</strong> the area falls in Tibetan<br />
catchment, therefore it is difficult to collect them in feasibility stage also.<br />
However, on availability <strong>of</strong> toposheets, the catchment plan need to be<br />
verified in feasibility stage/DPR stage.<br />
5.1.2 Temperature and Humidity<br />
The climate in the entire region is humid and fairly uniform. Thick mist<br />
formation from early morning everyday, which completely envelope the area<br />
and blocks out the sun is generally, the climatic feature during winter. The<br />
temperature varies from high altitude to lower altitude. The maximum and<br />
minimum temperature is 39.5 o C and 11.5 o C as observed at Menga. The<br />
relative humidity ranges from maximum 94% to minimum 62%.<br />
35
5.1.3 Precipitation Characteristics<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Subansiri basin extends from tropical to temperate zones and therefore the<br />
area exhibits a great diversity in rainfall characteristics. In the Northern and<br />
Central Himalayan tracts precipitation is scarce on account <strong>of</strong> high altitudes.<br />
Southeast part <strong>of</strong> the Subansiri basin comprising the sub-Himalayan and<br />
the plain tract in Arunachal Pradesh and Assam, lies in the tropics.<br />
Precipitation occurs in this region in copious quantities due to Northeast as<br />
well as Southwest monsoon. Particularly the Southwest monsoon causes<br />
very heavy precipitation in the whole <strong>of</strong> this region during May to October.<br />
July and August are generally the high flood months.<br />
The Eastern and Central Himalayas function as a great climate divide. In<br />
winter, it serves as a barrier to the intense cold continental air flowing<br />
southwards and in monsoon months, the moist rain bearing winds are<br />
forced up the mountains to deposit their moisture.<br />
The southwest monsoon, which enters Assam and adjoining area around<br />
end <strong>of</strong> May and beginning <strong>of</strong> June establishes firmly over the entire North<br />
East India by June end. During the monsoon season a low-pressure region<br />
extends from the seasonal low over Rajasthan to the head <strong>of</strong> Bay <strong>of</strong><br />
Bengal. This monsoon axis oscillates about the normal position to the North<br />
and South during the season. When it moves North towards the foothills <strong>of</strong><br />
Himalaya the rainfall over Assam increases and this is one <strong>of</strong> the primary<br />
causes <strong>of</strong> flood in the Brahmaputra Valley. Sometimes a minor east west<br />
oriented trough over Assam and West Bengal, while the primary trough is<br />
along normal position, can also give rise to increased precipitation over the<br />
Brahmaputra catchment. Land based low and depressions form in situ over<br />
Assam and adjoining region or move across Bangladesh and influence in<br />
increasing the precipitation over the various reaches <strong>of</strong> Brahmaputra Valley.<br />
36
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
The other features that normally cause increased precipitation over the<br />
Brahmaputra basin are passage <strong>of</strong> upper air trough in the monsoon<br />
westerlies and sometimes by the appearance <strong>of</strong> the remnants <strong>of</strong> mid<br />
latitude western disturbances over extreme North Arunachal Pradesh in<br />
conjunction with other precipitation causing features.<br />
The above account <strong>of</strong> weather and precipitation distribution is influenced by<br />
local orographic effects, with minor ranges, spurs, valleys <strong>of</strong> different width<br />
and narrow gaps permitting winds to enter from particular direction, in the<br />
sheltered valleys. The orography <strong>of</strong> the catchment is so complex that a<br />
detailed study would be possible only with a dense network <strong>of</strong><br />
observatories.<br />
The other meteorological situation causing very heavy rainfall is the<br />
passage <strong>of</strong> cyclonic storms, originating in Bay <strong>of</strong> Bengal, over the area.<br />
This is generally noted in late May or June and in late September or<br />
October, when the cyclonic storm developing over the Bay initially moves<br />
towards approximately 20 o N.<br />
The raingauge network in Subansiri Upper basin is not as per desired<br />
standards. No raingauge station is available within the catchment <strong>of</strong> <strong>Nalo</strong><br />
H.E. Project. NHPC has established rain gauge stations at Taliha, Siyum,<br />
Menga, Daporijo, Dumporijo, Nacho and Limeking in respect <strong>of</strong> Subansiri<br />
Upper Project. Out <strong>of</strong> these raingauge stations namely Taliha, Siyum,<br />
Nacho and Limeking lies near <strong>Nalo</strong> dam site, though outside the catchment<br />
<strong>of</strong> <strong>Nalo</strong>. Data Availability status <strong>of</strong> raingauge stations near <strong>Nalo</strong> is placed<br />
as Table 5.1.<br />
37
TABLE-5.1<br />
DATA AVAILABILITY STATUS<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
------------------------------------------------------------------------------------------------<br />
S.No STATION DATA AVAILABLE<br />
------------------------------------------------------------------------------------------------<br />
1. Taliha 1968-69,76-86,2000-2003<br />
2. Limeking 1966,68-69,77-80,2001-2002<br />
3. Siyum 1966,68-69,2001-2002<br />
4. Nacho 2001-2003<br />
------------------------------------------------------------------------------------------------<br />
The rainfall data is not continuous and missing in between prior to year<br />
2000. Further, it is not truly representative <strong>of</strong> entire basin. The raingauge<br />
stations could not be established due to inaccessibility and poor<br />
infrastructure <strong>of</strong> this region. Also most <strong>of</strong> the portion <strong>of</strong> this basin falls in<br />
Tibet. Monthly rainfall at all four stations for each year is given as<br />
Annexure 5.1A, 5.1B, 5.1C and 5.1D. Average monthly rainfall in near the<br />
catchment <strong>of</strong> proposed project is shown in Table –5.2. The average annual<br />
rainfall in the vicinity <strong>of</strong> the <strong>Nalo</strong> sub-basin is around 2810 mm.<br />
38
TABLE- 5.2<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
AVERAGE MONTHLY RAINFALL NEAR NALO SUB-BASIN<br />
MONTH TALIHA LIMEKING SIYUM NACHO AVERAGE<br />
JAN 62.5 111.8 40.2 22.5 59.2<br />
FEB 116.1 79.0 83.0 59.3 84.3<br />
MAR 186.2 174.5 193.3 138.7 173.2<br />
APR 283.7 199.9 232.3 173.1 222.3<br />
MAY 286.5 384.0 297.3 283.6 312.8<br />
JUN 315.5 537.2 573.0 582.4 502.0<br />
JUL 373.3 488.5 483.8 425.6 442.8<br />
AUG 281.0 444.0 392.5 473.5 397.8<br />
SEP 294.3 384.8 358.7 425.0 365.7<br />
OCT 123.7 186.5 189.1 117.8 154.3<br />
NOV 66.7 44.6 97.7 45.4 63.6<br />
DEC 49.3 40.2 20.0 17.8 31.8<br />
TOTAL 2438.8 3074.8 2960.9 2764.6 2809.8<br />
39
5.2 WATER AVAILABILITY STUDY<br />
5.2.1 Data Available<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Gauge and discharge data is not available anywhere in the catchment <strong>of</strong><br />
<strong>Nalo</strong> H.E. Project. Due to difficult condition <strong>of</strong> communication, accessibility<br />
and terrain, despite continuous efforts, much information about the<br />
discharge pattern in the catchment <strong>of</strong> proposed project could not be<br />
obtained. On the basis <strong>of</strong> available data and information the study has been<br />
made. However, few G&D sites has been established by various agencies<br />
within the Subansiri basin as detailed below.<br />
Brahmaputra Flood Control Commission (BFCC)/ Brahmaputra Board<br />
established a gauge discharge site at Daporijo 25 km d/s <strong>of</strong> Subansiri<br />
Upper dam site in 1978. The gauge and discharge Station at Bhimparaghat<br />
located 15 km downstream <strong>of</strong> the Subansiri Lower dam site was<br />
established by Central water Commission in 1956, which was subsequently<br />
shifted, to Chouldhowaghat in 1960 located 12 km downstream <strong>of</strong> the<br />
Subansiri Lower dam site. In 1971 the site was taken over by B.F.C.C.,<br />
Govt. <strong>of</strong> Assam. The gauge discharge site at Gorge Mouth was established<br />
in July 1973 located 2 km down stream <strong>of</strong> Subansiri Lower dam site, which<br />
was subsequently shifted to Subansiri Lower dam site in August 1977. A<br />
G&D site was established at Tamen on Kamla River, where gauge and<br />
discharge data is available from 1980 to 1998.<br />
NHPC has established G&D sites at Menga (260 m u/s <strong>of</strong> proposed dam<br />
site, operational since June 2000), Tamen Bridge (3 km d/s <strong>of</strong> Subansiri<br />
Middle dam site, operational since June 2000), Deo Nallah (situated at<br />
around 300 m d/s <strong>of</strong> Subansiri Lower dam site, operational since October<br />
2000) and Chouldhowaghat (operational since December 2000). A G&D<br />
site has also been established on Pein River, which joins Kamla near<br />
Tamen Bridge. A gauge site is at Ferryghat, which is around 1.9 km d/s <strong>of</strong><br />
40
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
proposed Subansiri Lower dam site. At present, floats are being used to<br />
measure the velocity. Current meters are also used mainly in lean season.<br />
5.2.2 Methodology<br />
The following methodology thought up to apply to obtain water availability<br />
series at proposed dam site.<br />
5.2.2.1 Rainfall Run<strong>of</strong>f Relationship<br />
First option is to generate discharge series on the basis <strong>of</strong> rainfall data<br />
available in the basin. A rainfall-run<strong>of</strong>f regression analysis could be<br />
performed in <strong>Nalo</strong> basin and the relationship so developed could be used to<br />
compute the discharge at proposed dam site. However this could not be<br />
done due to non-availability <strong>of</strong> discharge as well as rainfall for <strong>Nalo</strong> sub<br />
basin. A run<strong>of</strong>f factor <strong>of</strong> 0.73 had been established after detailed rainfallrun<strong>of</strong>f<br />
analysis in Subansiri basin as discussed in feasibility report <strong>of</strong><br />
Subansiri Upper Project. This factor could be used to compute run<strong>of</strong>f from<br />
rainfall. This methodology could also not be adopted because <strong>of</strong> the nonavailability<br />
<strong>of</strong> discharge and rainfall data within the <strong>Nalo</strong> sub-basin.<br />
5.2.2.2 Based on Discharge Series at Subansiri Upper Dam site<br />
Water availability study in Subansiri at Menga had been performed<br />
considering entire Subansiri river system as one, so as to maintain<br />
consistency in the flow at all the observation sites. After detailed analysis a<br />
20-year synthetic flow series (enclosed as Annexure-5.2) had been<br />
obtained at Subansiri Upper dam site (CA=20250 sq.km, Rainfed=9564<br />
sq.km). This synthetically generated 20 years discharge series at Subansiri<br />
Upper dam site may be transferred to <strong>Nalo</strong> dam site on the basis <strong>of</strong><br />
Catchment proportion considering the two basins as hydro-meteorologically<br />
homogeneous. The catchment correction factor has been worked out as<br />
0.524.<br />
41
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
For the present, the second methodology (catchment proportion) has been<br />
adopted. The discharge series so obtained has been checked for the<br />
consistency with the rainfall data available near <strong>Nalo</strong> basin. The run<strong>of</strong>f<br />
factor thus worked out as 0.72. However, this factor has been computed<br />
based on non-concurrent data base, therefore, detailed analysis need be<br />
done on availability <strong>of</strong> concurrent rainfall-run<strong>of</strong>f within the basin.<br />
The average 10 daily flow series at proposed dam site has been placed as<br />
Annexure-5.3. Average annual yield <strong>of</strong> at proposed dam site has been<br />
worked out as 10167 mcm.<br />
After establishing gauging station near proposed dam site with proper<br />
raingauge network in Subansiri Upper basin, detailed water availability<br />
study need be conducted in feasibility stage/DPR stage.<br />
5.3 RESERVOIR ELEVATION AREA CAPACITY CURVE<br />
The reservoir elevation-area-capacity curve at proposed dam site has been<br />
obtained on the basis <strong>of</strong> 1:50000 scale toposheets at 40 m contour interval.<br />
Area under various contours at 40 m interval has been measured from the<br />
elevation <strong>of</strong> 660 m to 800 m. The volume between any two elevations is<br />
calculated using the conical formula :<br />
Where<br />
V = (A1+A2+√A1A2)*H/3<br />
V = The volume between two contours<br />
H = Contour interval<br />
A1 = Area at level <strong>of</strong> first contour<br />
A2 = Area at level <strong>of</strong> second contour<br />
42
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
The incremental volumes thus obtained are added to obtain cumulative<br />
volume. The reservoir elevation-area-capacity curve at proposed dam site<br />
is given in Figure-5.1. This curve is subject to modification after availability<br />
<strong>of</strong> reservoir cross-sections or 1:15000 scale contour maps for the<br />
catchment.<br />
5.4 DESIGN FLOOD<br />
Design Flood for a project can be estimated by following approaches:<br />
(i) Deterministic approach using Unit Hydrograph technique.<br />
(ii) Statistical approach using Flood frequency analysis<br />
(iii) Empirical methods<br />
(i) Deterministic Approach Using Unit Hydrograph Technique<br />
Due to non-availability <strong>of</strong> G&D data, short term rainfall, hourly gauges<br />
etc, design storm values in the proposed catchment, rating curves<br />
and observed flood hydrographs could not be obtained for computing<br />
the Unit Hydrograph and Design Flood hydrograph. However, this<br />
approach has been used partially while transferring the flood <strong>of</strong><br />
Subansiri Upper dam site to the proposed dam site.<br />
(ii) Statistical Approach Using Flood Frequency Analysis<br />
Due to non-availability <strong>of</strong> long term, consistent G&D data near the<br />
proposed scheme, flood frequency analysis could not be performed<br />
at the project site.<br />
43
(iii) Empirical Methods<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
The following empirical relationships have been used to estimate the<br />
design flood peak:<br />
• Dicken’s Formula<br />
Q = CA 3/4<br />
Where,<br />
C = Dickens constant with value between 11-14 for North-<br />
Indian Hilly catchment. A value <strong>of</strong> 14 has been<br />
adopted in present study.<br />
A = Catchment area in sq.km<br />
Therefore<br />
Q = 14 x 5016 3/4<br />
= 8344 cumec<br />
• Fuller’s Formula<br />
Qmax = C.A 0.8 (1+0.8logT)*(1+2.66A -0.3 )<br />
Where,<br />
C = constant varying between 0.026 to 2.77 (2 adopted)<br />
Qmax = Maximum 24-h flood with a frequency <strong>of</strong> T years in<br />
cumec<br />
A = Catchment Area in sq.km<br />
1000 year Flood<br />
Q1000 =2 * 5016 0.8 (1+0.8log(1000))*(1+2.66*5016 -0.3 )<br />
= 7487 cumec<br />
44
• Ali Nawaz Jung Formula<br />
Q = C(0.386A) (0.925-1/14log0.386A)<br />
Where<br />
C = 49 to 60 (55 adopted)<br />
Q = 55* (0.386*5016) (0.925-1/14log(0.386*5016))<br />
= 10211 cumec<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
• Transferring design flood at Subansiri Upper dam site<br />
on the basis <strong>of</strong> Dickens formula.<br />
1-Day and 2-day PMF <strong>of</strong> 12226 cumec and 15210 cumec<br />
has been estimated at Subansiri Upper dam site<br />
(CA=20250 sq.km, Rainfed Area = 9564 sq.km). A base<br />
flow (including snow melt) <strong>of</strong> 3000 cumec had been<br />
assumed during computation <strong>of</strong> design flood by<br />
deterministic approach. The <strong>Nalo</strong> H.E. Project is located<br />
upstream <strong>of</strong> this dam site. Catchments <strong>of</strong> both the projects<br />
can be considered as hydro-meteorologically<br />
homogeneous. Therefore, it seems logical to transpose the<br />
design flood value <strong>of</strong> Subansiri Upper dam site to<br />
proposed dam site. This transposition has been done by<br />
Dicken’s formula using a conversion factor <strong>of</strong> 0.616 at<br />
proposed dam site. The design flood based on 1-day PMF<br />
and 2-day PMF at Subansiri Upper dam site thus<br />
computed as 10535 cumec and 12374 cumec respectively.<br />
A comparative study <strong>of</strong> flood peak computed by various methods is placed<br />
as Table-5.3.<br />
45
TABLE- 5.3<br />
FLOOD COMPUTED BY VARIOUS METHODS<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
S.No. Method Flood Peak (cumec)<br />
1 Dickens Formula 8344<br />
2 Fuller’s Formula 7487<br />
3 Ali Nawaz Jung Formula 10211<br />
4 Transposition <strong>of</strong> 2-day PMF on the<br />
basis <strong>of</strong> Dickens formula.<br />
5 Transposition <strong>of</strong> 1-day PMF on the<br />
basis <strong>of</strong> Dickens formula.<br />
12374<br />
10535<br />
Based on above mentioned studies summarized in Table-5.3, for prefeasibility<br />
stage study, a design flood <strong>of</strong> 12300 cumec at dam site <strong>of</strong> the<br />
proposed project has been recommended.<br />
It is worth mentioning here that although deterministic approach <strong>of</strong> design<br />
flood computation has not been used in the present study for <strong>Nalo</strong> sub<br />
basin, however, this approach has been used partially, as the design flood<br />
at Subansiri Upper dam site had been computed by this method only. The<br />
detail <strong>of</strong> design flood study may be referred in feasibility report <strong>of</strong> Subansiri<br />
Upper Project.<br />
On availability <strong>of</strong> more data/information, design flood need be estimated by<br />
deterministic approach using unit hydrograph technique and probabilistic<br />
approach using flood frequency analysis in feasibility stage/DPR stage.<br />
46
5.5 RESERVOIR SEDIMENTATION<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
As per compendium on silting <strong>of</strong> reservoirs in India, the sediment rate<br />
varies from 0.05658 to 0.2785 Ham/Sq.km/year for Indus, Ganga and<br />
Brahmaputra basin.<br />
An attempt has been made for an approximate assessment based on<br />
sediment yield rate <strong>of</strong> some <strong>of</strong> the North bank tributaries, which are flowing<br />
through Arunachal Pradesh and where sediment rates were earlier worked<br />
out for designing respective projects. All these tributaries have nearly<br />
similar topographical, physiographical, geological and soil vegetation cover<br />
characteristics. The values worked out are as below (Including bed load):<br />
(a) River Siang at Passighat =0.055 ham/sq.km/year<br />
(b) River Ranganadi at Yazali Dam site =0.074 ham/sq.km/year<br />
(c) River Debang at Munli dam site =0.100 ham/sq.km/year<br />
(adopted value)<br />
(d) River Subansiri At Chouldhowaghat =0.057 ham/sq.km/year<br />
(e) River Lohit at Mompani =0.011 ham/sq.km/year<br />
(f) River Lohit at Digerighat =0.235 ham/sq.km/year<br />
Considering all the above, for the present, a silt rate <strong>of</strong> 0.057<br />
ham/sq.km/year as calculated at Chouldhowaghat on Subansiri river may<br />
be adopted at the proposed dam site <strong>of</strong> <strong>Nalo</strong> H.E. Scheme.<br />
Detailed reservoir sedimentation study needs be done during feasibility<br />
stage with more observed data at the proposed site using a suitable<br />
method.<br />
47
5.6 RECOMMENDATIONS FOR FUTURE STUDIES<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
The following are the improvements suggested for feasibility/DPR stage<br />
study:<br />
• Proper raingauge network along with Gauge-discharge-sediment<br />
observation sites on Subansiri river near proposed dam site need<br />
be established before taking up preparation <strong>of</strong> feasibility report<br />
/DPR.<br />
• After establishing gauge and discharge site on Subansiri river<br />
with proper raingauge network in Subansiri Upper basin, detailed<br />
water availability study need be conducted in feasibility/DPR<br />
stage.<br />
• The reservoir elevation-area-capacity curve need be revised after<br />
availability <strong>of</strong> reservoir cross-sections or 1:15000 scale contour<br />
maps in feasibility/DPR stage study.<br />
• On availability <strong>of</strong> more data/information, design flood need be<br />
estimated by deterministic approach using unit hydrograph<br />
technique and probabilistic approach using flood frequency<br />
analysis in feasibility/DPR stage.<br />
• Detailed reservoir sedimentation study need be done during<br />
feasibility/DPR stage with observed data on Subansiri river at the<br />
proposed dam site using a suitable method.<br />
The observations <strong>of</strong> CWC along with reply <strong>of</strong> NHPC have been<br />
enclosed as Annexure 5.4 and need to be referred during feasibility/<br />
DPR stage.<br />
48
Elevation<br />
(metre)<br />
Reservoir<br />
Area (ha)<br />
Reservoir<br />
Capacity<br />
(Mcum)<br />
660 0.00 0.00<br />
680 79.18 5.28<br />
720 185.78 56.78<br />
760 266.96 146.84<br />
800 401.36 279.59<br />
-----> Elevation (m)<br />
Figure 5.1<br />
RESERVOIR ELEVATION AREA CAPACITY CURVE<br />
800<br />
780<br />
760<br />
740<br />
720<br />
700<br />
680<br />
280<br />
260<br />
240<br />
Capacity<br />
Curve<br />
220<br />
200<br />
180<br />
Area (Ha)<br />
120<br />
Area Curve<br />
100<br />
Note : This curve is prepared from 1:50000 scale<br />
toposheets and is applicable for pre-feasibility stage only.<br />
80<br />
60<br />
40<br />
20<br />
0<br />
800<br />
780<br />
760<br />
740<br />
720<br />
700<br />
680<br />
49<br />
-----> Elevation (m)
CHAPTER-VI<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 X 90 MW)<br />
CONCEPTUAL LAYOUT & PLANNING<br />
6.1 FINALIZATION OF CONCEPTUAL LAYOUT<br />
6.1.1 General<br />
<strong>Nalo</strong> and Dengser HE Projects are replacement Schemes in Subansiri<br />
Basin to exploit unutilized the head available between Naba and Upper<br />
Subansiri HE schemes and cover shortfall in the number <strong>of</strong> schemes<br />
allocated to NHPC, due to,- a) Combining <strong>of</strong> Kurung stage-I and Kurung<br />
stage-II HE Projects and b) Hegio HE Scheme (Annexure 2.1).<br />
6.1.2 NHPC PROPOSAL<br />
Based on the topographical input (SOI Toposheet No. 82 H/15 in 1 in<br />
50,000 Scale), the NHPC had developed certain layouts. These were also<br />
examined in the field. Based on topography, geology and parameters <strong>of</strong> u/s<br />
and d/s projects in the cascade, layout <strong>of</strong> <strong>Nalo</strong> H.E. Project has been<br />
finalised. It is proposed to locate diversion structure on river Subansiri<br />
where the river bed level is EL 660 m with FRL at EL 765 m. NHPC has<br />
been advised to keep the FRL <strong>of</strong> the scheme taking into account the tail<br />
water level <strong>of</strong> the upstream Naba HE Project. River bed level at power<br />
house site (tailrace outfall) <strong>of</strong> <strong>Nalo</strong> HE scheme has been proposed as<br />
EL635 m, keeping in view the FRL <strong>of</strong> the downstream project i.e. Dengser<br />
HE Project (EL 630 m). The length <strong>of</strong> water conductor system would be<br />
3.75 km. Conceptual layout <strong>of</strong> the project proposed by NHPC was vetted by<br />
CEA (Annexure 2.2) and NHPC has been advised to proceed with<br />
preparation <strong>of</strong> PFR <strong>of</strong> <strong>Nalo</strong> HE Project as proposed by them.<br />
50
ALTERNATIVE STUDIES<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 X 90 MW)<br />
Subsequent to vetting <strong>of</strong> project parameters by CEA, the project layout/<br />
parameters have been finalized considering the proposed Naba HE Project<br />
located on upstream and Dengser HE Project located in downstream as a<br />
part <strong>of</strong> the cascade development over river Subansiri.<br />
a) Location <strong>of</strong> Dam axis<br />
Alternative dam site namely alternative-1, alternative-2 and alternative-3<br />
located 3.1 km d/s, 0.8 km d/s and 1.6 km u/s <strong>of</strong> Ledi Ishi nallah have been<br />
considered (location as indicated on Plate 6.1). At these locations the river<br />
bed level is about EL625 m, EL642 m and EL 660 m respectively. Taking<br />
into account topographical, geological conditions and layout <strong>of</strong> the project,<br />
the dam axis (alt- 3) prima facie has been found to be preferable and as<br />
such adopted for PFR preparation. Needless to mention that during detailed<br />
investigation for DPR preparation location <strong>of</strong> dam axis shall need to be<br />
reviewed.<br />
b) Location <strong>of</strong> <strong>Power</strong> house and layout <strong>of</strong> water conductor system<br />
Alternative <strong>of</strong> laying water conductor system on left as well as right bank <strong>of</strong><br />
the river were examined. The length <strong>of</strong> water conductor system on left<br />
bank works out to be slightly less, in comparison to its length on right bank.<br />
However, the existing approach road to project is on right bank.<br />
Accordingly, water conductor system is laid on right bank to facilitate taking<br />
up <strong>of</strong> construction activity.<br />
As per topography from SOI Toposheet No. 82 H/15 (1 in 50,000 Scale)<br />
surface power house has been proposed. However, it may be mentioned<br />
that based on the topographical and geological data collected during<br />
feasibility /DPR stage, if required, above arrangements shall be reviewed.<br />
51
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 X 90 MW)<br />
Based on topographical details (SOI toposheet no.82 H/15 in 1 in 50,000<br />
scale) and geological details project layout has been developed.<br />
Various components <strong>of</strong> the project are:<br />
a) River diversion works comprising <strong>of</strong> 2 nos 10.75 m diameter<br />
horseshoe shaped diversion tunnel with u/s and d/s c<strong>of</strong>ferdams.<br />
b) Concrete gravity dam.<br />
c) Water conductor system consisting <strong>of</strong><br />
i) Intake structure<br />
ii) 4 nos 300m x 17m x 25m Desilting chamber.<br />
iii) 2 nos 7.5 m diameter horseshoe shaped Head Race<br />
Tunnel.<br />
iv) 2 nos 20 m diameter Surge Shaft.<br />
v) 2 nos 6.25 m diameter steel lined Pressure Shaft each<br />
feeding two units.<br />
vi) 60 m wide Tailrace channel.<br />
d) Surface power house.<br />
e) Switch yard 80 m x 160 m.<br />
Proposed General Layout plan and Longitudinal section through water<br />
conductor system is enclosed as Plate-6.1 & Plate-6.2 respectively.<br />
52
6.2 PRELIMINARY DESIGN FEATURES<br />
6.2.1 River Diversion Works<br />
6.2.1.1 Diversion Tunnel<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 X 90 MW)<br />
No G&D data for river Subansiri near proposed dam site is available.<br />
Keeping in view the hydrological studies as carried out for Subansiri Upper<br />
HE Project the diversion tunnel shall be designed for passing an assumed<br />
diversion discharge (non monsoon period) <strong>of</strong> 2600 cumec. For the<br />
construction <strong>of</strong> dam and appurtenant works, the river diversion is proposed<br />
to be carried out through 2 nos. <strong>of</strong> 10.75 m diameter concrete lined,<br />
horseshoe shaped diversion tunnel located on the left bank <strong>of</strong> the river. The<br />
length <strong>of</strong> diversion tunnels shall be about 650/800 m.<br />
6.2.1.2 C<strong>of</strong>fer Dam<br />
To facilitate river diversion, upstream and downstream c<strong>of</strong>ferdams with a<br />
central impervious core shall be provided. These c<strong>of</strong>fer dams shall be<br />
located about 100 m u/s and 250 m d/s <strong>of</strong> the proposed dam axis. The<br />
height <strong>of</strong> u/s and d/s c<strong>of</strong>fer dams shall be 28 m and 14 m respectively. As<br />
the diversion scheme has been designed to cater for non-monsoon flood,<br />
c<strong>of</strong>ferdams may get damaged during monsoon period and as such, shall<br />
require rebuilding before undertaking works in subsequent working season.<br />
6.2.2 Dam<br />
6.2.2.1 Dam Location<br />
Based on the topography, the dam axis has been proposed with river bed<br />
level as EL +660 m.<br />
53
6.2.2.2 Type <strong>of</strong> Dam<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 X 90 MW)<br />
Two alternatives were considered for the diversion structure. In first<br />
alternative concrete dam having 5 nos. <strong>of</strong> lower level orifice type spillway<br />
with a size <strong>of</strong> 9.75 m x 11.5 m. In addition 2 nos. <strong>of</strong> Upper level spillways<br />
one on either side <strong>of</strong> lower spillway a size <strong>of</strong> 9.75 m x 11.5 m has was<br />
considered. In second alternative, Rockfill dam with side spillway on right<br />
abutment with d/s chute (with same size and number <strong>of</strong> openings as in first<br />
alternative). Provision <strong>of</strong> spillway on right bank resulted in high quantities <strong>of</strong><br />
excavation along with high cut slopes. Further it necessitated provision <strong>of</strong><br />
50-55 m high retaining wall or cellular wall to support the rock fill material.<br />
Keeping above in view first alternative was found to be more favourable.<br />
The IS code stipulates consideration <strong>of</strong> 1 in 100 year monsoon flood for<br />
diversion in case <strong>of</strong> embankment dam and 1 in 25 years non-monsoon<br />
flood for concrete dam. The same also favours provision <strong>of</strong> concrete dam.<br />
In view <strong>of</strong> above pre-feasibility <strong>of</strong> the project has been examined with<br />
concrete gravity dam. However, it may be mentioned that based on the<br />
topographical and geological data collected during feasibility stage, if<br />
required, type <strong>of</strong> the dam and its height shall be reviewed.<br />
6.2.2.3 Fixation <strong>of</strong> FRL and MDDL<br />
The bed level <strong>of</strong> tailrace outfall <strong>of</strong> proposed Naba H.E. Project located<br />
upstream is EL ± 770 , keeping the difference <strong>of</strong> about 5 m between tailrace<br />
outfall bed level <strong>of</strong> upstream project & FRL , the FRL for <strong>Nalo</strong> project has<br />
been proposed as EL 765 m. Needless to mention that during FR/DPR<br />
stage considering the finally adopted parameters <strong>of</strong> upstream Naba H.E.<br />
Project, FRL <strong>of</strong> <strong>Nalo</strong> H.E. Project shall need to be optimised to minimise<br />
54
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 X 90 MW)<br />
loss <strong>of</strong> head. MDDL has been fixed at EL 745 m considering proposed<br />
power intake level and power potential studies.<br />
6.2.2.4 Dam Arrangement<br />
The proposed dam is concrete gravity dam across the river with dam top at<br />
EL 770 m. The deepest foundation level has been assumed as EL 645 m<br />
i.e. 15 m below the river bed level (overburden and weathered rock). The<br />
dam is divided in blocks <strong>of</strong> 15.0/18.0 m width each. The central 7 blocks<br />
shall be overflow/spillway blocks <strong>of</strong> 15.0/18.0 m width flanked by nonoverflow<br />
blocks on either side <strong>of</strong> 15.0 m each.<br />
Spillway<br />
Spillway for dam is proposed to be designed for a probable maximum flood<br />
(PMF) <strong>of</strong> 12300 cumec. Design discharge is proposed to be passed partly<br />
through upper level and rest through lower spillway. Provision <strong>of</strong> upper level<br />
spillway shall also facilitate in reservoir operation/regulation. Five nos. <strong>of</strong><br />
lower level orifice type spillway (inclusive <strong>of</strong> 1 bay as emergency) is<br />
proposed with crest at EL 715 m and spillway opening size 9.75 m x 11.5<br />
m. In addition two nos <strong>of</strong> Upper level spillways one on either side <strong>of</strong> lower<br />
spillway with crest at EL 753.5 m and opening <strong>of</strong> 9.75 m x 11.5 m has been<br />
proposed. Total length <strong>of</strong> spillway structure is 120 m.<br />
Non Overflow Blocks<br />
The non-overflow blocks have been provided with top width <strong>of</strong> 10 m and<br />
downstream slope <strong>of</strong> 1.1 H: 1V. An upstream slope <strong>of</strong> 1H: 4V has been<br />
provided below the level <strong>of</strong> EL 750 m.<br />
Proposed layout <strong>of</strong> dam area, upstream elevation & cross sections <strong>of</strong> dam<br />
are enclosed as Plate 6.3, Plate 6.4 and Plate 6.5.<br />
55
6.2.2.5 Energy Dissipation Arrangement<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 X 90 MW)<br />
A ski-jump type energy dissipation arrangement has been provided<br />
downstream <strong>of</strong> spillway with flip bucket having lip angle <strong>of</strong> 30 0 . It may be<br />
mentioned that based on stage- discharge curve at dam site developed at<br />
DPR stage, the lip level <strong>of</strong> spillway bucket will be kept above maximum tail<br />
water level. A preformed plunge pool <strong>of</strong> size 100 m (L) x 120 m (B) has<br />
been provided.<br />
6.2.3 Water Conductor System<br />
6.2.3.1 Head Race Tunnel Intake<br />
The water is led to 2 nos intake tunnel through intake structures with invert<br />
at EL 725 m. The invert has been kept 10 m above the lower spillway crest<br />
to minimize silt entry in water conductor system. 2 nos Intake shall be<br />
provided with gate opening <strong>of</strong> 7.5 m x 8.5 m. An inclined type trash rack<br />
structure is proposed at the entrance <strong>of</strong> the intake structure with a trash<br />
rack cleaning machine.<br />
6.2.3.2 Desilting Chamber<br />
In order to remove particle having size more than 0.2mm, desilting<br />
chamber has been proposed. Desilting chamber shall have four chambers<br />
each <strong>of</strong> size 300 m (L) X 17 m (W) X 25 m (H). 2 nos <strong>of</strong> 8.5 m dia intake<br />
tunnel about 250/350 m long have been proposed between HRT intake<br />
structure and desilting chamber. The 2 nos intake tunnel bifurcates into four<br />
6.0 m dia feeder tunnel feeding each desilting chamber. Tunnel <strong>of</strong> size<br />
5.3 m dia has been provided after each desilting chamber subsequently<br />
combining to two HRT.<br />
56
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 X 90 MW)<br />
For flushing out <strong>of</strong> accumulated silt, each desilting chamber has been<br />
