Chapter Two Project Justification<br />

referred to as Blow out preventer (BOP) with surface safety valves. This equipment shall be used to<br />

close in a well at the slightest detection of formation fluid ingress/flow into the well bore (mud system).<br />

This equipment shall be tested regularly to ensure proper functionality.<br />

In addition, there would be increased land and air logistics during the proposed drilling operations, since<br />

materials and workers would be moved to site due to operations demand.<br />

2.9 Flowline Contruction<br />

The activities to be undertaken will include:<br />

• Land-take for lay down area (for construction equipment);<br />

• Site Preparation;<br />

• Flushing of the existing flowlines;<br />

• Excavation and removal of old flowlines;<br />

• Site Construction (Welding and Non-Destructive Testing [Radiography]);<br />

• Pressure Testing of the new lines;<br />

• Pipe laying and tie-in;<br />

• Commissioning of the new flowlines;<br />

• Backfilling;<br />

• Operations/Maintenance;<br />

2.9.1 Flowline Construction<br />

Flowline construction methods differ depending on the geographical area, terrain, environment and third<br />

party presence. In all cases, the construction of the flowlines shall comply with codes and standards<br />

imposed by the law and standards organizations. The design for the proposed flowlines shall be in<br />

accordance with applicable national, international, industry and Shell standards.<br />

2.9.2 Land-take<br />

There shall be no route survey of the flowlines since the proposed routes are on existing SPDC Rightof-Way<br />

(ROW). The existing 15 m corridor of the ROW should be adequate for the flowlines activities.<br />

However, the construction activities may require about 80 m 2 additional land within SPDC acquired<br />

area, as temporary lay down area for construction equipment.<br />

2.9.3 Site Preparation<br />

A total area of ~800 m 2 would be required for lay down of construction equipment and shall be manually<br />

cleared of any grown vegetation. This will comprise ~720 m 2 on the existing ROW and the additional 80<br />

m 2 . The clearing activity will be carried out by community members (~10 persons). The vegetation<br />

cuttings shall be left in the field and allowed to decompose.<br />

2.9.4 Flushing of Existing Pipeline<br />

The existing Oben wells shall be shut-in to allow for flushing of the entire length of the flowlines. Water<br />

pump shall be used to provide the pressure necessary to flush the lines from the well head to the gas<br />

plant. The wastewater shall be disposed via the saver pit. Vacuum trucks shall be used to evacuate the<br />

water from the saver pit to Oben flowstation, where it will be pumped into the trunkline to Forcados<br />

Terminal for handling.<br />

2.9.5 Excavation and removal of old flowlines<br />

The excavation shall be carried out manually. The excavated section shall be manually freed of roots,<br />

stones, or other hard objects that may damage the pipe or its coatings. The maximum width of the<br />

excavated section shall be 3 m with a minimum depth of 1m<br />

2-8