17.07.2013 Views

Renewable Energy Technology Assessments - Kauai Island Utility ...

Renewable Energy Technology Assessments - Kauai Island Utility ...

Renewable Energy Technology Assessments - Kauai Island Utility ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Kaua’i <strong>Island</strong> <strong>Utility</strong> Cooperative<br />

<strong>Renewable</strong> <strong>Energy</strong> <strong>Technology</strong> <strong>Assessments</strong> 9.0 Wind<br />

increased by 50 percent and crane costs by 25 percent to represent the difficulties of<br />

working in rough terrain.<br />

The costs for each project assume a limited amount of civil works to bring roads<br />

and transmission to the wind farm. The Hanapepe and Anahola sites are not readily<br />

accessible and will require significant infrastructure upgrades. An additional $1.7 million<br />

(5 miles of road and 3 miles transmission) has been allocated for Hanapepe and an<br />

additional $0.9 million (3 miles road, 1 mile transmission) has been allocated for Anahola<br />

to account for additional road and transmission extensions which would likely be<br />

required.<br />

For each project, indirect costs were added using 10 percent of material and labor<br />

costs plus $1,000,000 to cover development costs such as permitting, environmental<br />

studies, outreach, etc. This fixed development cost makes the smaller project<br />

significantly more expensive on a per MW capacity basis. Installing three distributed<br />

generation installations for a total capacity similar to the central plant projects would<br />

decrease the cost per MW capacity closer to the level for the other projects, but<br />

development would still be more expensive since separate permits, road improvements,<br />

etc., would be required for each project.<br />

Based on the foregoing assumptions, the resulting capital cost estimates are shown<br />

in Table 9-3.<br />

Table 9-3. <strong>Kauai</strong> Wind Project Capital Costs<br />

Sites Scenario Capital Cost Cost per kW<br />

Kalaheo, Poipu: Flat 6.6 MW $10,750,000 $1,630<br />

Omao, Maha’ulepu: Ridge 6.6 MW $11,150,000 $1,690<br />

Hanapepe Ridge 6.6 MW + T&R * $12,850,000 $1,945<br />

Anahola Ridge 6.6 MW + T&R * $12,050,000 $1,825<br />

Kokee Ridge 2 MW $4,450,000 $2,250<br />

*<br />

Additional transmission and road costs<br />

9.6.2 Operating and Maintenance Costs<br />

The operating and maintenance costs assumed one full time employee at a cost of<br />

$90,000/year. Major maintenance activities would be contracted as required. Operating<br />

and maintenance costs varied with scenario and the results are listed in Table 9-4. The<br />

main factor effecting O&M costs was number of turbines. A capacity factor of 35<br />

percent was assumed for variable O&M which approximately matches most of the easily<br />

developable wind sites.<br />

21 March 2005 9-22 Black & Veatch

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!