<strong>Standard</strong> <strong>Bus</strong> <strong>Procurement</strong> <strong>Guidelines</strong><br />
acknowledge the receipt of each individual addendum and all prior addenda in their proposals.<br />
Failure to acknowledge in their proposals receipt of addenda may at the Procuring Agency's sole<br />
option disqualify the proposal.<br />
If the Procuring Agency determines that the addenda may require significant changes in the<br />
preparation of proposals, the deadline for submitting the proposals may be postponed by the number<br />
of days that the Procuring Agency determines will allow Offerors sufficient time to revise their<br />
proposals. Any new Due Date shall be included in the addenda.<br />
1.1.2.4 CONDITIONS, EXCEPTIONS, RESERVATIONS OR UNDERSTANDINGS<br />
Proposals stating conditions, exceptions, reservations or understandings (hereinafter “deviations”)<br />
relating to the RFP may be rejected. Offerors may submit an alternate proposal that states deviations<br />
so long as a basic proposal not containing deviations is submitted. Offerors may propose alternates<br />
either within one overall proposal or by submitting more than one proposal. Any alternate proposal<br />
shall include a price proposal in accordance with “Price Proposal Requirements” (Section 1.1.3.3).<br />
Any and all deviations must be explicitly, fully and separately stated in the proposal by <strong>com</strong>pleting<br />
form(s) provided in “Form for Proposal Deviation” (Section 1.1.6.9), setting forth at a minimum the<br />
specific reasons for each deviation so that it can be fully considered and, if appropriate, evaluated by<br />
the Procuring Agency. All deviations not found by the Procuring Agency to be unacceptable shall be<br />
evaluated in accordance with the appropriate evaluation criteria and procedures, and may result in the<br />
Offeror receiving a less favorable evaluation than without the deviation.<br />
1.1.3 INSTRUCTIONS TO OFFERORS<br />
1.1.3.1 DUE DATE<br />
Sealed proposals in original and (number) copies must be received at the address shown in<br />
“Procuring Agency and Contracting Officer” (Section 1.1.1.1)until (date/time) for the provision of<br />
(number of buses, spare parts, options, etc.). All labor, equipment, and materials shall be furnished in<br />
strict accordance with the delivery schedule and conditions of the Contract Documents. Proposals<br />
and subsequent offers shall be valid for a period of (Procuring Agency to specify, not less than 90<br />
and not more than 180 days) days .<br />
1.1.3.2 TECHNICAL PROPOSAL REQUIREMENTS<br />
(NOTE: Procuring Agency to develop and insert instructions to Offerors specifying the format and<br />
content of the technical proposal.)<br />
1.1.3.2.1 Offeror Qualifications Statement<br />
The Offeror shall state on the form provided in “Service and Parts Support” (Section 1.1.6.3) the<br />
representatives responsible for assisting the Procuring Agency, as well as the location of the nearest<br />
distribution center which shall furnish a <strong>com</strong>plete supply of parts and <strong>com</strong>ponents for the repair and<br />
maintenance of the buses to be supplied. The Offeror shall also state below, or by separate<br />
attachment, its policy on transportation charges for parts other than those covered by warranty.<br />
In addition, the Offeror shall provide the following information:(NOTE: Procuring Agency to specify<br />
the information necessary to evaluate against the qualifications requirements of Section 1.1.4.3.1.)<br />
Request for Proposals, Offer & Award 10/18/2007<br />
6