30.06.2013 Views

Untitled

Untitled

Untitled

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Commissioning and Qualification 333<br />

acircuit. The skid sequence typically has little variation from circuit to circuit (other<br />

than set points and time). There may be some variation between CIP cycles;<br />

however, the circulated wash steps are very similar to each other (as are the<br />

once-through rinses).<br />

Design Basis<br />

The NDS and ABS design and determination of some of the critical operating<br />

parameter values require the engineering and commissioning function to be<br />

somewhat iterative. The NDS and ABS and associated times are typically<br />

determined using adesign basis from rules of thumb (or designer experience)<br />

and assumed flow rates.<br />

Flow rates are initially estimated during the design phase. Flow rates for<br />

cleaning via spray balls (and the spray ball design) are usually initially determined<br />

based on the tank geometry. Minimum flow rate requirements for pipe filling and<br />

cleaning can be calculated by engineering during design based on achieving<br />

appropriate velocity (generally aminimum of 5ft/sec). Sequence time for line<br />

cleaning is typically based on volume turnovers.<br />

Sequence times for flow through spray balls are based on the number of<br />

circuit volume turnovers as well as a minimum tank contact time. The total<br />

number of NDS sequence iterations planned per cycle is based on the anticipated<br />

needed contact time for the alkaline and acid cycles and on the anticipated<br />

number of volume turnovers needed for the rinses. Adjustments are made as<br />

data is acquired via functional testing (such as actual process transfer line flow<br />

rates).<br />

It is important to understand and document the basis for design so that<br />

adjustments made during functional testing are within the capabilities of the<br />

design. Flow rates and times affect virtually all aspects of the CIP design. Affected<br />

areas include:<br />

1. CIP tank sizing<br />

2. Feed water flow requirements<br />

3. CIP tank vent sizing<br />

4. CIP circuit supply and return pump sizing<br />

5. Circuit supply and return piping sizes<br />

6. Heat exchanger sizing and associated utility needs<br />

IQ AND FACTORY COMMISSIONING ACTIVITIES<br />

Equipment is purchased and systems are fabricated and installed from the design<br />

documents. The functional testing portion of commissioning is typically performed<br />

on site after acompleted and verified installation. Functional testing does not<br />

usually proceed until IQ activities have been completed for the CIP skid, supply<br />

and return piping, and all of the process equipment system components used for (or<br />

immediately adjacent to) the CIP circuits. Prior to starting the functional testing on<br />

site it is prudent to ensure that all components associated with the CIP circuit<br />

operations are per specification and are installed and working properly to<br />

avoid rework.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!