provided with silt flushing duct <strong>of</strong> size 2.0 m (W) X2.0m (H).Two silt flushing<br />
duct combines to one SFT <strong>of</strong> size 3.75 m dia. Thus, two SFT have been<br />
proposed.<br />
6.2.3.3 Head Race Tunnel<br />
2 nos <strong>of</strong> 7.5 m diameter horseshoe shaped headrace tunnel has been<br />
proposed on the right bank <strong>of</strong> the river. The length <strong>of</strong> the tunnel shall be<br />
about 2.5/2.6 Km. One 6.5 m (D shaped) intermediate adit about 300 m in<br />
length has been proposed to facilitate construction <strong>of</strong> HRT.<br />
Rock bolts, shotcrete with wire mesh has been proposed as tunnel support<br />
system. Provision <strong>of</strong> steel rib support has also been kept to take care <strong>of</strong><br />
poor rock strata wherever encountered. The tunnel shall be 600 mm thick<br />
concrete lined.<br />
6.2.3.4 Surge Shaft<br />
2 nos <strong>of</strong> 20 m diameter and 90 m high circular restricted orifice type<br />
concrete lined surge shaft with gate has been proposed.<br />
Rock bolts, shotcrete with wire mesh has been proposed as shaft support<br />
system. Surge Shaft shall be concrete lined (1000 mm thick).<br />
6.2.3.5 Pressure Shaft<br />
Downstream <strong>of</strong> Surge Shafts, 2 nos <strong>of</strong> 6.25 m diameter steel lined pressure<br />
shaft with 82 m vertical drop has been proposed. The centerline elevation <strong>of</strong><br />
lower horizontal portion has been kept at EL 633 m i.e. center line <strong>of</strong><br />
turbine. After horizontal portion at bottom, each pressure shaft divides in<br />
57
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 X 90 MW)<br />
two nos 4.25 m dia penstock suitably connected to main inlet valves to feed<br />
each unit <strong>of</strong> powerhouse.<br />
6.2.3.6 Draft Tube and Tail Race Channel<br />
The water from turbine shall be discharged back to river through draft tubes<br />
and tailrace channel. 2 nos <strong>of</strong> 5.0 m (W) x 4.3 m (H) draft tube opening for<br />
each unit shall be provided. After the draft tube gates, discharge from four<br />
units shall be led to 60 m wide concrete lined tail race channel about 50m<br />
long.<br />
Proposed cross sections <strong>of</strong> Water Conductor System are enclosed as<br />
Plate 6.6.<br />
6.2.4 <strong>Power</strong> House<br />
Based on topography a surface powerhouse has been proposed. It may be<br />
mentioned that the location and type <strong>of</strong> power house shown in PFR is<br />
indicative only and underground power house, if necessary, may be<br />
considered during F.R. / D.P.R. stage based on collected detailed<br />
topography and geological data.<br />
6.2.4.1 <strong>Power</strong> House Building<br />
A surface powerhouse has been proposed to house four units <strong>of</strong> 90 MW<br />
each. The size <strong>of</strong> power house ( machine hall + service bay ) will be<br />
22m (W) x 103 m (L) x 47m (H) with unit spacing <strong>of</strong> 19 m. Control block<br />
has been proposed on upstream <strong>of</strong> the machine hall. The transformers are<br />
proposed to be kept on draft tube gate deck on downstream <strong>of</strong> the machine<br />
hall.<br />
58
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 X 90 MW)<br />
Proposed layout and cross section <strong>of</strong> <strong>Power</strong> House are enclosed as<br />
Plate 6.7 & 6.8.<br />
6.2.5 Switch Yard<br />
Switch yard is proposed on right bank. The size <strong>of</strong> switch yard will be 80 m<br />
(W) x 160 m (L).<br />
6.2.6 Hydro-Mechanical Equipment<br />
Following hydro-mechanical equipment have been envisaged for <strong>Nalo</strong><br />
Hydroelectric Project.<br />
6.2.6.1 Diversion Tunnel Gate and Hoist<br />
After the construction <strong>of</strong> the dam, for the purpose <strong>of</strong> plugging the diversion<br />
tunnel, four nos. (two nos. for each tunnel) fixed wheel type gates will be<br />
provided at the inlet <strong>of</strong> the tunnel. The gates shall be operated by means <strong>of</strong><br />
electrically operated rope drum hoists located on the hoist platform installed<br />
over the trestles above deck level. The gate is meant for one time closure,<br />
just before plugging <strong>of</strong> the tunnel.<br />
6.2.6.2 Lower Spillway Radial Gates, Hoists, Bulkheads and Gantry<br />
Crane<br />
Five numbers submerged type radial gates shall be provided to regulate the<br />
water level in the reservoir. Each gate shall be operated by means <strong>of</strong><br />
suitable capacity hydraulic hoist comprising <strong>of</strong> a power pack and two<br />
cylinders one on each end <strong>of</strong> the gate.<br />
59
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 X 90 MW)<br />
One trolley mounted mobile gasoline engine operated power pack capable<br />
<strong>of</strong> operating one gate at 25% <strong>of</strong> the normal rated speed is envisaged for<br />
emergency operation <strong>of</strong> spillway radial gates.<br />
One portable oil filter unit for filtration, dehydration & degasification <strong>of</strong><br />
hydraulic oil is also being provided.<br />
One number Fixed wheel type bulkhead gate fabricated in two units has<br />
been envisaged to cater to the maintenance requirement <strong>of</strong> five numbers<br />
spillway radial gates. The bulkhead gate shall be able to be lowered under<br />
unbalanced / emergency / flowing water condition corresponding to MDDL<br />
by means <strong>of</strong> a suitable Capacity Gantry crane with the help <strong>of</strong> lifting beam.<br />
6.2.6.3 Upper Spillway Radial Gates, Spillway Stoplog & Hoists<br />
Two numbers crest type radial gates shall be provided to control the<br />
discharge through the gated portion <strong>of</strong> the spillway. Each gate shall be<br />
operated by means <strong>of</strong> suitable capacity hydraulic hoist comprising <strong>of</strong> a<br />
power pack and two cylinders one on each end <strong>of</strong> the gate.<br />
Two numbers grooves with required embedded parts shall be<br />
provided in the upstream <strong>of</strong> upper spillway radial gate for the<br />
maintenance <strong>of</strong> radial gates. The bulkhead gate provided for the<br />
maintenance <strong>of</strong> lower spillway radial gates will be used for the<br />
maintenance <strong>of</strong> upper spillway radial gates also.<br />
6.2.6.4 Trash Rack and Trash Rack Cleaning Machine<br />
Upstream face <strong>of</strong> each intake shall be provided with the trash rack screen,<br />
which will be cleaned by means <strong>of</strong> a trash rack-cleaning machine.<br />
60
6.2.6.5 Intake Gate and Rope Drum Hoists<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 X 90 MW)<br />
Two numbers fixed wheel type gates shall be provided just downstream <strong>of</strong><br />
the bell mouth <strong>of</strong> the intake tunnels. The intake gates shall be lowered /<br />
raised under unbalanced / flowing water condition corresponding to FRL by<br />
means <strong>of</strong> suitable capacity electrically operated rope drum hoists.<br />
6.2.6.6 Desilting Chamber Inlet, Outlet Gates & Hoists<br />
Four numbers Fixed Wheel type gates shall be provided at the inlet <strong>of</strong><br />
desilting chambers for the maintenance requirement <strong>of</strong> desilting chambers.<br />
The gates shall be lowered / raised under unbalanced / flowing water<br />
condition corresponding to FRL by means <strong>of</strong> suitable capacity electrically<br />
operated rope drum hoists.<br />
Two numbers slide type gates shall be provided at the outlet <strong>of</strong> desilting<br />
chambers to isolate the chambers for the maintenance requirements. The<br />
gate shall be lowered / raised under balanced head condition by means <strong>of</strong><br />
suitable capacity EOT Crane with the help <strong>of</strong> lifting beam.<br />
6.2.6.7 Silt Flushing Tunnel Gates & Hoists<br />
In four silt-flushing tunnels, each tunnel is provided with a set <strong>of</strong> two slide<br />
(Emergency & Service) gates for regulating the discharge through flushing<br />
tunnels. Both the (Emergency & Service) gates shall be operated by means<br />
<strong>of</strong> hydraulic hoists comprising <strong>of</strong> individual double acting cylinder and a<br />
common power pack. The gate grooves are provided with bonnet structures<br />
embedded in the concrete and a watertight bonnet cover at the top <strong>of</strong> the<br />
groove.<br />
61
6.2.6.8 Surge Shaft Gate<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 X 90 MW)<br />
Two numbers slide type gate shall be provided at the intake <strong>of</strong> pressure<br />
shafts. The gate shall be operated under balanced head condition by<br />
means <strong>of</strong> an electrically operated rope drum hoist.<br />
6.2.6.9 Draft Tube Gates and Gantry Crane<br />
To isolate turbines from the tail race tunnel to cater to the inspection /<br />
maintenance requirements <strong>of</strong> turbines, eight numbers Fixed Wheel type<br />
draft tube gates (two nos. for each unit) have been envisaged. The gates<br />
shall be operated under balanced head conditions by suitable capacity<br />
Gantry Crane with the help <strong>of</strong> lifting beam.<br />
6.2.6.10 Adit Inspection Gate<br />
One number adit shall be provided with manually operated hinged type gate<br />
in the concrete plug at the HRT construction to give access to the head<br />
race tunnel in the event <strong>of</strong> any inspection, repair and maintenance.<br />
6.2.6.11 Pressure Shaft Steel Liner<br />
Two nos. Pressure Shaft <strong>of</strong> dia. 6250 mm fully steel lined will take <strong>of</strong>f from<br />
downstream <strong>of</strong> steel transition <strong>of</strong> surge shaft gate to feed the turbine placed<br />
in the power house. It comprises horizontal & vertical ferrules, 2 nos.<br />
vertical bends, 2 nos. plan bends, 1 no bifurcation and branch pipes for<br />
each pressure shaft to feed four turbines.<br />
The material <strong>of</strong> Pressure Shaft liner shall conform to IS 2002 Gr. 3.<br />
However, for bifurcation material shall conform to ASTM A537 Cl. 1.<br />
6.2.6.12 Instrument and Remote Control<br />
Gates shall be provided with PLC based remote control system for Control<br />
and operation <strong>of</strong> gates and automatic control <strong>of</strong> the reservoir level.<br />
62
6.2.6.13 Diesel Generating Set<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 X 90 MW)<br />
One diesel generating set complete with all accessories, equipment,<br />
instrument and wiring will be provided for emergency operation <strong>of</strong> gates and<br />
hoists.<br />
6.3 FURTHER STUDIES REQUIRED<br />
Following are some <strong>of</strong> the studies required to be undertaken during the<br />
preparation <strong>of</strong> feasibility report / detailed project report:<br />
• Optimisation / finalisation <strong>of</strong> location <strong>of</strong> dam type and height <strong>of</strong> dam<br />
based on topographical and geological inputs<br />
• Optimisation / finalisation <strong>of</strong> layout <strong>of</strong> water conductor system based<br />
on topographical and geological inputs<br />
• Optimisation / finalisation <strong>of</strong> location and orientation <strong>of</strong> powerhouse<br />
based on topographical and geological inputs<br />
• Evaluation <strong>of</strong> engineering properties <strong>of</strong> rock mass.<br />
• Transient analysis and Model studies.<br />
• Detailed design computation to fix size <strong>of</strong> various components <strong>of</strong> the<br />
project.<br />
• Integrated reservoir operation and power potential studies <strong>of</strong> <strong>Nalo</strong> HE<br />
Project with other Subansiri Basin projects.<br />
• The observations <strong>of</strong> CWC along with reply <strong>of</strong> NHPC have been<br />
enclosed as Annexure 6.1 & 6.2 and need to be referred during<br />
Feasibility/DPR stage.<br />
63
7.0 INTRODUCTION<br />
CHAPTER - VII<br />
POWER POTENTIAL STUDIES<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
The Chapter contains the optimization <strong>of</strong> power potential <strong>of</strong> the project on<br />
the basis <strong>of</strong> the discharge data for the synthetic year June 01 to May 20<br />
(19 Years). <strong>Nalo</strong> H.E. Project is essentially a run-<strong>of</strong>-the-river scheme. The<br />
installed capacity <strong>of</strong> <strong>Nalo</strong> project has been proposed as 360 MW<br />
comprising <strong>of</strong> four units, each <strong>of</strong> 90 MW in the Surface type powerhouse.<br />
The salient features <strong>of</strong> the project are as follows: -<br />
Installed capacity = 360 MW<br />
No. & size <strong>of</strong> unit = 4 units <strong>of</strong> 90MW<br />
Type <strong>of</strong> power house = Surface type<br />
Net head = 107 meters<br />
Design discharge per unit = 93.2 cumecs<br />
Type <strong>of</strong> switchgear = Conventional<br />
Turbine type = Vertical Francis<br />
Speed <strong>of</strong> turbine = 214.3 rpm<br />
Generation voltage = 11 KV<br />
Transmission voltage = 400 KV<br />
GSU Transformer = 13 Nos., 34 MVA, 1-phase<br />
Energy generation in 90%<br />
dependable year with 95%<br />
Machine availability<br />
= 1732.99 MU<br />
64
7.1 AVAILABLE DATA<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
The <strong>Power</strong> Potential studies have been carried out based on following<br />
data<br />
a) Discharge Data<br />
b) FRL, MDDL, TWL, Head losses and Area capacity curve.<br />
c) Due to non availability <strong>of</strong> evaporation loss, evaporation loss has not<br />
been accounted for in the power potential study.<br />
7.2 DISCHARGE DATA<br />
Inflow series <strong>of</strong> 19 years i.e. 1-2 to 19-20 has been obtained and used for<br />
carrying out power potential and optimization studies. The 10- daily<br />
discharge data in cumecs for all 19 years is shown in the enclosed<br />
Table-7.1. The criterion <strong>of</strong> 90% dependable flow is applied for conducting<br />
power potential studies and inflow <strong>of</strong> same is shown in Table-7.2.<br />
7.3 FIXATION OF FULL RESERVOIR LEVEL (FRL)<br />
The FRL level has been fixed at EL 765.0m based on the consideration<br />
that the bed level <strong>of</strong> tailrace outfall for upstream proposed Naba H.E.<br />
Project is at EL 770 m .<br />
7.4 FIXATION OF MINIMUM DRAW DOWN LEVEL (MDDL)<br />
The choice <strong>of</strong> MDDL has mainly been based on firm power requirement &<br />
water cover to intake structure . The MDDL has been fixed at EL 745 m.<br />
65
7.5 FIXATION OF TAIL WATER LEVEL (TWL)<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
The fixation <strong>of</strong> tail water level <strong>of</strong> <strong>Nalo</strong> power house (i.e EL 645 m) has<br />
been considered based on the River bed level EL 635 m at proposed<br />
power house site <strong>of</strong> this project.<br />
All these values shall require to be reviewed during detail investigation <strong>of</strong><br />
the power house complex and Tail race vis-à-vis Topographical and<br />
geological features <strong>of</strong> the area.<br />
7.6 OPERATING HEAD AND HEAD LOSSES<br />
Full Reservoir Level (FRL) and Minimum Draw Down Level (MDDL) are<br />
respectively at EL 765 m and 745 m. while the average tail water level<br />
corresponding to 4 units running has been taken as EL 645 m. Head<br />
losses in the water conductor system have been taken as 5% <strong>of</strong> the gross<br />
head. The net operating head for turbines has been calculated from the<br />
following formula,<br />
Net Operating Head:<br />
= MDDL + 2/3(FRL-MDDL) - Maximum Tail Water level – Head Losses<br />
Thus, by above-mentioned formula, net operating head works out to be<br />
107.0 m.<br />
7.7 DEFINITION OF TERMS<br />
7.7.1 90% Dependable Year<br />
This is the lower decile <strong>of</strong> the series <strong>of</strong> the corresponding monthly period<br />
<strong>of</strong> the record i.e. (N+1) x 0.90th year where N is the years for which<br />
hydrological data are available. 90% dependable year comes out as 10-11<br />
as shown in the enclosed Table-7.3.<br />
66
7.7.2 Annual Design Energy<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
This is the yearly energy generated during the 90% dependable year 10-<br />
11 with 95% machine availability, which works out to 1732.99 MU as<br />
shown in Table-7.4. Further it is also mentioned that the load factor during<br />
monsoon i.e. March to November and lean period i.e. Dec. to Feb are<br />
69.60% and 15.87% respectively.<br />
7.7.3 Installed Capacity<br />
The installed capacity <strong>of</strong> <strong>Power</strong> house has been selected based on the<br />
following considerations: -<br />
• Assessment <strong>of</strong> the energy generation with various installed<br />
capacities.<br />
• Maximum utilization <strong>of</strong> the available inflow.<br />
• Incremental value <strong>of</strong> energy generation with the increased installed<br />
capacity.<br />
• Annual Load factor.<br />
The power potential study has been carried out for different installed<br />
capacities ranging from 210 MW to 660 MW with an increment <strong>of</strong> 30 MW,<br />
as shown in Table-7.5. Based on the above-mentioned parameters, the<br />
installed capacity <strong>of</strong> the power plant has been selected as 360MW<br />
(Annexure 7.1).<br />
7.7.4 Size <strong>of</strong> Generating Units<br />
The power load demand in India is increasing at a very rapid rate, and<br />
both hydro electric and thermal (including nuclear) power potential in the<br />
67
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
country are being developed not only to meet the overall requirements, but<br />
simultaneously also to provide a proper hydro and thermal power for<br />
optimum operation <strong>of</strong> the system. Keeping this in view current practice is<br />
to opt for largest size hydro units permissible within the parameters <strong>of</strong><br />
economy, operating efficiency, maintenance, optimum utilization <strong>of</strong><br />
available water, transport limitations etc. Based on above-mentioned<br />
parameters, 4 No. Units <strong>of</strong> 90 MW each have been proposed for this<br />
project.<br />
7.7.5 Annual Energy Generation<br />
The restricted energy generations in the 90% dependable year i.e. (10-11)<br />
are shown in the enclosed Table-7.4. It may be seen from this table, that<br />
the total energy generation in 90% dependable year with 95% machine<br />
availability restricted to an installed capacity <strong>of</strong> 360 MW is 1732.99 MU.<br />
The observations <strong>of</strong> CEA alongwith reply <strong>of</strong> NHPC have been enclosed as<br />
Annexure 2.3, Annexure 7.2 and Annexure 7.3 and needed to be<br />
referred during feasibility/ DPR stage. All the suggestions made by CEA<br />
have been incorporated in the report.<br />
68
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
TABLE – 7.1<br />
DISCHARGE DATA (Cumecs)<br />
Month 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-9 9-10 10-11 11-12 12-13 13-14 14-15 15-16 16-17 17-18 18-19 19-20<br />
JUNE<br />
JULY<br />
AUGUST<br />
SEPTEMBER<br />
OCTOBER<br />
NOVEMBER<br />
DECEMBER<br />
JANUARY<br />
FEBRUARY<br />
MARCH<br />
APRIL<br />
MAY<br />
1-10 492.85 566.86 272.94 268.21 476.97 209.23 295.88 1127.03 202.66 143.23 255.80 343.43 327.54 501.43 155.90 631.53 146.16 134.07 611.35<br />
11-20 857.14 725.43 434.70 505.02 746.53 228.85 347.09 1408.97 193.10 297.93 290.04 417.71 308.80 855.74 292.02 439.38 187.34 175.79 936.14<br />
21-30 1305.27 873.72 456.62 666.80 844.43 283.63 495.99 1263.24 311.32 368.86 269.85 596.81 556.71 1144.36 445.15 443.16 279.69 338.61 948.94<br />
1-10 642.67 748.03 535.77 801.11 1086.80 538.75 580.81 1474.65 891.05 607.68 413.38 708.09 489.73 712.68 975.67 385.55 316.97 397.91 1117.63<br />
11-20 1008.71 752.87 525.04 1301.60 974.83 431.36 836.73 1627.29 694.81 468.63 713.66 565.00 768.24 841.70 913.19 320.03 613.60 756.95 1354.05<br />
21-31 875.61 610.58 417.68 987.43 779.52 674.55 1027.29 2049.64 995.86 746.06 521.46 925.59 607.71 1030.23 801.43 357.19 763.45 681.22 1782.59<br />
1-10 990.15 499.87 470.11 781.31 720.45 697.44 329.93 645.81 853.55 393.01 532.10 429.79 955.77 733.12 801.15 561.85 843.94 468.63 562.16<br />
11-20 966.28 547.46 489.65 618.76 632.06 774.60 421.36 728.91 1090.48 603.00 582.10 583.84 1247.86 777.43 721.60 863.04 1120.37 433.24 628.67<br />
21-31 624.84 629.23 901.83 507.45 766.95 708.83 389.33 798.77 807.46 537.79 960.57 1032.75 794.79 735.18 631.70 941.86 1339.13 438.42 1011.12<br />
1-10 574.95 367.59 1423.58 365.24 477.05 554.09 299.74 666.84 605.27 384.55 907.31 780.26 405.31 663.69 345.59 696.98 1116.37 446.45 723.53<br />
11-20 725.34 617.64 1283.45 323.17 398.80 427.67 365.63 477.13 545.42 716.92 993.40 824.58 379.00 482.91 381.17 545.20 789.80 412.03 587.53<br />
21-30 437.75 536.53 983.64 421.49 445.86 347.33 421.67 664.97 589.60 900.82 795.28 608.04 302.19 443.45 366.70 721.23 863.18 323.88 394.87<br />
1-10 252.41 270.35 589.21 291.62 627.37 563.08 382.66 536.10 652.76 505.86 665.92 352.42 570.93 543.27 300.63 429.30 392.29 457.51 347.47<br />
11-20 445.25 259.30 404.75 409.81 625.45 510.19 201.23 578.19 279.04 269.43 252.64 392.32 248.04 276.60 225.20 263.33 427.98 458.09 348.26<br />
21-31 243.22 236.40 292.90 226.10 304.32 263.75 161.81 262.65 290.91 157.76 237.27 198.59 205.54 162.34 198.21 186.56 336.30 273.36 318.61<br />
1-10 154.91 223.85 178.19 129.01 153.15 204.63 147.70 260.49 163.35 116.17 171.35 120.75 166.01 169.90 217.98 191.76 200.53 163.46 159.44<br />
11-20 112.49 189.75 107.63 105.46 122.11 118.95 161.80 223.00 170.88 135.75 146.90 114.47 157.73 145.41 179.36 172.43 120.63 103.16 96.11<br />
21-30 121.47 109.54 120.06 97.52 104.60 103.08 146.46 146.87 106.57 95.93 133.23 93.82 116.45 104.46 124.11 130.83 83.03 89.22 95.04<br />
1-10 80.10 101.96 121.31 78.94 108.24 81.17 141.82 92.97 73.71 82.45 90.09 102.86 78.68 109.03 134.37 89.32 83.82 106.50 116.13<br />
11-20 80.60 81.21 102.45 85.90 78.99 83.11 96.78 98.39 76.61 67.08 105.53 78.77 81.56 121.67 95.40 72.83 70.56 94.59 83.30<br />
21-31 76.17 66.44 87.51 83.89 82.62 68.69 79.89 88.03 63.55 60.27 93.17 70.09 79.24 105.63 80.57 75.21 72.67 88.76 71.94<br />
1-10 82.70 70.04 82.87 66.96 69.84 51.41 91.65 80.00 50.86 46.10 107.30 53.02 63.98 110.32 61.61 58.28 72.59 75.25 65.87<br />
11-20 65.82 76.92 79.61 53.32 73.13 61.40 85.77 63.86 47.68 45.22 108.06 53.42 52.32 99.72 67.64 46.25 73.94 75.77 54.11<br />
21-31 67.86 68.77 72.38 50.25 73.57 68.10 92.70 60.14 50.06 47.07 102.18 59.21 49.68 94.81 74.32 51.48 70.10 70.33 51.58<br />
1-10 74.46 70.85 71.97 56.10 87.71 75.43 102.01 53.70 61.23 62.73 92.55 70.94 65.95 124.04 99.04 65.83 80.36 94.21 48.22<br />
11-20 83.84 80.74 69.74 50.95 90.16 70.05 76.08 49.80 77.47 49.15 93.52 52.82 51.86 77.87 96.59 72.91 57.85 102.11 48.11<br />
21-28 79.53 71.29 75.55 69.87 94.86 66.06 79.04 51.94 74.76 77.24 85.84 78.70 65.75 93.32 104.22 73.11 85.71 107.91 61.54<br />
1-10 72.29 95.63 86.05 66.63 120.95 83.16 102.20 94.52 123.68 83.06 98.90 101.03 98.65 110.06 116.98 79.04 117.17 96.33 58.93<br />
11-20 81.32 114.89 114.73 68.28 116.03 76.01 94.85 98.77 97.55 118.52 88.76 131.10 134.06 121.05 91.86 87.91 97.08 127.56 69.54<br />
21-31 73.22 133.29 146.11 75.84 94.94 72.53 120.38 86.50 99.21 110.02 101.90 131.94 114.95 105.21 89.54 125.47 84.58 161.49 77.64<br />
1-10 124.18 191.30 161.66 137.06 170.96 115.96 170.23 103.38 122.78 114.92 159.46 161.94 151.52 112.48 163.52 226.34 126.05 198.21 102.43<br />
11-20 160.16 153.45 229.57 163.26 164.60 149.15 177.55 181.23 146.29 115.16 183.86 156.26 202.57 109.47 135.66 190.61 119.85 272.33 105.79<br />
21-30 193.61 186.08 302.46 174.99 144.14 184.79 132.75 194.81 148.80 141.68 183.40 173.86 172.71 105.84 208.33 245.73 177.89 196.93 152.49<br />
1-10 240.28 189.64 352.33 241.74 189.24 311.29 298.57 219.17 192.94 298.78 323.34 201.00 217.75 244.92 253.14 252.73 189.50 313.86 198.65<br />
11-20 384.61 241.77 412.33 298.49 265.90 285.81 456.79 155.68 142.68 361.63 277.86 192.93 216.13 210.27 188.54 197.81 139.43 414.88 198.70<br />
21-31 298.90 180.15 234.00 537.33 170.64 325.53 666.27 248.61 165.53 342.53 155.95 395.08 212.03 129.10 255.06 150.85 114.02 308.28 256.03<br />
69
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Table 7.2<br />
90% DEPENDABLE YEAR FLOWS FOR POWER GENERATION<br />
MONTH / PERIOD<br />
JUN<br />
JUL<br />
AUG<br />
SEP<br />
OCT<br />
NOV<br />
DEC<br />
JAN<br />
FEB<br />
MAR<br />
APR<br />
MAY<br />
90% dependable year 10-11<br />
flows CUMECS<br />
1-10 143.23<br />
11-20 297.93<br />
21-30 368.86<br />
1-10 607.68<br />
11-20 468.63<br />
21-31 746.06<br />
1-10 393.01<br />
11-20 603.00<br />
21-31 537.79<br />
1-10 384.55<br />
11-20 716.92<br />
21-30 900.82<br />
1-10 505.86<br />
11-20 269.43<br />
21-31 157.76<br />
1-10 116.17<br />
11-20 135.75<br />
21-30 95.93<br />
1-10 82.45<br />
11-20 67.08<br />
21-31 60.27<br />
1-10 46.10<br />
11-20 45.22<br />
21-31 47.07<br />
1-10 62.73<br />
11-20 49.15<br />
21-28 77.24<br />
1-10 83.06<br />
11-20 118.52<br />
21-31 110.02<br />
1-10 114.92<br />
11-20 115.16<br />
21-30 141.68<br />
1-10 298.78<br />
11-20 361.63<br />
21-31 342.53<br />
70
Installed<br />
Capacity(MW)<br />
360<br />
Table 7.3<br />
SUMMARY SHEET<br />
Selected<br />
Head<br />
107<br />
FRL 765<br />
Design<br />
Discharge<br />
372.79<br />
MDDL 745 Head Losses 5%<br />
Sl.No. Year<br />
Total Inflow<br />
(MCM)<br />
Unrestricted<br />
Energy (MU)<br />
Energy (with<br />
95% M/C<br />
Availability)<br />
(MU)<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Overall<br />
Efficiency<br />
Machine<br />
Availability<br />
Monsoon Period<br />
Load Factor (%)<br />
(March to Nov.)<br />
92%<br />
95%<br />
Lean period<br />
Load factor<br />
(%) (Dec. to<br />
Feb.)<br />
1 8-9 14956.79 4012.14 1855.91 74.42% 19.17%<br />
2 19-20 12264.77 3290.01 1756.33 70.22% 18.09%<br />
3 1-2 11543.89 3096.64 1832.92 73.00% 20.55%<br />
4 3-4 11143.93 2989.35 1962.30 77.64% 23.00%<br />
5 14-15 10995.51 2949.53 1798.35 68.94% 27.95%<br />
6 5-6 10965.93 2941.60 1845.61 72.89% 22.53%<br />
7 17-18 10398.07 2789.27 1661.02 65.28% 19.81%<br />
8 12-13 10038.68 2692.86 1815.62 72.81% 18.39%<br />
9 11-12 9938.23 2665.92 1826.68 70.06% 26.50%<br />
10 9-10 9928.91 2663.42 1668.15 66.48% 17.06%<br />
11 4-5 9849.40 2642.09 1775.41 70.97% 17.75%<br />
12 2-3 9605.69 2576.72 1819.82 71.92% 20.49%<br />
13 13-14 9427.09 2528.81 1763.05 70.31% 17.55%<br />
14 16-17 9173.26 2460.72 1806.62 72.17% 17.98%<br />
15 15-16 9154.77 2455.76 1781.23 68.47% 24.41%<br />
16 7-8 8920.21 2392.84 1873.80 72.40% 25.49%<br />
17 6-7 8704.51 2334.97 1777.21 70.55% 18.66%<br />
18 10-11 8517.07 2284.69 1732.99 69.60% 15.87%<br />
19 18-19 8327.15 2233.75 1883.59 73.41% 24.13%<br />
71
S.<br />
NO.<br />
Table 7.3 A<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
AVAILABILITY OF UNITS IN KWH/KW FOR INCREMENTAL INSTALLATION IN<br />
90% DEPENDABLE YEAR<br />
Net Head 107.00<br />
INSTALLED<br />
CAPACITY<br />
MW<br />
ANNUAL<br />
ENERGY<br />
MU<br />
LOAD<br />
FACTOR %<br />
1 210 1259.93 68.49%<br />
2 240 1377.29 65.51%<br />
3 270 1492.29 63.09%<br />
4 300 1596.75 60.76%<br />
5 330 1692.51 58.55%<br />
6 360 1777.06 56.35%<br />
7 390 1843.51 53.96%<br />
8 420 1902.55 51.71%<br />
9 450 1961.59 49.76%<br />
10 480 2014.04 47.90%<br />
11 510 2060.73 46.13%<br />
12 540 2099.91 44.39%<br />
13 570 2136.63 42.79%<br />
14 600 2165.95 41.21%<br />
15 630 2188.27 39.65%<br />
16 660 2210.59 38.23%<br />
10-11<br />
Overall<br />
Efficiency<br />
INCREMENTAL<br />
ENERGY MU<br />
92%<br />
INCREMENTAL<br />
ENERGY<br />
KWH/KW<br />
LOAD<br />
FACTOR FOR<br />
ADDITIONAL<br />
CAPACITY %<br />
117.36 3912.00 44.66%<br />
115.01 3833.53 43.76%<br />
104.46 3481.90 39.75%<br />
95.76 3192.00 36.44%<br />
84.55 2818.29 32.17%<br />
66.45 2215.13 25.29%<br />
59.04 1968.00 22.47%<br />
59.04 1968.00 22.47%<br />
52.45 1748.41 19.96%<br />
46.68 1556.09 17.76%<br />
39.19 1306.24 14.91%<br />
36.72 1224.00 13.97%<br />
29.32 977.23 11.16%<br />
22.32 744.00 8.49%<br />
22.32 744.00 8.49%<br />
72
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Table 7.4<br />
POWER POTENTIAL IN 90% DEPENDABLE YEAR WITH 95% m/c<br />
AVAILABILITY<br />
YEAR 10-11 Live storage(Mcum)= 50.37<br />
Net Head 107.00 Restricted MW 360 Overall Efficiency 92%<br />
UNRESTRICTED UNRESTRICTED RESTRICTED ENERGY<br />
PERIOD<br />
INFLOW<br />
Mcum<br />
INFLOW<br />
cumecs<br />
POWER<br />
POTENTIAL MW<br />
ENERGY (MU) POWER RESTRICTED TO<br />
POTENTIAL 360 MW<br />
95% m/c<br />
Availability<br />
(360 MW) (MU)<br />
1-10 123.75 143.23 138.32 33.20 138.32 33.20 33.20<br />
Jun-10 11-20 257.41 297.93 287.71 69.05 287.71 69.05 69.05<br />
21-30 318.69 368.86 356.20 85.49 356.20 85.49 85.49<br />
1-10 525.04 607.68 586.84 140.84 360.00 86.40 82.08<br />
Jul-10 11-20 404.89 468.63 452.55 108.61 360.00 86.40 82.08<br />
21-31 709.06 746.06 720.47 190.20 360.00 95.04 90.29<br />
1-10 339.56 393.01 379.53 91.09 360.00 86.40 82.08<br />
Aug-10 11-20 520.99 603.00 582.32 139.76 360.00 86.40 82.08<br />
21-31 511.12 537.79 519.35 137.11 360.00 95.04 90.29<br />
1-10 332.26 384.55 371.36 89.13 360.00 86.40 82.08<br />
Sep-10 11-20 619.42 716.92 692.33 166.16 360.00 86.40 82.08<br />
21-30 778.31 900.82 869.92 208.78 360.00 86.40 82.08<br />
1-10 437.07 505.86 488.51 117.24 360.00 86.40 82.08<br />
Oct-10 11-20 232.79 269.43 260.19 62.45 260.19 62.45 62.45<br />
21-31 149.94 157.76 152.35 40.22 152.35 40.22 40.22<br />
1-10 100.37 116.17 112.18 26.92 112.18 26.92 26.92<br />
Nov-10 11-20 117.29 135.75 131.10 31.46 131.10 31.46 31.46<br />
21-30 82.88 95.93 92.64 22.23 92.64 22.23 22.23<br />
1-10 71.23 82.45 79.62 19.11 79.62 19.11 19.11<br />
Dec-10 11-20 57.96 67.08 64.78 15.55 64.78 15.55 15.55<br />
21-31 57.28 60.27 58.20 15.36 58.20 15.36 15.36<br />
1-10 39.83 46.10 44.52 10.68 44.52 10.68 10.68<br />
Jan-11 11-20 39.07 45.22 43.67 10.48 43.67 10.48 10.48<br />
21-31 44.74 47.07 45.46 12.00 45.46 12.00 12.00<br />
1-10 54.20 62.73 60.57 14.54 60.57 14.54 14.54<br />
Feb-11 11-20 42.46 49.15 47.46 11.39 47.46 11.39 11.39<br />
21-28 53.39 77.24 74.59 14.32 74.59 14.32 14.32<br />
1-10 71.76 83.06 80.21 19.25 80.21 19.25 19.25<br />
Mar-11 11-20 102.40 118.52 114.45 27.47 114.45 27.47 27.47<br />
21-31 104.57 110.02 106.25 28.05 106.25 28.05 28.05<br />
1-10 99.29 114.92 110.97 26.63 110.97 26.63 26.63<br />
Apr-11 11-20 99.50 115.16 111.21 26.69 111.21 26.69 26.69<br />
21-30 122.41 141.68 136.82 32.84 136.82 32.84 32.84<br />
1-10 258.14 298.78 288.53 69.25 288.53 69.25 69.25<br />
May-11 11-20 312.45 361.63 349.23 83.81 349.23 83.81 83.81<br />
21-31 325.54 342.53 330.78 87.33 330.78 87.33 87.33<br />
Total 8517.07 2284.69 1777.06 1732.99<br />
Annual<br />
L/F=<br />
56.35%<br />
L/F monsoon<br />
(March to Nov.)=<br />
69.60%<br />
L/F non-monsoon<br />
(Dec. to Feb.)=<br />
15.87%<br />
Total Inflow during<br />
Monsoon<br />
season(Mcum)=<br />
8056.90<br />
Total Inflow during Nonmonsoon<br />
season<br />
(Mcum)= 460.16<br />
Average <strong>Power</strong><br />
during nonmonsoon<br />
season<br />
(MW)=<br />
57.65 MWhr.= 13511.70<br />
FIRM POWER(MW) 43.67 Hrs from Live storage 37.53<br />
73
Period<br />
Net Head 107.00 Design Discharge <strong>of</strong> Unit 93.2<br />
Inflow<br />
(Cumecs)<br />
<strong>Power</strong><br />
Potential<br />
(MW)<br />
Unrestricted<br />
Energy<br />
Generation<br />
(MU)<br />
Table 7.5<br />
POWER POTENTIAL IN 90% Dependable Year<br />
Incre<br />
menta<br />
l Steps<br />
10-11<br />
30 Overall Efficiency 92%<br />
ENERGY GENERATION IN MU RESTRICTED TO VARIOUS MW<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
210 240 270 300 330 360 390 420 450 480 510 540 570 600 630 660<br />
Jun-10 1-10 143.23 138.32 33.20 33.20 33.20 33.20 33.20 33.20 33.20 33.20 33.20 33.20 33.20 33.20 33.20 33.20 33.20 33.20 33.20<br />
11-20 297.93 287.71 69.05 50.40 57.60 64.80 69.05 69.05 69.05 69.05 69.05 69.05 69.05 69.05 69.05 69.05 69.05 69.05 69.05<br />
21-30 368.86 356.20 85.49 50.40 57.60 64.80 72.00 79.20 85.49 85.49 85.49 85.49 85.49 85.49 85.49 85.49 85.49 85.49 85.49<br />
Jul-10 1-10 607.68 586.84 140.84 50.40 57.60 64.80 72.00 79.20 86.40 93.60 100.80 108.00 115.20 122.40 129.60 136.80 140.84 140.84 140.84<br />
11-20 468.63 452.55 108.61 50.40 57.60 64.80 72.00 79.20 86.40 93.60 100.80 108.00 108.61 108.61 108.61 108.61 108.61 108.61 108.61<br />
21-31 746.06 720.47 190.20 55.44 63.36 71.28 79.20 87.12 95.04 102.96 110.88 118.80 126.72 134.64 142.56 150.48 158.40 166.32 174.24<br />
Aug-10 1-10 393.01 379.53 91.09 50.40 57.60 64.80 72.00 79.20 86.40 91.09 91.09 91.09 91.09 91.09 91.09 91.09 91.09 91.09 91.09<br />
11-20 603.00 582.32 139.76 50.40 57.60 64.80 72.00 79.20 86.40 93.60 100.80 108.00 115.20 122.40 129.60 136.80 139.76 139.76 139.76<br />
21-31 537.79 519.35 137.11 55.44 63.36 71.28 79.20 87.12 95.04 102.96 110.88 118.80 126.72 134.64 137.11 137.11 137.11 137.11 137.11<br />
Sep-10 1-10 384.55 371.36 89.13 50.40 57.60 64.80 72.00 79.20 86.40 89.13 89.13 89.13 89.13 89.13 89.13 89.13 89.13 89.13 89.13<br />
11-20 716.92 692.33 166.16 50.40 57.60 64.80 72.00 79.20 86.40 93.60 100.80 108.00 115.20 122.40 129.60 136.80 144.00 151.20 158.40<br />
21-30 900.82 869.92 208.78 50.40 57.60 64.80 72.00 79.20 86.40 93.60 100.80 108.00 115.20 122.40 129.60 136.80 144.00 151.20 158.40<br />
Oct-10 1-10 505.86 488.51 117.24 50.40 57.60 64.80 72.00 79.20 86.40 93.60 100.80 108.00 115.20 117.24 117.24 117.24 117.24 117.24 117.24<br />
11-20 269.43 260.19 62.45 50.40 57.60 62.45 62.45 62.45 62.45 62.45 62.45 62.45 62.45 62.45 62.45 62.45 62.45 62.45 62.45<br />
21-31 157.76 152.35 40.22 40.22 40.22 40.22 40.22 40.22 40.22 40.22 40.22 40.22 40.22 40.22 40.22 40.22 40.22 40.22 40.22<br />
Nov-10 1-10 116.17 112.18 26.92 26.92 26.92 26.92 26.92 26.92 26.92 26.92 26.92 26.92 26.92 26.92 26.92 26.92 26.92 26.92 26.92<br />
11-20 135.75 131.10 31.46 31.46 31.46 31.46 31.46 31.46 31.46 31.46 31.46 31.46 31.46 31.46 31.46 31.46 31.46 31.46 31.46<br />
21-30 95.93 92.64 22.23 22.23 22.23 22.23 22.23 22.23 22.23 22.23 22.23 22.23 22.23 22.23 22.23 22.23 22.23 22.23 22.23<br />
Dec-10 1-10 82.45 79.62 19.11 19.11 19.11 19.11 19.11 19.11 19.11 19.11 19.11 19.11 19.11 19.11 19.11 19.11 19.11 19.11 19.11<br />
11-20 67.08 64.78 15.55 15.55 15.55 15.55 15.55 15.55 15.55 15.55 15.55 15.55 15.55 15.55 15.55 15.55 15.55 15.55 15.55<br />
21-31 60.27 58.20 15.36 15.36 15.36 15.36 15.36 15.36 15.36 15.36 15.36 15.36 15.36 15.36 15.36 15.36 15.36 15.36 15.36<br />
Jan-11 1-10 46.10 44.52 10.68 10.68 10.68 10.68 10.68 10.68 10.68 10.68 10.68 10.68 10.68 10.68 10.68 10.68 10.68 10.68 10.68<br />
11-20 45.22 43.67 10.48 10.48 10.48 10.48 10.48 10.48 10.48 10.48 10.48 10.48 10.48 10.48 10.48 10.48 10.48 10.48 10.48<br />
