Panan - Ministry of Power
Panan - Ministry of Power
Panan - Ministry of Power
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
CHAPTER<br />
I<br />
TABLE OF CONTENTS<br />
DESCRIPTION<br />
Executive Summary<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE project (4 x 50 MW)<br />
PAGE NO.<br />
1-9<br />
II Background Information 10-17<br />
III Project Area 18-25<br />
IV Topographical & Geo-technical Aspects 26-32<br />
V Hydrology 33-52<br />
VI Conceptual Layout and Planning 53-63<br />
VII <strong>Power</strong> Potential Studies 64-94<br />
VIII <strong>Power</strong> Evacuation 95<br />
IX Environmental Aspects 96-119<br />
X Infrastructure 120-123<br />
XI Construction Planning & Schedule 124-130<br />
XII Cost Estimate 131-166<br />
XIII Economic Evaluation 167-174<br />
Plates<br />
Annexures
TITLE<br />
LIST OF DRAWINGS<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE project (4 x 50 MW)<br />
PLATE<br />
No.<br />
Preliminary Ranking Study Layout 1<br />
Cascade Development <strong>of</strong> Teesta River Basin 2<br />
Cascade Development <strong>of</strong> Tolung River Basin 3<br />
Geological Plan <strong>of</strong> the Project Area 4.1<br />
Vicinity Map<br />
6.1<br />
Layout Plan 6.2<br />
Layout Plan-Dam Area 6.3<br />
Layout Plan-<strong>Power</strong> House Area 6.4<br />
Water Conductor System L-Section 6.5<br />
Dam Upstream Elevation 6.6<br />
Dam Spillway & Non-Overflow Cross Section 6.7<br />
Typical Cross Section Of Constituents Of Water<br />
Conductor System & Diversion Tunnel<br />
6.8<br />
Single Line Diagram-<strong>Power</strong> Evacution 8.1
TITLE<br />
ANNEXURES<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE project (4 x 50 MW)<br />
No.<br />
Geology <strong>of</strong> the Area Around the Project- By G SI 4.1<br />
Technical Report on Seismic History and<br />
Seismicity- By IMD<br />
4.2<br />
Preliminary Ranking Study Report- By CEA 6.1<br />
Summary Record <strong>of</strong> the Discussion with CEA on<br />
Conceptual Layout<br />
Records <strong>of</strong> Discussions, CEA/CWC Comments<br />
and Replies<br />
6.2<br />
6.3
TITLE<br />
ANNEXURES 6.3<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE project (4 x 50 MW)<br />
No.<br />
Record Discussions on <strong>Power</strong> Potential Study 3-5<br />
Reply on CWC’s Comments on Hydrology 6-10<br />
Reply on General Comments <strong>of</strong> CEA 11-13<br />
Reply on comments on CMDD(E&NE), CWC 14-15<br />
Reply on Comments <strong>of</strong> SP&PA Division CEA 16-17
CHAPTER-I<br />
EXECUTIVE SUMMARY<br />
1<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
1.0 INTRODUCTION<br />
The <strong>Panan</strong> Hydroelectric Project located in North Sikkim district <strong>of</strong> Sikkim envisages<br />
utilization <strong>of</strong> the waters <strong>of</strong> the river Rangyong a tributary <strong>of</strong> river Teesta for power<br />
generation on a run <strong>of</strong> river type development, harnessing a head <strong>of</strong> about 322m.<br />
The project with a proposed installation <strong>of</strong> 200MW (4 x 50MW) would afford an annual<br />
energy generation <strong>of</strong> 762GWh in a 90% dependable year. The tariff from the project at<br />
present day cost would be Rs 1.99 per KWh(levellised).<br />
The diversion site is located at Latitude 27º33’ North, Longitude 88º27’ East. The dam<br />
site is approachable from Mangan-Lingza road. The dam site is at a distance <strong>of</strong> 1km from<br />
Lingza and 17km from Mangan, the head quarter <strong>of</strong> North Sikkim district. The nearest<br />
railhead is at New Jalpaiguri and airport at Bagdogra<br />
1.1 GENERAL PROJECT FEATURES<br />
The <strong>Panan</strong> HE Project envisages construction <strong>of</strong> :<br />
• a 50 m high concrete Dam across river Rangyong to provide a live storage <strong>of</strong><br />
1.69mcum. with FRL at 1095m and MDDL at 1085m;<br />
• two intakes and two desilting chambers <strong>of</strong> size 225m(L) x 15m(W) x 20m(H) to<br />
remove silt particles <strong>of</strong> size 0.2mm and above;<br />
• a 8.5km long , 6m diameter head race tunnel terminating in a surge shaft;<br />
• a 75m high, 15m dia surge shaft;<br />
• 425m long, 3m dia two pressure shaft;<br />
• an underground power house having an installation <strong>of</strong> 4 Francis turbine<br />
generating units <strong>of</strong> 50 MW each operating under a net head <strong>of</strong> 312m; and
2<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
• 500m long, 6m diameter tailrace tunnel to carry the power house release back to<br />
the river;<br />
The power generated from the project would be evacuated through 220KV double circuit<br />
lines to be connected at the pooling point near Teesta (III) HE project to feed power to<br />
National Grid.<br />
The salient features <strong>of</strong> the projects are as under:<br />
SALIENT FEATURES<br />
LOCATION<br />
State Sikkim<br />
District North Sikkim<br />
River Tolung Chu/ Rangyong<br />
Location <strong>of</strong> Dam Site Approx. 1.0km U/S <strong>of</strong> village Lingza<br />
Location <strong>of</strong> <strong>Power</strong> House Approx. 100m U/S <strong>of</strong> confluence <strong>of</strong> Tolung<br />
Chu and Rahi Chu<br />
Nearest Rail head New Jalpaiguri<br />
Nearest Airport Bagdogra<br />
Dam 88º27’00’’Longitude<br />
27º33’00’’ Latitude<br />
<strong>Power</strong> House 88º32’00’’ Longitude 27º31’00’’ Latitude<br />
HYDROLOGY<br />
Catchment area 592 km 2<br />
Design Flood (PMF) 2200 m 3 /sec
DIVERSION TUNNEL<br />
Diameter & Shape 8.5 m, Horse-shoe shaped<br />
Length 600 m<br />
Diversion Discharge ±400 m 3 /sec<br />
Diversion Tunnel Gate 2Nos, 3 m X 6.5 m<br />
COFFER DAMS<br />
Type Rockfill with Central clay core<br />
Maximum height <strong>of</strong> upstream c<strong>of</strong>fer 20.0 m<br />
dam<br />
Maximum height <strong>of</strong> downstream<br />
c<strong>of</strong>fer dam<br />
3<br />
10.0 m<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
DAM<br />
Type Concrete Gravity with central spillway<br />
Dam Top EL. 1100 m<br />
River bed level at dam site EL.1050 m<br />
Maximum Dam height (above deepest<br />
foundation level)<br />
55 m<br />
Length <strong>of</strong> the Dam 100 m<br />
Dam height (above River bed level) 50 m<br />
Max. Dam Height ( above deepest<br />
foundation level)<br />
55m<br />
SPILLWAY<br />
Design flood (PMF) 2200 m 3 /sec<br />
Type Low level orifice Type<br />
Crest level <strong>of</strong> spillway EL1065 m<br />
Number & Size <strong>of</strong> the opening 4 Nos. 5m(W)X 8m(H)
RESERVOIR<br />
Full Reservoir Level (FRL) EL.1095 m<br />
Minimum draw down level (MDDL) EL1085 m<br />
Area under submergence at FRL 15.6 Ha<br />
Gross Storage 3.52 MCM<br />
Live Storage 1.69 MCM<br />
INTAKE<br />
Invert level EL.1075 m<br />
Number <strong>of</strong> Intakes Two<br />
Size <strong>of</strong> each Gate 4.5 m × 4.5 m<br />
Total Design discharge 72.60 m 3 /sec<br />
Stop logs 1Set <strong>of</strong> Stop log (4.5 m wide)<br />
Trash Rack Steel trash rack with m/c<br />
4<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
DESILTING ARRANGEMENT<br />
Type & Numbers Dufour type, 2 Nos.<br />
Length 225 m.<br />
Design Discharge 44 m 3 /sec each ( including 20% flushing<br />
discharge)<br />
Particle size to be removed ≥ 0.2 mm (90% efficiency)<br />
Size 15m(W) x 20m(H)<br />
SILT FLUSHING TUNNEL<br />
Size & Shape 2m x 3 m
HEADRACE TUNNEL<br />
Size & Shape 6.0 m dia, Horse shoe<br />
Length 8.5 km<br />
Adits 3 No., 6 m dia D-shaped<br />
SURGE SHAFT<br />
Size 15 m dia.<br />
Height 75 m<br />
PRESSURE SHAFT<br />
Number Two<br />
Type Circular, steel lined<br />
Diameter<br />
3 m<br />
Height (including horizontal portion) 425 m<br />
POWER HOUSE COMPLEX<br />
Type and location Under ground, right bank<br />
Tail water level at outlet EL 770 m<br />
Centre line <strong>of</strong> M/C +763 m<br />
Type <strong>of</strong> Turbine Vertical Francis<br />
Gross head 322m<br />
Rated Net head 312 m<br />
Design Discharge 72.6 m 3 /sec<br />
<strong>Power</strong> House Size 120m X 22m X 45m<br />
TAILRACE TUNNEL<br />
Size & Type 6.0m dia, Horse-shoe<br />
Length 500m<br />
5<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)
POWER GENERATION<br />
Installed capacity 200 MW ( 4 x 50MW)<br />
Annual Energy generation in a 90% 762MU<br />
dependable<br />
COST ESTIMATES & FIANANCIAL ASPECTS ( Rs. Crores)<br />
Civil Works 554.10<br />
Electro Mechanical Works 209.17<br />
Sub Total (Generation) 763.27<br />
Transmission Works 1.67<br />
Total (Hard Cost) 764.94 at June,2003 Price Level<br />
Interest During Construction 81.14<br />
Grand Total 846.08<br />
Tariff for first year per KWh<br />
a. with 12% free power<br />
b. without 12% free power<br />
Levellised Tariff per KWh<br />
a. with 12% free power<br />
b. without free power<br />
6<br />
Rs. 2.45<br />
Rs. 2.15<br />
Rs. 1.99<br />
Rs. 1.75<br />
COSTRUCTION PERIOD 5 years<br />
1.2 STUDIES/INVESTIGATIONS UNDERTAKEN<br />
• Study <strong>of</strong> topographic maps and remote sensing imageries<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
• Reconnaissance <strong>of</strong> area for identifying probable alternative sites <strong>of</strong> projects<br />
components.<br />
• Study <strong>of</strong> regional geotechnical features/ seimotectonic aspects.<br />
• Geological appraisal <strong>of</strong> proposed project components.<br />
• Water availability design flood studies based on available meteorological/<br />
hydrological data.
• Conceptual layout and project planning.<br />
• <strong>Power</strong> potential studies.<br />
7<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
• Study <strong>of</strong> biotic environment, socio-economic environment for prediction <strong>of</strong><br />
environmental impacts <strong>of</strong> the projects.<br />
• Study <strong>of</strong> existing infrastructure.<br />
• Cost benefit and economic evaluation.<br />
1.3 RESULTS OF STUDIES AND INVESTIGATIONS<br />
1.3.1 Geology<br />
The preliminary geological survey <strong>of</strong> the locations <strong>of</strong> all the structures on the ground was<br />
carried out after site visits. The site-specific geological data were got collected and<br />
utilized in the design <strong>of</strong> various component <strong>of</strong> the project. The survey <strong>of</strong> the near by area<br />
was also carried out to co-relate the geology <strong>of</strong> the project area. The dam location has<br />
been fixed after observing the rock exposures on both the banks and in the riverbed.<br />
Similarly, the underground powerhouse has been fixed after observing the competency <strong>of</strong><br />
rock and its cover.<br />
1.3.2 Hydrology<br />
The river Rangyong drains a catchment area <strong>of</strong> about 592sq.km at the proposed dam site.<br />
The water availability for the project has been considered on the basis <strong>of</strong> 10-daily<br />
discharge series at Lachen for the period from 1976-1997. The water availability at the<br />
<strong>Panan</strong> dam site has been derived from the above data on the basis <strong>of</strong> catchment area<br />
proportion and applying an overall reduction factor <strong>of</strong> 77 %. The computed inflow series<br />
works out has been utilized for <strong>Power</strong> Potential Studies. The design flood has been<br />
assessed as 2200cumecs.<br />
1.3.3 <strong>Power</strong> Potential Studies<br />
The computed inflow series for 21 years viz June 1976 to May 97 has been considered in<br />
the assessment <strong>of</strong> a power benefits from the project. As per GOI notification for tariff the
8<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
year 1976-77 corresponds to 90% dependable year. An installation <strong>of</strong> 200MW<br />
comprising 4 generating units <strong>of</strong> 50MW has been proposed. The energy availability from<br />
the project in a 90%dependable and an average year has been summarized below:<br />
Annual Energy Generation<br />
Annual Energy Generation (GWh) 762<br />
Annual Load Factor (%) 42<br />
Generation during Lean Flow Season (Sept II – Jan I)<br />
Energy Output (GWh) 342.73<br />
Load Factor (%) 26<br />
The design energy for tariff at 95% availability in a 90% dependable year has been<br />
worked out at 762 GWh.<br />
A pondage <strong>of</strong> 1.69 mcum has been provided in the diversion dam which would enable the<br />
station to operate as peaking station. The pondage is equivalent to 1293.2 MWh which<br />
sufficient to operate the station for 3 hours.<br />
1.3.4 <strong>Power</strong> Evacuation Aspects<br />
The power generated from the project would be evacuated through 220 KV,double circuit<br />
line to be connected at the pooling point assumed to come up 2km from Teesta (III) HE<br />
project which shall be connected to National Grid.<br />
1.3.5 Environmental Aspects<br />
The project is located in north district <strong>of</strong> Sikkim. The total land requirement for the<br />
construction <strong>of</strong> various components is about 105ha. Most <strong>of</strong> the land falls under the<br />
category <strong>of</strong> private land. Based on assessment <strong>of</strong> environmental impacts, management<br />
plans have to be formulated for Catchment Area Treatment, compensatory afforestation<br />
and other environmental issues. These issues would be addressed during the investigation<br />
for DPR.
9<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
1.3.6 Estimates Of Cost<br />
The project is estimated to cost Rs. 846.08 crores including IDC at June,2003 price<br />
levels. The preliminary cost estimate <strong>of</strong> the project has been prepared as per guidelines <strong>of</strong><br />
CEA/CWC. The break down <strong>of</strong> the cost estimate is given below:<br />
Civil works : Rs. 554.10 crores<br />
Electro Mechanical Works : Rs. 209.17 crores<br />
Sub Total Cost (Generation) : Rs. 763.27 crores<br />
Transmission Works : Rs. 1.67 crores<br />
Total (Hard Cost) : Rs. 764.94 crores<br />
Interest During Construction : Rs. 81.14 crores<br />
Grand Total : Rs. 846.08 crores<br />
1.3.7 Financial Aspects<br />
As indicated above, the <strong>Panan</strong> HE project with an estimated cost <strong>of</strong> Rs. 846.08 crores<br />
(including IDC <strong>of</strong> Rs. 81.14 crores) and design energy <strong>of</strong> 762 GWh in a 90% dependable<br />
year is proposed to be completed in a period <strong>of</strong> 5 years. The tariff has been worked out<br />
considering a debt-equity ratio <strong>of</strong> 70:30, 16% return on equity, annual interest rate on<br />
loan at 10% and 12% <strong>of</strong> energy as free power to Home State available after losses. The<br />
tariff for the first year and levellised tariff has been worked out Rs. 2.45/KWh & Rs.<br />
1.99/KWh respectively.<br />
1.3.8 Conclusion<br />
The <strong>Panan</strong> HE project involves simple civil works and could be completed in 5 years.<br />
The project would afford a design energy <strong>of</strong> 762 GWh in a 90% dependable year. The<br />
cost per MW installed work out Rs.3.82. The Preliminary Feasibility Report indicates<br />
that the scheme merit consideration for taking up for Survey & Investigation and<br />
preparation <strong>of</strong> DPR.<br />
.
CHAPTER –II<br />
BACKGROUND INFORMATION<br />
10<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
2.1 GENERAL INFORMATION<br />
2.1.1 Introduction<br />
The Himalayan state <strong>of</strong> Sikkim, which in 1975, has elected to join the Indian Union to<br />
become 22 nd state. It is one <strong>of</strong> the most picturesque regions <strong>of</strong> Asia. The bowl like,<br />
mountain –girdled state in the eastern Himalayas bordered on the west by Nepal, on the<br />
north by Tibet, on the east by Bhutan and the south by Darjeeling district <strong>of</strong> the West<br />
Bengal, lies between 27 0 to 28 0 north latitude and 88 0 to 89 0 east longitudes. The Sikkim<br />
is the youngest and small hill state <strong>of</strong> India having an area <strong>of</strong> 7096 Sqkm. Sikkim is<br />
surrounded by important mountain ranges. The chola range <strong>of</strong> mountains on its east<br />
forms the watershed between it and Bhutan on one side and chumbi valley <strong>of</strong> Tibet on the<br />
other. The well-known singalila ridge is <strong>of</strong> the great Himalayas peaks.<br />
Sikkim is divided into four districts. The most populated area is the Eastern district,<br />
which contains the capital town Gangtok followed by Southern and Western districts.<br />
The northern district is sparsely populated because <strong>of</strong> its inhospitable climate and steep<br />
ridges. Lying along the slopes <strong>of</strong> Himalayas between Tibet and plain <strong>of</strong> India, cut <strong>of</strong>f<br />
from the rest <strong>of</strong> the world by mighty mountains, Sikkim’s scenic beauty has no parallel in<br />
the East, Sikkim’s historic past, mystic religion, sublime monasteries and age old rituals<br />
have an attraction hardly to be found anywhere else in the world.<br />
Sikkim is mountainous terrain with cliffs and valleys. Dominating both legend and<br />
landscape is the mighty massif <strong>of</strong> Khangchendzonga known to the outside world as<br />
Kanchenjunga, it is the third highest peak in the world, towering at 8550 meters. Sikkim<br />
is drained by number <strong>of</strong> Perennial Rivers. However, the two main river systems are<br />
Teesta and Rangit. The other entire stream eventually joins one or the other. Rangit also
11<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
joins the Teesta just near the broader between Sikkim and West Bengal at Melli. Besides<br />
the river, there are number <strong>of</strong> lakes and hot springs which add to the beauty <strong>of</strong> the region.<br />
The important hot springs are Phut sachu, Raeong sachu, Yumthang and Momay.<br />
2.1.2 Topography<br />
The total geographical area <strong>of</strong> Sikkim State is about 7300 sq. km. The maximum<br />
horizontal length from north to south is about 112 Km. whereas the maximum width from<br />
east to west is 90 Km. The Tibetan Plateau on the north, Nathula and other passes on the<br />
north east, Bhutan on the south east, Darjeeling district <strong>of</strong> West Bengal on the south and<br />
Singalila range <strong>of</strong> Nepal from the boundaries <strong>of</strong> this picturesque Himalayan State. It is a<br />
hill state having no plain area. The altitude above mean sea level varies from 213m in the<br />
south to over 8500m in the northwest. The Khangchedzonga, the third highest peak in the<br />
world at an elevation <strong>of</strong> about 8550m adorns the state with its beautiful range covered<br />
with shining snow. Gangtok, the capital is about 1677m above mean sea level. The<br />
northern part <strong>of</strong> the state is cut into deep escarpments. The northern part is not populated<br />
except in Lachung and Lachen valleys. Southern Sikkim is, however, more open and<br />
fairly well cultivated.<br />
2.1.3 Rivers<br />
The river Teesta is one <strong>of</strong> the main Himalayan Rivers, which originates in the glaciers <strong>of</strong><br />
Sikkim at an elevation <strong>of</strong> over 8500m above mean sea level. River rises in mountainous<br />
terrain and is formed mainly by the union <strong>of</strong> two hill streams Lachen Chu and Lachung<br />
Chu at Chungthang in North Sikkim. After the confluence <strong>of</strong> Lachen Chu and Lachung<br />
chu at Chungthang, the river gradually increases in width and takes a wide flowing down<br />
to Singhik, dropping in elevation from 1550m to 750m. At Singhik, the river receives one<br />
<strong>of</strong> the its major tributaries, the Talung chug on its right. Talung Chu originates from the<br />
Talung glaciers, which are the part <strong>of</strong> the Khangchendzonga range. From Singhik, the<br />
rivers flow towards Dikchu in a very deep valley and drops from 750mto 550m. From<br />
Dikchu the river flows in a big curve again down to the Singtam with a drop <strong>of</strong> about
12<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
200m. The Rongnichu, which drains the Changu lake area joins Teesta from left at<br />
Singtam and the river receives Ranpo Chu at Rangpo. After Rangpo, Teesta start<br />
widening rapidly and is joined by the great Rangit at Melli bazar on Sikkim – West<br />
Bengal border.<br />
2.1.4 Communication<br />
By Air<br />
Bagdogra is the nearest airport <strong>of</strong> Sikkim. There are regular scheduled flights operated by<br />
the Indian airlines and other private airlines between Calcutta, the capital <strong>of</strong> West Bengal<br />
and Bagdogra and also between New Delhi and Bagdogra. Jeep & taxis are available<br />
outsides Bagdogra airport for Gangtok. Gangtok is 124 kms from Bagdogra and the<br />
journey takes about 4 hours by jeep and 5 hours by bus.<br />
By Rail /Road<br />
The two closest railway stations to Gangtok are Siliguri junction, (Meter Gauge) which is<br />
114km away and New Jailpaiguri (Broad Gauge), which is 125km away. A number <strong>of</strong><br />
trains are available for Calcutta, Delhi, Guwhati and other important cities <strong>of</strong> India.<br />
Besides jeep taxis, Sikkim National Transport and other private buses ply regularly<br />
between Sikkim and Siliguri.<br />
2.1.5 Project<br />
2.1.5.1 Background<br />
In order to exploit vast hydro potential in the country and to achieve the ideal hydro<br />
thermal mix <strong>of</strong> 40:60, the Honourable Prime Minister <strong>of</strong> India had launched a hydroelectric<br />
initiative on 24th May 2003 to develop 50,000MW hydro power potential in the<br />
country. Accordingly, based on the results <strong>of</strong> the preliminary ranking studies <strong>of</strong> Central<br />
Electricity Authority, 162 hydroelectric power schemes with estimated installed capacity<br />
<strong>of</strong> 50,560MW were selected in 16 states for preparation <strong>of</strong> Pre Feasibility Reports. The<br />
work <strong>of</strong> preparation <strong>of</strong> PFR’s was entrusted by <strong>Ministry</strong> <strong>of</strong> <strong>Power</strong> under overall
13<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
coordination <strong>of</strong> CEA to NHPC Ltd, SJVN Ltd, NEEPCO, WAPCOS, KPCL, HPSEB and<br />
UJVN Ltd as consultancy work. NHPC was entrusted a total number <strong>of</strong> 43 schemes <strong>of</strong><br />
21345 MW comprising <strong>of</strong> 7 schemes in Indus-Jhelam Basin J&K, 25 schemes in Dihang-<br />
Dibang-Subansiri Basins Arunachal Pradesh, 1 scheme in Narmada Basin Madhya<br />
Pradesh and 10 schemes in Teesta Basin Sikkim. The <strong>Panan</strong> is one <strong>of</strong> the such scheme for<br />
PFR.<br />
2.1.5.2 About The Project<br />
The project is located on the river Rangyong Chu / Tolung Chu in Dzongu area <strong>of</strong> North<br />
Sikkim district <strong>of</strong> Sikkim. The headquarter <strong>of</strong> the district North Sikkim is at Mangan.<br />
The project involves construction <strong>of</strong> a 55 m high concrete dam, a 8.5 Km long headrace<br />
tunnel and an underground powerhouse with an installed capacity <strong>of</strong> 200 MW. The<br />
project shall generate 762 MU <strong>of</strong> energy in a 90% dependable year. The dam site is<br />
located about 1500 m d/s <strong>of</strong> the confluence <strong>of</strong> river Rangyang Chu and Ringyong Chu<br />
and 1000m u/s <strong>of</strong> village Linza. The underground powerhouse is located about 100 m u/s<br />
<strong>of</strong> the confluence <strong>of</strong> Tolung Chu and Rahi Chu near the village <strong>Panan</strong>. The village Linza<br />
nearest to dam site, is well connected from Mangan by 17 km long state PWD road.<br />
<strong>Panan</strong> , the nearest village to powerhouse site, is at a distance <strong>of</strong> 8.0 km from Mangan.<br />
Mangan falls on Gangtok– Chungthang state highway at 73 Km from Gangtok the<br />
Capital <strong>of</strong> Sikkim and about 160 km from New Jalpaiguri Railway Station and 175 km<br />
from Bagdogra airport.<br />
2.2 POWER SCENARIO AND EXISTING INSTALLATIONS<br />
2.2.1 <strong>Power</strong> System In India<br />
The <strong>Power</strong> System in India has grown from small, isolated stations, serving limited<br />
consumers in and around large cities, into large regional <strong>Power</strong> Grids. The generating<br />
capacity installed in the country has already grown to 107903.53 MW by March 2003.
14<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
For the purpose <strong>of</strong> system planning and operation the country has been divided into<br />
following five geopolitical regions: Northern, Western, Southern, Eastern and North-<br />
Eastern regional power grids and the transmission system are being progressively interconnected<br />
for efficient operation <strong>of</strong> these five regional grids.<br />
The objective <strong>of</strong> the system development is to evolve self-sufficient regional grid catering<br />
to the individual regional power demands. It is also aimed at achieving the maximum<br />
benefits from integrated operation, through a proper mix <strong>of</strong> thermal and hydro generation<br />
and ultimately to tie the five regional grids together to form a strong National <strong>Power</strong><br />
Gird, providing even greater reliability.<br />
The proposed <strong>Panan</strong> Hydro Electric Project located in North Sikkim is envisaged to be<br />
connected to feed the power at a pooling point near Teesta ( III) HE Project through one<br />
220KV double circuit line.<br />
2.2.2 <strong>Power</strong> Position in East Sikkim Region<br />
The total Installed Capacity in Eastern Region is 16696.68 MW. Out <strong>of</strong> this only<br />
2459.51MW is Hydel installation. Thus the Hydro-Thermal mix is 15:85, which is well<br />
below the national average <strong>of</strong> 25:75 and desirable ratio <strong>of</strong> 40:60.<br />
The power supply position for Eastern region during 10th and 11th Five Year Plans is<br />
summarized in Table 2.1. The power and energy availability & requirements during and<br />
after 10th Plan period in the Eastern Region is shown in Tables as projected in the 16th<br />
Electric <strong>Power</strong> Survey, published by CEA.<br />
Even considering the coordinated operation <strong>of</strong> existing hydro and thermal stations, as<br />
well as benefits from ongoing projects and also from the schemes cleared by CEA, the<br />
Eastern region is expected to face peak power and energy deficits during most <strong>of</strong> the 10th
15<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
five Year Plan. The power situation in the region is dynamic and it is expected that the<br />
power generated from this project shall be cheap and helpful to the region as compared to<br />
thermal and other expensive power in the region.<br />
2.2.3 Existing <strong>Power</strong> Installations In Sikkim<br />
First time, a micro hydel station was established in Sikkim on the bank <strong>of</strong> Ranikhola at<br />
Lower Sichey Busty with an installed capacity <strong>of</strong> 10 KW on 27 th May 1927 for the needs<br />
<strong>of</strong> the members <strong>of</strong> the Royal family and Gangtok. Later, Lower Lagyap Hydel Project with<br />
an installed capacity <strong>of</strong> 12MW was constructed by Govt. <strong>of</strong> Sikkim and this was a big<br />
boom. Presently following hydel schemes totaling 95.70MW are under operation in the<br />
state.<br />
Sl.<br />
No.<br />
Hydel Schemes Year <strong>of</strong><br />
Completion<br />
Installed<br />
Capacities<br />
(MW)<br />
Firm<br />
Capacity<br />
(MW)<br />
1 2 3 4 5<br />
1 Jali <strong>Power</strong> House 1966 2.10 1.20<br />
2 Rothak Micro Hydel 1971-72 0.20 0.10<br />
3 Rimbi Micro Hydel, Stage-I 1970-71 0.60 0.30<br />
4 Lower Lagyap HEP 1979-80 12.00 5.50<br />
5 Lachen Micro Hydel 1989-90 0.10 0.05<br />
6 Rimbi Stage-II 1989-90 1.00 0.50<br />
7 Rongnichu Micro Hydel-II 1988-89 2.50 1.20<br />
8 Lachung Micro Hydel 1991-92 0.20 0.10<br />
9 Mayongchu 1993-94 4.00 2.00<br />
10 Upper Rongnichu HEP 1994-95 8.00 4.00<br />
11 Kalej Khola 1995-96 2.00 1.00<br />
12 Rangit Hydel Project 1999-00 60.00 20.00
16<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
13 Robom Micro Hydel 2003-04 3.0 1.00<br />
I - Total Hydel <strong>Power</strong> 95.70 36.95<br />
II - Total Diesel <strong>Power</strong> 2.70 2.70<br />
Total Generation Capacity 98.40 39.65<br />
2.2.3 Load Demand & <strong>Power</strong> Position <strong>of</strong> Eastern Grid<br />
Table 2.1 shows the power supply position <strong>of</strong> Eastern grid up to 2011-12.<br />
2.3 NECESSITY OF THE PROJECT AND RELATED ASPECTS<br />
The need for <strong>Panan</strong> H.E.Project has been considered in the context <strong>of</strong> increasing demand<br />
<strong>of</strong> power in the eastern region. It has been assumed that eastern region will have energy<br />
requirements at the rate 10% per annum rise <strong>of</strong> each year. This is a run <strong>of</strong>f the river<br />
scheme in Teesta basin in North Sikkim District, Sikkim. It will generate 762 MU in 90%<br />
dependable year (1976-77) with 95% machine availability. The power generated at <strong>Panan</strong><br />
H. E. Project (4 X 50 MW) will be fed to a pooling point near Teesta (III) HE Project (<br />
approximate 2km from Teesta (III) through one 220KV double circuit line.
POWER SUPPLY POSITION OF EASTERN REGION<br />
10th Plan 11th Plan<br />
17<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
Table 2-1<br />
Eastern Region 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12<br />
1 2 3 4 5 6 7 8 9 10<br />
Installed Capacity MW 16697 17197 18327 20077 21237 22369 23269 24769 25429 26749<br />
Peak availability MW 7676 7906 8425 9230 9763 10284 10697 11387 11690 12297<br />
Peak requirement MW 8076 8527 9002 9505 10035 10586 11167 11780 12427 13109<br />
Peak Surplus(Deficit) MW -400 -621 -577 -275 -272 -302 -470 -393 -737 -812<br />
Peak Surplus(Deficit) % -4.95% -7.28% -6.41% -2.89% -2.71% -2.86% -4.21% -3.34% -5.93% -6.19%<br />
Energy availability MU 50260 51765 55167 60434 63926 67334 70043 74558 76545 80518<br />
Energy requirement MU 51653 54484 57469 60619 63941 67400 71046 74890 78941 83212<br />
EnergySurplus(Deficit) MU -1393 -2718 -2303 -184 -14 -66 -1003 -331 -2396 -2694<br />
EnergySurplus(Deficit) % -2.70% -4.99% -4.01% -0.30% -0.02% -0.10% -1.41% -0.44% -3.04% -3.24%<br />
1. All the data for the year 2002-2003 has been taken from the website www.cea.nic.in.<br />
2. Energy availability for the year 2002-2003 onwards have been estimated on the basis <strong>of</strong> ratio <strong>of</strong> Energy availability to Installed capacity for the year 2002-<br />
2003.<br />
3. Peak availability for the year 2002-2003 onwards have been estimated on the basis <strong>of</strong> ratio <strong>of</strong> Peak availability to installed capacity for the year 2002-<br />
2003.<br />
4. Energy requirement & peak requirement for the year 2002-2003 onwards is based on the annual increments given at page -117 & 118 <strong>of</strong> "Sixteenth<br />
Electric <strong>Power</strong> Survey Of India".<br />
5. Micro/mini projects have not been considered for the study.<br />
Note:- This is a statistical analysis based on various publications mentioned above and are meant for study and planning purposes.
1<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)
CHAPTER –III<br />
PROJECT AREA<br />
18<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
3.1 DESCRIPTION OF PROJECT INCLUDING RIVER SYSTEM<br />
<strong>Panan</strong> H.E. Project is situated in the Dzongu area <strong>of</strong> North Sikkim district <strong>of</strong> Sikkim .The<br />
project envisages construction <strong>of</strong> 55 m high concrete gravity dam at about 1.0 km<br />
upstream <strong>of</strong> village Lingza and an under ground powerhouse near the village <strong>Panan</strong>. The<br />
river water shall be diverted through a diversion tunnel <strong>of</strong> 600 m long and 8.5 m dia for<br />
construction <strong>of</strong> dam. A headrace tunnel <strong>of</strong> 8.5km length, 6.0m dia shall carry 72.6 cumec<br />
<strong>of</strong> water to the powerhouse. Two numbers <strong>of</strong> desilting chambers <strong>of</strong> 225mX15mX20 m<br />
size shall be constructed to separate the silt particles <strong>of</strong> 0.2mm size and above from the<br />
water. A surge shaft <strong>of</strong> 15 m dia and 75m deep along with two pressure shaft <strong>of</strong> 3.0m dia<br />
425 m deep shall be constructed. A tailrace tunnel <strong>of</strong> 500m length and 6.0m dia shall<br />
discharge the water back into the river. The powerhouse shall have installed capacity <strong>of</strong><br />
200 MW to generate 762MU <strong>of</strong> energy in a 90% dependable year.<br />
The river Rangyong / Tolung Chu are the tributaries <strong>of</strong> the Teesta river originating in the<br />
glaciers <strong>of</strong> North Sikkim at an elevation <strong>of</strong> about 6500 m above mean sea level. The main<br />
tributaries <strong>of</strong> the Tolung Chu are Umram Chu, Passaram Chu, Rangyang Chu ,Ringpi<br />
Chu, Rangli Chu and Rahi Chu. The Ringpi Chu meets Rangyong Chu upstream <strong>of</strong> the<br />
confluence <strong>of</strong> Rangli Chu. Both the river Rahi Chu and Rangyong Chu meets Teesta<br />
river near village Singhik . After running about 14 Km from the confluence, the Dikchu<br />
River joins the Teesta River near the village Dikchu. In the downstream the Rongni Chu<br />
joins Teesta River at Singtam, Rangpo Chu at Rangpo and Rangit at Melli.<br />
3.2 SOCIO-ECONOMIC AND OTHER ASPECTS<br />
3.2.1 Demographic Features<br />
Sikkim is a multi-ethnic state. Broadly, the population can be divided into tribal and nontribal<br />
groups. Lepchas, Bhutias, Sherpas are categorized as Scheduled Tribes. The
19<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
Lepchas are the original inhabitants <strong>of</strong> the State. Compared to other ethnic groups, the<br />
Lepchas still maintain many <strong>of</strong> their traditional ways. The Bhutias comprise, the<br />
Sikkimese Bhutia and Bhutia from Bhutan and Tibet. The Sherpas are a marginal ethnic<br />
group in the State. Over 80% population consist <strong>of</strong> Nepalese. The people from the plain,<br />
mostly involved in trade and services, represent a marginal group. As per the 2001census<br />
<strong>of</strong> India, the total population <strong>of</strong> the State is 540,493. The overall density <strong>of</strong> population in<br />
the State is 76 per sq. Km. East district is the most populated where as North's density<br />
only 7 and is the least populated. Sex ratio (females per thousand male) in 1981 was 835,<br />
where as it had improved in 1991 to 878 and in 2001 has shown a declining trend with a<br />
value <strong>of</strong> 875. There are only eight urban towns and urban population is 9.10% <strong>of</strong> total<br />
population. Literacy rate was 56.94% (19th position) in 1991 and has increased to<br />
70.65% in 2001. The rural literacy rate in 2001 is 68.59% whereas the urban literacy rate<br />
is 85.80%.<br />
The economy <strong>of</strong> Sikkim is mainly based on agricultural and animal husbandry.<br />
Approximately 11% <strong>of</strong> the total geographical area is under agriculture. The work force<br />
participation rate as per 2001 census is 48.52%. The female participation rate in Sikkim is<br />
also much higher than the national average. This is an important aspect <strong>of</strong> the hill<br />
economy, as productivity is low and hence all the able-bodied people are employed in<br />
agriculture and other activities. Cultivators account for the greater majority <strong>of</strong> the people<br />
in the State. Animal husbandry is an integral part <strong>of</strong> the house hold economy <strong>of</strong> the<br />
region. There are certain household industries also which substantially adds to house hold<br />
incomes. The past one and half decade has witnessed a tremendous upward swing in<br />
various development programme giving a new thrust to the Sikkim economy. This<br />
process has increased wage employment opportunities.
20<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
The area in the vicinity <strong>of</strong> the project is populated. The human settlements are scattered<br />
and the human population as per the 1991 census up to different aerial distances from the<br />
project are given in Table 3.1 below.<br />
Table 3.1: Human settlement and Population around the project vicinity<br />
Item Up to 2 km from Up to 2-5 km Up to 5-10 km<br />
Population 2575 3141 6448<br />
Households 463 1171 1316<br />
3.2.2 Ethnographic details (Details <strong>of</strong> the tribals in the area)<br />
In Sikkim various communities with their own customs, religion and culture intermingle<br />
freely to constitute a homogeneous blend. The predominant communities are the<br />
Lepchas, Bhutias and Nepalese. Many people from the plains have also settled, especially<br />
in the urban areas and they are almost always engaged in business or Government<br />
services. A small part <strong>of</strong> the population consists <strong>of</strong> migrant labourers from Bihar, West<br />
Bengal, Eastern UP and Nepal.<br />
3.2.3 Health & Education<br />
There are 4 district hospitals, Gyalshing, Namchi, Singtam & Mangan and one Central<br />
Referral Hospital at Gangtok, besides 25 Primary health centers 150 Primary health subcentre,<br />
9 Veterinary hospitals and 25 Veterinary dispensaries. There is a blood bank at<br />
Gangtok. There are 1234 doctors. Small pox and Kalzor have been eliminated from the<br />
state and many schemes for the provision <strong>of</strong> safe drinking water to the villages and<br />
bazars have been implemented. Sikkim has 700 Pre-nursery schools, 531Primary schools,<br />
122 Middle schools, 64 Secondary schools, and 28 Higher secondary schools 2 Public<br />
schools. There is a Training Institute for primary teachers, a Law college, a B.Ed. college,<br />
2 Degree colleges, one Industrial Training Institution, a Medical and an Engineering<br />
college.
