October 15, 2012 - City of Laredo
October 15, 2012 - City of Laredo
October 15, 2012 - City of Laredo
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
DATE:<br />
10/<strong>15</strong>/12<br />
COUNCIL COMMUNICATION<br />
SUBJECT: MOTION<br />
Consideration for approval <strong>of</strong> change order #8 in the amount <strong>of</strong> $266,286.00 to Pepper-<br />
Lawson Construction L.P. in Katy, Texas for the Jefferson Street Water Treatment Plant 65-<br />
mgd Process and Electrical Upgrade. This change order is required to enhance and upgrade<br />
existing facilities. The total contract amount is at $36,9<strong>15</strong>,091 58. Funding is available in the<br />
201 1 Water Bond - Jefferson WTP and is subject to Texas Water Development Board<br />
approval.<br />
INITIATED BY:<br />
Jesus Olivares, Assistant <strong>City</strong> Manager<br />
STAFF SOURCE:<br />
Tomas M. Rodriguez, Jr. P.E., Utilities Director<br />
PREVIOUS COUNCIL ACTION:<br />
On February 22, 201 1, <strong>City</strong> Council approved Change Orders No. 1 and 2 to Pepper-Lawson<br />
Construction L.P. in Katy, Texas for the Jefferson Street Water Treatment Plant 65-mgd Process and<br />
Electrical Upgrade for the contract amount <strong>of</strong> $35,424,992.54 and a completion period <strong>of</strong> 910 calendar<br />
days. On April 18, 201 1, <strong>City</strong> Council approved Change Order No. 3 for a total contract amount <strong>of</strong><br />
$35,424,992.54 and a completion period <strong>of</strong> 950 calendar days. On June 6, 201 1, Council approved<br />
Change Order No. 4 for a total contract amount <strong>of</strong> $36,055,736.54 and a completion period <strong>of</strong> 950<br />
calendar days. On September 19, 201 1, Council approved Change Order No. 5 for a total contract<br />
amount <strong>of</strong> $36,055,736.54 and a completion period <strong>of</strong> 1,000 calendar days. On November 7, 201 1,<br />
Council approved Change Order No. 6 for a total contract amount <strong>of</strong> $36,108,048.54 and a completion<br />
period <strong>of</strong> 1,000 calendar days. On July 2, <strong>2012</strong>, Council approved Change Order No. 7 for a total<br />
contract amount <strong>of</strong> $36,648,805.58 and a completion period <strong>of</strong> 1 ,I 19 calendar days.<br />
BACKGROUND:<br />
The construction <strong>of</strong> the Jefferson Street Water Treatment Plant 65-mgd Process and Electrical Upgrade<br />
commenced on January 4, 2010 and is expected to be completed by January 23, 2013. This change<br />
order consists <strong>of</strong> various items required due to discrepancies in the contract drawings and field<br />
conditions, and lack <strong>of</strong> details in the contract documents. The contract amount is at $36,9<strong>15</strong>,091.58.<br />
Calendar Days<br />
Original Project Total $35,170,000.00 91 0<br />
Allowance $ 1,500,000.00<br />
Change Order #I (From Allowance).. ...... $ 625,468.00 0<br />
Change Order #2.. ............................. .$ 254,992.54 0<br />
Change Order #3(From Allowance). ....... .$ 370,213.74 40<br />
Change Order #4((From Allowance). ....... $ 32,828.74 0<br />
Change Order #4.. ............................... $ 630,744.00<br />
Change Order #5(From Allowance). ....... .$ 271,639.56 50<br />
Change Order #6((From Allowance). ....... $ 107,265.00 0<br />
Change Order #6 ................................ .$ 52,312.00<br />
Change Order #7 (From Allowance). ...... .$ 92,584.96 119<br />
Change Order #7 (From ARRA Account)..$ 537,040.05<br />
Change Order #7 ................................ $ 3,716.99<br />
Change Order #8 ............................... .$ 266,286.00 0<br />
Current Project Amount $ 36,9<strong>15</strong>,091.58<br />
Allowance Balance $ 0.00<br />
Total Working Days including<br />
Change order no 8: 1,119<br />
FINANCIAL IMPACT:<br />
Funding is available in the 201 1 Water Bond - Jefferson WTP account number 557-4193-538.01-08.<br />
COMMITTEE RECOMMENDATION:<br />
Finance & Operations Committee<br />
STAFF RECOMMENDATION:<br />
Approval <strong>of</strong> this Motion.