Chapter ñ 10 Final Report: Ambur <strong>Municipal</strong>ity<br />
10 CAPIITAL IINVESTMENT NEEDS FOR IIDENTIIFIIED<br />
PROJECTS<br />
All the projects relating to urban infrastructure, urban growth and development<br />
have been identified through a conscious participatory process. The projects are in<br />
the form of improvements and, extension of the existing services and facilities such<br />
that the present inadequacies as per the norms and standards are made up and, in<br />
addition meet the requirements of the projected population of the town during the<br />
perspective period of plan.<br />
Each project component, as identified has been verified in the field of their<br />
suitability and feasibility in terms of location, coverage and adequacy and finalized<br />
with as intensive consultation with the office of the municipality and as suggested<br />
and recommended in the review meetings of the previous stage of this exercise in<br />
the office of TNUIFSL. The projects thus finalized and firmed up are detailed thus<br />
finalized and firmed up are detailed out in their present status, gaps, projected<br />
requirements, cost estimates, capital needs, funding pattern etc in the following<br />
section. In all the identified projects constituting physical and social infrastructure<br />
facilities and other projects including bus stand, remunerating projects are including<br />
cost about Rs. 208.36 Crores to be implemented starting from the current financial<br />
year. The Capital Investment <strong>Plan</strong> has been prepared based on Ambur Master <strong>Plan</strong><br />
of the DTCP. The projects, breakup of the investment and implementation schedule<br />
are given in the following tables:<br />
Table 10-1: Summery of Capital Investments under CCCBP<br />
S.No Focus Area Total Cost Rs.in Lacs<br />
1 Water supply 13667<br />
2 Sewerage 3950<br />
3 Solid waste management 847<br />
4 Storm water drainage 684<br />
5 Roads 256<br />
6 Bus stand 12<br />
7 Street light 111<br />
8 Parks 11<br />
9 Schools 25.70<br />
10 Slaughter house 36<br />
11 Maternity Centre 54.30<br />
12 Market 3<br />
13 Shopping complex 100<br />
14 Burial ground 73<br />
15 E-Governance 18<br />
16 GIS mapping for Comprehensive Property database 37<br />
17 Slum development 2272<br />
18 Mobile tax collection vehicle 10<br />
Total 22167<br />
. - 93 -<br />