21<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
3.2.4 Religion<br />
Hinduism and Buddhism are the two main religions prevalent in Sikkim. Hindus and<br />
Buddhists constitute 99 percent <strong>of</strong> the population; Christians, Muslims, Jains and Sikhs<br />
together are less than one per cent.<br />
3.2.5 Trade & Industry<br />
Sikkim has a State Industrial Development Investment Corporation, which is encouraging<br />
establishment <strong>of</strong> industrial units in Sikkim. The Industrial Training Institute located at<br />
Rangpo is providing necessary expertise to the younger people for self-independence in<br />
the trade and the know-how. Sikkim has two distilleries , one tannery, and other ancillary<br />
units. Rangpo area has been declared as an industrial Zone. A Brewery is located at<br />
Melli, South Sikkim. and another at Rangpo, East Sikkim. There is also a fruit<br />
preservation factory at Singtam. The Sikkim Mining Corporation mines copper, zinc, lead<br />
etc in the state. The Sikkim Time Corporation a watch-manufacturing factory is located at<br />
Gangtok, which is producing one <strong>of</strong> the latest watches in India. There is a jewel factory<br />
located at Gangtok. Besides the above a good number <strong>of</strong> entrepreneurs have recently<br />
proposed to set up new factories. Some <strong>of</strong> the units are manufacturing leather goods,<br />
safety matches, local crafts, carpet weaving, handmade paper, woodcarving and similar<br />
works. The Sikkim State Tea Board has also been established for quality tea production.<br />
3.2.6 Natural Resources<br />
Sikkim is gifted with abundant natural resources. The resources can be grouped into a<br />
biotic & biotic both <strong>of</strong> which can be renewable and non-renewable. Biotic resources<br />
include agricultural crops, forests etc. The entire Himalayan region is endowed with<br />
natural flora and fauna and is a natural paradise for nature lovers, conservationists,<br />
botanists, zoo lists and environmentalists. There are 4500 species <strong>of</strong> flowering plants, 300<br />
species <strong>of</strong> primulas, 20 species <strong>of</strong> bamboos etc., 45 species <strong>of</strong> rhododendrons and around<br />
450 species <strong>of</strong> orchids.
22<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
The State is very rich in fauna also. There are 144 species <strong>of</strong> mammals, 500-600 species<br />
<strong>of</strong> birds, over 400 species <strong>of</strong> butterflies and moths and many species <strong>of</strong> reptiles are<br />
available. Sikkim is rich in medicinal plants/herbs and also important shrubs are found in<br />
low and high altitude areas. The State is endowed with water resources, tourism,<br />
hydroelectric potential etc. Under economic geology minerals like copper, iron, lime,<br />
dolomite, limestone, coal, quartzite, silicate & graphite are available in the state. As per<br />
the available data around 60% <strong>of</strong> cardamom production in India is from Sikkim. There is<br />
a vast potential for hydroelectric power generation. Tourism development deserves<br />
considerable attention to add to the economy <strong>of</strong> the region.<br />
3.2.6 Hydropower Potential<br />
The Teesta and Rangit are the two main rivers <strong>of</strong> Sikkim where considerable hydro<br />
potential is available. Sikkim have developed 95.7 MW <strong>of</strong> hydropower potential so far by<br />
constructing mini & micro hydel projects and about 600 MW hydel potential is under<br />
development in different stages. The details <strong>of</strong> hydropower potential identified is as<br />
under:<br />
Teesta Basin :<br />
According to the preliminary reconnaissance survey, the river could be harnessed under a<br />
cascade development for hydropower generation is six stages as under :<br />
i) Teesta Stage-I<br />
It is possible to diver the water <strong>of</strong> Teesta river d/s <strong>of</strong> confluence Chento chu near<br />
Shacham and d/s <strong>of</strong> confluence Lhonak chu and Poke chu by constructing diversion<br />
structures at EL ± 3330 and interconnecting tunnels discharging the Tail water at an EL ±<br />
2623 near the place Zema. The scheme will have installed capacity <strong>of</strong> about 320 MW.
23<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
ii) Teesta Stage-II<br />
Under this scheme, a diversion dam <strong>of</strong> 83 m high is proposed near Bonsoi to divert the<br />
tail water <strong>of</strong> Teesta Stage-I and the power house at Chungthang. The scheme shall<br />
generate 330 MW.<br />
iii) Teesta Stage-III<br />
The schemes involve construction <strong>of</strong> Teesta River and Lachung chu near Chungthang and<br />
a <strong>Power</strong> house near Singhik. The scheme shall have the installed capacity <strong>of</strong> 1200 MW .<br />
iv) Teesta Stage-IV<br />
A diversion dam is proposed just d/s <strong>of</strong> confluence <strong>of</strong> Teesta and Tolung chu near the<br />
place called Sanklan and power house near the village Dikchu. The scheme shall have<br />
installed capacity <strong>of</strong> 495 MW.<br />
v) Teesta Stage-V<br />
A diversion dam has been proposed d/s <strong>of</strong> confluence <strong>of</strong> Dikchu chu and Teesta river and<br />
a power house near the village Sherwani. The scheme shall have installed capacity <strong>of</strong> 510<br />
MW.<br />
vi)Teesta Stage-VI<br />
<strong>Power</strong> Potential <strong>of</strong> Rangit Basin It envisages construction <strong>of</strong> a 76 m high concrete dam<br />
near Khanitar d/s <strong>of</strong> the confluence <strong>of</strong> the Teesta and Rongni chu in East Sikkim and the<br />
power house near the village Namthang/Tarkhola in South Sikkim with installed capacity<br />
<strong>of</strong> 360 MW.
24<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
Rangit Basin<br />
The hydropower development <strong>of</strong> Rangit river was identified in four stages as under :<br />
i) Rangit HE Project Stage –I<br />
The Rathong chu, a major perennial tributary <strong>of</strong> Rangit river has a very steep bad slop.<br />
The river takes a big loop near Yoksum. It is proposed to divert the water <strong>of</strong> Rathong chu<br />
at an elevation <strong>of</strong> about 2300 m U/S <strong>of</strong> Yoksum to elevation <strong>of</strong> 100 m near village<br />
Thingtom. The scheme shall generate 47 MW <strong>of</strong> power at 60 % load factor.<br />
ii) Rangit HE Project Stage-II<br />
It is proposed to divert the water <strong>of</strong> Rimbhi chu near Sigglitem and allow the water to<br />
drop through 425 m near Lingchum on Kalet chu to generate 10 MW <strong>of</strong> power at 60%<br />
load factor.<br />
iii) Rangit HE Project Stage –III<br />
A dam has been constructed just d/s <strong>of</strong> confluence <strong>of</strong> Rathong chu and Rangit river and a<br />
power house near the village Mongbru. The installed capacity <strong>of</strong> the scheme is 60 MW.<br />
The project has been commissioned by NHPC in the year 1999 and is in operation.<br />
iv) Rangit HE Project Stage-IV<br />
The scheme shall utilize a drop <strong>of</strong> 110 m from an elevation <strong>of</strong> 440 m to 355 m in Reshi<br />
loop. The scheme shall generate 18 MW <strong>of</strong> power at 60 % load factor.<br />
Schemes For PFR in Teesta Basin<br />
The Cenrtral Elecrtricity authority entrusted 10 schemes with total installed capacity <strong>of</strong><br />
1569 MW for preparation <strong>of</strong> prefeasibility reports as per details given below:<br />
Sl. Name <strong>of</strong> Scheme Installed Name <strong>of</strong><br />
District<br />
No.<br />
Capacity (MW) River<br />
1. Dikchu 105 Bakchachu/Dikchu chu East<br />
2. Rongni 195 Rongni chu East
25<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
3. Namlum 160 Rangit South<br />
4. <strong>Panan</strong> 200 Tolung chu North<br />
5. Lingza 160 Ringpi North<br />
6. Rangyong 141 Rangyong/ Umramchu North<br />
7. Ringpi 70 Ringpi North<br />
8. Rukel 33 Rukel/Rangyong North<br />
9. Jedang 185 Jhonak chu North<br />
10. Teesta Stage-I 320 Teesta & Zemu chu North<br />
OTHER SCHEMES IDENTIFIED BY CEA AND SIKKIM<br />
The CEA in the preliminary ranking studies and Sikkim in the preliminary studies<br />
identified the fallowing schemes:<br />
Sl. Name <strong>of</strong> Scheme Installed Capacity Name <strong>of</strong> River<br />
No.<br />
(MW)<br />
1. KalepHE Project 40 Teesta<br />
2. Talem HE Scheme 65 Teesta<br />
3. Serum HE Scheme 50 Lachung Chu<br />
4. Lachung HE Scheme 30 Lachung<br />
5. Chhota Pathing/Rolep 55 Rangpo Chu<br />
6. Chuzachen 13 Rangpo Chu<br />
7. Suntalitar HE Scheme 25 Rangpo Chu<br />
8. Mana 37 Rangit<br />
9. Gompa 46 Rangit<br />
10. Rammam Stage-I 70 Rammam<br />
11. Rammam Stage-II 85 Rammam<br />
12. Rammam Stage-III 100 Rammam<br />
13 Chakhung Chu hydel 30 Chakhung Chu<br />
In addition to above schemes, the Govt. <strong>of</strong> Sikkim have identified about 40 mini/micro/<br />
small schemes for hydropower development in the region.
CHAPTER-IV<br />
26<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
TOPOGRAPHIC AND GEOTECHNICAL ASPECTS<br />
4.1 INTRODUCTION<br />
Central Electricity Authority had proposed construction <strong>of</strong> <strong>Panan</strong> Hydroelectric Scheme,<br />
on Tolung Chu a right bank tributary <strong>of</strong> river Teesta, meeting Teesta near Sankalang. The<br />
scheme envisaged construction <strong>of</strong> a diversion structure near village Lingza, a 7.5km long<br />
water conductor system and a powerhouse on the right bank <strong>of</strong> river Teesta. This<br />
powerhouse would be located down stream <strong>of</strong> confluence <strong>of</strong> river Teesta and Tolung<br />
Chhu and tail water would be discharged into river Teesta. The scheme was expected to<br />
generate about 230 MW <strong>of</strong> power. The task <strong>of</strong> preparation <strong>of</strong> pre-feasibility report was<br />
given to NHPC. As per the MOU, GSI reports and site visits <strong>of</strong> experts would form major<br />
input for topographic and geotechnical aspects. The GSI report titled “Geology <strong>of</strong> The<br />
Area Around The Proposed <strong>Panan</strong> Hydroelectric Project, Teesta Basin, Sikkim” has now<br />
been received and accordingly the geology <strong>of</strong> the project has been modified. The GSI<br />
report is enclosed as Annexure-4.1.<br />
A study <strong>of</strong> DPR <strong>of</strong> Teesta stage-IV project was undertaken. This project envisages<br />
construction <strong>of</strong> a dam at about 150m downstream <strong>of</strong> confluence <strong>of</strong> Teesta and Tolung<br />
Chu. FRL <strong>of</strong> this scheme has been kept at 768M. The powerhouse <strong>of</strong> <strong>Panan</strong> scheme<br />
(CEA proposal) was proposed downstream <strong>of</strong> the dam <strong>of</strong> stage-IV. Also powerhouse <strong>of</strong><br />
Teesta stage project envisaged in the upstream will discharge tail water on Tolung Chhu.<br />
As a sequel to these the powerhouse <strong>of</strong> <strong>Panan</strong> scheme had to be relocated with the tail<br />
water discharging in Tolung Chu above the FRL level <strong>of</strong> stage-IV scheme and upstream<br />
<strong>of</strong> the tail water <strong>of</strong> Teesta stage (IV) project.<br />
The area is approachable by a fair-weather road from Mangan which crosses river Teesta<br />
near Sankalang and runs in the right bank <strong>of</strong> Tolung Chhu upto village Kayem and
27<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
beyond in the left bank <strong>of</strong> the river passing through village Lingza. Further, a road<br />
reaches village Laven (Right Bank), which is located in the downstream <strong>of</strong> the proposed<br />
diversion structure. Village Laven was unapproachable during the current visit.<br />
4.2 Regional Geology and tectonic setup<br />
Teesta is a major river flowing in Sikkim and West Bengal. The river originates from<br />
Zemeu glaciers and generally flows in north-south direction, at a steeper gradient. Several<br />
tributaries join the river and major amongst these being Yumthang, Zemu, Talung Chu,<br />
Dik Chu and Rangpo Chu. The area has a rugged terrain with the peaks reaching a<br />
maximum <strong>of</strong> 6000M. The regional geological aspects have been provide by GSI, and<br />
these are appended as Annexure-4.1. However, stratigraphic succession brought out by<br />
GSI is provided hereunder.<br />
Group Lithology<br />
Gondwana<br />
Daling<br />
Chungthan<br />
Central Crystalline<br />
Gneissic Complex<br />
Grits, pebble cum boulder beds and carbonaceous shales<br />
with occasional coal seams, pegmatite, quartzite<br />
(Tourmaline bearing)<br />
Interbedde quartzite and chlorite sericite phyllite / schist.<br />
Quartzite/ Biotite schist<br />
Interbedded quartzite and garnetiferous biotite schist.<br />
Calc-silicate rock/marble<br />
Garnet-kyanite-Sillimanite-biotite-quartz-schist.<br />
Banded gneiss with augen gneiss and quartz-biotite gneiss.<br />
Augen gneiss
28<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
4.3 Topographic and Geotechnical Aspects <strong>of</strong> Component Structures<br />
Tolung Chu by generally flows in southeasterly direction. The area exhibits sharp and<br />
rugged hills with steep inaccessible rocky scarps. Steep slopes on both sides bind the<br />
river valley. In general the river flows along the strike <strong>of</strong> formations in cascades and has<br />
developed few falls. In vicinity <strong>of</strong> diversion axis, the river flows in a steep and deep<br />
gorge (Photo-1) while towards the downstream the river valley becomes wider. The left<br />
slopes are dissected by deep drainages namely Rangli Chu, Tadung Chu and Rahi Chu.<br />
Few high level terraces have been observed in this area especially in vicinity <strong>of</strong> Lingza<br />
and Kayem village. Generally thick vegetal cover occupies the area.<br />
4.3.1 Diversion Structure<br />
The proposed diversion structure is located about 1km upstream <strong>of</strong> village Lingza, on<br />
Tolung Chu (Photo-1). At the proposed axis the river flows easterly within a narrow and<br />
deep gorge. Further downstream <strong>of</strong> confluence <strong>of</strong> Ringpi Chhu and Ringyong Chhu,<br />
which is located in close proximity, Tolung Chhu flows in a step gradient and has<br />
developed a fall. Towards the downstream the river valley becomes broader (Photo-2).<br />
Both the banks rise steeply at about 70°-75°. Upstream <strong>of</strong> the axis the river flows in<br />
cascades in a steeper gradient. Both banks appear to be fairly stable. The riverbed is<br />
occupied by river borne material, which is about 6-8m thick. At the proposed axis<br />
gneissic rocks are exposed along h the right bank. Towards the left bank, which was<br />
inaccessible during the visit the rocks appear to be gneissic. The gneisses are strong to<br />
very strong. The formations generally trend NE-SW and dip northweasterly at about 45-<br />
60° (Plate-4.1). Towards downstream a wide terrace is observed which is used for<br />
cultivation purposes. Upstream <strong>of</strong> the proposed axis the slopes are occupied by a thin<br />
veneer <strong>of</strong> slope wash material. Since the area in vicinity <strong>of</strong> proposed diversion structure<br />
shows steep rock exposures the need for geophysical surveys was not felt.
29<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
4.3.2 Water Conductor System<br />
Approximately 9 Km long water conductor system in the right hill has been proposed, to<br />
carry the water from the reservoir to the powerhouse. This tunnel will pass below<br />
Lingdem village. The proposed water conductor system is expected to be housed within<br />
gneisses and quartz biotite schists (Plate-4.1). Few thin bands <strong>of</strong> quartzites may also be<br />
expected. A part <strong>of</strong> the tunnel shall be sub-parallel to the principal discontinuity. The<br />
rock types trend NW-SE dipping NE at 45-60°. Fair to good tunneling media is expected<br />
during tunneling. The tunnel area at places especially downstream <strong>of</strong> Lingdem, Kayem<br />
and Lingthem is occupied by debris material. Thickness <strong>of</strong> this debris material may be<br />
ascertained during feasibility stage to assess the extent <strong>of</strong> rock cover above the water<br />
conductor system and the alignment be suitably modified. Few slides have been observed<br />
above the tunnel alignment especially in and around Village Lingdem. The tunnel area is<br />
occupied by a few small drainages as is observed form topographic maps.<br />
4.3.3 <strong>Power</strong>house<br />
The powerhouse location was fixed keeping in view the FRL <strong>of</strong> Teesta Stage-IV project<br />
and tail water level <strong>of</strong> Teesta stage-III project. The area was studied in detail. A wide<br />
terrace has been deposited on the right bank below the suspension, here, which was<br />
considered for locating a surface powerhouse. Since, the area shall be submerged due to<br />
impoundment <strong>of</strong> stage-IV dam, this alternative was rejected. Alternately, an underground<br />
powerhouse has been proposed in the right hill upstream <strong>of</strong> confluence <strong>of</strong> Tolung Chhu<br />
and Rahi Chhu. This are is bound by steep hill, which shows rock exposures. This area is<br />
thickly vegetated. Towards the upstream the area is occupied by few slides, which shall<br />
require suitable treatment. At the proposed location the slopes are steep and quartz biotite<br />
schists/gneisses are exposed. In this area the rock type is under a veneer <strong>of</strong> slope wash<br />
material. The rock formations trend NW-SE dipping northeasterly (Plate-1) and are<br />
expected to provide a fair to good tunneling media. However, the schists are weaker and<br />
when charged with water these may pose a few problems. Few bands <strong>of</strong> quartzites have<br />
also been noticed towards the downstream <strong>of</strong> the proposed powerhouse. Towards the
30<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
tailrace portion the area is occupied by overburden cover and construction <strong>of</strong> the same<br />
may interfere with the existing road. Since the area shall be submerged by Teesta stage-<br />
IV project the tail water level shall be kept at appropriate level.<br />
4.4 Seismicity<br />
The site lies within Zone-IV <strong>of</strong> seismic zonation map <strong>of</strong> India IS 1893 (Part-I) 2002. IMD<br />
data for the region covering longitude 86 0 -90 0 and latitude 25 0 -29 0 has been analyzed.<br />
Table-I gives a list <strong>of</strong> earthquake events that have occurred within the region. The<br />
probable intensity <strong>of</strong> earthquake within seismic zone-IV corresponds to intensity VIII on<br />
Modified Mercali Scale. Notable earthquakes that have occurred close to this area are<br />
Cachar 1869 (M 7.5), Great Assam Earthquake 1897 (M 8.7), Dhubri 1930 (M 7.1),<br />
Bihar-Nepal Earthquake 1934 (M 8.3), Assam Earthquake 1950 (M 8.5) and Nepal-India<br />
border earthquake 1988 (M 6.4). The maximum intensity experienced in Sikkim region<br />
during Great Assam Earthquake, 1897 was VIII (MMI) and during Bihar-Nepal border<br />
earthquake, 1934 was VII (MMI).<br />
Two major tectonic features occur in the area namely MBT (Main Boundary Thrust) and<br />
MCT (Main Central Thrust) besides other minor features. Many past occurrences <strong>of</strong><br />
earthquakes have been associated with these major lineaments.<br />
It is worthwhile to mention here, that at Teesta Stage-V, Sikkim, site-specific earthquake<br />
studies were conducted. The <strong>Panan</strong> scheme lies very close to Teesta-V project and<br />
earthquake parameters <strong>of</strong> Teesta-V project can be considered for initial design <strong>of</strong> the<br />
project components. However, site-specific studies for the scheme are recommended.<br />
An account <strong>of</strong> seismicity <strong>of</strong> the area has been provided by IMD in Annexure-4.2.
31<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
4.5 GEO-PHYSICAL SURVEY<br />
At dam site, the rock is exposed on the both banks. The power house site is also having<br />
sufficient rock exposures and hence the Geophysical survey was not done. Moreover, the<br />
site was not approachable most <strong>of</strong> the time in rainy season.<br />
4.6 CONSTRUCTION MATERIAL SURVEY<br />
Few terraces near village Lingza can be utilized as construction material. However,<br />
quarries in nearby hills can be developed for the purpose <strong>of</strong> obtaining construction<br />
material.<br />
4.7 RECOMMENDATIONS<br />
The present studies are based on limited field traverses, as the area was mostly<br />
inaccessible. Hence, the following aspects need to be taken up during the feasibility<br />
studies.<br />
• Geological mapping <strong>of</strong> the project components needs to be taken up besides<br />
carrying out subsurface investigations at the dam and powerhouse location to<br />
ascertain the bedrock characteristics and abutment conditions.<br />
• Availability <strong>of</strong> construction material is required to be carried out in detail. The<br />
material is required to be tested for its suitability as construction material. .Further<br />
material obtained from excavation <strong>of</strong> various underground structures can be<br />
utililised after ascertaining its suitability.
Lingza Village<br />
32<br />
Proposed Axis<br />
Photo-1 View <strong>of</strong> Tolung Chu in Vicinity <strong>of</strong> Proposed Diversion Axis<br />
Photo-2 View <strong>of</strong> Proposed <strong>Power</strong>house Area <strong>of</strong> <strong>Panan</strong> Scheme on Tolung<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)
5.1 GENERAL<br />
CHAPTER – V<br />
HYDROLOGY<br />
33<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
<strong>Panan</strong> scheme is a run <strong>of</strong> the river scheme, proposed on Tolung chu/Rangyong Chu near<br />
village Lingza. The project envisages construction <strong>of</strong> a diversion structure about 1 km<br />
upstream <strong>of</strong> village Lingza, a water conductor system in the right bank and a power house<br />
located in the right bank <strong>of</strong> Teesta upstream <strong>of</strong> its confluence with Tolung Chu.The<br />
hydrological investigations and analysis have been carried out for <strong>Panan</strong> Project with a<br />
view to:<br />
• Assess the availability <strong>of</strong> water for power generation by establishing a series <strong>of</strong><br />
average 10-daily discharges for the project site.<br />
• Establish the spillway design flood<br />
• Determine the capacity <strong>of</strong> the reservoir and the area <strong>of</strong> submergence at different<br />
levels including FRL and MDDL.<br />
5.2 RIVER SYSTEM AND BASIN CHARACTERSTICS<br />
Talung chu is one <strong>of</strong> the major tributary <strong>of</strong> river Teesta, which meets Teesta at Singhik<br />
on its right. Talung Chu originates from the Talung glacier, which is a part <strong>of</strong> the<br />
Kanchenjunga range. The river Teesta is one <strong>of</strong> the main Himalayan Rivers, which<br />
originates in the glaciers <strong>of</strong> Sikkim at an elevation <strong>of</strong> over 8500m above mean sea level.<br />
It is being snow fed by the glaciers Zemu, Changame Khanpu, Talung etc. It is an<br />
international river, which flows through the states <strong>of</strong> Sikkim and West Bengal in Indian<br />
Territory and then to Bangladesh.<br />
The river rises in mountainous terrain and is formed mainly by the union <strong>of</strong> two hill<br />
streams Lachen Chu and Lachung Chu at Chunthang in North Sikkim. The river upto this<br />
reach generally flows in a very steep gradient and the slope <strong>of</strong> the Teesta river upto the
34<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
confluence <strong>of</strong> Lachen chu and Lachung chu is about 1 in 20. After the confluence <strong>of</strong><br />
Lachen chu and Lachung chu at Chungthang the river gradually increases in width and<br />
takes a wide loop flowing down to Singhik dropping in elevation from EL 1550 m to EL<br />
750 m. It is here after traversing about 20 Km that the river confluences with Tolung<br />
Chu. Tolung Chu is known as Rangyong Chu at the site <strong>of</strong> proposed diversion<br />
structure.The total length <strong>of</strong> Tolung Chu / Rangyong Chu from origin upto proposed<br />
diversion structure is about 30km. Tolung Chu has a very steep gradient with a slope <strong>of</strong><br />
about 1 in 80 in the vicinity <strong>of</strong> proposed diversion structure and an average slope <strong>of</strong> 1 in<br />
12.<br />
The area has a rugged terrain with the surrounding peaks reaching a maximum elevation<br />
<strong>of</strong> approximately 4000m. The nallah joins Teesta river almost perpendicularly. The<br />
terrain hosts a rich growth <strong>of</strong> vegetation. In general the river flows in southeasterly<br />
direction. Numerous valleys are seen in the area, which are occupied by cultivated<br />
terraces. Few high level terraces have been observed in this area especially in vicinity <strong>of</strong><br />
Lingza and Kayem village. The proposed diversion scheme on Tolung Chu is located<br />
within a deep gorge in a narrow valley <strong>of</strong> about 25-30m width. The right bank slopes are<br />
generally laid at about 70 0 while the left banks are laid at about 75 0 for about 60m height<br />
beyond which a 50-60m wide terrace has been developed. Further uphill the left bank<br />
slopes rise at an angle <strong>of</strong> about 60 0 . Upstream <strong>of</strong> the axis the river flows in cascades in a<br />
steeper gradient.<br />
5.2.1 Cascade Development In Teesta Basin<br />
The river Teesta has tremendous potential for development <strong>of</strong> hydro power, as the river<br />
descends from an elevation <strong>of</strong> about 3600m to about 300m over a distance <strong>of</strong> about 175<br />
Km. According to the preliminary reconnaissance survey by Central water and power<br />
Commission in 1974, the river could be harnessed under a cascade development for<br />
hydro power generation. The cascade development proposed at that stage consisted <strong>of</strong><br />
power generation in six stages on river Teesta. Out <strong>of</strong> these schemes, NHPC had
35<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
submitted a DPR for Teesta H.E project, Stage-III in 1990. The diversion structure for<br />
Teesta-III was proposed to be constructed at Chungthang, which lies downstream <strong>of</strong> the<br />
confluence <strong>of</strong> Lachen Chu and Lachung Chu. Another project under Teesta Basin<br />
development, which is under execution by NHPC, is Teesta Stage-V having an installed<br />
capacity <strong>of</strong> 510 MW, where a diversion structure is being built at Dikchu, about 2 Km<br />
downstream <strong>of</strong> confluence <strong>of</strong> Dikchu with Teesta. About 70km downstream <strong>of</strong> Teesta-V,<br />
NHPC has been entrusted two projects namely, Teesta Low Dam H.E projects, Stage-III<br />
& IV, having an installed capacity <strong>of</strong> 132 MW and 168 MW respectively.<br />
The proposed <strong>Panan</strong> H.E project on Tolung Chu, lies downstream <strong>of</strong> Chungthang, which<br />
was the proposed damsite <strong>of</strong> Teesta-III H.E project.<br />
5.2.2 Catchment Area<br />
The catchment area <strong>of</strong> the proposed scheme lies between Longitude 88 o 10′00” E to<br />
88 o 32′00” E and Latitude 27 o 30′00” N to 28 o 45’00” N. The catchment area upto the<br />
proposed dam site is about 592 Sq.km. The catchment is both snowfed as well as rainfed.<br />
The proposed diversion structure lies at Longitude 88 o 27′00” E and latitude 27 o 33′00” N.<br />
The deepest riverbed elevation at the proposed diversion structure is 1050m. The<br />
catchment Plan is shown in Plate-5.1.<br />
The catchment plan has been prepared from 1:50000, Survey <strong>of</strong> India toposheets. The<br />
entire catchment is covered in toposheets no. 78A/6, 78A/7 and 78A/2. The area above<br />
EL4600m is about 148 Sq.km and has been assumed to be the snowfed area in the<br />
catchment. Thus the rainfed and snowfed area in the catchment is 444 Sq.km and 148<br />
Sq.km respectively.<br />
5.2.3 Temperature And Humidity<br />
The climate in the region is fairly humid and moist. The abrupt variation in altitude is<br />
chiefly responsible for abrupt changes in the climatic conditions and aided by the
36<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
complex orography, the area experiences frequent rainfall <strong>of</strong> varying intensity and<br />
duration. The maximum and minimum temperature varies from 39 0 C in summer to 6 0 C<br />
in winter and the relative humidity varies from 80% to 100%. Temperature and relative<br />
humidity observations are being made in the basin at Dikchu site where Teesta-V H.E<br />
project is being constructed by NHPC and at TLDP-III and TLDP-IV sites, as a part <strong>of</strong><br />
cascade development on Teesta river. The monthly maximum, minimum temperatutre<br />
and relative humidity at Dikchu from Jan 1998 to Dec 2001 is enclosed as Annexure-5.1<br />
and annual maximum and minimum temperature from 1998 to 2001 is given in Table 5-<br />
1.<br />
Month &<br />
Year<br />
Table 5-1<br />
Temperature And Humidity Data At Dikchu<br />
Maximum<br />
Temp o C<br />
Minimum<br />
Temp o C<br />
Max. Relative<br />
Humidity %<br />
Min. Relative<br />
Humidity %<br />
1998 38.0 7.0 99.0 89.0<br />
1999 39.0 6.0 99.0 90.0<br />
2000 39.0 7.0 97.0 85.0<br />
2001 31.0 11.0 97.0 90.0<br />
Overall 39.0 6.0 99.0 85.0<br />
5.2.4 Precipitation Characterstics<br />
In the Teesta basin the southwest monsoon normally sets in the third week <strong>of</strong> May and<br />
withdraws in the second week <strong>of</strong> October. The major portion <strong>of</strong> the catchment being hilly<br />
and the river flowing down in steep gradient, heavy rains in the upper and middle<br />
catchments has an immediate effect <strong>of</strong> rendering the plains to flash floods.<br />
Sh. B.Biswas and C.V.V Bhadram in their paper titled “A study <strong>of</strong> major rainstorms <strong>of</strong><br />
Teesta Basin” and published in Mausam (1984), have studied the rainfall distribution,<br />
major rainstorms and their associated synoptic situations over the catchment based on 22
37<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
years data (1960-81). The entire Teesta catchment extending from its origin in north upto<br />
the Indo Bangladesh border has been considered. On the basis <strong>of</strong> the rainfall distribution,<br />
the Teesta catchment has been divided into three parts viz. upper, middle & lower. The<br />
average annual rainfall is 1328 mm, 2619 mm & 3289 mm for the upper, middle and<br />
lower parts respectively. The monthly breakup <strong>of</strong> the annual rainfall <strong>of</strong> the basin is given<br />
in Table 5-2 .<br />
Table 5-2<br />
Average Monthly Rainfall (mm) <strong>of</strong> Teesta Basin<br />
Month<br />
Catchment<br />
Upper Middle Lower<br />
Jan 21 23 6<br />
Feb 41 32 16<br />
Mar 73 66 30<br />
Apr 72 147 144<br />
May 142 274 315<br />
Jun 245 463 547<br />
Jul 236 621 866<br />
Aug 222 512 645<br />
Sep 171 338 495<br />
Oct 77 112 191<br />
Nov 15 19 21<br />
Dec 13 12 13<br />
Annual 1328 2619 3289<br />
From the table it is clear that July is the wettest month followed by August and June. The<br />
upper, middle and lower catchments receive 71.6%, 78.1% and 83.4% <strong>of</strong> the annual<br />
rainfall respectively due to southwest monsoon. The catchment area upto the present<br />
proposed scheme comprises the upper and middle portions only.
38<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
The authors have considered 53 rainstorms <strong>of</strong> duration ranging from one to three days in<br />
the study. The selection <strong>of</strong> storms is based on isohyetal analysis <strong>of</strong> daily rainfall values.<br />
Out <strong>of</strong> the 53 rain storms 40 were <strong>of</strong> 1 day, 11 were <strong>of</strong> 2 day and only 2 were <strong>of</strong> 3 day<br />
duration. It was concluded that 1 day duration storm are more frequent, a fact which is<br />
also supported by the narrow width <strong>of</strong> the catchment for which the effect <strong>of</strong> any system<br />
lasts for a shorter duration. No storm <strong>of</strong> longer duration than 3 day is reported. Majority<br />
<strong>of</strong> the storms have been reported in July & August. It has also been concluded that rain<br />
storms over this catchment occur in association with any <strong>of</strong> the following synoptic<br />
situations:<br />
(i) Break monsoon conditions i.e. shifting <strong>of</strong> the axis <strong>of</strong> trough close to the<br />
foothills <strong>of</strong> the Himalayas.<br />
(ii) Eastern end <strong>of</strong> monsoon trough lying north <strong>of</strong> Latitude 24 0 N.<br />
(iii) Movement <strong>of</strong> trough in west lies across the eastern Himalayas ; and<br />
(iv) Low pressure system lying over or to the west <strong>of</strong> the catchment.<br />
Many <strong>of</strong> the rainstorms studied by the authors were seen to occur due to either <strong>of</strong> the first<br />
two synoptic situations in July & August. A combination <strong>of</strong> first three synoptic situations<br />
is also a common feature over the area, giving rise to heavy precipitation.<br />
5.2.4.1 Rain Gauge Network<br />
As per the paper <strong>of</strong> Sh. B.Biswas and C.V.V Bhadram, the network density <strong>of</strong> rain<br />
gauges in the basin works out to be one raingauge per 300 Sq.km <strong>of</strong> the basin area. The<br />
data used by them is <strong>of</strong> 42 raingauge stations working under Indian Meteorology<br />
Department (IMD) and Central Water Commision (CWC), 24 <strong>of</strong> which are equipped with<br />
self recording raingauges. The rainfall data availability status <strong>of</strong> the raingauge stations in<br />
the catchment upto Teesta-V H.E project is shown in Table 5-3.
Table 5-3<br />
39<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
S.No Name <strong>of</strong> station Period <strong>of</strong> data availability<br />
1. Lachung Jul 57 to Dec 58, 1960 to 1964,1970 to 1981,<br />
Feb 91 to Dec 97<br />
2. Chunthang Apr 57 to Dec 58, 1960 to 1964,1970 to Jul 85,<br />
1991 to 1997<br />
3. Lachen Jan 57 to Dec 58, Jan 60 to Apr64, 1971, Sep<br />
77 to Jan 78, Jun 92 to Dec 97<br />
4. Yumthang Jul 57 to Oct 57, 1958, 1960 to 1964, Jan 70 to<br />
Sep 82, Jan 83 to Apr 85<br />
5. Singhik Sep 75 to Sep 85, 1991 to 1993<br />
6. Thangu Jan 57 to Dec 58, 1960 to 1964, 1970 to 1974,<br />
Jan to Apr 83<br />
7. Dikchu (near Teesta-<br />
V dam site)<br />
8. Gayzing 1978 to 1988<br />
9. Yoksam 1978 to 1988<br />
10 Rangit dam site 1991 to 1997<br />
1992 to 1997, 2001 to Feb 03<br />
11. Pelling May 93 to Dec 96<br />
At all the above raingauge sites, data for few months is missing in between. Raingauge<br />
sites have also been established near Teesta Low dam projects, Stage-III & IV and are<br />
operational since August 2000.<br />
5.3 WATER AVAILABILITY STUDY<br />
5.3.1 Stream flow and River gauges<br />
Since Teesta River <strong>of</strong>fers ideal conditions for cascade development <strong>of</strong> hydroelectric<br />
schemes, the discharge passing through the river is measured at various sites by CWC.<br />
Recently NHPC has also established its various G&D
40<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
sites on Teesta river since a number <strong>of</strong> projects have been entrusted to NHPC as a part <strong>of</strong><br />
cascade development on the river. These include Teesta-III, Teesta-V, and Teesta Low<br />
Dam projects, Stage-III & IV. The various G&D sites and period <strong>of</strong> data availability in<br />
Teesta Basin is shown in Table 5-4.<br />
Table 5-4<br />
S.No Name <strong>of</strong> site River Period<br />
availabilty<br />
<strong>of</strong><br />
1. Chunthang (before<br />
confluence <strong>of</strong> Lachung &<br />
Lachung Chu)<br />
2. Chungthang (after<br />
confluence <strong>of</strong> Lachung &<br />
Lachung Chu)<br />
3.<br />
Lachen<br />
Chu<br />
Third Mile Tolung<br />
Chu<br />
4. Lachung Lachung<br />
Chu<br />
5. Chuba Yumtha<br />
ng Chu<br />
6. Zema Zema<br />
Chu<br />
Catchment<br />
Area<br />
(Sq.km)<br />
Jan 75 to Aug 85 1919.25<br />
Teesta Jan 75 to Jun 86 2786.8<br />
Jan 75 to Aug 85,<br />
Apr 90 to Apr 98<br />
731.25<br />
May 76 to Aug 85 634.50<br />
Jan 78 to Aug 85 355.5<br />
Jan 79 to Aug 85 900.0<br />
7. Sankalang Teesta Dec 89 to May 98
.<br />
8. Dikchu (near Teesta-V<br />
damsite)<br />
9. Sirwani (<strong>Power</strong> house<br />
site-TeestaV)<br />
10. Legship<br />
damsite)<br />
(near Rangit<br />
Teesta Jan 84 to Oct 91,<br />
Nov91 to Mar97,<br />
Jan 00to Oct01,<br />
Sep02 to Feb 03<br />
Teesta May 84 to Mar 97,<br />
2000<br />
Rangit Jan 77 to Dec 79,<br />
Apr 87 to Dec 87,<br />
Jan 90 to Dec 91<br />
11. Teesta Bazar Teesta 1972 to 1994<br />
41<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
4307<br />
12. Samco Ropeway Teesta Aug 2000 till date 7755<br />
13. Coronation Bridge Teesta 1972 to 1994, Aug<br />
2000 till date<br />
14. Domohoni Teesta 1972 to 2000<br />
8065<br />
5.3.2 Present Study<br />
For the pre feasibility study, water availability for the proposed project has been<br />
computed based on the following methodologies:<br />
(i) The proposed diversion structure for <strong>Panan</strong> project is located on Tolung<br />
Chu/Rangyong chu river which is a major tributary <strong>of</strong> Teesta. At the site <strong>of</strong><br />
diversion structure the river is known as Rangyong Chu while little downstream it<br />
is known as Tolung Chu. Daily G&D data is available on Tolung Chu from Jan 75<br />
to Aug 85 and Apr 90 to Apr 98. The site lies downstream <strong>of</strong> the proposed<br />
project, having a catchment area <strong>of</strong> 731 Sq.km. Average 10-daily series has been<br />
prepared based on this observed data and reduced to dam site using catchment<br />
area proportion, using a reduction factor <strong>of</strong> 0.76.<br />
(ii) Average10-daily series recommended for Teesta-III H.E project by CWC at<br />
Chungthang has been converted at proposed site using catchment area reduction
42<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
(catchment reduction factor – 0.53). Thus a series for the period 1976 to 1984 has<br />
been obtained.<br />
(iii) G&D data observed at Lachen has been converted at proposed site using<br />
catchment area reduction (catchment reduction factor – 0.77). Thus a series for<br />
the period 1976 to 1997 has been obtained. Data at Lachen is missing for the<br />
years 1986-1988, i.e for 3 years. This missing data has been filled from the<br />
observed data at Dikchu G&D site (Teesta-V) using catchment area reduction.<br />
(iv) The 10-daily series recommended for Teesta-V H.E project for the period 1976-<br />
1996 has been converted at proposed damsite using catchment area reduction<br />
(catchment reduction factor – 0.22).<br />
Average 10-daily for all the above four series developed is worked out and compared.<br />
The plot showing this comparison <strong>of</strong> average 10-daily at <strong>Panan</strong> is enclosed at Figure-5.1.<br />
From the plot it is obvious that the average 10-daily <strong>of</strong> the series obtained on the basis <strong>of</strong><br />
G&D data observed on Tolung Chu is on a much higher side as compared to other three<br />
series. For pre-feasibility study, no consistency checks have been made for this observed<br />
data on Tolung Chu and hence the series so obtained cannot be adopted as such, it<br />
comparatively being on a higher side. Average 10-daily obtained from other three<br />
approaches are almost comparable. For pre-feasibility stage, the average 10-daily<br />
obtained from G&D data at Lachen is recommended for <strong>Panan</strong> H.E. project. This has<br />
been adopted as Lachen G&D site is nearer to <strong>Panan</strong> site and also has a smaller<br />
catchment area as compared to Chungtahng and Teesta-V. The final 10-daily series at<br />
<strong>Panan</strong> is enclosed as Annexure-5.2.<br />
5.4 RESERVOIR ELEVATION AREA CAPACITY CURVE<br />
The reservoir elevation-area-capacity curve for <strong>Panan</strong> project has been prepared from<br />
1:50000 Survey <strong>of</strong> India toposheets. The contours are available at an interval <strong>of</strong> 40m the<br />
minimum contour being <strong>of</strong> 1080m. The elevation at the proposed dam axis is about<br />
1050m as read from the toposheets. The area enclosed within the contours has been found
43<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
using Autocad. Area has been found from elevation 1080m to 1240m at an interval <strong>of</strong><br />
40m. The volume between any two elevations is calculated using the formula :<br />
V = H * (A1+A2+√A1A2)/3<br />
Where<br />
V = Volume between two contours<br />
H = Contour interval<br />
A1 = Area at level <strong>of</strong> first contour<br />
A2 = Area at level <strong>of</strong> second contour<br />
The incremental volumes thus computed are added up to obtain cumulative volume. The<br />
resultant area capacity curve is enclosed as Figure-5.2. The curve may be improved after<br />
receiving toposheets in scale <strong>of</strong> 1:25000.<br />
5.5 DESIGN FLOOD<br />
Design Flood for a project can be estimated by following approaches:<br />
(i) Deterministic approach using Unit Hydrograph technique.<br />
(ii) Statistical approach using Flood frequency analysis<br />
(iii) Empirical methods<br />
• Unit Hydrograph technique<br />
Due to non-availability <strong>of</strong> G&D data and hourly gauges, design storm values in the<br />
proposed catchment, rating curves and observed flood hydrographs could not be<br />
developed for computing the Unit Hydrograph and Design Flood hydrograph.<br />
• Flood Frequency analysis<br />
Due to non-availability <strong>of</strong> long term, consistent G&D data near the proposed scheme,<br />
frequency analysis could not be done to estimate the design flood.<br />
• Empirical Methods<br />
The following empirical relationships have been used to estimate the design flood peak:
44<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
(i) Dicken’s formula<br />
Q = CA 3/4<br />
Where C = Dickens constant with value between 11-14 for North- Indian Hilly<br />
catchment. A value <strong>of</strong> 14 has been adopted in present study.<br />
A = Catchment area in sq.km<br />
Therefore, Q = 14 x 592 3/4<br />
= 1680 cumec<br />
(ii) Ali Nawab Jung formula<br />
Q = C(0.386A) (0.925-1/14logA)<br />
Where C = 49 to 60 (55 used)<br />
Q = 55* (0.386*592) (0.925-1/14log(592))<br />
= 2853 cumec<br />
(iii) Computation <strong>of</strong> Design Flood from Design Flood at Teetsa-III using Dicken’s<br />
formula<br />
The design flood recommended for Teesta H.E project, Stage-III was 4572 cumec. The<br />
total catchment area upto Stage-III dam site is 2786 Sq.km. <strong>Panan</strong> H.e project is located<br />
on Tolung Chu river which is a major tributary <strong>of</strong> Teesta river and both the catchments<br />
are hydrologically and hydro-meteorologically similar. Therefore, it seems logical to<br />
transpose the design flood value <strong>of</strong> Teesta-III to proposed dam at <strong>Panan</strong>. This<br />
transposition has been done by Dicken’s formula using a conversion factor <strong>of</strong> 0.313.<br />
Q <strong>Panan</strong> = Q Teesta-III * (A <strong>Panan</strong>/A Teesta-III) 0.75<br />
= 1431 cumec<br />
(iv) Computation <strong>of</strong> Design Flood from Design Flood at Teetsa-V using Dicken’s<br />
formula<br />
The design flood for <strong>Panan</strong> project has also been estimated by transposing the design<br />
flood at Teesta(V) H.E. project using Dicken’s formula. The design flood recommended<br />
for Teesta(V) H.E. project, having a catchment area <strong>of</strong> 4307 Sq.km is 9500 cumec. The<br />
conversion factor for converting it at <strong>Panan</strong> project, having a catchment area <strong>of</strong> 592<br />
Sq.km comes out to be 0.226.
