KIUC to Begin Rebuild of Lydgate Substation<br />
FOR IMMEDIATE RELEASE<br />
8/13/08<br />
Contact:<br />
Shelley Paik<br />
808.246.4378<br />
spaik@kiuc.coop<br />
Lihue, <strong>Kauai</strong>, HI - 8/13/08 - KIUC will begin the rebuild of the Lydgate Substation next week.<br />
Lydgate Substation which serves portions of Wailua and Kapa`a, has suffered from the corrosive<br />
effects of salt laden on-shore trade winds and it is time to rebuild the station. The Lydgate<br />
Substation is being built to minimize the effects of the corrosive environment and will include<br />
increased capacity to handle future growth in the area. Existing loads are being transferred to<br />
Kapa`a and Kapaia Substations during the re-construction period.<br />
“We are looking towards long-term solutions instead of quick fixes,” said Jack Leavitt, KIUC<br />
Transmission & Distribution Manager. "It's an investment; and a quantum leap in reliability."<br />
Leavitt explains the newly built substation will be an indoor design utilizing gas insulated<br />
switchgear (GIS) for the transmission section, while metal-clad vacuum switchgear will handle<br />
distribution energy from two new power transformers to be installed on the Mauka side of the<br />
building such that they will be shielded them from the corrosive trade winds. All protective<br />
relaying will be microprocessor based, and fiber optics will supply communications.<br />
TOMCO Corporation was the successful bidder and was selected as the contractor; the<br />
construction phase should be completed by mid-2009.<br />