18.07.2013 Views

THE PALACE OF JUSTICE CIVIL APPEAL NO. P-02-2074-2011 ...

THE PALACE OF JUSTICE CIVIL APPEAL NO. P-02-2074-2011 ...

THE PALACE OF JUSTICE CIVIL APPEAL NO. P-02-2074-2011 ...

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

The above proposition was cited with approval by the Singapore<br />

Court of Appeal in Man B & W Diesel (see paragraph 31 of the<br />

judgment at page 312).<br />

The finding of the High Court Judge<br />

Now, in the present case, the learned High Court Judge, on the issue<br />

of liability in negligence, made a finding of mixed law and fact as<br />

follows:<br />

In my considered opinion the long delay in completing the project was<br />

caused or contributed by the 2 nd and 3 rd defendant as:<br />

(a) All the amendments (due to negligence of the defendants)<br />

took time and they affected the completion of Phase 1 of the<br />

project;<br />

(b) The completion of phase 1 of the project was delayed and<br />

the CF was only issued on 4/7/2005 because of the time<br />

taken for the approval of many amended plans and also the<br />

rectification works on works not done according to the<br />

original plans.<br />

23

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!