developer proceeded to construct the CEITS. However, the CEITS<br />
that was constructed by the developer did not function according to<br />
the satisfaction of the DOE, and as a consequence the DOE refused<br />
to issue its certification of approval.<br />
By reason of the absence of the certification of approval by the DOE,<br />
the appellants, as the architects of the project, refused to apply for<br />
the CFOs notwithstanding the instruction of the developer for them to<br />
do so.<br />
Subsequently, the appellants, by reason of their refusal to follow the<br />
instruction, resigned as the architects for the project on 13 June<br />
2005. At the time of their resignation, the developer has yet to obtain<br />
the CFOs from the local authority.<br />
As a consequence, there was a delay in the application for the CFOs.<br />
The CFOs for the industrial buildings were issued only on 4 July<br />
2005. Therefore there was a delay of some 8 years before the<br />
purchasers could lawfully occupy the industrial buildings. The<br />
respondents alleged that this delay in the obtaining of the CFOs had<br />
11