21-31 47.07 45.46 12.00 12.00 12.00 12.00 12.00 12.00 12.00 12.00 12.00 12.00 12.00 12.00 12.00 12.00 12.00 12.00 12.00<br />
Feb-11 1-10 62.73 60.57 14.54 14.54 14.54 14.54 14.54 14.54 14.54 14.54 14.54 14.54 14.54 14.54 14.54 14.54 14.54 14.54 14.54<br />
11-20 49.15 47.46 11.39 11.39 11.39 11.39 11.39 11.39 11.39 11.39 11.39 11.39 11.39 11.39 11.39 11.39 11.39 11.39 11.39<br />
21-28 77.24 74.59 14.32 14.32 14.32 14.32 14.32 14.32 14.32 14.32 14.32 14.32 14.32 14.32 14.32 14.32 14.32 14.32 14.32<br />
Mar-11 1-10 83.06 80.21 19.25 19.25 19.25 19.25 19.25 19.25 19.25 19.25 19.25 19.25 19.25 19.25 19.25 19.25 19.25 19.25 19.25<br />
11-20 118.52 114.45 27.47 27.47 27.47 27.47 27.47 27.47 27.47 27.47 27.47 27.47 27.47 27.47 27.47 27.47 27.47 27.47 27.47<br />
21-31 110.02 106.25 28.05 28.05 28.05 28.05 28.05 28.05 28.05 28.05 28.05 28.05 28.05 28.05 28.05 28.05 28.05 28.05 28.05<br />
Apr-11 1-10 114.92 110.97 26.63 26.63 26.63 26.63 26.63 26.63 26.63 26.63 26.63 26.63 26.63 26.63 26.63 26.63 26.63 26.63 26.63<br />
11-20 115.16 111.21 26.69 26.69 26.69 26.69 26.69 26.69 26.69 26.69 26.69 26.69 26.69 26.69 26.69 26.69 26.69 26.69 26.69<br />
21-30 141.68 136.82 32.84 32.84 32.84 32.84 32.84 32.84 32.84 32.84 32.84 32.84 32.84 32.84 32.84 32.84 32.84 32.84 32.84<br />
May-11 1-10 298.78 288.53 69.25 50.40 57.60 64.80 69.25 69.25 69.25 69.25 69.25 69.25 69.25 69.25 69.25 69.25 69.25 69.25 69.25<br />
11-20 361.63 349.23 83.81 50.40 57.60 64.80 72.00 79.20 83.81 83.81 83.81 83.81 83.81 83.81 83.81 83.81 83.81 83.81 83.81<br />
21-31 342.53 330.78 87.33 55.44 63.36 71.28 79.20 87.12 87.33 87.33 87.33 87.33 87.33 87.33 87.33 87.33 87.33 87.33 87.33<br />
2284.69<br />
1259.<br />
93<br />
1377.<br />
29<br />
1492.<br />
29<br />
1596.<br />
75<br />
1692.<br />
51<br />
1777.<br />
06<br />
1843.51 1902.55 1961.59 2014.04 2060.73 2099.91 2136.63 2165.95 2188.27 2210.59<br />
74
Installed<br />
Capacity<br />
POWER POTENTIAL STUDY FOR YEAR<br />
1-2<br />
360 Net Head 107 Efficiency 92%<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Month DISCHARGE<br />
RESTRICTED RESTRICTED<br />
DISCHARGEUNRESTRICTEDUNRESTRICTED<br />
95% m/c<br />
POWER ENERGY<br />
( MCum) ( Qmecs) POWER ( MW) ENERGY ( MU)<br />
Availability<br />
( 360MW) ( MU)<br />
1-10 425.82 492.85 475.94 114.23 360 86.40 82.08<br />
June-01 11-20 740.57 857.14 827.73 198.66 360 86.40 82.08<br />
21-30 1127.75 1305.27 1260.49 302.52 360 86.40 82.08<br />
1-10 555.26 642.67 620.62 148.95 360 86.40 82.08<br />
July-01 11-20 871.52 1008.71 974.10 233.79 360 86.40 82.08<br />
21-31 832.18 875.61 845.58 223.23 360 95.04 90.29<br />
1-10 855.49 990.15 956.18 229.48 360 86.40 82.08<br />
Aug-01 11-20 834.86 966.28 933.13 223.95 360 86.40 82.08<br />
21-31 593.85 624.84 603.41 159.30 360 95.04 90.29<br />
1-10 496.75 574.95 555.22 133.25 360 86.40 82.08<br />
Sep-01 11-20 626.69 725.34 700.46 168.11 360 86.40 82.08<br />
21-30 378.22 437.75 422.73 101.46 360 86.40 82.08<br />
1-10 218.08 252.41 243.75 58.50 244 58.50 58.50<br />
Oct-01 11-20 384.70 445.25 429.98 103.19 360 86.40 82.08<br />
21-31 231.16 243.22 234.88 62.01 235 62.01 62.01<br />
1-10 133.84 154.91 149.59 35.90 150 35.90 35.90<br />
Nov-01 11-20 97.19 112.49 108.63 26.07 109 26.07 26.07<br />
21-30 104.95 121.47 117.30 28.15 117 28.15 28.15<br />
1-10 69.20 80.10 77.35 18.56 77 18.56 18.56<br />
Dec-01 11-20 69.64 80.60 77.84 18.68 78 18.68 18.68<br />
21-31 72.39 76.17 73.56 19.42 74 19.42 19.42<br />
1-10 71.46 82.70 79.87 19.17 80 19.17 19.17<br />
Jan-02 11-20 56.86 65.82 63.56 15.25 64 15.25 15.25<br />
21-31 64.49 67.86 65.53 17.30 66 17.30 17.30<br />
1-10 64.33 74.46 71.90 17.26 72 17.26 17.26<br />
Feb-02 11-20 72.44 83.84 80.97 19.43 81 19.43 19.43<br />
21-28 54.97 79.53 76.80 14.75 77 14.75 14.75<br />
1-10 62.46 72.29 69.81 16.75 70 16.75 16.75<br />
Mar-02 11-20 70.26 81.32 78.53 18.85 79 18.85 18.85<br />
21-31 69.58 73.22 70.70 18.67 71 18.67 18.67<br />
1-10 107.29 124.18 119.92 28.78 120 28.78 28.78<br />
Apr-02 11-20 138.38 160.16 154.66 37.12 155 37.12 37.12<br />
21-30 167.28 193.61 186.97 44.87 187 44.87 44.87<br />
1-10 207.60 240.28 232.04 55.69 232 55.69 55.69<br />
May-02 11-20 332.30 384.61 371.41 89.14 360 86.40 82.08<br />
21-31 284.07 298.90 288.65 76.20 289 76.20 76.20<br />
Total 11543.89 3096.64 1894.26 1832.92<br />
Annual<br />
L/F 60.07%<br />
L/F monsoon<br />
(March to Nov.)<br />
73.00%<br />
L/F non-monsoon (Dec<br />
to Feb.)<br />
20.55%<br />
75
Installed<br />
Capacity<br />
POWER POTENTIAL STUDY FOR YEAR<br />
2-3<br />
360 Net Head 107 Efficiency 92%<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Month DISCHARGE<br />
RESTRICTED RESTRICTED<br />
DISCHARGE UNRESTRICTED UNRESTRICTED<br />
95% m/c<br />
POWER ENERGY<br />
( MCum) ( Qmecs) POWER ( MW) ENERGY ( MU)<br />
Availability<br />
( 360MW) ( MU)<br />
1-10<br />
June-<br />
11-20<br />
02<br />
21-30<br />
489.77<br />
626.77<br />
754.90<br />
566.86<br />
725.43<br />
873.72<br />
547.42<br />
700.55<br />
843.75<br />
131.38<br />
168.13<br />
202.50<br />
360<br />
360<br />
360<br />
86.40<br />
86.40<br />
86.40<br />
82.08<br />
82.08<br />
82.08<br />
1-10 646.29 748.03 722.37 173.37 360 86.40 82.08<br />
July-0211-20<br />
650.48 752.87 727.04 174.49 360 86.40 82.08<br />
21-31 580.30 610.58 589.64 155.66 360 95.04 90.29<br />
1-10 431.89 499.87 482.73 115.85 360 86.40 82.08<br />
Aug-0211-20<br />
473.00 547.46 528.68 126.88 360 86.40 82.08<br />
21-31 598.02 629.23 607.65 160.42 360 95.04 90.29<br />
1-10 317.60 367.59 354.98 85.20 355 85.20 85.20<br />
Sep-0211-20<br />
533.64 617.64 596.46 143.15 360 86.40 82.08<br />
21-30 463.57 536.53 518.13 124.35 360 86.40 82.08<br />
1-10 233.58 270.35 261.08 62.66 261 62.66 62.66<br />
Oct-02 11-20 224.04 259.30 250.41 60.10 250 60.10 60.10<br />
21-31 224.68 236.40 228.29 60.27 228 60.27 60.27<br />
1-10 193.40 223.85 216.17 51.88 216 51.88 51.88<br />
Nov-0211-20<br />
163.95 189.75 183.24 43.98 183 43.98 43.98<br />
21-30 94.64 109.54 105.78 25.39 106 25.39 25.39<br />
1-10 88.09 101.96 98.46 23.63 98 23.63 23.63<br />
Dec-0211-20<br />
70.17 81.21 78.43 18.82 78 18.82 18.82<br />
21-31 63.15 66.44 64.17 16.94 64 16.94 16.94<br />
1-10 60.52 70.04 67.64 16.23 68 16.23 16.23<br />
Jan-03 11-20 66.46 76.92 74.28 17.83 74 17.83 17.83<br />
21-31 65.36 68.77 66.41 17.53 66 17.53 17.53<br />
1-10 61.21 70.85 68.42 16.42 68 16.42 16.42<br />
Feb-0311-20<br />
69.76 80.74 77.97 18.71 78 18.71 18.71<br />
21-28 49.27 71.29 68.84 13.22 69 13.22 13.22<br />
1-10 82.63 95.63 92.35 22.16 92 22.16 22.16<br />
Mar-0311-20<br />
99.27 114.89 110.95 26.63 111 26.63 26.63<br />
21-31 126.68 133.29 128.72 33.98 129 33.98 33.98<br />
1-10 165.29 191.30 184.74 44.34 185 44.34 44.34<br />
Apr-03 11-20 132.58 153.45 148.18 35.56 148 35.56 35.56<br />
21-30 160.77 186.08 179.69 43.13 180 43.13 43.13<br />
1-10 163.85 189.64 183.14 43.95 183 43.95 43.95<br />
May-0311-20<br />
208.89 241.77 233.48 56.04 233 56.04 56.04<br />
21-31 171.22 180.15 173.97 45.93 174 45.93 45.93<br />
Total 9605.69 2576.72 1868.21 1819.82<br />
Annua<br />
L/F 59.24%<br />
L/F monsoon<br />
(March to Nov.)<br />
71.92%<br />
L/F non-monsoon (Dec<br />
to Feb.)<br />
20.49%<br />
76
Installed<br />
Capacity<br />
POWER POTENTIAL STUDY FOR YEAR<br />
3-4<br />
360 Net Head 107 Efficiency 92%<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Month<br />
RESTRICTED RESTRICTED<br />
DISCHARGE DISCHARGE UNRESTRICTED UNRESTRICTED<br />
95% m/c<br />
POWER ENERGY<br />
( MCum) ( Qmecs) POWER ( MW) ENERGY ( MU)<br />
Availability<br />
( 360MW) ( MU)<br />
1-10<br />
June-<br />
11-20<br />
03<br />
21-30<br />
235.82<br />
375.58<br />
394.52<br />
272.94<br />
434.70<br />
456.62<br />
263.58<br />
419.79<br />
440.95<br />
63.26<br />
100.75<br />
105.83<br />
264<br />
360<br />
360<br />
63.26<br />
86.40<br />
86.40<br />
63.26<br />
82.08<br />
82.08<br />
1-10 462.91 535.77 517.40 124.17 360 86.40 82.08<br />
July-0311-20<br />
453.63 525.04 507.03 121.69 360 86.40 82.08<br />
21-31 396.96 417.68 403.35 106.48 360 95.04 90.29<br />
1-10 406.18 470.11 453.98 108.96 360 86.40 82.08<br />
Aug-0311-20<br />
423.06 489.65 472.86 113.49 360 86.40 82.08<br />
21-31 857.10 901.83 870.90 229.92 360 95.04 90.29<br />
1-10 1229.97 1423.58 1374.74 329.94 360 86.40 82.08<br />
Sep-0311-20<br />
1108.90 1283.45 1239.43 297.46 360 86.40 82.08<br />
21-30 849.86 983.64 949.90 227.97 360 86.40 82.08<br />
1-10 509.07 589.21 569.00 136.56 360 86.40 82.08<br />
Oct-03 11-20 349.70 404.75 390.86 93.81 360 86.40 82.08<br />
21-31 278.37 292.90 282.85 74.67 283 74.67 74.67<br />
1-10 153.95 178.19 172.08 41.30 172 41.30 41.30<br />
Nov-0311-20<br />
92.99 107.63 103.94 24.95 104 24.95 24.95<br />
21-30 103.73 120.06 115.94 27.83 116 27.83 27.83<br />
1-10 104.81 121.31 117.15 28.12 117 28.12 28.12<br />
Dec-0311-20<br />
88.52 102.45 98.93 23.74 99 23.74 23.74<br />
21-31 83.17 87.51 84.51 22.31 85 22.31 22.31<br />
1-10 71.60 82.87 80.02 19.21 80 19.21 19.21<br />
Jan-04 11-20 68.79 79.61 76.88 18.45 77 18.45 18.45<br />
21-31 68.79 72.38 69.90 18.45 70 18.45 18.45<br />
1-10 62.18 71.97 69.50 16.68 70 16.68 16.68<br />
Feb-0411-20<br />
60.26 69.74 67.35 16.16 67 16.16 16.16<br />
21-29 58.75 75.55 72.96 15.76 73 15.76 15.76<br />
1-10 74.35 86.05 83.10 19.94 83 19.94 19.94<br />
Mar-0411-20<br />
99.12 114.73 110.79 26.59 111 26.59 26.59<br />
21-31 138.86 146.11 141.10 37.25 141 37.25 37.25<br />
1-10 139.67 161.66 156.11 37.47 156 37.47 37.47<br />
Apr-04 11-20 198.35 229.57 221.70 53.21 222 53.21 53.21<br />
21-30 261.33 302.46 292.08 70.10 292 70.10 70.10<br />
1-10 304.41 352.33 340.25 81.66 340 81.66 81.66<br />
May-0411-20<br />
356.25 412.33 398.19 95.56 360 86.40 82.08<br />
21-31 222.39 234.00 225.97 59.66 226 59.66 59.66<br />
Total 11143.93 2989.35 2023.64 1962.30<br />
Annua<br />
L/F 64.17%<br />
L/F monsoon<br />
(March to Nov.)<br />
77.64%<br />
L/F non-monsoon<br />
(Dec to Feb.)<br />
23.00%<br />
77
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
POWER POTENTIAL STUDY FOR YEAR<br />
4-5<br />
Installed<br />
Capacity<br />
360 Net Head 107 Efficiency 92%<br />
Month DISCHARGE<br />
RESTRICTED RESTRICTED<br />
DISCHARGE UNRESTRICTED UNRESTRICTED<br />
95% m/c<br />
POWER ENERGY<br />
( MCum) ( Qmecs) POWER ( MW) ENERGY ( MU)<br />
Availability<br />
( 360MW) ( MU)<br />
June-<br />
04<br />
1-10<br />
11-20<br />
21-30<br />
231.74<br />
436.34<br />
576.11<br />
268.21<br />
505.02<br />
666.80<br />
259.01<br />
487.70<br />
643.92<br />
62.16<br />
117.05<br />
154.54<br />
259<br />
360<br />
360<br />
62.16<br />
86.40<br />
86.40<br />
62.16<br />
82.08<br />
82.08<br />
1-10 692.16 801.11 773.63 185.67 360 86.40 82.08<br />
July-04 11-20 1124.58 1301.60 1256.95 301.67 360 86.40 82.08<br />
21-31 938.46 987.43 953.56 251.74 360 95.04 90.29<br />
1-10 675.05 781.31 754.51 181.08 360 86.40 82.08<br />
Aug-04 11-20 534.60 618.76 597.53 143.41 360 86.40 82.08<br />
21-31 482.28 507.45 490.04 129.37 360 95.04 90.29<br />
1-10 315.57 365.24 352.71 84.65 353 84.65 84.65<br />
Sep-04 11-20 279.22 323.17 312.08 74.90 312 74.90 74.90<br />
21-30 364.17 421.49 407.03 97.69 360 86.40 82.08<br />
1-10 251.96 291.62 281.62 67.59 282 67.59 67.59<br />
Oct-04 11-20 354.07 409.81 395.75 94.98 360 86.40 82.08<br />
21-31 214.89 226.10 218.35 57.64 218 57.64 57.64<br />
1-10 111.47 129.01 124.59 29.90 125 29.90 29.90<br />
Nov-04 11-20 91.12 105.46 101.84 24.44 102 24.44 24.44<br />
21-30 84.26 97.52 94.17 22.60 94 22.60 22.60<br />
1-10 68.20 78.94 76.23 18.30 76 18.30 18.30<br />
Dec-04 11-20 74.22 85.90 82.95 19.91 83 19.91 19.91<br />
21-31 79.73 83.89 81.02 21.39 81 21.39 21.39<br />
1-10 57.86 66.96 64.67 15.52 65 15.52 15.52<br />
Jan-05 11-20 46.07 53.32 51.49 12.36 51 12.36 12.36<br />
21-31 47.76 50.25 48.53 12.81 49 12.81 12.81<br />
1-10 48.47 56.10 54.17 13.00 54 13.00 13.00<br />
Feb-05 11-20 44.02 50.95 49.20 11.81 49 11.81 11.81<br />
21-28 48.30 69.87 67.48 12.96 67 12.96 12.96<br />
1-10 57.57 66.63 64.34 15.44 64 15.44 15.44<br />
Mar-05 11-20 58.99 68.28 65.93 15.82 66 15.82 15.82<br />
21-31 72.08 75.84 73.24 19.34 73 19.34 19.34<br />
1-10 118.42 137.06 132.36 31.77 132 31.77 31.77<br />
Apr-05 11-20 141.06 163.26 157.66 37.84 158 37.84 37.84<br />
21-30 151.19 174.99 168.99 40.56 169 40.56 40.56<br />
1-10 208.86 241.74 233.44 56.03 233 56.03 56.03<br />
May-05 11-20 257.90 298.49 288.25 69.18 288 69.18 69.18<br />
21-31 510.68 537.33 518.90 136.99 360 95.04 90.29<br />
Total 9849.40 2642.09 1824.23 1775.41<br />
Annual<br />
L/F 57.85%<br />
L/F monsoon<br />
(March to Nov.)<br />
70.97%<br />
L/F non-monsoon (Dec<br />
to Feb.)<br />
17.75%<br />
78
Installed<br />
Capacity<br />
POWER POTENTIAL STUDY FOR YEAR<br />
5-6<br />
360 Net Head 107 Efficiency 92%<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Month DISCHARGE<br />
RESTRICTED RESTRICTED<br />
DISCHARGE UNRESTRICTED UNRESTRICTED<br />
95% m/c<br />
POWER ENERGY<br />
( MCum) ( Qmecs) POWER ( MW) ENERGY ( MU)<br />
Availability<br />
( 360MW) ( MU)<br />
1-10 412.10 476.97 460.60 110.54 360 86.40 82.08<br />
11-20 645.00 746.53 720.92 173.02 360 86.40 82.08<br />
June-<br />
05<br />
July-05<br />
Aug-05<br />
Sep-05<br />
Oct-05<br />
Nov-05<br />
Dec-05<br />
Jan-06<br />
Feb-06<br />
Mar-06<br />
Apr-06<br />
May-06<br />
21-30 729.59 844.43 815.47 195.71 360 86.40 82.08<br />
1-10 939.00 1086.80 1049.52 251.88 360 86.40 82.08<br />
11-20 842.25 974.83 941.39 225.93 360 86.40 82.08<br />
21-31 740.86 779.52 752.78 198.73 360 95.04 90.29<br />
1-10 622.47 720.45 695.74 166.98 360 86.40 82.08<br />
11-20 546.10 632.06 610.38 146.49 360 86.40 82.08<br />
21-31 728.91 766.95 740.64 195.53 360 95.04 90.29<br />
1-10 412.17 477.05 460.69 110.56 360 86.40 82.08<br />
11-20 344.57 398.80 385.12 92.43 360 86.40 82.08<br />
21-30 385.23 445.86 430.57 103.34 360 86.40 82.08<br />
1-10 542.05 627.37 605.85 145.40 360 86.40 82.08<br />
11-20 540.39 625.45 604.00 144.96 360 86.40 82.08<br />
21-31 289.22 304.32 293.88 77.58 294 77.58 77.58<br />
1-10 132.32 153.15 147.90 35.50 148 35.50 35.50<br />
11-20 105.50 122.11 117.92 28.30 118 28.30 28.30<br />
21-30 90.37 104.60 101.01 24.24 101 24.24 24.24<br />
1-10 93.52 108.24 104.53 25.09 105 25.09 25.09<br />
11-20 68.25 78.99 76.28 18.31 76 18.31 18.31<br />
21-31 78.53 82.62 79.79 21.06 80 21.06 21.06<br />
1-10 60.34 69.84 67.45 16.19 67 16.19 16.19<br />
11-20 63.19 73.13 70.62 16.95 71 16.95 16.95<br />
21-31 69.92 73.57 71.05 18.76 71 18.76 18.76<br />
1-10 75.78 87.71 84.70 20.33 85 20.33 20.33<br />
11-20 77.89 90.16 87.06 20.90 87 20.90 20.90<br />
21-28 65.56 94.86 91.60 17.59 92 17.59 17.59<br />
1-10 104.50 120.95 116.80 28.03 117 28.03 28.03<br />
11-20 100.25 116.03 112.05 26.89 112 26.89 26.89<br />
21-31 90.23 94.94 91.68 24.20 92 24.20 24.20<br />
1-10 147.71 170.96 165.09 39.62 165 39.62 39.62<br />
11-20 142.21 164.60 158.95 38.15 159 38.15 38.15<br />
21-30 124.54 144.14 139.19 33.41 139 33.41 33.41<br />
1-10 163.50 189.24 182.75 43.86 183 43.86 43.86<br />
11-20 229.74 265.90 256.78 61.63 257 61.63 61.63<br />
21-31 162.17 170.64 164.78 43.50 165 43.50 43.50<br />
Total 10965.93 2941.60 1906.96 1845.61<br />
Annual<br />
L/F 60.47%<br />
L/F monsoon<br />
(March to Nov.)<br />
72.89%<br />
L/F non-monsoon (Dec<br />
to Feb.)<br />
22.53%<br />
79
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
POWER POTENTIAL STUDY FOR YEAR<br />
6-7<br />
Installed<br />
Capacity<br />
360 Net Head 107 Efficiency 92%<br />
Month DISCHARGE<br />
RESTRICTED RESTRICTED<br />
DISCHARGE UNRESTRICTED UNRESTRICTED<br />
95% m/c<br />
POWER ENERGY<br />
( MCum) ( Qmecs) POWER ( MW) ENERGY ( MU)<br />
Availability<br />
( 360MW) ( MU)<br />
June-<br />
06<br />
1-10<br />
11-20<br />
21-30<br />
180.78<br />
197.73<br />
245.06<br />
209.23<br />
228.85<br />
283.63<br />
202.05<br />
221.00<br />
273.90<br />
48.49<br />
53.04<br />
65.74<br />
202<br />
221<br />
274<br />
48.49<br />
53.04<br />
65.74<br />
48.49<br />
53.04<br />
65.74<br />
1-10 465.48 538.75 520.27 124.87 360 86.40 82.08<br />
July-06 11-20 372.70 431.36 416.57 99.98 360 86.40 82.08<br />
21-31 641.09 674.55 651.41 171.97 360 95.04 90.29<br />
1-10 602.59 697.44 673.52 161.64 360 86.40 82.08<br />
Aug-06 11-20 669.25 774.60 748.03 179.53 360 86.40 82.08<br />
21-31 673.67 708.83 684.52 180.71 360 95.04 90.29<br />
1-10 478.73 554.09 535.08 128.42 360 86.40 82.08<br />
Sep-06 11-20 369.50 427.67 413.00 99.12 360 86.40 82.08<br />
21-30 300.10 347.33 335.42 80.50 335 80.50 80.50<br />
1-10 486.50 563.08 543.77 130.50 360 86.40 82.08<br />
Oct-06 11-20 440.80 510.19 492.68 118.24 360 86.40 82.08<br />
21-31 250.67 263.75 254.70 67.24 255 67.24 67.24<br />
1-10 176.80 204.63 197.61 47.43 198 47.43 47.43<br />
Nov-06 11-20 102.78 118.95 114.87 27.57 115 27.57 27.57<br />
21-30 89.06 103.08 99.54 23.89 100 23.89 23.89<br />
1-10 70.13 81.17 78.39 18.81 78 18.81 18.81<br />
Dec-06 11-20 71.81 83.11 80.26 19.26 80 19.26 19.26<br />
21-31 65.28 68.69 66.33 17.51 66 17.51 17.51<br />
1-10 44.42 51.41 49.64 11.91 50 11.91 11.91<br />
Jan-07 11-20 53.05 61.40 59.30 14.23 59 14.23 14.23<br />
21-31 64.72 68.10 65.77 17.36 66 17.36 17.36<br />
1-10 65.17 75.43 72.84 17.48 73 17.48 17.48<br />
Feb-07 11-20 60.53 70.05 67.65 16.24 68 16.24 16.24<br />
21-28 45.66 66.06 63.79 12.25 64 12.25 12.25<br />
1-10 71.85 83.16 80.31 19.27 80 19.27 19.27<br />
Mar-07 11-20 65.67 76.01 73.40 17.62 73 17.62 17.62<br />
21-31 68.93 72.53 70.04 18.49 70 18.49 18.49<br />
1-10 100.19 115.96 111.99 26.88 112 26.88 26.88<br />
Apr-07 11-20 128.87 149.15 144.04 34.57 144 34.57 34.57<br />
21-30 159.65 184.79 178.45 42.83 178 42.83 42.83<br />
1-10 268.95 311.29 300.61 72.15 301 72.15 72.15<br />
May-07 11-20 246.94 285.81 276.00 66.24 276 66.24 66.24<br />
21-31 309.38 325.53 314.36 82.99 314 82.99 82.99<br />
Total 8704.51 2334.97 1821.27 1777.21<br />
Annual<br />
L/F 57.75%<br />
L/F monsoon<br />
(March to Nov.)<br />
70.55%<br />
L/F non-monsoon (Dec<br />
to Feb.)<br />
18.66%<br />
80
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
POWER POTENTIAL STUDY FOR YEAR<br />
7-8<br />
Installed<br />
Capacity<br />
360 Net Head 107 Efficiency 92%<br />
Month DISCHARGE<br />
RESTRICTED RESTRICTED<br />
DISCHARGE UNRESTRICTED UNRESTRICTED<br />
95% m/c<br />
POWER ENERGY<br />
( MCum) ( Qmecs) POWER ( MW) ENERGY ( MU)<br />
Availability<br />
( 360MW) ( MU)<br />
June-<br />
07<br />
1-10<br />
11-20<br />
21-30<br />
255.64<br />
299.89<br />
428.53<br />
295.88<br />
347.09<br />
495.99<br />
285.73<br />
335.19<br />
478.97<br />
68.58<br />
80.44<br />
114.95<br />
286<br />
335<br />
360<br />
68.58<br />
80.44<br />
86.40<br />
68.58<br />
80.44<br />
82.08<br />
1-10 501.82 580.81 560.89 134.61 360 86.40 82.08<br />
July-07 11-20 722.94 836.73 808.03 193.93 360 86.40 82.08<br />
21-31 976.34 1027.29 992.05 261.90 360 95.04 90.29<br />
1-10 285.06 329.93 318.61 76.47 319 76.47 76.47<br />
Aug-07 11-20 364.06 421.36 406.91 97.66 360 86.40 82.08<br />
21-31 370.02 389.33 375.98 99.26 360 95.04 90.29<br />
1-10 258.97 299.74 289.46 69.47 289 69.47 69.47<br />
Sep-07 11-20 315.90 365.63 353.08 84.74 353 84.74 84.74<br />
21-30 364.32 421.67 407.21 97.73 360 86.40 82.08<br />
1-10 330.61 382.66 369.53 88.69 360 86.40 82.08<br />
Oct-07 11-20 173.86 201.23 194.32 46.64 194 46.64 46.64<br />
21-31 153.78 161.81 156.26 41.25 156 41.25 41.25<br />
1-10 127.61 147.70 142.63 34.23 143 34.23 34.23<br />
Nov-07 11-20 139.79 161.80 156.25 37.50 156 37.50 37.50<br />
21-30 126.54 146.46 141.44 33.95 141 33.95 33.95<br />
1-10 122.53 141.82 136.95 32.87 137 32.87 32.87<br />
Dec-07 11-20 83.62 96.78 93.46 22.43 93 22.43 22.43<br />
21-31 75.93 79.89 77.15 20.37 77 20.37 20.37<br />
1-10 79.19 91.65 88.51 21.24 89 21.24 21.24<br />
Jan-08 11-20 74.11 85.77 82.83 19.88 83 19.88 19.88<br />
21-31 88.11 92.70 89.52 23.63 90 23.63 23.63<br />
1-10 88.14 102.01 98.51 23.64 99 23.64 23.64<br />
Feb-08 11-20 65.74 76.08 73.47 17.63 73 17.63 17.63<br />
21-29 61.46 79.04 76.33 16.49 76 16.49 16.49<br />
1-10 88.30 102.20 98.69 23.69 99 23.69 23.69<br />
Mar-08 11-20 81.95 94.85 91.60 21.98 92 21.98 21.98<br />
21-31 114.41 120.38 116.25 30.69 116 30.69 30.69<br />
1-10 147.08 170.23 164.39 39.45 164 39.45 39.45<br />
Apr-08 11-20 153.40 177.55 171.46 41.15 171 41.15 41.15<br />
21-30 114.70 132.75 128.20 30.77 128 30.77 30.77<br />
1-10 257.96 298.57 288.33 69.20 288 69.20 69.20<br />
May-08 11-20 394.67 456.79 441.13 105.87 360 86.40 82.08<br />
21-31 633.22 666.27 643.42 169.86 360 95.04 90.29<br />
Total 8920.21 2392.84 1918.30 1873.80<br />
Annual<br />
L/F 60.83%<br />
L/F monsoon<br />
(March to Nov.)<br />
72.40%<br />
L/F non-monsoon (Dec<br />
to Feb.)<br />
25.49%<br />
81
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
POWER POTENTIAL STUDY FOR YEAR<br />
8-9<br />
Installed<br />
Capacity<br />
360 Net Head 107 Efficiency 92%<br />
Month DISCHARGE<br />
RESTRICTED RESTRICTED<br />
DISCHARGE UNRESTRICTED UNRESTRICTED<br />
95% m/c<br />
POWER ENERGY<br />
( MCum) ( Qmecs) POWER ( MW) ENERGY ( MU)<br />
Availability<br />
( 360MW) ( MU)<br />
June-<br />
08<br />
1-10<br />
11-20<br />
21-30<br />
973.75<br />
1217.35<br />
1091.44<br />
1127.03<br />
1408.97<br />
1263.24<br />
1088.37<br />
1360.64<br />
1219.91<br />
261.21<br />
326.55<br />
292.78<br />
360<br />
360<br />
360<br />
86.40<br />
86.40<br />
86.40<br />
82.08<br />
82.08<br />
82.08<br />
1-10 1274.10 1474.65 1424.06 341.78 360 86.40 82.08<br />
July-08 11-20 1405.98 1627.29 1571.47 377.15 360 86.40 82.08<br />
21-31 1947.98 2049.64 1979.33 522.54 360 95.04 90.29<br />
1-10 557.98 645.81 623.65 149.68 360 86.40 82.08<br />
Aug-08 11-20 629.78 728.91 703.90 168.94 360 86.40 82.08<br />
21-31 759.15 798.77 771.37 203.64 360 95.04 90.29<br />
1-10 576.15 666.84 643.96 154.55 360 86.40 82.08<br />
Sep-08 11-20 412.24 477.13 460.76 110.58 360 86.40 82.08<br />
21-30 574.53 664.97 642.16 154.12 360 86.40 82.08<br />
1-10 463.19 536.10 517.71 124.25 360 86.40 82.08<br />
Oct-08 11-20 499.56 578.19 558.36 134.01 360 86.40 82.08<br />
21-31 249.63 262.65 253.64 66.96 254 66.96 66.96<br />
1-10 225.06 260.49 251.55 60.37 252 60.37 60.37<br />
Nov-08 11-20 192.67 223.00 215.35 51.68 215 51.68 51.68<br />
21-30 126.89 146.87 141.83 34.04 142 34.04 34.04<br />
1-10 80.33 92.97 89.78 21.55 90 21.55 21.55<br />
Dec-08 11-20 85.01 98.39 95.01 22.80 95 22.80 22.80<br />
21-31 83.66 88.03 85.01 22.44 85 22.44 22.44<br />
1-10 69.12 80.00 77.26 18.54 77 18.54 18.54<br />
Jan-09 11-20 55.17 63.86 61.67 14.80 62 14.80 14.80<br />
21-31 57.15 60.14 58.07 15.33 58 15.33 15.33<br />
1-10 46.40 53.70 51.86 12.45 52 12.45 12.45<br />
Feb-09 11-20 43.03 49.80 48.09 11.54 48 11.54 11.54<br />
21-28 35.90 51.94 50.16 9.63 50 9.63 9.63<br />
1-10 81.67 94.52 91.28 21.91 91 21.91 21.91<br />
Mar-09 11-20 85.34 98.77 95.38 22.89 95 22.89 22.89<br />
21-31 82.21 86.50 83.53 22.05 84 22.05 22.05<br />
1-10 89.32 103.38 99.83 23.96 100 23.96 23.96<br />
Apr-09 11-20 156.58 181.23 175.01 42.00 175 42.00 42.00<br />
21-30 168.32 194.81 188.13 45.15 188 45.15 45.15<br />
1-10 189.37 219.17 211.66 50.80 212 50.80 50.80<br />
May-09 11-20 134.51 155.68 150.34 36.08 150 36.08 36.08<br />
21-31 236.28 248.61 240.08 63.38 240 63.38 63.38<br />
Total 14956.79 4012.14 1917.25 1855.91<br />
Annual<br />
L/F 60.80%<br />
L/F monsoon<br />
(March to Nov.)<br />
74.42%<br />
L/F non-monsoon (Dec<br />
to Feb.)<br />
19.17%<br />
82
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
POWER POTENTIAL STUDY FOR YEAR<br />
9-10<br />
Installed<br />
Capacity<br />
360 Net Head 107 Efficiency 92%<br />
Month DISCHARGE<br />
RESTRICTED RESTRICTED<br />
DISCHARGE UNRESTRICTED UNRESTRICTED<br />
95% m/c<br />
POWER ENERGY<br />
( MCum) ( Qmecs) POWER ( MW) ENERGY ( MU)<br />
Availability<br />
( 360MW) ( MU)<br />
June-<br />
09<br />
1-10<br />
11-20<br />
21-30<br />
175.10<br />
166.84<br />
268.98<br />
202.66<br />
193.10<br />
311.32<br />
195.71<br />
186.48<br />
300.64<br />
46.97<br />
44.76<br />
72.15<br />
196<br />
186<br />
301<br />
46.97<br />
44.76<br />
72.15<br />
46.97<br />
44.76<br />
72.15<br />
1-10 769.87 891.05 860.48 206.52 360 86.40 82.08<br />
July-09 11-20 600.32 694.81 670.98 161.03 360 86.40 82.08<br />
21-31 946.46 995.86 961.70 253.89 360 95.04 90.29<br />
1-10 737.47 853.55 824.27 197.83 360 86.40 82.08<br />
Aug-09 11-20 942.18 1090.48 1053.07 252.74 360 86.40 82.08<br />
21-31 767.41 807.46 779.76 205.86 360 95.04 90.29<br />
1-10 522.95 605.27 584.50 140.28 360 86.40 82.08<br />
Sep-09 11-20 471.25 545.42 526.71 126.41 360 86.40 82.08<br />
21-30 509.41 589.60 569.37 136.65 360 86.40 82.08<br />
1-10 563.99 652.76 630.37 151.29 360 86.40 82.08<br />
Oct-09 11-20 241.09 279.04 269.47 64.67 269 64.67 64.67<br />
21-31 276.48 290.91 280.93 74.17 281 74.17 74.17<br />
1-10 141.13 163.35 157.75 37.86 158 37.86 37.86<br />
Nov-09 11-20 147.64 170.88 165.01 39.60 165 39.60 39.60<br />
21-30 92.08 106.57 102.92 24.70 103 24.70 24.70<br />
1-10 63.68 73.71 71.18 17.08 71 17.08 17.08<br />
Dec-09 11-20 66.19 76.61 73.98 17.76 74 17.76 17.76<br />
21-31 60.40 63.55 61.37 16.20 61 16.20 16.20<br />
1-10 43.95 50.86 49.12 11.79 49 11.79 11.79<br />
Jan-10 11-20 41.20 47.68 46.05 11.05 46 11.05 11.05<br />
21-31 47.57 50.06 48.34 12.76 48 12.76 12.76<br />
1-10 52.90 61.23 59.13 14.19 59 14.19 14.19<br />
Feb-10 11-20 66.93 77.47 74.81 17.95 75 17.95 17.95<br />
21-28 51.67 74.76 72.19 13.86 72 13.86 13.86<br />
1-10 106.86 123.68 119.44 28.66 119 28.66 28.66<br />
Mar-10 11-20 84.28 97.55 94.20 22.61 94 22.61 22.61<br />
21-31 94.29 99.21 95.81 25.29 96 25.29 25.29<br />
1-10 106.08 122.78 118.57 28.46 119 28.46 28.46<br />
Apr-10 11-20 126.39 146.29 141.27 33.91 141 33.91 33.91<br />
21-30 128.56 148.80 143.69 34.49 144 34.49 34.49<br />
1-10 166.70 192.94 186.32 44.72 186 44.72 44.72<br />
May-10 11-20 123.27 142.68 137.78 33.07 138 33.07 33.07<br />
21-31 157.32 165.53 159.85 42.20 160 42.20 42.20<br />
Total 9928.91 2663.42 1712.21 1668.15<br />
Annual<br />
L/F 54.29%<br />
L/F monsoon<br />
(March to Nov.)<br />
66.48%<br />
L/F non-monsoon (Dec to<br />
Feb.)<br />
17.06%<br />
83
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
POWER POTENTIAL STUDY FOR YEAR<br />
11-12<br />
Installed<br />
Capacity<br />
360 Net Head 107 Efficiency 92%<br />
Month DISCHARGE<br />
RESTRICTED RESTRICTED<br />
DISCHARGE UNRESTRICTED UNRESTRICTED<br />
95% m/c<br />
POWER ENERGY<br />
( MCum) ( Qmecs) POWER ( MW) ENERGY ( MU)<br />
Availability<br />
( 360MW) ( MU)<br />
June-<br />
11<br />
1-10<br />
11-20<br />
21-30<br />
221.01<br />
250.59<br />
233.15<br />
255.80<br />
290.04<br />
269.85<br />
247.02<br />
280.09<br />
260.60<br />
59.29<br />
67.22<br />
62.54<br />
247<br />
280<br />
261<br />
59.29<br />
67.22<br />
62.54<br />
59.29<br />
67.22<br />
62.54<br />
1-10 357.16 413.38 399.20 95.81 360 86.40 82.08<br />
July-11 11-20 616.60 713.66 689.18 165.40 360 86.40 82.08<br />
21-31 495.59 521.46 503.57 132.94 360 95.04 90.29<br />
1-10 459.73 532.10 513.84 123.32 360 86.40 82.08<br />
Aug-11 11-20 502.93 582.10 562.13 134.91 360 86.40 82.08<br />
21-31 912.93 960.57 927.62 244.89 360 95.04 90.29<br />
1-10 783.91 907.31 876.18 210.28 360 86.40 82.08<br />
Sep-11 11-20 858.30 993.40 959.33 230.24 360 86.40 82.08<br />
21-30 687.12 795.28 768.00 184.32 360 86.40 82.08<br />
1-10 575.35 665.92 643.07 154.34 360 86.40 82.08<br />
Oct-11 11-20 218.28 252.64 243.97 58.55 244 58.55 58.55<br />
21-31 225.50 237.27 229.13 60.49 229 60.49 60.49<br />
1-10 148.05 171.35 165.47 39.71 165 39.71 39.71<br />
Nov-11 11-20 126.92 146.90 141.86 34.05 142 34.05 34.05<br />
21-30 115.11 133.23 128.66 30.88 129 30.88 30.88<br />
1-10 77.84 90.09 87.00 20.88 87 20.88 20.88<br />
Dec-11 11-20 91.18 105.53 101.91 24.46 102 24.46 24.46<br />
21-31 88.55 93.17 89.98 23.75 90 23.75 23.75<br />
1-10 92.71 107.30 103.62 24.87 104 24.87 24.87<br />
Jan-12 11-20 93.36 108.06 104.35 25.04 104 25.04 25.04<br />
21-31 97.11 102.18 98.67 26.05 99 26.05 26.05<br />
1-10 79.97 92.55 89.38 21.45 89 21.45 21.45<br />
Feb-12 11-20 80.80 93.52 90.31 21.68 90 21.68 21.68<br />
21-29 66.75 85.84 82.89 17.91 83 17.91 17.91<br />
1-10 85.45 98.90 95.51 22.92 96 22.92 22.92<br />
Mar-12 11-20 76.69 88.76 85.72 20.57 86 20.57 20.57<br />
21-31 96.85 101.90 98.41 25.98 98 25.98 25.98<br />
1-10 137.77 159.46 153.99 36.96 154 36.96 36.96<br />
Apr-12 11-20 158.86 183.86 177.56 42.61 178 42.61 42.61<br />
21-30 158.45 183.40 177.10 42.51 177 42.51 42.51<br />
1-10 279.37 323.34 312.25 74.94 312 74.94 74.94<br />
May-12 11-20 240.07 277.86 268.33 64.40 268 64.40 64.40<br />
21-31 148.22 155.95 150.60 39.76 151 39.76 39.76<br />
Total 9938.23 2665.92 1870.74 1826.68<br />
Annual<br />
L/F 59.32%<br />
L/F monsoon<br />
(March to Nov.)<br />
70.06%<br />
L/F non-monsoon (Dec<br />
to Feb.)<br />
26.50%<br />
84
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
POWER POTENTIAL STUDY FOR YEAR<br />
12-13<br />
Installed<br />
Capacity<br />
360 Net Head 107 Efficiency 92%<br />
Month DISCHARGE<br />
RESTRICTED RESTRICTED<br />
DISCHARGE UNRESTRICTED UNRESTRICTED<br />
95% m/c<br />
POWER ENERGY<br />
( MCum) ( Qmecs) POWER ( MW) ENERGY ( MU)<br />
Availability<br />
( 360MW) ( MU)<br />
June-<br />
12<br />
1-10<br />
11-20<br />
21-30<br />
296.72<br />
360.90<br />
515.65<br />
343.43<br />
417.71<br />
596.81<br />
331.65<br />
403.38<br />
576.34<br />
79.60<br />
96.81<br />
138.32<br />
332<br />
360<br />
360<br />
79.60<br />
86.40<br />
86.40<br />
79.60<br />
82.08<br />
82.08<br />
1-10 611.79 708.09 683.80 164.11 360 86.40 82.08<br />
July-12 11-20 488.16 565.00 545.62 130.95 360 86.40 82.08<br />
21-31 879.69 925.59 893.84 235.97 360 95.04 90.29<br />
1-10 371.34 429.79 415.05 99.61 360 86.40 82.08<br />
Aug-12 11-20 504.43 583.84 563.81 135.31 360 86.40 82.08<br />
21-31 981.52 1032.75 997.32 263.29 360 95.04 90.29<br />
1-10 674.14 780.26 753.49 180.84 360 86.40 82.08<br />
Sep-12 11-20 712.43 824.58 796.29 191.11 360 86.40 82.08<br />
21-30 525.34 608.04 587.18 140.92 360 86.40 82.08<br />
1-10 304.49 352.42 340.33 81.68 340 81.68 81.68<br />
Oct-12 11-20 338.97 392.32 378.86 90.93 360 86.40 82.08<br />
21-31 188.74 198.59 191.78 50.63 192 50.63 50.63<br />
1-10 104.33 120.75 116.61 27.99 117 27.99 27.99<br />
Nov-12 11-20 98.90 114.47 110.54 26.53 111 26.53 26.53<br />
21-30 81.06 93.82 90.60 21.74 91 21.74 21.74<br />
1-10 88.87 102.86 99.34 23.84 99 23.84 23.84<br />
Dec-12 11-20 68.06 78.77 76.07 18.26 76 18.26 18.26<br />
21-31 66.61 70.09 67.69 17.87 68 17.87 17.87<br />
1-10 45.81 53.02 51.20 12.29 51 12.29 12.29<br />
Jan-13 11-20 46.16 53.42 51.59 12.38 52 12.38 12.38<br />
21-31 56.28 59.21 57.18 15.10 57 15.10 15.10<br />
1-10 61.29 70.94 68.51 16.44 69 16.44 16.44<br />
Feb-13 11-20 45.64 52.82 51.01 12.24 51 12.24 12.24<br />
21-28 54.39 78.70 76.00 14.59 76 14.59 14.59<br />
1-10 87.29 101.03 97.56 23.41 98 23.41 23.41<br />
Mar-13 11-20 113.27 131.10 126.60 30.38 127 30.38 30.38<br />
21-31 125.40 131.94 127.41 33.64 127 33.64 33.64<br />
1-10 139.92 161.94 156.39 37.53 156 37.53 37.53<br />
Apr-13 11-20 135.01 156.26 150.90 36.22 151 36.22 36.22<br />
21-30 150.22 173.86 167.90 40.30 168 40.30 40.30<br />
1-10 173.67 201.00 194.11 46.59 194 46.59 46.59<br />
May-13 11-20 166.69 192.93 186.31 44.71 186 44.71 44.71<br />
21-31 375.48 395.08 381.53 100.72 360 95.04 90.29<br />
Total 10038.68 2692.86 1873.08 1815.62<br />
Annual<br />
L/F 59.39%<br />
L/F monsoon<br />
(March to Nov.)<br />
72.81%<br />
L/F non-monsoon (Dec<br />
to Feb.)<br />
18.39%<br />
85
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
POWER POTENTIAL STUDY FOR YEAR<br />
13-14<br />
Installed<br />
Capacity<br />
360 Net Head 107 Efficiency 92%<br />
Month DISCHARGE<br />
RESTRICTED RESTRICTED<br />
DISCHARGE UNRESTRICTED UNRESTRICTED<br />
95% m/c<br />
POWER ENERGY<br />
( MCum) ( Qmecs) POWER ( MW) ENERGY ( MU)<br />
Availability<br />
( 360MW) ( MU)<br />
June-<br />
13<br />
1-10<br />
11-20<br />
21-30<br />
282.99<br />
266.80<br />
480.99<br />
327.54<br />
308.80<br />
556.71<br />
316.30<br />
298.21<br />
537.61<br />
75.91<br />
71.57<br />
129.03<br />
316<br />
298<br />
360<br />
75.91<br />
71.57<br />
86.40<br />
75.91<br />
71.57<br />
82.08<br />
1-10 423.13 489.73 472.93 113.50 360 86.40 82.08<br />
July-13 11-20 663.76 768.24 741.89 178.05 360 86.40 82.08<br />
21-31 577.57 607.71 586.86 154.93 360 95.04 90.29<br />
1-10 825.79 955.77 922.99 221.52 360 86.40 82.08<br />
Aug-13 11-20 1078.15 1247.86 1205.06 289.21 360 86.40 82.08<br />
21-31 755.37 794.79 767.53 202.63 360 95.04 90.29<br />
1-10 350.19 405.31 391.41 93.94 360 86.40 82.08<br />
Sep-13 11-20 327.45 379.00 365.99 87.84 360 86.40 82.08<br />
21-30 261.09 302.19 291.82 70.04 292 70.04 70.04<br />
1-10 493.28 570.93 551.34 132.32 360 86.40 82.08<br />
Oct-13 11-20 214.30 248.04 239.53 57.49 240 57.49 57.49<br />
21-31 195.34 205.54 198.49 52.40 198 52.40 52.40<br />
1-10 143.43 166.01 160.31 38.48 160 38.48 38.48<br />
Nov-13 11-20 136.28 157.73 152.32 36.56 152 36.56 36.56<br />
21-30 100.61 116.45 112.45 26.99 112 26.99 26.99<br />
1-10 67.98 78.68 75.98 18.24 76 18.24 18.24<br />
Dec-13 11-20 70.47 81.56 78.76 18.90 79 18.90 18.90<br />
21-31 75.31 79.24 76.52 20.20 77 20.20 20.20<br />
1-10 55.28 63.98 61.78 14.83 62 14.83 14.83<br />
Jan-14 11-20 45.21 52.32 50.53 12.13 51 12.13 12.13<br />
21-31 47.22 49.68 47.98 12.67 48 12.67 12.67<br />
1-10 56.98 65.95 63.69 15.29 64 15.29 15.29<br />
Feb-14 11-20 44.81 51.86 50.08 12.02 50 12.02 12.02<br />
21-28 45.45 65.75 63.50 12.19 63 12.19 12.19<br />
1-10 85.23 98.65 95.26 22.86 95 22.86 22.86<br />
Mar-14 11-20 115.83 134.06 129.46 31.07 129 31.07 31.07<br />
21-31 109.25 114.95 111.00 29.31 111 29.31 29.31<br />
1-10 130.92 151.52 146.33 35.12 146 35.12 35.12<br />
Apr-14 11-20 175.02 202.57 195.62 46.95 196 46.95 46.95<br />
21-30 149.22 172.71 166.78 40.03 167 40.03 40.03<br />
1-10 188.13 217.75 210.28 50.47 210 50.47 50.47<br />
May-14 11-20 186.74 216.13 208.72 50.09 209 50.09 50.09<br />
21-31 201.51 212.03 204.75 54.05 205 54.05 54.05<br />
Total 9427.09 2528.81 1807.11 1763.05<br />
Annual<br />
L/F 57.30%<br />
L/F monsoon<br />
(March to Nov.)<br />
70.31%<br />
L/F non-monsoon (Dec<br />
to Feb.)<br />
17.55%<br />
86
Installed<br />
Capacity<br />
POWER POTENTIAL STUDY FOR YEAR<br />
14-15<br />
360 Net Head 107 Efficiency 92%<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Month DISCHARGE<br />
RESTRICTED RESTRICTED<br />
DISCHARGE UNRESTRICTED UNRESTRICTED<br />
95% m/c<br />
POWER ENERGY<br />
( MCum) ( Qmecs) POWER ( MW) ENERGY ( MU)<br />
Availability<br />
( 360MW) ( MU)<br />
1-10 433.24 501.43 484.23 116.22 360 86.40 82.08<br />
11-20 739.36 855.74 826.39 198.33 360 86.40 82.08<br />
June-<br />
14<br />
July-14<br />
Aug-14<br />
Sep-14<br />
Oct-14<br />
Nov-14<br />
Dec-14<br />
Jan-15<br />
Feb-15<br />
Mar-15<br />
Apr-15<br />
May-15<br />
21-30 988.73 1144.36 1105.10 265.23 360 86.40 82.08<br />
1-10 615.75 712.68 688.23 165.18 360 86.40 82.08<br />
11-20 727.23 841.70 812.83 195.08 360 86.40 82.08<br />
21-31 979.13 1030.23 994.89 262.65 360 95.04 90.29<br />
1-10 633.41 733.12 707.97 169.91 360 86.40 82.08<br />
11-20 671.70 777.43 750.76 180.18 360 86.40 82.08<br />
21-31 698.72 735.18 709.96 187.43 360 95.04 90.29<br />
1-10 573.43 663.69 640.92 153.82 360 86.40 82.08<br />
