Construction of the New Naval Hospital at Camp<br />
Pendleton 70 Percent Complete<br />
Construction of a new $ 451 million Naval Hospital at Camp Pendleton is 70<br />
percent complete, according to the joint venture team in charge of the project.<br />
Clark Construction Group LLC and McCarthy Building Cos. Inc. are charged<br />
with building the 500,000-square-foot hospital that will replace the existing facility.<br />
The project falls under the American Recovery and Reinvestment Act and<br />
represents the largest one in the Navy, having a base contract value of $394 million<br />
and incorporating a planned modification for turnkey medical equipment<br />
valued at $55 million. Completion is targeted for early 2014. Seventy percent of<br />
the subcontracts issued by Clark/McCarthy have gone to first-tier small businesses<br />
(more than $200 million worth out of a total of $320 million). More than<br />
50 percent issued specifically to Service Disabled Veteran Owned Small Businesses<br />
add up to $160 million out of the total $320 million.<br />