19.07.2013 Views

May - Library

May - Library

May - Library

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

p roblems, and getting their ideas on how we can improve the design’.<br />

Certainly these are important, but not likely to be sufficient. Let’s ask<br />

the following:<br />

A.In light of the failure modes analysis described above, how will<br />

you modify the design of your equipment to eliminate, mitigate or<br />

better manage (through condition monitoring methods that allow<br />

early detection of problems) these failure modes? If condition<br />

monitoring technologies or methods are applied, please describe<br />

those that apply, including their potential costs and benefits.<br />

Include in your discussion a review of the application of<br />

continuous monitoring.<br />

B.Describe 3 or 4 design changes that have been made as a result<br />

of working with your customers, and why. What additional<br />

efforts are currently on-going for improved reliability and<br />

maintainability in the equipment?<br />

C.Attached is a listing of several problems that we have had in<br />

reliability and maintainability. Please provide us with a<br />

description as to how you will address and resolve these<br />

problems in the design to assure improved reliability and<br />

maintainability.<br />

D.Will approval of your drawings be permitted, and if so, in<br />

sufficient time to allow for equipment modifications and still<br />

meet the project schedule? Please outline your plans.<br />

Experience with Reliability and<br />

Maintainability<br />

When asked about their specific experience in providing reliable,<br />

readily maintainable equipment, or more to the point, when asked<br />

about the reliability of the equipment being procured, a typical reply<br />

f rom the supplier might be ‘This equipment has been installed in many<br />

places throughout the world, and has operated very re l i a b l y. In<br />

particular, this equipment was installed at the First-Up plant, and had<br />

few difficulties during commissioning, and is currently running re l i a b l y.<br />

I t ’s also been installed at the Next-Other plant. Let’s ask the following:<br />

At the First-Up and Next-Other plants, please respond to the<br />

following for each plant:<br />

A.What has been the historical average % unplanned maintenance<br />

downtime?<br />

B.What is the mean time between repair?<br />

C. What is the mean time to repair?<br />

D.What are the five most common failure modes?<br />

E.What is being done in the design to mitigate or eliminate these<br />

reliability and maintainability issues?<br />

F. How long did the commissioning process take to achieve full,<br />

sustainable production rates? How many failures and of what<br />

duration occurred during that period? Did any supplied parts<br />

exceed the guaranteed failure rate?<br />

G.What were the major problems encountered during<br />

commissioning?<br />

H.What design changes have been made to minimize these<br />

commissioning problems?<br />

I. What is the standard commissioning process? We desire that<br />

the equipment run at least one full production cycle while<br />

maintaining full production requirements. We also desire that<br />

this same test be repeatable within 6 months of initial<br />

commissioning. Please describe your process for meeting these<br />

requirements.<br />

J . We desire a mean time between failure (MTBF) of not less than<br />

_____ hours. For our purpose, a failure is defined as anything that<br />

occurs with the equipment that results in any downtime,<br />

p roduction rate reduction, or quality loss. For example, at a ____%<br />

confidence level, this re q u i res that we have no more than ____<br />

f a i l u res during a ____hour period. Please aff i rm your commitment<br />

to running a commissioning test over the period stated with these<br />

specific confidence limits, and pre d e t e rmined number of failure s ,<br />

or offer your alternative that will meet this need.<br />

Developing Suppliers That Provide Reliability and Maintainability<br />

K.Could you arrange for our engineers and purchasing people to<br />

visit these two plants, and perhaps other plants, to review their<br />

practices and performance?<br />

PM and Spares Requirements<br />

When asked about PM and spares re q u i rements, and how they are<br />

developed, vendor responses vary considerably. A typical answer<br />

might be ‘Spares recommendations are based on our experience and<br />

on feedback from our customers, separated into capital spares and<br />

routine wear parts, with expected lifetimes.’ What this means is not<br />

very clear. To add greater clarity, let’s ask the following:<br />

A.What statistical methods and other techniques were used to<br />

convert your experience and feedback into spares<br />

recommendations and PM intervals? In light of the failure<br />

modes described above, and assuming the failure modes cannot<br />

be entirely eliminated in the design, describe how these PM will<br />

assure mitigation and/or early detection of these failure modes.<br />

Describe how the spares recommended are to be used for better<br />

managing these failure modes.<br />

B.Please provide one example of each major component analysis,<br />

wherein techniques such as RCM, FMEA, PM Optimization were<br />

used in conjunction with statistical failure and wear data to<br />

determine PM requirements and intervals and spare parts<br />

requirements.<br />

Training<br />

Training is critical for the proper startup, operation and<br />

maintenance of new equipment. A typical question might be ‘What<br />

level of training is re q u i red for operators and maintainers for<br />

equipment of this type?’ A typical answer might be ‘We do good<br />

training, and much of the equipment is automated, minimizing the need<br />

for training.’<br />

Increased automation is more likely to increase the complexity of<br />

the equipment, resulting in a need for greater skill and competency in<br />

our staff, not less, particularly during problem analysis and corre c t i v e<br />

action. With this in mind:<br />

A.Describe the operator training, as well as mechanical and<br />

electrical maintenance training required to assure world-class<br />

practice, including a detailed outline of all training and support<br />

requirements that will be necessary for supporting the reliable<br />

operation and maintenance of the equipment.<br />

Summary<br />

Using the model outlined above should be an integral part of an<br />

overall strategy for minimizing the total cost of ownership for major<br />

capital equipment. The key to using this approach is having a good<br />

understanding of your current operating results and problem are a s ,<br />

the failure modes most likely to result in lost production, downtime, or<br />

high costs; or that may have the most severe consequence to your<br />

overall operation. Having a good understanding of these issues will<br />

a s s u re that you can work with your supplier to eliminate, mitigate, and<br />

manage these risks; and that you can minimize your total cost of<br />

ownership, and be more profitable. Many of you may be far along the<br />

path for this and have more detailed processes to achieve the above<br />

re q u i rements. No doubt others would consider these re q u i re m e n t s<br />

beyond the scope of many of your procurement efforts. Somewhere<br />

in the middle are many of you who could use this model to more fully<br />

develop your re q u i rements for improving reliability and maintainability.<br />

Hopefully the suggestions above will help you in that effort.<br />

Ron Moore is Managing Partner of The RM Group, Inc., Knoxville,<br />

TN, and author of Making Common Sense Common Practice: Models<br />

for Manufacturing Excellence from Butterworth-Heinemann. He can<br />

be contacted by telephone at 865-675-7647; or by email at<br />

RonsRMGp@aol.com.<br />

40

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!