Q <strong>Panan</strong> = Q Teesta-V * (A <strong>Panan</strong>/A Teesta-V) 0.75<br />
= 2145 cumec<br />
45<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
A comparative study <strong>of</strong> flood peak computed from various methods is placed as Table 5-<br />
5. For pre-feasibility stage study, a design flood <strong>of</strong> 2200 cumec has been recommended<br />
at proposed dam site.<br />
Table 5.5<br />
Comparison Of Various Flood Values<br />
S.No Method used Design Flood<br />
(cumec)<br />
1. Dickens Formula 1680<br />
2. Ali Nawaz Jung Formula 2853<br />
3. Transposition <strong>of</strong> Teesta-III Flood peak on the<br />
basis <strong>of</strong> Dickens formula.<br />
4. Transposition <strong>of</strong> Teesta-V Flood peak on the<br />
basis <strong>of</strong> Dickens formula.<br />
1431<br />
2145<br />
On availability <strong>of</strong> more data/information, design flood will be estimated by deterministic<br />
approach using unit hydrograph technique and probabilistic approach using flood<br />
frequency analysis in feasibility stage.<br />
5.6 SEDIMENTATION<br />
A rate <strong>of</strong> sedimentation <strong>of</strong> 0.1385 Ham/Sq.km/Year has been worked out for<br />
Teesta(V) H.E. project based on suspended sediment observations at Dikchu. This silt<br />
rate may be adopted for <strong>Panan</strong> H.E. project too. Detailed sediment study will be done<br />
during feasibility stage with more observed data at the proposed site using a suitable<br />
method.
49<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
TEESTA BASIN PROJECTS Annexure 5.1<br />
Maximum, Minimum monthly temperature and Relative humidity at Dikchu (Teesta-V dam site)<br />
Month 1998 1999 2000 2001<br />
TEMPERATURE RELATIVE<br />
RELATIVE<br />
RELATIVE TEMPERATURE<br />
HUMIDITY TEMPERATURE HUMIDITY TEMPERATURE HUMIDITY<br />
(%)<br />
(%)<br />
(%)<br />
Max O C Min O C<br />
Max O C Min O C<br />
Max O C Min O C<br />
Max O C Min O C<br />
RELATIVE<br />
HUMIDITY<br />
(%)<br />
Jan 25 7 92 23 6 90 22 9 90 20 11 96<br />
Feb 27 8 90 24 7 92 24 7 92 22 14 93<br />
Mar 30 10 92 28 9 91 N.A N.A N.A 24 15 91<br />
Apr 36 12 89 34 16 94 32 22 90 29 20 92<br />
May 38 14 91 35 18 93 36 17 87 29 19 91<br />
Jun 36 20 98 37 20 99 38 20 89 31 22 93<br />
Jul 35 20 99 39 21 96 39 22 90 31 20 90<br />
Aug 36 21 93 38 20 96 36 21 89 30 22 97<br />
Sep 35 20 93 34 16 97 35 20 89 28 22 95<br />
Oct 31 16 93 30 15 96 35 16 85 27 19 96<br />
Nov 29 14 92 28 13 91 31 14 90 25 16 95<br />
Dec 24 9 92 23 9 91 25 10 97 N.A N.A N.A
AVERAGE 10-DAILY DISCHARGE<br />
50<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
Annexure 5.2<br />
YEAR/MONTH JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC AVG<br />
I 17.37 16.13 18.87 25.61 30.30 48.13 87.13 73.67 78.21 27.90 22.12 13.31<br />
1976 II 16.63 15.84 20.23 28.03 23.99 93.93 83.03 80.31 45.10 22.04 18.32 11.39 37.15<br />
III 15.82 16.52 21.94 32.78 33.64 68.15 63.20 85.85 32.93 22.25 16.38 10.52<br />
I 9.38 15.73 8.69 16.69 18.20 51.76 76.32 87.83 60.26 50.15 26.19 16.31<br />
1977 II 8.92 15.32 12.40 15.66 22.48 91.83 89.80 73.90 49.28 31.62 23.89 17.23 37.01<br />
III 8.54 9.18 11.51 16.65 32.03 66.78 107.55 86.29 41.09 25.26 18.04 19.49<br />
I 13.41 12.41 11.31 16.11 27.85 76.46 89.06 109.05 57.39 54.03 28.77 20.37<br />
1978 II 12.01 12.15 12.09 20.63 57.09 80.23 95.47 92.15 74.73 42.13 21.46 17.26 43.70<br />
III 12.27 11.17 13.41 24.44 66.65 101.44 92.13 69.18 56.17 35.91 21.12 15.50<br />
I 14.30 11.81 13.16 25.04 46.88 54.47 97.05 96.11 79.16 84.45 43.09 31.46<br />
1979 II 13.20 11.79 13.78 24.90 59.76 65.18 92.84 75.88 69.08 57.63 35.09 25.91 46.99<br />
III 12.97 12.82 16.96 31.24 45.71 93.46 104.00 80.48 50.67 43.22 33.03 24.95<br />
I 23.51 21.53 24.74 38.48 53.63 74.98 118.19 128.09 111.92 55.55 37.57 29.25<br />
1980 II 22.63 22.56 25.37 49.36 45.87 99.79 120.99 140.66 87.73 47.73 34.21 26.59 59.82<br />
III 22.43 24.06 34.26 56.23 48.89 111.68 126.76 117.15 71.01 44.47 31.49 24.15<br />
I 23.27 20.02 24.62 30.82 56.47 65.12 135.07 106.24 104.32 65.33 45.04 27.32<br />
1981 II 21.81 20.59 26.08 39.03 60.99 77.89 115.83 112.11 89.40 60.47 35.94 24.57 57.43<br />
III 21.53 24.90 30.79 45.99 59.15 105.73 108.94 108.98 71.26 52.85 29.77 19.26<br />
I 17.69 19.25 20.25 33.93 47.11 90.75 97.01 86.15 73.62 49.46 31.33 23.38<br />
1982 II 19.69 20.00 22.67 33.88 52.91 99.95 108.68 81.55 106.47 41.54 27.33 21.56 52.00<br />
III 19.42 19.44 27.00 37.58 51.40 110.48 128.20 95.71 69.86 40.00 26.46 20.41<br />
I 20.24 11.49 17.08 29.05 47.84 95.92 148.79 102.79 102.35 93.33 51.28 32.37<br />
1983 II 18.02 11.42 21.89 23.75 57.33 93.09 126.58 109.00 115.08 92.01 47.11 30.35 63.80<br />
III 12.63 15.89 19.74 29.73 76.29 129.92 125.58 127.34 132.74 62.72 38.80 27.20
51<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
YEAR/MONTH JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC AVG<br />
I 24.27 20.48 45.11 52.07 63.01 135.95 168.98 161.63 174.74 111.42 81.14 39.95<br />
1984 II 23.89 21.27 50.41 55.51 92.09 163.48 169.53 162.06 166.76 141.33 70.12 39.31 93.07<br />
III 21.26 20.43 49.54 55.52 130.83 146.81 179.22 169.66 132.28 108.88 62.32 39.46<br />
I 39.81 35.77 50.28 61.04 62.60 64.93 181.10 160.58 84.58 58.20 34.11 22.37<br />
1985 II 37.81 32.70 54.46 73.66 72.65 81.06 236.32 169.39 80.80 51.01 29.65 20.24 80.46<br />
III 32.74 39.58 50.71 86.99 101.19 229.69 198.71 207.38 67.70 42.03 26.27 18.61<br />
I 17.65 16.79 21.08 23.17 31.50 42.91 93.39 93.15 77.83 63.46 34.07 23.43<br />
1986 II 17.56 17.28 22.95 29.96 33.50 72.78 116.69 80.07 96.67 47.46 30.31 21.58 47.59<br />
III 16.62 19.78 23.56 33.61 35.30 107.83 104.96 88.65 78.69 37.06 26.18 15.91<br />
I 13.89 11.63 11.80 32.07 33.48 72.49 101.37 102.60 134.61 61.32 31.70 16.02<br />
1987 II 13.08 11.52 14.00 22.40 37.23 105.29 96.91 111.95 72.01 45.67 19.34 14.66 48.41<br />
III 12.26 12.64 17.58 29.61 43.70 88.36 108.36 74.82 98.76 39.06 16.99 13.41<br />
I 13.08 12.68 15.30 26.64 35.78 57.30 141.13 121.26 80.62 51.35 22.60 18.05<br />
1988 II 13.08 13.28 22.66 30.09 53.61 82.91 110.87 111.31 54.38 34.07 20.40 17.12 50.61<br />
III 12.92 14.75 23.30 34.99 71.04 90.82 122.19 168.87 60.82 27.41 19.01 16.20<br />
I 9.92 10.64 11.76 12.81 32.30 72.18 128.75 102.30 76.32 54.25 23.36 15.04<br />
1989 II 9.65 9.72 11.99 15.34 33.36 119.57 126.65 80.26 69.13 46.17 18.96 13.04 47.04<br />
III 9.56 10.35 12.32 18.39 81.29 126.45 117.89 78.74 68.68 37.55 17.24 11.42<br />
I 10.41 8.60 7.13 6.12 18.48 79.11 99.60 92.56 80.08 44.75 22.95 13.12<br />
1990 II 9.65 8.08 5.82 10.11 32.57 77.28 126.97 94.03 76.69 45.59 17.15 10.82 40.75<br />
III 8.74 7.80 5.92 12.52 37.46 90.37 108.67 83.45 53.41 37.50 14.32 9.33<br />
I 9.45 8.89 9.11 28.74 29.11 42.00 69.65 84.81 81.34 53.14 28.66 16.25<br />
1991 II 9.27 8.45 10.39 16.39 35.47 66.32 67.86 97.71 85.93 42.14 25.34 12.46 38.09<br />
III 9.17 8.54 10.95 17.34 39.24 60.99 73.96 80.74 66.56 34.58 19.33 10.96<br />
I 9.98 8.94 8.86 10.83 13.64 17.63 41.84 52.64 50.40 31.01 13.98 11.19<br />
1992 II 8.28 8.62 8.92 15.22 15.88 25.13 42.34 52.85 49.61 22.24 12.42 9.69 23.12<br />
III 8.46 8.27 9.17 13.91 15.96 48.70 48.10 57.46 41.06 18.93 11.32 8.95<br />
I 9.10 8.34 13.99 14.84 24.66 28.86 99.34 130.65 124.81 88.33 46.60 36.75<br />
1993 II 9.19 8.86 13.96 16.23 22.20 36.87 99.34 123.86 105.12 65.54 41.08 33.77 49.43<br />
III 8.62 8.56 14.62 19.43 22.48 47.43 116.49 118.63 99.39 56.17 37.66 27.74
52<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
YEAR/MONTH JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC AVG<br />
I 26.13 24.25 22.90 25.39 32.66 59.78 78.56 78.02 69.52 47.05 31.52 20.95<br />
1994 II 24.34 23.19 20.67 31.76 33.67 79.15 83.30 76.20 69.62 41.83 25.98 19.16 44.13<br />
III 24.58 24.87 26.14 29.14 41.41 91.87 84.89 81.95 60.15 38.30 21.71 18.12<br />
I 17.17 17.01 15.49 19.79 52.20 90.43 124.33 87.59 70.83 45.07 22.29 19.16<br />
1995 II 17.36 16.95 14.69 24.52 80.59 96.71 104.29 88.37 63.43 43.88 25.46 17.06 48.23<br />
III 17.15 17.04 20.24 35.79 77.87 97.96 80.17 78.51 61.02 34.28 25.60 15.84<br />
I 13.65 14.85 14.70 16.69 43.95 50.02 84.05 77.01 72.26 52.72 39.29 22.37<br />
1996 II 13.57 13.23 17.02 16.21 38.53 42.35 90.50 71.81 68.95 48.32 36.53 20.24 43.54<br />
III 14.34 14.48 18.14 36.06 53.33 75.64 80.56 72.38 59.97 43.19 32.49 18.61<br />
I 21.05 20.32 20.49 22.50 26.86 35.26 77.39 64.12 54.96 39.64 18.79 14.18<br />
1997 II 20.03 20.25 21.50 22.37 30.89 50.27 66.99 78.23 62.25 25.98 17.36 13.84 34.26<br />
III 20.36 20.01 23.45 23.03 31.91 61.90 55.95 51.39 50.39 20.51 15.73 13.06<br />
I 17.37 16.13 18.87 25.61 38.30 64.93 105.38 99.04 84.58 58.20 34.11 22.37<br />
AVG II 16.63 15.84 20.23 28.03 45.70 81.06 107.75 97.91 80.80 51.01 29.65 20.24 49.37<br />
III 15.82 16.52 21.94 32.78 55.09 98.18 105.32 97.43 67.70 42.03 26.27 18.61
1<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)
Discharge (cumec)<br />
180.00<br />
160.00<br />
140.00<br />
120.00<br />
100.00<br />
80.00<br />
60.00<br />
40.00<br />
20.00<br />
0.00<br />
Jan I<br />
II<br />
III<br />
Feb I<br />
II<br />
III<br />
Mar I<br />
II<br />
PANAN H.E PROJECT<br />
Comparison <strong>of</strong> average 10-daily discharge at <strong>Panan</strong><br />
III<br />
Apr I<br />
II<br />
III<br />
May I<br />
II<br />
III<br />
Jun I<br />
II<br />
47<br />
III<br />
Jul I<br />
II<br />
Period<br />
III<br />
Aug I<br />
II<br />
III<br />
Sep I<br />
II<br />
Transferred from Chunthang<br />
Transferred from Lachen<br />
Transferred from observed data at Tolung Chu<br />
Transferred from Teesta-V<br />
III<br />
Oct I<br />
II<br />
III<br />
Nov I<br />
II<br />
III<br />
Dec I<br />
II<br />
III<br />
Figure 5.1
S.No<br />
Elevation<br />
(m)<br />
Area<br />
(sq.km)<br />
Volume<br />
(Mcum)<br />
1 1050 0.00 0.00<br />
2 1080 0.10 0.98<br />
3 1120 0.25 7.75<br />
4 1160 0.52 22.85<br />
5 1200 0.87 50.31<br />
6 1240 1.27 92.93<br />
Elevation (m)<br />
PANAN H.E PROJECT<br />
RESERVOIR ELEVATION AREA CAPACITY CURVE<br />
100.00<br />
1240<br />
1220<br />
1200<br />
1180<br />
1160<br />
1140<br />
1120<br />
1100<br />
1080<br />
1060<br />
90.00<br />
80.00<br />
PANAN H.E PROJECT<br />
Reservoir Elevation Area Capacity curve<br />
1040<br />
1040<br />
0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90 1.00 1.10 1.20 1.30<br />
Area (Sq.km)<br />
48<br />
70.00<br />
Capacity (Mcum)<br />
60.00<br />
50.00<br />
40.00<br />
30.00<br />
20.00<br />
10.00<br />
0.00<br />
1240<br />
1220<br />
1200<br />
1180<br />
1160<br />
1140<br />
1120<br />
1100<br />
1080<br />
1060<br />
Elevation (m)<br />
Figure 5.2
Discharge (cumec)<br />
180.00<br />
160.00<br />
140.00<br />
120.00<br />
100.00<br />
80.00<br />
60.00<br />
40.00<br />
20.00<br />
0.00<br />
Jan I<br />
II<br />
III<br />
Feb I<br />
II<br />
III<br />
Mar I<br />
II<br />
PANAN H.E PROJECT<br />
Comparison <strong>of</strong> average 10-daily discharge at <strong>Panan</strong><br />
III<br />
Apr I<br />
II<br />
III<br />
May I<br />
II<br />
III<br />
Jun I<br />
II<br />
III<br />
Jul I<br />
II<br />
Period<br />
III<br />
Aug I<br />
II<br />
III<br />
Sep I<br />
II<br />
Transferred from Chunthang<br />
Transferred from Lachen<br />
Transferred from observed data at Tolung Chu<br />
Transferred from Teesta-V<br />
III<br />
Oct I<br />
II<br />
III<br />
Nov I<br />
II<br />
III<br />
Dec I<br />
II<br />
III
CHAPTER – VI<br />
CONCEPTUAL LAYOUT AND PLANNING<br />
53<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
6.1 INTRODUCTION<br />
The <strong>Panan</strong> H.E. project is located in North Sikkim district <strong>of</strong> Sikkim at 1Km U/S <strong>of</strong><br />
village Lingza. It is a run <strong>of</strong> the river scheme proposed to harness hydel potential <strong>of</strong> the<br />
Tolung Chu, a tributary <strong>of</strong> river Teesta. A maximum gross head <strong>of</strong> the order <strong>of</strong> 325 m<br />
between Dam site and <strong>Power</strong> House is proposed to be utilised for power generation. The<br />
powerhouse will have an installed capacity <strong>of</strong> 200 MW. A small reservoir <strong>of</strong> adequate<br />
capacity has been provided as an operating pool to meet diurnal peaking load demands.<br />
6.2 PROJECT COMPONENTS<br />
• 6.5 m diameter, 600 m long Diversion Tunnel with u/s & d/s c<strong>of</strong>fer dam<br />
• 50 m high & 100m long concrete Dam with a central spillway<br />
• Intake Structure leading to 2 Nos. 4.5-m dia D-shaped intake tunnels.<br />
• Two Nos. Underground Desilting Chambers <strong>of</strong> size 225m (L) x 15m (W) x<br />
18m(H)<br />
• One 6.0-m diameter horseshoe shaped concrete lined and 8.5 kms long Head Race<br />
Tunnel with three adits.<br />
• One 15 m diameter & apprx. 75 m high semi-Underground Surge Shaft.<br />
• Two circular Pressure Shaft <strong>of</strong> 3.0m diameter, 425m long each further bifurcating<br />
into 2 numbers steel lined circular penstocks <strong>of</strong> 1.6 m diameter & 35 m long each<br />
upto <strong>Power</strong> House.<br />
• Underground <strong>Power</strong> House <strong>of</strong> size 120m x 22m x 45m consisting <strong>of</strong> 4 Francis<br />
units <strong>of</strong> 50 MW each.<br />
• One no. 6.0m diameter Horseshoe shaped tailrace tunnel <strong>of</strong> about 500 m length.
54<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
The conceptual planning and lay-out <strong>of</strong> project components have been worked out based<br />
on S.O.I topo-sheets <strong>of</strong> 1:50000 scale with contour intervals 40 m.<br />
6.3 CONCEPTUAL LAYOUT<br />
The choice <strong>of</strong> location <strong>of</strong> the dam has been made keeping in view the topography,<br />
geology and maximum water availability at the various locations <strong>of</strong> the diversion<br />
structure near the one suggested earlier by CEA.The location <strong>of</strong> the power house has<br />
been fixed keeping the tailrace outlet at EL 770 m taking into consideration the FRL <strong>of</strong><br />
the proposed Teesta H E Project (Stage-IV) which is 768.00m.<br />
The location <strong>of</strong> major component <strong>of</strong> the project, riverbed levels at dam site, TRT outlet<br />
site and generation capacity <strong>of</strong> the project as identified in the ranking study undertaken<br />
by CEA in 1990 have been taken into account during the preparation <strong>of</strong> this report. Also,<br />
the ongoing/upcoming hydroelectric projects on Teesta river <strong>of</strong> which <strong>Panan</strong> is a tributary<br />
have been taken into consideration in the conceptual planning <strong>of</strong> the project.<br />
The layout plan <strong>of</strong> the project and a brief write up by CEA during ranking study are<br />
enclosed as plate-1 and annexure 6.1 respectively and the cascade development schemes<br />
on the Teesta River as prepared by CEA are enclosed as plate -2.<br />
Based on the hydrological and topographical study, reconnaissance survey <strong>of</strong> the site<br />
input data <strong>of</strong> ranking study; a conceptual layout plan <strong>of</strong> the project was prepared and<br />
discussed in CEA for vetting during sept’03. The minutes <strong>of</strong> meeting is enclosed as<br />
annexure- 6.2.<br />
6.3.1 Dam and River diversion works<br />
Construction <strong>of</strong> 50-m high concrete Dam has been proposed across river Tolung Chu<br />
near village Lingza. Width <strong>of</strong> the valley at Dam site varies from 50 m at riverbed level to<br />
100 m at EL1100 m. Average bed level at Dam site is EL 1150 m. FRL is proposed to
55<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
be fixed at EL 1095 and MDDL at El.1085 m keeping in view the inflow <strong>of</strong> water in<br />
Tolung Chu during lean period. The top <strong>of</strong> the dam has been proposed at EL 1100 m and<br />
seat <strong>of</strong> the dam is proposed to be kept at EL 1045 m after removal <strong>of</strong> approx. 5.0 m thick<br />
overburden. Near the dam axis, both the banks slopes rise at about 70º and the rocks are<br />
exposed .The rock types comprise gneiss/schist.<br />
The overflow section is 44 m long. and Non –overflow section is 56m The spillway has<br />
four bays each <strong>of</strong> size 5 m X 8 m with 3.0 m wide piers. The spillway is designed to pass<br />
a probable maximum flood <strong>of</strong> 2200 cumecs with one gate inoperative. The crest <strong>of</strong><br />
spillway has been kept 35 m below the dam top i.e. at EL1065 m. The low-level orifice<br />
type spillway has been provided to flush out the sediment accumulated in the reservoir to<br />
maintain the live storage capacity <strong>of</strong> the reservoir. Out <strong>of</strong> 100 m dam length, 56 m length<br />
<strong>of</strong> dam constitutes as non-overflow section comprising 16m on right abutment and 40m<br />
on left abutment. The top width <strong>of</strong> non-overflow section is fixed as 8 m. The d/s slope <strong>of</strong><br />
the Non-overflow section has been proposed as 0.8H: 1V and u/s slope as 0.1H: 1V.The<br />
project area falls within Zone-IV <strong>of</strong> seismic zoning map. The availability <strong>of</strong> construction<br />
material for the dam, c<strong>of</strong>ferdam and its suitability has been discussed elsewhere in the<br />
report.<br />
One no. Concrete lined 6.5 m dia 600 m long diversion tunnel has been proposed on the<br />
left bank <strong>of</strong> the river to divert a flood <strong>of</strong> approx. 500 cumecs <strong>of</strong> Tolung chu. The design<br />
diversion discharge has been decided based on the experience <strong>of</strong> various ongoing NHPC<br />
projects in Teesta valley and fast track completion <strong>of</strong> the project. This date shall required<br />
to be firmed up during the preparation <strong>of</strong> feasibility / detailed project report with the<br />
availability <strong>of</strong> more hydrological data & experience gained during the erection <strong>of</strong> Teesta-<br />
IV project just d/s <strong>of</strong> the scheme In order to divert the river during construction <strong>of</strong> the<br />
dam, an u/s c<strong>of</strong>fer dam <strong>of</strong> apprx. height 20m and d/s c<strong>of</strong>ferdam <strong>of</strong> 10m heights is<br />
proposed.
56<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
The reservoir formed by construction <strong>of</strong> Dam has a gross storage pre-sedimentation<br />
capacity <strong>of</strong> 3.52M.cum and live storage capacity <strong>of</strong> 1.69M cum. After sedimentation, the<br />
reservoir is likely to have a live storage capacity <strong>of</strong> more than what is adequate for<br />
running the power station at full capacity for four to six hours in a day during the period<br />
<strong>of</strong> lean flows.<br />
6.3.2 <strong>Power</strong> Intake & Desilting Chambers<br />
The proposed power intake system is on the right side <strong>of</strong> the river and consists <strong>of</strong> two no.<br />
intake and two no. D-shaped intake tunnels <strong>of</strong> dia 4.5 m each. Each tunnel will carry<br />
discharge <strong>of</strong> 36.3 cumec. Two no intakes are proposed to keep the desilting chambers<br />
dimension within the manageable limits and to put either <strong>of</strong> the desilting chambers to<br />
inspection and maintenance while the other is in operation. The intake structures are<br />
designed to pass 88 cumecs, which is about 20% excess <strong>of</strong> turbine discharge <strong>of</strong><br />
72.6cumecs. The invert level <strong>of</strong> the intake structure has been kept as 1075m taking into<br />
consideration the water seal requirement to prevent the vortex formation and air<br />
entrainment. Also, this level being 10m higher than the spillway crest, it is ensured that<br />
entry <strong>of</strong> sediments shall be reduced in the water conductor system. The intake structure<br />
shall be provided with the trash racks to prevent the entry <strong>of</strong> trash in the water conductor<br />
system. The gross area <strong>of</strong> the trash racks shall be determined to give a velocity <strong>of</strong> not<br />
more than 1.5m/s. The racks shall be cleaned by a mechanical raking machine operated<br />
from El.1100m<br />
For the efficient, trouble free and continuos operation <strong>of</strong> turbines with least possible<br />
wearing and erosion damages due to silt, it is necessary to remove 90% <strong>of</strong> the sediments<br />
larger than 0.2mm-particle size. Two nos. 15 m wide Dufour type Desilting chambers<br />
with height 20m shall be provided to remove 90% <strong>of</strong> particles having size greater than or<br />
equal to 0.2m. Two separate intakes lead the water to two independent desilting chambers<br />
225 m long spaced at 30 m c/c, through 25 m long upstream transition which will<br />
gradually reduce the velocity <strong>of</strong> water in the chamber to 0.25 m /sec. The chambers have
57<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
been provided with central gutter with holes to facilitate the flushing <strong>of</strong> settled silt<br />
particles through the flushing tunnel. A silt flushing conduit at the bottom <strong>of</strong> each<br />
chamber runs along the length and two flushing tunnels join to form a single silt flushing<br />
tunnel <strong>of</strong> size 2m x 3.0m d-shaped and 500 m length which will discharge the sediment<br />
back into the river d/s <strong>of</strong> the dam. Thus practically silt free water will be led into the<br />
headrace tunnel. The requirement <strong>of</strong> desilting chambers is being foreseen, as the<br />
TEESTA-V project, which is d/s <strong>of</strong> this project The alignment and orientation <strong>of</strong> the<br />
chambers can be optimized after more geological and topo-graphical data become<br />
available.<br />
6.3.3 Head Race Tunnel, Surge Shaft, and Pressure Shaft<br />
The proposed 6.0 m diameter concrete lined horse- shoe shaped headrace tunnel <strong>of</strong> 8.5<br />
km length, and having a slope <strong>of</strong> 1 in 300 is designed to carry a design discharge <strong>of</strong> 72.6<br />
cumec. The diameter has been fixed keeping the velocity <strong>of</strong> water within 3.0m/s in the<br />
tunnel. Invert level <strong>of</strong> headrace tunnel is fixed at EL. 1075m near intake. The rock cover<br />
above headrace tunnel generally varies from +100 m to +500 m. The low cover reaches<br />
are confined to prominent nalla crossings. The HRT shall be aligned with in the rock type<br />
<strong>of</strong> schist and gneiss. Three nos. constructions Adits are proposed to facilitate excavation<br />
<strong>of</strong> headrace tunnel within the scheduled completion time. The length <strong>of</strong> tunnel between<br />
550m long adit-1 & 450 m long adit-2 is 3Km, between adit-2 & 500 m long adit-3 is 3.5<br />
Km. The tunnel is proposed to be lined with 300 mm thick plain M-20 concrete. The rock<br />
support treatment shall consist <strong>of</strong> grouted rock bolts/anchors and shotcrete with or<br />
without wire mesh. In rock class <strong>of</strong> IV & V steel ribs supports is envisaged.<br />
A vertical, restricted orifice type semi-underground surge shaft <strong>of</strong> 15 m finished dia and<br />
about 75 m height has been proposed with its top opening into a platform at elevation EL<br />
+1150 m. Surge shaft is proposed to be concrete lined with 0.75 m thick R.C.C. Its<br />
bottom is kept at EL 1070m at the HRT and surge shaft junction. The transient studies
58<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
shall be required to be done to work out the maximum and minimum levels for the worst<br />
conditions.<br />
Two no. Steel lined circular Pressure Shaft <strong>of</strong> 3m diameter and 850 m length takes <strong>of</strong>f<br />
from the surge shaft each further bifurcating into 2 numbers underground steel lined<br />
circular penstocks <strong>of</strong> 1.6 m diameter and 150 m length upto <strong>Power</strong> House which will feed<br />
water to 4 units <strong>of</strong> Francis turbines each <strong>of</strong> 50 MW.<br />
6.3.4 <strong>Power</strong> House Complex & Tail Race Tunnel<br />
The underground <strong>Power</strong> House is located on the right bank <strong>of</strong> Tolung Chu River near<br />
village <strong>Panan</strong> about 100m upstream <strong>of</strong> confluence <strong>of</strong> Tolung Chu and Rahi Chu. It will<br />
have an installed capacity <strong>of</strong> 200MW (4 generating units <strong>of</strong> 50 MW each). The units are<br />
spaced at a distance <strong>of</strong> 20 m center to center. The centerline <strong>of</strong> the turbine is proposed at<br />
about EL 763m. The deepest level <strong>of</strong> the tailrace pit is at EL753m. One number<br />
electrically operated overhead traveling crane (E.O.T) <strong>of</strong> apprx.150 MT capacity shall be<br />
provided for handling the electrical and mechanical equipment. The Main inlet valve<br />
chamber is proposed on the u/s <strong>of</strong> the powerhouse. A lift shall be provided near the<br />
service bay for the transportation <strong>of</strong> men and material. The overall dimension <strong>of</strong> the<br />
<strong>Power</strong> House is length 120m, width 22 m, and height 45 m. A Control block area shall<br />
be located on one end <strong>of</strong> machine hall. The transformer cavern cum draft tube gate shaft<br />
is proposed 30m d/s <strong>of</strong> powerhouse cavern. The approx. size is 100mx 14m x 25m.<br />
A cable tunnel <strong>of</strong> size 2.0 m x 3.0 m will take <strong>of</strong>f from transformer area and shall carry<br />
cables to the Pothead yard. The Pothead yard shall measure 100 m x 40 m, which shall<br />
be formed in cutting/filling.<br />
Water from the turbines is discharged through four draft tubes, which merges into a<br />
single tailrace tunnel <strong>of</strong> diameter 6.0m in the Tolung Chu. This tunnel is 6.0 m diameter<br />
horseshoe and about 500m long with invert at EL.768 at tailrace outlet. The tailrace outlet
59<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
level has been kept so, in view the FRL <strong>of</strong> proposed Teesta H E Project (Stage-IV) which<br />
is768.00m. The reservoir <strong>of</strong> Teesta-IV shall extend beyond the junction <strong>of</strong> the Tolung<br />
Chu and Teesta River on the u/s side.<br />
6.4 FURTHER STUDIES<br />
6.4.1 Topographical Studies<br />
1. Topographical contour Survey <strong>of</strong> the dam area and <strong>Power</strong> House area in 1:5000 scale<br />
with 5m contour interval.<br />
2. Survey in 1:1000 scale for locating the adits <strong>of</strong> the HRT.<br />
3. The riverbed survey at Dam axis and tailrace outlet shall be undertaken to firm up the<br />
power potential <strong>of</strong> the project.<br />
6.4.2 Geological and Geo-technical investigations<br />
1. Geological/geotechnical investigations including surface mapping and subsurface<br />
explorations like exploratory drilling and seismic pr<strong>of</strong>iling at the dam and<br />
powerhouse area.<br />
2. Rock mechanic lab tests shall be required for finding out the properties <strong>of</strong> the rock<br />
material.<br />
3. Construction material survey shall be required to be undertaken involving drifts, pits,<br />
and topographical surveys <strong>of</strong> the borrow/quarry areas.<br />
4. Site-specific studies for earthquake design parameters shall also be required to be<br />
undertaken.<br />
6.4.3 Design Studies<br />
1. Hydraulic design <strong>of</strong> various structures like spillway, power intake, desilting<br />
chambers, transient studies <strong>of</strong> surge shaft shall be required for firming up the<br />
dimensions.<br />
2. Stability analysis <strong>of</strong> non-overflow and overflow sections shall have to be done taking<br />
into account the approved seismic parameters.
60<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
3. Hydraulic model studies for reservoir and Dam spillway shall be required for the<br />
confirmation <strong>of</strong> design parameters.<br />
4. Sedimentation analysis for working out the post sedimentation storage capacity <strong>of</strong> the<br />
reservoir.<br />
5. Alternative studies for location, type and layout <strong>of</strong> main components based on<br />
detailed topographical and geological studies.<br />
6.5 HYDRO- MECHENICAL EQUIPMENT<br />
6.5.1 Diversion Tunnel Gate And Hoist<br />
After the construction <strong>of</strong> the dam, for the purpose <strong>of</strong> plugging the diversion<br />
tunnel, two numbers fixed wheel type gates will be provided at the inlet <strong>of</strong> the<br />
tunnel. The gate shall be operated by means <strong>of</strong> electrically operated rope drum<br />
hoist located on the hoist platform installed over the trestle above deck level. The<br />
gate is meant for one time closure, just before plugging <strong>of</strong> the tunnel & designed<br />
for operation against water height corresponding to c<strong>of</strong>fer dam height i.e. 20m.<br />
6.5.2 Spillway Radial Gates, Hoists, Stoplogs And Gantry Crane<br />
Four submerged type radial gates shall be provided to control the discharge<br />
through the gated portion <strong>of</strong> the spillway. Each gate shall be operated by means<br />
<strong>of</strong> suitable capacity hydraulic hoist from a power pack and two double acting<br />
cylinders (one on each end <strong>of</strong> the gate) having a provision <strong>of</strong> 25% pushing force.<br />
One trolley mounted mobile gasoline engine operated power pack capable <strong>of</strong><br />
operating one gate at 25% <strong>of</strong> the normal rated speed is envisaged for emergency<br />
operation <strong>of</strong> spillway radial gates.<br />
One portable oil filter unit for filtration, dehydration & degasification <strong>of</strong> hydraulic<br />
oil.
