17.07.2013 Views

Renewable Energy Technology Assessments - Kauai Island Utility ...

Renewable Energy Technology Assessments - Kauai Island Utility ...

Renewable Energy Technology Assessments - Kauai Island Utility ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Kaua’i <strong>Island</strong> <strong>Utility</strong> Cooperative<br />

<strong>Renewable</strong> <strong>Energy</strong> <strong>Technology</strong> <strong>Assessments</strong> 1.0 Executive Summary<br />

1.5 Biomass and Municipal Solid Waste<br />

Biomass project sizes from 5 to 30 MW were considered, and an optimum size of<br />

20 MW was selected based on preliminary technical and economic analysis. The<br />

biomass fuel mix and cost change based on the project size. Smaller projects can utilize<br />

lower cost waste biomass resources (wood chips, bagasse, and cane trash), while larger<br />

projects would need to rely on dedicated energy crops such as banagrass (elephant grass).<br />

A stoker boiler was selected as the basis for the project conceptual design due to its good<br />

mix of technical maturity, efficiency, and cost. The location for the biomass project has<br />

not been specified yet.<br />

After selecting 20 MW as the preferred size for the biomass project, capital and<br />

O&M costs and plant performance were estimated to determine cost of energy for such a<br />

plant for KIUC. The life-cycle costs were analyzed using the likely low, high and mid<br />

range fuel costs to establish upper and lower bounds for the analysis. The results of these<br />

estimates are shown in Table 1-1.<br />

Table 1-1. Biomass Life-Cycle Economic Assumptions ($2005).<br />

Unit<br />

Low Fuel<br />

Cost Mid Fuel Cost<br />

High Fuel<br />

Cost<br />

Capacity MW 20.0 20.0 20.0<br />

Capital Cost $/kW 4,556 4,556 4,556<br />

First Year Fixed O&M $/kW-yr 150 150 150<br />

First Year Variable O&M $/MWh 8.4 8.4 8.4<br />

First Year Fuel Cost $/MBtu 3.50 4.15 4.57<br />

Net Plant Heat Rate Btu/kWh 15,397 15,397 15,397<br />

Capacity Factor percent 80% 80% 80%<br />

KIUC Levelized Cost 2009$/MWh 179.5 194.8 204.6<br />

KIUC Premium* 2009$/MWh 5.6 20.9 30.7<br />

*Electricity cost premium (or savings) compared to KIUC’s forecasted avoided costs.<br />

Based on the assumptions shown in Table 1-1, the levelized cost of electricity can<br />

be calculated. The levelized electricity cost includes all costs to generate power (capital,<br />

O&M, fuel, etc.) levelized over the life cycle of the project. In 2009, it is projected that<br />

the levelized cost of supplying power from a biomass fueled power station would range<br />

from $180/MWh to $205/MWh, depending on the fuel cost. This cost can be compared<br />

to the cost of KIUC’s existing resources and projected new unit additions. These costs<br />

would be “avoided” if the biomass plant were built. Based on avoided cost forecasts<br />

from KIUC, biomass is able to avoid $174/MWh in energy and capacity costs on a<br />

levelized basis (2009$). Taking these costs into account, the premium for biomass ranges<br />

21 March 2005 1-9 Black & Veatch

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!