Chapter ñ 10 Final Report: Ambur <strong>Municipal</strong>ity<br />

10.1.2 Sewerage System<br />

1. Needs:<br />

At present municipality do not have sewerage system but Government of Tamil<br />

Nadu has proposed to lay new system in every municipality in Tamil Nadu. Ambur<br />

<strong>Municipal</strong>ity has prepared the DPR for the sewerage system for the town and sent it<br />

to CMA for approval.<br />

2. Sewerage Proposals<br />

The Detailed Project Report was prepared by TWAD Board. The Town has been<br />

considered as single zone for designing of the collection system. They estimate total<br />

length of sewerage 82.00 km .The Sewage Treatment <strong>Plan</strong>t of capacity of 18.00 mld<br />

(ASP Technology) is proposed to be located near Sivarajapuram .<br />

Table 10-4: Capital Investment Needs for the Sewerage System<br />

S.No Description Qty<br />

Amount<br />

Rs. Lacs<br />

1<br />

Supply, Delivery, Laying and Jointing of sewer Lines including<br />

Appurtenances<br />

81.72<br />

Km<br />

1744.00<br />

2 House Service Connection 11500 397.02<br />

3 Pumping Main 1 No 102.14<br />

4 Pumping Machineries and Diesel generator sets 1 No 200.00<br />

5<br />

Pumping main from main pumping main station to treatment plant<br />

800 mm DI K7<br />

1.10 km 86.60<br />

6 Sewage Treatment <strong>Plan</strong>t with ASP Technology<br />

14.65<br />

MLD<br />

623.00<br />

Sub total I 3152.76<br />

7 Petty supervision & Contingency @ 2.5 % 78.81<br />

8 Un-forseen Item @ about 2.5 % 78.81<br />

Sub Total II 3310.39<br />

9 Centage @ 5 % on sub total II 165.51<br />

Sub Total III 3475.91<br />

10 Miscellaneous Items<br />

Towards Road Restoration Charges for NH and state Highways<br />

Dept for sewers and Pumping Main<br />

Towards TNEB charges for separate Feeder main and connection<br />

85<br />

charges NH and state Highways Departments for sewers and<br />

pumping main<br />

25<br />

Towards Charges for telephone Connections 4<br />

Add service charges at 1 % on miscellaneous Items 1.2<br />

Add price escalation 10 % for 2 years 358.88<br />

Grand Total 3950.00<br />

10.1.3 Drainage<br />

1. Needs:<br />

The existing drainage condition of Ambur consists of tanks and manmade drainage<br />

system (Storm water open drains). Due to the natural slope of the town, all the drains<br />

- 98 -<br />

Voyants Solutions Private Limited