61<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
One set <strong>of</strong> stoplog has been envisaged to cater to the maintenance requirement<br />
<strong>of</strong> four nos. spillway radial gates. The spillway stoplog shall be lowering / raising<br />
under balanced head condition by means <strong>of</strong> a suitable Capacity Gantry crane<br />
with the help <strong>of</strong> a lifting beam.<br />
6.5.3 Trash Rack And Trash Rack Cleaning Machine<br />
Upstream face <strong>of</strong> the intake shall be provided with the trash rack screen, which<br />
will be cleaned by means <strong>of</strong> a trash rack-cleaning machine.<br />
6.5.4 Intake Gate, Bulkhead Gates And Hoists<br />
Two numbers fixed wheel type gates shall be provided just downstream <strong>of</strong> the<br />
bell mouth <strong>of</strong> the intake. The intake gates are to be designed for self-lowering<br />
against upstream water level corresponding to FRL. The gate shall be operated<br />
by means <strong>of</strong> electrically operated rope drum hoist <strong>of</strong> suitable capacity.<br />
For maintenance and inspection <strong>of</strong> intake gates and embedded parts, two<br />
numbers vertical slide gates have been proposed on the upstream <strong>of</strong> the intake<br />
gates. The slide gates shall be operated by means <strong>of</strong> a electrically operated rope<br />
drum hoist under balance head condition.<br />
6.5.5 Desilting Chamber Gate<br />
One set <strong>of</strong> slide type gate has been envisaged to cater to the maintenance<br />
requirement <strong>of</strong> two nos. desilting chambers. The gate shall be lowering / raising<br />
under balanced head condition by means <strong>of</strong> a suitable Capacity EOT Crane.<br />
6.5.6 Silt Flushing Tunnel Gates And Hoists<br />
In two silt-flushing tunnels, each tunnel is provided with a set <strong>of</strong> two slide<br />
(emergency & service) gates for regulating the discharge through flushing<br />
tunnels. Both the (emergency & service) gates shall be operated by means <strong>of</strong>
62<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
hydraulic hoists. The gate grooves are provided with bonnet structures<br />
embedded in the concrete & a watertight bonnet cover at the top <strong>of</strong> the groove.<br />
6.5.7 Surge Shaft Gate And Hoist<br />
The intake <strong>of</strong> pressure shaft is provided with two numbers slide type gates. The<br />
gate shall be operated under balanced head condition by means <strong>of</strong> an electrically<br />
operated rope drum hoist.<br />
6.5.8 Draft Tube Gates And Hoists<br />
To isolate turbines from the tailrace tunnel to cater to the inspection /<br />
maintenance requirements <strong>of</strong> turbines, four nos. fixed wheel type draft tube gates<br />
(one for each unit) have been envisaged. The gates shall be operated under<br />
balanced head conditions by suitable capacity rope drum hoist.<br />
6.5.9 Tailrace Gate And Hoist<br />
One set <strong>of</strong> slide type bulk head gate to isolate tailrace tunnel has been<br />
envisaged. The slide gate shall be operated under balanced head conditions by a<br />
suitable capacity rope drum hoist. Adjoining civil structure shall be provided with<br />
by-pass valve to create balanced head condition.<br />
6.5.10 Adit Inspection Gates<br />
Three nos. adits shall be provided with manually operated hinged type gates in<br />
the concrete plug at the HRT construction to give access to the head race tunnel<br />
in the event <strong>of</strong> any inspection, repair and maintenance.<br />
6.5.11 Pressure Shaft Steel Liner<br />
Two no. Pressure Shaft <strong>of</strong> dia. 3000 mm fully steel lined will take <strong>of</strong>f from Surge<br />
Shaft to feed the turbine placed in the powerhouse. It comprises horizontal &
63<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
vertical ferrules, 2 nos. vertical bends, 2 nos. plan bends, 1 no. bifurcations and<br />
branch pipes for each pressure shaft for feeding four turbines.<br />
The material <strong>of</strong> Pressure Shaft liner shall conform to ASTM A537 Class 1.<br />
However bifurcation material shall conform to ASTM A517 Gr. F.<br />
6.5.12 Instrument And Remote Control<br />
Gates shall be provided with PLC based remote control system for Control and<br />
operation <strong>of</strong> gates and automatic control <strong>of</strong> the reservoir level.<br />
6.5.13 Diesel Generating Set<br />
One diesel generating set complete with all accessories will be provided for<br />
emergency operation <strong>of</strong> gates and hoists.
CHAPTER-VII<br />
POWER POTENTIAL STUDIES<br />
64<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
7.1 GENERAL<br />
The <strong>Power</strong> potential studies <strong>of</strong> <strong>Panan</strong> HE Project has been made for 90%<br />
dependable year based on 21 hydrological years, from 1976-77 (June) to 1996-<br />
97 (May) as given in table 7.1. The salient features <strong>of</strong> the project are as<br />
follows:<br />
FRL (EL) =1095 m<br />
MDDL (EL) =1085 m<br />
TWL = EL 770M<br />
Rated net head= 312 m<br />
Type <strong>of</strong> turbine = Vertical Francis<br />
Speed = 500 RPM<br />
Rated Discharge <strong>of</strong> Plant=72.60 cumecs<br />
Proposed Plant Capacity= 200 MW (4x50 MW)<br />
Design Energy =761.71 MU in the 90% dependable year with 95%<br />
machine availability<br />
Minimum Peaking (Hrs) = 3 hrs (approx.)<br />
7.2 AVAILABLE FLOW<br />
The discharge data for the 90% dependable hydrological year is given in Table<br />
7.3. For carrying out the power potential and optimisation studies, the following<br />
statistics have been computed.<br />
Year:<br />
Each 10-daily period <strong>of</strong> the year represents the average <strong>of</strong> the flow recorded for<br />
the corresponding period <strong>of</strong> each year.
65<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
90% Dependable Year:<br />
This is the lower decile <strong>of</strong> the series <strong>of</strong> the corresponding 10-daily period <strong>of</strong> the<br />
record i.e. (N+1) x 0.9 th year where N is the years for which continuous<br />
hydrological data are available. The 90% dependable year comes out to be<br />
1976-77 whose calculations are shown in table 7.2.<br />
7.3 DEFINITION OF TERMS<br />
Annual Energy<br />
This is the yearly energy provided during the 90% dependable hydrological year<br />
with 95% machine availability.<br />
Firm <strong>Power</strong><br />
This is the power capacity, which can be guaranteed continuously during the lean<br />
period in 90% dependable year. Here no reservoir capacity has been selected in<br />
order to have minimum environmental impact. During lean inflow period (winter<br />
season) the firm power comes out to be 23.52 MW.<br />
7.4 FULL RESERVOIR LEVEL (FRL) AND MINIMUM DRAW DOWN LEVEL<br />
(MDDL)<br />
FRL and MDDL have been fixed at EL 1095m & EL 1085 m respectively based<br />
on civil consideration. This project is envisaged as a run <strong>of</strong> the river scheme.<br />
7.5 OPERATING HEAD AND HEAD LOSSES<br />
The net operating head for turbines has been derived from the following formula<br />
where head losses are taken as 10 m.<br />
Net operating head = FRL-1/3 (FRL-MDDL)-TWL (all units running)-<br />
Head losses<br />
The net operating head comes out to 312 m.
66<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
7.6 INSTALLED CAPACITY<br />
The studies for power output and annual energy generation for the 90%<br />
dependable year has been given in Tables 7.4. Considering water availability the<br />
total installed capacity has been selected as 200 MW.<br />
7.7 SIZE OF GENERATING UNITS<br />
The power load demand in India is increasing at a very rapid rate and both<br />
hydroelectric and thermal (including nuclear) <strong>Power</strong> potential in the country are<br />
being developed not only to meet the overall requirements, but stimulatingly also<br />
to provide a proper mix <strong>of</strong> hydro and thermal power for optimum operation <strong>of</strong> the<br />
system. Keeping this in view current practice is to opt for largest size hydro units<br />
permissible within the parameters <strong>of</strong> economy, operating efficiency,<br />
maintenance, optimum utilization <strong>of</strong> available water, transport limitation etc. It is<br />
therefore proposed to install 4 units with capacity each <strong>of</strong> 50 MW with Francis<br />
turbine as prime mover has been envisaged, however detailed optimization<br />
studies for fixation <strong>of</strong> installed capacity would have to be done at FR/ DPR stage.<br />
7.8 ENERGY GENERATION<br />
The energy generation in the 90% dependable year (1976-77) indicating lean<br />
inflow period and high inflow period is shown in Table 7.5 and 7.2. It may be<br />
seen from this table that the total unrestricted energy generation is 838.70 MU.<br />
Annual energy generation at 200 MW comes out to be 761.71 MU. Incremental<br />
benefits have been shown in Table 7.6 which comes out to be 1.71 for this year.<br />
Also annual energy generation unrestricted has been indicated in table 7.7(A) to<br />
7.7(U) for 21 hydrological years. Energy available at bus bar shall be 752.6 MU<br />
after allowing auxiliary consumption <strong>of</strong> 0.7% and transformer losses <strong>of</strong> 0.5%<br />
respectively.
Month<br />
JUNE<br />
JULY<br />
AUGUST<br />
SEPTEMBER<br />
OCTOBER<br />
NOVEMBER<br />
DECEMBER<br />
JANUARY<br />
FEBRUARY<br />
MARCH<br />
APRIL<br />
MAY<br />
1976-<br />
1977<br />
1977-<br />
1978<br />
1978-<br />
1979<br />
1979-<br />
1980<br />
1980-<br />
1981<br />
1981-<br />
1982<br />
1982-<br />
1983<br />
HYDROLOGICAL SERIES<br />
1983-<br />
1984<br />
67<br />
1984-<br />
1985<br />
1985-<br />
1986<br />
1986-<br />
1987<br />
1987-<br />
1988<br />
1988-<br />
1989<br />
1989-<br />
1990<br />
1990-<br />
1991<br />
1991-<br />
1992<br />
1992-<br />
1993<br />
1993-<br />
1994<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
1-10 48.13 51.76 76.46 54.47 74.98 65.12 90.75 95.92 135.95 64.93 42.91 72.49 57.30 72.18 79.11 42.00 17.63 28.86 59.78 90.43 50.02<br />
11-20 1 93.93 91.83 80.23 65.18 99.79 77.89 99.95 93.09 163.48 81.06 72.78 105.29 82.91 119.57 77.28 66.32 25.13 36.87 79.15 96.71 42.35<br />
21-30 2 68.15 66.78 101.44 93.46 111.68 105.73 110.48 129.92 146.81 229.69 107.83 88.36 90.82 126.45 90.37 60.99 48.70 47.43 91.87 97.96 75.64<br />
1-10 Jan-00 87.13 76.32 89.06 97.05 118.19 135.07 97.01 148.79 168.98 181.10 93.39 101.37 141.13 128.75 99.60 69.65 41.84 99.34 78.56 124.33 84.05<br />
11-20 4 83.03 89.80 95.47 92.84 120.99 115.83 108.68 126.58 169.53 236.32 116.69 96.91 110.87 126.65 126.97 67.86 42.34 99.34 83.30 104.29 90.50<br />
21-31 5 83.03 107.55 92.13 104.00 126.76 108.94 128.20 125.58 179.22 198.71 104.96 108.36 122.19 117.89 108.67 73.96 48.10 116.49 84.89 80.17 80.56<br />
1-10 Jan-00 73.67 87.83 109.05 96.11 128.09 106.24 86.15 102.79 161.63 160.58 93.15 102.60 121.26 102.30 92.56 84.81 52.64 130.65 78.02 87.59 77.01<br />
11-20 7 80.31 73.90 92.15 75.88 140.66 112.11 81.55 109.00 162.06 169.39 80.07 111.95 111.31 80.26 94.03 97.71 52.85 123.86 76.20 88.37 71.81<br />
21-31 8 85.85 86.29 69.18 80.48 117.15 108.98 95.71 127.34 169.66 207.38 88.65 74.82 168.87 78.74 83.45 80.74 57.46 118.63 81.95 78.51 72.38<br />
1-10 Jan-00 78.21 60.26 57.39 79.16 111.92 104.32 73.62 102.35 174.74 84.58 77.83 134.61 80.62 76.32 80.08 81.34 50.40 124.81 69.52 70.83 72.26<br />
11-20 10 45.10 49.28 74.73 69.08 87.73 89.40 106.47 115.08 166.76 80.80 96.67 72.01 54.38 69.13 76.69 85.93 49.61 105.12 69.62 63.43 68.95<br />
21-30 11 32.93 41.09 56.17 50.67 71.01 71.26 69.86 132.74 132.28 67.70 78.69 98.76 60.82 68.68 53.41 66.56 41.06 99.39 60.15 61.02 59.97<br />
1-10 Jan-00 27.90 50.15 54.03 84.45 55.55 65.33 49.46 93.33 111.42 58.20 63.46 61.32 51.35 54.25 44.75 53.14 31.01 88.33 47.05 45.07 52.72<br />
11-20 13 22.04 31.62 42.13 57.63 47.73 60.47 41.54 92.01 141.33 51.01 47.46 45.67 34.07 46.17 45.59 42.14 22.24 65.54 41.83 43.88 48.32<br />
21-31 14 22.25 25.26 35.91 43.22 44.47 52.85 40.00 62.72 108.88 42.03 37.06 39.06 27.41 37.55 37.50 34.58 18.93 56.17 38.30 34.28 43.19<br />
1-10 Jan-00 22.12 26.19 28.77 43.09 37.57 45.04 31.33 51.28 81.14 34.11 34.07 31.70 22.60 23.36 22.95 28.66 13.98 46.60 31.52 22.29 39.29<br />
11-20 16 18.32 23.89 21.46 35.09 34.21 35.94 27.33 47.11 70.12 29.65 30.31 19.34 20.40 18.96 17.15 25.34 12.42 41.08 25.98 25.46 36.53<br />
21-30 17 16.38 18.04 21.12 33.03 31.49 29.77 26.46 38.80 62.32 26.27 26.18 16.99 19.01 17.24 14.32 19.33 11.32 37.66 21.71 25.60 32.49<br />
1-10 Jan-00 13.31 16.31 20.37 31.46 29.25 27.32 23.38 32.37 39.95 22.37 23.43 16.02 18.05 15.04 13.12 16.25 11.19 36.75 20.95 19.16 22.37<br />
11-20 19 11.39 17.23 17.26 25.91 26.59 24.57 21.56 30.35 39.31 20.24 21.58 14.66 17.12 13.04 10.82 12.46 9.69 33.77 19.16 17.06 20.24<br />
21-31 20 10.52 19.49 15.50 24.95 24.15 19.26 20.41 27.20 39.46 18.61 15.91 13.41 16.20 11.42 9.33 10.96 8.95 27.74 18.12 15.84 18.61<br />
1-10 Jan-00 9.38 13.41 14.30 23.51 23.27 17.69 20.24 24.27 39.81 17.65 13.89 13.08 9.92 10.41 9.45 9.98 9.10 26.13 17.17 13.65 21.05<br />
11-20 22 8.92 12.01 13.20 22.63 21.81 19.69 18.02 23.89 37.81 17.56 13.08 13.08 9.65 9.65 9.27 8.28 9.19 24.34 17.36 13.57 20.03<br />
21-31 23 8.54 12.27 12.97 22.43 21.53 19.42 12.63 21.26 32.74 16.62 12.26 12.92 9.56 8.74 9.17 8.46 8.62 24.58 17.15 14.34 20.36<br />
1-10 Jan-00 15.73 12.41 11.81 21.53 20.02 19.25 11.49 20.48 35.77 16.79 11.63 12.68 10.64 8.60 8.89 8.94 8.34 24.25 17.01 14.85 20.32<br />
11-20 25 15.32 12.15 11.79 22.56 20.59 20.00 11.42 21.27 32.70 17.28 11.52 13.28 9.72 8.08 8.45 8.62 8.86 23.19 16.95 13.23 20.25<br />
21-28 26 9.18 11.17 12.82 24.06 24.90 19.44 15.89 20.43 39.58 19.78 12.64 14.75 10.35 7.80 8.54 8.27 8.56 24.87 17.04 14.48 20.01<br />
1-10 Jan-00 8.69 11.31 13.16 24.74 24.62 20.25 17.08 45.11 50.28 21.08 11.80 15.30 11.76 7.13 9.11 8.86 13.99 22.90 15.49 14.70 20.49<br />
11-20 28 12.40 12.09 13.78 25.37 26.08 22.67 21.89 50.41 54.46 22.95 14.00 22.66 11.99 5.82 10.39 8.92 13.96 20.67 14.69 17.02 21.50<br />
21-31 29 11.51 13.41 16.96 34.26 30.79 27.00 19.74 49.54 50.71 23.56 17.58 23.30 12.32 5.92 10.95 9.17 14.62 26.14 20.24 18.14 23.45<br />
1-10 Jan-00 16.69 16.11 25.04 38.48 30.82 33.93 29.05 52.07 61.04 23.17 32.07 26.64 12.81 6.12 28.74 10.83 14.84 25.39 19.79 16.69 22.50<br />
11-20 31 15.66 20.63 24.90 49.36 39.03 33.88 23.75 55.51 73.66 29.96 22.40 30.09 15.34 10.11 16.39 15.22 16.23 31.76 24.52 16.21 22.37<br />
21-30 32 16.65 24.44 31.24 56.23 45.99 37.58 29.73 55.52 86.99 33.61 29.61 34.99 18.39 12.52 17.34 13.91 19.43 29.14 35.79 36.06 23.03<br />
1-10 Feb-00 18.20 27.85 46.88 53.63 56.47 47.11 47.84 63.01 62.60 31.50 33.48 35.78 32.30 18.48 29.11 13.64 24.66 32.66 52.20 43.95 26.86<br />
11-20 34 22.48 57.09 59.76 45.87 60.99 52.91 57.33 92.09 72.65 33.50 37.23 53.61 33.36 32.57 35.47 15.88 22.20 33.67 80.59 38.53 30.89<br />
1994-<br />
1995<br />
1995-<br />
1996<br />
TABLE 7.1<br />
21-31 35 32.03 66.65 45.71 48.89 59.15 51.40 76.29 130.83 101.19 35.30 43.70 71.04 81.29 37.46 39.24 15.96 22.48 41.41 77.87 53.33 31.91<br />
1996-<br />
1997
YEAR<br />
UNRESTRICTED<br />
ENERGY<br />
GENERATION<br />
MU<br />
Table No. 7.2<br />
CALCULATION FOR 90% DEPENDABLE YEAR<br />
YEAR<br />
UNRESTRICTED<br />
ENERGY IN<br />
DESCENDING<br />
ORDER<br />
1976-1977 838.70 1984-1985 2325.33 1<br />
1977-1978 968.36 1983-1984 1760.17 2<br />
1978-1979 1078.03 1985-1986 1636.45<br />
1979-1980 1245.68 1980-1981 1443.51<br />
1980-1981 1443.51 1981-1982 1347.72<br />
1981-1982 1347.72 1993-1994 1329.93<br />
1982-1983 1241.86 1979-1980 1245.68<br />
1983-1984 1760.17 1982-1983 1241.86<br />
1984-1985 2325.33 1987-1988 1224.20<br />
1985-1986 1636.45 1988-1989 1163.43<br />
9<br />
10<br />
1986-1987 1123.53 1986-1987 1123.53 11<br />
1987-1988 1224.20 1995-1996 1096.81 12<br />
1988-1989 1163.43 1994-1995 1092.11 13<br />
1989-1990 1072.05 1978-1979 1078.03 14<br />
1990-1991 1028.94 1989-1990 1072.05 15<br />
1991-1992 864.89 1990-1991 1028.94 16<br />
1992-1993 594.21 1996-1997 1011.07 17<br />
1993-1994 1329.93 1977-1978 968.36 18<br />
68<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
RANK<br />
OF<br />
THE<br />
CALCULATION OF 90% DEPENDABLE<br />
YEAR<br />
YEAR<br />
3<br />
4<br />
5<br />
6<br />
7<br />
8<br />
N= No. <strong>of</strong> year<br />
90% Dependable Year<br />
=(N+1)*0.9th year<br />
=(21+1)*0.9th year<br />
=19.8th year<br />
=20th year (say)<br />
90% Dependable year is 1976-1977<br />
90% Dependable energy (unrestricted)<br />
is 838.70 MU<br />
90% Dependable energy<br />
whenpower is restricted<br />
to 200 MW is 761.71<br />
MU<br />
1994-1995 1092.11 1991-1992 864.89 19 90% DEPENDABLE YEAR IS 1976-1977<br />
1995-1996 1096.81 1976-1977 838.70 20<br />
1996-1997 1011.07 1992-1993 594.21 21
PERIOD 90%<br />
DEPENDABLE<br />
INFLOW<br />
CUMECS<br />
Table No. 7.3<br />
POWER GENERATION IN 90% DEPENDABLE YEAR (1976-77)<br />
UNRESTRI<br />
CTED<br />
POWER<br />
POWER IN MW ENERGY IN MU<br />
RESTRICTED<br />
TO INSTALLED<br />
CAPACITY<br />
69<br />
UNRESTRICTED<br />
ENERGY<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
RESTRICTED<br />
ENERGY<br />
(MU)<br />
1 2 4 5 6 7 8<br />
MONTHLY<br />
ENERGY IN<br />
GWH<br />
Jun- 1-10 48.13 132.58 132.58 31.82<br />
124.88<br />
76 11-20 93.93 258.74 200.00 62.10 48.00<br />
21-30 68.15 187.74 187.74 45.06 45.06<br />
Jul- 1-10 87.13 240.01 200.00 57.60 48.00 148.80<br />
76 11-20 83.03 228.72 200.00 54.89 48.00<br />
21-31 83.03 228.72 200.00 60.38 52.80<br />
Aug- 1-10 73.67 202.93 200.00 48.70 48.00 148.80<br />
76 11-20 80.31 221.22 200.00 53.09 48.00<br />
21-31 85.85 236.49 200.00 62.43 52.80<br />
Sep- 1-10 78.21 215.44 200.00 51.71 48.00 99.59<br />
76 11-20 45.10 124.25 124.25 29.82 29.82<br />
21-30 32.93 90.71 90.71 21.77 21.77<br />
Oct- 1-10 27.90 76.86 76.86 18.45 18.45 49.19<br />
76 11-20 22.04 60.71 60.71 14.57 14.57<br />
21-31 22.25 61.28 61.28 16.18 16.18<br />
Nov- 1-10 22.12 60.94 60.94 14.63 14.63 37.56<br />
76 11-20 18.32 50.46 50.46 12.11 12.11<br />
21-30 16.38 45.11 45.11 10.83 10.83<br />
Dec- 1-10 13.31 36.67 36.67 8.80 8.80 23.98<br />
76 11-20 11.39 31.36 31.36 7.53 7.53<br />
21-31 10.52 28.98 28.98 7.65 7.65<br />
Jan- 1-10 9.38 25.85 25.85 6.20 6.20 18.31<br />
77 11-20 8.92 24.57 24.57 5.90 5.90<br />
21-31 8.54 23.52 23.52 6.21 6.21<br />
Feb- 1-10 15.73 43.32 43.32 10.40 10.40 25.38<br />
77 11-20 15.32 42.21 42.21 10.13 10.13<br />
21-28 9.18 25.29 25.29 4.86 4.86<br />
Mar- 1-10 8.69 23.93 23.93 5.74 5.74 22.31<br />
77 11-20 12.40 34.16 34.16 8.20 8.20<br />
21-31 11.51 31.71 31.71 8.37 8.37<br />
Apr- 1-10 16.69 45.98 45.98 11.04 11.04 32.40<br />
77 11-20 15.66 43.15 43.15 10.36 10.36<br />
21-30 16.65 45.85 45.85 11.01 11.01<br />
May- 1-10 18.20 50.14 50.14 12.03 12.03 50.19<br />
77 11-20 22.48 61.92 61.92 14.86 14.86<br />
21-31 32.03 88.24 88.24 23.29 23.29<br />
838.70 781.39 #REF!<br />
NOTE : The energy is calculated taking into consideration 95% machine availability
TABLE -7.4<br />
70<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
POWER GENERATION IN 905DEPENDEBLE YEAR (1976-77)<br />
PERIOD INFLOW UNRESTR UNRESTR RESTRIC 95% m/c<br />
10 1-10 48.13 132.58 31.82 31.82 31.82<br />
Jun-76 10 11-20 93.93 258.74 62.10 48.00 45.60<br />
10 21-30 68.15 187.74 45.06 45.06 45.06<br />
10 1-10 87.13 240.01 57.60 48.00 45.60<br />
Jul-76 10 11-20 83.03 228.72 54.89 48.00 45.60<br />
11 21-31 83.03 228.72 60.38 52.80 50.16<br />
10 1-10 73.67 202.93 48.70 48.00 45.60<br />
Aug-76 10 11-20 80.31 221.22 53.09 48.00 45.60<br />
11 21-31 85.85 236.49 62.43 52.80 50.16<br />
10 1-10 78.21 215.44 51.71 48.00 45.60<br />
Sep-76 10 11-20 45.10 124.25 29.82 29.82 29.82<br />
10 21-30 32.93 90.71 21.77 21.77 21.77<br />
10 1-10 27.90 76.86 18.45 18.45 18.45<br />
Oct-76 10 11-20 22.04 60.71 14.57 14.57 14.57<br />
11 21-31 22.25 61.28 16.18 16.18 16.18<br />
10 1-10 22.12 60.94 14.63 14.63 14.63<br />
Nov-76 10 11-20 18.32 50.46 12.11 12.11 12.11<br />
10 21-30 16.38 45.11 10.83 10.83 10.83<br />
10 1-10 13.31 36.67 8.80 8.80 8.80<br />
Dec-76 10 11-20 11.39 31.36 7.53 7.53 7.53<br />
11 21-31 10.52 28.98 7.65 7.65 7.65<br />
10 1-10 9.38 25.85 6.20 6.20 6.20<br />
Jan-77 10 11-20 8.92 24.57 5.90 5.90 5.90<br />
11 21-31 8.54 23.52 6.21 6.21 6.21<br />
10 1-10 15.73 43.32 10.40 10.40 10.40<br />
Feb-77 10 11-20 15.32 42.21 10.13 10.13 10.13<br />
8 21-28 9.18 25.29 4.86 4.86 4.86<br />
10 1-10 8.69 23.93 5.74 5.74 5.74<br />
Mar-77 10 11-20 12.40 34.16 8.20 8.20 8.20<br />
11 21-31 11.51 31.71 8.37 8.37 8.37<br />
10 1-10 16.69 45.98 11.04 11.04 11.04<br />
Apr-77 10 11-20 15.66 43.15 10.36 10.36 10.36<br />
10 21-30 16.65 45.85 11.01 11.01 11.01<br />
10 1-10 18.20 50.14 12.03 12.03 12.03<br />
May-77 10 11-20 22.48 61.92 14.86 14.86 14.86<br />
11 21-31 32.03 88.24 23.29 23.29 23.29<br />
838.70 781.39 761.71<br />
Restricted Energy generated in 90% dependable year with 95% machine availability with installed capacity <strong>of</strong> 200<br />
MW = 761.71MU (say)<br />
Energy available at Bus – Bar after allowing auxiliary consumptions <strong>of</strong> 0.7% and transformer losses <strong>of</strong> 0.5% = 752.6<br />
MU
TABLE 7.5<br />
71<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
POWER POTENTIAL IN 90% DEPENDABLE YEAR WITH 95% m/c AVAILABILITY<br />
1976-1977<br />
Net Head Restricted MW 200 Overall Efficiency 90%<br />
Period Inflow Head <strong>Power</strong> Unrestricted <strong>Power</strong> Energy Energy Energy during<br />
1-10 48.13 312.0 132.58 31.82 132.58 31.82 0.00 31.82<br />
Jun-76<br />
Jul-76<br />
Aug-76<br />
Sep-76<br />
Oct-76<br />
Nov-76<br />
Dec-76<br />
Jan-77<br />
Feb-77<br />
Mar-77<br />
Apr-77<br />
May-77<br />
11-20 93.93 312.0 258.74 62.10 200.00 48.00 48.00 0.00<br />
21-30 68.15 312.0 187.74 45.06 187.74 45.06 45.06 0.00<br />
1-10 87.13 312.0 240.01 57.60 200.00 48.00 48.00 0.00<br />
11-20 83.03 312.0 228.72 54.89 200.00 48.00 48.00 0.00<br />
21-31 83.03 312.0 228.72 60.38 200.00 52.80 52.80 0.00<br />
1-10 73.67 312.0 202.93 48.70 200.00 48.00 48.00 0.00<br />
11-20 80.31 312.0 221.22 53.09 200.00 48.00 48.00 0.00<br />
21-31 85.85 312.0 236.49 62.43 200.00 52.80 52.80 0.00<br />
1-10 78.21 312.0 215.44 51.71 200.00 48.00 48.00 0.00<br />
11-20 45.10 312.0 124.25 29.82 124.25 29.82 0.00 29.82<br />
21-30 32.93 312.0 90.71 21.77 90.71 21.77 0.00 21.77<br />
1-10 27.90 312.0 76.86 18.45 76.86 18.45 0.00 18.45<br />
11-20 22.04 312.0 60.71 14.57 60.71 14.57 0.00 14.57<br />
21-31 22.25 312.0 61.28 16.18 61.28 16.18 0.00 16.18<br />
1-10 22.12 312.0 60.94 14.63 60.94 14.63 0.00 14.63<br />
11-20 18.32 312.0 50.46 12.11 50.46 12.11 0.00 12.11<br />
21-30 16.38 312.0 45.11 10.83 45.11 10.83 0.00 10.83<br />
1-10 13.31 312.0 36.67 8.80 36.67 8.80 0.00 8.80<br />
11-20 11.39 312.0 31.36 7.53 31.36 7.53 0.00 7.53<br />
21-31 10.52 312.0 28.98 7.65 28.98 7.65 0.00 7.65<br />
1-10 9.38 312.0 25.85 6.20 25.85 6.20 0.00 6.20<br />
11-20 8.92 312.0 24.57 5.90 24.57 5.90 0.00 5.90<br />
21-31 8.54 312.0 23.52 6.21 23.52 6.21 0.00 6.21<br />
1-10 15.73 312.0 43.32 10.40 43.32 10.40 0.00 10.40<br />
11-20 15.32 312.0 42.21 10.13 42.21 10.13 0.00 10.13<br />
21-28 9.18 312.0 25.29 4.86 25.29 4.86 0.00 4.86<br />
1-10 8.69 312.0 23.93 5.74 23.93 5.74 0.00 5.74<br />
11-20 12.40 312.0 34.16 8.20 34.16 8.20 0.00 8.20<br />
21-31 11.51 312.0 31.71 8.37 31.71 8.37 0.00 8.37<br />
1-10 16.69 312.0 45.98 11.04 45.98 11.04 0.00 11.04<br />
11-20 15.66 312.0 43.15 10.36 43.15 10.36 0.00 10.36<br />
21-30 16.65 312.0 45.85 11.01 45.85 11.01 0.00 11.01<br />
1-10 18.20 312.0 50.14 12.03 50.14 12.03 0.00 12.03<br />
11-20 22.48 312.0 61.92 14.86 61.92 14.86 0.00 14.86<br />
21-31 32.03 312.0 88.24 23.29 88.24 23.29 0.00 23.29<br />
Energy obtained on 95% machine availability 781.39 438.66 342.73<br />
LOAD FACTOR 44.600 99.334 26.154
72<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)
S.<br />
No.<br />
1<br />
2<br />
3<br />
4<br />
5<br />
6<br />
7<br />
8<br />
9<br />
10<br />
11<br />
TABLE 7.6<br />
72<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
AVAILABILITY OF UNITS IN KWH/KW FOR INCREMENTAL INSTALLATION IN 90%<br />
DEPENDABLE YEAR<br />
1976-1977<br />
Design Discharge 72.60<br />
Net Head 312.00<br />
Overall<br />
Efficiency<br />
90%<br />
Installed<br />
Capacity MW<br />
Annual<br />
Energy<br />
MU<br />
Load<br />
Factor %<br />
80 491.39 70.12%<br />
100 549.89 62.77%<br />
120 603.65 57.42%<br />
140 651.85 53.15%<br />
160 696.01 49.66%<br />
180 740.17 46.94%<br />
200 781.39 44.60%<br />
220 815.56 42.32%<br />
240 834.20 39.68%<br />
260 838.70 36.82%<br />
280 838.70 34.19%<br />
Incremental<br />
Energy MU<br />
Incremental<br />
Energy<br />
Kwh/Kw<br />
Load Factor<br />
For Additional<br />
Capacity %<br />
58.50 2925.19 33.39%<br />
53.76 2688.00 30.68%<br />
48.20 2409.86 27.51%<br />
44.16 2208.00 25.21%<br />
44.16 2208.00 25.21%<br />
41.22 2060.91 23.53%<br />
34.17 1708.53 19.50%<br />
18.64 932.00 10.64%<br />
4.50 225.00 2.57%<br />
0.00 0.00 0.00%
INCREMENTAL∆MU/∆MW<br />
3.00<br />
2.50<br />
2.00<br />
1.50<br />
1.00<br />
0.50<br />
0.00<br />
PANAN H E PROJECT<br />
INCREMENTAL BENEFIT FOR 90% DEPENDABLE YEAR(1976-1977)<br />
2.93<br />
2.69<br />
2.41<br />
2.21 2.21<br />
73<br />
2.06<br />
1.71<br />
0.93<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
40 60 80 100 120 140 160 180 200 220 240 260 280 300<br />
CAPACITY ( MW)<br />
0.23<br />
0.00
TABLE 7.7(A)<br />
1976-1977<br />
PERIOD FLOW UNRISTRICTED ENERGY<br />
MONTH CUMECS MU<br />
JUNE 1-10 48.13 31.82<br />
11-20 93.93 62.10<br />
21-30 68.15 45.06<br />
JULY 1-10 87.13 57.60<br />
11-20 83.03 54.89<br />
21-31 83.03 60.38<br />
AUGUST 1-10 73.67 48.70<br />
11-20 80.31 53.09<br />
21-31 85.85 62.43<br />
SEPTEMBER 1-10 78.21 51.71<br />
11-20 45.10 29.82<br />
21-30 32.93 21.77<br />
OCTOBER 1-10 27.90 18.45<br />
11-20 22.04 14.57<br />
21-31 22.25 16.18<br />
NOVEMBER 1-10 22.12 14.63<br />
11-20 18.32 12.11<br />
21-30 16.38 10.83<br />
DECEMBER 1-10 13.31 8.80<br />
11-20 11.39 7.53<br />
21-31 10.52 7.65<br />
JANUARY 1-10 9.38 6.20<br />
11-20 8.92 5.90<br />
21-31 8.54 6.21<br />
FEBRUARY 1-10 15.73 10.40<br />
11-20 15.32 10.13<br />
21-28 9.18 4.86<br />
MARCH 1-10 8.69 5.74<br />
11-20 12.40 8.20<br />
21-31 11.51 8.37<br />
APRIL 1-10 16.69 11.04<br />
11-20 15.66 10.36<br />
21-30 16.65 11.01<br />
MAY 1-10 18.20 12.03<br />
11-20 22.48 14.86<br />
21-31 32.03 23.29<br />
74
TABLE 7.7 (B)<br />
1977-1978<br />
PERIOD FLOW UNRISTRICTED ENERGY<br />
MONTH CUMECS MU<br />
JUNE 1-10 51.76 34.22<br />
11-20 91.83 60.71<br />
21-30 66.78 44.15<br />
JULY 1-10 76.32 50.46<br />
11-20 89.80 59.37<br />
21-31 107.55 78.21<br />
AUGUST 1-10 87.83 58.06<br />
11-20 73.90 48.86<br />
21-31 86.29 62.76<br />
SEPTEMBER 1-10 60.26 39.84<br />
11-20 49.28 32.58<br />
21-30 41.09 27.16<br />
OCTOBER 1-10 50.15 33.15<br />
11-20 31.62 20.91<br />
21-31 25.26 18.37<br />
NOVEMBER 1-10 26.19 17.32<br />
11-20 23.89 15.80<br />
21-30 18.04 11.93<br />
DECEMBER 1-10 16.31 10.78<br />
11-20 17.23 11.39<br />
21-31 19.49 14.18<br />
JANUARY 1-10 13.41 8.86<br />
11-20 12.01 7.94<br />
21-31 12.27 8.92<br />
FEBRUARY 1-10 12.41 8.21<br />
11-20 12.15 8.03<br />
21-28 11.17 5.91<br />
MARCH 1-10 11.31 7.48<br />
11-20 12.09 7.99<br />
21-31 13.41 9.75<br />
APRIL 1-10 16.11 10.65<br />
11-20 20.63 13.64<br />
21-30 24.44 16.16<br />
MAY 1-10 27.85 18.41<br />
11-20 57.09 37.74<br />
21-31 66.65 48.47<br />
75
TABLE 7.7(C)<br />
1978-1979<br />
PERIOD FLOW UNRISTRICTED ENERGY<br />
MONTH CUMECS MU<br />
JUNE 1-10 76.46 50.55<br />
11-20 80.23 53.04<br />
21-30 101.44 67.06<br />
JULY 1-10 89.06 58.88<br />
11-20 95.47 63.12<br />
21-31 92.13 67.00<br />
AUGUST 1-10 109.05 72.10<br />
11-20 92.15 60.92<br />
21-31 69.18 50.31<br />
SEPTEMBER 1-10 57.39 37.94<br />
11-20 74.73 49.40<br />
21-30 56.17 37.14<br />
OCTOBER 1-10 54.03 35.72<br />
11-20 42.13 27.86<br />
21-31 35.91 26.12<br />
NOVEMBER 1-10 28.77 19.02<br />
11-20 21.46 14.19<br />
21-30 21.12 13.97<br />
DECEMBER 1-10 20.37 13.46<br />
11-20 17.26 11.41<br />
21-31 15.50 11.27<br />
JANUARY 1-10 14.30 9.46<br />
11-20 13.20 8.72<br />
21-31 12.97 9.43<br />
FEBRUARY 1-10 11.81 7.81<br />
11-20 11.79 7.79<br />
21-28 12.82 6.78<br />
MARCH 1-10 13.16 8.70<br />
11-20 13.78 9.11<br />
21-31 16.96 12.33<br />
APRIL 1-10 25.04 16.55<br />
11-20 24.90 16.46<br />
21-30 31.24 20.65<br />
MAY 1-10 46.88 31.00<br />
11-20 59.76 39.51<br />
21-31 45.71 33.25<br />
76
TABLE 7.7 (D)<br />
1979-1980<br />
PERIOD FLOW UNRISTRICTED ENERGY<br />
MONTH CUMECS MU<br />
JUNE 1-10 54.47 36.01<br />
11-20 65.18 43.09<br />
21-30 93.46 61.79<br />
JULY 1-10 97.05 64.16<br />
11-20 92.84 61.38<br />
21-31 104.00 75.63<br />
AUGUST 1-10 96.11 63.54<br />
11-20 75.88 50.17<br />
21-31 80.48 58.53<br />
SEPTEMBER 1-10 79.16 52.34<br />
11-20 69.08 45.67<br />
21-30 50.67 33.50<br />
OCTOBER 1-10 84.45 55.83<br />
11-20 57.63 38.10<br />
21-31 43.22 31.43<br />
NOVEMBER 1-10 43.09 28.48<br />
11-20 35.09 23.20<br />
21-30 33.03 21.84<br />
DECEMBER 1-10 31.46 20.80<br />
11-20 25.91 17.13<br />
21-31 24.95 18.14<br />
JANUARY 1-10 23.51 15.54<br />
11-20 22.63 14.96<br />
21-31 22.43 16.31<br />
FEBRUARY 1-10 21.53 14.24<br />
11-20 22.56 14.92<br />
21-29 24.06 14.31<br />
MARCH 1-10 24.74 16.36<br />
11-20 25.37 16.77<br />
21-31 34.26 24.91<br />
APRIL 1-10 38.48 25.44<br />
11-20 49.36 32.63<br />
21-30 56.23 37.18<br />
MAY 1-10 53.63 35.45<br />
11-20 45.87 30.33<br />
21-31 48.89 35.56<br />
77
TABLE 7.7 (E)<br />
1980-1981<br />
PERIOD FLOW UNRISTRICTED ENERGY<br />
MONTH CUMECS MU<br />
JUNE 1-10 74.98 49.57<br />
11-20 99.79 65.97<br />
21-30 111.68 73.83<br />
JULY 1-10 118.19 78.13<br />
11-20 120.99 79.99<br />
21-31 126.76 92.19<br />
AUGUST 1-10 128.09 84.68<br />
11-20 140.66 93.00<br />
21-31 117.15 85.19<br />
SEPTEMBER 1-10 111.92 73.99<br />
11-20 87.73 58.00<br />
21-30 71.01 46.95<br />
OCTOBER 1-10 55.55 36.72<br />
11-20 47.73 31.56<br />
21-31 44.47 32.34<br />
NOVEMBER 1-10 37.57 24.84<br />
11-20 34.21 22.61<br />
21-30 31.49 20.82<br />
DECEMBER 1-10 29.25 19.34<br />
11-20 26.59 17.58<br />
21-31 24.15 17.56<br />
JANUARY 1-10 23.27 15.38<br />
11-20 21.81 14.42<br />
21-31 21.53 15.66<br />
FEBRUARY 1-10 20.02 13.23<br />
11-20 20.59 13.61<br />
21-28 24.90 13.17<br />
MARCH 1-10 24.62 16.28<br />
11-20 26.08 17.24<br />
21-31 30.79 22.39<br />
APRIL 1-10 30.82 20.38<br />
11-20 39.03 25.80<br />
21-30 45.99 30.40<br />
MAY 1-10 56.47 37.34<br />
11-20 60.99 40.32<br />
21-31 59.15 43.02<br />
78
TABLE 7.7 (F)<br />
1981-1982<br />
PERIOD FLOW UNRISTRICTED ENERGY<br />
MONTH CUMECS MU<br />
JUNE 1-10 65.12 43.05<br />
11-20 77.89 51.49<br />
21-30 105.73 69.90<br />
JULY 1-10 135.07 89.30<br />
11-20 115.83 76.57<br />
21-31 108.94 79.23<br />
AUGUST 1-10 106.24 70.23<br />
11-20 112.11 74.12<br />
21-31 108.98 79.25<br />
SEPTEMBER 1-10 104.32 68.97<br />
11-20 89.40 59.11<br />
21-30 71.26 47.11<br />
OCTOBER 1-10 65.33 43.19<br />
11-20 60.47 39.98<br />
21-31 52.85 38.44<br />
NOVEMBER 1-10 45.04 29.78<br />
11-20 35.94 23.76<br />
21-30 29.77 19.68<br />
DECEMBER 1-10 27.32 18.06<br />
11-20 24.57 16.25<br />
21-31 19.26 14.01<br />
JANUARY 1-10 17.69 11.70<br />
11-20 19.69 13.02<br />
21-31 19.42 14.12<br />
FEBRUARY 1-10 19.25 12.73<br />
11-20 20.00 13.22<br />
21-28 19.44 12.85<br />
MARCH 1-10 20.25 13.39<br />
11-20 22.67 14.99<br />
21-31 27.00 19.64<br />
APRIL 1-10 33.93 22.43<br />
11-20 33.88 22.40<br />
21-30 37.58 24.84<br />
MAY 1-10 47.11 31.14<br />
11-20 52.91 34.98<br />
21-31 51.40 37.38<br />
79
TABLE 7.7 (G)<br />
1982-1983<br />
PERIOD FLOW<br />
UNRISTRICTED<br />
ENERGY<br />
MONTH CUMECS MU<br />
JUNE 1-10 90.75 60.00<br />
11-20 99.95 66.08<br />
21-30 110.48 73.04<br />
JULY 1-10 97.01 64.14<br />
11-20 108.68 71.85<br />
21-31 128.20 93.23<br />
AUGUST 1-10 86.15 56.95<br />
11-20 81.55 53.92<br />
21-31 95.71 69.60<br />
SEPTEMBER 1-10 73.62 48.67<br />
11-20 106.47 70.39<br />
21-30 69.86 46.19<br />
OCTOBER 1-10 49.46 32.70<br />
11-20 41.54 27.46<br />
21-31 40.00 29.09<br />
NOVEMBER 1-10 31.33 20.71<br />
11-20 27.33 18.07<br />
21-30 26.46 17.49<br />
DECEMBER 1-10 23.38 15.46<br />
11-20 21.56 14.25<br />
21-31 20.41 14.84<br />
JANUARY 1-10 20.24 13.38<br />
11-20 18.02 11.92<br />
21-31 12.63 9.19<br />
FEBRUARY 1-10 11.49 7.60<br />
11-20 11.42 7.55<br />
