MANUAL- IV<br />
Section 4 (1) (b) (iv) of Right to <strong>Information</strong> Act 2005<br />
(The norms set by it for discharge of its function)<br />
Directorate of <strong>Rural</strong> <strong>Development</strong>, <strong>Nagaland</strong>.<br />
Besides, following the norms set by Govt. of <strong>Nagaland</strong> in the<br />
<strong>Nagaland</strong> Secretariat Manual of Office Procedure as also applicable Guidelines of<br />
Central/ <strong>State</strong> Schemes, Rules and Regulation, the Directorate of R.D. has set the<br />
following standard norms for execution of V.D.B. household allocation under Grantin-Aid<br />
(GIA) etc.<br />
(With effect from 2006-07 onwards)<br />
SL.<br />
NO.<br />
ACTIVITIES TIME SCHEDULED / DATELINE<br />
1 2 3<br />
1 Provisional allocation of fund to VDBs<br />
by DRD <strong>Nagaland</strong>, Kohima as per<br />
budget allotment from Government.<br />
By 30 th June every year<br />
2 Holding of VDBs’ meeting for selection<br />
of schemes and collection of scheme list<br />
for village Plan by BDOs.<br />
To be completed by 31 st August every year.<br />
3 Preparation of detailed project report<br />
and submission of list to DRDA for<br />
District Planning Board approval.<br />
To be completed by 30 th September every year.<br />
4 Preparation of Technical Estimate and<br />
issue of work order by BDOs.<br />
To be completed by 31 st October every year.<br />
5 Obtaining sanction order and drawal of<br />
scheme fund by DRD <strong>Nagaland</strong>,<br />
Kohima.<br />
By 31 st March every year.<br />
6 Completion of works by VDB and<br />
intimate to the BDOs that the Plan<br />
activities have been completed.<br />
To be completed by 31 st March every year.<br />
7 Physical inspection/ verification of<br />
works by BDO and his field staff and<br />
issue of works completion certificate by<br />
BDOs.<br />
To be completed by 31 st March every year.<br />
8 Submission of detailed projects/<br />
schemes approved by D.P.B alongwith<br />
previous year schemes Utilization<br />
Certificate and Post Office Time Deposit<br />
accounts by BDOs.<br />
To be completed by 30 th April every year.<br />