11-20 417.24 482.91 466.35 111.92 360 86.40 82.08<br />
21-30 383.14 443.45 428.24 102.78 360 86.40 82.08<br />
1-10 469.38 543.27 524.63 125.91 360 86.40 82.08<br />
11-20 238.98 276.60 267.11 64.11 267 64.11 64.11<br />
21-31 154.29 162.34 156.77 41.39 157 41.39 41.39<br />
1-10 146.79 169.90 164.07 39.38 164 39.38 39.38<br />
11-20 125.63 145.41 140.42 33.70 140 33.70 33.70<br />
21-30 90.26 104.46 100.88 24.21 101 24.21 24.21<br />
1-10 94.20 109.03 105.29 25.27 105 25.27 25.27<br />
11-20 105.12 121.67 117.50 28.20 117 28.20 28.20<br />
21-31 100.39 105.63 102.01 26.93 102 26.93 26.93<br />
1-10 95.32 110.32 106.54 25.57 107 25.57 25.57<br />
11-20 86.16 99.72 96.30 23.11 96 23.11 23.11<br />
21-31 90.11 94.81 91.56 24.17 92 24.17 24.17<br />
1-10 107.17 124.04 119.79 28.75 120 28.75 28.75<br />
11-20 67.28 77.87 75.20 18.05 75 18.05 18.05<br />
21-28 64.51 93.32 90.12 17.30 90 17.30 17.30<br />
1-10 95.09 110.06 106.28 25.51 106 25.51 25.51<br />
11-20 104.59 121.05 116.90 28.06 117 28.06 28.06<br />
21-31 99.99 105.21 101.60 26.82 102 26.82 26.82<br />
1-10 97.18 112.48 108.62 26.07 109 26.07 26.07<br />
11-20 94.58 109.47 105.71 25.37 106 25.37 25.37<br />
21-30 91.45 105.84 102.21 24.53 102 24.53 24.53<br />
1-10 211.61 244.92 236.51 56.76 237 56.76 56.76<br />
11-20 181.67 210.27 203.06 48.73 203 48.73 48.73<br />
21-31 122.69 129.10 124.67 32.91 125 32.91 32.91<br />
Total 10995.51 2949.53 1855.38 1798.35<br />
Annual<br />
L/F 58.83%<br />
L/F monsoon<br />
(March to Nov.)<br />
68.94%<br />
L/F non-monsoon (Dec<br />
to Feb.)<br />
27.95%<br />
87
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
POWER POTENTIAL STUDY FOR YEAR<br />
15-16<br />
Installed<br />
Capacity<br />
360 Net Head 107 Efficiency 92%<br />
Month DISCHARGE<br />
RESTRICTED RESTRICTED<br />
DISCHARGE UNRESTRICTED UNRESTRICTED<br />
95% m/c<br />
POWER ENERGY<br />
( MCum) ( Qmecs) POWER ( MW) ENERGY ( MU)<br />
Availability<br />
( 360MW) ( MU)<br />
June-<br />
15<br />
1-10<br />
11-20<br />
21-30<br />
134.70<br />
252.30<br />
384.61<br />
155.90<br />
292.02<br />
445.15<br />
150.55<br />
282.00<br />
429.88<br />
36.13<br />
67.68<br />
103.17<br />
151<br />
282<br />
360<br />
36.13<br />
67.68<br />
86.40<br />
36.13<br />
67.68<br />
82.08<br />
1-10 842.98 975.67 942.20 226.13 360 86.40 82.08<br />
July-15 11-20 788.99 913.19 881.86 211.65 360 86.40 82.08<br />
21-31 761.68 801.43 773.94 204.32 360 95.04 90.29<br />
1-10 692.20 801.15 773.67 185.68 360 86.40 82.08<br />
Aug-15 11-20 623.46 721.60 696.84 167.24 360 86.40 82.08<br />
21-31 600.37 631.70 610.03 161.05 360 95.04 90.29<br />
1-10 298.59 345.59 333.73 80.10 334 80.10 80.10<br />
Sep-15 11-20 329.33 381.17 368.09 88.34 360 86.40 82.08<br />
21-30 316.83 366.70 354.12 84.99 354 84.99 84.99<br />
1-10 259.75 300.63 290.32 69.68 290 69.68 69.68<br />
Oct-15 11-20 194.57 225.20 217.47 52.19 217 52.19 52.19<br />
21-31 188.38 198.21 191.41 50.53 191 50.53 50.53<br />
1-10 188.34 217.98 210.51 50.52 211 50.52 50.52<br />
Nov-15 11-20 154.97 179.36 173.21 41.57 173 41.57 41.57<br />
21-30 107.23 124.11 119.85 28.76 120 28.76 28.76<br />
1-10 116.10 134.37 129.76 31.14 130 31.14 31.14<br />
Dec-15 11-20 82.43 95.40 92.13 22.11 92 22.11 22.11<br />
21-31 76.57 80.57 77.80 20.54 78 20.54 20.54<br />
1-10 53.23 61.61 59.50 14.28 59 14.28 14.28<br />
Jan-16 11-20 58.44 67.64 65.32 15.68 65 15.68 15.68<br />
21-31 70.63 74.32 71.77 18.95 72 18.95 18.95<br />
1-10 85.57 99.04 95.64 22.95 96 22.95 22.95<br />
Feb-16 11-20 83.45 96.59 93.27 22.39 93 22.39 22.39<br />
21-29 81.04 104.22 100.65 21.74 101 21.74 21.74<br />
1-10 101.07 116.98 112.96 27.11 113 27.11 27.11<br />
Mar-16 11-20 79.37 91.86 88.71 21.29 89 21.29 21.29<br />
21-31 85.10 89.54 86.47 22.83 86 22.83 22.83<br />
1-10 141.28 163.52 157.91 37.90 158 37.90 37.90<br />
Apr-16 11-20 117.21 135.66 131.00 31.44 131 31.44 31.44<br />
21-30 180.00 208.33 201.19 48.28 201 48.28 48.28<br />
1-10 218.72 253.14 244.46 58.67 244 58.67 58.67<br />
May-16 11-20 162.90 188.54 182.07 43.70 182 43.70 43.70<br />
21-31 242.41 255.06 246.31 65.03 246 65.03 65.03<br />
Total 9154.77 2455.76 1816.66 1781.23<br />
Annual<br />
L/F 57.61%<br />
L/F monsoon<br />
(March to Nov.)<br />
68.47%<br />
L/F non-monsoon (Dec<br />
to Feb.)<br />
24.41%<br />
88
Installed<br />
Capacity<br />
POWER POTENTIAL STUDY FOR YEAR<br />
16-17<br />
360 Net Head 107 Efficiency 92%<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Month DISCHARGE<br />
RESTRICTED RESTRICTED<br />
DISCHARGE UNRESTRICTED UNRESTRICTED<br />
95% m/c<br />
POWER ENERGY<br />
( MCum) ( Qmecs) POWER ( MW) ENERGY ( MU)<br />
Availability<br />
( 360MW) ( MU)<br />
1-10 545.64 631.53 609.87 146.37 360 86.40 82.08<br />
11-20 379.62 439.38 424.31 101.83 360 86.40 82.08<br />
June-<br />
16<br />
July-16<br />
Aug-16<br />
Sep-16<br />
Oct-16<br />
Nov-16<br />
Dec-16<br />
Jan-17<br />
Feb-17<br />
Mar-17<br />
Apr-17<br />
May-17<br />
21-30 382.89 443.16 427.96 102.71 360 86.40 82.08<br />
1-10 333.12 385.55 372.33 89.36 360 86.40 82.08<br />
11-20 276.51 320.03 309.06 74.17 309 74.17 74.17<br />
21-31 339.47 357.19 344.94 91.06 345 91.06 91.06<br />
1-10 485.44 561.85 542.58 130.22 360 86.40 82.08<br />
11-20 745.67 863.04 833.44 200.02 360 86.40 82.08<br />
21-31 895.15 941.86 909.55 240.12 360 95.04 90.29<br />
1-10 602.19 696.98 673.08 161.54 360 86.40 82.08<br />
11-20 471.06 545.20 526.50 126.36 360 86.40 82.08<br />
21-30 623.14 721.23 696.49 167.16 360 86.40 82.08<br />
1-10 370.91 429.30 414.57 99.50 360 86.40 82.08<br />
11-20 227.52 263.33 254.30 61.03 254 61.03 61.03<br />
21-31 177.31 186.56 180.16 47.56 180 47.56 47.56<br />
1-10 165.68 191.76 185.18 44.44 185 44.44 44.44<br />
11-20 148.98 172.43 166.52 39.96 167 39.96 39.96<br />
21-30 113.04 130.83 126.34 30.32 126 30.32 30.32<br />
1-10 77.17 89.32 86.26 20.70 86 20.70 20.70<br />
11-20 62.93 72.83 70.33 16.88 70 16.88 16.88<br />
21-31 71.48 75.21 72.63 19.17 73 19.17 19.17<br />
1-10 50.35 58.28 56.28 13.51 56 13.51 13.51<br />
11-20 39.96 46.25 44.66 10.72 45 10.72 10.72<br />
21-31 48.92 51.48 49.71 13.12 50 13.12 13.12<br />
1-10 56.88 65.83 63.57 15.26 64 15.26 15.26<br />
11-20 62.99 72.91 70.41 16.90 70 16.90 16.90<br />
21-28 50.53 73.11 70.60 13.56 71 13.56 13.56<br />
1-10 68.29 79.04 76.33 18.32 76 18.32 18.32<br />
11-20 75.96 87.91 84.90 20.37 85 20.37 20.37<br />
21-31 119.25 125.47 121.17 31.99 121 31.99 31.99<br />
1-10 195.56 226.34 218.58 52.46 219 52.46 52.46<br />
11-20 164.69 190.61 184.07 44.18 184 44.18 44.18<br />
21-30 212.31 245.73 237.30 56.95 237 56.95 56.95<br />
1-10 218.36 252.73 244.06 58.57 244 58.57 58.57<br />
11-20 170.91 197.81 191.02 45.85 191 45.85 45.85<br />
21-31 143.37 150.85 145.68 38.46 146 38.46 38.46<br />
Total 9173.26 2460.72 1854.57 1806.62<br />
Annual<br />
L/F 58.81%<br />
L/F monsoon<br />
(March to Nov.)<br />
72.17%<br />
L/F non-monsoon (Dec<br />
to Feb.)<br />
17.98%<br />
89
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
POWER POTENTIAL STUDY FOR YEAR<br />
17-18<br />
Installed<br />
Capacity<br />
360 Net Head 107 Efficiency 92%<br />
Month DISCHARGE<br />
RESTRICTED RESTRICTED<br />
DISCHARGE UNRESTRICTED UNRESTRICTED<br />
95% m/c<br />
POWER ENERGY<br />
( MCum) ( Qmecs) POWER ( MW) ENERGY ( MU)<br />
Availability<br />
( 360MW) ( MU)<br />
June-<br />
17<br />
1-10<br />
11-20<br />
21-30<br />
126.29<br />
161.87<br />
241.65<br />
146.16<br />
187.34<br />
279.69<br />
141.15<br />
180.92<br />
270.09<br />
33.88<br />
43.42<br />
64.82<br />
141<br />
181<br />
270<br />
33.88<br />
43.42<br />
64.82<br />
33.88<br />
43.42<br />
64.82<br />
1-10 273.86 316.97 306.09 73.46 306 73.46 73.46<br />
July-17 11-20 530.15 613.60 592.55 142.21 360 86.40 82.08<br />
21-31 725.58 763.45 737.26 194.64 360 95.04 90.29<br />
1-10 729.16 843.94 814.99 195.60 360 86.40 82.08<br />
Aug-17 11-20 968.00 1120.37 1081.94 259.67 360 86.40 82.08<br />
21-31 1272.71 1339.13 1293.19 341.40 360 95.04 90.29<br />
1-10 964.54 1116.37 1078.07 258.74 360 86.40 82.08<br />
Sep-17 11-20 682.39 789.80 762.71 183.05 360 86.40 82.08<br />
21-30 745.79 863.18 833.57 200.06 360 86.40 82.08<br />
1-10 338.93 392.29 378.83 90.92 360 86.40 82.08<br />
Oct-17 11-20 369.78 427.98 413.30 99.19 360 86.40 82.08<br />
21-31 319.62 336.30 324.77 85.74 325 85.74 85.74<br />
1-10 173.26 200.53 193.65 46.48 194 46.48 46.48<br />
Nov-17 11-20 104.23 120.63 116.49 27.96 116 27.96 27.96<br />
21-30 71.74 83.03 80.19 19.24 80 19.24 19.24<br />
1-10 72.42 83.82 80.94 19.43 81 19.43 19.43<br />
Dec-17 11-20 60.97 70.56 68.14 16.35 68 16.35 16.35<br />
21-31 69.07 72.67 70.18 18.53 70 18.53 18.53<br />
1-10 62.71 72.59 70.10 16.82 70 16.82 16.82<br />
Jan-18 11-20 63.88 73.94 71.40 17.14 71 17.14 17.14<br />
21-31 66.62 70.10 67.70 17.87 68 17.87 17.87<br />
1-10 69.43 80.36 77.60 18.62 78 18.62 18.62<br />
Feb-18 11-20 49.99 57.85 55.87 13.41 56 13.41 13.41<br />
21-28 59.25 85.71 82.77 15.89 83 15.89 15.89<br />
1-10 101.24 117.17 113.15 27.16 113 27.16 27.16<br />
Mar-18 11-20 83.88 97.08 93.75 22.50 94 22.50 22.50<br />
21-31 80.38 84.58 81.67 21.56 82 21.56 21.56<br />
1-10 108.90 126.05 121.72 29.21 122 29.21 29.21<br />
Apr-18 11-20 103.55 119.85 115.73 27.78 116 27.78 27.78<br />
21-30 153.70 177.89 171.79 41.23 172 41.23 41.23<br />
1-10 163.72 189.50 182.99 43.92 183 43.92 43.92<br />
May-18 11-20 120.47 139.43 134.65 32.32 135 32.32 32.32<br />
21-31 108.37 114.02 110.11 29.07 110 29.07 29.07<br />
Total 10398.07 2789.27 1705.08 1661.02<br />
Annual<br />
L/F 54.07%<br />
L/F monsoon<br />
(March to Nov.)<br />
65.28%<br />
L/F non-monsoon (Dec<br />
to Feb.)<br />
19.81%<br />
90
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
POWER POTENTIAL STUDY FOR YEAR<br />
18-19<br />
Installed<br />
Capacity<br />
360 Net Head 107 Efficiency 92%<br />
Month DISCHARGE<br />
RESTRICTED RESTRICTED<br />
DISCHARGE UNRESTRICTED UNRESTRICTED<br />
95% m/c<br />
POWER ENERGY<br />
( MCum) ( Qmecs) POWER ( MW) ENERGY ( MU)<br />
Availability<br />
( 360MW) ( MU)<br />
June-<br />
18<br />
1-10<br />
11-20<br />
21-30<br />
115.84<br />
151.88<br />
292.56<br />
134.07<br />
175.79<br />
338.61<br />
129.48<br />
169.76<br />
327.00<br />
31.07<br />
40.74<br />
78.48<br />
129<br />
170<br />
327<br />
31.07<br />
40.74<br />
78.48<br />
31.07<br />
40.74<br />
78.48<br />
1-10 343.80 397.91 384.26 92.22 360 86.40 82.08<br />
July-18 11-20 654.00 756.95 730.98 175.44 360 86.40 82.08<br />
21-31 647.43 681.22 657.85 173.67 360 95.04 90.29<br />
1-10 404.89 468.63 452.55 108.61 360 86.40 82.08<br />
Aug-18 11-20 374.32 433.24 418.37 100.41 360 86.40 82.08<br />
21-31 416.68 438.42 423.38 111.77 360 95.04 90.29<br />
1-10 385.73 446.45 431.14 103.47 360 86.40 82.08<br />
Sep-18 11-20 355.99 412.03 397.89 95.49 360 86.40 82.08<br />
21-30 279.84 323.88 312.77 75.07 313 75.07 75.07<br />
1-10 395.29 457.51 441.82 106.04 360 86.40 82.08<br />
Oct-18 11-20 395.79 458.09 442.38 106.17 360 86.40 82.08<br />
21-31 259.80 273.36 263.99 69.69 264 69.69 69.69<br />
1-10 141.23 163.46 157.85 37.88 158 37.88 37.88<br />
Nov-18 11-20 89.13 103.16 99.62 23.91 100 23.91 23.91<br />
21-30 77.08 89.22 86.16 20.68 86 20.68 20.68<br />
1-10 92.01 106.50 102.84 24.68 103 24.68 24.68<br />
Dec-18 11-20 81.73 94.59 91.35 21.92 91 21.92 21.92<br />
21-31 84.35 88.76 85.71 22.63 86 22.63 22.63<br />
1-10 65.01 75.25 72.66 17.44 73 17.44 17.44<br />
Jan-19 11-20 65.47 75.77 73.18 17.56 73 17.56 17.56<br />
21-31 66.84 70.33 67.91 17.93 68 17.93 17.93<br />
1-10 81.40 94.21 90.98 21.83 91 21.83 21.83<br />
Feb-19 11-20 88.22 102.11 98.61 23.67 99 23.67 23.67<br />
21-28 74.59 107.91 104.21 20.01 104 20.01 20.01<br />
1-10 83.23 96.33 93.03 22.33 93 22.33 22.33<br />
Mar-19 11-20 110.21 127.56 123.18 29.56 123 29.56 29.56<br />
21-31 153.48 161.49 155.95 41.17 156 41.17 41.17<br />
1-10 171.25 198.21 191.41 45.94 191 45.94 45.94<br />
Apr-19 11-20 235.29 272.33 262.99 63.12 263 63.12 63.12<br />
21-30 170.14 196.93 190.17 45.64 190 45.64 45.64<br />
1-10 271.18 313.86 303.10 72.74 303 72.74 72.74<br />
May-19 11-20 358.46 414.88 400.65 96.16 360 86.40 82.08<br />
21-31 292.99 308.28 297.71 78.59 298 78.59 78.59<br />
Total 8327.15 2233.75 1931.97 1883.59<br />
Annual<br />
L/F 61.26%<br />
L/F monsoon<br />
(March to Nov.)<br />
73.41%<br />
L/F non-monsoon (Dec<br />
to Feb.)<br />
24.13%<br />
91
Installed<br />
Capacity<br />
POWER POTENTIAL STUDY FOR YEAR<br />
19-20<br />
360 Net Head 107 Efficiency 92%<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Month DISCHARGE<br />
RESTRICTED RESTRICTED<br />
DISCHARGE UNRESTRICTED UNRESTRICTED<br />
95% m/c<br />
POWER ENERGY<br />
( MCum) ( Qmecs) POWER ( MW) ENERGY ( MU)<br />
Availability<br />
( 360MW) ( MU)<br />
1-10 528.21 611.35 590.38 141.69 360 86.40 82.08<br />
11-20 808.83 936.14 904.03 216.97 360 86.40 82.08<br />
June-<br />
19<br />
July-19<br />
Aug-19<br />
Sep-19<br />
Oct-19<br />
Nov-19<br />
Dec-19<br />
Jan-20<br />
Feb-20<br />
Mar-20<br />
Apr-20<br />
May-20<br />
21-30 819.88 948.94 916.39 219.93 360 86.40 82.08<br />
1-10 965.63 1117.63 1079.29 259.03 360 86.40 82.08<br />
11-20 1169.90 1354.05 1307.60 313.82 360 86.40 82.08<br />
21-31 1694.17 1782.59 1721.44 454.46 360 95.04 90.29<br />
1-10 485.71 562.16 542.88 130.29 360 86.40 82.08<br />
11-20 543.17 628.67 607.10 145.70 360 86.40 82.08<br />
21-31 960.97 1011.12 976.43 257.78 360 95.04 90.29<br />
1-10 625.13 723.53 698.71 167.69 360 86.40 82.08<br />
11-20 507.62 587.53 567.37 136.17 360 86.40 82.08<br />
21-30 341.17 394.87 381.33 91.52 360 86.40 82.08<br />
1-10 300.22 347.47 335.56 80.53 336 80.53 80.53<br />
11-20 300.89 348.26 336.31 80.71 336 80.71 80.71<br />
21-31 302.81 318.61 307.68 81.23 308 81.23 81.23<br />
1-10 137.76 159.44 153.97 36.95 154 36.95 36.95<br />
11-20 83.04 96.11 92.82 22.28 93 22.28 22.28<br />
21-30 82.12 95.04 91.78 22.03 92 22.03 22.03<br />
1-10 100.33 116.13 112.14 26.91 112 26.91 26.91<br />
11-20 71.97 83.30 80.44 19.31 80 19.31 19.31<br />
21-31 68.37 71.94 69.47 18.34 69 18.34 18.34<br />
1-10 56.91 65.87 63.61 15.27 64 15.27 15.27<br />
11-20 46.75 54.11 52.26 12.54 52 12.54 12.54<br />
21-31 49.02 51.58 49.81 13.15 50 13.15 13.15<br />
1-10 41.67 48.22 46.57 11.18 47 11.18 11.18<br />
11-20 41.57 48.11 46.46 11.15 46 11.15 11.15<br />
21-29 47.85 61.54 59.42 12.84 59 12.84 12.84<br />
1-10 50.92 58.93 56.91 13.66 57 13.66 13.66<br />
11-20 60.08 69.54 67.15 16.12 67 16.12 16.12<br />
21-31 73.79 77.64 74.98 19.79 75 19.79 19.79<br />
1-10 88.50 102.43 98.91 23.74 99 23.74 23.74<br />
11-20 91.40 105.79 102.16 24.52 102 24.52 24.52<br />
21-30 131.75 152.49 147.26 35.34 147 35.34 35.34<br />
1-10 171.63 198.65 191.83 46.04 192 46.04 46.04<br />
11-20 171.68 198.70 191.89 46.05 192 46.05 46.05<br />
21-31 243.33 256.03 247.25 65.27 247 65.27 65.27<br />
Total 12264.77 3290.01 1809.03 1756.33<br />
Annual<br />
L/F 57.36%<br />
L/F monsoon<br />
(March to Nov.)<br />
70.22%<br />
L/F non-monsoon (Dec<br />
to Feb.)<br />
18.09%<br />
92
8.0 INTRODUCTION<br />
CHAPTER - VIII<br />
POWER EVACUATION<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
The <strong>Nalo</strong> H.E. Project is envisaged for the installation <strong>of</strong> four generating<br />
units <strong>of</strong> 90 MW each, operating under a rated net head <strong>of</strong> 107 m in<br />
Surface type power house. The generation voltage is proposed to be<br />
11 KV. This voltage will be stepped up to 400 KV voltage level through<br />
single-phase Generator step-up transformers. The Generator step-up<br />
transformers will be connected to 400 KV outdoor conventional switchyard<br />
through overhead conductor. The power from <strong>Nalo</strong> H.E. Project would be<br />
fed to the North-Eastern Grid to be ultimately connected to the National<br />
Grid through EHV/HVDC transmission lines. Provision <strong>of</strong> two outgoing<br />
bays has been kept in Switchyard for 360 MW power evacuation from this<br />
project.<br />
8.1 EXISTING POWER EVACUATION FACILITIES<br />
<strong>Power</strong> system is controlled by the Electricity boards/<br />
Departments/Corporations <strong>of</strong> the states <strong>of</strong> Assam, Meghalaya, Arunachal<br />
Pradesh, Nagaland, Manipur, Mizoram and Tripura.<br />
<strong>Power</strong> System Networks <strong>of</strong> PSUs located in the region are two 400KV line<br />
going to Balipara from Dikrong (Ranga Nadi) power station and two<br />
132KV line are also emanating from Dikrong Switchyard and feeding to<br />
Along and Nirjuli areas.<br />
93
8.2 PROPOSED EVACUATION ARRANGEMENT<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
It is proposed to provide two outgoing bays for evacuating power at 400<br />
KV level from <strong>Nalo</strong> H.E. Project. This power would be pooled to the<br />
pooling point planned at Daporijo through one No. 400 KV Double circuit<br />
transmission line with Twin moose conductor (Plate 8.1). The power from<br />
Oju-I, Oju-II, Niare & Naba H. E. Projects would also be pooled at Daporijo<br />
pooling point. The power from Daporijo pooling point would be ultimately<br />
pooled directly through HVDC Link to the National Grid. Further, it is to<br />
mention that the cost <strong>of</strong> the transmission network <strong>of</strong> 75 km distance from<br />
<strong>Nalo</strong> H. E. Project to Daporijo pooling point & other end equipment at<br />
Daporijo pooling point have been considered. The <strong>Power</strong> evacuation<br />
system for Subansiri Basin is enclosed herewith for reference (Plate 8.2).<br />
94
9.0 INTRODUCTION<br />
General<br />
CHAPTER- IX<br />
ENVIRONMENTAL ASPECTS<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
The height <strong>of</strong> the concrete gravity dam would be 125 m above the deepest<br />
foundation level on river Subansiri/ Singit in Arunachal Pradesh. The<br />
surface powerhouse will have a generation capacity <strong>of</strong> 360 MW.<br />
Location<br />
The dam site is proposed to be located 1.6 km u/s <strong>of</strong> Ledi Ishi Nallah <strong>of</strong><br />
Upper Subansiri district in Arunachal Pradesh. The nearest BG railhead is<br />
Nagaon in Assam and the nearest airport is at Lilabari (North Lakhimpur).<br />
9.1 PHYSICAL ENVIRONMENT<br />
9.1.1 Climate/Meteorology<br />
The climate in the entire region is humid and fairly uniform. Thick mist<br />
formation is a feature during the early morning hours which completely<br />
envelope the area and block the sun. Temperature variation is observed<br />
with increasing altitude. It varies between 39.5° C and 11.5° C as observed<br />
at Menga. The relative humidity ranges between 94% and 62%. Premonsoon<br />
rains occur from mid-February. The average annual rainfall is<br />
about 2810 mm.<br />
95
9.1.2 Topography<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
It is an enormous virgin terrain <strong>of</strong> rugged mountains, covered by insatiable<br />
forests fed by copious rains. A number <strong>of</strong> hilly streams intersect the region<br />
with gradual altitudinal variation.<br />
9.1.3 Soil<br />
The general and average soil character <strong>of</strong> cultivable land in the district is<br />
mainly alluvial and composed <strong>of</strong> a mixture <strong>of</strong> sand (coarse to fine) and clay<br />
in varying proportions. Soils in the area are results <strong>of</strong> degradation and<br />
weathering <strong>of</strong> rocks as well as depositional features in the form <strong>of</strong> river<br />
terraces. The soil on the slopes is mainly composed <strong>of</strong> silt and support<br />
good vegetation. The clayey soils formed on river terrace due to river<br />
deposits are fertile and has been developed into paddy fields by the local<br />
inhabitants.<br />
9.1.4 Geology<br />
The entire project is located in broadly two rock types i.e Biotite gneiss and<br />
Biotite Schist. The dam site has been chosen in a relatively straight stretch<br />
<strong>of</strong> the river where rock is exposed on left bank as steep rocky escarpment<br />
but right bank is covered under overburden and vegetation. From regional<br />
geological assessment it is expected that dam, diversion tunnel & desilting<br />
chambers will be housed in biotite gneiss <strong>of</strong> Gelensiniak Formation<br />
whereas powerhouse complex and most <strong>of</strong> the part <strong>of</strong> HRT will be housed<br />
in Biotite Schist <strong>of</strong> Nacho Formation.<br />
96
9.1.5 Seismicity<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
The entire northeast region has been classified in zone-V <strong>of</strong> the seismic<br />
zoning map <strong>of</strong> India. Though MBT and MCT associated with the tectonic<br />
activity are located at a far distance from the project area and the proposed<br />
project area has not experienced any major earthquake shocks in the<br />
recent past, adequate site specific seismic design parameter will have to be<br />
determined for safe design <strong>of</strong> the civil structures.<br />
9.1.6 Catchment Area<br />
The <strong>Nalo</strong> basin lies between longitude 91° 45’E & 93° 49’E and between<br />
latitude 27° 50’N & 29° 00’ N. The total catchment area upto the proposed<br />
dam site is about 14500 sq km. The vast stretch <strong>of</strong> the catchment<br />
possesses mainly sub-tropical forests, which is evergreen and dense in<br />
nature. The permanent snow cover has been assumed above an elevation<br />
<strong>of</strong> 4500 m.<br />
9.1.7 Drainage Pattern<br />
Subansiri is a major right bank tributary <strong>of</strong> river Brahmaputra. It originates<br />
in Tibet beyond the Great Himalayan range (Central Himalaya) at an<br />
altitude <strong>of</strong> around 5340 m. Several mountain streams or rather a big “Chu”<br />
family <strong>of</strong> streams drains into the main valley. The principal stream<br />
belonging to this “Chu” group is Nye Chu, which may be considered as the<br />
main source <strong>of</strong> river Subansiri originating from the snow clad peaks <strong>of</strong><br />
Krakang, Shaota, Baru and Mata (EL 5389 m). Nye Chu is then joined by<br />
another stream Laro Chu near Chayal thereby taking the name <strong>of</strong> Chayal<br />
Chu.<br />
After crossing the international boundary as the river approaches the Miri<br />
Hills in Arunachal Pradesh, it runs in an unexplored valley. The course <strong>of</strong><br />
97
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
the main river and its tributaries are more or less marked on conjectural<br />
lines rather than by accurate mapping. In its early reaches as the river<br />
gathers more and more torrents in the Himalayas, it rushes through deep<br />
gorges, far below the snow-tipped mountain peaks.<br />
9.1.8 Land Use Pattern<br />
About 740 ha <strong>of</strong> land are going to be acquired for the project out <strong>of</strong> which<br />
about 285 ha are private land and 455 ha is falling under forestland. About<br />
300 ha would come under submergence out <strong>of</strong> which 150 ha falls under<br />
private land and another 150 ha under forest land category. The land use<br />
pattern <strong>of</strong> the area is studied using satellite data. These studies have been<br />
carried out through NRSA, Hyderabad who would use IRS 1C PAN + LISS<br />
III merged satellite data.<br />
Based on the analysis <strong>of</strong> satellite data and other available<br />
ancillary information, the following outputs were generated by NRSA<br />
(Annexure 9.1):<br />
Map 1 (a) Shows IRS 1 C PAN + LISS III merged satellite image <strong>of</strong> 26 th<br />
December, 2002 on 1:50,000 scale covering 7 km radius from the dam site<br />
overlaid with FRL , location <strong>of</strong> dam site and power house.<br />
Map 1(b) Shows satellite derived landuse- landcover map on 1:50,000<br />
scale covering 7 km radius from the dam site overlaid with FRL , location <strong>of</strong><br />
dam site and power house. Land use /land cover map shows the following<br />
categories: Forest (High and Medium Dense Forest), Agricultural Land,<br />
Open Scrub, Barren and Rock Outcrop, Snow, River Course/ Dry River<br />
Bed.<br />
Map 1(c) Shows the landuse- landcover classes and their corresponding<br />
area statistics in hectares within the submergence area on 1:25000 scale<br />
overlaid with FRL , location <strong>of</strong> dam site and power house.<br />
98
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Map 1 (d) Shows the location <strong>of</strong> the National parks / Wildlife Sanctuaries<br />
vis-à-vis the location <strong>of</strong> the dam/ <strong>Power</strong> House and 7 km radius area<br />
around the dam site.<br />
Following broad conclusion can be drawn from studies conducted by<br />
NRSA<br />
(i) Total area under submergence at proposed FRL <strong>of</strong> 765 m. (above<br />
MSL) is estimated to be 283.80 ha ( Table.9.1).<br />
(ii) It is observed that vegetation cover is mostly dominated by forest<br />
category which is 146 ha ( 51% <strong>of</strong> the submergence area ). Entire<br />
forest vegetation is classified as high and medium dense forest in the<br />
submergence area.<br />
Table 9.1<br />
Landuse-landcover Information within the Submergence Area<br />
S.No Landuse-landcover<br />
Category<br />
Area under<br />
submergence (Ha)<br />
% <strong>of</strong> the total<br />
submergence area<br />
1 High Dense Forest 118.36 41.71<br />
2. Medium Dense Forest 27.49 9.69<br />
3. Low Dense Forest Nil Nil<br />
4. Open Scrub 56.78 20.01<br />
5. Barren / Rock Outcrop 4.10 1.44<br />
6. Snow Nil Nil<br />
7. Agricultural Land 1.14 0.40<br />
8. Human Settlement 0.49 0.17<br />
9. River Course including dry<br />
river bed<br />
75.44 26.58<br />
Total 283.80 100.00<br />
99
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
(iii) Submergence <strong>of</strong> forest vegetation (High dense and Medium dense)<br />
may be <strong>of</strong> some immediate concern which needs to be rehabilitated<br />
with alternate afforestation measures within the vicinity <strong>of</strong> the dam<br />
site when the project scheme is taken up for implementation.<br />
(iv) There is very little 1.14 ha <strong>of</strong> (Insignificant) agricultural area present<br />
within the proposed submergence area which is a positive sign to<br />
develop the proposed hydropower site.<br />
Table 9.2<br />
Landuse-landcover Information within the 7 Km Radius from<br />
the Dam site at <strong>Nalo</strong><br />
S.No Landuse-landcover<br />
Category<br />
Total Area ( ha)<br />
% <strong>of</strong> the total<br />
area<br />
1 High Dense Forest 12523.73 81.35<br />
2. Medium Dense Forest 1585.85 10.30<br />
3. Low Dense Forest Nil Nil<br />
4. Open Scrub 980.42 6.37<br />
5. Barren / Rock Outcrop 80.17 0.52<br />
6. Snow 7.24 0.05<br />
7. Agricultural Land 33.39 0.22<br />
8. Human Settlement 13.46 0.09<br />
9. River Course including dry<br />
river bed<br />
169.74<br />
1.10<br />
Total area 15394.00 100.00<br />
100
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
(v) Open scrub land is the next dominant land use – land cover category<br />
after the forest and constitutes 20% <strong>of</strong> the submergence area. This is<br />
followed by Barren / Rock outcrop land which is 1.44%.<br />
(vi) There are no surface water bodies other than the river course. The<br />
area under river course including dry river bed is estimated to be<br />
75.44 ha, which constitutes 27% <strong>of</strong> the total submergence area.<br />
(vii) It is also observed that the submergence area at EL + 765 m (FRL)<br />
above MSL is likely to affect (Inundate) few isolated settlements.<br />
Hence, a close look at the ground is required to assess the exact<br />
impact.<br />
(viii) Since 7 Km radius around the dam site was considered as the area<br />
<strong>of</strong> study, efforts were made to check whether the geo-coordinates <strong>of</strong><br />
any Wildlife Sanctuary is falling within the area <strong>of</strong> study. The map<br />
No. 1(d) (Annexure-9.1) explains the location <strong>of</strong> the Sanctuaries visà-vis<br />
the dam site and the power house.<br />
(ix) The nearest National park is Mouling which is about 93 Km from the<br />
dam site. The nearest sanctuaries are Kane, Itanagar, Pakhui and<br />
D’Ering memorial which are about at distance <strong>of</strong> 115 km, 145 km,<br />
156 km and 169 km respectively. So it is observed that the dam site<br />
is more than 90 km away from the National Park and Sanctuaries.<br />
Hence, proposed development <strong>of</strong> the site is least likely to have<br />
impact on them.<br />
Further, results <strong>of</strong> Land use- Landcover study covering an area <strong>of</strong> 7 km<br />
radius around the damsite are presented in Table 9.2.<br />
101
9.1.9 Water Quality<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Population density along the reservoir is not very high. Scattered huts<br />
along the road have been observed. People are mostly engaged in<br />
agriculture. Since there is no industrial unit in or around the proposed<br />
project area and also the fact that the inhabitants are still following their<br />
age-old methods <strong>of</strong> cultivation, it is assumed that there would be no such<br />
chemical pollution in the river. However, a detailed water quality analysis<br />
would be carried out during the environmental survey to ascertain the<br />
quality <strong>of</strong> water and necessary measures would be adopted accordingly to<br />
prevent its deterioration.<br />
9.2 BIOTIC ENVIRONMENT<br />
9.2.1 Flora<br />
The predominant vegetation is sub-tropical type and is basically dense and<br />
evergreen in nature. The floristic components observed in the area<br />
dominated by tall trees like Oblongum, Actinodaphne obovata, Alnus<br />
nepalnensis, Beilschemiedia roxburghiana, Bytineria grandiflora, Callicarpa<br />
arborea, Castanopsis indica, Dichroa febrifuga, Kydia calycina, Magnolia<br />
pterocarpa, Sauraria punduana, Schima wallichii, Sterculia hamiltonii, etc.<br />
The next storey is composed <strong>of</strong> small trees like Lepisanthes senegalensis,<br />
Capparis muliflora, Photinia integrifolia.etc.<br />
Third storey is comprised <strong>of</strong> small trees and shrubs like Eurya acuminate,<br />
Myrsina semiserrata, Camellia candata, etc. Comman climbers generally<br />
occurring in the area are Clematis acuminate, holboelia latifolia, Tinospors<br />
sinensis, etc.<br />
102
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
The ground flora formed by the dense growth <strong>of</strong> shrubs and herbs is<br />
represented by Cassia mimosoides, Drymaria diandra, Mahonia<br />
acanthifolia, Plectranthus griffithii, Solanum erianthum, Sophora acuminate,<br />
Tephrosia candida, Vernonia saligna, Viburnum foetidum, Begonia pocta,<br />
Oxalis corniculata, O. corymbosa, Impatiens spp.Lobelia spp.,etc.<br />
These forests shows good diversity <strong>of</strong> epiphytic flora including a variety <strong>of</strong><br />
ferns and a number <strong>of</strong> Orchid species <strong>of</strong> Cymbidium, Bulbophyllum,<br />
Dedrobium, Oberonia etc.<br />
The excerpts from preliminary report <strong>of</strong> Botanical Survey <strong>of</strong> India (BSI),<br />
Itanagar, Arunachal Pradesh is placed at Annexure 9.2.<br />
9.2.2 Fauna and Wildlife<br />
The entire project area has fairly good forest coverage. It serves as a<br />
habitat for many faunal species. But, with progress <strong>of</strong> time due to increases<br />
in human interference, shifting cultivation and other activities, wildlife has<br />
been affected. However some <strong>of</strong> the faunal species found in the area are as<br />
follows:<br />
Mammalia (Mammals)<br />
Talpa micrura (Himalayan Mole), Suncus murinus (House Shrew), Pteropus<br />
gigantcus (Indian Flying Fox), Macaca mulata (Rhesus Monkey), Canis<br />
aureus (Golden Jackal), Vulpes vulpes (Red Fox), Viverra zibetha (Large<br />
Indian Civet), Felis chaus (Jungle Cat), Prionailurus bengalensis (Leopard<br />
Cat), Rotufa bicolor (Malayan Giant Squirrel).<br />
Aves (Birds)<br />
Acridotheres grandis (Great Myna), Picus canus (Grey- Headed<br />
Woodpeeker), Upupa epops (Eurarsian Hoopoe), Ninox scutulata (Brown<br />
Hawk-Owl), Venellus indicus (Red Wattled Lapwing), Gracula religiosa (Hill<br />
Myna).<br />
103
Pisces (Fish)<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Barilius vagra, Puntius chola, Puntius sophore, Tor putitora, Mystus<br />
montanus, Psilorhynchus balitora, Channa striatus, Colisa fasciatus,<br />
Mastacembelus pancalus.<br />
Amphibia (Frogs)<br />
Rana danielli, Amolops gerbillus, Microhyla rubra.<br />
Reptilia (Snakes)<br />
Bungarus fasciatus, Elaphe radiata, Ptys korros, Xenohrophis piscator,<br />
Oligodon albocinectus.<br />
Lepidoptera (Butterflies)<br />
Phalanta phalantha (Common Leopard), Papilio helenus (Red Helen),<br />
Papilio demoleus (Lime Butterfly), Eureuma hecabe (Common Grass<br />
Yellow).<br />
The species listed above are commonly distributed. However, the frog<br />
species reported above are rarely found. Detail survey <strong>of</strong> the area in<br />
different seasons <strong>of</strong> the year is likely to add more knowledge on the fauna<br />
<strong>of</strong> the project area.<br />
The preliminary report from Zoological Survey <strong>of</strong> India (ZSI), Itanagar and<br />
from Department <strong>of</strong> Fishery, Arunachal Pradesh are enclosed as<br />
Annexure 9.3 & Annexure 9.4 respectively.<br />
Thus from the above list it is evident that the species found are generally<br />
common fauna usually encountered in such ecological condition. There is<br />
no endangered or threatened species observed or recorded from the<br />
project area so far. However, a detailed survey <strong>of</strong> the area in different<br />
seasons <strong>of</strong> the year may yield a different picture on the faunal diversity <strong>of</strong><br />
104
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
the area and which may be useful in preparation <strong>of</strong> the environmental<br />
impact assessment for the proposed project<br />
9.3 PREDICTION OF ENVIRONMENTAL IMPACTS<br />
Based on above baseline data and project features, the potential impacts<br />
that are expected as a result <strong>of</strong> the proposed project are summarized as<br />
follows<br />
9.3.1 Impacts on land environment<br />
About 740 ha would be required for the proposed project out <strong>of</strong> which 300<br />
ha would come under submergence. About 455 ha <strong>of</strong> forest land would get<br />
affected in the process. With the acquisition <strong>of</strong> forestland, the local<br />
population, dependent on these forests, might get affected. Most <strong>of</strong> the<br />
environmental impacts resultant <strong>of</strong> construction work is temporary in nature<br />
rarely lasting beyond the construction period. All these issues are to be<br />
properly addressed so that the long-term effects, if any, can be minimized.<br />