21-28 15.89 8.40<br />
MARCH 1-10 17.08 11.29<br />
11-20 21.89 14.47<br />
21-31 19.74 14.36<br />
APRIL 1-10 29.05 19.21<br />
11-20 23.75 15.70<br />
21-30 29.73 19.66<br />
MAY 1-10 47.84 31.63<br />
11-20 57.33 37.90<br />
21-31 76.29 55.48<br />
80
TABLE 7.7 (H)<br />
1983-1984<br />
PERIOD FLOW UNRISTRICTED ENERGY<br />
MONTH CUMECS MU<br />
JUNE 1-10 95.92 63.42<br />
11-20 93.09 61.55<br />
21-30 129.92 85.89<br />
JULY 1-10 148.79 98.37<br />
11-20 126.58 83.68<br />
21-31 125.58 91.33<br />
AUGUST 1-10 102.79 67.96<br />
11-20 109.00 72.06<br />
21-31 127.34 92.60<br />
SEPTEMBER 1-10 102.35 67.67<br />
11-20 115.08 76.08<br />
21-30 132.74 87.76<br />
OCTOBER 1-10 93.33 61.70<br />
11-20 92.01 60.83<br />
21-31 62.72 45.61<br />
NOVEMBER 1-10 51.28 33.90<br />
11-20 47.11 31.14<br />
21-30 38.80 25.65<br />
DECEMBER 1-10 32.37 21.40<br />
11-20 30.35 20.06<br />
21-31 27.20 19.78<br />
JANUARY 1-10 24.27 16.05<br />
11-20 23.89 15.79<br />
21-31 21.26 15.46<br />
FEBRUARY 1-10 20.48 13.54<br />
11-20 21.27 14.06<br />
21-29 20.43 12.16<br />
MARCH 1-10 45.11 29.82<br />
11-20 50.41 33.33<br />
21-31 49.54 32.75<br />
APRIL 1-10 52.07 34.42<br />
11-20 55.51 36.70<br />
21-30 55.52 36.71<br />
MAY 1-10 63.01 41.66<br />
11-20 92.09 60.88<br />
21-31 130.83 95.14<br />
81
TABLE 7.7 (I)<br />
1984-1985<br />
PERIOD FLOW UNRISTRICTED ENERGY<br />
MONTH CUMECS MU<br />
JUNE 1-10 135.95 89.88<br />
11-20 163.48 108.08<br />
21-30 146.81 97.06<br />
JULY 1-10 168.98 111.71<br />
11-20 169.53 112.08<br />
21-31 179.22 130.34<br />
AUGUST 1-10 161.63 106.85<br />
11-20 162.06 107.14<br />
21-31 169.66 123.38<br />
SEPTEMBER 1-10 174.74 115.52<br />
11-20 166.76 110.24<br />
21-30 132.28 87.45<br />
OCTOBER 1-10 111.42 73.66<br />
11-20 141.33 93.44<br />
21-31 108.88 79.18<br />
NOVEMBER 1-10 81.14 53.64<br />
11-20 70.12 46.36<br />
21-30 62.32 41.20<br />
DECEMBER 1-10 39.95 26.41<br />
11-20 39.31 25.99<br />
21-31 39.46 28.70<br />
JANUARY 1-10 39.81 26.32<br />
11-20 37.81 25.00<br />
21-31 32.74 23.81<br />
FEBRUARY 1-10 35.77 23.65<br />
11-20 32.70 21.62<br />
21-28 39.58 20.93<br />
MARCH 1-10 50.28 33.24<br />
11-20 54.46 36.00<br />
21-31 50.71 36.88<br />
APRIL 1-10 61.04 40.35<br />
11-20 73.66 48.70<br />
21-30 86.99 57.51<br />
MAY 1-10 62.60 41.39<br />
11-20 72.65 48.03<br />
21-31 101.19 73.59<br />
82
TABLE 7.7 (J)<br />
1985-1986<br />
PERIOD FLOW UNRISTRICTED ENERGY<br />
MONTH CUMECS MU<br />
JUNE 1-10 64.93 42.93<br />
11-20 81.06 53.59<br />
21-30 229.69 151.85<br />
JULY 1-10 181.10 119.73<br />
11-20 236.32 156.24<br />
21-31 198.71 144.51<br />
AUGUST 1-10 160.58 106.16<br />
11-20 169.39 111.98<br />
21-31 207.38 150.81<br />
SEPTEMBER 1-10 84.58 55.92<br />
11-20 80.80 53.42<br />
21-30 67.70 44.76<br />
OCTOBER 1-10 58.20 38.48<br />
11-20 51.01 33.72<br />
21-31 42.03 30.57<br />
NOVEMBER 1-10 34.11 22.55<br />
11-20 29.65 19.60<br />
21-30 26.27 17.37<br />
DECEMBER 1-10 22.37 14.79<br />
11-20 20.24 13.38<br />
21-31 18.61 13.53<br />
JANUARY 1-10 17.65 11.67<br />
11-20 17.56 11.61<br />
21-31 16.62 12.08<br />
FEBRUARY 1-10 16.79 11.10<br />
11-20 17.28 11.42<br />
21-28 19.78 10.46<br />
MARCH 1-10 21.08 13.94<br />
11-20 22.95 15.17<br />
21-31 23.56 17.14<br />
APRIL 1-10 23.17 15.32<br />
11-20 29.96 19.81<br />
21-30 33.61 22.22<br />
MAY 1-10 31.50 20.82<br />
11-20 33.50 22.15<br />
21-31 35.30 25.67<br />
83
TABLE 7.7 (K)<br />
1986-1987<br />
PERIOD FLOW<br />
UNRISTRICTED<br />
ENERGY<br />
MONTH CUMECS MU<br />
JUNE 1-10 42.91 28.37<br />
11-20 72.78 48.11<br />
21-30 107.83 71.29<br />
JULY 1-10 93.39 61.74<br />
11-20 116.69 77.15<br />
21-31 104.96 76.33<br />
AUGUST 1-10 93.15 61.58<br />
11-20 80.07 52.94<br />
21-31 88.65 64.47<br />
SEPTEMBER 1-10 77.83 51.46<br />
11-20 96.67 63.91<br />
21-30 78.69 52.02<br />
OCTOBER 1-10 63.46 41.95<br />
11-20 47.46 31.37<br />
21-31 37.06 26.95<br />
NOVEMBER 1-10 34.07 22.52<br />
11-20 30.31 20.04<br />
21-30 26.18 17.31<br />
DECEMBER 1-10 23.43 15.49<br />
11-20 21.58 14.27<br />
21-31 15.91 11.57<br />
JANUARY 1-10 13.89 9.18<br />
11-20 13.08 8.65<br />
21-31 12.26 8.92<br />
FEBRUARY 1-10 11.63 7.69<br />
11-20 11.52 7.61<br />
21-28 12.64 6.68<br />
MARCH 1-10 11.80 7.80<br />
11-20 14.00 9.26<br />
21-31 17.58 11.63<br />
APRIL 1-10 32.07 21.20<br />
11-20 22.40 14.81<br />
21-30 29.61 19.57<br />
MAY 1-10 33.48 22.13<br />
11-20 37.23 24.62<br />
21-31 43.70 31.78<br />
84
TABLE 7.7 (L)<br />
1987-1988<br />
PERIOD FLOW<br />
UNRISTRICTED<br />
ENERGY<br />
MONTH CUMECS MU<br />
JUNE 1-10 72.49 47.92<br />
11-20 105.29 69.61<br />
21-30 88.36 58.42<br />
JULY 1-10 101.37 67.02<br />
11-20 96.91 64.07<br />
21-31 108.36 78.80<br />
AUGUST 1-10 102.60 67.83<br />
11-20 111.95 74.01<br />
21-31 74.82 54.41<br />
SEPTEMBER 1-10 134.61 88.99<br />
11-20 72.01 47.61<br />
21-30 98.76 65.29<br />
OCTOBER 1-10 61.32 40.54<br />
11-20 45.67 30.20<br />
21-31 39.06 28.40<br />
NOVEMBER 1-10 31.70 20.95<br />
11-20 19.34 12.79<br />
21-30 16.99 11.23<br />
DECEMBER 1-10 16.02 10.59<br />
11-20 14.66 9.69<br />
21-31 13.41 9.75<br />
JANUARY 1-10 13.08 8.65<br />
11-20 13.08 8.65<br />
21-31 12.92 9.40<br />
FEBRUARY 1-10 12.68 8.38<br />
11-20 13.28 8.78<br />
21-29 14.75 8.78<br />
MARCH 1-10 15.30 10.11<br />
11-20 22.66 14.98<br />
21-31 23.30 15.40<br />
APRIL 1-10 26.64 19.37<br />
11-20 30.09 19.89<br />
21-30 34.99 23.13<br />
MAY 1-10 35.78 23.66<br />
11-20 53.61 35.44<br />
21-31 71.04 51.66<br />
85
TABLE 7.7 (M)<br />
1988-1989<br />
PERIOD FLOW UNRISTRICTED ENERGY<br />
MONTH CUMECS MU<br />
JUNE 1-10 57.30 37.88<br />
11-20 82.91 54.81<br />
21-30 90.82 60.04<br />
JULY 1-10 141.13 93.31<br />
11-20 110.87 73.30<br />
21-31 122.19 88.86<br />
AUGUST 1-10 121.26 80.17<br />
11-20 111.31 73.59<br />
21-31 168.87 122.81<br />
SEPTEMBER 1-10 80.62 53.30<br />
11-20 54.38 35.95<br />
21-30 60.82 40.21<br />
OCTOBER 1-10 51.35 33.95<br />
11-20 34.07 22.52<br />
21-31 27.41 19.93<br />
NOVEMBER 1-10 22.60 14.94<br />
11-20 20.40 13.49<br />
21-30 19.01 12.57<br />
DECEMBER 1-10 18.05 11.93<br />
11-20 17.12 11.32<br />
21-31 16.20 11.78<br />
JANUARY 1-10 9.92 6.56<br />
11-20 9.65 6.38<br />
21-31 9.56 6.95<br />
FEBRUARY 1-10 10.64 7.03<br />
11-20 9.72 6.42<br />
21-28 10.35 5.47<br />
MARCH 1-10 11.76 7.77<br />
11-20 11.99 7.93<br />
21-31 12.32 8.96<br />
APRIL 1-10 12.81 8.47<br />
11-20 15.34 10.14<br />
21-30 18.39 12.16<br />
MAY 1-10 32.30 21.36<br />
11-20 33.36 22.06<br />
21-31 81.29 59.12<br />
86
TABLE 7.7(N)<br />
1989-1990<br />
PERIOD FLOW UNRISTRICTED ENERGY<br />
MONTH CUMECS MU<br />
JUNE 1-10 72.18 47.72<br />
11-20 119.57 79.05<br />
21-30 126.45 83.60<br />
JULY 1-10 128.75 85.12<br />
11-20 126.65 83.73<br />
21-31 117.89 85.73<br />
AUGUST 1-10 102.30 67.63<br />
11-20 80.26 53.06<br />
21-31 78.74 57.26<br />
SEPTEMBER 1-10 76.32 50.46<br />
11-20 69.13 45.70<br />
21-30 68.68 45.41<br />
OCTOBER 1-10 54.25 35.87<br />
11-20 46.17 30.52<br />
21-31 37.55 27.31<br />
NOVEMBER 1-10 23.36 15.44<br />
11-20 18.96 12.53<br />
21-30 17.24 11.40<br />
DECEMBER 1-10 15.04 9.94<br />
11-20 13.04 8.62<br />
21-31 11.42 8.31<br />
JANUARY 1-10 10.41 6.88<br />
11-20 9.65 6.38<br />
21-31 8.74 6.36<br />
FEBRUARY 1-10 8.60 5.68<br />
11-20 8.08 5.34<br />
21-28 7.80 4.13<br />
MARCH 1-10 7.13 4.71<br />
11-20 5.82 3.85<br />
21-31 5.92 4.31<br />
APRIL 1-10 6.12 4.05<br />
11-20 10.11 6.68<br />
21-30 12.52 8.28<br />
MAY 1-10 18.48 12.22<br />
11-20 32.57 21.53<br />
21-31 37.46 27.24<br />
87
TABLE 7.7(O)<br />
1990-1991<br />
PERIOD FLOW UNRISTRICTED ENERGY<br />
MONTH CUMECS MU<br />
JUNE 1-10 79.11 52.30<br />
11-20 77.28 51.09<br />
21-30 90.37 59.74<br />
JULY 1-10 99.60 65.85<br />
11-20 126.97 83.94<br />
21-31 108.67 79.03<br />
AUGUST 1-10 92.56 61.19<br />
11-20 94.03 62.17<br />
21-31 83.45 60.68<br />
SEPTEMBER 1-10 80.08 52.94<br />
11-20 76.69 50.70<br />
21-30 53.41 35.31<br />
OCTOBER 1-10 44.75 29.59<br />
11-20 45.59 30.14<br />
21-31 37.50 27.27<br />
NOVEMBER 1-10 22.95 15.18<br />
11-20 17.15 11.34<br />
21-30 14.32 9.47<br />
DECEMBER 1-10 13.12 8.67<br />
11-20 10.82 7.15<br />
21-31 9.33 6.79<br />
JANUARY 1-10 9.45 6.25<br />
11-20 9.27 6.13<br />
21-31 9.17 6.67<br />
FEBRUARY 1-10 8.89 5.87<br />
11-20 8.45 5.58<br />
21-28 8.54 4.51<br />
MARCH 1-10 9.11 6.02<br />
11-20 10.39 6.87<br />
21-31 10.95 7.97<br />
APRIL 1-10 28.74 19.00<br />
11-20 16.39 10.83<br />
21-30 17.34 11.47<br />
MAY 1-10 29.11 19.25<br />
11-20 35.47 23.45<br />
21-31 39.24 28.54<br />
88
TABLE 7.7 (P)<br />
1991-1992<br />
PERIOD FLOW<br />
UNRISTRICTED<br />
ENERGY<br />
MONTH CUMECS MU<br />
JUNE 1-10 42.00 27.77<br />
11-20 66.32 43.84<br />
21-30 60.99 40.32<br />
JULY 1-10 69.65 46.05<br />
11-20 67.86 44.86<br />
21-31 73.96 53.79<br />
AUGUST 1-10 84.81 56.07<br />
11-20 97.71 64.60<br />
21-31 80.74 58.72<br />
SEPTEMBER 1-10 81.34 53.77<br />
11-20 85.93 56.81<br />
21-30 66.56 44.01<br />
OCTOBER 1-10 53.14 35.13<br />
11-20 42.14 27.86<br />
21-31 34.58 25.15<br />
NOVEMBER 1-10 28.66 18.95<br />
11-20 25.34 16.75<br />
21-30 19.33 12.78<br />
DECEMBER 1-10 16.25 10.74<br />
11-20 12.46 8.24<br />
21-31 10.96 7.97<br />
JANUARY 1-10 9.98 6.60<br />
11-20 8.28 5.48<br />
21-31 8.46 6.15<br />
FEBRUARY 1-10 8.94 5.91<br />
11-20 8.62 5.70<br />
21-29 8.27 4.92<br />
MARCH 1-10 8.86 5.86<br />
11-20 8.92 5.90<br />
21-31 9.17 6.67<br />
APRIL 1-10 10.83 7.16<br />
11-20 15.22 10.06<br />
21-30 13.91 9.20<br />
MAY 1-10 13.64 9.02<br />
11-20 15.88 10.50<br />
21-31 15.96 11.61<br />
89
TABLE 7.7 (Q)<br />
1992-1993<br />
PERIOD FLOW<br />
UNRISTRICTED<br />
ENERGY<br />
MONTH CUMECS MU<br />
JUNE 1-10 17.63 11.65<br />
11-20 25.13 16.62<br />
21-30 48.70 32.20<br />
JULY 1-10 41.84 27.66<br />
11-20 42.34 27.99<br />
21-31 48.10 34.98<br />
AUGUST 1-10 52.64 34.80<br />
11-20 52.85 34.94<br />
21-31 57.46 41.79<br />
SEPTEMBER 1-10 50.40 33.32<br />
11-20 49.61 32.80<br />
21-30 41.06 27.15<br />
OCTOBER 1-10 31.01 20.50<br />
11-20 22.24 14.71<br />
21-31 18.93 13.76<br />
NOVEMBER 1-10 13.98 9.24<br />
11-20 12.42 8.21<br />
21-30 11.32 7.48<br />
DECEMBER 1-10 11.19 7.40<br />
11-20 9.69 6.41<br />
21-31 8.95 6.51<br />
JANUARY 1-10 9.10 6.01<br />
11-20 9.19 6.07<br />
21-31 8.62 6.27<br />
FEBRUARY 1-10 8.34 5.52<br />
11-20 8.86 5.86<br />
21-28 8.56 4.53<br />
MARCH 1-10 13.99 9.25<br />
11-20 13.96 9.23<br />
21-31 14.62 10.63<br />
APRIL 1-10 14.84 9.81<br />
11-20 16.23 10.73<br />
21-30 19.43 12.85<br />
MAY 1-10 24.66 16.30<br />
11-20 22.20 14.68<br />
21-31 22.48 16.35<br />
90
TABLE 7.7 (R)<br />
1993-1994<br />
PERIOD FLOW<br />
UNRESTRICTED<br />
ENERGY<br />
MONTH CUMECS MU<br />
JUNE 1-10 28.86 19.08<br />
11-20 36.87 24.37<br />
21-30 47.43 31.36<br />
JULY 1-10 99.34 65.67<br />
11-20 99.34 65.67<br />
21-31 116.49 84.72<br />
AUGUST 1-10 130.65 86.38<br />
11-20 123.86 81.89<br />
21-31 118.63 86.27<br />
SEPTEMBER 1-10 124.81 82.51<br />
11-20 105.12 69.50<br />
21-30 99.39 65.71<br />
OCTOBER 1-10 88.33 58.39<br />
11-20 65.54 43.33<br />
21-31 56.17 40.85<br />
NOVEMBER 1-10 46.60 30.81<br />
11-20 41.08 27.16<br />
21-30 37.66 24.90<br />
DECEMBER 1-10 36.75 24.29<br />
11-20 33.77 22.32<br />
21-31 27.74 20.18<br />
JANUARY 1-10 26.13 17.28<br />
11-20 24.34 16.09<br />
21-31 24.58 17.88<br />
FEBRUARY 1-10 24.25 16.03<br />
11-20 23.19 15.33<br />
21-28 24.87 13.15<br />
MARCH 1-10 22.90 15.14<br />
11-20 20.67 13.66<br />
21-31 26.14 19.01<br />
APRIL 1-10 25.39 16.78<br />
11-20 31.76 21.00<br />
21-30 29.14 19.27<br />
MAY 1-10 32.66 21.59<br />
11-20 33.67 22.26<br />
21-31 41.41 30.11<br />
91
TABLE 7.7 (S)<br />
1994-1995<br />
PERIOD FLOW<br />
UNRISTRICTED<br />
ENERGY<br />
MONTH CUMECS MU<br />
JUNE 1-10 59.78 39.52<br />
11-20 79.15 52.32<br />
21-30 91.87 60.74<br />
JULY 1-10 78.56 51.94<br />
11-20 83.30 55.07<br />
21-31 84.89 61.73<br />
AUGUST 1-10 78.02 51.58<br />
11-20 76.20 50.38<br />
21-31 81.95 59.59<br />
SEPTEMBER 1-10 69.52 45.96<br />
11-20 69.62 46.02<br />
21-30 60.15 39.77<br />
OCTOBER 1-10 47.05 31.10<br />
11-20 41.83 27.65<br />
21-31 38.30 27.85<br />
NOVEMBER 1-10 31.52 20.84<br />
11-20 25.98 17.18<br />
21-30 21.71 14.36<br />
DECEMBER 1-10 20.95 13.85<br />
11-20 19.16 12.66<br />
21-31 18.12 13.18<br />
JANUARY 1-10 17.17 11.35<br />
11-20 17.36 11.48<br />
21-31 17.15 12.47<br />
FEBRUARY 1-10 17.01 11.24<br />
11-20 16.95 11.21<br />
21-28 17.04 11.27<br />
MARCH 1-10 15.49 10.24<br />
11-20 14.69 9.71<br />
21-31 20.24 14.72<br />
APRIL 1-10 19.79 13.08<br />
11-20 24.52 16.21<br />
21-30 35.79 23.66<br />
MAY 1-10 52.20 34.51<br />
11-20 80.59 53.28<br />
21-31 77.87 56.63<br />
92
TABLE 7.7 (T)<br />
1995-1996<br />
PERIOD FLOW<br />
UNRISTRICTE<br />
D ENERGY<br />
MONTH CUMECS MU<br />
JUNE 1-10 90.43 59.78<br />
11-20 96.71 63.94<br />
21-30 97.96 64.77<br />
JULY 1-10 124.33 82.20<br />
11-20 104.29 68.95<br />
21-31 80.17 58.30<br />
AUGUST 1-10 87.59 57.90<br />
11-20 88.37 58.43<br />
21-31 78.51 57.09<br />
SEPTEMBER 1-10 70.83 46.83<br />
11-20 63.43 41.93<br />
21-30 61.02 40.34<br />
OCTOBER 1-10 45.07 29.80<br />
11-20 43.88 29.01<br />
21-31 34.28 24.93<br />
NOVEMBER 1-10 22.29 14.74<br />
11-20 25.46 16.83<br />
21-30 25.60 16.92<br />
DECEMBER 1-10 19.16 12.67<br />
11-20 17.06 11.28<br />
21-31 15.84 11.52<br />
JANUARY 1-10 13.65 9.02<br />
11-20 13.57 8.97<br />
21-31 14.34 10.43<br />
FEBRUARY 1-10 14.85 9.82<br />
11-20 13.23 8.74<br />
21-29 14.48 8.62<br />
MARCH 1-10 14.70 9.72<br />
11-20 17.02 11.25<br />
21-31 18.14 13.19<br />
APRIL 1-10 16.69 11.04<br />
11-20 16.21 10.71<br />
21-30 36.06 23.84<br />
MAY 1-10 43.95 29.06<br />
11-20 38.53 25.48<br />
21-31 53.33 38.78<br />
93
TABLE 7.7 (U)<br />
1996-1997<br />
PERIOD FLOW UNRISTRICTED ENERGY<br />
MONTH CUMECS MU<br />
JUNE 1-10 50.02 33.07<br />
11-20 42.35 28.00<br />
21-30 75.64 50.01<br />
JULY 1-10 84.05 55.57<br />
11-20 90.50 59.83<br />
21-31 80.56 58.58<br />
AUGUST 1-10 77.01 50.91<br />
11-20 71.81 47.48<br />
21-31 72.38 52.64<br />
SEPTEMBER 1-10 72.26 47.77<br />
11-20 68.95 45.58<br />
21-30 59.97 39.64<br />
OCTOBER 1-10 52.72 34.85<br />
11-20 48.32 31.94<br />
21-31 43.19 31.41<br />
NOVEMBER 1-10 39.29 25.98<br />
11-20 36.53 24.15<br />
21-30 32.49 21.48<br />
DECEMBER 1-10 22.37 14.79<br />
11-20 20.24 13.38<br />
21-31 18.61 13.53<br />
JANUARY 1-10 21.05 13.92<br />
11-20 20.03 13.24<br />
21-31 20.36 14.81<br />
FEBRUARY 1-10 20.32 13.43<br />
11-20 20.25 13.39<br />
21-28 20.01 10.59<br />
MARCH 1-10 20.49 13.55<br />
11-20 21.50 14.22<br />
21-31 23.45 17.06<br />
APRIL 1-10 22.50 14.88<br />
11-20 22.37 14.79<br />
21-30 23.03 15.22<br />
MAY 1-10 26.86 17.76<br />
11-20 30.89 20.42<br />
21-31 31.91 23.21<br />
94
CHAPTER – VIII<br />
POWER EVACUATION<br />
95<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
8.1 GENERAL<br />
This chapter contains data regarding existing <strong>Power</strong> network <strong>of</strong> the Eastern region and<br />
the power evacuation arrangement required, consequent upon power generation at the<br />
proposed <strong>Panan</strong> Hydro Electric Project.<br />
8.2 APPRAISAL OF EXISTING POWER EVACUATION<br />
FACILITIES<br />
The nearest pooling point being proposed is a new 400/220 KV substation at<br />
Siliguri(New Jalpaiguri) where power from Tala H.E.P and Teesta stages is expected to<br />
be pooled. Adjoining to this is also a new substation <strong>of</strong> 220/132 KV level being created<br />
by WBSEB. Hence power evacuation with respect to development <strong>of</strong> national grid and<br />
consumption by the state can be considered as assured for the present project. Underlying<br />
220/132 KV 200 MVA PGCIL and 132 KV network in the entire area is available to<br />
cater for local loads.<br />
8.3 PROPOSED EVACUATION ARRANGEMENT TO THE NEAREST<br />
FACILITY<br />
After study <strong>of</strong> existing power evacuation facilities, it emerges that evacuation <strong>of</strong> power<br />
generated at <strong>Panan</strong> Hydro Electric Project can be done through one 220 kV double circuit<br />
line to be connected at the pooling point which has been assumed to come up about 2km<br />
from Teesta III H.E.Project. The length <strong>of</strong> this 220 kV double circuit line would be<br />
approximately 5km.
CHAPTER-IX<br />
ENVIRONMENTAL ASPECTS<br />
96<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
9.1 INTRODUCTION<br />
9.1.1 General<br />
Sikkim has immense potential <strong>of</strong> hydropower generation from the abundance <strong>of</strong> snow<br />
and monsoon fed rivers. The proposed <strong>Panan</strong> hydroelectric project envisages construction<br />
<strong>of</strong> a 55 m high concrete gravity dam (above the deepest foundation level) with a central<br />
spillway on river Talung chu/ Rangyong, 1 km u/s <strong>of</strong> village Lingza in the North Sikkim<br />
district (Fig. 9.1). The water will be conveyed to the underground powerhouse on the<br />
right bank approximately 100 m u/s <strong>of</strong> confluence <strong>of</strong> Tolung and Rahi chu through a 8.5<br />
km long tunnel and the tailrace will be at riverbed elevation <strong>of</strong> +770 m which would<br />
utilise a net head <strong>of</strong> 312 m. The firm power generation will be about 28 MW and would<br />
have an optimum power generation capacity <strong>of</strong> about 200 MW.<br />
9.1.2 Location<br />
Sikkim is a small hilly State in the Eastern Himalayas, extending approximately 114 kms<br />
from north to south and 64 kms from east to west, surrounded by vast stretches <strong>of</strong> Tibetan<br />
Plateau in the North, Chumbi Valley <strong>of</strong> Tibet and the Kingdom <strong>of</strong> Bhutan in the east,<br />
Darjeeling district <strong>of</strong> West Bengal in the south and the Kingdom <strong>of</strong> Nepal in the west.<br />
The State, being a part <strong>of</strong> inner ranges <strong>of</strong> the Himalaya, has no open valley or plains. The<br />
elevations range from 300 to 8476 m above mean sea level consisting <strong>of</strong> lower, middle<br />
and higher hills, alpine zones and snow bound land. The project would involve<br />
construction <strong>of</strong> a diversion structure on river Talung chu/ Rangyong, 1 km u/s <strong>of</strong> village<br />
Lingza in the North Sikkim district. North Sikkim, with its Headquarters at Mangan,<br />
comprises <strong>of</strong> the valleys <strong>of</strong> Lachen, Lachung, Dzongu and Tholung. Each <strong>of</strong> these is<br />
formed by fast flowing glacier fed rivers originating from The Great Himalayan range<br />
and its <strong>of</strong>fshoots. The nearest railhead is New Jalpaiguri whereas the nearest airport is at<br />
Bagdogra.
97<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
9.2 PHYSICAL ENVIRONMENT<br />
9.2.1 Climate/Meteorology<br />
The climate <strong>of</strong> the State has been roughly divided into tropical, temperate and alpine<br />
zones. For most <strong>of</strong> the period in the year, the climate is cold and humid. A peculiar<br />
feature <strong>of</strong> the State is that it experiences a cold winter from end <strong>of</strong> November to February<br />
and monsoons throughout the year with a little respite during May - June and October -<br />
November. Even the winter months can be irritatingly wet and damp with unpredictable<br />
showers. The area experiences heavy rainfall due to its proximity to the Bay <strong>of</strong> Bengal.<br />
The general trend <strong>of</strong> decrease in temperature with increase in altitude holds good every<br />
where. Though summer is <strong>of</strong>ficially from May to October, Sikkim is almost always wet<br />
due to the heavy monsoons, with rains at times continuing for days on ends. Longest<br />
recorded nonstop rain is 11 days. September to October is autumn.<br />
9.2.1.1 Temperature<br />
The minimum temperature in the lower altitudinal zone varies from 1.5˚ C to 9.5˚ C.<br />
Temperature varies with altitude and slope. The maximum temperature is recorded<br />
usually during July - August and minimum during December - January. Fog is a common<br />
feature in the entire State from May to September. Biting cold is experienced at high<br />
altitude places in the winter months and snowfall is also not uncommon during this<br />
period.<br />
9.2.1.2 Rainfall<br />
Rainfall is heavy and well distributed during the months from May to early October. July<br />
is the wettest month in most <strong>of</strong> the places. The intensity <strong>of</strong> rainfall during southwest<br />
monsoon season decreases from south to north, while the distribution <strong>of</strong> winter rainfall is<br />
in the opposite order. The highest annual rainfall for the individual station may exceed<br />
5000 mm and average number <strong>of</strong> rainy days (days with rain <strong>of</strong> 2.5 mm or more) ranges<br />
from 100 at Thangu to 184 at Gangtok.
98<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
9.2.2 Topography<br />
Sikkim encompasses the Lesser Himalaya, Central Himalaya, and the Tethys Himalaya.<br />
It is a mountainous State without flat piece <strong>of</strong> land <strong>of</strong> any extent anywhere. The<br />
mountains rise in elevation northward. The northern portion <strong>of</strong> the State is deeply cut into<br />
steep escarpments. South Sikkim is lower, more open, and fairly well cultivated. This<br />
configuration <strong>of</strong> the State is partly due to the direction <strong>of</strong> the main drainage, which is<br />
towards the south. The trend <strong>of</strong> the mountain system is generally in east-west direction.<br />
The Rangit and the Teesta, which form the main channels <strong>of</strong> drainage, run nearly north -<br />
south. The valleys cut by these rivers and their feeders are very deep and are rather open<br />
towards the top, but usually attain a steep gorge like structure as they approach the bed <strong>of</strong><br />
the rivers.<br />
9.2.3 Soils<br />
The State <strong>of</strong> Sikkim enjoys a wide range <strong>of</strong> climate, physiography, geology and<br />
vegetation, which have further influenced formation <strong>of</strong> different kinds <strong>of</strong> soils that are,<br />
classified under 5 broad physiographic units. Table 9.1 gives area wise details <strong>of</strong> this soil.<br />
The light textured soil and rocky areas are prone to sliding. Topsoil in most areas is rich<br />
in humus and organic matter. The water holding capacity in most area is low and has low<br />
cohesiveness. The soil is mainly coarse to fine loam in texture. Some soil has a gray<br />
tinge. Depth <strong>of</strong> soil varies between 100 cm and 200 cm. The humus cover over the soil is<br />
sufficiently thick while at some places depleted in higher areas.
Table 9.1: Major physiographic units <strong>of</strong> soil in Sikkim<br />
99<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
No. Physiographic units Area (ha) % <strong>of</strong> total<br />
geographic area<br />
1 Summit & Ridge (>30%) 31459.45 4.43<br />
2<br />
2.1<br />
2.2<br />
2.3<br />
2.4<br />
Slide slope <strong>of</strong> hills<br />
Very steep slope (>50%)<br />
Escarpments (>50%)<br />
Steeply sloping (30-50%)<br />
Moderately sloping (15-30%)<br />
213100.01<br />
30480.73<br />
214641.28<br />
16024.82<br />
30.03<br />
4.3<br />
30.24<br />
2.26<br />
3 Valleys (
100<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
Geology<br />
The proposed diversion scheme on Tolung chu is located within a deep gorge in a narrow<br />
valley <strong>of</strong> about 25-30 m width. At the proposed axis the river flows easterly. Both the<br />
banks rise steeply. The right bank slopes are generally laid at about 70° while the left<br />
bank is laid at about 75° for about 60 m height beyond which a 50-60 m wide terrace has<br />
been developed for cultivation. Further uphill, the left bank slopes rise at an angle <strong>of</strong><br />
about 60°. Upstream <strong>of</strong> the axis the river flows in cascades in a steeper gradient. Both<br />
banks appear to be fairly stable, as no instability has been observed. At the proposed axis<br />
rocks are exposed along both the banks and the bedrock in the channel portion is<br />
expected to be under a thin pile <strong>of</strong> overburden material. The rock types comprises <strong>of</strong><br />
gneiss/ schist. The gneisses are strong to very strong while the schist is moderately<br />
strong.<br />
9.2.5 Seismicity<br />
Sikkim falls in the active part <strong>of</strong> Himalayan seismic belt. The project area falls in zone –<br />
IV <strong>of</strong> the seismic zoning map <strong>of</strong> India.<br />
9.2.6 Catchment area<br />
The total catchment area <strong>of</strong> the project is 592 km 2 (Fig. 9.1). The entire catchment <strong>of</strong><br />
Tolung is mountainous with rugged terrain. The area is imparted by approximately N-S<br />
trending steep longitudinal hill ranges and valleys. The tributaries are angular and have<br />
dendritic drainage patterns. Streams have moderate to steep slopes with falls at a number<br />
<strong>of</strong> places. The natural vegetation consists <strong>of</strong> mixed evergreen to deciduous, conifers to<br />
almost tundra like vegetation at higher elevations.<br />
9.2.7 River System<br />
Tolung is a major tributary <strong>of</strong> Teesta River and joins Teesta upstream <strong>of</strong> Mangan near<br />
Sankalang in the North District <strong>of</strong> Sikkim. Tolung originates from Talung and
101<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
Tongshiong Glaciers as Rukel chu. Rukel chu, Urman chu and Ringpi chu rivulets join to<br />
form river Tolung (Fig. 9.3).<br />
Rangyong chu rises as Rukel chu from Tongshi and Talung glacier from the base <strong>of</strong> South<br />
Kanchenjunga peak (8,476 m). Along its eastward course, Rukel chu receives drainage<br />
from Tingchen glacier on its right bank (Fig 9.3). Umram chu is the major tributary <strong>of</strong><br />
Rukel chu originating from Umram glacier. Umram chu is joined by Passaram chu on its<br />
left bank and then drains into Rukel Chu. Thereafter Rukel chu is known as Rangyong chu.<br />
Rangyong Chu in certain stretches is also known as Tolung chu. Another tributary Ringpi<br />
Chu joins Rangyong Chu on its left bank about 1.00 km upstream <strong>of</strong> the proposed dam site.<br />
The catchment area <strong>of</strong> <strong>Panan</strong> H.E. Scheme up to the proposed dam site is 678.35 sq km.<br />
Total length <strong>of</strong> Rangyong Chhu from its origin up to dam site is about 25 km.<br />
9.2.8 Landuse Pattern<br />
The landuse / land cover pattern within the 7 km radius <strong>of</strong> the proposed <strong>Panan</strong> H.E.<br />
Project was interpreted and generated from LISS-III scene <strong>of</strong> Path/Row 107/051 <strong>of</strong> 19th<br />
January, 2000 and PAN D scene <strong>of</strong> Path/Row 107/051 <strong>of</strong> 13th January, 2002. LISS and<br />
Pan Scenes <strong>of</strong> area covering 7 km radius <strong>of</strong> the project site are given in Figures 9.4 & 9.5.<br />
The level classified landuse / landcover map generated from these two scenes coupled<br />
with ground truthing is given in Figure 9.6. Area covered by various landuse /land cover<br />
categories is given in Table 9.2 and the percent representation <strong>of</strong> each <strong>of</strong> the landuse /<br />
landcover type is shown in Figure 9.7. From the data it is clear that Dense Mixed<br />
Broadleaf Forests constitute more than half (55%) <strong>of</strong> the total land area, therefore form<br />
the predominant landuse in the vicinity <strong>of</strong> the proposed project site. The degradational<br />
type <strong>of</strong> forests, namely open and degraded, constitutes 12% and 14%, respectively <strong>of</strong> the<br />
land area covering about 6300 ha <strong>of</strong> land. It is evident from the results that the area does<br />
not significantly disturb ecosystems, as the area under human intervention around the<br />
project vicinity comprises only 7% <strong>of</strong> the land area. A sizeable portion <strong>of</strong> the area is<br />
under rocky land and cliffs comprising about 7% <strong>of</strong> land area. Primary analysis <strong>of</strong> the
102<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
landuse / landcover indicates that the area is under natural ecosystem with only limited<br />
human intervention. Presence <strong>of</strong> modified or managed landscapes is limited and majority<br />
<strong>of</strong> the area is under natural ecosystems. Natural landscape features also include areas<br />
under snow and water bodies, which constitute 3% and 20% <strong>of</strong> the land area,<br />
respectively. The dense forests in the catchment are present towards northeast, east,<br />
northwest and southwest. These forests are represented by Tolung Reserve Forest in the<br />
north and north-east, Sakyong Reserve Forest in the west and southwest and Lingdem<br />
Reserve Forest in the south and south-east. These forests are mostly broad-leaf forests<br />
with occasional representation <strong>of</strong> bamboo in them, particularly in the warmer areas.<br />
Table 9.2 Area (ha) under different landuse/landcover categories in 7 km<br />
radius <strong>of</strong> <strong>Panan</strong> H.E. Scheme<br />
Landuse/landcover Area (ha)<br />
Barren land/Cultivation/Settlements 1822.65<br />
Degraded Forest 3290.41<br />
Open Forest 3001.37<br />
Rocky land 1781.75<br />
Dense Mixed Forest 13202.12<br />
Damp Areas/Water bodies 603.76<br />
Snow 609.08
103<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
Figure 9.7 Percent area under various landuse/landcover categories in 7 km<br />
radius <strong>of</strong> the proposed <strong>Panan</strong> H.E. Scheme.<br />
14%<br />
12%<br />
9.2.9 Submergence<br />
The project is likely to inundate a total area <strong>of</strong> 15.6 ha <strong>of</strong> land, which is very small and is<br />
confined to the river valley. The FRL is at an elevation <strong>of</strong> 1095 m and the MDDL is at<br />
EL 1085 m. The spread <strong>of</strong> reservoir is shown in Figure 9.8. The predominant landuse in<br />
the submergence area is degraded and open forest and does not involve inundation <strong>of</strong> any<br />
village or human habitation.<br />
7%<br />
55%<br />
Dense Forest Degraded Forest Open Forest<br />
Barren /Cultivation/Settlements<br />
Snow<br />
Rockyland Water/Damp Areas<br />
7%<br />
2%<br />
3%
9.2.10 Infrastructure<br />
The existing facilities in the project area are as follows:<br />
104<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
Road communication Network<br />
The project area falls in the North District <strong>of</strong> Sikkim and mainly single lane road exists in<br />
the area. Roads are impaired at a number <strong>of</strong> places by landslides and sinking zones. The<br />
Government <strong>of</strong> Sikkim has taken up road widening works at a number <strong>of</strong> places. The<br />
roads are maintained by DGBR organization and State PWD.<br />
Bank<br />
There exists branches <strong>of</strong> SBI at Mangan, Chungthang and Tolung .<br />
Post <strong>of</strong>fice<br />
One Post <strong>of</strong>fice branch exists at Mangan.<br />
Educational Facilities<br />
Higher Secondary school exists at Tingbong. Primary schools are situated at a number <strong>of</strong><br />
places in the vicinity <strong>of</strong> the project as Namprick Primary School. Tingbong Community<br />
Information Centre (CIC) North Sikkim Upper Dzongu is there to provide education in<br />
information technology to the students <strong>of</strong> the school. For higher education, students go to<br />
Gangtok at Sikkim Govt. College, Tadong, Gangtok, Manipal Institute <strong>of</strong> Technology<br />
Sikkim and Sikkim Manipal University <strong>of</strong> Health Technology & Medical Sciences.<br />
Communication<br />
The communication network is poor. However, there is one telephone exchange at<br />
Mangan. Tingbong Community Information Centre (CIC) at North Sikkim, Upper<br />
Dzongu and another one at Mangan, provide internet facilities to the locals.<br />
Government Department<br />
Government department <strong>of</strong>fices exist at block level in the project area. There is a District<br />
centre at Mangan.
