(4) Set a time schedule of the work<br />

<strong>JAEA</strong>-<strong>Testing</strong> <strong>2011</strong>-007<br />

<strong>JAEA</strong>-<strong>Testing</strong> <strong>2011</strong>-007<br />

Set a time schedule of the work using the form, “Record 5: Time schedule of the<br />

work” based on information obtained in the precedent steps such as dimension of<br />

swimming pool (volume of pool water), number of available materials and tools,<br />

available number of staffs and overall schedule.<br />

Approximate times that are assumed to require for each task are shown below.<br />

【Briefing of the procedures】 1 hour<br />

Briefings are held before starting the procedures. It will include explanation to<br />

all of the program members to inform about the entire procedures and detailed<br />

explanation to each task group members about practical method and note to be<br />

aware of.<br />

【Securing of a discharge flow path (removal of sediment)】 0.5 day<br />

Remove mud and fallen leaves accumulated in the discharge flow path.<br />

【Radiation survey before work】 3 hours<br />

Sample swimming pool water at predetermined sampling points, and measure<br />

radioactivity concentration with a radioactivity detector. If the radioactivity<br />

detector is not available at the site, time required to transport the samples<br />

needs to be added to the above time.<br />

【Discharge of supernatant】 1 day<br />

When the radioactivity concentration in the pool water is lower than the<br />

criteria for discharge, discharge the supernatant with engine pumps, while<br />

taking care of not to pumping up mud or fallen leaves accumulated on the<br />

bottom.<br />

【Treatment in 1 ton plastic tank】 1.5 hour/one tank<br />

When the radioactivity concentration is higher than the criteria for the<br />

discharge, pump up the pool water together with mud and fallen leaves<br />

accumulated on the bottom. It takes 20 minutes to feed zeolite, flocculant and<br />

neutralizer. Leave at rest 30 minutes to allow sufficient precipitation. It takes<br />

15 minute for discharging the supernatant and 15 minutes for recovery of the<br />

precipitate on the bottom of the plastic tank.<br />

- 123 -<br />