Renewable Energy Technology Assessments - Kauai Island Utility ...
Renewable Energy Technology Assessments - Kauai Island Utility ...
Renewable Energy Technology Assessments - Kauai Island Utility ...
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Kaua’i <strong>Island</strong> <strong>Utility</strong> Cooperative<br />
<strong>Renewable</strong> <strong>Energy</strong> <strong>Technology</strong> <strong>Assessments</strong> 9.0 Wind<br />
increased by 50 percent and crane costs by 25 percent to represent the difficulties of<br />
working in rough terrain.<br />
The costs for each project assume a limited amount of civil works to bring roads<br />
and transmission to the wind farm. The Hanapepe and Anahola sites are not readily<br />
accessible and will require significant infrastructure upgrades. An additional $1.7 million<br />
(5 miles of road and 3 miles transmission) has been allocated for Hanapepe and an<br />
additional $0.9 million (3 miles road, 1 mile transmission) has been allocated for Anahola<br />
to account for additional road and transmission extensions which would likely be<br />
required.<br />
For each project, indirect costs were added using 10 percent of material and labor<br />
costs plus $1,000,000 to cover development costs such as permitting, environmental<br />
studies, outreach, etc. This fixed development cost makes the smaller project<br />
significantly more expensive on a per MW capacity basis. Installing three distributed<br />
generation installations for a total capacity similar to the central plant projects would<br />
decrease the cost per MW capacity closer to the level for the other projects, but<br />
development would still be more expensive since separate permits, road improvements,<br />
etc., would be required for each project.<br />
Based on the foregoing assumptions, the resulting capital cost estimates are shown<br />
in Table 9-3.<br />
Table 9-3. <strong>Kauai</strong> Wind Project Capital Costs<br />
Sites Scenario Capital Cost Cost per kW<br />
Kalaheo, Poipu: Flat 6.6 MW $10,750,000 $1,630<br />
Omao, Maha’ulepu: Ridge 6.6 MW $11,150,000 $1,690<br />
Hanapepe Ridge 6.6 MW + T&R * $12,850,000 $1,945<br />
Anahola Ridge 6.6 MW + T&R * $12,050,000 $1,825<br />
Kokee Ridge 2 MW $4,450,000 $2,250<br />
*<br />
Additional transmission and road costs<br />
9.6.2 Operating and Maintenance Costs<br />
The operating and maintenance costs assumed one full time employee at a cost of<br />
$90,000/year. Major maintenance activities would be contracted as required. Operating<br />
and maintenance costs varied with scenario and the results are listed in Table 9-4. The<br />
main factor effecting O&M costs was number of turbines. A capacity factor of 35<br />
percent was assumed for variable O&M which approximately matches most of the easily<br />
developable wind sites.<br />
21 March 2005 9-22 Black & Veatch