105<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
Hospitals/ Primary Health Centers<br />
Primary health centres are available at Sankalang. There is a District Hospital at Mangan.<br />
A new 100 bed Community Health Centre is under construction at Mangan, North<br />
Sikkim. Central Referral hospital is at Gangtok<br />
9.3 BIOTIC ENVIRONMENT<br />
Sikkim stretches from the low lands in the south with tropical climate to the mountainous<br />
regions in the north. The altitude varies right from sea level to mountain peaks covering a<br />
wide spectrum <strong>of</strong> flora and fauna. Nowhere in the world in such a small area can one find<br />
flora and fauna <strong>of</strong> all varieties - Tropical to the Alpines. Sikkim's botanical and<br />
zoological richness is awe- inspiring, boasting <strong>of</strong> more than 4500 species <strong>of</strong> flowering<br />
plants. 30% <strong>of</strong> all the birds in the country are found in Sikkim.<br />
9.3.1 Vegetation (details <strong>of</strong> forest types, etc.)<br />
Its extreme altitudinal variation brings in tremendous change in climatic conditions that<br />
in turn supports the biodiversity <strong>of</strong> different heights. With only 0.22% geographical area<br />
<strong>of</strong> the country, Sikkim harbors 1/3 rd <strong>of</strong> the country’s flowering plants. There are 4500<br />
species <strong>of</strong> flowering plants, 362 species <strong>of</strong> ferns and its allies, 11species <strong>of</strong> oaks, 8<br />
species <strong>of</strong> tree ferns, 448 species <strong>of</strong> orchids, 30 species <strong>of</strong> Primula and 20 species <strong>of</strong><br />
bamboos. Many medicinal plants/herbs/and important shrubs are found in low and high<br />
altitude areas.<br />
9.3.2 Flora<br />
The dam site is located in a tropical hilly terrain and the area in the vicinity <strong>of</strong> the project<br />
is mainly comprised <strong>of</strong> dense mixed forests. This area experiences hot and humid<br />
summers and mild winters. There is an extended spell <strong>of</strong> warm humid<br />
climate throughout the year with a short dry spell during winter months starting from<br />
October to February. Owing to prolonged spell <strong>of</strong> humidity and moderate temperatures at<br />
these altitudes the vegetation is constituted mostly by tropical moist deciduous and
106<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
evergreen plant species. These areas are densely vegetated by all the physiognomic forms<br />
– trees, shrubs and herbaceous flora. At warmer altitudes Duabanga sonnertoides and<br />
other woody elements like Aglaia lawii, Bombax ceiba, Chukrasia tabularis, Eugenia<br />
kurzii, and Mangifera sylvatica can be seen. In the catchment broad-leaved species are<br />
represented by Castanopsis indica, Eurya cerasifolia, Gynocardia odorata and<br />
Macaranga. The vegetation in the sub-tropical zone is comprised <strong>of</strong> elements like Adina<br />
cordifolia, Bisch<strong>of</strong>ia javanica, Michelia velutina, etc. At higher reaches, the species like<br />
Magnolia hodsonii and Helicia sp. are encountered. Schima wallichi is an important<br />
constituent <strong>of</strong> the vegetation <strong>of</strong> this area. At many places the mixed forests is replaced by<br />
pure bamboo formations <strong>of</strong> Dendrocalamus strictus (Ringal) on the slopes. Wherever<br />
bamboo is absent the natural formations have pr<strong>of</strong>use growth <strong>of</strong> ground and shrubby<br />
flora. The shrubs are represented by Buddleja asiatica, Clerodendrum japonicum, C.<br />
viscosum and Embelica floribunda. The undershrubs and ground flora comprises Barleria<br />
cristata, B. strigosa, Justicia procumbens, Pavetta indica and Vitex negundo. Some <strong>of</strong> the<br />
important and commonly occurring lianas and climbers besides Bauhinia vahlii are the<br />
species <strong>of</strong> Piper, Cissus and Cryptolepis. In areas where first storey tree cover is sparse<br />
and gaps are huge, Cyathea spinulosa, the tree fern is met with frequently among the<br />
shrubs and undershrubs. Majority <strong>of</strong> area is under dense broad leaf mixed forests and<br />
human intervention is limited to the area surrounding villages like Sakkyong, Phantong,<br />
Myong, Lingzah, Laven, Lingdem and Nung.<br />
9.3.3 Faunal and Wildlife<br />
As the project site falls in the vicinity <strong>of</strong> dense forests a good presence <strong>of</strong> wildlife is<br />
expected in and around the project site. The upper part <strong>of</strong> catchments <strong>of</strong> Ringpi Chhu and<br />
Tolung Chhu and Rangyong Chhu harbour several faunal species like Hoary-bellied<br />
squirrel (Callossciurus pygerithrus), Orange-bellied squirrel (Dremomys lokhriah),<br />
Assamese macaque (Macaca assamensis), Himalayan palm civet (Paguma larvata),<br />
Stone marten (Martes foina) and jackals (Canis aureus). These animals are generally<br />
found in the vicinity <strong>of</strong> agricultural crops. They raid the crops <strong>of</strong> large cardamom during
107<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
the fruiting season. In addition there are also species like Civets (Viverra zibetha),<br />
porcupines (Hystrix brachyura), Grey musk shrew (Suncus murinus), the house mouse<br />
(Mus musculus) and Bandicoot rat (Bandicota bengalensis). The upper reaches i.e. the<br />
alpine areas <strong>of</strong> the catchment harbour other mammalian species, which include Nayan,<br />
Bharal, Snow leopard, bear, Himalayan tahr, Barking Deer, Himalayan marmot and<br />
pikas. These animals, however seldom come down below altitudes <strong>of</strong> 2,100 m. The<br />
avifauna is comprised <strong>of</strong> bulbuls, thrushes, eagles, partridges, pigeons, doves, koels,<br />
owls, kingfishers, nightjars, woodpeckers, orioles, drongos, mynas, flycatchers, babblers,<br />
robins, etc. Among the reptiles Python molurus, Naja naja and Dendrelaphis sp. are<br />
important species found in the catchment. Among the invertebrates many species <strong>of</strong><br />
butterflies and dragonflies are found abundantly in the area.<br />
Among the various faunal species present in the catchment area Panthera pardus,<br />
Ne<strong>of</strong>elis nebulosa, Felis bengalensis, Macaca assamensis and Cervus duvaucelli are<br />
Scheduled as threatened animals <strong>of</strong> India while Panthera tigris, Selenarctos thibetanus<br />
and Cervus duvaucelli are considered as globally threatened species.<br />
9.3.4 Aquatic life<br />
Ichthy<strong>of</strong>auna <strong>of</strong> the river in lower reaches is comprised mainly <strong>of</strong> Balm, Asala, Chepti,<br />
Gadela, etc. and snow trout and minor trouts are also found at higher elevations. Some <strong>of</strong><br />
the identified fish species found in the area are Schizothorax richardsonii, Schizothorax<br />
progastis, Barilius bendelisis, Acrossocheilus hexagonolepis, Tor putitora, Garra gotylo<br />
gotylo, Bagarius bagarius, Glyptothorax cavia, Channa orientalis, etc.<br />
9.4 EXISTENCE OF ANY PROTECTED AREA/ARCHAEOLOGICAL SITES<br />
There is no protected area in the form <strong>of</strong> Wildlife Sanctuary or National Park within 7 km<br />
radius <strong>of</strong> the proposed project. In addition to this, there are no sites or monuments <strong>of</strong><br />
archaeological or national importance, which would be affected by the project activities<br />
directly or indirectly.
108<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
9.5 SOCIO-ECONOMIC ENVIRONMENT<br />
The area in the vicinity <strong>of</strong> the project is very thinly populated. The human settlements are<br />
scattered and the human population as per the 1991 census up to different aerial distances<br />
from the project are given below.<br />
Up to 2 km Up to 2-5 km Up to 5-10 km<br />
Population 328 565 2773<br />
Households 69 125 535<br />
Most <strong>of</strong> the land required for the project area lies in the North district <strong>of</strong> Sikkim. The land<br />
requirement for the project may include private land, marginal forestland and village<br />
forests. Most <strong>of</strong> the population in the project area comprises <strong>of</strong> Lepchas, Bhutias and<br />
Nepalese which constitute about 85% <strong>of</strong> the population. Most <strong>of</strong> the people are tribals<br />
with little agricultural earnings being farmers with meager land holdings. Cardamom and<br />
ginger is grown at a number <strong>of</strong> places on private as well as forestlands. The families in<br />
general have a few cattle, sheep and pigs with some poultry. Most parts <strong>of</strong> the valley are<br />
inhabited with minuscule population. Yaks herds, herdsmen and sheep grazers are seen<br />
in to migrate in the catchment area.<br />
The existing public facilities in the project area are not sufficient. There are very low<br />
opportunities <strong>of</strong> employment in the local area. People are involved in small roadside<br />
business as kiosks selling tea, snacks, eggs, vegetables, etc. grown in the fields. The<br />
overall economic conditions are not very healthy. Jhoras (small streams) are main source<br />
<strong>of</strong> drinking water in the area. Most <strong>of</strong> the houses <strong>of</strong> the locals are kuccha. However, the<br />
Government is constructing pucca model houses in a number <strong>of</strong> villages.
109<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
9.6 PREDICTION OF ENVIRONMENTAL IMPACTS<br />
9.6.1 Impacts on Land Environment<br />
Sufficient land would be required for construction <strong>of</strong> the proposed dam, powerhouse,<br />
colonies & approach roads etc. Some portion <strong>of</strong> the land would also come under<br />
submergence. All these activities would mean some disturbance and change in the<br />
landscape/landuse pattern <strong>of</strong> the area.<br />
9.6.2 Impacts on Water Environment<br />
During the construction phase there may be some instances <strong>of</strong> excavated and quarried<br />
material getting washed away along with the rain water that may cause turbidity or<br />
sedimentation downstream. Natural sedimentation emanating from severely degraded<br />
catchment area is one <strong>of</strong> the important issues to be addressed. Also the problems <strong>of</strong><br />
waste disposal and management (human excreta and domestic sewage) due to<br />
congregation <strong>of</strong> large population <strong>of</strong> migrant labourers may be encountered. Proper waste<br />
management measures are required to be implemented during the construction phase <strong>of</strong><br />
the project so as to protect water body from pollution.<br />
9.6.3 Impacts on Air Environment<br />
The construction <strong>of</strong> the proposed dam would increase dust generation in the area and<br />
some vehicular pollution. However, these would only be limited to the construction<br />
period.<br />
9.6.4 Impacts on Flora/Fauna<br />
9.6.4.1 Impacts on terrestrial flora<br />
Due to construction <strong>of</strong> dam, some land will be inundated. The direct impact <strong>of</strong><br />
construction activity <strong>of</strong> a water resources project in a hilly terrain is generally limited to<br />
the vicinity <strong>of</strong> the construction sites. A large number <strong>of</strong> labourers and technical staff and<br />
other groups <strong>of</strong> people are likely to aggregate in the area during construction phase. In<br />
this area majority <strong>of</strong> rural community depends on forest for food, fodder and timber.
110<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
Submergence <strong>of</strong> forest area in primary impact zone may reduce the availability <strong>of</strong><br />
resources for the local people. This would also result in significant changes at the<br />
structural resource level in forest. The acquisition <strong>of</strong> land for various project activities<br />
would also lead to cutting <strong>of</strong> vegetation on these lands.<br />
9.6.4.2 Impacts on terrestrial fauna<br />
During the construction phase, a large number <strong>of</strong> machinery and construction labour will<br />
have to be mobilized. This activity may cause some disturbance to the wildlife<br />
population. The operation <strong>of</strong> various construction equipments is likely to generate<br />
significant noise. Likewise blasting too is likely to generate noise level and vibration<br />
intermittently. The noise may scare the fauna in the region and force them to migrate to<br />
other areas. There might also be some impacts due to increased human interference.<br />
9.6.4.3 Impacts on avi-fauna<br />
The construction <strong>of</strong> the proposed dam will lead to formation <strong>of</strong> a reservoir, which will<br />
have a fluctuation <strong>of</strong> 8-10 m in the water level, which precisely means the reservoir bank<br />
will remain wet throughout the year. Due to such reasons grasses may grow along the<br />
reservoir banks. Such conditions are generally ideal for various kinds <strong>of</strong> birds, especially<br />
water birds. However because <strong>of</strong> the presence <strong>of</strong> a good habitat it is quite likely that<br />
water birds will flock in this area in a large number. The birds from cold climatic areas<br />
could also use this area during the winter season.<br />
9.6.4.4 Impacts on aquatic ecology:<br />
The major physical change upstream <strong>of</strong> the proposed dam will be formation <strong>of</strong> a<br />
lacustrine habitat from a riverine habitat. Whereas below the damsite, there will be<br />
regulated water or very little water in river course. As such there will be some changes in<br />
the aquatic environment in this stretch. There is a possibility <strong>of</strong> stratification in the<br />
reservoir during winter. For this the water quality analysis shall be conducted regularly.<br />
Moreover, some migratory fish species may get affected due to construction <strong>of</strong> the dam.
111<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
Also fish species which are riverine and are not accustomed to deep lake environment<br />
may also get replaced.<br />
9.6.5 Impacts on Socio-Economic Environment<br />
Since the submergence area is small and is confined to the river valley, no village is<br />
expected to be submerged. Thus displacement is not anticipated.<br />
At present, there are small business and little employment facilities in the project area.<br />
However with the construction <strong>of</strong> the project new business and employment opportunities<br />
will open up for the local people which are likely to improve the economic conditions <strong>of</strong><br />
the local people. Further, there will be development <strong>of</strong> infrastructure facilities as housing,<br />
water supply, medical facilities, schools, transportation and communications. These<br />
factors are expected to bring about positive impact on the socio-economic status <strong>of</strong> the<br />
people living in the project area.<br />
There is possibility <strong>of</strong> changes in lifestyle and cultural values <strong>of</strong> local people due to<br />
migrant worker population. However, the impact is expected to be low as the number <strong>of</strong><br />
immigrant people will be small for a project <strong>of</strong> this magnitude and most <strong>of</strong> the labourers<br />
employed in the project will be from the local population.<br />
As a part <strong>of</strong> the Environmental Impact Assessment Study, a detailed socioeconomic<br />
survey would be carried out to determine the following:<br />
Information on various aspects <strong>of</strong> the affected population viz; demographic<br />
details, socio-economic and cultural characteristics, enumeration <strong>of</strong> personal<br />
properties <strong>of</strong> the affected population, education level and occupational pr<strong>of</strong>ile etc.<br />
Enumeration <strong>of</strong> social infrastructure and community property resources in the<br />
submergence area.<br />
Ethnographic assessment <strong>of</strong> PAFs.
112<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
9.7 ENVIRONMENTAL MANAGEMENT PLANS<br />
The objective <strong>of</strong> the Environmental Management Plan (EMP) is to ameliorate the<br />
negative impacts <strong>of</strong> a developmental project. The most reliable way to ensure proper<br />
implementation <strong>of</strong> these management plans is to integrate the same with various<br />
processes involved during project planning, designing, construction and operation phases.<br />
Based on the assessment <strong>of</strong> environmental impacts, following management plans will be<br />
formulated:<br />
Catchment Area Treatment<br />
Compensatory Afforestation<br />
Wildlife Conservation<br />
Resettlement and Rehabilitation<br />
Public Health Management System<br />
Muck Disposal<br />
Fishery Management<br />
Restoration <strong>of</strong> Construction Area<br />
Green Belt Development<br />
Free Fuel Provision<br />
Disaster Management
CHAPTER – X<br />
INFRASTRUCTURE<br />
120<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
10.1 EXISTING ACCESS AND INFRASTRUCTURE FACILITIES<br />
10.1.1 Road Communication<br />
The <strong>Power</strong>house is located on the right bank <strong>of</strong> Ranyong Chu u/s <strong>of</strong> confluence <strong>of</strong><br />
Tolung Chu and Rahi Chu near the village <strong>Panan</strong>. The <strong>Power</strong>house is about 9.0 Km from<br />
Mangan and 7.5 Km from Singtam - Mangan state highway which runs along the left<br />
bank <strong>of</strong> river Teesta. The power house is about 1.5 Km from CWC gauge and discharge<br />
site at Sanklan, about 600m u/s <strong>of</strong> the power house <strong>of</strong> Teesta (III) H.E. Project and about<br />
1300 m u/s <strong>of</strong> the dam <strong>of</strong> Teesta (IV) H.E. Project. The <strong>Power</strong> house site is well<br />
connected by road from Mangan, Singtam (NH31A) and Gangtok.<br />
The dam site is located near the village Lingza. The Lingza is 17 Km from Mangan, the<br />
head quarter <strong>of</strong> North Sikkim District 0f Sikkim, 62 Km from Singtam (NH31A), 152<br />
Km from NJP railway station and 167 Km from Bagdogra airport. The Lingza village is<br />
well connected form Mangan by a PWD road. . The Siliguri-Gangtok (NH-31A) and<br />
Singtam-Mangan-Sanklan state highways are being maintained by BRO while the<br />
Lingza-Sanklan-Rungto-Laven roads are being maintained by state PWD.<br />
10.1.2 Housing And Community Facilities<br />
<strong>Panan</strong> is the small village near to power house with basic facilities <strong>of</strong> health care,<br />
schooling, market, postal and telephone. These facilities are catering the need <strong>of</strong> very<br />
small population and would be totally inadequate for the project personals. It is therefore<br />
necessary to plan housing, <strong>of</strong>fice, recreation, store etc. for meeting the requirement <strong>of</strong> the<br />
project.
121<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
10.1.3 <strong>Power</strong> Availability<br />
The state <strong>of</strong> Sikkim, at present, is dependent mainly its mini and micro hydel power<br />
stations for meeting its power demand. The total installed capacity <strong>of</strong> state at present is<br />
about 95 MW. The state gets some share <strong>of</strong> power from Chuka Hydel Electric Project in<br />
Bhutan, Farakka Thermal <strong>Power</strong> Station, West Bengal and Rangit Hydel <strong>Power</strong> Project<br />
<strong>of</strong> NHPC Ltd. Teesta (V) HE Project, 510 MW being executed by NHPC in central sector<br />
is also under advance stage <strong>of</strong> construction. The existing transmission system <strong>of</strong> this state<br />
comprises <strong>of</strong> mainly 66 KV and 11 KV transmission lines. A 132 KV S/C transmission<br />
line is being constructed from Melli border town <strong>of</strong> Sikkim-West Bengal to Ranipool. A<br />
132 KV sub station is being constructed at Melli. A substation <strong>of</strong> 2.5MVA, 66/11KV is<br />
located at Phodong near the project area. Therefore , the necessary construction power<br />
shall be available from Phodong Sub-Station for the execution <strong>of</strong> <strong>Panan</strong> H.E. Project.<br />
10.2 PROPOSED ACCESS AND INFRASTRUCTURE FACILITIES<br />
Keeping in view the available infrastructure facilities <strong>of</strong> communication,, housing and<br />
power, the requirement <strong>of</strong> the same for <strong>Panan</strong> H.E. Project has been worked out.<br />
10.2.1 Improvement Of Existing Road And Bridges<br />
The <strong>Power</strong>house is located near the confluence <strong>of</strong> Tolung Chu and Rahi Chu near the<br />
village <strong>Panan</strong> . The state highway having a length <strong>of</strong> 11km from Sanklan connects the<br />
power house and dam sites. The Sanklan-Lingza-Rungto-Laven PWD roads connecting<br />
damsite , adit I&II are required to be improved for a length <strong>of</strong> about 8.5 Km by<br />
widening. There are 2 bridges from Sanklan to Lingza, one across the river Rangyong<br />
about 120m long and another 30m long on the road to Lingza are required to be upgraded<br />
to suitable classes. The bridges from Tolung chu to the power house <strong>of</strong> Teesta (III)<br />
H.E.Project have not been considered as these should form the cost <strong>of</strong> Teesta (III)<br />
H.E.Project . The Dam <strong>of</strong> Teesta (V) HE Project under execution is located about 18 Km<br />
downstream <strong>of</strong> Sanklan, therefore, all the bridges are being upgraded to class 30R unto
122<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
Dam site and class 70R unto <strong>Power</strong>house at Dipudara. Therefore, no more bridges are<br />
required to be upgraded.<br />
10.2.2 Construction Of Roads & Bridges<br />
The dam site shall be accessed from Mangan - Lingza road from left bank for which a<br />
new project road <strong>of</strong> 3.0 Km is to be constructed alongwith a bridge at dam site across the<br />
river. The adit-I, II &III & surge shaft shall be approached from right bank PWD road.<br />
Two townships have been proposed one at Lingza and another at Sanklan.<br />
10.2.3 Accommodation For Residential Purpose<br />
To accommodate the project employees and contractors, land would be required for<br />
construction <strong>of</strong> suitable residential complexes. The residential colony and <strong>of</strong>fice<br />
complexes will be located near Lingza and Sanklan villages where suitable land is<br />
available. The project colony would have accommodation for all categories <strong>of</strong> <strong>of</strong>ficials<br />
deployed for the construction. The strength <strong>of</strong> the <strong>of</strong>ficials and staff <strong>of</strong> various categories<br />
required for the project has been worked out as . 100. Each personal would be provided<br />
with the accommodation as per the entitlement. Keeping in view the construction period<br />
and subsequent operation and maintenance <strong>of</strong> the project, it is proposed to construct<br />
about 40% <strong>of</strong> the buildings as the permanent and the remaining as temporary. This<br />
conclusion has been drawn on the basis that 40% <strong>of</strong> the staff strength would be required<br />
for maintenance and operation after the completion <strong>of</strong> the project.<br />
Requirement <strong>of</strong> built up accommodation has been worked out and it is estimated that<br />
about 2484 Sq.m <strong>of</strong> permanent built up area and 4675 Sq.m <strong>of</strong> temporary builtup area<br />
would be required. Total plinth area for residential accommodation worked out to be<br />
7159 Sq.m,
123<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
10.2.4 Accommodation For Non-Residential Purposes<br />
The <strong>of</strong>fice complexes are proposed at Lingza and Sanklan. Workshops, laboratories,<br />
stores, water supply, fire stations, electrical substations etc would be accommodated in<br />
the project area near Sanklan. One small –store – cum –stockyard is proposed at railhead<br />
near new Jalpaiguri Railway station where construction materials like cement, steel and<br />
machinery and equipments would be store for further transportation to the project site,<br />
Batching and mixing plants are to be commissioned, one near dam site and the other near<br />
power house site.<br />
Accommodation required for non residential purposes have been worked out to be 2220<br />
Sq.m <strong>of</strong> which about 40% would be permanent and rest will be temporary.<br />
10.3 TELECOMMUNICATION FACILITIES<br />
The different work sites <strong>of</strong> the project, <strong>of</strong>fices, stores, laboratories, workshop and<br />
residences would be connected through a telecommunication network. The<br />
telecommunication facilities would also be provided between the projects and outside.<br />
Therefore, an internal telephone exchange would be provided at the project for<br />
communication within and outside the project. Most parts <strong>of</strong> Sikkim are presently<br />
connected with different parts <strong>of</strong> the world through satellite telecommunication network<br />
for which an earth satellite station with electronic exchange exists. The same network<br />
would be extended to the project area for telecommunication with outstation agencies.<br />
10.4 CONSTRUCTION POWER<br />
A 11KV line from 2.5 MVA, 66/11KV Sub-station at Phodong have been considered to<br />
meet the construction power requirements for the execution <strong>of</strong> <strong>Panan</strong> H.E. Project. A 10<br />
to 15 km long 11KV transmission line shall be constructed from Phodong/ Mangan<br />
substations to <strong>Panan</strong> H.E. Project.
CHAPTER –XI<br />
CONSTRUCTION PLANNING & SCHEDULE<br />
124<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
11.1 INTRODUCTION<br />
The equipment planning & construction methodology <strong>of</strong> <strong>Panan</strong> H.E. Project in Teesta<br />
Basin has been developed on following considerations.<br />
1. The project construction period has been considered as five years.<br />
2. Available Geological Data at PFR stage.<br />
3. Requirement <strong>of</strong> Construction Equipment has been planned to handle the quantities<br />
worked out on the basis <strong>of</strong> preliminary layout.<br />
4. Five months (from May to September) rainy season has been considered while<br />
planning surface works. The progress will slow down during rainy season.<br />
11.2 CONSTRUCTION METHODOLOGY<br />
11.2.1 Infrastructure Works<br />
The main infrastructure development is proposed to be carried out in a period <strong>of</strong> 12<br />
months. During infrastructure period Land Acquisition, construction <strong>of</strong> approach roads,<br />
bridges & culverts, arrangement <strong>of</strong> construction power will be undertaken. Platform to<br />
accommodate batching plant, stores for construction material, site workshop, <strong>of</strong>fices and<br />
other buildings (residential/ non residential) colonies will also be developed in<br />
infrastructure period. Crawler Dozer, Loader cum Excavator, Motor Grader, Air<br />
compressor, Road Roller etc. are proposed for deployment during infrastructure stage.<br />
11.2.2 Diversion <strong>of</strong> River<br />
The excavation <strong>of</strong> 6.5m finished diameter, Horse shoe shaped 600m long diversion tunnel<br />
would be carried out by full face drilling & blasting method from 7 th month. Excavation<br />
<strong>of</strong> Diversion Tunnel will be carried out with 2 Boom drill jumbo, Air Track/ Wagon Drill<br />
2.5cum side dump loader, L.P. Dumpers etc.. Diversion tunnel excavation & concreting
125<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
would be completed in 12 months. The concreting equipment proposed are 30 cum/hr<br />
Batching & Mixing plant, Concrete pump, Transit mixer, shotcrete m/c, Grout pump and<br />
shutters. U/s & D/s C<strong>of</strong>fer dam would be constructed immediately after construction <strong>of</strong><br />
diversion tunnel within a period <strong>of</strong> 4 months to divert the river .<br />
11.2.3 Concrete Dam<br />
After construction <strong>of</strong> c<strong>of</strong>fer dam and river diversion, the excavation <strong>of</strong> river bed will be<br />
taken up. The excavation <strong>of</strong> Dam & foundation treatment would be carried out in 5<br />
months. Excavated material will be handled by 1.0 cum Hyd. Excavator and 20/ 25t<br />
dumpers. Concreting <strong>of</strong> Dam & HM work would be carried out in further 26 months.<br />
Concreting would be done by 2 Nos. traveling tower crane (4.5 t at 30 m radius) with<br />
2.0/3.0 cum bucket capacity, 30 Cum/hr Batching& Mixing plant installed at Diversion<br />
Tunnel, another 120 cum/hr. Batching & Mixing Plant at Dam site and 300TPH<br />
Aggregate Processing plant. Batching & Mixing Plant and Aggregate Processing plant<br />
would also cater the requirement <strong>of</strong> Diversion tunnel, Desilting chambers and some<br />
portion <strong>of</strong> HRT.<br />
11.2.4 Intake Structure, Desilting Chamber & Silt Flushing tunnel<br />
2Nos. dufour type desilting chamber <strong>of</strong> size 225m length, 15m width & 20m height<br />
would be excavated in 24 months. For excavation <strong>of</strong> desilting chamber, the intake<br />
structure & intake tunnels would be excavated first. The intake tunnels would be<br />
extended upto the full length <strong>of</strong> desilting chamber. Thereafter it will be expanded side<br />
wise to the full width <strong>of</strong> desilting chamber resulting in desilting chamber dome. Mucking<br />
<strong>of</strong> excavated material would be done through the intake tunnel. After the excavation <strong>of</strong><br />
desilting chamber concreting will be carried out. Excavation <strong>of</strong> silt flushing tunnel & gate<br />
operation chamber would be a parallel activity. The equipment to be deployed are Jack<br />
hammers, wagon drills, air compressors, loader, excavators, Dumpers, concrete pump,<br />
transit mixers etc.
126<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
11.2.5 Head Race Tunnel<br />
Construction <strong>of</strong> 9.0 km long, 6.0 m finished diameter horse shoe shaped Head Race<br />
Tunnel is proposed by full face drilling & blasting method. It will be excavated through 3<br />
nos intermediate adits <strong>of</strong> 6m dia.. The excavation <strong>of</strong> adits would be carried out in five<br />
months. Excavation would be carried out by 2 boom drill jumbo, 2.5Cum Side Dump<br />
Loader and L.P. Dumpers. Concreting will be carried out by deploying 4 sets <strong>of</strong><br />
concreting equipment i.e. Concrete pump, 4.0cum Transit Mixer etc. 30 cum/hr Batching<br />
& Mixing Plant & 50 TPH Aggregate processing Plant would be deployed at HRT. The<br />
excavation, concreting and grouting <strong>of</strong> HRT will be completed in 41months.<br />
11.2.6 Surge Shaft<br />
For Construction <strong>of</strong> Surge Shaft an adit to surge shaft bottom would be excavated. After<br />
completion <strong>of</strong> construction adit, 15m dia., Surge shaft would be taken up from top <strong>of</strong><br />
surge shaft. Excavation <strong>of</strong> Surge Shaft would involve pilot hole drilling, reaming <strong>of</strong> pilot<br />
hole & enlargement <strong>of</strong> reamed hole. Raise borer, Jack Hammer, L.P. Dumpers etc will<br />
be deployed for excavation <strong>of</strong> Surge shaft. Concreting would be completed employing 2<br />
m shutter. 30 cum/hr. Batching & Mixing Plant would be deployed at surge shaft.<br />
Construction <strong>of</strong> surge shaft would be completed in 32 months.<br />
11.2.7 Pressure Shaft<br />
3.0 m diameter, two no. pressure shaft will be excavated in the same way as surge shaft<br />
by deploying Raise borer , Jack hammer etc. Steel liner erection & concreting will be<br />
carried out by deploying 10/20 t winches, Slipform liner etc. Construction <strong>of</strong> Pressure<br />
shaft would take around 30 month time.<br />
11.2.8 <strong>Power</strong> House<br />
4 X 50 MW (200 MW) underground power house (120 m X 22 m X 45 m size) would be<br />
excavated in 18 months. For excavation <strong>of</strong> <strong>Power</strong> House a Main Access Tunnel would be<br />
excavated in about 6 months. A branch from this Main Access Tunnel would be extended
127<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
upto the crown <strong>of</strong> power house followed by extension <strong>of</strong> this extended MAT upto full<br />
length <strong>of</strong> power House. Thereafter it will be expanded side wise to the full width <strong>of</strong><br />
power house resulting in <strong>Power</strong> House Cavern. Mucking <strong>of</strong> excavated material would be<br />
done through the adit. From <strong>Power</strong> House Cavern four shafts <strong>of</strong> 2.0 m diameter would be<br />
excavated up to the bottom level <strong>of</strong> draft tube followed by benching <strong>of</strong> <strong>Power</strong> House<br />
cavern upto the bottom <strong>of</strong> <strong>Power</strong> House. Mucking will be carried out through TRT. The<br />
equipment to be deployed for excavation are jack hammers, wagon drills, air<br />
compressors, loader, excavators, dumpers, winches etc. Concreting <strong>of</strong> <strong>Power</strong>house would<br />
be carried out with the help <strong>of</strong> concrete pump, Transit Mixers etc. 60 cum/hr. Batching<br />
& Mixing Plant 150 TPH aggregate processing Plant would be deployed at <strong>Power</strong> House<br />
which would also cater the requirement <strong>of</strong> Pressure shaft and TRT. Installation & Testing<br />
<strong>of</strong> Machine would be undertaken in such a manner that Project get commissioned in 60 th<br />
month from the start <strong>of</strong> Project construction.<br />
11.2.9 Tail Race Tunnel<br />
500m long horse shoe shaped Tail Race Tunnel having 6.0 m finished diameter will be<br />
excavated in 7 months. Excavation <strong>of</strong> Tail Race Tunnel would be carried out by full face<br />
drilling & blasting method with 2 boom Drill Jumbo, Side dump Loader, 25T L.P.<br />
Dumper etc. The TRT will be excavated from the start <strong>of</strong> major work because TRT will<br />
be used for mucking <strong>of</strong> power house. After the excavation <strong>of</strong> power house concreting <strong>of</strong><br />
TRT will be taken up with the help <strong>of</strong> concrete pump, Transit Mixer, Batching & Mixing<br />
plant and aggregate processing Plant installed at Dam.<br />
11.3 CONSTRUCTION SCHEDULE<br />
The construction schedule has been drawn up for the actual construction phase, wherein a<br />
total period <strong>of</strong> five years has been assumed for construction. Main considerations/<br />
assumptions while framing the construction schedule are as under:
128<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
i) Since the date <strong>of</strong> CCEA clearance cannot be anticipated at this stage, the time<br />
assumed for various activities is inclusive <strong>of</strong> the effect <strong>of</strong> monsoon.<br />
ii) The major contracts will be awarded within three months <strong>of</strong> CCEA clearance<br />
and within another three months, the agencies will mobilize to start work at<br />
site.<br />
iii) The 600m Diversion Tunnel (including HM work) will be done within next 14<br />
months. Since the lean discharge is less, c<strong>of</strong>ferdam building (initial stage) and<br />
river diversion will be possible in another one month, i.e., by 21st month.<br />
iv) A total period <strong>of</strong> 31 months has been allowed for complete concreting and<br />
HM works <strong>of</strong> concrete dam including 5 months for foundation work apart<br />
from 2 months for reservoir filling.<br />
v) The Head Race Tunnel <strong>of</strong> about 9 km. length will be executed mainly from 6<br />
faces through three adits, in a total period <strong>of</strong> 50 months including adits<br />
plugging, charging <strong>of</strong> HRT Tunnel construction <strong>of</strong> adits.<br />
vi) Surge shaft, Pressure shaft and Penstocks works will be taken up concurrently<br />
and independently.<br />
vii) <strong>Power</strong> House and Transformer Caverns will be excavated in 18 months in all.<br />
However after about 12 months’ work concreting should start and EOT level<br />
will be achieved in Service Bay portion by 27 th month. The EOT crane should<br />
be made available for use from 30 th month.<br />
viii) The E&M works upto commissioning <strong>of</strong> all three units will be done in 35<br />
months time, <strong>of</strong> which 31 months will be available after commissioning <strong>of</strong><br />
EOT crane.<br />
ix) Other works like Trail Race Tunnel, Pothead yard, etc. will be executed<br />
concurrently.<br />
The schedule for stage I & II activities upto CCEA clearance and construction schedule<br />
has been prepared in the form <strong>of</strong> bar chart at annexure –11.1 & 11.2 respectively.