9.3.2 Impact on Water Environment<br />
The construction <strong>of</strong> a reservoir will replace the riverine eco-system by a<br />
lacustrine ecosystem. The vectors <strong>of</strong> various diseases breed in shallow<br />
areas are not very far from reservoir margins. The breeding site for<br />
mosquitoes and other vectors in impounded water is in direct proportion to<br />
the length <strong>of</strong> the shoreline. The construction <strong>of</strong> the reservoir would increase<br />
the shoreline many times as compared to the pre-project shoreline <strong>of</strong><br />
various rivers and tributaries under submergence. In the proposed project<br />
area, malaria is the prominent vector borne disease. There are chances<br />
that its incidence may increase as the proposed project is a storage<br />
scheme. Because <strong>of</strong> the regulated flow <strong>of</strong> water some changes is also likely<br />
in the aquatic environment in the downstream areas <strong>of</strong> the project. The<br />
105
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
important changes that are likely to happen in this area are: reduction in<br />
flow rate changes in water temperature, reduction in population <strong>of</strong><br />
stenothermal species (species adapted to small temperature range) and<br />
increase in population <strong>of</strong> eurythermal species (species adopted to higher<br />
temperature range).<br />
9.3.3 Impacts on Air and Noise Environment<br />
Impacts on the air environment are limited to the construction period <strong>of</strong> a<br />
hydropower project. The major sources <strong>of</strong> air pollution during construction<br />
phase are emission from crushers, DG sets, construction equipments etc.<br />
Thus local air pollution (including dust and odour) will result from the<br />
operation <strong>of</strong> plant machinery and traffic. Noise and vibration due to<br />
construction activities (e.g. blasting, machinery and traffic) may disturb local<br />
wildlife and human populations. However, there will be only short-term<br />
increase in emissions like SO2 and Suspended Particulate Matters (SPM)<br />
during the construction period <strong>of</strong> the project. The level <strong>of</strong> noise would also<br />
decrease substantially once the construction phase is over. Hence no<br />
major impact is anticipated on this account.<br />
9.3.4 Impacts on flora and fauna<br />
Due to construction <strong>of</strong> dam about 300 ha <strong>of</strong> land will be inundated out <strong>of</strong><br />
which 150 ha is falling under forest land category. The direct impact <strong>of</strong><br />
construction activity <strong>of</strong> a water resources project in a hilly terrain is<br />
generally limited to the vicinity <strong>of</strong> the construction sites. This may alter the<br />
local diversity <strong>of</strong> flora and also affect habitat available for fauna. Changes<br />
to, or loss <strong>of</strong> habitat will affect areas used for mating, breeding, nursing,<br />
moulting, feeding, and drinking for both resident and migratory wildlife.<br />
106
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
The extent and severity <strong>of</strong> these effects will vary according to the existing<br />
habitat and the particular species involved which would be known after<br />
detailed study is done on flora and fauna during the comprehensive<br />
EIA/EMP study and suitable mitigation measures would be formulated and<br />
implemented in consultation with the State Forest Department <strong>of</strong> Arunachal<br />
Pradesh.<br />
9.3.5 Impacts on Avifauna<br />
The construction <strong>of</strong> the proposed dam will lead to formation <strong>of</strong> a reservoir,<br />
which will have a fluctuation in the water level, which precisely means the<br />
reservoir bank will remain wet throughout the year. Due to such reasons,<br />
some aquatic weeds / grasses may grow along the reservoir banks. Such<br />
conditions are generally ideal for various kinds <strong>of</strong> birds, especially water<br />
birds. However because <strong>of</strong> the presence <strong>of</strong> a good habitat it is quite likely<br />
that water birds will flock in this area in a large number. The birds from cold<br />
climatic areas could also use this area during the winter season.<br />
9.3.6 Impacts on Fishes<br />
A dam will fragment and isolate upstream resident fish. The resident<br />
species may congregate in the tail water release site. Fish from upstream<br />
will occasionally sweep downstream during the monsoon, stay in the tail<br />
water or swim further downstream. A dam may obstruct the route <strong>of</strong> the<br />
long and mid-distance migratory fish. There may be an impact on the fish<br />
composition due to construction <strong>of</strong> dam. A detailed fishery study would be<br />
conducted during the EIA/EMP study to determine the likely impacts and<br />
suitable mitigatory measures would be adopted.<br />
107
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
9.3.7 Impacts on Socio-Economic Environment (Resettlement &<br />
Rehabilitation)<br />
Due to acquisition <strong>of</strong> 285 ha <strong>of</strong> private land, there is a possibility that some<br />
families would get affected either partially or fully. To ascertain the extent<br />
<strong>of</strong> impact due to this proposed project, a detailed socio-economic survey<br />
would be carried out, as a part <strong>of</strong> the EIA/EMP study to ascertain the<br />
degree and extent <strong>of</strong> impact and accordingly a suitable rehabilitation<br />
package would be formulated. During the construction <strong>of</strong> the project the<br />
basic problem relates to management <strong>of</strong> large population that migrate to the<br />
area in search <strong>of</strong> jobs and other allied activities. Thus migration <strong>of</strong> a<br />
population having different cultural, ethnic and social backgrounds has its<br />
own advantages and disadvantages. Exchange <strong>of</strong> ideas, cultures between<br />
various groups <strong>of</strong> people would result in a healthy bonding amongst the<br />
population at large. A new culture having a distinct socio-economic status<br />
with an entity <strong>of</strong> its own would develop. As a result <strong>of</strong> this project there<br />
would be all-round development <strong>of</strong> the region.<br />
9.3.8 Impact on Archaeological structures/Sanctuaries or National<br />
Parks<br />
As per the initial survey there is neither any archaeological structure nor<br />
any Sanctuary or National Park that are likely to get affected due to the<br />
project directly or indirectly.<br />
9.4 ENVIRONMENTAL MANAGEMENT PLANS<br />
The objective <strong>of</strong> the Environmental Management Plan (EMP) is to<br />
ameliorate the negative impacts <strong>of</strong> a developmental project. The most<br />
reliable way to ensure proper implementation <strong>of</strong> these management plans is<br />
108
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
to integrate the same with various processes involved during project<br />
planning, designing, construction and operation phases. Based on the<br />
assessment <strong>of</strong> environmental impacts, following management plans will be<br />
formulated:<br />
Catchment Area Treatment<br />
Compensatory Afforestation<br />
Wildlife Conservation<br />
Resettlement and Rehabilitation<br />
Public Health Management System<br />
Muck Disposal<br />
Fishery Management<br />
Restoration <strong>of</strong> Construction Area<br />
Green Belt Development<br />
Free Fuel Provision<br />
Disaster Management<br />
MOEF Restriction on Construction <strong>of</strong> dams in Subansiri Basin<br />
It is stated that <strong>Ministry</strong> <strong>of</strong> Environment and Forest (MOEF) vide their letter<br />
No: 6-I/2002 WL-I dated 27.05.2003 regarding diversion <strong>of</strong> 42 ha <strong>of</strong> land<br />
falling within the Tale Wildlife Sanctuary for construction <strong>of</strong> Subansiri Lower<br />
Project (SLP) has imposed a condition that there would be no construction<br />
<strong>of</strong> dam upstream <strong>of</strong> the Subansiri river in future. As this project is located<br />
upstream <strong>of</strong> Subansiri Lower Project in Subansiri river this condition is<br />
required to be considered while considering the project for preparation <strong>of</strong><br />
DPR.<br />
109
10.0 INTRODUCTION<br />
CHAPTER –X<br />
INFRASTRUCTURE<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
The project is located near <strong>Nalo</strong> village in Upper Subansiri District <strong>of</strong><br />
Arunachal Pradesh. The Dam site is proposed upstream <strong>of</strong> confluence <strong>of</strong><br />
Ledi Ishi nallah with Subansiri. The power house is proposed on the right<br />
bank <strong>of</strong> Subansiri river at about 5 Km (along river course) downstream <strong>of</strong><br />
damsite. Dam site is easily accessible by all weather Daporijo –Limeking<br />
road. Daporijo, the district headquarter <strong>of</strong> Upper Subansiri District is about<br />
120 km from dam site. Project township and its headquarters can be<br />
proposed at Nacho. Nacho is about 10 km (downstream) from dam site<br />
and 5 km from powerhouse site. Itanagar, the state capital is about 460<br />
km from dam site. Project is about 800 km from Guwahati and 400 km<br />
from North Lakhimpur. The project site can be accessed from NH-52<br />
which runs almost parallel to the river Brahmaputra on its North Bank<br />
from Baihata Chariali (near Guwahati) to Murkongselek (Jonai) in Dhemaji<br />
District.<br />
Nearest MG Railhead is North Lakhimpur and Broad Gauge Railhead is at<br />
Nagaon. Nearest Airport is at North Lakhimpur (Lilabari). Presently,<br />
there is tri-weekly air service from Guwahati (Borjhar) to North<br />
Lakhimpur (Lilabari). There are helipads at Daporijo, Nacho and<br />
Limeking nearer to the project area.<br />
Approximate distances and conditions <strong>of</strong> road from/to Project Site is given<br />
in Table 10.1.<br />
110
Sl<br />
No.<br />
Table10.1<br />
Status <strong>of</strong> Road Network connecting Project site<br />
Destination Approx<br />
distance<br />
1 Pahumara<br />
(Take-<strong>of</strong>f point<br />
<strong>of</strong> Road from<br />
NH-52) to<br />
Daporijo<br />
2 Daporijo to<br />
Dengser<br />
damsite<br />
3 Dengser<br />
damsite to<br />
<strong>Nalo</strong> damsite<br />
4 Approach<br />
roads for adit<br />
to<br />
PH<br />
HRT and<br />
Condition <strong>of</strong><br />
Road.<br />
284 Km Single lane black<br />
topped road.<br />
(Maintained by<br />
BRO)<br />
110 km Single lane black<br />
topped road.<br />
(Maintained by<br />
BRO)<br />
15 km Single lane black<br />
topped road.<br />
(Maintained by<br />
BRO)<br />
25 km New proposal.<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Remarks<br />
Provision <strong>of</strong> widening<br />
<strong>of</strong> road and<br />
strengthening <strong>of</strong><br />
bridges has been kept<br />
in FR/DPR <strong>of</strong><br />
Subansiri<br />
Middle/Upper Projects<br />
Provision <strong>of</strong> widening<br />
<strong>of</strong> road and<br />
strengthening <strong>of</strong><br />
bridges has been kept<br />
in PFR <strong>of</strong> Dengser HE<br />
Project.<br />
Provision <strong>of</strong> widening<br />
<strong>of</strong> road and<br />
strengthening <strong>of</strong><br />
bridges has been kept<br />
in PFR <strong>of</strong> <strong>Nalo</strong> HEP.<br />
111
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Provision for widening <strong>of</strong> existing road from Pahumara/ Kimin to Daporijo<br />
has been kept in cost estimates <strong>of</strong> Subansiri Middle /Upper Projects and<br />
provision for widening and strengthening <strong>of</strong> roads & bridges from Daporijo<br />
to Dengser dam site has been kept in cost estimates <strong>of</strong> Dengser HE<br />
Project. As such, the same has not been considered in cost estimate <strong>of</strong><br />
this project. Nevertheless, cost <strong>of</strong> upgradation <strong>of</strong> road between Dengser<br />
dam site and <strong>Nalo</strong> dam site is taken into account. In case, <strong>Nalo</strong> HE<br />
Project, if decided to be taken for construction before construction <strong>of</strong><br />
Subansiri Middle/Upper/Dengser Projects, infrastructure requirement (R-<br />
Communication) <strong>of</strong> <strong>Nalo</strong> HE Project shall need to be revised.<br />
10.1 IDENTIFICATION OF BROAD INFRASTRUCTURE<br />
REQUIREMENTS<br />
In order to complete the project over a period <strong>of</strong> 6 years, broad<br />
infrastructure requirements are identified as under:<br />
10.1.1 Road Communication Network<br />
Strengthening/ widening <strong>of</strong> existing road network (Table-10.1)<br />
including bridges/culvert from Daporijo to project site measuring<br />
about 125 km.<br />
However, as mentioned in Table 10.1, provision for widening<br />
/strengthening from Daporijo to Dengser damsite (110 km) is kept<br />
in PFR <strong>of</strong> Dengser HE Project. In <strong>Nalo</strong> HE Project, provision <strong>of</strong><br />
widening /strengthening <strong>of</strong> road is kept for the stretch from Dengser<br />
damsite to <strong>Nalo</strong> dam site alongwith some miscellaneous stretches<br />
(25km).<br />
Construction <strong>of</strong> approach roads for adit to power house and HRT.<br />
112
10.1.2 Project headquarter, Offices and Colonies<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
The project township is planned to accommodate about 650<br />
quarters and 200 single/ shared accommodation in Field Hostel and<br />
Barracks.<br />
Non-residential buildings, such as Administrative building, School,<br />
Hospital, Bank, Post Office, Clubs, Auditorium, Shopping complex,<br />
Canteen, Workshops, Stores, Diesel <strong>Power</strong> House, etc will be<br />
required at project headquarter. It is estimated that the Nonresidential<br />
buildings will be required about 30,000 sqm <strong>of</strong> plinth<br />
area.<br />
10.1.3 Miscellaneous<br />
Arrangements for <strong>Power</strong>, Fuel station and Telecommunication system etc<br />
will also be required.<br />
113
CHAPTER – XI<br />
CONSTRUCTION PLANNING & SCHEDULE<br />
11.0 INTRODUCTION<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
The Equipment Planning & Construction Methodology <strong>of</strong> <strong>Nalo</strong> H.E. Project<br />
(4x90 MW), in Subansiri Basin has been developed on following<br />
considerations , -<br />
1. The project construction period has been considered as six years<br />
after completion <strong>of</strong> Stage I & II activities.<br />
2. Available Geological Data at PFR stage.<br />
3. Requirement <strong>of</strong> Construction Equipment has been planned to handle<br />
the quantities worked out on the basis <strong>of</strong> preliminary layout.<br />
4. Five months rainy season has been considered while planning<br />
surface works. However the time period indicated in the schedule for<br />
various components includes rainy season.<br />
The Construction Planning Schedule prepared for the project based on<br />
above considerations is placed at Table 11.1.<br />
11.1 CONSTRUCTION METHODOLOGY<br />
11.1.1 Infrastructure Works<br />
The main infrastructure development is proposed to be initiated<br />
simultaneously with preparation <strong>of</strong> DPR (Stage II activity) for which a<br />
provision <strong>of</strong> 18 months will be kept and completed in initial 12 months after<br />
taking up construction activity (Stage-III activity). During infrastructure<br />
114
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
development period Land Acquisition, construction <strong>of</strong> approach roads,<br />
bridges & culverts, arrangement <strong>of</strong> construction power will be undertaken.<br />
Critical components <strong>of</strong> project would be started from 7th month after<br />
construction <strong>of</strong> approach roads. Platform to accommodate batching plant,<br />
stores for construction material, site workshop, <strong>of</strong>fices and other buildings<br />
(residential/ non residential) colonies will also be developed in<br />
infrastructure period. Crawler Dozer, Loader cum Excavator, Motor<br />
Grader, Air compressor, Road Roller etc. are proposed for deployment<br />
during infrastructure stage.<br />
11.1.2 Diversion <strong>of</strong> River<br />
The construction <strong>of</strong> 2 nos. 10.75 m finished diameter, Horse shoe shaped<br />
650/800 m long diversion tunnels would be carried out by heading &<br />
benching method. Excavation <strong>of</strong> Diversion Tunnels will be carried out with<br />
2 Boom drill jumbo, Air Track/Wagon Drill, Jack hammer, 2.5 cum side<br />
dump loader and 20/25T L P Dumpers. Diversion tunnel excavation,<br />
erection <strong>of</strong> shutters & concreting and HM work would be completed in 24<br />
months. The concreting <strong>of</strong> diversion tunnel would be catered by Batching<br />
& Mixing plant, aggregate processing plant being proposed at dam,<br />
Concrete pump, Transit mixer and shutters etc. U/s & D/s C<strong>of</strong>fer dams<br />
would be constructed immediately after construction <strong>of</strong> diversion tunnel<br />
within a period <strong>of</strong> 4 months to divert the river. However river bed<br />
excavation would be taken up during the start <strong>of</strong> 3 rd month <strong>of</strong> construction<br />
<strong>of</strong> c<strong>of</strong>fer dams. Repair work <strong>of</strong> c<strong>of</strong>fer dams would be done twice in two<br />
months after each rainy season.<br />
11.1.3 Concrete Dam and Plunge Pool<br />
Dam abutment stripping would be done in 26 months. After diversion <strong>of</strong><br />
river, excavation <strong>of</strong> river bed & foundation treatment would be carried out<br />
in 3 months. Excavated material will be handled by 2 nos. 2.0 cum Hyd.<br />
115
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Excavator and 25 T Rear dumpers. Concreting <strong>of</strong> Dam & HM work would<br />
be carried out in further 30 months. Concreting would be catered by<br />
deploying 2x28T Cable ways with 3.0/6.0/9.0 cum buckets, 2 nos. 350<br />
Cum/hr Batching & Mixing Plant and 1400TPH Aggregate Processing<br />
plant which will cater the requirement <strong>of</strong> Diversion tunnel, intake structure,<br />
Desilting chamber, part <strong>of</strong> HRT, plunge pool and Dam.<br />
Excavation <strong>of</strong> plunge pool would be carried out in 6 months. The same<br />
equipment as deployed at Dam for excavation would be used for plunge<br />
pool excavation. Concreting <strong>of</strong> plunge pool would be done in 4 months<br />
with the help <strong>of</strong> Concrete pump with placer boom, Concrete mixers ,<br />
vibrator etc.<br />
11.1.4 Intake Structure, Desilting Chamber Silt Flushing tunnel<br />
2 Nos intake structures, intake tunnels and 4 Nos Desilting Chamber <strong>of</strong><br />
size 300m X17mX 25m would be excavated in 24 months. Excavation <strong>of</strong> 2<br />
nos 8.5 m dia , 250 m and 350m long intake tunnels would be carried out<br />
by heading and benching method. Excavation <strong>of</strong> Desilting Chamber would<br />
be taken up from adits to desilting chamber. Initially tunnels <strong>of</strong> 6.0 m dia<br />
would be excavated by full face method to the full length <strong>of</strong> Desilting<br />
Chambers. Thereafter it will be expanded side wise to the full width <strong>of</strong><br />
desilting chambers resulting in desilting chamber dome. Mucking <strong>of</strong><br />
excavated material would be done through the adits <strong>of</strong> desilting chamber.<br />
After the excavation <strong>of</strong> desilting chamber, concreting will be carried out.<br />
Excavation <strong>of</strong> silt flushing tunnel & gate operation chamber would be a<br />
parallel activity. The equipment to be deployed are two boom drill jumbo,<br />
Jack hammers, wagon drills, air compressors, side dump loader, L.P.<br />
dumpers, concrete pump, transit mixers etc. However concreting<br />
requirement <strong>of</strong> intake tunnel & Desilting chamber would be catered by<br />
Batching & Mixing Plant and aggregate processing plant installed at Dam.<br />
116
11.1.5 Head Race Tunnel<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Initially excavation <strong>of</strong> approaches and adits for HRT would be carried out<br />
in 4 months. Thereafter excavation <strong>of</strong> 2 nos. 7.5 m finished diameter<br />
each, 2.5 km and 2.6 km long horse shoe shaped Head Race Tunnels<br />
would be done by heading and benching method in 18 months through 1<br />
number intermediate adit. Excavation would be carried out by deploying<br />
two boom drill jumbo, 2.5 cum side dump loader and 20/25T L.P. dumper.<br />
Concreting will be done by deploying concreting equipment i.e. Concrete<br />
pump, Transit Mixer in 12 months. 1 no. 60 cum/hr Batching & mixing plant<br />
and 100 TPH aggregate processing Plant is proposed at HRT.<br />
11.1.6 Surge Shaft<br />
Initially construction <strong>of</strong> approaches for surge shaft would be done in 4<br />
months. Thereafter excavation <strong>of</strong> 2 nos 20 m diameter, 90 m high, Surge<br />
shaft would be taken up from top <strong>of</strong> surge shaft. Excavation <strong>of</strong> Surge Shaft<br />
would involve pilot hole drilling, reaming <strong>of</strong> pilot hole & enlargement <strong>of</strong><br />
reamed hole. Raise borer, Wagon Drill, 100 HP Dozer, 2.5 cum Side Dump<br />
Loader & 20/25 t LP Dumpers etc will be deployed for excavation <strong>of</strong> Surge<br />
shaft. Concreting would be completed employing 2 m shutter, concrete<br />
pump. 120 cum/hr Batching &mixing plant and 250 TPH aggregate<br />
processing Plant would be deployed to cater the requirement <strong>of</strong> surge<br />
shaft, part <strong>of</strong> HRT and part <strong>of</strong> pressure shaft. Excavation and concreting <strong>of</strong><br />
surge shaft would be completed in 50 months.<br />
11.1.7 Pressure Shaft<br />
Before construction <strong>of</strong> Pressure shaft, approaches and adits would be<br />
completed in 4 months. 2 nos. 6.25 m diameter, 82 m high each, vertical<br />
pressure shafts will be excavated by deploying Raise Borer, 2.5 cum side<br />
dump loader, 20 t LP dumper, Jack hammer etc. Steel liner erection &<br />
117
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
concreting will be carried out by deploying 10/20 t winches, Slipform liner<br />
etc. Excavation <strong>of</strong> Pressure shaft, erection <strong>of</strong> steel liners and concreting<br />
would done in 50 months. Concreting <strong>of</strong> pressure shaft would be catered by<br />
Batching & Mixing Plant and aggregate Processing Plant proposed to be<br />
installed at surge shaft & <strong>Power</strong> House.<br />
11.1.8 <strong>Power</strong> House<br />
4 X 90MW (360 MW) surface power house would be excavated in 16<br />
months. For excavation <strong>of</strong> <strong>Power</strong> House benches <strong>of</strong> suitable height will be<br />
developed by cutting hill slopes. The equipment to be deployed for<br />
excavation are Jack Hammers, wagon drills, air compressors, loaders,<br />
excavators dumpers etc. Concreting <strong>of</strong> <strong>Power</strong> house would be carried out<br />
in 36 months. Concreting <strong>of</strong> <strong>Power</strong> house would be carried out by<br />
deploying 1 no. Tower Crane 6.9 T at 60 m radius, concrete pump, Transit<br />
mixers, concrete vibrators etc. 80 cum/ hr Batching & Mixing Plant and 100<br />
TPH aggregate processing Plant would be installed at <strong>Power</strong> House which<br />
also cater the requirement <strong>of</strong> part <strong>of</strong> pressure shaft and Tail Race Channel.<br />
Installation & Testing <strong>of</strong> Machine would be undertaken in such a manner<br />
that Project get commissioned in 72nd month from the start <strong>of</strong> Project<br />
construction.<br />
11.1.9 Tail Race Channel<br />
Excavation <strong>of</strong> Tail Race Channel having bed width <strong>of</strong> 60 m and side slope<br />
<strong>of</strong> 1V: 1.5H would be carried out by deploying wagon drill, jack hammer, 1.0<br />
cum hyd. Excavator, 20t Dumpers etc. in 4 months. Concreting & misc.<br />
works <strong>of</strong> tail race channel would be started from 38th month and completed<br />
in further 6 months. Concreting requirement <strong>of</strong> TRC would be catered by<br />
concrete pump, transit Mixer, Batching & Mixing Plant and aggregate<br />
processing Plant installed at <strong>Power</strong> House.<br />
118
Sl.<br />
No.<br />
CCEA Clearance 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72<br />
1 INFRASTRUCTURE DEVELOPMENT<br />
a Acquisition <strong>of</strong> private & forest land Ha 8<br />
b Construction <strong>of</strong> roads & buildings LS 12<br />
2 AWARD OF CONTRACTS<br />
a Tendering & award LS 3<br />
b Mobilization LS 3<br />
3 DIVERSION TUNNELS( 2 nos., 10.75 m<br />
dia, 650/800 m long horseshoe)<br />
a Excavation m 3 4,21,000 16<br />
b Erection <strong>of</strong> shutters & Conc. Lining m 3 1,04,000 10<br />
c HM Works Job LS 6<br />
d Plugging <strong>of</strong> tunnels Job LS 2<br />
4 COFFER DAMS<br />
( U/s <strong>of</strong> 28m height & D/s <strong>of</strong> 14m ht)<br />
a Const.<strong>of</strong> C<strong>of</strong>fer Dams & River Diversion 3<br />
m<br />
U/s=4.50lacs<br />
D/s=1.06 lacs<br />
4<br />
b Reconstruction <strong>of</strong> C<strong>of</strong>fer Dams 12,12,000 4<br />
5 CONCRETE DAM (125 m High,<br />
381 m Length at top) with Spillways<br />
a Dam abutments stripping m 3 5,10,000 26<br />
b Excavation and foundation treatment m 3 1,70,000 3<br />
c Mass Concreting m 3 17,48,000 26<br />
d HM and other misc. works Job LS 18<br />
e Reservoir filling Job 2<br />
6 PLUNGE POOL<br />
a Excavation m 3 2,60,000 6<br />
b Concreting Works m 3 52,000 4<br />
7 HEAD RACE TUNNELS (2 nos. <strong>of</strong> 2.5/2.6 km<br />
length & 7.5m dia horseshoe<br />
a Excavation <strong>of</strong> approches and Adits Job LS 4<br />
b Excavation m 3 4,30,000 18<br />
c Concrete Lining m 3 1,58,000 12<br />
d Grouting Job LS 6<br />
e Adit pluggings, Cleanning etc. Job LS 3<br />
f Water conductor charging Job LS 1<br />
8 INTAKE STRUCTURES, INTAKE<br />
TUNNELS AND DISILTING<br />
CHAMBERS ( 4 nos. <strong>of</strong> size 300x17x25m)<br />
a Excavation m 3 10,34,000 24<br />
b Concrete Lining m 3 2,88,000 20<br />
c HM Works Job LS 15<br />
d Grouting and other misc. works Job LS 6<br />
9 SURFACE POWER HOUSE<br />
(<strong>Power</strong>house cavern 103x22x47m )<br />
CONSTRUCTION SCHEDULE OF NALO HE PROJECT IN SUBANSIRI BASIN (4X90=360 MW), ARUNACHAL PRADESH<br />
Name <strong>of</strong> Work Unit Quantity Duration<br />
(months) Ist year IInd year<br />
a Const. <strong>of</strong> Approches Job LS 3<br />
b Excavation <strong>of</strong> PH & TG m 3 5,35,000 16<br />
c Concreting in sub & super structures m 3 1,24,000 36<br />
d Erection <strong>of</strong> EOT crane Job LS 3<br />
10 SURGE SHAFTS<br />
(2 nos.<strong>of</strong> 20m dia. <strong>of</strong> 90m high)<br />
a Const. <strong>of</strong> approches Job LS 4<br />
b Excavation m 3 97,000 30<br />
c Concreting & HM Works m 3 35,000 20<br />
11 STEEL LINED PRESSURE SHAFTS<br />
(2 nos. <strong>of</strong> 6.25 m dia, 82 m vertical height )<br />
& Penstocks<br />
a Const.<strong>of</strong> approaches & adit Job LS 4<br />
b Excavation m 3 33,000 30<br />
c Erection <strong>of</strong> steel liners & Concreting m 3 16,000 20<br />
12 TAILRACE CHANNEL<br />
( 60 m bed width & 50 m length )<br />
a Excavation m 3 30,000 4<br />
b Concreting & Misc.Works m 3 1,500 6<br />
13 SWITCH YARD (Size 160x80m)<br />
3<br />
m<br />
Exc.<br />
2,95,000<br />
15<br />
14 ELECTRO-MECHANICAL WORKS<br />
a<br />
Erection, Testing & Commisioning<br />
<strong>of</strong> all four units<br />
Job 42<br />
Note: Since the date <strong>of</strong> CCEA clearance cannot be anticipated at this stage, the time assumed for various activities is inclusive <strong>of</strong> the effect <strong>of</strong> monsoon.<br />
Schedule <strong>of</strong> Constructiom<br />
IIIrd year IVth year<br />
-<br />
V th year<br />
VI th year<br />
TABLE-11.1<br />
119
12.0 COST ESTIMATE<br />
CHAPTER –XII<br />
COST ESTIMATE<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
12.1 PRELIMINARY COST ESTIMATE FOR CIVIL, HYDRO-<br />
MECHANICAL, ELECTRO-MECHANICAL WORKS<br />
The estimate has been prepared to arrive at the Capital Cost <strong>of</strong> <strong>Nalo</strong> H. E.<br />
Project and is <strong>of</strong> Pre-feasibility level <strong>of</strong> accuracy. The base date <strong>of</strong> the<br />
estimate is June 2003 and the Cost is expressed in Indian Rupees. The<br />
Cost Estimate is divided into Civil, Electrical and Transmission Works. For<br />
Civil Works, the sub heads are as under :<br />
12.1.1 I-Works<br />
Under this head, provision has been made for various components <strong>of</strong> the<br />
Project as detailed hereunder :<br />
12.1.2 A-Preliminary<br />
Under A-Preliminary, provision has been made for all surveys and<br />
investigations to be conducted to arrive at the optimum <strong>of</strong> the Project<br />
Components.<br />
12.1.3 B-Land<br />
This covers the provision for acquisition <strong>of</strong> land for construction <strong>of</strong> the<br />
Project, colonies, <strong>of</strong>fices and stores and compensation for trees and<br />
standing crops etc. This head also contains the provision for Rehabilitation<br />
and Resettlement measures for Project Affected People.<br />
120
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
12.1.4 C-Works<br />
This covers the cost <strong>of</strong> Diversion Tunnel, C<strong>of</strong>fer dam, Concrete Dam with<br />
associated Hydro-mechanical works.<br />
12.1.5 J-<strong>Power</strong> Plant Civil Works<br />
This covers the cost <strong>of</strong> project components viz. Intake Structure and Head<br />
Race Tunnel, Desilting Basins, TRT, <strong>Power</strong> House and Transformer<br />
Cavern, Pressure Shaft, Surge Shaft and other Appurtenant Works along<br />
with associated Hydro-mechanical woks.<br />
The quantities indicated in the estimates for C - Works & J-<strong>Power</strong> Plant Civil<br />
Works (Civil & HM) are calculated from the preliminary Engineering<br />
drawings and as per experience <strong>of</strong> other on-going or commissioned<br />
projects.<br />
The unit rates for various items are taken as per the Guidelines issued by<br />
CEA for preparation <strong>of</strong> PFRs. It has been assumed that the quarry is<br />
available at a distance <strong>of</strong> 10 Kms from the work site.<br />
12.1.6 K-Buildings<br />
Buildings, both residential and non-residential have been provided under<br />
this head. Under the permanent category only those structures have been<br />
included which shall be subsequently utilized during the operation and<br />
maintenance <strong>of</strong> the project. The costs are worked out on plinth area basis<br />
prevalent in the area for the type <strong>of</strong> construction involved.<br />
12.1.7 O-Miscellaneous<br />
Provision under this head has been made for the Capital & running cost <strong>of</strong><br />
Electrification, Water Supply, Sewage Disposal, Fire Fighting Equipments,<br />
121
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Medical Assistance, Recreation, Post Office, Telephone and Telegraph<br />
Office, etc. The Provisions have been made for the security arrangements,<br />
inspection vehicles, schools, transport <strong>of</strong> labour, laboratory testing, R&M <strong>of</strong><br />
guest house and transit camps, community center, retrenchment<br />
compensation, photographic instruments as well as R&M charges etc.<br />
12.1.8 P-Maintenance During Construction and Y-Losses on Stock<br />
A provision <strong>of</strong> 1% and 0.25% <strong>of</strong> C-Civil works, J-<strong>Power</strong> Plants, K-Buildings<br />
& R-Communications has been made for maintenance <strong>of</strong> works during<br />
construction period and losses on stock respectively.<br />
12.1.9 Q-Special Tools and Plant<br />
It is assumed that the work will be carried out through Contracts and not<br />
through departmental construction. Accordingly, provision for general<br />
purpose equipment and inspection vehicle only has been made as per CWC<br />
guidelines.<br />
12.1.10 R-Communication<br />
Provision under this head covers the cost <strong>of</strong> new roads,<br />
widening/improvement <strong>of</strong> roads and strengthening <strong>of</strong> bridges. The costs <strong>of</strong><br />
roads and bridges are based on the rate structure prevalent in the area <strong>of</strong><br />
the Project, for the type <strong>of</strong> construction involved.<br />
12.1.11 X-Environment and Ecology<br />
Provision under this head has been taken as 2% <strong>of</strong> I -Works towards biodiversity<br />
Conservation, creation <strong>of</strong> Green Belt, Restoration <strong>of</strong> Construction<br />
Area, Catchment Area Treatment, Compensatory Afforestation etc<br />
122
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
12.1.12 II-Establishment<br />
Provision for establishment has been made at 8% <strong>of</strong> I-works minus B-Land<br />
for civil works.<br />
12.1.13 III-Tools and Plants<br />
This provision is distinct from that under Q-Special T&P and is meant to<br />
cover cost <strong>of</strong> survey instruments, camp equipment and other small tools<br />
and plants. The outlay is provided at 1% <strong>of</strong> cost <strong>of</strong> I-works.<br />
12.1.14 IV-Suspense<br />
No provision has been made under this head as all the outstanding<br />
suspense are expected to be cleared by adjustment to appropriate heads at<br />
completion <strong>of</strong> the project.<br />
12.1.15 V-Receipts and Recoveries<br />
Under this head, provision has been made for estimated recoveries by way<br />
<strong>of</strong> resale or transfer <strong>of</strong> equipment used in infrastructure works.<br />
12.1.16 Electrical Works and Generating Plant<br />
The cost <strong>of</strong> Generating Plant and Equipment is based on indigenous<br />
sources. The prices <strong>of</strong> auxiliary equipment and services are based on<br />
prevailing market prices/costs incurred at other ongoing or commissioned<br />
projects.<br />
123
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
ABSTRACT OF COST OF WORKS<br />
S.No Description Amount<br />
(Rs. in Crores)<br />
( June 2003 P.L.)<br />
