29.06.2013 Views

Prescient presentation - Petmin

Prescient presentation - Petmin

Prescient presentation - Petmin

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

NAIC<br />

39<br />

Metallurgy<br />

• Ore dressing studies continue to be carried out by Dr Jayson Ripke and<br />

Glenn Hoffman of Cardero Resources.<br />

• During the period a Wet High Intensity Magnetic Separator (WHIMS) was<br />

purchased and further testwork has begun using this unit.<br />

• Metallurgical testing has indicated that an adequate concentrate can be<br />

produced using just magnetic separation but this requires further<br />

optimisation.<br />

• Some optimisation has been achieved via the screening of the<br />

concentrate post magnetic separation but further work is required for<br />

production plant optimisation.<br />

• Tenova has been engaged to carry out a conceptual study on the pig iron<br />

production plant – proposal has been received.<br />

Environmental / Community<br />

• Some delays were experienced due to tree cutting on some of the claims<br />

and due to the environmental registration process that was triggered for<br />

the bulk sample.<br />

• Stantec have been engaged to run the permitting process for the bulk<br />

sample as well as to carry out a scoping study for the whole project.<br />

• The Innu Nation hold a land claim to our property and own 5% of Grand<br />

River shares.<br />

Pilot Plant<br />

• Objective of the pilot plant is to produce 200t of concentrate for a<br />

continuous melt test.<br />

• All equipment has been detailed (Process flowsheet engineering,<br />

equipment sizing and specifications).<br />

• An RFQ was sent out, on the basis of responses the ordering has begun.<br />

• Expectations are to operate the pilot plant during February 2012 and<br />

March 2012.<br />

• Negotiations are underway for access to furnace facilities to conduct the<br />

melt test.<br />

• Current cost estimates for the pilot plant are $650 000 – higher than the<br />

budget of $400 000. NAIC has applied for 50% of the costs to be paid by<br />

the Atlantic Canada Opportunity Agency (ACOA). Awaiting feedback.<br />

Location<br />

• Location remains a big advantage of the project.<br />

• Close proximity to a port has given the project options to produce a<br />

concentrate in Goose Bay but locate the smelter in other regions.<br />

• Erie, Pennsylvania, Quebec & Louisiana have all shown a significant<br />

interest in locating the project in<br />

their jurisdictions.<br />

• Each of these have indicated the<br />

potential for low electricity rates,<br />

soft loans and tax holidays for the<br />

project.<br />

• Potential loan financing of up to<br />

50% of the smelter CAPEX on soft<br />

repayment terms.<br />

…Committed …A PLATFORM to growth, FOR dedicated GROWTH to value

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!