CHAPTER-XII<br />
COST ESTIMATE<br />
131<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
12.1 PRELIMINARY COST ESTIMATE FOR CIVIL, HYDRO-<br />
MECHANICAL, ELECTRO-MECHANICAL WORKS: -<br />
The estimate has been prepared to arrive at the Capital Cost <strong>of</strong> <strong>Panan</strong> H. E. Project and is<br />
<strong>of</strong> Pre-feasibility level <strong>of</strong> accuracy. The base date <strong>of</strong> the estimate is June 2003 and the<br />
Cost is expressed in Indian Rupees. The Cost Estimate is divided into Civil, Electrical<br />
and Transmission Works. For Civil Works, the sub heads are as under: -<br />
12.1.1 I-WORKS<br />
Under this head, provision has been made for various components <strong>of</strong> the Project as<br />
detailed hereunder:<br />
A-PRELIMINARY<br />
Under A-Preliminary, provision has been made for all surveys and investigations to be<br />
conducted to arrive at the optimum <strong>of</strong> the Project Components.<br />
B-LAND<br />
This covers the provision for acquisition <strong>of</strong> land for construction <strong>of</strong> the Project, colonies,<br />
<strong>of</strong>fices and stores and compensation for trees and standing crops etc<br />
C-WORKS<br />
This covers the cost <strong>of</strong> River Diversion Work , C<strong>of</strong>fer dam, Concrete Dam and Spillway<br />
along with associated Hydro-mechanical equipment.<br />
J-POWER PLANT CIVIL WORKS<br />
This covers the cost <strong>of</strong> project components viz. Intake Structure,Desilting Chamber,<br />
Headrace Tunnel and TRT, Surge Shaft, Pressure Shaft, <strong>Power</strong> House and Transformer
132<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
Cavern and other Appurtenant Works along with associated Hydro-mechanical<br />
equipment.<br />
The quantities indicated in the estimates for C - Works & J-<strong>Power</strong> Plant Civil Works<br />
(Civil & HM) are calculated from the preliminary Engineering drawings and as per<br />
experience <strong>of</strong> other on-going or commissioned projects.<br />
The unit rates for various items are taken as per the Guidelines issued by CEA for<br />
preparation <strong>of</strong> PFRs. It has been assumed that the quarry is available at a distance <strong>of</strong> 10<br />
Kms from the work site.<br />
K-BUILDINGS<br />
Buildings, both residential and non-residential have been provided under this head. Under<br />
the permanent category only those structures have been included which shall be<br />
subsequently utilized during the operation and maintenance <strong>of</strong> the project. The costs are<br />
worked out on plinth area basis prevalent in the area for the type <strong>of</strong> construction<br />
involved.<br />
O-MISCELLANEOUS<br />
Under this head provision has been made to cover the cost <strong>of</strong> the following miscellaneous<br />
works.<br />
a) Capital cost <strong>of</strong> electrification, water supply, sewage disposal, fire fighting<br />
equipments etc.<br />
b) Repair and maintenance <strong>of</strong> electrification, water supply, sewage disposal,<br />
medical assistance, recreation, post <strong>of</strong>fice, telephone and telegraph <strong>of</strong>fice,<br />
security arrangements, fire fighting, inspection vehicles, schools, transport<br />
<strong>of</strong> labour etc.
133<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
c) Other services such as laboratory testing, R&M <strong>of</strong> Guest House and transit<br />
camps, Community center, retrenchment compensation, photographic<br />
instruments as well as R&M charges etc.<br />
P-MAINTENANCE DURING CONSTRUCTION AND Y-LOSSES ON STOCK<br />
A provision <strong>of</strong> 1% and 0.25% <strong>of</strong> C-Civil works, J-<strong>Power</strong> Plants, K-Buildings & R-<br />
Communications has been made for maintenance <strong>of</strong> works during construction period<br />
and losses on stock respectively.<br />
Q-SPECIAL TOOLS AND PLANT<br />
It is assumed that the work will be carried out through Contracts and not through<br />
departmental construction. Accordingly, provision for general purpose equipment and<br />
inspection vehicle only has been made as per CWC guidelines.<br />
R-COMMUNICATION<br />
Provision under this head covers the cost <strong>of</strong> new roads, widening/improvement <strong>of</strong> roads<br />
and strengthening <strong>of</strong> bridges. The costs <strong>of</strong> roads and bridges are based on the rate<br />
structure prevalent in the area <strong>of</strong> the Project for the type <strong>of</strong> construction involved.<br />
X-ENVIRONMENT AND ECOLOGY<br />
Provision under this head has been taken as 2% <strong>of</strong> I -Works towards bio-diversity<br />
Conservation, creation <strong>of</strong> Green Belt, Restoration <strong>of</strong> Construction Area, Catchment Area<br />
Treatment, Compensatory Afforestation etc<br />
12.2 II-ESTABLISHMENT<br />
Provision for establishment has been made at 8% <strong>of</strong> I-works minus B-Land for civil<br />
works.
134<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
12.3 III-TOOLS AND PLANTS<br />
This provision is distinct from that under Q-Special T&P and is meant to cover cost <strong>of</strong><br />
survey instruments, camp equipment and other small tools and plants. The outlay is<br />
provided at 1% <strong>of</strong> cost <strong>of</strong> I-works.<br />
12.4 IV-SUSPENSE<br />
No provision has been made under this head as all the outstanding suspense are expected<br />
to be cleared by adjustment to appropriate heads at completion <strong>of</strong> the project.<br />
12.5 V-RECEIPTS AND RECOVERIES<br />
Under this head, provision has been made for estimated recoveries by way <strong>of</strong> resale or<br />
transfer <strong>of</strong> equipment used in infrastructure works. Also the recoveries on account <strong>of</strong><br />
resale <strong>of</strong> DG sets, Transformer etc and resale <strong>of</strong> temporary buildings have also been<br />
envisaged.<br />
12.6 ELECTRICAL WORKS AND GENERATING PLANT<br />
The cost <strong>of</strong> Generating Plant and Equipment is based on indigenous sources. The prices<br />
<strong>of</strong> auxiliary equipment and services are based on prevailing market prices/costs incurred<br />
at other ongoing or commissioned projects.
135<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
ABSTRACT OF COST OF WORKS<br />
S.No Description Amount<br />
(Rs. in Crores)<br />
( June 2003<br />
P.L.)<br />
A CIVIL WORKS<br />
1. DIRECT CHARGES<br />
I - Works<br />
A - Preliminary 4.54<br />
B - Land 11.00<br />
C - Works 95.41<br />
J - <strong>Power</strong> Plant Civil Works 331.37<br />
K - Buildings 12.92<br />
O - Miscellaneous 10.94<br />
P - Maintenance 4.61<br />
Q-Special Tools & Plants 3.98<br />
R - Communication 20.94<br />
X - Environment & Ecology 10.14<br />
Y - Losses on Stock 1.15<br />
Total <strong>of</strong> I-Works 506.99<br />
II - Establishment @ 8% <strong>of</strong> cost <strong>of</strong> I-Works less B- 39.68<br />
III - Tools and Plants @ 1% <strong>of</strong> cost <strong>of</strong> I-Works 5.07<br />
IV - Suspense 0.00<br />
V - Receipt & Recoveries (-) -2.82<br />
Total Direct Charges 548.92<br />
2. INDIRECT CHARGES<br />
a) Capitalised Value <strong>of</strong> Abatement <strong>of</strong> Land Revenue 0.11<br />
b) Audit and Account Charges @1% <strong>of</strong> cost <strong>of</strong> I- 5.07<br />
Total Indirect Charges 5.18<br />
Total Of Direct & Indirect Charges 554.10<br />
ABSTRACT :<br />
A Civil Works 554.10<br />
B Electrical Works 209.17<br />
C Transmission Works 1.67<br />
Total Cost 764.94<br />
C IDC 81.14<br />
D Total Cost With IDC 846.08
S.<br />
No.<br />
A- PRELIMINARY<br />
Description <strong>of</strong> Work Qty Unit<br />
136<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
Rs in Lakhs<br />
Rate Amount<br />
1.0 Prefeasibility<br />
1.1 Preparation <strong>of</strong> Prefeasibility Report LS 14.00<br />
2.0 Preparation <strong>of</strong> Detailed Project<br />
Report<br />
2.1 Detail survey for final location <strong>of</strong> project<br />
components<br />
LS 25.00<br />
2.2 Aerial survey, contour survey for<br />
reservoir basin including establishment <strong>of</strong><br />
permanent benchmarks.<br />
LS 10.00<br />
2.3 Geological and geophysical surveys and<br />
investigation<br />
I) Drifting 800 m 0.05 40.00<br />
ii) Geophysical LS 20.00<br />
iii) Core drilling 300 m 0.10 30.00<br />
2.4 Hydrological and Metrological surveys<br />
including establishment <strong>of</strong> rain gauges/<br />
river gauges and discharge, sedimentation<br />
stations and their running charge for 1<br />
year<br />
LS 8.00<br />
2.5 Investigations for foundation and rock<br />
LS 6.00<br />
testing<br />
2.6 Investigation for availability <strong>of</strong><br />
construction materials.<br />
LS 3.50<br />
2.7 Construction <strong>of</strong> access roads to facilitate<br />
investigations<br />
LS 7.00<br />
2.8 Model experiment. LS 8.00<br />
2.9 Computer and telecommunication<br />
LS 3.00<br />
facilities.<br />
2.10 Vehicles for inspecting <strong>of</strong>ficers for site<br />
investigations<br />
LS 25.00<br />
2.11 Camping equipment LS 2.00<br />
2.12 Preliminary soil test, establishing soil<br />
testing laboratory.<br />
LS 6.00
137<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
2.13 Consultant’s fees including charges for<br />
preliminary design work or device<br />
LS 15.00<br />
2.14 Training <strong>of</strong> engineers during investigation<br />
and preparation <strong>of</strong> project reports<br />
LS 4.00<br />
2.15 Ground water studies. LS 6.00<br />
2.16 Environment and ecological studies. LS 10.00<br />
2.17 Preparation and printing <strong>of</strong> DPR LS 10.00<br />
Sub Total 252.50<br />
3.0 Pre-Construction Stage Investigations<br />
3.1 Topographical Surveys LS 15.00<br />
3.2 Geological Investigation<br />
I) Diamond Core Drilling 100 m 0.10 10.00<br />
ii) Exploratory Drift 100 m 0.1 10.00<br />
iii) Excavation in trenches & pits LS 0.75<br />
iv) Testing <strong>of</strong> Samples LS 4.00<br />
3.3 Hydrological and Silt data collection - 2<br />
sites for 4 years<br />
8.00 Year 2.00 16.00<br />
3.4 Meteorological Data Collection 2 sites for<br />
4 years<br />
8.00 Year 0.40 3.20<br />
3.5 Construction material survey<br />
I) Topographical Survey 4.00 Hec. 0.05 0.20<br />
ii) Collection and Transportation <strong>of</strong> samples LS 3.00<br />
iii) Laboratory Testing <strong>of</strong> Samples including<br />
charges for all T&P and Machineries<br />
LS 6.00<br />
3.6 Model studies LS 10.00<br />
3.7 Seismological data collection for 4 years 4.00 Year 1 4.00<br />
3.8 Survey for layout <strong>of</strong> colonies and roads<br />
I) Residential-cum-Office accommodation 2.00 Hec. 0.5 1.00<br />
ii) Batching Mixing Plant and Workshop 1.00 Hec. 0.5 0.50<br />
iii) Project and quarry site road 0.50 Hec. 0.5 0.25<br />
3.9 Workcharged establishment for<br />
unforeseen works<br />
5.00 Year 2 8.00
4.0 Design & Consultancy<br />
4.1 Cost <strong>of</strong> Design Establishment including<br />
procurement <strong>of</strong> printing stationery and<br />
preparation <strong>of</strong> completion report, History<br />
<strong>of</strong> Project etc.<br />
138<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
LS 25.00<br />
4.2 Cost <strong>of</strong> Special Studies and Designs LS 15.00<br />
4.3 Fees for Consultant and specialists LS 15.00<br />
4.4 Training <strong>of</strong> Engineers LS 5.00<br />
5.0 Equipment<br />
5.1 Drawing and Mathematical Instruments LS 10.00<br />
5.3 Survey Instruments LS 30.00<br />
5.4 Office instruments LS 10.00<br />
Grand Total : 454.40
S.<br />
No.<br />
B – LAND<br />
139<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
Rs in Lakhs<br />
Description Qty. Unit Rate Amount<br />
1. Private Land required<br />
i Permanent Residential and Non<br />
Residential Buildings<br />
6.00 Ha 5.50 33.00<br />
ii Diversion tunnel 3.00 Ha 5.50 16.50<br />
iii Submerged in the reservoir area 15.60 Ha 5.50 85.80<br />
iv Construction <strong>of</strong> dam/ weir 4.00 Ha 5.50 22.00<br />
v Construction material 2.00 Ha 5.50 11.00<br />
vi Approach Roads 40.00 Ha 5.50 220.00<br />
vii <strong>Power</strong> house 2.00 Ha 5.50 11.00<br />
viii Adits 3.00 Ha 5.50 16.50<br />
ix Switch Yard 1.00 Ha 5.50 5.50<br />
x Surge Shaft 1.00 Ha 5.50 5.50<br />
x Land for Misc Purpose 2.40 Ha 5.50 13.20<br />
Sub total (1) 80.00 440.00<br />
2, Forest Land<br />
I River bed 10.00 Ha 0.00 0.00<br />
ii Underground 5.00 Ha 0.00 0.00<br />
Sub total (2) 15.00 0.00<br />
3. Land on lease/ hire for 4 Years<br />
Dumping area 0.50 Ha 3.00 1.50<br />
Dumping area for Batching and<br />
mixing plant<br />
0.50 Ha 3.00 1.50<br />
Temporary residential & nonresidential<br />
buildings<br />
2.00 Ha 3.00 6.00<br />
Contractors Colony 2.00 Ha 3.00 6.00<br />
Construction facilities 2.00 Ha 3.00 6.00<br />
Railway Siding Facilities 1.00 Ha 3.00 3.00<br />
Electro - mechanical Contractor 1.00 Ha 3.00 3.00<br />
Hydro -mechanical works 1.00 Ha 3.00 3.00<br />
Total (3) 10.00 30.00
4. Other Compensation<br />
I Cost <strong>of</strong> crops standing on<br />
cultivated land required @ 30% <strong>of</strong><br />
cultivated land<br />
140<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
80 Ha 1.65 132.00<br />
ii Buildings with brick walls and<br />
GGI sheet ro<strong>of</strong>ing<br />
3.00 Nos 3.00 9.00<br />
iii Compensation for trees LS 10.00<br />
Sub total (4) 151.00<br />
5. Misc. Compensation<br />
Compensation for relocating<br />
2.00<br />
electric and telephone poles<br />
Crop Compensation for LS 200.00<br />
submergence<br />
Total (5) 202.00<br />
Total (1+2+3+4+5) 823.00<br />
6. Interest on account <strong>of</strong> award for<br />
the period taking over possession<br />
<strong>of</strong> land and date <strong>of</strong> award @ 12%<br />
per year <strong>of</strong> 25% cost <strong>of</strong> land<br />
acquisition for two years<br />
7. Solatium charges for compulsory<br />
acquisition <strong>of</strong> land @ 30% <strong>of</strong> the<br />
cost <strong>of</strong> private land<br />
8. Provision for legal charges @1%<br />
on total compensation<br />
9. Labour and material required for<br />
measurement and demarcation <strong>of</strong><br />
land and properties @ 1% <strong>of</strong> land<br />
acquisition<br />
10. Establishment charges @6.25% <strong>of</strong><br />
cost <strong>of</strong> total compensation<br />
35.46<br />
177.30<br />
8.23<br />
4.70<br />
51.44<br />
Total 1100.13
S.<br />
N.<br />
ABSTRACT OF COST OF C - WORKS<br />
Description Amount (Rs. In Lakhs)<br />
141<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
civil HM total<br />
1. Diversion Tunnel 930.50 94.50 1025.00<br />
2. C<strong>of</strong>fer Dam 447.39 447.39<br />
3 Concrete Dam 2021.83 118.13 2139.96<br />
4 Spillway 5060.88 680.40 5741.28<br />
Total 8460.60 893.03 9353.62<br />
Add For Works Tax @ 2% 169.21 17.86 187.07<br />
Grand Total 8629.81 910.89 9540.70
S.<br />
No.<br />
DIVERSION TUNNEL<br />
Description Unit Qty. Rate<br />
(Rs.)<br />
142<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
Amount<br />
( Rs. in<br />
Lakhs)<br />
1.0 Surface Excavation<br />
1.1 Common excavation Cum 15,000 125 18.75<br />
1.2 Rock excavation Cum 4,000 300 12.00<br />
2.0 Underground excavation Cum 25,000 1000 250.00<br />
3.0 Rock Support System<br />
3.1 Rock bolts M 14,000 400 56.00<br />
3.2 Steel Supports MT 100 42000 42.00<br />
3.3 Shotcreting Cum 1,000 4000 40.00<br />
3.4 Concrete lagging Cum 200 7000 14.00<br />
4.0 Concrete<br />
4.1 Concrete lining M-20 Cum 4,000 4000 160.00<br />
4.2 M-15 Cum 2,200 2930 64.46<br />
4.4 M-25 Cum 2,500 3610 90.25<br />
5.0 Reinforcement MT 200 27000 54.00<br />
Sub total A 801.46<br />
6.0 Miscellaneous and ancillary works @<br />
7.5% <strong>of</strong> sub-total A<br />
7.50% 60.11<br />
Sub total B 861.57<br />
7.0 Instrumentation @ 1% <strong>of</strong> sub-total B 1.00% 8.62<br />
8.0 Dewatering @ 2% <strong>of</strong> sub total B 2.00% 17.23<br />
9.0 Contingency @ 3% <strong>of</strong> sub-total B 3.00% 25.85<br />
10.0 Work Charged establishment @ 2% <strong>of</strong><br />
Sub-total B except <strong>of</strong> lump-sum items<br />
2.00% 17.23<br />
Total 930.50
S.<br />
No.<br />
COFFER DAM<br />
Description Unit Qty. Rate<br />
(Rs.)<br />
143<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
Amount<br />
(In<br />
Lakhs)<br />
1.0 Surface Excavation<br />
1.1 Common excavation Cum 5,000 125 6.25<br />
2.0 Embankment Construction<br />
2.1 Earth/ Rockfill Cum 40,000 342 136.80<br />
2.2 Impervious Core Cum 15,000 354 53.10<br />
2.3 Filter Cum 4,000 901 36.04<br />
3.0 Concrete<br />
3.1 Concrete cut-<strong>of</strong>f wall Sqm 900 20000 180.00<br />
Sub Total (A) 412.19<br />
4.0 Miscellaneous and ancillary works<br />
@ 0.50% <strong>of</strong> sub-total A<br />
0.50% 2.06<br />
Sub Total (B) 414.25<br />
5.0 Dewatering @ 3% <strong>of</strong> sub total-B 3.00% 12.43<br />
6.0 Contingency @ 3% <strong>of</strong> sub-total-B 3.00% 12.43<br />
7.0 Work Charged establishment @ 2%<br />
<strong>of</strong> Sub-total-B except <strong>of</strong> lump-sum<br />
items<br />
2.00% 8.29<br />
Total 447.39
S.<br />
No.<br />
CONCRETE DAM<br />
144<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
Description Unit Quantity Rate Amount<br />
( Rs. in<br />
Lakhs)<br />
1.0 Surface Excavation<br />
1.1 Common excavation Cum 40,000 125 50.00<br />
1.2 Rock excavation Cum 8,000 300 24.00<br />
2.0 Rock Support system<br />
2.1 Rock bolts m 1,000 400 4.00<br />
2.2 shotcrete cum 500 4000 20.00<br />
3.0 Concrete<br />
3.1 M-15 cum 40,000 2930 1172.00<br />
3.2 M-20 cum 500 3390 16.95<br />
3.3 M-25 cum 7,000 3610 252.70<br />
4.0 Reinforcement steel MT 1,000 27000 270.00<br />
Sub Total (A) 1809.65<br />
5.0 Miscellaneous and ancillary<br />
works @ 2.5% <strong>of</strong> sub-total<br />
2.5% 45.24<br />
Sub-Total (B) 1854.89<br />
6.0 Instrumentation @ 1% <strong>of</strong> sub-total 1% 18.55<br />
7.0 Dewatering @ 3% <strong>of</strong> sub total 3% 55.65<br />
8.0 Contingency @ 3% <strong>of</strong> sub-total 3% 55.65<br />
9.0 Work Charged establishment @<br />
2% <strong>of</strong> Sub-total except <strong>of</strong> lumpsum<br />
items<br />
2% 37.10<br />
Total 2021.83
S.<br />
No.<br />
SPILLWAY<br />
145<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
Description Unit Quantity Rate (Rs.) Amount<br />
( Rs. in<br />
Lakhs)<br />
1.0 Surface Excavation<br />
1.1 Common excavation Cum 15,000 125 18.75<br />
1.2 Rock excavation Cum 2,000 300 6.00<br />
2.0 Concrete<br />
2.1 M-15 cum 50,000 2930 1465.00<br />
2.2 M-25 cum 40,000 3610 1444.00<br />
3.0 Reinforcement steel MT 6,000 27000 1620.00<br />
4.0 Structural Steel T 150 42000 63.00<br />
Sub Total (A) 4616.75<br />
5.0 Various Miscellaneous works<br />
like wire mesh/steel fibre<br />
reinforcement, drilling &<br />
grouting, PVC pipes, water<br />
stops, other steel works, slope<br />
protection works, road works,<br />
architectural works for dam etc<br />
@ 2.5% <strong>of</strong> sub-total<br />
1.5% 69.25<br />
Sub-Total (B) 4686.00<br />
6.0 Instrumentation @ 1% <strong>of</strong> sub-total 1% 46.86<br />
7.0 Dewatering @ 3% <strong>of</strong> sub total 2% 93.72<br />
8.0 Contingency @ 3% <strong>of</strong> sub-total 3% 140.58<br />
9.0 Work Charged establishment @<br />
2% <strong>of</strong> Sub-total except <strong>of</strong> lumpsum<br />
items<br />
2% 93.72<br />
Total 5060.88
146<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
J -POWER PLANT APPURTENANCES (CIVIL WORKS)<br />
S. Description Amount (Rs. in Lakhs)<br />
No. civil HM Total<br />
1. Intake Structure 937.32 276.15 1213.47<br />
2. Desilting Chamber (Including S.F.T.) 5134.61 357.74 5492.35<br />
3. Adits 2094.05 25.20 2119.25<br />
4. Head Race & Tail Race Tunnel 12933.31 40.69 12974.00<br />
5. Surge Shaft 646.87 95.55 742.42<br />
6. Pressure Shafts And Penstocks 904.93 1591.28 2496.20<br />
7. <strong>Power</strong> House Complex 7039.30 187.95 7227.25<br />
8. Switchyard 222.18 222.18<br />
Total 29912.57 2574.55 32487.11<br />
Add For Works Tax @ 2% 598.25 51.49 649.74<br />
Grand Total 30510.82 2626.04 33136.86
S.<br />
No.<br />
INTAKE STRUCTURE<br />
147<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
Description Unit Qty. Rate(Rs.) Amount<br />
( Rs. in<br />
Lakhs)<br />
1.0 Surface excavation<br />
1.1 Common excavation Cum 10,000 125 12.50<br />
1.2 Rock excavation Cum 7,000 300 21.00<br />
2.0 Underground excavation Cum 15,000 1000 150.00<br />
3 Supports System<br />
2.1 Rock bolts m 9,000 400 36.00<br />
2.2 Steel Rib Supports MT 50 42000 21.00<br />
2.3 Shotcreting Cum 400 4000 16.00<br />
2.4 Concrete lagging Cum 500 7000 35.00<br />
3.0 Concrete<br />
3.2 M15 Cum 2,000 2930 58.60<br />
3.3 M-20 Cum 500 3390 16.95<br />
3.4 M-25 Cum 10,000 3610 361.00<br />
4.0 Reinforcing Steel MT 500 27000 135.00<br />
Sub Total (A) 863.05<br />
5.0 Miscellaneous and ancillary<br />
works @ 1.5% <strong>of</strong> sub-total<br />
1.5% 12.95<br />
Sub Total (B) 876.00<br />
6.0 Instrumentation @ 1% <strong>of</strong> sub-total<br />
B<br />
1% 8.76<br />
7.0 Dewatering @ 1% <strong>of</strong> sub total B 1% 8.76<br />
8.0 Contingency @ 3% <strong>of</strong> sub-total B 3% 26.28<br />
9.0 Work Charged establishment<br />
@ 2% <strong>of</strong> Sub-total B except<br />
<strong>of</strong> lump-sum items<br />
2% 17.52<br />
Total 937.32
S.<br />
No.<br />
DESILTING CHAMBER (INCLUDING S.F.T.)<br />
148<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
Description Unit Qty. Rate (Rs.) Amount<br />
( Rs. in<br />
Lakhs)<br />
1.0 Surface excavation<br />
1.1 Common excavation Cum 5,000 125 6.25<br />
1.2 Rock excavation Cum 3,000 300 9.00<br />
2.0 Underground excavation Cum 185,000 1000 1850.00<br />
3.0 Rock Support System<br />
3.1 Rock bolts m 81,000 400 324.00<br />
3.2 Steel Rib Supports MT 300 42000 126.00<br />
3.3 Shotcreting Cum 4,600 4000 184.00<br />
3.4 Concrete lagging Cum 400 7000 28.00<br />
4.0 Concrete<br />
4.1 M15 Cum 18,000 2930 527.40<br />
4.2 M-20 Cum 1,500 3390 50.85<br />
4.3 M-25 Cum 30,000 3610 1083.00<br />
5.0 Reinforcing Steel MT 1,500 27000 405.00<br />
Sub Total (A) 4593.50<br />
6.0 Miscellaneous and ancillary<br />
works @3.5% <strong>of</strong> sub-total<br />
3.5% 160.77<br />
Sub Total (B) 4754.27<br />
7.0 Instrumentation @ 1% <strong>of</strong> sub-total<br />
B<br />
1% 47.54<br />
8.0 Dewatering @ 2% <strong>of</strong> sub total B 2% 95.09<br />
9.0 Contingency @ 3% <strong>of</strong> sub-total B 3% 142.63<br />
10.0 Work Charged establishment<br />
@ 2% <strong>of</strong> Sub-total B except<br />
<strong>of</strong> lump-sum items<br />
2% 95.09<br />
Total 5134.61
S.<br />
No.<br />
ADITS<br />
Description Unit Qty. Rate<br />
(Rs.)<br />
149<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
Amount<br />
( Rs. in<br />
Lakhs)<br />
1.0 Surface Excavation<br />
1.1 Common excavation Cum 10,000 125 12.50<br />
1.2 Rock excavation Cum 3,000 300 9.00<br />
2.0 Underground excavation Cum 90,000 1000 900.00<br />
3.0 Supports System<br />
3.1 Rock bolts m 50,000 400 200.00<br />
3.2 Steel Ribs Support MT 200 42000 84.00<br />
3.3 Shotcrete Cum 2,000 4000 80.00<br />
3.4 Concrete lagging Cum 2,500 7000 175.00<br />
4.0 Concrete<br />
4.1 Cement Concrete lining M-20 Cum 2,000 4000 80.00<br />
4.2 Concrete in portals, backfill etc.<br />
M-15 Cum 8,500 2930 249.05<br />
M-20 Cum 1,200 3610 43.32<br />
5.0 Reinforcing steel MT 150 27000 40.50<br />
Sub Total (A) 1873.37<br />
6.0 Miscellaneous and ancillary works @<br />
3.5% <strong>of</strong> sub-total A<br />
3.5% 65.57<br />
Sub-Total (B) 1938.94<br />
7.0 Instrumentation @ 1% <strong>of</strong> sub-total B 1% 19.39<br />
8.0 Dewatering @ 2% <strong>of</strong> sub total B 2% 38.78<br />
9.0 Contingency @ 3% <strong>of</strong> sub-total B 3% 58.17<br />
10.0 Work Charged establishment @ 2% <strong>of</strong><br />
Sub-total except <strong>of</strong> lump-sum items<br />
2% 38.78<br />
Total 2094.05
S.<br />
No.<br />
HEAD RACE & TAIL RACE TUNNEL<br />
150<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
Description Unit Qty. Rate (Rs.) Amount<br />
( Rs. in<br />
Lakhs)<br />
1.0 Surface excavation<br />
1.1 Common excavation Cum 15,000 125 18.75<br />
1.2 Rock excavation Cum 5,000 300 15.00<br />
2.0 Underground excavation Cum 405,000 1000 4050.00<br />
3.0 Rock Support System<br />
3.1 Rock bolts m 222,000 400 888.00<br />
3.2 Steel Rib Supports MT 1,100 42000 462.00<br />
3.3 Shotcrete Cum 11,000 4000 440.00<br />
3.4 Concrete lagging Cum 10,000 7000 700.00<br />
4.0 Concrete<br />
4.1 Cement Concrete Linning M20 Cum 60,000 4000 2400.00<br />
4.2 Concrete M15 Cum 49,000 2930 1435.70<br />
4.4 M-25 Cum 13,500 3610 487.35<br />
5.0 Reinforcement Steel MT 900 27000 243.00<br />
Sub-Total (A) 11139.80<br />
6.0 Miscellaneous and ancillary works<br />
@7.5% <strong>of</strong> sub-total A<br />
7.5% 835.49<br />
Sub-Total (B) 11975.29<br />
7.0 Instrumentation @ 1% <strong>of</strong> sub-total<br />
B<br />
1% 119.75<br />
8.0 Dewatering @ 2% <strong>of</strong> sub total B 2% 239.51<br />
9.0 Contingency @ 3% <strong>of</strong> sub-total B 3% 359.26<br />
10.0 Work Charged establishment @ 2%<br />
<strong>of</strong> Sub-total B except <strong>of</strong> lump-sum<br />
items<br />
2% 239.51<br />
Total 12933.31
S.<br />
No.<br />
SURGE SHAFT<br />
151<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
Description Unit Qty. Rate (Rs.) Amount<br />
( Rs. in<br />
Lakhs)<br />
1.0 Surface Excavation<br />
1.1 Common excavation Cum 40,000 125 50.00<br />
1.2 Rock excavation Cum 10,000 300 30.00<br />
2.0 Underground excavation<br />
2.1 Surge shaft Excavation Cum 12,000 1200 144.00<br />
2.2 Surge shaft Excavation with raise Cum 200 1500 3.00<br />
borer<br />
2.3 Concrete Lagging Cum 200 7000 14.00<br />
3.0 Support System<br />
3.1 Rock bolts m 11,000 400 44.00<br />
3.2 Steel Rib Support MT 25 42000 10.50<br />
3.3 Shotcrete Cum 500 4000 20.00<br />
4.0 Concrete<br />
4.1 M20 Cum 2,000 3390 67.80<br />
4.2 M-25 Cum 3,000 3610 108.30<br />
5.0 Steel Works<br />
5.1 Deformed Reinforcement steel MT 300 27000 81.00<br />
5.2 Steel Liner MT 25 70000 17.50<br />
Sub Total (A) 590.10<br />
6.0 Miscellaneous and ancillary works @<br />
1.5% (sub-total) A<br />
1.5% 8.85<br />
Sub Total (B) 598.95<br />
7.0 Instrumentation @ 1% <strong>of</strong> sub-total B 1% 5.99<br />
8.0 Dewatering @ 2% <strong>of</strong> sub total B 2% 11.98<br />
9.0 Contingency @ 3% <strong>of</strong> sub-total B 3% 17.97<br />
10.0 Work Charged establishment @ 2%<br />
<strong>of</strong> Sub-total B except <strong>of</strong> lump-sum<br />
items<br />
2% 11.98<br />
Total 646.87
S.<br />
No.<br />
PRESSURE SHAFTS AND PENSTOCKS<br />
152<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
Description Unit Qty. Rate (Rs.) Amount<br />
( Rs. in<br />
Lakhs)<br />
1.0 Underground excavation Cum 22,000 1200 264.00<br />
2.0 Supports System<br />
2.1 Rock bolts m 24,000 400 96.00<br />
2.2 Steel ribs support MT 175 42000 73.50<br />
2.3 Shotcrete Cum 1,000 4000 40.00<br />
3.0 Concrete<br />
3.1 Backfill concrete M15 Cum 12,000 2930 351.60<br />
Sub Total<br />
(A)<br />
825.10<br />
4.0 Miscellaneous and ancillary<br />
works @ 2.5% (sub-total)<br />
2.5% 20.63<br />
Sub Total<br />
(B)<br />
845.73<br />
5.0 Instrumentation @ 1% <strong>of</strong> sub-total B 1% 8.46<br />
6.0 Dewatering @ 1% <strong>of</strong> sub total B 1% 8.46<br />
7.0 Contingency @ 3% <strong>of</strong> sub-total B 3% 25.37<br />
8.0 Work Charged establishment @<br />
2% <strong>of</strong> Sub-total B except <strong>of</strong> lumpsum<br />
items<br />
2% 16.91<br />
Total 904.93
S.<br />
No.<br />
POWER HOUSE COMPLEX<br />
153<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
Description Unit Qty. Rate<br />
(Rs.)<br />
1.0 Under ground excavation<br />
Excavation <strong>of</strong> PH cavern, Transformer<br />
cum MIV cavern and draft tube gate<br />
Amount<br />
( Rs. in<br />
Lakhs)<br />
Cum 175,000 1000 1750.00<br />
2.0 Supports System<br />
2.1 Rock bolts m 70,000 400 280.00<br />
2.2 Steel ribs support MT 100 42000 42.00<br />
2.3 Shotcrete Cum 7,000 4000 280.00<br />
2.4 Concrete lagging Cum 1,000 7000 70.00<br />
3.0 Concrete<br />
3.1 Backfill concreteM15 Cum 1,000 2930 29.30<br />
3.2 Concrete lining M20 Cum 3,000 3390 101.70<br />
3.3 M25 Cum 52,000 3610 1877.20<br />
4.0 Reinforcing Steel MT 6,000 27000 1620.00<br />
5.0 Structural Steel. MT 350 42000 147.00<br />
6.0 Masonry Work<br />
6.1 Stone Masonry Cum 500 2000 10.00<br />
6.2 Brick Masonry Cum 1,500 2000 30.00<br />
Sub Total (A) 6237.20<br />
7.0 Miscellaneous and ancillary works<br />
@4.5% <strong>of</strong> sub-total<br />
4.5% 280.7<br />
Sub Total (B) 6517.87<br />
8.0 Instrumentation @ 1% <strong>of</strong> sub-total B 1% 65.18<br />
9.0 Dewatering @ 2% <strong>of</strong> sub total B 2% 130.36<br />
10.0 Contingency @ 3% <strong>of</strong> sub-total B 3% 195.54<br />
11.0 Work Charged establishment @ 2% <strong>of</strong><br />
Sub-total B except <strong>of</strong> lump-sum items<br />
2% 130.36<br />
Total 7039.30
S.<br />
No.<br />
SWITCHYARD<br />
154<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
Description Unit Qty. Rate<br />
(Rs.)<br />
Amount<br />
( Rs. in<br />
Lakhs)<br />
1.0 Surface excavation<br />
1.1 Common excavation Cum 10,000 125 12.50<br />
1.2 Rock excavation Cum 4,000 300 12.00<br />
3.0 Supports System<br />
3.1 Rock bolts m 1,000 400 4.00<br />
3.2 Shotcrete Cum 50 4000 2.00<br />
4.0 Earthwork in filling Cum 25,000 342 85.50<br />
5.0 Concrete<br />
5.1 M15 Cum 1,000 2930 29.30<br />
5.2 M20 Cum 1,000 3390 33.90<br />
6.0 Reinforcing Steel MT 50 27000 13.50<br />
7.0 Masonry Work<br />
Stone Masonry/Brick Masonry Cum 300 2000 6.00<br />
Sub Total (A) 198.70<br />
8.0 Miscellaneous and ancillary works<br />
@4.5% <strong>of</strong> sub-total A<br />
4.5% 8.94<br />
Sub Total (B) 207.64<br />
9.0 Dewatering @ 2% <strong>of</strong> sub total B 2% 4.15<br />
10.0 Contingency @ 3% <strong>of</strong> sub-total B 3% 6.23<br />
11.0 Work Charged establishment @ 2% <strong>of</strong><br />
Sub-total B except <strong>of</strong> lump-sum items<br />
2% 4.15<br />
Total 222.18
S.<br />
No.<br />
HYDRO MECHANICAL EQUIPMENT<br />
155<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
Detail <strong>of</strong> Items Unit Qnty. Rate (Rs.) Amount<br />
(Rs. In<br />
Lakh )<br />
1 Diversion tunnel gate & hoist<br />
Gate(Fixed wheel type) including ballast-<br />
(3.0mx6.5m)-2 Nos.<br />
Ton 40 60000 24.00<br />
Embedded Parts -2 Sets Ton 12 50000 6.00<br />
Ropedrum hoist 55 T Capacity -2 Nos. Ton 40 100000 40.00<br />
Hoist platform and trestle - 2 Nos. Ton 40 50000 20.00<br />
2 Spillway structure<br />
a) Radial Gates (5.0m x 8.0m) - 4 Nos. Ton 240 100000 240.00<br />
Embedded Parts (including anchorages,<br />
hoist structure) including breast wall liners -<br />
4 Sets<br />
Ton 152 50000 76.00<br />
Hydraulic Hoist (One power pack + Two<br />
80T Cap. Hydraulic cylinders with<br />
provision <strong>of</strong> 25% pushing force)<br />
Set 4 6000000 240.00<br />
Portable oil filter unit along with<br />