A CIVIL WORKS<br />
1. DIRECT CHARGES<br />
I – Works<br />
A – Preliminary 30.29<br />
B – Land 8.96<br />
C – Works 990.41<br />
J - <strong>Power</strong> Plant Civil Works 716.78<br />
K – Buildings 55.86<br />
O – Miscellaneous 80.57<br />
P – Maintenance 18.26<br />
Q-Special Tools & Plants 5.58<br />
R – Communication 62.80<br />
X - Environment & Ecology 40.29<br />
Y - Losses on Stock 4.56<br />
Total <strong>of</strong> I-Works 2014.37<br />
II - Establishment @ 8% <strong>of</strong> cost <strong>of</strong> I-Works less B-Land 160.43<br />
III - Tools and Plants @ 1% <strong>of</strong> cost <strong>of</strong> I-Works 20.14<br />
IV – Suspense 0.00<br />
V - Receipt & Recoveries (-) -2.78<br />
TOTAL DIRECT CHARGES 2192.17<br />
2. INDIRECT CHARGES<br />
a) Capitalised Value <strong>of</strong> Abatement <strong>of</strong> Land Revenue 0.15<br />
b) Audit and Account Charges @1% <strong>of</strong> cost <strong>of</strong> I-Works 20.14<br />
TOTAL INDIRECT CHARGES 20.30<br />
TOTAL OF DIRECT & INDIRECT CHARGES 2212.47<br />
ABSTRACT :<br />
A Civil Works 2212.47<br />
B Electrical Works 334.89<br />
C Transmission Works 62.31<br />
TOTAL COST 2609.66<br />
D IDC 312.48<br />
E Total Cost With IDC 2922.14<br />
124
S.<br />
No.<br />
A - PRELIMINARY<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Particulars Unit Qty Rates Amount Rs.<br />
in Lakhs<br />
1 Expenditure incurred on PFR stage investigation -- -- -- 14.00<br />
2 Detailed Survey for final location L. S. -- -- 150.00<br />
3 Aerial Survey, contour survey for reservoir basin<br />
including establishment <strong>of</strong> permanent bench marks<br />
L. S. -- -- 150.00<br />
4 Geological surveys, Geophysical surveys and rock<br />
mechanics tests<br />
L. S. -- -- 150.00<br />
5 Ground water studies L. S. -- -- 10.00<br />
6 Hydrological and Meteorological Surveys including<br />
establishment <strong>of</strong> rain gauges/river gauges and<br />
discharge, sedimentation station and their running<br />
L. S. -- -- 100.00<br />
7 Investigation for foundation and rock testing.<br />
Drilling - 3000m . Drifting - 700m<br />
8 Investigation for availability <strong>of</strong> construction<br />
materials<br />
9 Construction <strong>of</strong> access roads & foot/ suspension<br />
bridge to facilitate investigations<br />
-- -- 350.00<br />
L. S. -- -- 100.00<br />
L. S. -- -- 75.00<br />
10 Model Experiments L. S. -- -- 150.00<br />
11 Computer & Telecommunication L. S. -- -- 50.00<br />
12 Preparation & Printing <strong>of</strong> project report L. S. -- -- 35.00<br />
13 Vehicles for inspecting <strong>of</strong>ficers for site<br />
investigations<br />
No. 10 5 50.00<br />
14 Helicopter Support L. S. -- -- 100.00<br />
15 Construction power for investigation and<br />
infrastructure works<br />
L. S. -- -- 100.00<br />
16 Office and camp equipments L. S. -- -- 100.00<br />
17 R & M <strong>of</strong> Office and Transit camps etc. L. S. -- -- 200.00<br />
18 Preliminary soil test establishing soil testing<br />
laboratory<br />
L. S. -- -- 50.00<br />
19 Consultant's fees including charges for preliminary<br />
design work for advice<br />
L. S. -- -- 1000.00<br />
20 Training <strong>of</strong> engineers during investigation and L. S. -- -- 20.00<br />
preparation <strong>of</strong> project reports.<br />
21 Environmental & Ecological studies L. S. -- -- 75.00<br />
Total 3029.00<br />
125
B - LAND<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
S. No. Particulars Area (ha) Rates (Rs Amount (Rs. in<br />
1<br />
Lakhs /ha) Lakhs)<br />
A Forest/Govt. Land<br />
a) Reservoir Area 150 0.65 97.50<br />
b) Project features 80 0.65 52.00<br />
c) Township, stores area and roads 100 0.65 65.00<br />
d) quarry site 20 0.65 13.00<br />
e) muck Disposable area 10 0.65 6.50<br />
f) Transit Camp and Guest houses 5 0.65 3.25<br />
g) Land for rehablitation purpose 90 0.65 58.50<br />
Sub Total A 295.75<br />
B Private Land<br />
a) Reservoir Area 150 1.10 165.00<br />
b) Project features 50 1.10 55.00<br />
c) Township, stores area and roads 75 1.10 82.50<br />
d) Transit Camp and Guest houses 10 1.10 11.00<br />
Sub Total B 313.50<br />
2 Rehabilitation & Resettlement (land<br />
for rehablitation included)<br />
3 Cost <strong>of</strong> Establishment for land<br />
acquisition and Rehabilitation @<br />
6.25% <strong>of</strong> Item 1&2<br />
4 Solatium charges @ 30% <strong>of</strong> the cost<br />
<strong>of</strong> Private Land<br />
5 Interest charges on amount <strong>of</strong> award<br />
for the period between taking over<br />
possession <strong>of</strong> land and date <strong>of</strong> award<br />
@ 12% per annum on 25% <strong>of</strong> cost <strong>of</strong><br />
total compensation for 2 years<br />
6 Legal charges @ 1% <strong>of</strong> total<br />
compensation<br />
7 Labour and material required for<br />
measurement & demarcation <strong>of</strong><br />
land/Properties @ 1% <strong>of</strong> cost <strong>of</strong> land<br />
Acquisition<br />
L. S. 100.00<br />
44.33<br />
94.05<br />
36.56<br />
6.09<br />
6.09<br />
Total 896.37<br />
Note : 50% <strong>of</strong> rock quarries and all clay borrow areas fall in submergence area/ project area.<br />
Hence provision for these has not been made<br />
126
ABSTRACT OF COST OF C - WORKS<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
S. N. Description Amount (Rs. In Lakhs)<br />
CIVIL HM TOTAL<br />
1. DIVERSION TUNNEL 9753.79 686.70 10440.49<br />
2. COFFER DAMS 5373.63 5373.63<br />
3. CONCRETE DAM INCLUDING SPILLWAY<br />
AND PLUNGE POOL<br />
73253.05 3668.18 76921.23<br />
TOTAL 88380.48 4354.88 92735.35<br />
ADD FOR WORKS TAX @ 6.8% 6009.87 296.13 6306.00<br />
GRAND TOTAL 94390.35 4651.01 99041.36<br />
127
DIVERSION TUNNEL<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
S. No. Description Unit Qty. Rate Amount<br />
( Rs. in<br />
Lakhs)<br />
1 Surface Excavation<br />
1.1 Common excavation Cum 46,000 125 57.50<br />
1.2 Rock excavation Cum 110,000 300 330.00<br />
2 Underground excavation Cum 265,000 1000 2650.00<br />
3 Support System<br />
3.1 Rock bolts M 70,000 400 280.00<br />
3.2 Steel Rib Supports MT 800 42000 336.00<br />
3.3 Shotcrete Cum 11,000 4000 440.00<br />
3.4 Concrete Lagging Cum 1,300 7000 91.00<br />
4 Concrete<br />
4.1 Concrete Lining M-20 Cum 45,000 4000 1800.00<br />
4.2 Concrete in portals, backfill etc.<br />
M-15 Cum 8,000 2930 234.40<br />
M-20 Cum 29,000 3390 983.10<br />
M-25 Cum 22,000 3610 794.20<br />
5 Reinforcing steel MT 1,500 27000 405.00<br />
Sub total A 8401.20<br />
6 Miscellaneous and ancillary works @<br />
7.5% <strong>of</strong> sub-total A<br />
7.50% 630.09<br />
Sub total B 9031.29<br />
7 Instrumentation @ 1% <strong>of</strong> sub-total B 1.00% 90.31<br />
8 Dewatering @ 2% <strong>of</strong> sub total B 2.00% 180.63<br />
9 Contingency @ 3% <strong>of</strong> sub-total B 3.00% 270.94<br />
10 Work Charged establishment @ 2% <strong>of</strong><br />
Sub-total –B<br />
2.00% 180.63<br />
Total civil works 9753.79<br />
128
COFFER DAMS<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
S. No. Description Unit Quantity Rate Amount<br />
( Rs. in<br />
Lakhs)<br />
1 Surface Excavation<br />
1.1 Common excavation Cum 18,000 125 22.50<br />
2 Embankment Constrcution<br />
2.1 Earth /Rock fill Cum1,100,000 342 3762.00<br />
2.2 Impervious Core Cum 280,000 354 991.20<br />
2.3 Filter Cum 17,000 901 153.17<br />
3 Concrete<br />
3.1 M-10 Cum 400 2560 10.24<br />
3.2 M-15 Cum 400 2930 11.72<br />
Sub Total(A) 4950.83<br />
4 Miscellaneous and Ancillary<br />
Works @ 0.5% <strong>of</strong> sub-total A<br />
0.5% 24.75<br />
Sub-Total(B) 4975.58<br />
5 Dewatering @ 3% <strong>of</strong> sub total (B) 3% 149.27<br />
6 Contingency @ 3% <strong>of</strong> sub-total B 3% 149.27<br />
7 Work Charged establishment @<br />
2% <strong>of</strong> Sub-total B<br />
2% 99.51<br />
Total civil works 5373.63<br />
129
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
CONCRETE DAM INCLUDING SPILLWAY AND PLUNGE POOL<br />
S. No. Description Unit Quantity Rate Amount<br />
( Rs. in<br />
Lakhs)<br />
1 Surface Excavation<br />
1.1 Common excavation Cum 410,000 125 512.50<br />
1.2 Rock excavation Cum 530,000 300 1590.00<br />
2 Support System<br />
2.1 Rock bolts M 14,000 400 56.00<br />
2.2 Shotcrete Cum 6,000 4000 240.00<br />
3 Concrete<br />
3.1 M-15 Cum 1,065,000 2930 31204.50<br />
3.2 M-20 Cum 355,000 3390 12034.50<br />
3.3 M-25 Cum 380,000 3610 13718.00<br />
4 Reinforcing steel MT 23,000 27000 6210.00<br />
5 Miscellaneous and Ancillary Works<br />
@ 2.5% <strong>of</strong> sub-total A<br />
2.5%<br />
Sub Total(A) 65565.50<br />
1639.14<br />
Sub-Total(B) 67204.64<br />
6 Instrumentation @ 1% <strong>of</strong> sub-total (B) 1% 672.05<br />
7 Dewatering @ 3% <strong>of</strong> sub total (B) 3% 2016.14<br />
8 Contingency @ 3% <strong>of</strong> sub-total B 3% 2016.14<br />
9 Work Charged establishment @ 2%<br />
<strong>of</strong> Sub-total B<br />
2% 1344.09<br />
Total civil works 73253.05<br />
130
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
J -POWER PLANT APPURTENANCES (CIVIL WORKS)<br />
S. Description Amount (Rs. in Lakhs)<br />
NO. CIVIL HM TOTAL<br />
1. INTAKE STRUCTURE INCLUDING INTAKE<br />
TUNNEL UPTO DESILTING CHAMBERS<br />
5054.61 725.55 5780.16<br />
2. DESILTING CHAMBERS 22591.63 1162.77 23754.40<br />
3. HEAD RACE TUNNEL 16029.11 16029.11<br />
4. SURGE SHAFTS 3707.86 229.11 3936.97<br />
5. PRESSURE SHAFT AND PENSTOCKS 1194.69 1470.00 2664.69<br />
6. POWER HOUSE COMPLEX 10763.68 175.88 10939.56<br />
7. TAIL RACE CHANNEL 189.80 0.00 189.80<br />
8. SWITCH YARD 1665.88 1665.88<br />
9. ADITS 2146.06 7.14 2153.20<br />
Total 63343.33 3770.45 67113.78<br />
ADD FOR WORKS TAX @ 6.8% 4307.35 256.39 4563.74<br />
GRAND TOTAL 67650.68 4026.84 71677.51<br />
131
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
INTAKE STRUCTURE INCLUDING INTAKE TUNNEL UPTO<br />
DESILTING CHAMBERS<br />
S. No. Description Unit Quantity Rate Amount<br />
( Rs. in<br />
Lakhs)<br />
1 Surface excavation<br />
1.1 Common excavation Cum 2,500 125 3.13<br />
1.2 Rock excavation Cum 45,000 300 135.00<br />
2 Underground excavation Cum 62,000 1000 620.00<br />
3 Rock stabilisation and supports<br />
3.1 Rock bolts M 31,000 400 124.00<br />
3.2 Steel Rib Supports MT 300 42000 126.00<br />
3.3 Shotcreting Cum 5,400 4000 216.00<br />
3.4 Concrete lagging Cum 400 7000 28.00<br />
4 Concrete<br />
4.1 Concrete Lining M20 Cum 15,000 4000 600.00<br />
4.2 Concrete M15 Cum 5,000 2930 146.50<br />
4.3 Backfill Concrete M20 Cum 6,000 3390 203.40<br />
4.4 M25 Cum 41,000 3610 1480.10<br />
5 Reinforcing Steel MT 3,600 27000 972.00<br />
Sub Total(A) 4654.13<br />
6 Miscellaneous and ancillary works<br />
@1.5% <strong>of</strong> sub-total A<br />
1.5% 69.81<br />
Sub Total(B) 4723.94<br />
7 Instrumentation @ 1% <strong>of</strong> sub-total B 1% 47.24<br />
8 Dewatering @ 1% <strong>of</strong> sub total B 1% 47.24<br />
9 Contingency @ 3% <strong>of</strong> sub-total B 3% 141.72<br />
10 Work Charged establishment @<br />
2% <strong>of</strong> Sub-total B<br />
2% 94.48<br />
Total Civil Cost 5054.61<br />
132
DESILTING CHAMBERS<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
S. No. Description Unit Qty. Rate Amount<br />
( Rs. in<br />
Lakhs)<br />
1 Surface excavation<br />
1.1 Common excavation Cum 10,000 125 12.50<br />
1.2 Rock excavation Cum 25,000 300 75.00<br />
2 Underground excavation Cum 890,000 1000 8900.00<br />
3 Rock stabilisation and supports<br />
3.1 Rock bolts M 225,000 400 900.00<br />
3.2 Steel Rib Supports MT 1,900 42000 798.00<br />
3.3 Shotcreting Cum 33,000 4000 1320.00<br />
3.4 Concrete lagging Cum 350 7000 24.50<br />
4 Concrete<br />
4.1 Concrete Lining M 20 Cum 85,000 4000 3400.00<br />
4.2 Concrete Lining M 25 Cum 10,000 4500 450.00<br />
4.3 Concrete in portals, backfill etc.<br />
M15/A40 Cum 6,000 2930 175.80<br />
M20 Cum 105,000 3390 3559.50<br />
M25 Cum 15,000 3610 541.50<br />
5 Reinforcing Steel MT 200 27000 54.00<br />
Sub Total(A) 20210.80<br />
6 Miscellaneous and ancillary works @<br />
3.5% <strong>of</strong> sub-total A<br />
3.5% 707.38<br />
Sub Total(B) 20918.18<br />
7 Instrumentation @ 1% <strong>of</strong> sub-total B 1% 209.18<br />
8 Dewatering @ 2% <strong>of</strong> sub total B 2% 418.36<br />
9 Contingency @ 3% <strong>of</strong> sub-total B 3% 627.55<br />
10 Work Charged establishment @ 2%<br />
<strong>of</strong> Sub-total B<br />
2% 418.36<br />
Total Civil Cost 22591.63<br />
133
HEAD RACE TUNNEL<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
S. No. Description Unit Qty. Rate Amount<br />
( Rs. in<br />
Lakhs)<br />
1. Underground excavation Cum 430,000 1000 4300.00<br />
2. Support System<br />
2.1 Rockbolts m 210,000 400 840.00<br />
2.2 Steel Rib Supports MT 2,200 42000 924.00<br />
2.3 Shotcrete Cum 33,000 4000 1320.00<br />
2.4 Concrete lagging Cum 2,800 7000 196.00<br />
3 Concrete<br />
3.1 Concrete Lining M-20 Cum 115,000 4000 4600.00<br />
3.2 Concrete in portals, backfill etc.<br />
3.3 M-15 Cum 5,000 2930 146.50<br />
3.4 M-20 Cum 38,000 3610 1371.80<br />
5 Reinforcing Steel MT 400 27000 108.00<br />
6 Miscellaneous and ancillary works @<br />
7.5% <strong>of</strong> sub-total A<br />
7.5%<br />
Sub-Total(A) 13806.30<br />
1035.47<br />
Sub-Total(B) 14841.77<br />
7 Instrumentation @ 1% <strong>of</strong> sub-total B 1% 148.42<br />
8 Dewatering @ 2% <strong>of</strong> sub total B 2% 296.84<br />
9 Contingency @ 3% <strong>of</strong> sub-total B 3% 445.25<br />
10 Work Charged establishment @ 2% <strong>of</strong><br />
Sub-total B<br />
2% 296.84<br />
Total civil works 16029.11<br />
134
SURGE SHAFTS<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
S. No. Description Unit Quantity Rate Amount<br />
( Rs. in<br />
Lakhs)<br />
1 Surface Excavation<br />
1.1 Common excavation Cum 3,000 125 3.75<br />
1.2 Rock excavation Cum 9,000 300 27.00<br />
2 Underground excavation<br />
2.1 Surge Shaft Excavation Cum 85,000 1200 1020.00<br />
2.2 Surge Shaft Excavation with raise borer Cum 814 1500 12.21<br />
2.3 Concrete Lagging Cum 250 7000 17.50<br />
3 Rock stabilisation & Supports<br />
3.1 Rock bolts / anchors 25mm dia M 22,000 400 88.00<br />
3.2 Shotcrete Cum 3,300 4000 132.00<br />
3.3 Structural steel Rib MT 17542000 73.50<br />
4 Concrete<br />
4.1 Concrete M20 Cum 5,000 3390 169.50<br />
4.2 M25 Cum 30,000 3610 1083.00<br />
5 Reinforcing steel MT 2,80027000 756.00<br />
Sub Total(A) 3382.46<br />
6 Miscellaneous and ancillary works @<br />
1.5% <strong>of</strong> sub-total A<br />
1.5% 50.74<br />
Sub Total(B) 3433.20<br />
7 Instrumentation @ 1% <strong>of</strong> sub-total B 1% 34.33<br />
8 Dewatering @ 2% <strong>of</strong> sub total B 2% 68.66<br />
9 Contingency @ 3% <strong>of</strong> sub-total B 3% 103.00<br />
10 Work Charged establishment @ 2% <strong>of</strong><br />
Sub-total B<br />
2% 68.66<br />
Total Civil Cost 3707.86<br />
135
PRESSURE SHAFT AND PENSTOCKS<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
S. No. Description Unit Qty. Rate Amount<br />
( Rs. in<br />
Lakhs)<br />
1 Underground excavation 33,000 1200 396.00<br />
2 Rock stabilisation & Supports<br />
2.1 Rock bolts / anchors 25mm dia M 17,000 400 68.00<br />
2.2 Shotcrete Cum 2,600 4000 104.00<br />
2.3 Structural steel Rib MT 125 42000 52.50<br />
3 Concrete<br />
3.1 Backfill concrete M 15 Cum 16,000 2930 468.80<br />
Sub Total (A) 1089.30<br />
4 Miscellaneous and ancillary<br />
works @ 2.5% sub-total A<br />
2.5% 27.23<br />
Sub Total (B) 1116.53<br />
5 Instrumentation @ 1% <strong>of</strong> sub-total B 1% 11.17<br />
6 Dewatering @ 1% <strong>of</strong> sub total B 1% 11.17<br />
7 Contingency @ 3% <strong>of</strong> sub-total<br />
3% 33.50<br />
B<br />
8 Work Charged establishment @<br />
2% <strong>of</strong> Sub-total B<br />
2% 22.33<br />
Total Civil Cost 1194.69<br />
136
POWER HOUSE COMPLEX<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
S. No. Description Unit Quantity Rate Amount<br />
( Rs. in<br />
Lakhs)<br />
1 Surface Excavation<br />
1.1 Common Excavation Cum 135,000 125 168.75<br />
1.2 Rock Excavation Cum 400,000 300 1200.00<br />
2 Rock stabilization and Supports including accessories<br />
2.1 Rockbolts M 20,000 400 80.00<br />
2.2 Shotcrete Cum 6,000 4000 240.00<br />
3 Concrete including formwork<br />
3.1 M-15 Cum 4,000 2930 117.20<br />
3.2 M-20 Cum 80,000 3390 2712.00<br />
3.3 M-25 Cum 40,000 3610 1444.00<br />
4 Reinforcing Steel MT 12,500 27000 3375.00<br />
5 Structural Steel MT 400 42000 168.00<br />
6 Masonry Work<br />
Stone Cum 500 2000 10.00<br />
Brick Cum 800 2000 16.00<br />
Stone pitching Cum 800 781 6.25<br />
Sub Total(A) 9537.20<br />
7 Miscellaneous and ancillary works @<br />
4.5% <strong>of</strong> sub-total A<br />
4.5% 429.17<br />
Sub Total(B) 9966.37<br />
8 Instrumentation @ 1% <strong>of</strong> sub-total B 1% 99.66<br />
9 Dewatering @ 2% <strong>of</strong> sub total B 2% 199.33<br />
10 Contingency @ 3% <strong>of</strong> sub-total B 3% 298.99<br />
11 Work Charged establishment @ 2% <strong>of</strong><br />
Sub-total B<br />
2% 199.33<br />
Total Civil Cost 10763.68<br />
137
TAIL RACE CHANNEL<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
S. No. Description Unit Qty. Rate Amount<br />
( Rs. in<br />
Lakhs)<br />
1 Surface excavation<br />
1.1 Common excavation Cum 15,000 125 18.75<br />
1.2 Rock excavation Cum 15,000 300 45.00<br />
1.3 Embankment Construction Cum 3,000 518 15.54<br />
2 Concrete including formwork<br />
2.1 M20 Cum 1,500 3390 50.85<br />
3 Reinforcing Steel MT 100 27000 27.00<br />
4 Masonry Work<br />
Stone Cum 100 2000 2.00<br />
Brick Cum 100 2000 2.00<br />
Stone pitching Cum 300 781 2.34<br />
Sub-Total(A) 163.48<br />
5 Miscellaneous and ancillary works @<br />
7.5% <strong>of</strong> sub-total A<br />
7.5% 12.26<br />
Sub-Total(B) 175.74<br />
6 Instrumentation @ 1% <strong>of</strong> sub-total B 1% 1.76<br />
7 Dewatering @ 2% <strong>of</strong> sub total B 2% 3.51<br />
8 Contingency @ 3% <strong>of</strong> sub-total B 3% 5.27<br />
9 Work Charged establishment @ 2% <strong>of</strong><br />
Sub-total B<br />
2% 3.51<br />
Total civil works 189.80<br />
138
SWITCH YARD<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
S. No. Description Unit Qty. Rate Amount<br />
( Rs. in<br />
Lakhs)<br />
1 Surface excavation<br />
1.1 Common excavation Cum 55,000 125 68.75<br />
1.2 Rock excavation Cum 55,000 300 165.00<br />
1.3 Backfilling Cum 185,000 356 658.60<br />
2 Concrete including form work<br />
2.1 M-15 Cum 1,000 2930 29.30<br />
2.2 M-20 Cum 4,000 3390 135.60<br />
2.3 M-25 Cum 6,000 3610 216.60<br />
3 Reinforcing Steel MT 600 27000 162.00<br />
4 Structural steel MT 100 42000 42.00<br />
5 Stone / Brick Masonry Cum 600 2000 12.00<br />
Sub Total(A) 1489.85<br />
6 Miscellaneous and ancillary<br />
works @ 4.5% <strong>of</strong> sub-total A<br />
4.5% 67.04<br />
Sub Total(B) 1556.89<br />
7 Dewatering @ 2% <strong>of</strong> sub total B 2% 31.14<br />
8 Contingency @ 3% <strong>of</strong> sub-total B 3% 46.71<br />
9 Work Charged establishment @<br />
2% <strong>of</strong> Sub-total B<br />
2% 31.14<br />
Total Civil Cost 1665.88<br />
139
ADITS<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
S. Description Unit Quantity Rate Amount<br />
No.<br />
( Rs. in<br />
Lakhs)<br />
1 Surface Excavation at Portals<br />
1.1 Common excavation Cum 7,000 125 8.75<br />
1.2 Rock excavation Cum 24,000 300 72.00<br />
2 Underground excavation Cum 80,000 1000 800.00<br />
3 Rock stabilisation and supports<br />
3.1 Rockbolts/Rock anchor 25 mm dia M 60,000 400 240.00<br />
3.2 Shotcrete Cum 6,500 4000 260.00<br />
3.3 Structural steel Rib MT 400 42000 168.00<br />
4 Concrete<br />
4.1 Concrete in portals, backfill etc.<br />
M-15 Cum 2,500 2930 73.25<br />
M-20 Cum 6,000 3390 203.40<br />
5 Reinforcing steel MT 350 27000 94.50<br />
Sub Total (A) 1919.90<br />
6 Miscellaneous and ancillary works @ 3.5%<br />
<strong>of</strong> sub-total A<br />
3.5% 67.20<br />
Sub-Total(B) 1987.10<br />
7 Instrumentation @ 1% <strong>of</strong> sub-total (B) 1% 19.87<br />
8 Dewatering @ 2% <strong>of</strong> sub total (B) 2% 39.74<br />
9 Contingency @ 3% <strong>of</strong> sub-total (B) 3% 59.61<br />
10 Work Charged establishment @ 2% <strong>of</strong><br />
Sub-total B<br />
2% 39.74<br />
Total Civil Cost 2146.06<br />
140
S.<br />
No.<br />
HYDRO MECHANICAL EQUIPMENT<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Detail <strong>of</strong> Items UnitQuantity Rate<br />
(Rs.)<br />
Amount<br />
in Lacs<br />
1 Diversion tunnel gate & hoist<br />
Gate (Fixed wheel type) (4.5m x 10.75m)- 4 No. Ton 300 60000 180.00<br />
Embedded Parts - 4 Set Ton 108 50000 54.00<br />
Ropedrum hoist 200 T Capacity - 4 Set Ton 280 100000 280.00<br />
Hoist Supporting structure and trestle - 4 Set Ton 280 50000 140.00<br />
2 Spillway structure<br />
a) Lower spillway Radial Gates (9.75m x 11.5m) - 5 Nos. Ton 950 100000 950.00<br />
Embedded Parts (including anchorages, hoist<br />
structure) including breast wall liners - 5 Set<br />
Ton 600 50000 300.00<br />
Hydraulic Hoist (One power pack + Two cylinders <strong>of</strong> Set<br />
220T Cap. each)<br />
5 18500000 925.00<br />
b) Bulkhead Gate( Fixed Wheel type) 9.75m x 13.5m - 1 Ton<br />
No.<br />
210 60000 126.00<br />
Embedded Parts - 5Set Ton 325 50000 162.50<br />
Lifting Beam Ton 50 50000 25.00<br />
Gantry crane 490 T capacity with cross travel<br />
arrangement<br />
Set 1 54000000 540.00<br />
Portable oil filter unit along with Contamination<br />
checking kit & Low vacuum dehydration and<br />
degassification unit<br />
Set 1 1000000 10.00<br />
Portable trolley mounted gasoline engine operated<br />
power pack<br />
Set 1 1500000 15.00<br />
c) Upper Spillway Radial Gates (9.75m x 11.5m) - 2<br />
Nos.<br />
Ton 124 100000 124.00<br />
Embedded Parts (including anchorages, hoist<br />
structure) including breast wall liner - 2 Set<br />
Ton 90 50000 45.00<br />
Hydraulic Hoist (One power pack + Two cylinder <strong>of</strong><br />
70T Cap.each)<br />
d) Spillway Bulkhead (Lower spillway bulkhead to be<br />
used)<br />
Set 2 6500000 130.00<br />
Embedded Parts - 2 Set Ton 32 50000 16.00<br />
3 Intake structure<br />
a) TrashRacks and Embedded parts (18m x 20m) - 2 Set Ton 204 50000 102.00<br />
Trash rack cleaning machine Set 1 10000000 100.00<br />
b) Intake gate(fixed wheel type) including ballast (7.5m Ton 300 60000 180.00<br />
x 8.5m) - 2 No.<br />
Embedded Parts -2 Set Ton 90 50000 45.00<br />
Rope drum hoist 250T Cap.- 2 Sets Ton 176 100000 176.00<br />
Hoist platform and trestle - 2 Sets Ton 176 50000 88.00<br />
141
4 Desilting Chamber Gates<br />
Inlet Gates<br />
Gate (Fixed Wheel Type) including ballast 6.0m<br />
x6.0m - 4No.<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Ton 240 60000 144.00<br />
Embedded parts - 4 Set Ton 80 50000 40.00<br />
Rope drum hoist 120T Capacity- 4 Sets Ton 168 100000 168.00<br />
Hoist platform and Trestles - 4 Sets Ton 168 50000 84.00<br />
Outlet Gates<br />
Gate (Slide Type) 5.3m x5.3m - 2No. Ton 64 60000 38.40<br />
Embedded parts - 4 Set Ton 40 50000 20.00<br />
Lifting Beam Ton 6 50000 3.00<br />
EOT Crane 60T Cap. Set 1 5400000 54.00<br />
5 Silt Flushing Gates (Slide Type)<br />
Gates (Service & Emergency) 2.5m x2.0m - 8<br />
Nos.<br />
Embedded parts (including bonnet, bonnet<br />
cover,gate body liner etc.)-2Set<br />
Hydraulic Hoist ( Two Double acting cylindres<br />
<strong>of</strong> 300T Cap. each + one common power pack )<br />
Ton 64 100000 64.00<br />
Ton 144 50000 72.00<br />
Set 4 10500000 420.00<br />
6 Surge shaft gate & hoist<br />
Gate (Slide Type) 6.25m x8.25m - 2 No. Ton 132 60000 79.20<br />
Embedded parts - 2 Set Ton 56 50000 28.00<br />
Rope drum hoist 105T Cap.- 2 Set Ton 74 100000 74.00<br />
Hoist platform and trestle - 2 Set Ton 74 50000 37.00<br />
7 Draft Tube gates & hoist<br />
Gate (Fixed Wheel type) 5.0m x4.3m - 8 No. Ton 160 60000 96.00<br />
Embedded Parts - 8 Set Ton 56 50000 28.00<br />
Lifting Beam Ton 3 50000 1.50<br />
Gantry Crane 35T Cap. Set 1 4200000 42.00<br />
8 Pressure shaft steel Liner<br />
Steel Liner including transition and bifurcations -<br />
2 No. (IS 2002 Gr. 3)<br />
Ton 2000 70000 1400.00<br />
9 Adit Gates<br />
Adit gates (2.5m x2.5m) - 1 Nos. Ton 8 60000 4.80<br />
Embedded Parts - 1 Set Ton 4 50000 2.00<br />
10 Instruments and Remote Control Set 1 10000000 100.00<br />
11 D G Set 500 KVA Set 1 2500000 25.00<br />
7738.40<br />
Add 5% for contingencies, spares and bypass<br />
Valves<br />
5% 386.92<br />
Grand Total 8125.32<br />
142
S.<br />
No.<br />
K - BUILDINGS<br />
Description Unit Total<br />
Plinth<br />
Area<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Rate (Rs.) Amount<br />
(Rs. in<br />
Lakhs)<br />
1. Residential Building<br />
C/o Permanent residential buildings Sqm 35000 7000 2450.00<br />
Service charges @ 31% 759.50<br />
Total Residential Buildings<br />
2. Non-Residential Building<br />
C/o Permanent non-residential buildingsSqm. 30000 5500 1650.00<br />
Service charges @ 22.50% 371.25<br />
Total Non-Residential Buildings<br />
(Residential + Non-Residential)<br />
Add for Works Tax @ 6.8% 355.69<br />
Grand Total 5586.44<br />
143
Q-Spl T&P for Infrastructure Development<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
S. No. Description <strong>of</strong> equipment Quantity Rate Amount<br />
(Nos.) (Rs in Lacs)<br />
1 Hydraulic Excavator, 1.0 cum. 1 50.00 50.00<br />
2 Loader cum Excavator, 1.0/0.25 cum. 2 18.00 36.00<br />
3 Crawler Dozer, 200 FHP with ripper 1 85.00 85.00<br />
4 Crawler Dozer, 100 FHP 1 55.00 55.00<br />
5 Wheel Dozer, 300 FHP 1 95.00 95.00<br />
6 Motor Grader, 145 FHP 1 60.00 60.00<br />
7 Air Track/Wagon Drill 2 15.00 30.00<br />
8 Jack Hammer/Pavement Breaker 5 0.35 1.75<br />
9 Diamond Core Drill (Mechanical) 1 15.00 15.00<br />
10 Diamond Core Drill (Hyd) 1 60.00 60.00<br />
11 Compressed Air(cfm) 2000 0.0125 25.00<br />
12 Rock splitter 1 10.00 10.00<br />
13 Hyd. Rock breaker 1 60.00 60.00<br />
14 Mobile Crane, 10 t Pick & Carry 1 10.00 10.00<br />
15 Mobile Crane, 20 t (Rough terrain) 1 60.00 60.00<br />
16 Fork Lift, 5t 1 15.00 15.00<br />
17 Fork Lift, 8t/10T 1 25.00 25.00<br />
18 Road Roller, 8/10 t 2 10.00 20.00<br />
19 Concrete Mixer, 14/10 cft 1 1.50 1.50<br />
20 Concrete Mixer, 28 NT 1 4.00 4.00<br />
21 Dewatering Pump L.S 20.00 20.00<br />
22 Submersible cutter pump 1 100.00 100.00<br />
23 Tipper 4.5/6.0 cum. 8 9.00 72.00<br />
24 Truck, 10 t 8 8.00 64.00<br />
25 Low Bed Tractor Trailor, 30 t 1 45.00 45.00<br />
26 Explosive Van, 10 t 1 10.00 10.00<br />
27 Water Tanker/Sprinkler, 10 KL 4 12.00 48.00<br />
28 Petrol/Diesel Tanker, 10 KL 2 12.00 24.00<br />
29 Bus/Mini Bus 6 8.00 48.00<br />
30 Car/MUV 6 4.50 27.00<br />
31 Jeep (Petrol/Diesel) 30 4.50 135.00<br />
32 Ambulance 2 8.00 16.00<br />
33 Workshop Equipment L.S 20.00 20.00<br />
34 Fire Tender 2 15.00 30.00<br />
35 Recovery Van 1 5.00 5.00<br />
36 Pick up Van/L.C.V 4 5.50 22.00<br />
37 Motor boat 2 5.00 10.00<br />
38 Barges with travwlers 2 10.00 20.00<br />
39 Motorised winch 100 HP 2 5.00 10.00<br />
40 Motorised winch 200 HP 2 10.00 20.00<br />
1464.25<br />
144
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
DISTRIBUTION OF COST UNDER HEAD Q - SPECIAL T & P AND V -<br />
RECEIPT & RECOVERIES<br />
Cost Q R&R<br />
(Rs. In lakhs)<br />
Cost <strong>of</strong> equipments excluding inspection vehicles 1208.25 302.06 226.55<br />
Cost <strong>of</strong> inspection vehicles 256.00 256.00 51.20<br />
Provision under head Q - Spl. T&P 1464.25 558.06<br />
Recoveries to be shown under V- Receipt and<br />
Recoveries<br />
277.75<br />
145
S.<br />
No.<br />
R- COMMUNICATION<br />
Description Length<br />
(km)<br />
A New Road<br />
1Approach road connecting<br />
Dam Site , PH site, Adits etc<br />
on right bank & quarry site/<br />
muck disposal etc on left<br />
bank <strong>of</strong> river Singit<br />
2Road for Township and<br />
Store area<br />
Rate (Rs. In<br />
lakhs)<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
Amount<br />
(Rs. in<br />
Lakhs)<br />
25 90.00 2250.00<br />
a)Township area<br />
i) Two lane 5 120.00 600.00<br />
ii) Single lane 10 90.00 900.00<br />
b)Store area<br />
i) Two lane 1 120.00 120.00<br />
ii) Single lane 4 90.00 360.00<br />
Subtotal "A" 4230.00<br />
B 1 Widening and strengthening<br />
<strong>of</strong> existing Road from<br />
Dengser damsite to <strong>Nalo</strong><br />
damsite and miscellaneous<br />
stretches<br />
2 Bridge on river Singit<br />
Bailey Bridge Near Damsite<br />
and <strong>Power</strong> House<br />
25 50 1250.00<br />
2 X 0.12 L.S. 400.00<br />
Total (A+B) 5880.00<br />
Add for Works Tax @ 6.8% 399.84<br />
Grand Total 6279.84<br />
146
V - RECEIPT & RECOVERIES<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
S. No. Item Amount<br />
(Rs. In Lakhs)<br />
1. Recovery from the Sale <strong>of</strong> Equipments 277.75<br />
Total 277.75<br />
147
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
148
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
149
13.0 ECONOMIC EVALUATION<br />
CHAPTER – XIII<br />
ECONOMIC EVALUATION<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
The Project has been contemplated as a run-<strong>of</strong>f the river scheme on<br />
river Subansiri/Si Ngit. The project is estimated to cost Rs. 2609.66<br />
crores excluding IDC at June 2003 Price Level. Sale price <strong>of</strong> energy<br />
generated at powerhouse bus bars has been worked out as Rs. 3.71<br />
per unit with free power to home state (Table 13.2) and Rs. 3.27 per<br />
unit without free power to home state (Table 13.2-A).<br />
13.1 ECONOMIC JUSTIFICATION<br />
The energy generation <strong>of</strong> the project with an installed capacity <strong>of</strong><br />
(4 x 90) MW has been estimated at 1732.99 MU in a 90% dependable<br />
year.<br />
13.2 COST ESTIMATES AND PHASING OF EXPENDITURES<br />
The cost <strong>of</strong> construction <strong>of</strong> the project has been estimated at June 2003<br />
price level with a construction schedule <strong>of</strong> 7.5 years including 1.5 years for<br />
Infrastructure works during stage-II activity.<br />
The estimated Present Day Cost <strong>of</strong> the project is Rs. 2609.66 Crores<br />
without IDC at June 2003 Price level.<br />
13.3 PHASING OF EXPENDITURE<br />
The phasing <strong>of</strong> expenditure has been worked out on the basis <strong>of</strong><br />
anticipated construction programme.<br />
150
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
The phasing <strong>of</strong> expenditure without IDC for the present cost is shown as<br />
below:<br />
Year Estimated Cost at June 2003 P.L.<br />
(Rs. in Crores)<br />
1 st 104.39<br />
2 nd 208.77<br />
3 rd<br />
234.87<br />
4 th 339.26<br />
5 th 391.45<br />
6 th 574.13<br />
7 th 469.74<br />
7.5 th 287.06<br />
Net Cost 2609.67<br />
13.4 INTEREST DURING CONSTRUCTION (IDC)<br />
Based upon above phasing <strong>of</strong> expenditure the interest during construction<br />
(IDC) have been calculated with 70:30 debt equity ratio and 10.0% interest<br />
on loan. (Table 13.1)<br />
The estimated IDC with estimated present cost is Rs 312.48 Crores<br />
151
13.5 COST OF ENERGY GENERATION<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
The cost <strong>of</strong> energy generation has been calculated for the annual energy<br />
generation in a 90% dependable year based upon following assumptions.<br />
1. Debt-equity ratio 70 : 30<br />
2. Annual interest rate on loan 10.0%<br />
3. Return on equity 16%<br />
4. Annual interest rate on working capital 10.0%<br />
5. O&M Charges 1.5% <strong>of</strong> Project Cost<br />
6. Free power to Home State 12% <strong>of</strong> the energy available<br />
after losses<br />
7. Depreciation considered 1/12 th <strong>of</strong> loan amount during<br />
loan repayment period.<br />
The levellised tariff <strong>of</strong> the Project at present day cost works out to be<br />
Rs.3.01 Per Unit with free power to home state (Table 13.3) and Rs. 2.65<br />
per unit without free power to home state (Table 13.3-A).<br />
152
Table 13.1<br />
STATEMENT SHOWING IDC CALCULATION AT PRESENT DAY COST (JUNE 2003 LEVEL)<br />
PRESENT DAY COST 2609.66 Crs. Transmission Works 62.31 Crores<br />
Civil Works 2212.47 Crs. Electrical Works 334.89Crs.<br />
INTEREST RATE PER ANNUM 10% Transmission cost 62.31 Crs.<br />
(Rs. in Crs.)<br />
Present Day Amount Receivable I.D.C Loan Outstanding Amount Receivable<br />
Year Cost Equity Loan at the end <strong>of</strong> Equity Loan<br />
year (for the year)<br />
1 2 3 4 5 6 7 8<br />
1 104.39 104.39 104.39<br />
2 208.77 208.77 208.77<br />
3 234.87 234.87 234.87<br />
4 339.26 328.61 10.64 0.02 10.66 328.61 10.66<br />
5 391.45 391.45 20.64 422.75 412.09<br />
6 574.13 574.13 70.98 1067.85 645.11<br />
7 469.74 469.74 130.27 1667.87 600.01<br />
7.5 287.06 287.06 90.57 2045.50 377.63<br />
Total 2609.66 876.64 1733.02 312.48 876.64 2045.50<br />
IDC 312.48 Crs. Equity 876.64 Crs.<br />
Net cost <strong>of</strong> the project 2922.14 Crs. Loan 2045.50 Crs.<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
153
TABLE-13.2<br />
UNIT COST OF ENERGY AT BUS BAR AT CURRENT PRICE LEVEL<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
(June 2003 P.L.) With 12% Free <strong>Power</strong> to Home State<br />
(Based on 16% return on equity & 10% interest on loan, 10% interest on working<br />
1 Installed capacity 360 MW<br />
2 Cost <strong>of</strong> the Project (Net) Rs. 2609.66 Crores<br />
3 Interest During Construction Rs. 312.48 Crores<br />
4 Total Cost <strong>of</strong> Project Rs. 2922.14 Crores<br />
(Including IDC)<br />
a) Equity 30% Rs. 876.64 Crores<br />
b) Loan 70% Rs. 2045.50 Crores<br />
5 Annual Energy Generation 1732.99 MU<br />
6 0.7% As Auxiliary Consumption <strong>of</strong> No. 5 0.50% 8.66 MU<br />
7 Energy Available After Auxiliary Consumption 1724.33 MU<br />
8 0.5% As Transformer Loss <strong>of</strong> No. 7 0.50% 8.62 MU<br />
9 Energy Available After Transformer Loss 1715.70 MU<br />
10 Free <strong>Power</strong> to Home State 12% 205.88 MU<br />
11 Energy Available After Allowing Free <strong>Power</strong> 1509.82 MU<br />
12 Fixed and Running Charges<br />
A) Capacity Charges<br />
a) Interest on Loan 10.00% 196.03 Crores<br />
b) Depreciation Charges 170.46 Crores<br />
(Limited to 1/12 th <strong>of</strong> Loan Amount)<br />
SUB-TOTAL 366.49 Crores<br />
B) Energy Charges<br />
a) O&M Charges 1.50% 43.83 Crores<br />
b) Return on Equity 16.00% 140.26 Crores<br />
SUB-TOTAL 184.09 Crores<br />
c) Interest on Working Capital 10.00% 9.70 Crores<br />
I) O&M Charges for 1 month 3.65<br />
II) 2 Months Average Billing 93.38<br />
TOTAL Rs. 560.29 Crores<br />
13 Sale Price at Bus Bar/Unit 3.71 Rs.<br />
14 Cost <strong>of</strong> Generation at Bus Bar/Unit 2.45 Rs.<br />
(Without Allowing Free <strong>Power</strong> to Home State and Return on Equity)<br />
Note : This unit rate is excluding water cess, income tax incentive, penalties etc.<br />
154
TABLE-13.2 A<br />
UNIT COST OF ENERGY AT BUS BAR AT CURRENT PRICE LEVEL<br />
