Chapter Two Project Justification<br />
referred to as Blow out preventer (BOP) with surface safety valves. This equipment shall be used to<br />
close in a well at the slightest detection of formation fluid ingress/flow into the well bore (mud system).<br />
This equipment shall be tested regularly to ensure proper functionality.<br />
In addition, there would be increased land and air logistics during the proposed drilling operations, since<br />
materials and workers would be moved to site due to operations demand.<br />
2.9 Flowline Contruction<br />
The activities to be undertaken will include:<br />
• Land-take for lay down area (for construction equipment);<br />
• Site Preparation;<br />
• Flushing of the existing flowlines;<br />
• Excavation and removal of old flowlines;<br />
• Site Construction (Welding and Non-Destructive Testing [Radiography]);<br />
• Pressure Testing of the new lines;<br />
• Pipe laying and tie-in;<br />
• Commissioning of the new flowlines;<br />
• Backfilling;<br />
• Operations/Maintenance;<br />
2.9.1 Flowline Construction<br />
Flowline construction methods differ depending on the geographical area, terrain, environment and third<br />
party presence. In all cases, the construction of the flowlines shall comply with codes and standards<br />
imposed by the law and standards organizations. The design for the proposed flowlines shall be in<br />
accordance with applicable national, international, industry and Shell standards.<br />
2.9.2 Land-take<br />
There shall be no route survey of the flowlines since the proposed routes are on existing SPDC Rightof-Way<br />
(ROW). The existing 15 m corridor of the ROW should be adequate for the flowlines activities.<br />
However, the construction activities may require about 80 m 2 additional land within SPDC acquired<br />
area, as temporary lay down area for construction equipment.<br />
2.9.3 Site Preparation<br />
A total area of ~800 m 2 would be required for lay down of construction equipment and shall be manually<br />
cleared of any grown vegetation. This will comprise ~720 m 2 on the existing ROW and the additional 80<br />
m 2 . The clearing activity will be carried out by community members (~10 persons). The vegetation<br />
cuttings shall be left in the field and allowed to decompose.<br />
2.9.4 Flushing of Existing Pipeline<br />
The existing Oben wells shall be shut-in to allow for flushing of the entire length of the flowlines. Water<br />
pump shall be used to provide the pressure necessary to flush the lines from the well head to the gas<br />
plant. The wastewater shall be disposed via the saver pit. Vacuum trucks shall be used to evacuate the<br />
water from the saver pit to Oben flowstation, where it will be pumped into the trunkline to Forcados<br />
Terminal for handling.<br />
2.9.5 Excavation and removal of old flowlines<br />
The excavation shall be carried out manually. The excavated section shall be manually freed of roots,<br />
stones, or other hard objects that may damage the pipe or its coatings. The maximum width of the<br />
excavated section shall be 3 m with a minimum depth of 1m<br />