contracted and started to develop the Guideline for site mapping, plantation design, <br />
afforestation and natural forest regeneration techniques. <br />
Consultation workshops on the implementing of the Restoration Component were <br />
conducted in Quangnam and ThuaThien Hue. Comments from related partners and <br />
consultants on implementing methods/system for key activities of the Restoration <br />
Component and lessons learnt from other restoration and CFM projects, especially <br />
KfW6 in Quangnam, also contributed positively to the guideline development <br />
process towards actual implementation. <br />
A fundamental mechanism for the implementation of the forest restoration activities <br />
in Quangnam, has also been discussed with the PMU, and it was concluded that <br />
relevant agencies, boards, sectors, and authorities will actively participate in the <br />
planning and management of activities. The District Forest Restoration <br />
Management Board will for instance be responsible for supporting the forest <br />
plantation, enhancement and forest protection activities; District FPD will support <br />
CFM activities on the basis of the plan approved by District; Natural Resource and <br />
Environment office will support the VLUP activities, etc. This agreement was <br />
fundamental in unlocking the synergy and goodwill required for successful <br />
implementation of this important CarBi Component. <br />
Challenges and solutions <br />
The qualified consultants (working experience with KfW projects) were quite busy <br />
with other projects and could not support CarBi as initially planned. Alternative <br />
qualified and experienced consultants have/will be sourced to address this issue, <br />
and the KFW experienced consultants will also be considered if and when required <br />
once they become available again. <br />
The project implementing structure for CarBi does not provide for project staff at <br />
district or commune level to facilitate implementation and monitor progress in close <br />
cooperation with communities and government counterparts. This situation was <br />
integrated into the discussions with the PMU’s, and stronger implementation <br />
involvement from their side has been agreed upon. We will also optimize on <br />
potential synergy with other related KFW projects, and discuss this with KFW <br />
during their upcoming visit to Vietnam in February 2012. <br />
<br />
Intermediate result 3.2 <br />
Additionally 3000 ha are under performance based protection contracts in the buffer <br />
zones in both provinces by 12 months after project start. <br />
<br />
<strong>Progress</strong> <br />
A list of villages/communes are now being selected for forest restoration, including <br />
protection contracts. The guidelines for Village land use planning have been <br />
developed, and commented upon by relevant partners in Hue (September and <br />
December 2011) and Quangnam (September 2011). The guidelines have been <br />
revised by the consultant and submitted for approval to the relevant agencies. A <br />
21