(June 2003 P.L.) WITHOUT FREE POWER TO HOME STATE<br />
(Based on 16% return on equity & 10% interest on loan, 10% interest on working capital)<br />
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
1 Installed capacity 360 MW<br />
2 Cost <strong>of</strong> the Project (Net) Rs. 2609.66 Crores<br />
3 Interest During Construction Rs. 312.48 Crores<br />
4 Total Cost <strong>of</strong> Project Rs. 2922.14 Crores<br />
(Including IDC)<br />
a) Equity 30% Rs. 876.64 Crores<br />
b) Loan 70% Rs. 2045.50 Crores<br />
5 Annual Energy Generation 1732.99 MU<br />
6 0.7% As Auxiliary Consumption <strong>of</strong> No. 5 0.50% 8.66 MU<br />
7 Energy Available After Auxiliary<br />
1724.33 MU<br />
C i<br />
8 0.5% As Transformer Loss <strong>of</strong> No. 7 0.50% 8.62 MU<br />
9 Energy Available After Transformer Loss 1715.70 MU<br />
10 Free <strong>Power</strong> to Home State 0% 0.00 MU<br />
11 Energy Available After Allowing Free <strong>Power</strong> 1715.70 MU<br />
12 Fixed and Running Charges<br />
A) Capacity Charges<br />
a) Interest on Loan 10.00% 196.03 Crores<br />
b) Depreciation Charges 170.46 Crores<br />
(Limited to 1/12 th <strong>of</strong> Loan Amount)<br />
SUB-TOTAL 366.49 Crores<br />
B) Energy Charges<br />
a) O&M Charges 1.50% 43.83 Crores<br />
b) Return on Equity 16.00% 140.26 Crores<br />
SUB-TOTAL 184.09 Crores<br />
c) Interest on Working Capital 10.00% 9.70 Crores<br />
I) O&M Charges for 1 month 3.65<br />
II) 2 Months Average Billing 93.38<br />
TOTAL Rs. 560.29 Crores<br />
13 Sale Price at Bus Bar/Unit 3.27 Rs.<br />
14 Cost <strong>of</strong> Generation at Bus Bar/Unit 2.45 Rs.<br />
(Without Allowing Free <strong>Power</strong> to Home State and Return on Equity)<br />
Note : This unit rate is excluding water cess, income tax incentive, penalties etc.<br />
155
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
156
Preliminary Feasibility Report<br />
<strong>Nalo</strong> HE Project (4 x 90 MW)<br />
157
SALIENT FEATURES<br />
1 LOCATION<br />
State : Arunachal Pradesh<br />
District : Upper Subansiri<br />
River : Subansiri/Singit<br />
Dam site : 1.6 km u/s <strong>of</strong><br />
Ledi Ishi Nallah<br />
Nearest BG rail head : Nagaon<br />
Nearest airport : Lilabari(North Lakhimpur)<br />
2 HYDROLOGY<br />
Catchment area : 14500 sq.km.<br />
Location <strong>of</strong> catchment :<br />
Latitude 27 o 50’ N to 29 o 00’ N<br />
Longitude 91 o 45' E to 93 o 49' E<br />
Average annual rainfall : 2810 mm<br />
3 RESERVOIR<br />
Full reservoir level<br />
(FRL)<br />
: EL 765 m<br />
Min.Draw Down Level<br />
(MDDL)<br />
Gross storage<br />
: EL 745 m<br />
-at FRL : 163.37 mcm<br />
-at MDDL<br />
Area under<br />
: 113 mcm<br />
submergence at FRL : 283.8 ha<br />
4 DIVERSIONTUNNEL<br />
Number : 2<br />
Size : 10.75 m<br />
Shape : Horse shoe<br />
Length : 650/800 m<br />
Diversion capacity<br />
(assumed)<br />
: 2600 cumec<br />
U/s c<strong>of</strong>fer dam : 28 m<br />
D/s c<strong>of</strong>fer dam : 14 m<br />
Annexure 1.1<br />
1-4<br />
174
5 DAM<br />
Type : Concrete<br />
Top elevation <strong>of</strong> dam<br />
Height <strong>of</strong> dam above<br />
: EL 770 m<br />
deepest foundation level : 125 m<br />
Length <strong>of</strong> dam at top : 366 m<br />
River Bed level EL 660 m<br />
SPILLWAY<br />
Design flood<br />
Lower spillway<br />
: 12300 cumec<br />
Crest elevation EL 715 m<br />
Type : Orifice<br />
Number 5<br />
Size <strong>of</strong> opening<br />
Upper spillway<br />
9.75 x 11.5 m<br />
Crest elevation EL 753.5 m<br />
Type : Crest<br />
Number 2<br />
Size <strong>of</strong> opening 9.75 x 11.5 m<br />
Energy dissipation : Ski jump with preformed<br />
plunge pool<br />
Length <strong>of</strong> spillway : 120 m<br />
6 INTAKE<br />
Invert level : EL 725 m<br />
Number : 2<br />
Size <strong>of</strong> gate opening : 7.5 x 8.5 m<br />
Trash rack : 18 x 20 m<br />
Intake tunnel 8.5 m<br />
Intake tunnel length 250/350 m<br />
7 DESILTING CHAMBERS<br />
Number : 4<br />
Size : 17 x 25 m<br />
Length : 300 m<br />
Design discharge<br />
per chamber<br />
: 111.8 cum<br />
Particle size to be removed : 0.2 mm and above<br />
8 HEAD RACE TUNNEL<br />
Number : 2<br />
Size : 7.5 m<br />
Shape : Horse shoe<br />
Length : 2.5 /2.6 km<br />
Design discharge<br />
per tunnel<br />
: 186.4 cumec<br />
Annexure 1.1<br />
2-3<br />
175
9 SURGE SHAFT<br />
Number : 2<br />
Size : 20 m<br />
Height : 90 m<br />
10 PRESSURE SHAFT<br />
Number 2<br />
Size 6.25 m<br />
Vertical height 82 m<br />
11 POWER HOUSE<br />
Type : Surface<br />
Installed capacity : 360 MW<br />
Number <strong>of</strong> units : 4 (90MW each)<br />
<strong>Power</strong> house size<br />
(machine hall + service bay)<br />
: 103 (L)x 22 (W) x 47 (H)<br />
Type <strong>of</strong> turbine : Vertical Shaft Francis<br />
C.L <strong>of</strong> turbine : EL 633 m<br />
Draft tube opening for :<br />
each unit 2 nos, 5 m (W) X 4.3m(H)<br />
12 TAIL RACE CHANNEL<br />
Bed Width 60 m<br />
Side Slope 1V:1.5H<br />
Design discharge : 372.8 cumec<br />
River Bed level EL 635 m<br />
Maximum TWL EL 645 m<br />
13 SWITCH YARD<br />
Size : 80m (W) X160m(L)<br />
14 POWER GENERATED<br />
Installed capacity<br />
Annual energy generation<br />
: 360 MW<br />
in 90% dependable year : 1732.99 MU<br />
Annexure 1.1<br />
3-3<br />
176
Reply to the comments <strong>of</strong> HP&I Division, CEA vide letter No.<br />
7/9/NHPC/HP&I/2004/695 dt.6.2.2004<br />
<strong>Nalo</strong> H.E Project (4×90 MW)<br />
Annexure-2.3<br />
3-5<br />
Comments Reply<br />
General Comments<br />
1 It may be ensured that the Initial Initial Environmental studies have been<br />
Environmental studies incorporated in the carried out through National Remote<br />
PFR are as per scope <strong>of</strong> the work for PFR. Sensing Agency (NRSA), Hyderabad as<br />
per scope <strong>of</strong> work and same are<br />
incorporated in PFR.<br />
2. It may be ensured that the Financial<br />
Parameters are taken as per guidelines sent<br />
vide our Lr. No. 7/9/HP&I-2003/1118-<br />
1123, dated 21 st October, 2003.<br />
3. It may be ensured that the Cost Estimates<br />
prepared are as per the guidelines sent<br />
vide our Lr. No. 7/9/HP&I/2003/1163-<br />
1172, dated 24.10.2003<br />
4. NHPC may indicate recommendations for<br />
further studies required wherever<br />
necessary in the relevant chapters <strong>of</strong> PFRs<br />
for consideration during FR/DPR stage.<br />
5. It may be ensured that the Installed<br />
Capacities & Assessment <strong>of</strong> power<br />
benefits takes into account various<br />
comments and advise given in this regard.<br />
Guidelines have been followed.<br />
Cost estimates have been prepared as<br />
per the guidelines.<br />
Recommendations for further studies<br />
have been incorporated in the relevant<br />
chapters <strong>of</strong> PFR.<br />
Installed capacity and assessment <strong>of</strong><br />
power benefits have been vetted by CEA<br />
and comments have been taken into<br />
account. (Annexure 7.1)<br />
183
6. It may be ensured that the hydrology<br />
adopted is approved by CWC.<br />
.<br />
7. The layout planning <strong>of</strong> project<br />
components may take into account the<br />
views & advice <strong>of</strong> CWC.<br />
8. The power evacuation arrangements<br />
considered in the PFR should take into<br />
account views and suggestions <strong>of</strong> SP &<br />
PA Division <strong>of</strong> CEA.<br />
9. An Executive Summary may be prepared<br />
as per general guidance sent vide our Lr.<br />
No. 7/9/HPI-2003/1412-1419 dated 2 nd<br />
December, 2003.<br />
<strong>Power</strong> Potential Studies<br />
1. Utilization <strong>of</strong> 5m drop between TWL (770)<br />
<strong>of</strong> upstream Naba HEP& proposed FRL<br />
(765m) <strong>of</strong> <strong>Nalo</strong> HEP may be kept in view<br />
at FR/DPR stage.<br />
2. The TWL (645m) has been fixed<br />
considering river bed level (635m) <strong>of</strong> the<br />
proposed power house. The TWL would<br />
have to be reviewed at FR/DPR stage.<br />
Annexure-2.3<br />
4-5<br />
Hydrology chapter submitted to CWC.<br />
Replies to comments received are<br />
appended with PFR.<br />
Comments <strong>of</strong> CWC on project<br />
components received. Replies to<br />
comments received are appended with<br />
PFR.<br />
Comments on power evacuation<br />
arrangements by CEA have been taken<br />
into account while finalizing PFR.<br />
Executive summary (chapter-I) has been<br />
prepared as per CEA’s guidelines.<br />
Noted<br />
Noted<br />
184
3. It is presumed that the selection <strong>of</strong> unit size<br />
<strong>of</strong> 130 MW takes into account<br />
transportation constraints etc.<br />
4. NHPC may indicate recommendations for<br />
further studies required for preparation <strong>of</strong><br />
FR/DPR.<br />
Annexure-2.3<br />
5-5<br />
The unit size is 90 MW instead <strong>of</strong> 130<br />
MW as mentioned in the comments <strong>of</strong><br />
CEA. The unit size <strong>of</strong> 90 MW has been<br />
taken considering transport constraints<br />
<strong>of</strong> this project.<br />
Recommendations for further studies<br />
required for preparation <strong>of</strong> FR/DPR are<br />
given in PFR.<br />
185
SUBANSIRI BASIN PROJECTS<br />
Annexure-5.1A<br />
MONTHLY RAINFALL (MM) AT TALIHA<br />
YEAR JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC Annual<br />
1968 83.0 167.9 183.4 169.1 353.1 258.0 530.1 346.6 113.0 128.0 3.0 2335.2<br />
1969 75.0 164.1 348.1 221.3 347.2 333.6 488.2 41.3 2018.8<br />
1976 99.1 181.9 215.7 417.7 504.0 341.2 211.8 220.1 124.2 128.0 2443.7<br />
1977 58.9 124.4 141.1 450.1 357.7 357.4 344.2 319.2 310.6 165.3 60.0 49.5 2738.4<br />
1978 37.3 71.1 174.4 458.1 318.8 437.0 342.1 161.2 422.4 108.4 76.6 2607.4<br />
1979 40.8 144.1 182.4 272.4 155.7 333.0 471.4 339.3 315.4 145.8 36.8 184.7 2621.8<br />
1980 139.5 219.9 241.8 251.4 69.7 287.4 268.0 29.6 20.7 1528.0<br />
1981 128.4 126.5 189.2 127.5 569.7 488.7 724.4 130.7 65.7 68.7 45.6 51.7 2716.8<br />
1982 0.5 93.2 167.5 34.0 36.5 49.6 110.9 113.4 265.1 26.2 33.3 0.0 930.2<br />
1983 0.0 241.7 419.7 247.7 582.9 521.7 2013.7<br />
1985 157.5 263.3 74.0 7.3 52.6 554.7<br />
1986 75.1 147.9 223.0<br />
1997 36.7 170.0 99.8 293.4 280.4 146.8 269.6 118.2 126.8 123.2 1664.9<br />
2000 498.4 400.0 161.4 96.8 5.0 1161.6<br />
2001 38.2 83.6 141.0 610.0 275.8 358.2 305.5 376.0 486.7 245.7 132.9 20.0 3073.6<br />
2002 184.5 69.5 184.0 464.6 98.6 270.7 475.8 363.3 335.0 46.6 34.0 26.6 2553.2<br />
2003 40.8 104.2 171.6 267.1 279.8 417.0 1280.5<br />
AVG 62.5 116.1 186.2 283.7 286.5 315.5 373.3 281.0 294.3 123.7 66.7 49.3 2438.8<br />
195
SUBANSIRI BASIN PROJECTS<br />
MONTHLY RAINFALL(MM) AT SIYUM<br />
YEAR JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC TOTAL<br />
1966 11.4 122.0 200.0 293.0 217.0 604.0 372.0 356.0 129.4 2304.8<br />
1968 69.0 90.1 187.0 188.0 383.0 511.0 615.0 284.1 406.0 319.0 80.0 3132.2<br />
1969 37.0 193.0 216.0 292.0 604.0 567.0 418.0 132.0 4.0 88.0 2551.0<br />
2001 381.0 475.3 540.7 244.2 93.4 20.0 1754.6<br />
2002 92.2 44.0 281.6 316.7 391.1 495.0 766.7 354.3 333.5 95.5 15.0 28.3 3213.9<br />
AVG 40.2 83.0 193.3 232.3 297.3 573.0 483.8 392.5 358.7 189.1 97.7 20.0 2960.9<br />
196<br />
Annexure-5.1B
SUBANSIRI BASIN PROJECTS<br />
MONTHLY RAINFALL(MM) AT LIMEKING<br />
YEAR JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC TOTAL<br />
1966 169.6 209.0 516.6 558.6 385.2 1839.0<br />
1968 25.0 69.0 149.0 98.0 332.0 448.1 449.0 399.0 362.0 134.0 2465.1<br />
1969 48.2 100.0 166.1 330.0 503.1 502.0 394.5 331.0 2374.9<br />
1977 55.7 519.8 458.0 334.1 134.3 1501.9<br />
1978 19.1 55.7 33.8 111.4 381.6 548.6 461.4 206.0 456.3 139.0 67.7 21.8 2502.4<br />
1979 296.9 140.2 227.2 325.3 540.2 733.0 511.6 599.2 525.0 380.6 64.0 58.6 4401.8<br />
1980 183.9 123.0 416.0 464.2 588.6 955.3 663.8 548.1 339.0 153.2 18.2 4453.3<br />
2001 241.4 503.0 345.7 177.8 28.6 1296.5<br />
2002 33.9 37.9 120.7 64.8 306.6 563.9<br />
AVG 111.8 79.0 174.5 199.9 384.0 537.2 488.5 444.0 384.8 186.5 44.6 40.2 3074.8<br />
197<br />
Annexure-5.1C
SUBANSIRI BASIN PROJECTS<br />
MONTHLY RAINFALL(MM) AT NACHO<br />
YEAR JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC TOTAL<br />
2001 6.5 62.4 117.3 239.9 340.2 504.6 427.0 694.1 573.5 204.1 72.9 13.3 3255.8<br />
2002 45.6 57.7 149.4 153.0 279.7 492.2 389.5 239.4 242.9 63.2 21.0 28.2 2161.8<br />
2003 15.3 57.7 149.4 126.3 230.9 750.5 460.2 487.1 458.6 86.1 42.2 11.8 2876.1<br />
Average 22.5 59.3 138.7 173.1 283.6 582.4 425.6 473.5 425.0 117.8 45.4 17.8 2764.6<br />
198<br />
Annexure-5.1D
SUBANSIRI UPPER PROJECT<br />
SYNTHETIC 10-DAILY FLOW SERIES AT MENGA (NHPC)<br />
Annexure-5.2<br />
1-2<br />
YEAR JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC AVG<br />
I 123.66 154.30 206.02 307.57 451.79 939.71 1225.37 1887.91 1096.25 481.27 295.36 152.72<br />
1 II 137.62 171.89 252.37 273.85 303.63 1634.30 1923.30 1842.40 1383.00 848.96 214.49 153.68 699.69<br />
III 144.25 187.98 224.34 466.39 679.70 2488.75 1669.53 1191.39 834.66 463.75 231.60 145.23<br />
I 157.69 141.97 137.83 236.77 458.14 1080.84 1426.26 953.11 700.89 515.48 426.81 194.40<br />
2 II 125.49 159.86 155.05 305.37 733.33 1383.18 1435.49 1043.84 1177.66 494.41 361.80 154.85 587.76<br />
III 129.38 151.64 139.60 369.15 569.91 1665.93 1164.20 1199.76 1023.01 450.75 208.86 126.69<br />
I 133.55 135.09 182.34 364.76 361.59 520.42 1021.56 896.36 2714.33 1123.44 339.75 231.30<br />
3 II 146.66 153.94 219.07 292.58 460.99 828.84 1001.09 933.62 2447.16 771.73 205.22 195.34 642.13<br />
III 131.13 135.92 254.14 354.79 343.50 870.63 796.39 1719.52 1875.50 558.47 228.92 166.86<br />
I 158.00 137.23 164.07 308.23 671.79 511.40 1527.47 1489.72 696.41 556.04 245.99 150.51<br />
4 II 151.80 132.98 218.75 437.73 786.19 962.93 2481.76 1179.78 616.18 781.38 201.08 163.78 611.58<br />
III 138.01 144.06 278.59 576.70 446.16 1271.38 1882.74 967.55 803.65 431.11 185.94 159.96<br />
I 127.68 106.96 127.04 261.34 460.92 909.43 2072.20 1373.69 909.59 1196.20 292.01 206.39<br />
5 II 101.66 97.14 130.18 311.29 569.13 1423.40 1858.70 1205.15 760.40 1192.55 232.82 150.61 670.96<br />
III 95.81 133.23 144.61 333.65 1024.53 1610.08 1486.31 1462.35 850.13 580.24 199.44 157.54<br />
I 133.17 167.23 230.61 325.96 360.82 398.94 1027.24 1329.81 1056.48 1073.63 390.16 154.77<br />
6 II 139.44 171.90 221.23 313.84 507.00 436.35 822.48 1476.93 815.43 972.77 226.81 158.47 519.03<br />
III 140.28 180.86 181.02 274.83 325.35 540.80 1286.16 1351.53 662.26 502.89 196.54 130.97<br />
I 98.02 143.82 158.56 221.11 593.53 564.16 1107.43 629.07 571.51 729.61 281.62 270.40<br />
7 II 117.08 133.57 144.93 284.39 544.95 661.80 1595.40 803.41 697.14 383.68 308.50 184.53 494.06<br />
III 129.85 125.95 138.29 352.33 620.69 945.70 1958.74 742.34 804.00 308.52 279.26 152.33<br />
I 174.75 194.50 194.86 324.57 569.28 2148.90 2811.71 1231.36 1271.46 1022.18 496.67 177.27<br />
8 II 163.54 145.07 180.85 338.53 870.97 2686.49 3102.75 1389.81 909.74 1102.44 425.20 187.60 951.59<br />
III 176.76 150.71 229.53 253.12 1270.38 2408.62 3908.05 1523.02 1267.89 500.80 280.03 167.84<br />
I 152.54 102.39 180.23 197.11 417.90 386.42 1698.96 1627.47 1154.06 1244.62 311.46 140.54<br />
9 II 121.76 94.96 188.32 345.55 296.84 368.19 1324.80 2079.22 1039.96 532.05 325.81 146.07 603.79<br />
III 114.66 99.03 164.93 371.45 474.02 593.60 1898.80 1539.58 1124.19 554.68 203.20 121.18<br />
I 96.98 116.74 235.82 234.11 367.88 273.10 1158.67 749.35 733.23 964.53 221.50 157.20<br />
10 II 90.92 147.71 186.00 278.93 272.04 568.06 893.53 1149.74 1366.95 513.73 258.84 127.91 490.48<br />
III 95.44 142.54 189.17 283.71 315.61 703.30 1422.52 1025.41 1717.59 300.81 182.91 114.91<br />
199
Annexure-5.2<br />
2-2<br />
I 87.90 119.60 158.37 219.11 569.68 487.73 788.20 1014.55 1729.96 1269.70 326.71 171.77<br />
11 II 86.23 93.71 225.98 219.58 689.52 553.01 1360.74 1109.88 1894.12 481.71 280.09 201.21 590.27<br />
III 89.75 147.28 209.78 270.14 653.10 514.53 994.26 1831.52 1516.36 452.40 254.03 177.65<br />
I 204.59 176.47 188.58 304.04 616.52 654.82 1350.12 819.48 1487.72 671.95 230.24 196.13<br />
12 II 206.03 178.32 169.24 350.57 529.79 796.45 1077.28 1113.20 1572.22 748.04 218.26 150.20 609.24<br />
III 194.82 163.67 194.30 349.68 297.35 1137.94 1764.83 1969.14 1159.34 378.65 178.89 133.64<br />
I 101.10 135.26 192.63 308.78 383.25 624.52 933.77 1822.37 772.81 1088.59 316.53 150.02<br />
13 II 101.86 100.72 249.97 297.95 367.85 588.79 1464.80 2379.30 722.63 472.93 300.75 155.51 575.25<br />
III 112.90 150.05 251.57 331.50 753.30 1061.47 1158.72 1515.43 576.18 391.90 222.03 151.09<br />
I 121.99 125.75 188.09 288.91 415.18 956.08 1358.86 1397.83 1265.46 1035.85 323.94 207.88<br />
14 II 99.76 98.88 255.61 386.24 412.10 1631.64 1604.87 1482.32 920.77 527.39 277.25 231.99 663.64<br />
III 94.73 125.37 219.17 329.30 404.27 2181.95 1964.34 1401.77 845.52 309.53 199.18 201.41<br />
I 210.35 236.51 209.85 214.46 466.98 297.26 1860.31 1527.56 658.93 573.22 415.63 256.21<br />
15 II 190.14 148.47 230.81 208.72 400.92 556.79 1741.17 1375.87 726.77 429.38 341.99 181.90 542.12<br />
III 180.77 177.94 200.61 201.81 246.15 848.77 1528.09 1204.47 699.18 377.92 236.64 153.62<br />
I 117.47 188.83 223.04 311.78 482.67 1204.14 735.13 1071.28 1328.94 818.54 365.63 170.31<br />
16 II 128.96 184.16 175.15 258.66 359.49 837.76 610.21 1645.56 1039.54 502.10 328.78 138.87 557.43<br />
III 141.70 198.72 170.73 397.23 486.32 844.98 681.05 1795.85 1375.16 355.72 249.45 143.40<br />
I 111.12 125.52 150.71 431.57 481.88 278.69 604.36 1609.13 2128.58 747.97 382.35 159.82<br />
17 II 88.18 139.01 167.62 363.44 377.16 357.21 1169.95 2136.21 1505.91 816.03 230.01 134.54 640.45<br />
III 98.15 139.40 239.24 468.54 287.63 533.28 1455.66 2553.31 1645.83 641.23 158.32 138.56<br />
I 138.40 153.22 223.41 240.33 361.31 255.64 758.70 893.53 851.25 872.34 311.66 203.06<br />
18 II 140.98 110.31 185.10 228.51 265.86 335.18 1443.27 826.05 785.61 873.44 196.70 180.36 447.44<br />
III 133.66 163.43 161.26 339.18 217.41 645.63 1298.88 835.94 617.55 521.22 170.11 169.23<br />
I 143.47 179.63 183.68 377.92 598.44 1165.66 2130.98 1071.87 1379.56 662.53 304.01 221.42<br />
19 II 144.48 194.69 243.21 519.25 791.05 1784.94 2581.77 1198.68 1120.24 664.02 183.26 158.83 789.71<br />
III 134.09 205.76 307.92 375.48 587.80 1809.34 3398.86 1927.90 752.90 607.50 181.22 137.17<br />
I 125.59 91.95 112.37 195.30 378.76 603.21 1619.12 1182.85 1156.89 485.50 236.36 144.43<br />
20 II 103.18 91.74 132.59 201.71 378.87 1112.78 2207.89 1459.76 1396.46 518.88 149.31 129.07 605.06<br />
III 98.34 117.33 148.04 290.76 488.17 1113.56 2788.79 1129.60 774.37 328.84 165.53 124.32<br />
I 135.90 146.65 182.41 283.69 473.42 713.05 1360.82 1228.92 1183.22 856.66 325.72 185.83<br />
AVG II 129.29 137.45 196.60 310.83 495.88 975.40 1585.06 1391.54 1144.89 681.38 263.35 164.27 614.58<br />
III 128.72 152.04 202.34 349.49 524.57 1189.51 1725.35 1444.37 1046.26 450.85 210.61 148.68<br />
Note : All Discharges are in cumec.<br />
200
NALO H.E. PROJECT<br />
SYNTHETIC AVERAGE 10-DAILY DISCHARGE SERIES AT DAM SITE<br />
YEAR JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC<br />
I 64.86 80.93 108.05 161.31 236.95 492.85 642.67 990.15 574.95 252.41 154.91 80.10<br />
1 II 72.18 90.15 132.36 143.63 159.24 857.14 1008.71 966.28 725.34 445.25 112.49 80.60<br />
III 75.65 98.59 117.66 244.61 356.48 1305.27 875.61 624.84 437.75 243.22 121.47 76.17<br />
I 82.70 74.46 72.29 124.18 240.28 566.86 748.03 499.87 367.59 270.35 223.85 101.96<br />
2 II 65.82 83.84 81.32 160.16 384.61 725.43 752.87 547.46 617.64 259.30 189.75 81.21<br />
III 67.86 79.53 73.22 193.61 298.90 873.72 610.58 629.23 536.53 236.40 109.54 66.44<br />
I 70.04 70.85 95.63 191.30 189.64 272.94 535.77 470.11 1423.58 589.21 178.19 121.31<br />
3 II 76.92 80.74 114.89 153.45 241.77 434.70 525.04 489.65 1283.45 404.75 107.63 102.45<br />
III 68.77 71.29 133.29 186.08 180.15 456.62 417.68 901.83 983.64 292.90 120.06 87.51<br />
I 82.87 71.97 86.05 161.66 352.33 268.21 801.11 781.31 365.24 291.62 129.01 78.94<br />
4 II 79.61 69.74 114.73 229.57 412.33 505.02 1301.60 618.76 323.17 409.81 105.46 85.90<br />
III 72.38 75.55 146.11 302.46 234.00 666.80 987.43 507.45 421.49 226.10 97.52 83.89<br />
I 66.96 56.10 66.63 137.06 241.74 476.97 1086.80 720.45 477.05 627.37 153.15 108.24<br />
5 II 53.32 50.95 68.28 163.26 298.49 746.53 974.83 632.06 398.80 625.45 122.11 78.99<br />
III 50.25 69.87 75.84 174.99 537.33 844.43 779.52 766.95 445.86 304.32 104.60 82.62<br />
I 69.84 87.71 120.95 170.96 189.24 209.23 538.75 697.44 554.09 563.08 204.63 81.17<br />
6 II 73.13 90.16 116.03 164.60 265.90 228.85 431.36 774.60 427.67 510.19 118.95 83.11<br />
III 73.57 94.86 94.94 144.14 170.64 283.63 674.55 708.83 347.33 263.75 103.08 68.69<br />
I 51.41 75.43 83.16 115.96 311.29 295.88 580.81 329.93 299.74 382.66 147.70 141.82<br />
7 II 61.40 70.05 76.01 149.15 285.81 347.09 836.73 421.36 365.63 201.23 161.80 96.78<br />
III 68.10 66.06 72.53 184.79 325.53 495.99 1027.29 389.33 421.67 161.81 146.46 79.89<br />
I 91.65 102.01 102.20 170.23 298.57 1127.03 1474.65 645.81 666.84 536.10 260.49 92.97<br />
8 II 85.77 76.08 94.85 177.55 456.79 1408.97 1627.29 728.91 477.13 578.19 223.00 98.39<br />
III 92.70 79.04 120.38 132.75 666.27 1263.24 2049.64 798.77 664.97 262.65 146.87 88.03<br />
I 80.00 53.70 94.52 103.38 219.17 202.66 891.05 853.55 605.27 652.76 163.35 73.71<br />
9 II 63.86 49.80 98.77 181.23 155.68 193.10 694.81 1090.48 545.42 279.04 170.88 76.61<br />
III 60.14 51.94 86.50 194.81 248.61 311.32 995.86 807.46 589.60 290.91 106.57 63.55<br />
I 50.86 61.23 123.68 122.78 192.94 143.23 607.68 393.01 384.55 505.86 116.17 82.45<br />
10 II 47.68 77.47 97.55 146.29 142.68 297.93 468.63 603.00 716.92 269.43 135.75 67.08<br />
III 50.06 74.76 99.21 148.80 165.53 368.86 746.06 537.79 900.82 157.76 95.93 60.27<br />
I 46.10 62.73 83.06 114.92 298.78 255.80 413.38 532.10 907.31 665.92 171.35 90.09<br />
11 II 45.22 49.15 118.52 115.16 361.63 290.04 713.66 582.10 993.40 252.64 146.90 105.53<br />
III 47.07 77.24 110.02 141.68 342.53 269.85 521.46 960.57 795.28 237.27 133.23 93.17<br />
201<br />
Annexure-5.3<br />
1-2
NALO H.E. PROJECT<br />
SYNTHETIC AVERAGE 10-DAILY DISCHARGE SERIES AT DAM SITE<br />
YEAR JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC<br />
I 107.30 92.55 98.90 159.46 323.34 343.43 708.09 429.79 780.26 352.42 120.75 102.86<br />
12 II 108.06 93.52 88.76 183.86 277.86 417.71 565.00 583.84 824.58 392.32 114.47 78.77<br />
III 102.18 85.84 101.90 183.40 155.95 596.81 925.59 1032.75 608.04 198.59 93.82 70.09<br />
I 53.02 70.94 101.03 161.94 201.00 327.54 489.73 955.77 405.31 570.93 166.01 78.68<br />
13 II 53.42 52.82 131.10 156.26 192.93 308.80 768.24 1247.86 379.00 248.04 157.73 81.56<br />
III 59.21 78.70 131.94 173.86 395.08 556.71 607.71 794.79 302.19 205.54 116.45 79.24<br />
I 63.98 65.95 98.65 151.52 217.75 501.43 712.68 733.12 663.69 543.27 169.90 109.03<br />
14 II 52.32 51.86 134.06 202.57 216.13 855.74 841.70 777.43 482.91 276.60 145.41 121.67<br />
III 49.68 65.75 114.95 172.71 212.03 1144.36 1030.23 735.18 443.45 162.34 104.46 105.63<br />
I 110.32 124.04 110.06 112.48 244.92 155.90 975.67 801.15 345.59 300.63 217.98 134.37<br />
15 II 99.72 77.87 121.05 109.47 210.27 292.02 913.19 721.60 381.17 225.20 179.36 95.40<br />
III 94.81 93.32 105.21 105.84 129.10 445.15 801.43 631.70 366.70 198.21 124.11 80.57<br />
I 61.61 99.04 116.98 163.52 253.14 631.53 385.55 561.85 696.98 429.30 191.76 89.32<br />
16 II 67.64 96.59 91.86 135.66 188.54 439.38 320.03 863.04 545.20 263.33 172.43 72.83<br />
III 74.32 104.22 89.54 208.33 255.06 443.16 357.19 941.86 721.23 186.56 130.83 75.21<br />
I 58.28 65.83 79.04 226.34 252.73 146.16 316.97 843.94 1116.37 392.29 200.53 83.82<br />
17 II 46.25 72.91 87.91 190.61 197.81 187.34 613.60 1120.37 789.80 427.98 120.63 70.56<br />
III 51.48 73.11 125.47 245.73 150.85 279.69 763.45 1339.13 863.18 336.30 83.03 72.67<br />
I 72.59 80.36 117.17 126.05 189.50 134.07 397.91 468.63 446.45 457.51 163.46 106.50<br />
18 II 73.94 57.85 97.08 119.85 139.43 175.79 756.95 433.24 412.03 458.09 103.16 94.59<br />
III 70.10 85.71 84.58 177.89 114.02 338.61 681.22 438.42 323.88 273.36 89.22 88.76<br />
I 75.25 94.21 96.33 198.21 313.86 611.35 1117.63 562.16 723.53 347.47 159.44 116.13<br />
19 II 75.77 102.11 127.56 272.33 414.88 936.14 1354.05 628.67 587.53 348.26 96.11 83.30<br />
III 70.33 107.91 161.49 196.93 308.28 948.94 1782.59 1011.12 394.87 318.61 95.04 71.94<br />
I 65.87 48.22 58.93 102.43 198.65 316.36 849.17 620.37 606.75 254.63 123.96 75.75<br />
20 II 54.11 48.11 69.54 105.79 198.70 583.62 1157.96 765.60 732.40 272.14 78.31 67.69<br />
III 51.58 61.54 77.64 152.49 256.03 584.03 1462.63 592.44 406.13 172.47 86.81 65.20<br />
I 71.28 76.91 95.67 148.78 248.29 373.97 713.71 644.53 620.56 449.29 170.83 97.46<br />
AVG II 67.81 72.09 103.11 163.02 260.07 511.57 831.31 729.81 600.46 357.36 138.12 86.15<br />
III 67.51 79.74 106.12 183.29 275.12 623.86 904.89 757.52 548.73 236.45 110.46 77.98<br />
Note : All Discharges are in cumec.<br />
202<br />
Annexure-5.3<br />
2-2
Reply to the Comments <strong>of</strong> CWC on Hydrology chapter<br />
Vide letter No. 7/9/NHPC/HP&I/1014 dated 13.05.2004.<br />
<strong>Nalo</strong> H.E.Project (4×90 MW)<br />
Annexure-5.4<br />
5-7<br />
SL.NO HEADING CWC COMMENTS NHPC REPLY<br />
1 Consistency <strong>of</strong><br />
data<br />
2 Water availability<br />
studies<br />
The methodology and the<br />
detailed analysis done to<br />
generate the synthetic<br />
series is not available in the<br />
report.<br />
1. The methodology and the<br />
detailed analysis done to<br />
generate the synthetic<br />
series is not available in the<br />
report. The series <strong>of</strong> Upper<br />
Subansiri is not yet<br />
approved<br />
2. NHPC is observing the<br />
discharge data at Menga<br />
site since June 2000. An<br />
inter comparison <strong>of</strong><br />
observed and generated<br />
series at Menga site for<br />
concurrent period can throw<br />
light on acceptability <strong>of</strong> the<br />
generated series.<br />
3. Alternatively, available<br />
observed discharge record<br />
since 2000 may be used for<br />
time series analysis for<br />
generation <strong>of</strong> a series <strong>of</strong><br />
desired length and the<br />
same series after transfer to<br />
<strong>Nalo</strong> dam site can be used<br />
for power potential studies.<br />
20% reduction may be<br />
applied to the series so<br />
generated to account for<br />
inaccuracies in discharge<br />
observation for the purpose<br />
<strong>of</strong> PFR<br />
3 Design flood a) The design flood<br />
computation done by NHPC<br />
are too empirical to be<br />
relied upon.<br />
b) In the absence <strong>of</strong> short<br />
interval concurrent rainfall<br />
run<strong>of</strong>f data the design flood<br />
Kindly refer feasibility<br />
report <strong>of</strong> Upper Subansiri<br />
project submitted by<br />
NHPC.<br />
1. Kindly refer water<br />
availability study <strong>of</strong><br />
Hydrology Chapter <strong>of</strong><br />
Feasibility report <strong>of</strong><br />
Subansiri Upper Project,<br />
submitted in August 2002,<br />
to CEA/CWC and CEA has<br />
accorded the commercial<br />
viability <strong>of</strong> the same.<br />
2. A plot between average 10daily<br />
discharge based on<br />
observed and generated<br />
series is enclosed (page<br />
no-209). The series<br />
generated at Subansiri<br />
Upper is a synthetic series<br />
therefore inter comparison<br />
<strong>of</strong> observed and generated<br />
series at Menga site for<br />
concurrent period is not<br />
possible.<br />
3. Since only 3 years data is<br />
available and so it would not<br />
be logical to generate series<br />
based on such short-term<br />
record. The flow series<br />
generated in a synthetic<br />
series based on available<br />
data <strong>of</strong> the entire basin <strong>of</strong><br />
Subansiri, for methodology<br />
refer F.R. <strong>of</strong> Upper<br />
Subansiri Project.<br />
It is worth mentioning here that<br />
although deterministic<br />
approach <strong>of</strong> design flood<br />
computation has not been<br />
used directly in the present<br />
study for <strong>Nalo</strong> sub basin,<br />
however, this approach has<br />
207
4<br />
Sedimentation<br />
may be calculated using<br />
relevant sub zonal report <strong>of</strong><br />
CWC superimposing PMP<br />
values from IMD.<br />
c) The results may be<br />
incorporated in the<br />
comparative study to adopt<br />
a realistic value <strong>of</strong> design<br />
flood.<br />
1. The sedimentation rate for<br />
the region is about 0.1765<br />
Ham/sqkm/year as per<br />
CWC publication named<br />
Compendium on Silting <strong>of</strong><br />
Reservoirs in India. Hence it<br />
would be prudent to re-look<br />
to the sediment rate figures<br />
to be adopted.<br />
2. An approximate sediment<br />
study may also be carried<br />
out to decide the sill level <strong>of</strong><br />
outlet and live storage<br />
available.<br />
The hydrological studies for<br />
the PFR may be revised<br />
incorporating the above<br />
observations.<br />
5 General The agency taking detailed<br />
investigations/DPR must<br />
review the hydrological and<br />
hydro-meteorological<br />
network and the other<br />
recommendations given in<br />
the report in consultation<br />
with HSO, CWC.<br />
The possibility <strong>of</strong> making<br />
the project multipurpose<br />
may be studied in detail at<br />
DPR stage.<br />
Annexure-5.4<br />
6-7<br />
been used indirectly along with<br />
Empirical method, as the<br />
design flood at Subansiri<br />
Upper dam site had been<br />
computed by deterministic<br />
approach only. The details <strong>of</strong><br />
design flood study may be<br />
referred in feasibility report <strong>of</strong><br />
Subansiri Upper Project,<br />
August 2002.<br />
1. We are aware <strong>of</strong> the findings<br />
<strong>of</strong> CWC studies published<br />
in the Compendium on<br />
silting <strong>of</strong> reservoirs in India.<br />
As per that report, the<br />
sediment rate varies from<br />
0.05658 to 0.2785<br />
Ham/Sq.km /year for Indus,<br />
Ganga and Brahmaputra<br />
basin. But the silt rate<br />
adopted for this particular<br />
project has been adopted<br />
on the basis <strong>of</strong> observed<br />
data at Chouldhowaghat in<br />
Subansiri basin and is<br />
more region specific than<br />
that given in “Compendium<br />
on silting <strong>of</strong> reservoirs in<br />
India”.<br />
2. Detailed reservoir<br />
sedimentation study need<br />
be done during feasibility<br />
stage with more observed<br />
data at the proposed site<br />
using a suitable method.<br />
Agreed, the observation<br />
network and analysis needs to<br />
be done at the time <strong>of</strong> DPR.<br />
208
Annexure-6.1<br />
4-5<br />
Reply to the comments <strong>of</strong> CMDD Division, CWC vide letter<br />
No.7/9/NHPC/2004/HPI/872 dated 21.04.2004<br />
<strong>Nalo</strong> H.E.Project (4 x 90 MW).<br />
Comments Reply<br />
1. The report should indicate Various alternative locations <strong>of</strong> dam axis<br />
alternate locations <strong>of</strong> dam axis as examined during PFR preparation have<br />
examined during the preparation been indicated in para 6.1 <strong>of</strong> PFR. The<br />
<strong>of</strong> PFR to bring out the merits &<br />
demerits <strong>of</strong> each including that<br />
finally adopted in PFR.<br />
same have also been shown in Plate - 6.1.<br />
2. As per clause no. 5.2 <strong>of</strong> IS :<br />
12966 (Part-I)- 1992 inspection<br />
galleries at higher levels above the<br />
foundations gallery may be<br />
provided. Also instrumentation<br />
gallery may be incorporated in the<br />
drawings. As per codal provision<br />
one more foundation gallery<br />
should be provided.<br />
3. It should be mentioned in the<br />
report that the PMF has been<br />
vetted by Hydrology Directorate<br />
(NE) <strong>of</strong> the Central Water<br />
Commission.<br />
4. Justification for assuming non<br />
monsoon diversion discharge as<br />
2600 cumecs should be provided.<br />
5. The down stream slope <strong>of</strong> nonoverflow<br />
section seems to be on<br />
the higher side, which may be<br />
Location and alignment <strong>of</strong> galleries are<br />
finalized during detailed design.<br />
However, as desired galleries have been<br />
indicatively shown in cross section <strong>of</strong><br />
dam (Plate-6.5)<br />
For reply to observations <strong>of</strong> Hydrology<br />
(NE) Dte. <strong>of</strong> CWC regarding PMF,<br />
Annexure - 5.4 may be referred.<br />
No G&D data is available for river<br />
Subansiri at proposed dam site. Based on<br />
the hydrological studies as carried out for<br />
Subansiri Upper HE Project located on<br />
d/s, value <strong>of</strong> diversion flood has been<br />
assumed (Refer para 6.2.1).<br />
Keeping in view high value <strong>of</strong> seismic<br />
coefficient being recommended for<br />
adoption, a flatter d/s slope <strong>of</strong> NOF has
educed considering the stability<br />
criteria. Moreover the down<br />
stream pr<strong>of</strong>ile <strong>of</strong> the overflow<br />
section should be furnished.<br />
6. The TRT outlet <strong>of</strong> Naba HE<br />
project is at EL 770.00 m and the<br />
MWL <strong>of</strong> <strong>Nalo</strong> HE Project has<br />
been proposed at EL 770.00 m.<br />
But at least a difference <strong>of</strong> 5.0 m<br />
may be kept.<br />
7. The overflow section through<br />
low-level orifice, needs to be<br />
revised.<br />
8. In the layout drawing, the position<br />
<strong>of</strong> spillway needs to be shifted<br />
towards right side.<br />
9. The Water head above the crest is<br />
likely to generate a high exit<br />
velocity <strong>of</strong> the bucket end.<br />
However, in case <strong>of</strong> lean<br />
discharge there is a likelihood <strong>of</strong><br />
scour <strong>of</strong> the portion immediately<br />
below the bucket lip. A suitable<br />
provision in the form <strong>of</strong> concrete<br />
apron needs to be worked out.<br />
Annexure-6.1<br />
5-5<br />
been adopted. The same needs to be<br />
reviewed during DPR stage. Further,<br />
downstream pr<strong>of</strong>ile <strong>of</strong> the overflow<br />
section shall be finalized at DPR stage.<br />
It may be clarified that for <strong>Nalo</strong> HE<br />
Project, FRL has already been proposed at<br />
EL 765m i.e. 5m below the TRT outfall <strong>of</strong><br />
Naba HE Project. Further in PFR dam top<br />
elevation has been specified as EL 770m<br />
and not the MWL.<br />
Reasons for CWC observations are not<br />
clear.<br />
Needful done.<br />
Concrete apron is normally provided on<br />
downstream below the bucket lip.<br />
However, such detailing is done only<br />
during detailed design. Needless to<br />
mention that provision <strong>of</strong> d/s concrete<br />
apron stands already made in BOQ.