Contamination checking kit & Low<br />
vacuum dehydration and degassification<br />
unit<br />
Portable trolley mounted gasoline engine<br />
operated power pack<br />
Set 1 750000 7.50<br />
Set 1 1000000 10.00<br />
Spillway Stoplogs( slide type) - 5.0m x<br />
10.0m - 1 Set<br />
Ton 40 60000 24.00<br />
Embedded Parts - 4 Sets Ton 48 50000 24.00<br />
Lifting Beam - 1 No. Ton 3 50000 1.50<br />
Gantry crane 25 T capacity Set 1 2500000 25.00<br />
3 Intake structure<br />
a) Trash rack cleaning machine Set 1 10000000 100.00<br />
TrashRacks and Embedded Parts including<br />
raking guides<br />
Ton 40 50000 20.00
156<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
b) Intake Bulkhead Gate( slide type) -4.5m x<br />
4.5m - 2 Nos.<br />
Ton 30 60000 18.00<br />
Embedded Parts - 2 Sets Ton 8 50000 4.00<br />
Ropedrum hoist 30T Capacity - 2 Nos.<br />
Hoist platform and trestles (Included in the<br />
intake service gate)<br />
Ton 20 100000 20.00<br />
b) Intake service gate(fixed wheel type)<br />
including ballast - 4.5m x 4.5m - 2Nos.<br />
Ton 60 60000 36.00<br />
Embedded Parts - 2 Sets Ton 10 50000 5.00<br />
Ropedrum hoist 60T Capacity - 2 Nos. Ton 40 100000 40.00<br />
Hoist platform and trestles (Including<br />
bulkhead gate) - 2 Sets<br />
Ton 40 50000 20.00<br />
4 Desilting Chamber gate ( slide type) -<br />
6.0m x 6.0m - 1 No.<br />
Ton 27 60000 16.20<br />
Embedded Parts - 2 Sets Ton 15 50000 7.50<br />
EOT Crane 50T Capacity Set 1 4500000 45.00<br />
5 Silt Flushing gates (slide type)<br />
Gates (service & emergency) -3.0m x 2.0m<br />
- 4 Nos.<br />
Embedded Parts (including bonnet,bonnet<br />
cover, gate body liner etc) - 4 Sets<br />
Hydraulic Hoist (Two double acting<br />
cylinders 240T capacity each and one<br />
power pack)<br />
Ton 32 100000 32.00<br />
Ton 120 50000 60.00<br />
Set 2 9000000 180.00<br />
6 Surge shaft gate & hoist<br />
Gate(Slide Type)- 4.0m x 6.0m - 2 Nos. Ton 60 60000 36.00<br />
Embedded parts- 2 Sets Ton 30 50000 15.00<br />
Rope drum hoist 50T Cap. - 2 Nos. Ton 30 100000 30.00<br />
Hoist platform and trestle- 2 Sets Ton 20 50000 10.00<br />
7 Draft Tube gates & hoist<br />
Gate(Fixed wheel type)- 6.0m x 6.0m - 4<br />
Nos.<br />
Ton 140 60000 84.00<br />
Embedded Parts - 4 Sets Ton 40 50000 20.00<br />
Rope drum hoist 50 T Cap.- 4 Nos. Ton 60 100000 60.00
157<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
Hoist platform and trestle- 4 Sets Ton 30 50000 15.00<br />
8 Tail race gates & hoist<br />
Gate(Slide Type) - 6.0m x 6.0m - 1 No. Ton 25 60000 15.00<br />
Embedded Parts - 1 Set Ton 7.5 50000 3.75<br />
Rope drum hoist 50 T Cap.- 1 No. Ton 15 100000 15.00<br />
Hoist platform and trestle - 1 Set Set 10 50000 5.00<br />
9 Pressure shaft steel Liner<br />
Ferrules (ASTM A 537Cl-I) - 2 Sets Ton 2000 70000 1400.00<br />
Bifurcation, (ASTM A 517Gr. F) - 2 Sets Ton 150 77000 115.50<br />
10 Adit Gates<br />
Adit gates - 2.5m x 2.5m - 3 Nos. Ton 30 60000 18.00<br />
Embedded Parts - 3 Sets Ton 12 50000 6.00<br />
11 Instruments and Remote Control Set 1 10000000 100.00<br />
12 D G Set 250 KVA Set 1 1250000 12.50<br />
13 Spare parts & contingency (5% <strong>of</strong> total<br />
cost)<br />
5% 165.12<br />
Total 3467.57
S.<br />
No.<br />
K - BUILDINGS<br />
Description <strong>of</strong> Buildings Plinth<br />
Area<br />
158<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
Rs.in<br />
lakhs<br />
Rate Unit Amount<br />
1.0 Residential Buildings<br />
i Permanent residential buildings 3960 0.075 Sqm 297.00<br />
Service Charges @ 31% 92.07<br />
ii Temporary residential buildings 3970 0.065 Sqm 258.05<br />
Service Charges @ 27% 69.67<br />
Residential Buildings 7930 716.79<br />
2.0 Non - Residential Buildings<br />
i Non residential permanent buildings 3485 0.065 Sqm 226.53<br />
Service Charges @ 22.5% 50.97<br />
ii Non residential and other purposes<br />
temporary buildings<br />
4105 0.055 Sqm 225.78<br />
Service Charges @ 20.5% 46.28<br />
Total Non - residential Buildings 7590 549.55<br />
Total 15520 1266.35<br />
Add Works Tax @ 2% 25.33<br />
Grand Total 1291.67
S.<br />
No.<br />
O-MISCELLANEOUS<br />
159<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
(Rs. In Lakh)<br />
Description Quantity Unit Rate Amount<br />
1.0 CAPITAL COST<br />
1.1 Purchase <strong>of</strong> Diesel Generator Sets<br />
(25 KVA) including ancillary<br />
equipments etc.<br />
1.2 Cost <strong>of</strong> transmission line for<br />
construction power<br />
1.2 Water Supply, purification &<br />
distribution arrangements including<br />
purchase <strong>of</strong> water tankers, filters,<br />
cost <strong>of</strong> tanks & chlorination.<br />
1.4 Providing sewage disposal and<br />
storm water drains in <strong>of</strong>fice and<br />
residential complexes.<br />
1.5 Providing & fixing <strong>of</strong> fire fighting<br />
equipments.<br />
3.00 Nos 2.50 7.50<br />
15.00 km 10.00 150.00<br />
LS 30.00<br />
LS 25.00<br />
LS 20.00<br />
1.6 Providing telephone, Telegraph<br />
<strong>of</strong>fice, Post <strong>of</strong>fice and Wireless<br />
equipments.<br />
LS 20.00<br />
1.7 Providing hospital equipments. LS 15.00<br />
1.8 Construction <strong>of</strong> children park and<br />
welfare centres for <strong>of</strong>ficials and<br />
labourers.<br />
LS 8.00<br />
1.9 Furnishing and equipping <strong>of</strong> rest<br />
houses and field hostels <strong>of</strong> <strong>of</strong>ficers<br />
and staff.<br />
1.10 Purchase <strong>of</strong> furniture and other<br />
articles for labour welfare centres<br />
and clubs and schools.<br />
1.11 Purchase <strong>of</strong> equipment for quality<br />
control/field Laboratories<br />
LS 5.00<br />
LS 5.00<br />
LS 15.00<br />
Sub Total Item 1 300.50
2.0 MAINTENANCE & SERVICE CHARGES<br />
OF<br />
2.1 R&M <strong>of</strong> Diesel Generator sets 3<br />
Nos. for five years.<br />
2.2 R&M <strong>of</strong> Transmission line for five<br />
years.<br />
2.3 R&M <strong>of</strong> water supply facilities to<br />
the staff and labour colonies<br />
2.4 R&M <strong>of</strong> sanitation and drainage<br />
facilities for <strong>of</strong>fice and residential<br />
complex and labour colonies.<br />
160<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
15.00 Nos 5.00 75.00<br />
20.00 km 5.00 100.00<br />
LS 10.00<br />
LS 8.00<br />
2.5 R&M <strong>of</strong> fire fighting equipments. LS 4.00<br />
2.6 Maint. Of telecommunication<br />
system and post <strong>of</strong>fices.<br />
LS 20.00<br />
2.7 R&M <strong>of</strong> hospitals. LS 16.00<br />
2.8 Maint. <strong>of</strong> parks and welfare centres,<br />
clubs and school.<br />
LS 10.00<br />
2.9 R&M <strong>of</strong> Rest houses and field<br />
hostels.<br />
LS 8.00<br />
2.10 R&M <strong>of</strong> research & quality control<br />
laboratories<br />
LS 8.00<br />
2.11 Labour welfare compensation and<br />
retrenchment benefits.<br />
LS 40.00<br />
2.12 Providing Security & Policing LS 8.00<br />
2.13 R&M <strong>of</strong> Inspection vehicles and<br />
staff cars (25 nos) for five<br />
years<br />
25*5 year 2.50 312.50<br />
2.14 R&M <strong>of</strong> school buses, Ambulance<br />
Car etc. (4 nos) for five years<br />
4*5 year 1.80 36.00<br />
Sub Total Item 2 655.50<br />
3.0 MISCELLANEOUS<br />
3.1 Foundation stone laying ceremony,<br />
inauguration and visit <strong>of</strong><br />
Dignitaries.<br />
LS 30.00<br />
3.2 Railway siding LS 20.00<br />
3.3 Installation and maintenance <strong>of</strong><br />
Petrol/Diesel Pumps<br />
LS 16.00
161<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
3.4 Providing anti malarial measures LS 2.00<br />
3.5 Procurement <strong>of</strong> technical literature. LS 2.00<br />
3.6 Model Exhibits LS 4.00<br />
3.7 Canteen facilities and co-operative<br />
LS 12.00<br />
stores.<br />
3.8 Photographic and Cinematographic<br />
equipment and their maintenance<br />
LS 8.00<br />
3.9 Group insurance LS 15.00<br />
3.10 Publication and pamphlets LS 2.00<br />
3.11 Creches LS 2.00<br />
3.12 Compensation for accident LS 8.00<br />
3.13 Training <strong>of</strong> personnels aboard<br />
including study course and visit<br />
LS 15.00<br />
3.14 Award to workers LS 1.5<br />
Sub Total Item 3 137.50<br />
Grand Total Item (1+2+3) 1093.50
Q-Spl T&P for Infrastructure Development<br />
Sl.No. Description <strong>of</strong> equipment Quantity<br />
(Nos.)<br />
162<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
(Rs in Lacs)<br />
Rate Amount<br />
1 Hydraulic Excavator, 1.0 cum. 1 50.00 50.00<br />
2 Loader cum Excavator, 1.0/0.25<br />
cum.<br />
1 20.00 20.00<br />
3 Crawler Dozer, 100 FHP 2 50.00 100.00<br />
4 Wheel dozer 300 HP 1 95.00 95.00<br />
5 Motor Grader, 145 FHP 1 60.00 60.00<br />
6 Diamond Core Drill (Mechanical) 2 15.00 30.00<br />
7 Diamond Core Drill (Hyd) 1 60.00 60.00<br />
8 Air Track/Wagon Drill 2 16.00 32.00<br />
9 Jack Hammer/Pavement Breaker 5 0.35 1.75<br />
10 Compressed Air (cfm) 2000 0.0125 25.00<br />
11 Mobile Crane, 10 t Pick & Carry 2 10.00 20.00<br />
12 Mobile Crane, 20 t (Rough terrain) 1 70.00 70.00<br />
13 Road Roller, 8/10 t 2 10.00 20.00<br />
14 Dewatering Pump L.S 20.00 20.00<br />
15 Tipper 4.5/6.0 cum. 4 10.00 40.00<br />
16 Truck, 10 t 4 8.00 32.00<br />
17 Low Bed Tractor Trailor, 30 t 1 50.00 50.00<br />
18 Concrete Mixer, 14/10 cft 2 2.00 4.00<br />
19 Explosive Van, 10 t 1 12.00 12.00<br />
20 Water Tanker/Sprinkler, 10 KL 1 15.00 15.00<br />
21 Petrol/Diesel Tanker, 10 KL 1 12.00 12.00<br />
22 Bus/Mini Bus 5 10.00 50.00<br />
23 Car/MUV 4 5.50 22.00<br />
24 Jeep (Petrol/Diesel) 20 4.50 90.00<br />
25 Ambulance 2 10.00 20.00<br />
26 Workshop Equipment L.S 20.00 20.00<br />
27 Fire Tender 1 15.00 15.00<br />
28 Recovery Van 1 5.00 5.00<br />
29 Pick up Van/L.C.V 2 5.00 10.00<br />
1000.75
S.<br />
No.<br />
163<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
R - COMMUNICATION<br />
Description Quantity Unit<br />
Rs. In Lakhs<br />
Rate Amount<br />
1 Improvement/Reconstruction <strong>of</strong><br />
bridges on existing District Road<br />
from Mangan to Lingza<br />
Bridges<br />
Bridge on Lingza road 2.0 Nos 30.00 60.00<br />
Bridge across the river Rangyong<br />
Roads<br />
120.0 m 2.25 270.00<br />
To lingza 4.0 Km 60.00 240.00<br />
Widening on curves 6.0 Nos 1.50 9.00<br />
Suspension Bridge to Rungto<br />
(Adit-II)<br />
1.5 Km 60.00 90.00<br />
Rungto (Adit-II) to Laven (Adit-I) 4.5 Km 60.00 270.00<br />
2 Proposed new roads<br />
Approach road to dam site, DT,<br />
Top <strong>of</strong> Dam<br />
3.0 Km 80.00 240.00<br />
Approach road to power house site 0.8 Km 80.00 64.00<br />
Switch yard 1.0 Km 75.00 75.00<br />
Surge shaft 2.0 Km 75.00 150.00<br />
Adit-III/II/I 4.6 Km 75.00 345.00<br />
Colony Roads 2.0 Km 75.00 150.00<br />
3 Proposed new bailey bridges Cl<br />
30<br />
At Dam site 40.0 m 2.25 90.00<br />
Grand Total 2053.00<br />
Add Works Tax @ 2% 41.06<br />
Grand Total 2094.06
S.<br />
No.<br />
V - RECEIPT & RECOVERIES<br />
Item Amount<br />
164<br />
(Rs. In Lakhs)<br />
1. Recovery from the Sale <strong>of</strong> Equipments 190.10<br />
2. Recovery from Resale <strong>of</strong> DG Sets 1.50<br />
3. Recovery from Temporary Building 89.97<br />
Total 281.57<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)
165<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
ELECTRO MECHANICAL WORKS<br />
Annex-I Page 1 <strong>of</strong> 2<br />
Generator, Turbine and Accessories<br />
S.N Item Particulars Qty Unit Rate Amount<br />
Dec 2003 Price Level<br />
Excise Duty* Total<br />
(Rs in Rate Amount (Rs. In<br />
Lakh) % (Rs. In<br />
Lakh)<br />
Lakh)<br />
1 2 3 3(a) 4 5 6 7 5+7<br />
1 (a) Generating units and Bus Ducts 4 no. 4600.00 9200.00 16 1472.00 10672.00<br />
4X50 MW, 500 rpm, Head 312<br />
meters<br />
Rs/KW<br />
2<br />
3<br />
4<br />
Step up transformer,3 phase 11/ 220<br />
KV, 62 MVA,<br />
Auxiliary Electrical Equipment for<br />
<strong>Power</strong> Stations (Except<br />
Transformer) (5% <strong>of</strong> item 1)<br />
Auxiliary Equipment & Services for<br />
<strong>Power</strong> stations (5% <strong>of</strong> Item 1)<br />
4 no. 220.00 545.60 16 87.30 632.90<br />
460 16 73.6 533.60<br />
460 16 73.6 533.60<br />
5 Spares (5% <strong>of</strong> 1 and 3% <strong>of</strong> 2 to 4) ) 460 43.97 503.97 16 80.635 584.60<br />
6 SUB TOTAL(1-5)<br />
12956.70<br />
7 Central Sales tax **4% <strong>of</strong> item 6 518.27<br />
8<br />
9<br />
Transportation & Insurance 6% <strong>of</strong><br />
item 6<br />
Erection & commissioning 8% <strong>of</strong><br />
item 6 Excluding spares<br />
10 Sub total item 6,7, 8,9<br />
11 Total <strong>of</strong> FC(GIS,XLPE Cable and<br />
Termination kit) in INR(As per<br />
Annexure-I)<br />
12 Custom Duty @22% <strong>of</strong> item 11 included in above item 11<br />
13 Marine frieght and insurance @6%<br />
Approx <strong>of</strong> 11<br />
14 Inland Frieght and insurance 6% <strong>of</strong><br />
item 11<br />
15 Erection & commissioning 8% <strong>of</strong><br />
item 11 Excluding spares<br />
16 SUB TOTAL <strong>of</strong> FC ( item<br />
11,12,13,14,15, in INR)<br />
17 Subtotal <strong>of</strong> item no 16+10(Foreign<br />
plus indian component)<br />
18 Establishment,Contingency,other<br />
charges (11% <strong>of</strong> Item17 excluding<br />
duties)<br />
GRAND TOTAL (Rs in Lakh)<br />
777.40<br />
989.77<br />
15242.14<br />
3445.98<br />
206.76<br />
206.76<br />
275.52<br />
4135.01<br />
19377.15<br />
1539.36<br />
20916.51
166<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
Annex-I Page 2 <strong>of</strong> 2<br />
S.N Item Particulars Qty Rate Amount Custom Duty* Total<br />
( USD in<br />
Lakh)<br />
Rate<br />
%<br />
Amount (<br />
USD in<br />
Lakh)<br />
(USD in<br />
Lakh)<br />
1 2 3 4 5 6 7 5+7<br />
1 220 KV GIS BAY<br />
6.521<br />
(USD in<br />
45.65 22 10.04 55.69<br />
7<br />
Lakh)<br />
2 XLPE Cable (220 kV) 350 m 280.00 9.80 22 2.16 11.96<br />
0<br />
(USD)<br />
3 XLPE Cable termination Kit<br />
no. 35000.00 4.90 22 1.08 5.98<br />
14<br />
(USD)<br />
4 Spares for above @ 3% <strong>of</strong> 1 & 2<br />
1.66 22 0.37 2.03<br />
Total 62.01 75.65<br />
*Custom duty in case <strong>of</strong><br />
**Not applicable for Imported<br />
1 USD conversion rate as on 15/12/03= 45.55<br />
POWER EVACUATION SYSTEM<br />
Dec 2003 Price Level<br />
Annex-II (page 1 <strong>of</strong> 1)<br />
S.N Item Particulars Qty Rate Amoun Total<br />
(Rs (Rs Rate Amount (Rs<br />
1 2 3 4 5 6 7 5+7<br />
1 220kV Double Circuit line 5 km 22.00 110.00 16 17.60 127.60<br />
3 Spares ( 3% <strong>of</strong> 1 ) 3.3 16 0.528 3.83<br />
4 Subtotal(1) 131.43<br />
5 Central Sales tax **4% <strong>of</strong> item 4 #REF! 5.26<br />
6 Transportation & Insurance 6%<br />
<strong>of</strong> item 4 7.89<br />
7 Erection & commissioning 8%<br />
<strong>of</strong> item 4 except spares 10.21<br />
8 Subtotal(2) 154.78<br />
9 Establishment,Contingency,<br />
other charges (11% <strong>of</strong> Item 8)<br />
12.46<br />
GRAND TOTAL (In Lacs) 167.24<br />
*Custom duty in case <strong>of</strong><br />
**Not applicable for Imported<br />
1 USD conversion rate as on 15/12/03= 45.55
167<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)
CHAPTER – XIII<br />
ECONOMIC EVALUATION<br />
167<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
13.1 GENERAL<br />
The Project has been contemplated as a run-<strong>of</strong>f the river scheme on river Tolung Chu /<br />
Rangyong. The project is estimated to cost Rs. 764.94 crores excluding IDC at June<br />
2003 Price Level. Sale price <strong>of</strong> energy generated at powerhouse bus bars has been<br />
worked out as 2.45 Rs. per unit (Table 13.2) & without free power to state government<br />
comes to Rs. 2.15 per unit (Table 13.2-A).<br />
13.2 ECONOMIC JUSTIFICATION:<br />
The energy generation <strong>of</strong> the project with an installed capacity <strong>of</strong> 4 X 50 MW has been<br />
estimated at 762 MU in a 90% dependable year.<br />
13.3 COST ESTIMATES AND PHASING OF EXPENDITURES<br />
The cost <strong>of</strong> construction <strong>of</strong> the project has been estimated at June 2003 price level with a<br />
construction schedule <strong>of</strong> 6.5 years including 1.5 years for Infrastructure works.<br />
The estimated Present Day Cost <strong>of</strong> the project is Rs. 764.94 Crores without IDC at June<br />
2003 Price level.<br />
13.4 PHASING OF EXPENDITURE<br />
The phasing <strong>of</strong> expenditure has been worked out on the basis <strong>of</strong> anticipated construction<br />
programme.<br />
The phasing <strong>of</strong> expenditure without IDC for the present cost is shown as below:
Year Estimated Cost at June 2003 P.L.<br />
(Rs. in Crores)<br />
1 st 30.60<br />
2 nd 68.84<br />
3 rd<br />
168<br />
99.44<br />
4 th 130.04<br />
5 th 191.24<br />
6 th 145.34<br />
6.5 th 99.44<br />
Net Cost 764.94<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
13.5 INTEREST DURING CONSTRUCTION (IDC)<br />
Based upon above phasing <strong>of</strong> expenditure the interest during construction (IDC) have<br />
been calculated with 70:30 debt equity ratio and 10.0% interest on loan. (Table 13.1)<br />
The estimated IDC with estimated present cost is Rs 81.14 Crores<br />
13.6 COST OF ENERGY GENERATION<br />
The cost <strong>of</strong> energy generation has been calculated for the annual energy generation in a<br />
90% dependable year based upon following assumptions.<br />
1. Debt-equity ratio 70 : 30<br />
2. Annual interest rate on loan 10.0%<br />
3. Return on equity 16%<br />
4. Annual interest rate on working capital 10.0%<br />
5. O&M Charges 1.5% <strong>of</strong> Project Cost<br />
6. Free power to Home State 12% <strong>of</strong> the energy<br />
available after losses
169<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project, (4 x 50 MW)<br />
7. Depreciation considered 1/12 th <strong>of</strong> loan amount<br />
during loan repayment<br />
period.<br />
The levellised tariff <strong>of</strong> the Project at present day cost works out to be Rs. 1.99 Per Unit<br />
(Table 13.3) & tariff without free power to state government comes to Rs. 1.75 per unit<br />
(Table 13.3-A).
170<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
STATEMENT SHOWING IDC CALCULATION AT PRESENT DAY COST (JUNE 2003 LEVEL)<br />
Table-13.1<br />
PRESENT DAY COST 764.94 Crs. Electrical Works 209.17 Crs.<br />
Civil Works 554.10 Crs. Transmission cost 1.67 Crs.<br />
INTEREST RATE PER ANNUM 10%<br />
(Rs. in Crs.)<br />
Present Day Amount Receivable I.D.C Loan Outstanding Amount Receivable<br />
Year Cost Equity Loan at the end <strong>of</strong> Equity Loan<br />
year (for the year)<br />
1 2 3 4 5 6 7 8<br />
1 30.60 30.60 30.60<br />
2 68.84 68.84 68.84<br />
3 99.44 99.44 99.44<br />
4 130.04 54.94 75.10 2.17 77.27 54.94 77.27<br />
5 191.24 191.24 17.29 285.79 208.52<br />
6 145.34 145.34 35.85 466.98 181.19<br />
6.5 99.44 99.44 25.83 592.26 125.28<br />
Total 764.94 253.82 511.12 81.14 253.82 592.26<br />
IDC 81.14 Crs. Equity 253.82 Crs.<br />
Net cost <strong>of</strong> the<br />
project 846.08 Crs. Loan 592.26 Crs.
171<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
Table-13.2<br />
UNIT COST OF ENERGY AT BUS BAR AT CURRENT PRICE LEVEL<br />
(June 2003 P.L.)<br />
(Based on 16% return on equity & 10% interest on loan, 10% interest on working capital)<br />
1 Installed capacity 200 MW<br />
2 Cost <strong>of</strong> the Project (Net) Rs. 764.94 Crores<br />
3 Interest During Construction Rs. 81.14 Crores<br />
4 Total Cost <strong>of</strong> Project Rs. 846.08 Crores<br />
(Including IDC)<br />
a) Equity 30% Rs. 253.82 Crores<br />
b) Loan 70% Rs. 592.26 Crores<br />
5 Annual Energy Generation 762.00 MU<br />
6 0.7% As Auxiliary Consumption <strong>of</strong> No. 5 0.70% 5.33 MU<br />
7 Energy Available After Auxiliary Consumption 756.67 MU<br />
8 0.5% As Transformer Loss <strong>of</strong> No. 7 0.50% 3.78 MU<br />
9 Energy Available After Transformer Loss 752.88 MU<br />
10 Free <strong>Power</strong> to Home State 12% 90.35 MU<br />
11<br />
Energy Available After Allowing Free<br />
<strong>Power</strong> 662.54 MU<br />
12 Fixed and Running Charges<br />
A) Capacity Charges<br />
a) Interest on Loan 10.00% 56.76 Crores<br />
b) Depreciation Charges<br />
(Limited to 1/12 th <strong>of</strong> Loan Amount)<br />
49.35 Crores<br />
Sub-Total 106.11 Crores<br />
B) Energy Charges<br />
a) O&M Charges 1.50% 12.69 Crores<br />
b) Return on Equity 16.00% 40.61 Crores<br />
Sub-Total 53.30 Crores<br />
c) Interest on Working Capital 10.00% 2.81 Crores<br />
I) O&M Charges for 1 month 1.06<br />
II) 2 Months Average Billing 27.04<br />
Total Rs. 162.22 Crores<br />
13 Sale Price at Bus Bar/Unit 2.45 Rs.<br />
14 Cost <strong>of</strong> Generation at Bus Bar/Unit 1.62 Rs.<br />
(Without Allowing Free <strong>Power</strong> to Home State and Return on Equity)<br />
Note : This unit rate is excluding water cess, income tax incentive, penalties etc.
172<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
Table-13.2 A<br />
UNIT COST OF ENERGY AT BUS BAR AT CURRENT PRICE LEVEL<br />
(June 2003 P.L.) WITHOUT FREE POWER TO HOME STATE<br />
(Based on 16% return on equity & 10% interest on loan, 10% interest on working capital)<br />
1 Installed capacity 200 MW<br />
2 Cost <strong>of</strong> the Project (Net) Rs. 764.94 Crores<br />
3 Interest During Construction Rs. 81.14 Crores<br />
4 Total Cost <strong>of</strong> Project Rs. 846.08 Crores<br />
(Including IDC)<br />
a) Equity 30% Rs. 253.82 Crores<br />
b) Loan 70% Rs. 592.26 Crores<br />
5 Annual Energy Generation 762.00 MU<br />
6 0.7% As Auxiliary Consumption <strong>of</strong> No. 5 0.70% 5.33 MU<br />
7 Energy Available After Auxiliary Consumption 756.67 MU<br />
8 0.5% As Transformer Loss <strong>of</strong> No. 7 0.50% 3.78 MU<br />
9 Energy Available After Transformer Loss 752.88 MU<br />
10 Free <strong>Power</strong> to Home State 0% 0.00 MU<br />
11<br />
Energy Available After Allowing Free<br />
<strong>Power</strong> 752.88 MU<br />
12 Fixed and Running Charges<br />
A) Capacity Charges<br />
a) Interest on Loan 10.00% 56.76 Crores<br />
b) Depreciation Charges<br />
(Limited to 1/12 th <strong>of</strong> Loan Amount)<br />
49.35 Crores<br />
Sub-Total 106.11 Crores<br />
B) Energy Charges<br />
a) O&M Charges 1.50% 12.69 Crores<br />
b) Return on Equity 16.00% 40.61 Crores<br />
Sub-Total 53.30 Crores<br />
c) Interest on Working Capital 10.00% 2.81 Crores<br />
I) O&M Charges for 1 month 1.06<br />
II) 2 Months Average Billing 27.04<br />
Total Rs. 162.22 Crores<br />
13 Sale Price at Bus Bar/Unit 2.15 Rs.<br />
14 Cost <strong>of</strong> Generation at Bus Bar/Unit 1.62 Rs.<br />
(Without Allowing Free <strong>Power</strong> to Home State and Return on Equity)<br />
Note : This unit rate is excluding water cess, income tax incentive, penalties etc.
173<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
CALCULATION OF ENERGY RATE WITH PRESENT COST (JUNE 2003 PRICE LEVEL) AS PER TARIFF NOTIFICATION<br />
Table-13.3<br />
Annual Generation in a 90% dependable 762 MU O&M Charges 1.50%<br />
Annual Generation after allowing losses& Rate <strong>of</strong> increase <strong>of</strong> O&M Charges after 1st Year (Compounded) 6%<br />
power to home state in a 90% dependable 662.54 MU Interest rate on 10.0%<br />
Total cost including IDC Rs. 846.08 Crores Interest rate on Working 10.00%<br />
Equity 30% Rs. 253.82 Crores Return on 16%<br />
Loan 70% Rs. 592.26 Crores Discounting rate 12%<br />
YEAR CAPACITY (Rs.in Cr.) CHARGES PER UNIT Discounting Discounted<br />
Out- (Rs.in Cr.) (Rs. per Factor Tariff<br />
standing Interest Depre- Total Return O&M Interest on Working Capital Total Capacity Energy Total<br />
(Paisa per<br />
Loan on loan ciation on Charges O&M 2months Interest charges charges Unit)<br />
(Rs.in<br />
equity<br />
1 month Average<br />
Billing<br />
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16<br />
1 592.26 56.76 49.35 106.11 40.61 12.69 1.06 27.04 2.81 56.11 1.60 0.85 2.45 1.0000 2.45<br />
2 542.90 51.82 49.35 101.18 40.61 13.45 1.12 26.33 2.75 56.81 1.53 0.86 2.38 0.8929 2.13<br />
3 493.55 46.89 49.35 96.24 40.61 14.26 1.19 25.63 2.68 57.55 1.45 0.87 2.32 0.7972 1.85<br />
4 444.19 41.95 49.35 91.31 40.61 15.12 1.26 24.94 2.62 58.35 1.38 0.88 2.26 0.7118 1.61<br />
5 394.84 37.02 49.35 86.37 40.61 16.02 1.34 24.26 2.56 59.19 1.30 0.89 2.20 0.6355 1.40<br />
6 345.48 32.08 49.35 81.44 40.61 16.98 1.42 23.59 2.50 60.10 1.23 0.91 2.14 0.5674 1.21<br />
7 296.13 27.15 49.35 76.50 40.61 18.00 1.50 22.93 2.44 61.06 1.15 0.92 2.08 0.5066 1.05<br />
8 246.77 22.21 49.35 71.56 40.61 19.08 1.59 22.27 2.39 62.08 1.08 0.94 2.02 0.4523 0.91<br />
9 197.42 17.27 49.35 66.63 40.61 20.23 1.69 21.63 2.33 63.17 1.01 0.95 1.96 0.4039 0.79<br />
10 148.06 12.34 49.35 61.69 40.61 21.44 1.79 21.00 2.28 64.33 0.93 0.97 1.90 0.3606 0.69<br />
11 98.71 7.40 49.35 56.76 40.61 22.73 1.89 20.39 2.23 65.57 0.86 0.99 1.85 0.3220 0.59<br />
12 49.35 2.47 49.35 51.82 40.61 24.09 2.01 19.78 2.18 66.88 0.78 1.01 1.79 0.2875 0.52<br />
13 7.36 7.36 40.61 25.54 2.13 12.49 1.46 67.61 0.11 1.02 1.13 0.2567 0.29<br />
14 7.36 7.36 40.61 27.07 2.26 12.76 1.50 69.18 0.11 1.04 1.16 0.2292 0.26<br />
15 7.36 7.36 40.61 28.69 2.39 13.03 1.54 70.85 0.11 1.07 1.18 0.2046 0.24<br />
16 7.36 7.36 40.61 30.42 2.53 13.33 1.59 72.61 0.11 1.10 1.21 0.1827 0.22<br />
17 7.36 7.36 40.61 32.24 2.69 13.64 1.63 74.48 0.11 1.12 1.24 0.1631 0.20<br />
18 7.36 7.36 40.61 34.17 2.85 13.97 1.68 76.47 0.11 1.15 1.27 0.1456 0.18<br />
19 7.36 7.36 40.61 36.22 3.02 14.32 1.73 78.57 0.11 1.19 1.30 0.1300 0.17<br />
20 7.36 7.36 40.61 38.40 3.20 14.69 1.79 80.80 0.11 1.22 1.33 0.1161 0.15<br />
21 7.36 7.36 40.61 40.70 3.39 15.09 1.85 83.16 0.11 1.26 1.37 0.1037 0.14<br />
22 7.36 7.36 40.61 43.14 3.60 15.50 1.91 85.67 0.11 1.29 1.40 0.0926 0.13<br />
23 7.36 7.36 40.61 45.73 3.81 15.95 1.98 88.32 0.11 1.33 1.44 0.0826 0.12<br />
24 7.36 7.36 40.61 48.48 4.04 16.42 2.05 91.13 0.11 1.38 1.49 0.0738 0.11<br />
25 7.36 7.36 40.61 51.39 4.28 16.91 2.12 94.12 0.11 1.42 1.53 0.0659 0.10<br />
26 7.36 7.36 40.61 54.47 4.54 17.44 2.20 97.28 0.11 1.47 1.58 0.0588 0.09<br />
27 7.36 7.36 40.61 57.74 4.81 18.00 2.28 100.63 0.11 1.52 1.63 0.0525 0.09<br />
28 7.36 7.36 40.61 61.20 5.10 18.59 2.37 104.18 0.11 1.57 1.68 0.0469 0.08<br />
29 7.36 7.36 40.61 64.87 5.41 19.22 2.46 107.95 0.11 1.63 1.74 0.0419 0.07<br />
30 7.36 7.36 40.61 68.77 5.73 19.88 2.56 111.94 0.11 1.69 1.80 0.0374 0.07<br />
31 7.36 7.36 40.61 72.89 6.07 20.59 2.67 116.17 0.11 1.75 1.86 0.0334 0.06<br />
32 7.36 7.36 40.61 77.27 6.44 21.34 2.78 120.65 0.11 1.82 1.93 0.0298 0.06<br />
33 7.36 7.36 40.61 81.90 6.83 22.13 2.90 125.41 0.11 1.89 2.00 0.0266 0.05<br />
34 7.36 7.36 40.61 86.82 7.23 22.97 3.02 130.45 0.11 1.97 2.08 0.0238 0.05<br />
35 7.36 7.36 40.61 92.02 7.67 23.86 3.15 135.79 0.11 2.05 2.16 0.0212 0.05<br />
TOTAL 9.1566 18.19<br />
(A) (B)<br />
Note: The charges per unit is exclusive <strong>of</strong> water cess, spares, incentive & Income Tax Levellised 1.99
CALCULATION OF ENERGY RATE WITH PRESENT COST (JUNE 2003 PRICE LEVEL) AS PER TARIFF NOTIFICATION<br />
WITHOUT FREE POWER TO HOME STATE<br />
174<br />
Preliminary Feasibility Report<br />
<strong>Panan</strong> HE Project (4 x 50 MW)<br />
Table-13.3 A<br />
Annual Generation in a 90% dependable year 762 MU O&M Charges 1.50%<br />
Annual Generation after allowing losses Rate <strong>of</strong> increase <strong>of</strong> O&M Charges after 1st Year (Compounded) 6%<br />
in a 90% dependable year 752.88 MU Interest rate on 10.0%<br />
Total cost including IDC Rs. 846.08 Crores Interest rate on Working 10.00%<br />
Equity 30% Rs. 253.82 Crores Return on 16%<br />
Loan 70% Rs. 592.26 Crores Discounting rate 12%<br />
YEAR CAPACITY CHARGES PER UNIT Discounting Discounted<br />
Out- (Rs.in Cr.) (Rs.in Cr.) (Rs. per Unit) Factor Tariff<br />
standing Interest Depre- Total Return O&M Interest on Working Capital Total Capacity Energy Total (Paisa per<br />
Loan on loan ciation on Charges O&M 2months Interest charges charges Unit)<br />
(Rs.in Cr.) 1 month Average<br />
equity<br />
Billing<br />
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16<br />
1 592.26 56.76 49.35 106.11 40.61 12.69 1.06 27.04 2.81 56.11 1.41 0.75 2.15 1.0000 2.15<br />
2 542.90 51.82 49.35 101.18 40.61 13.45 1.12 26.33 2.75 56.81 1.34 0.75 2.10 0.8929 1.87<br />
3 493.55 46.89 49.35 96.24 40.61 14.26 1.19 25.63 2.68 57.55 1.28 0.76 2.04 0.7972 1.63<br />
4 444.19 41.95 49.35 91.31 40.61 15.12 1.26 24.94 2.62 58.35 1.21 0.77 1.99 0.7118 1.41<br />
5 394.84 37.02 49.35 86.37 40.61 16.02 1.34 24.26 2.56 59.19 1.15 0.79 1.93 0.6355 1.23<br />
6 345.48 32.08 49.35 81.44 40.61 16.98 1.42 23.59 2.50 60.10 1.08 0.80 1.88 0.5674 1.07<br />
7 296.13 27.15 49.35 76.50 40.61 18.00 1.50 22.93 2.44 61.06 1.02 0.81 1.83 0.5066 0.93<br />
8 246.77 22.21 49.35 71.56 40.61 19.08 1.59 22.27 2.39 62.08 0.95 0.82 1.78 0.4523 0.80<br />
9 197.42 17.27 49.35 66.63 40.61 20.23 1.69 21.63 2.33 63.17 0.88 0.84 1.72 0.4039 0.70<br />
10 148.06 12.34 49.35 61.69 40.61 21.44 1.79 21.00 2.28 64.33 0.82 0.85 1.67 0.3606 0.60<br />
11 98.71 7.40 49.35 56.76 40.61 22.73 1.89 20.39 2.23 65.57 0.75 0.87 1.62 0.3220 0.52<br />
12 49.35 2.47 49.35 51.82 40.61 24.09 2.01 19.78 2.18 66.88 0.69 0.89 1.58 0.2875 0.45<br />
13 7.36 7.36 40.61 25.54 2.13 12.49 1.46 67.61 0.10 0.90 1.00 0.2567 0.26<br />
14 7.36 7.36 40.61 27.07 2.26 12.76 1.50 69.18 0.10 0.92 1.02 0.2292 0.23<br />
15 7.36 7.36 40.61 28.69 2.39 13.03 1.54 70.85 0.10 0.94 1.04 0.2046 0.21<br />
16 7.36 7.36 40.61 30.42 2.53 13.33 1.59 72.61 0.10 0.96 1.06 0.1827 0.19<br />
17 7.36 7.36 40.61 32.24 2.69 13.64 1.63 74.48 0.10 0.99 1.09 0.1631 0.18<br />
18 7.36 7.36 40.61 34.17 2.85 13.97 1.68 76.47 0.10 1.02 1.11 0.1456 0.16<br />
19 7.36 7.36 40.61 36.22 3.02 14.32 1.73 78.57 0.10 1.04 1.14 0.1300 0.15<br />
20 7.36 7.36 40.61 38.40 3.20 14.69 1.79 80.80 0.10 1.07 1.17 0.1161 0.14<br />
21 7.36 7.36 40.61 40.70 3.39 15.09 1.85 83.16 0.10 1.10 1.20 0.1037 0.12<br />
22 7.36 7.36 40.61 43.14 3.60 15.50 1.91 85.67 0.10 1.14 1.24 0.0926 0.11<br />
23 7.36 7.36 40.61 45.73 3.81 15.95 1.98 88.32 0.10 1.17 1.27 0.0826 0.11<br />
24 7.36 7.36 40.61 48.48 4.04 16.42 2.05 91.13 0.10 1.21 1.31 0.0738 0.10<br />
25 7.36 7.36 40.61 51.39 4.28 16.91 2.12 94.12 0.10 1.25 1.35 0.0659 0.09<br />
26 7.36 7.36 40.61 54.47 4.54 17.44 2.20 97.28 0.10 1.29 1.39 0.0588 0.08<br />
27 7.36 7.36 40.61 57.74 4.81 18.00 2.28 100.63 0.10 1.34 1.43 0.0525 0.08<br />
28 7.36 7.36 40.61 61.20 5.10 18.59 2.37 104.18 0.10 1.38 1.48 0.0469 0.07<br />
29 7.36 7.36 40.61 64.87 5.41 19.22 2.46 107.95 0.10 1.43 1.53 0.0419 0.06<br />
30 7.36 7.36 40.61 68.77 5.73 19.88 2.56 111.94 0.10 1.49 1.58 0.0374 0.06<br />
31 7.36 7.36 40.61 72.89 6.07 20.59 2.67 116.17 0.10 1.54 1.64 0.0334 0.05<br />
32 7.36 7.36 40.61 77.27 6.44 21.34 2.78 120.65 0.10 1.60 1.70 0.0298 0.05<br />
33 7.36 7.36 40.61 81.90 6.83 22.13 2.90 125.41 0.10 1.67 1.76 0.0266 0.05<br />
34 7.36 7.36 40.61 86.82 7.23 22.97 3.02 130.45 0.10 1.73 1.83 0.0238 0.04<br />
35 7.36 7.36 40.61 92.02 7.67 23.86 3.15 135.79 0.10 1.80 1.90 0.0212 0.04<br />
TOTAL 9.1566 16.01<br />
(A) (B)<br />
Note: The charges per unit is exclusive <strong>of</strong> water cess, spares, incentive & Income Tax etc. Levellised Tariff =(B)/(A) 1.75