Annexure-6.2<br />
2-3<br />
Reply to the comments <strong>of</strong> HCD (E&NE) Division, CWC vide letter<br />
No.3/5/2000-HCD (E&NE)/875 dated 08.04.2004<br />
<strong>Nalo</strong> H.E Project (4 x 90 MW)<br />
Comments Reply<br />
1. Documents furnished alongwith<br />
CEA letter No.<br />
7/9/NHPC/03/HPI/160-2 dated<br />
29 th March 04 does not indicate<br />
design discharge and as such it is<br />
not possible to comment on the<br />
sizing <strong>of</strong> different components.<br />
2. Specific comments cannot be<br />
made on the general layout <strong>of</strong> the<br />
scheme due to non-availability <strong>of</strong><br />
the contours u/s <strong>of</strong> the intake and<br />
further d/s <strong>of</strong> the powerhouse.<br />
3. Provision/design <strong>of</strong> desilting<br />
chamber needs to be reviewed with<br />
the more observed data.<br />
4. Sizing, shape, type & location <strong>of</strong><br />
surge shaft needs to be reviewed<br />
with detailed transient studies.<br />
NHPC has submitted complete draft PFR<br />
and the same clearly indicates the design<br />
discharge. It is understood that copy <strong>of</strong><br />
complete draft PFR was forwarded to CWC<br />
by CEA for comments.<br />
Contours <strong>of</strong> area about 600m u/s <strong>of</strong><br />
proposed intake and upto 800m d/s <strong>of</strong><br />
proposed power house stands already<br />
included in the layout plan (Plate - 6.1)<br />
In the absence <strong>of</strong> observed sediment data,<br />
desilting chamber has been proposed in<br />
order to provide adequate provision in cost<br />
estimate. Requirement/provision <strong>of</strong> desilting<br />
chamber needs to be reviewed based on<br />
sedimentation studies at DPR stage.<br />
As already indicated in para 6.3 <strong>of</strong> PFR,<br />
transient analysis/studies needs to be carried<br />
out during DPR stage. Based on transient<br />
studies size, type and location <strong>of</strong> surge shaft<br />
needs to be finalised.
5. Efficacy <strong>of</strong> silt flushing through<br />
low level spillway on the live<br />
storage and also at the power<br />
intake vicinity needs to be<br />
examined.<br />
Annexure-6.2<br />
3-3<br />
It is a standard practice to undertake model<br />
studies to check efficacy <strong>of</strong> spillway for silt<br />
removal from reservoir and from the power<br />
intake vicinity. However, such model<br />
studies are taken up after detailed<br />
topographical and geotechnical<br />
investigations leading to firming up <strong>of</strong><br />
design at DPR stage.
Reply to the comments <strong>of</strong> SP&PA Division, CEA vide letter No.<br />
7/9/NHPC/2004/HP&I/892 dt.22.4.2004.<br />
<strong>Nalo</strong> H.E. Project (4×90 MW)<br />
Comments Reply<br />
A. Technical Aspects:<br />
1. Location:<br />
<strong>Nalo</strong> HE project is one <strong>of</strong> the new<br />
schemes identified by CEA in Subansiri basin.<br />
<strong>Nalo</strong> HEP, a run-<strong>of</strong>-river scheme is proposed<br />
on Subansiri river (a major tributary <strong>of</strong><br />
Brahmaputra river), near <strong>Nalo</strong> village in Upper<br />
Subansiri District <strong>of</strong> Arunachal Pradesh. The<br />
Project is located in upper reaches <strong>of</strong> Subansiri<br />
River around 1.6km upstream <strong>of</strong> confluence <strong>of</strong><br />
Ledi Ishi with Subansiri River. Dam site is<br />
about 10km upstream <strong>of</strong> Nacho and <strong>Power</strong><br />
House is located on right bank <strong>of</strong> the river near<br />
Jiba-Aying village about 5km downstream <strong>of</strong><br />
dam site. The project is located about 120km<br />
upstream <strong>of</strong> Daporijo town.<br />
Three schemes viz. Subansiri lower (2000<br />
MW), Subansiri Middle (1600 MW) and<br />
Subansiri Upper (2000 MW) have been<br />
planned to harness power potential <strong>of</strong> river<br />
Subansiri.<br />
CEA has identified eight additional projects in<br />
the Subansiri basin, which are Oju-I (700<br />
MW), Oju-II (1000 MW), Niare (800 MW),<br />
Naba (1000MW), Kurung-I & Kurung-II (330<br />
MW), Heigo and Duimukh (90 MW). Kurung I<br />
& II projects have been clubbed and named as<br />
Kurung HE Project. Further, Heigo project has<br />
It is a statement.<br />
Annexure-7.2<br />
5-9
een found to be located within submergence<br />
<strong>of</strong> proposed Subansiri Middle Project. As such,<br />
in lieu <strong>of</strong> these two projects (Kurung HEP and<br />
Heigo HEP), two schemes namely <strong>Nalo</strong> (360<br />
MW) & Dengser (552 MW) located in between<br />
<strong>of</strong> Naba HE Project and Subansiri Upper<br />
Project have been identified for preparation <strong>of</strong><br />
PFR.<br />
2. Cost <strong>of</strong> the Project:<br />
The project is estimated to cost Rs. 2903.76<br />
crores including IDC <strong>of</strong> Rs. 310.51cr. at June<br />
2003 price level. The levellised tariff <strong>of</strong> the<br />
project at present day cost works out to be Rs.<br />
2.99 per unit. However, levellised tariff at<br />
present day cost without any free power to<br />
home state works out to be Rs. 2.63 per unit.<br />
3. <strong>Power</strong> house:<br />
<strong>Nalo</strong> power house which would be a surface<br />
power house envisages installation <strong>of</strong> 4 units <strong>of</strong><br />
90 MW each. <strong>Power</strong> is proposed to be<br />
generated at 11 kV and stepped upto 400kV<br />
through 13 nos. (including one spare), 34 MVA<br />
single phase, 11/400 kV step up generator<br />
transformer as given on page 63 and 92 <strong>of</strong> the<br />
PFR. However, in the SLD, generation voltage<br />
Annexure-7.2<br />
6-9<br />
It is a statement. However,<br />
project cost is revised as Rs.<br />
2922.14 Crores including IDC <strong>of</strong><br />
Rs. 312.48 Crores at June 2003<br />
price level due to change in<br />
certain parameters <strong>of</strong> the project.<br />
Revised levellised tariff <strong>of</strong> the<br />
project at present day cost works<br />
out to be Rs. 3.01 per unit.<br />
However, levellised tariff at<br />
present day cost without free<br />
power to home state is Rs. 2.65<br />
per unit.<br />
Generation voltage shown as<br />
13.8 kV in SLD is a<br />
typographical error. Generation<br />
voltage is at 11kV only.<br />
Accordingly, corrected SLD is<br />
enclosed.
has been shown as 13.8 kV. This needs<br />
clarification. The generator transformers will<br />
be further connected to 400kV outdoor<br />
conventional switchyard through overhead<br />
conductor.<br />
4. <strong>Power</strong> evacuation:<br />
In order to evacuate 360 MW <strong>of</strong> power from<br />
<strong>Nalo</strong> HEP, a 400kV D/C transmission line with<br />
Quad Moose conductor, 70 km in length from<br />
<strong>Nalo</strong> HEP to Daporijo pooling point is<br />
proposed as stated on page 8 and 93 <strong>of</strong> the<br />
PFR. This is not correct. Instead <strong>of</strong> Quad<br />
Moose conductor, it is suggested to use Twin<br />
Moose conductor as mentioned in plate 8.2 <strong>of</strong><br />
the PFR. Accordingly, provision <strong>of</strong> 2 Nos.<br />
400 kV outgoing bays has been kept in the<br />
switchyard for 360 MW power evacuation<br />
from this project. This is in order.<br />
5. Daporijo Pooling Point:<br />
It has been shown on plate 8.2 <strong>of</strong> the PFR that<br />
the power from Oju-I (700 MW), Oju-II (1000<br />
MW), Niare (800 MW), Naba (1000 MW),<br />
<strong>Nalo</strong> (360 MW) and Dengser (552 MW) HE<br />
Projects would be pooled at Daporijo pooling<br />
point. Also, the power from Subansiri Upper<br />
HEP – 2000 MW has been planned to be<br />
pooled at Daporijo pooling point, from where<br />
the total power (6412 MW) from 7 projects<br />
would be ultimately transmitted directly<br />
through HVDC link to the National Grid. This<br />
is in order.<br />
Annexure-7.2<br />
7-9<br />
The length <strong>of</strong> 400 kV D/C<br />
transmission line with Twin<br />
Moose Conductor from <strong>Nalo</strong><br />
HEP to Daporijo pooling point is<br />
75 kms. The same has been<br />
corrected as 75 kms instead <strong>of</strong><br />
70kms. Accordingly, the chapter<br />
<strong>of</strong> power evacuation has been<br />
revised.<br />
It is a statement.
6. Switchyard<br />
The switchyard <strong>of</strong> <strong>Nalo</strong> HEP would thus It is a statement.<br />
comprise <strong>of</strong> the following bays as given in<br />
plate 8.1. This is in order.<br />
a) Generator transformer bays - 4 Nos.<br />
b) 400 kV line bays - 2 Nos<br />
c) 400 kV bus coupler - 1 Nos<br />
Works covered at Daporijo pooling point<br />
a) 400 kV line bays at Daporijo pooling point<br />
7. Construction <strong>Power</strong>:<br />
- 2 Nos.<br />
Source <strong>of</strong> construction power for the project<br />
has not been stated in the PFR. This may please<br />
be furnished.<br />
8. Cost <strong>of</strong> transmission works:<br />
It has been stated on page 93 <strong>of</strong> the PFR that<br />
the cost <strong>of</strong> 400kV D/C 70km. long<br />
transmission line from <strong>Nalo</strong> HEP to Daporijo<br />
pooling point and other end equipment at <strong>Nalo</strong><br />
pooling point has been considered. The cost <strong>of</strong><br />
transmission works has been given as Rs 62.31<br />
crores under the abstract <strong>of</strong> cost <strong>of</strong> works on<br />
page 118 and page 143 <strong>of</strong> the PFR. Details <strong>of</strong><br />
transmission works may be furnished. The<br />
length <strong>of</strong> line has been given as 75 km on page<br />
143 <strong>of</strong> PFR.<br />
9. General Comments:<br />
a) It may be stated that the benefits from these<br />
projects may not be fully absorbed from NE<br />
region and needs to be exported to other<br />
Annexure-7.2<br />
8-9<br />
Requirements <strong>of</strong> construction<br />
power for this project would be<br />
met by suitable capacity <strong>of</strong> D.G.<br />
Sets.<br />
Cost for 75 km long transmission<br />
line from <strong>Nalo</strong> HEP to Daporijo<br />
pooling point has been<br />
considered. The details <strong>of</strong> the<br />
cost <strong>of</strong> transmission work will be<br />
provided at FR/DPR stage.<br />
Noted
egions. In long term perspective for<br />
evacuating bulk power from we may need to<br />
adopt a combination <strong>of</strong> HVDC/EHVAC<br />
transmission system which requires least<br />
transmission corridor, because <strong>of</strong> limited<br />
corridor in the chicken –neck area taking into<br />
account the various power projects likely to be<br />
developed in NER in foreseeable future. We<br />
may need to plan an integrated transmission<br />
system from the pooling points in NER and<br />
phase out the implementation schedule<br />
suitably.<br />
b) The transmission system as proposed for above<br />
schemes is tentative. The final transmission<br />
system would be determined by detailed power<br />
system studies on the basis <strong>of</strong> total power to be<br />
transmitted from NER, which may require a<br />
change in the voltage levels or configuration <strong>of</strong><br />
the transmission system taking into<br />
consideration the mountainous terrain, thick<br />
forest area and right <strong>of</strong> way problems.<br />
c) Beneficiaries States / Regions along with their<br />
tentative shares from these projects have not<br />
been identified so far.<br />
B.Cost Aspects:<br />
Comments on cost aspects shall be forwarded<br />
in due course.<br />
Noted<br />
It is a statement.<br />
Annexure-7.2<br />
9-9<br />
Comments on cost aspects have<br />
been received vide letter<br />
No.7/1/2004/SP&PA(C)/239<br />
dated 13.05.2004. Replies are<br />
appended as Annexure 7.3.
Annexure-7.3<br />
3-4<br />
Reply to the comments <strong>of</strong> SP&PA Division on Cost Aspects, CEA vide letter<br />
No. 7/1//2004/SP&PA(C)/239 dated.13.05.2004<br />
<strong>Nalo</strong> H.E. Project (4x90 MW)<br />
Switchyard Cost Estimates:<br />
Comments Reply<br />
1. As per single line diagram power from<br />
<strong>Nalo</strong> HE Project ( 4×90 MW) would be<br />
stepped up to 400 kV and evacuated<br />
over 2 no 400kV lines to Daporijo.<br />
Accordingly, provision for 7 bays has<br />
been made in the switchyard (4GT bays<br />
+2 line bay +1BC)<br />
2. The average basic equipment cost <strong>of</strong><br />
400 kV bay for open switchyard in<br />
double main bus arrangement has been<br />
estimated at the rate <strong>of</strong> Rs. 2.50 crores<br />
per bay. Over and above this ED @<br />
16%, CST @ 4%, Spares @ 2 %,<br />
Transportation & Insurance @ 6%,<br />
Erection and Commissioning @ 8% has<br />
been taken. This is generally in order.<br />
3. Establishment and Contingency has<br />
been taken as 8%. This is in order.<br />
4. Detailed break up <strong>of</strong> switchyard<br />
equipment cost has not been included<br />
in the PFR. It may be noted that<br />
detailed break up <strong>of</strong> cost for switchyard<br />
equipment and works need to be<br />
included at the time <strong>of</strong> preparation <strong>of</strong><br />
feasibility report.<br />
Transmission line Cost:<br />
1. The cost <strong>of</strong> 400kV D/C transmission<br />
line with twin moose conductor has<br />
been taken as Rs. 50 lakhs/Km. Over<br />
and above this cost ED @ 16%, CST @<br />
4%, Transportation and Insurance @<br />
6%, Erection and Commissioning @<br />
8% has been taken. For a hilly terrain<br />
It is a statement.<br />
It is a statement.<br />
It is a statement.<br />
It is a statement. However, the detail breakup<br />
<strong>of</strong> cost for the switchyard equipment<br />
will be provided at the DPR stage.<br />
It is statement. However, the detail break-<br />
up <strong>of</strong> cost for the 400kV transmission line<br />
components will be provided at the DPR<br />
stage.
<strong>of</strong> Arunachal Pradesh these estimates<br />
are on lower side. An estimate <strong>of</strong> Rs.<br />
60 lakh per km for 400kV D/C line<br />
may be taken against Rs. 50 lakh per<br />
km taken in the PFR. Detailed break up<br />
<strong>of</strong> transmission line cost alongwith<br />
details <strong>of</strong> tower, conductor and<br />
insulators etc needs to be included at<br />
the time <strong>of</strong> preparation <strong>of</strong> feasibility<br />
report.<br />
2. The rate for 400 kV D/C line bay at the<br />
terminating station has been taken as<br />
Rs. 2.5 lakhs per bay. Over and above<br />
this ED @ 16% , CST @ 4%, Spares @<br />
2%, Transportation & Insurance @ 6%<br />
Erection and Commissioning @ 8% has<br />
been taken. This is generally in order.<br />
However, detailed breakup <strong>of</strong> cost<br />
needs to be included at the time <strong>of</strong><br />
preparation <strong>of</strong> feasibility report.<br />
Annexure-7.3<br />
4-4<br />
It is a statement. However, the detail breakup<br />
<strong>of</strong> cost for 400kV line layout at<br />
terminating station will be provided at the<br />
DPR stage.
Annexure-9.1<br />
Final Report<br />
Satellite Remote Sensing Based Inputs for Initial<br />
Environmental Study in respect <strong>of</strong> 10 Proposed Hydro-<strong>Power</strong><br />
Sites in Subansiri Basin in Arunachal Pradesh<br />
Name <strong>of</strong> the Hydro-<strong>Power</strong> Site : NALO<br />
Prepared for<br />
National Hydroelectric <strong>Power</strong> Corporation Ltd.<br />
Subansiri Basin Projects<br />
Hapoli (Ziro)<br />
Arunachal Pradesh – 791 120<br />
Water Resource Division<br />
Water Resource & Oceanography Group<br />
Remote Sensing & GIS Applications Area<br />
National Remote Sensing Agency<br />
Dept. <strong>of</strong> Space, Govt. <strong>of</strong> India<br />
Balanagar, Hyderabad- 500037<br />
April, 2004
1. Study Background<br />
2. Objective<br />
CONTENTS<br />
3. Salient Features <strong>of</strong> the <strong>Nalo</strong> Hydro-<strong>Power</strong> Site<br />
4. Satellite data Used<br />
5. Brief Methodology <strong>of</strong> Satellite Data Analysis<br />
6. Outputs provided<br />
7. Critical Analysis <strong>of</strong> Satellite based Initial Environmental Study<br />
8. Conclusion & Recommendation<br />
List <strong>of</strong> Maps<br />
1.a. IRS 1C PAN + LISS III merged satellite image <strong>of</strong> 26th December<br />
2002<br />
1.b. Satellite derived landuse-land cover map <strong>of</strong> surroundings <strong>of</strong><br />
proposed hydro power site at <strong>Nalo</strong>, Arunachal Pradesh<br />
1.c. Landuse-Landcover map <strong>of</strong> immediate surroundings upstream<br />
<strong>of</strong> proposed Dam site at <strong>Nalo</strong>.<br />
1.d. Map <strong>of</strong> National Parks/ Sanctuaries and the location <strong>of</strong> <strong>Nalo</strong><br />
hydro power site and 7 Km radius circle from the dam site<br />
List <strong>of</strong> Tables<br />
Table 1. Land use – land cover Information within the Submergence<br />
Area<br />
Table 2. Landuse-landcover Information within the 7 Km radius from<br />
the dam site at <strong>Nalo</strong><br />
234
Satellite Remote Sensing Based Inputs for Initial environmental study in respect <strong>of</strong> 8 Proposed Hydro-<strong>Power</strong> Sites in Arunachal Pradesh –<br />
<strong>Nalo</strong> Hydro-power Site<br />
--------------------------------------------------------------------------------------------------------------------------------------------------------------------<br />
1. Study Background<br />
Annexure-9.1<br />
Central Electricity Authority (CEA) under <strong>Ministry</strong> <strong>of</strong> <strong>Power</strong>, Govt. <strong>of</strong> India<br />
has earlier identified 399 potential hydroelectric sites in the country with an<br />
installed capacity <strong>of</strong> 1,07,000 Megawatt (MW). With a view to preparing an<br />
action plan to develop this hydroelectric potential and prioritizing the<br />
implementation <strong>of</strong> hydro-electric projects, a Ranking Study was taken up by the<br />
CEA in 2001. This Ranking Study identified 162 most potential sites with a total<br />
installed capacity <strong>of</strong> 50,560 MW for development.<br />
Preparation <strong>of</strong> Pre-Feasibility Reports (PFR) <strong>of</strong> these 162 sites has been<br />
initiated by the CEA in 2002 with works entrusted to a number <strong>of</strong> Consultants,<br />
namely, National Hydroelectric <strong>Power</strong> Corporation (NHPC), North Eastern<br />
Electric <strong>Power</strong> Corporation (NEEPCO), Water And <strong>Power</strong> Consultancy Services<br />
India Limited (WAPCOS), Satluj Jal Vidut Nigam Limited ( SVJNL) , Himachal<br />
Pradesh State Electricity Board ( HPSEB), Uttaranchal Jal Vidut Nigam Limited (<br />
UJVNL) and Kerala <strong>Power</strong> Corporation Limited ( KPCL) with time target <strong>of</strong><br />
completion <strong>of</strong> the whole exercise by September 2003. To oversee the progress<br />
<strong>of</strong> the PFRs preparation in time and with full cooperation <strong>of</strong> the Central<br />
Government agencies, a Central Coordination Committee consisting <strong>of</strong> Central<br />
Electricity Authority (CEA), Central Water Commission (CWC), India<br />
Meteorological Department (IMD), <strong>Ministry</strong> <strong>of</strong> Environment & Forest, Survey <strong>of</strong><br />
India, Geological Survey <strong>of</strong> India (GSI) and National Remote Sensing Agency<br />
(NRSA) was constituted by the CEA with Member (Hydro-power) as its<br />
Chairman. The Committee is sitting periodically in presence <strong>of</strong> the<br />
representatives <strong>of</strong> the Consultants to take stock <strong>of</strong> the completion <strong>of</strong> the studies.<br />
One <strong>of</strong> the mandates <strong>of</strong> PFR preparation is “Initial Environmental Study” with<br />
respect to each <strong>of</strong> the 162 proposed sites using satellite remote sensing data.<br />
------------------------------------------------------------------------------------------------------------------<br />
Prepared for National Hydroelectric <strong>Power</strong> Corporation Ltd , Regional Office at Hapoli (Ziro)<br />
by National Remote Sensing Agency (NRSA), Dept <strong>of</strong> Space, Govt. <strong>of</strong> India, Hyderabad<br />
235
Annexure-9.1<br />
Satellite Remote Sensing Based Inputs for Initial environmental study in respect <strong>of</strong> 8 Proposed Hydro-<strong>Power</strong> Sites in Arunachal Pradesh –<br />
<strong>Nalo</strong> Hydro-power Site<br />
--------------------------------------------------------------------------------------------------------------------------------------------------------------------<br />
As is well known in India and elsewhere in the world, space technology<br />
plays a very important role in terrain mapping and scientific assessment <strong>of</strong> the<br />
ground condition at speed, and is ideally suitable for inaccessible mountainous<br />
regions where majority <strong>of</strong> these hydroelectric dam/diversion sites are located.<br />
Computer processing <strong>of</strong> satellite digital data <strong>of</strong> the dam / diversion sites and their<br />
immediate environ provides wealth <strong>of</strong> information for preparation <strong>of</strong> the Pre-<br />
Feasibility Reports. The Potential <strong>of</strong> this technology was amply demonstrated in<br />
the preliminary ranking study <strong>of</strong> the 81 proposed hydro-electric sites in Indus<br />
Basin completed by NRSA in October 2001 on behalf <strong>of</strong> CEA. In view <strong>of</strong> this,<br />
NRSA has been approached by a number <strong>of</strong> consultants, namely, NHPC and<br />
HPSEB to take up Initial Environmental Studies in respect <strong>of</strong> 42 proposed hydro-<br />
power sites located in the States <strong>of</strong> Arunachal Pradesh, Himachal Pradesh,<br />
Jammu & Kashmir and Madhya Pradesh using most recent satellite remote<br />
sensing data.<br />
Regional Office <strong>of</strong> NHPC, Subansiri projects at Hapoli ( Ziro) with<br />
responsibility <strong>of</strong> survey and investigation in Subansiri river basin in Arunachal<br />
Pradesh, has approached NRSA for satellite remote sensing based inputs for<br />
initial environmental study <strong>of</strong> 10 hydro-power sites located in Subansiri Basin.<br />
This Report deals with <strong>Nalo</strong> hydro-power site.<br />
2. Objective<br />
Principal objective <strong>of</strong> the satellite based study is to acquire Indian Remote<br />
Sensing satellites (IRS 1C/1D) LISS-III and PAN sensor digital data <strong>of</strong> the hydro-<br />
power sites and to make quick analysis <strong>of</strong> these data in terms <strong>of</strong> estimation <strong>of</strong> the<br />
submergence area at proposed Full Reservoir Level (FRL) and mapping <strong>of</strong> land<br />
------------------------------------------------------------------------------------------------------------------<br />
Prepared for National Hydroelectric <strong>Power</strong> Corporation Ltd , Regional Office at Hapoli (Ziro)<br />
by National Remote Sensing Agency (NRSA), Dept <strong>of</strong> Space, Govt. <strong>of</strong> India, Hyderabad<br />
236
Annexure-9.1<br />
Satellite Remote Sensing Based Inputs for Initial environmental study in respect <strong>of</strong> 8 Proposed Hydro-<strong>Power</strong> Sites in Arunachal Pradesh –<br />
<strong>Nalo</strong> Hydro-power Site<br />
--------------------------------------------------------------------------------------------------------------------------------------------------------------------<br />
use - land cover information within and in immediate surrounding <strong>of</strong> the proposed<br />
submergence area as inputs for Initial Environmental Study (IES) <strong>of</strong> the Pre-<br />
Feasibility Report.<br />
The specific objectives and scope <strong>of</strong> the study are:<br />
• To estimate the area <strong>of</strong> submergence at proposed FRL <strong>of</strong> the proposed<br />
hydro-power sites<br />
• To analyse the satellite data for identifying broad landuse – land cover<br />
categories like agricultural land, forest land, barren land, scrub land, water<br />
bodies, settlements, infrastructural features (roads and bridges) and to<br />
estimate the area under each <strong>of</strong> the categories within and in immediate<br />
surrounding <strong>of</strong> the proposed submergence area at FRL.<br />
• To prepare land use - land cover map at 1:50,000 scale and/or 1:25,000 scale<br />
<strong>of</strong> the submergence area and its immediate surrounding for each hydro-<br />
power site.<br />
3. Salient Features <strong>of</strong> the <strong>Nalo</strong> Hydro-<strong>Power</strong> Site<br />
Proposed hydro-power site is located at <strong>Nalo</strong> in Subansiri Basin in<br />
Arunachal Pradesh falling in Survey <strong>of</strong> India topo sheet No.82 H/15. The proposed<br />
project scheme at <strong>Nalo</strong> envisages construction <strong>of</strong> a Dam on on Subansiri river,<br />
and a power house with a installed capacity <strong>of</strong> 360MW. FRL is proposed to be 765<br />
metre above MSL. The Head-Race Tunnel from the dam to the power house is<br />
proposed to be 3.75 km in length. The river water will be stored in the reservoir<br />
which will be diverted through the Head-Race Tunnel to the <strong>Power</strong> House for<br />
------------------------------------------------------------------------------------------------------------------<br />
Prepared for National Hydroelectric <strong>Power</strong> Corporation Ltd , Regional Office at Hapoli (Ziro)<br />
by National Remote Sensing Agency (NRSA), Dept <strong>of</strong> Space, Govt. <strong>of</strong> India, Hyderabad<br />
237
Annexure-9.1<br />
Satellite Remote Sensing Based Inputs for Initial environmental study in respect <strong>of</strong> 8 Proposed Hydro-<strong>Power</strong> Sites in Arunachal Pradesh –<br />
<strong>Nalo</strong> Hydro-power Site<br />
--------------------------------------------------------------------------------------------------------------------------------------------------------------------<br />
hydro-power generation and subsequent power evacuation to areas in Arunachal<br />
Pradesh and other areas<br />
The geographic location <strong>of</strong> Dam and <strong>Power</strong> House for this hydro-power site is<br />
given below :<br />
Dam <strong>Power</strong> House<br />
Latitude : 28° 24’ 26.68” N 28° 24’ 29.63” N<br />
Longitude: 93° 46’ 53.71” E 93° 48’ 42.98” E<br />
4. Satellite data Used<br />
Indian Remote Sensing Satellite, IRS-IC LISS III and PAN sensors data <strong>of</strong><br />
26 th December, 2002 covering the study site were procured from the NRSA Data<br />
Centre (NDC) after intensive browsing <strong>of</strong> the available satellite data for cloud-free<br />
and radiometric suitability. IRS-1C covers the study site by satellite geo-<br />
reference number Path 112 and Row 51. These data are geometrically and<br />
radiometrically corrected digital data products which can be used readily in<br />
Window based image analysis platform.<br />
5. Brief Methodology <strong>of</strong> Satellite Data Analysis<br />
Image processing and analysis was done using ERDAS Imagine image<br />
analysis s<strong>of</strong>tware in Windows platform. Satellite data <strong>of</strong> IRS 1C LISS III sensor<br />
provides 23.5 m spatial resolution and PAN sensor provides 5.8m spatial<br />
resolution. The two sensor data were geocoded and digitally merged using IHS<br />
transformation technique . Baseline information layers (like rivers/ streams) and<br />
infrastructural features (like roads and bridges), settlements / villages were<br />
initially interpreted on the digital image scene. Subsequently, image<br />
------------------------------------------------------------------------------------------------------------------<br />
Prepared for National Hydroelectric <strong>Power</strong> Corporation Ltd , Regional Office at Hapoli (Ziro)<br />
by National Remote Sensing Agency (NRSA), Dept <strong>of</strong> Space, Govt. <strong>of</strong> India, Hyderabad<br />
238
Annexure-9.1<br />
Satellite Remote Sensing Based Inputs for Initial environmental study in respect <strong>of</strong> 8 Proposed Hydro-<strong>Power</strong> Sites in Arunachal Pradesh –<br />
<strong>Nalo</strong> Hydro-power Site<br />
--------------------------------------------------------------------------------------------------------------------------------------------------------------------<br />
classification technique was performed to obtain the land use-land cover<br />
categories <strong>of</strong> the study area.<br />
Output maps were composed in the image processing system which<br />
provide the landuse / land cover information along with other interpreted<br />
information such as roads, settlements etc., within the 7 Km radius from the dam<br />
site. The Full Reservoir Level (FRL) boundary, provided by the NHPC, Regional<br />
Office at Hapoli, was superimposed on the satellite data as well as on the land<br />
use - land cover map. Area statistics <strong>of</strong> different landuse-landcover categories<br />
were generated within the submergence area at FRL and within the 7 km radius<br />
circle from the dam site.<br />
6. Outputs provided<br />
Based on the analysis <strong>of</strong> satellite data and other available ancillary<br />
information, the following outputs were generated :<br />
• Map 1 (a) Shows IRS 1 C PAN + LISS III merged satellite image <strong>of</strong> 26 th<br />
December, 2002on 1:50,000 scale covering 7 km radius from<br />
the dam site overlaid with FRL , location <strong>of</strong> dam site and<br />
power house.<br />
• Map 1(b) Shows satellite derived landuse-landcover map on 1:50,000<br />
scale covering 7 km radius from the dam site overlaid with<br />
FRL , location <strong>of</strong> dam site and power house. Land use /land<br />
cover map shows the following categories : Forest (High and<br />
Medium Dense Forest), Agricultural Land, Open Scrub,<br />
Barren and Rock Outcrop, Snow, River Course/ Dry River<br />
Bed.<br />
------------------------------------------------------------------------------------------------------------------<br />
Prepared for National Hydroelectric <strong>Power</strong> Corporation Ltd , Regional Office at Hapoli (Ziro)<br />
by National Remote Sensing Agency (NRSA), Dept <strong>of</strong> Space, Govt. <strong>of</strong> India, Hyderabad<br />
239
Annexure-9.1<br />
Satellite Remote Sensing Based Inputs for Initial environmental study in respect <strong>of</strong> 8 Proposed Hydro-<strong>Power</strong> Sites in Arunachal Pradesh –<br />
<strong>Nalo</strong> Hydro-power Site<br />
--------------------------------------------------------------------------------------------------------------------------------------------------------------------<br />
• Map 1(c) Shows the landuse- landcover classes and their corresponding<br />
area statistics in hectares within the submergence area on<br />
1:25000 scale overlaid with FRL , location <strong>of</strong> dam site and<br />
power house.<br />
• Map 1 (d) Shows the location <strong>of</strong> the National parks / Wildlife Sanctuaries<br />
vis-à-vis the location <strong>of</strong> the dam/ <strong>Power</strong> House and 7 km<br />
radius area around the dam site.<br />
• Table.1 Landuse-landcover Information within the Submergence Area<br />
S.No Landuse-landcover<br />
Category<br />
Area under<br />
submergence (Ha)<br />
% <strong>of</strong> the total<br />
submergence area<br />
1 High Dense Forest 118.36 41.71<br />
2. Medium Dense Forest 27.49 9.69<br />
3. Low Dense Forest Nil Nil<br />
4. Open Scrub 56.78 20.01<br />
5. Barren / Rock Outcrop 4.10 1.44<br />
6. Snow Nil Nil<br />
7. Agricultural Land 1.14 0.40<br />
8. Human Settlement 0.49 0.17<br />
9. River Course including<br />
dry river bed<br />
75.44 26.58<br />
Total 283.80 100.00<br />
------------------------------------------------------------------------------------------------------------------<br />
Prepared for National Hydroelectric <strong>Power</strong> Corporation Ltd , Regional Office at Hapoli (Ziro)<br />
by National Remote Sensing Agency (NRSA), Dept <strong>of</strong> Space, Govt. <strong>of</strong> India, Hyderabad<br />
240
Annexure-9.1<br />
Satellite Remote Sensing Based Inputs for Initial environmental study in respect <strong>of</strong> 8 Proposed Hydro-<strong>Power</strong> Sites in Arunachal Pradesh –<br />
<strong>Nalo</strong> Hydro-power Site<br />
--------------------------------------------------------------------------------------------------------------------------------------------------------------------<br />
• Table.2 Landuse-landcover Information within the 7 Km Radius from<br />
the Dam site at <strong>Nalo</strong><br />
S.No Landuse-landcover<br />
Category<br />
Total Area ( ha)<br />
% <strong>of</strong> the total<br />
area<br />
1 High Dense Forest 12523.73 81.35<br />
2. Medium Dense Forest 1585.85 10.30<br />
3. Low Dense Forest Nil Nil<br />
4. Open Scrub 980.42 6.37<br />
5. Barren / Rock Outcrop 80.17 0.52<br />
6. Snow 7.24 0.05<br />
7. Agricultural Land 33.39 0.22<br />
8. Human Settlement 13.46 0.09<br />
9. River Course including<br />
dry river bed<br />
169.74<br />
------------------------------------------------------------------------------------------------------------------<br />
Prepared for National Hydroelectric <strong>Power</strong> Corporation Ltd , Regional Office at Hapoli (Ziro)<br />
by National Remote Sensing Agency (NRSA), Dept <strong>of</strong> Space, Govt. <strong>of</strong> India, Hyderabad<br />
1.10<br />
Total area 15394.00 100.00<br />
7. Critical Analysis <strong>of</strong> Satellite based Initial Environmental Study<br />
• Total area under submergence at proposed FRL <strong>of</strong> 765 m. (above MSL) is<br />
estimated to be 283.80 ha ( Table.1).<br />
• It is observed that vegetation cover is mostly dominated by forest category<br />
which is 146 ha ( 51% <strong>of</strong> the submergence area ). Entire forest vegetation is<br />
classified as high and medium dense forest in the submergence area.<br />
241
Annexure-9.1<br />
Satellite Remote Sensing Based Inputs for Initial environmental study in respect <strong>of</strong> 8 Proposed Hydro-<strong>Power</strong> Sites in Arunachal Pradesh –<br />
<strong>Nalo</strong> Hydro-power Site<br />
--------------------------------------------------------------------------------------------------------------------------------------------------------------------<br />
• Submergence <strong>of</strong> forest vegetation ( High dense and Medium dense) may be<br />
<strong>of</strong> some immediate concern which needs to be rehabilitated with alternate<br />
afforestation measures within the vicinity <strong>of</strong> the dam site when the project<br />
scheme is taken up for implementation.<br />
• There is very little 1.14 ha. Of (Insignificant) agricultural area present within<br />
the proposed submergence area which is positive sign to develop the<br />
proposed hydropower site.<br />
• Open scrub land is the next dominant land use – land cover category after the<br />
forest and constitutes 20% <strong>of</strong> the submergence area. This is followed by<br />
Barren / Rock outcrop land which is 1.44%.<br />
• There are no surface water bodies other than the river course. The area under<br />
river course including dry river bed is estimated to be 75.44 ha., which<br />
constitutes 27% <strong>of</strong> the total submergence area.<br />
• It is also observed that the submergence area at EL + 765 m. above MSL<br />
(FRL) is likely to affect (Inundate) few isolated settlements. Hence, a close<br />
look at the ground is required to assess the exact impact.<br />
• In the absence <strong>of</strong> available information from other sources about the<br />
existence and spatial extent <strong>of</strong> national parks and wildlife sanctuaries, best<br />
efforts were made to collect information from the Internet. The information<br />
available in website <strong>of</strong> United Nations Environment programme World<br />
Conservation Monitoring Center (http://www.unep-wcmc.org), National<br />
Informatics Centre, www.wildarunachal.org and www.arunachalbhawan.com<br />
regarding Arunachal Pradesh State and its National Parks / Wild<br />
Sanctuaries, were browsed through. The information at hand is made use in<br />
242<br />
------------------------------------------------------------------------------------------------------------------<br />
Prepared for National Hydroelectric <strong>Power</strong> Corporation Ltd , Regional Office at Hapoli (Ziro)<br />
by National Remote Sensing Agency (NRSA), Dept <strong>of</strong> Space, Govt. <strong>of</strong> India, Hyderabad
Annexure-9.1<br />
Satellite Remote Sensing Based Inputs for Initial environmental study in respect <strong>of</strong> 8 Proposed Hydro-<strong>Power</strong> Sites in Arunachal Pradesh –<br />
<strong>Nalo</strong> Hydro-power Site<br />
--------------------------------------------------------------------------------------------------------------------------------------------------------------------<br />
preparing map 1(d) which depicts the latitude and longitude <strong>of</strong> dam site and<br />
the sanctuaries/national parks. 7 km radius circle around the dam is plotted<br />
and the radial distance to the various national park/ sanctuary were estimated<br />
around the nearest national park/ sanctuary which are <strong>of</strong> significant only are<br />
measured on the map 1(d). The following points are observed from the map<br />
1(d).<br />
- The nearest National park is Mouling which is about 93 Km from the dam<br />
site. The nearest sanctuaries are Kane, Itanagar, Pakhui and D’Ering<br />
memorial which are about at distance <strong>of</strong> 115 Km, 145 km, 156 km and<br />
169 Km . So it is observed that the dam site is more than 93 Km away from<br />
the National park and sanctuaries. Hence, proposed development <strong>of</strong> the<br />
site is least likely to have impact on them.<br />
- Since 7 Km radius around the dam site was considered as the area <strong>of</strong><br />
study, efforts were made to check whether the geo-coordinates <strong>of</strong> this<br />
Wildlife Sanctuary is falling within the area <strong>of</strong> study. The map No. 1(d)<br />
explains the location <strong>of</strong> the sanctuary vis-à-vis the dam site and the power<br />
house.<br />
8. Conclusion & Recommendation<br />
1. Satellite based study has provided insight into the landuse-landcover<br />
pattern and their spatial extent within the submergence area at FRL and<br />
within the 7 Km radius vicinity <strong>of</strong> the proposed dam site. Such detail<br />
information on a scale <strong>of</strong> 1:25,000 are not available from any other sources<br />
at present.<br />
------------------------------------------------------------------------------------------------------------------<br />
Prepared for National Hydroelectric <strong>Power</strong> Corporation Ltd , Regional Office at Hapoli (Ziro)<br />
by National Remote Sensing Agency (NRSA), Dept <strong>of</strong> Space, Govt. <strong>of</strong> India, Hyderabad<br />
243
Annexure-9.1<br />
Satellite Remote Sensing Based Inputs for Initial environmental study in respect <strong>of</strong> 8 Proposed Hydro-<strong>Power</strong> Sites in Arunachal Pradesh –<br />
<strong>Nalo</strong> Hydro-power Site<br />
--------------------------------------------------------------------------------------------------------------------------------------------------------------------<br />
2. There is practically no agricultural land ( 1.14 ha., very insignificant) within<br />
the submergence area. The environmental cost on this score is therefore<br />
nil.<br />
3. Few isolated settlements are likely to be affected by the submergence area<br />
at the proposed FRL. This has to be verified on the ground for detailed<br />
information.<br />
4. The proposed dam site and the power house locale is endowed with rich<br />
forest vegetation. However, since the submergence area at FRL is<br />
confined within the river gorge, forest vegetation <strong>of</strong> the spatial extent <strong>of</strong><br />
146 hectares will be affected due to submergence. Species types <strong>of</strong><br />
these forest vegetation need to be identified from local Forest Department<br />
and by field visit to the area. These forest vegetation needs to be<br />
rehabilitated with alternate afforestation measures. Within the vicinity <strong>of</strong><br />
the hydro-electric project. Alternate lands in the form <strong>of</strong> open scrub<br />
(980 ha) is available within the 7 Km radius <strong>of</strong> the dam site for<br />
rehabilitation <strong>of</strong> this forest vegetation loss in the submergence area.<br />
5. Mouling Natinal park is at a radial distance <strong>of</strong> 93 Km from the proposed<br />
dam site, and Kane, Itanagar, Pakhui and D’Ering memorial Sancturies<br />
are at a distance <strong>of</strong> 115 km, 145 km, 156 km and 169 km respectively<br />
away from the dam site according to the information collected from several<br />
websites. The location and wildlife <strong>of</strong> this sanctuary will in no way be<br />
affected by the hydro-electric project, since the fetch distance <strong>of</strong> the<br />
reservoir submergence will be around 10 Km .<br />
------------------------------------------------------------------------------------------------------------------<br />
Prepared for National Hydroelectric <strong>Power</strong> Corporation Ltd , Regional Office at Hapoli (Ziro)<br />
by National Remote Sensing Agency (NRSA), Dept <strong>of</strong> Space, Govt. <strong>of</strong> India, Hyderabad<br />
244