Source: Study Team<br />

Note: Upstream is <strong>on</strong> the left side).<br />

Figure 3-21 Alternative Routes for the Sec<strong>on</strong>d My Thuan Bridge<br />

In Figure 3-21 above, a curved secti<strong>on</strong> needs to be introduced in the side span of the cable-stayed bridge<br />

al<strong>on</strong>g Alternative 3 route. This curved secti<strong>on</strong> is needed to avoid the towers of 200 kV and 500 kV power<br />

lines. This curved secti<strong>on</strong> cannot be avoided under Alternative 3; however, it is realized that the curved side<br />

span causes unbalanced secti<strong>on</strong> forces which is generally not preferred in the planning of l<strong>on</strong>g span<br />

cable-stayed bridges.<br />

Therefore, said route was not selected, although it has the shortest span length of 500 m. It is also evaluated<br />

that although the width of the river is 50 m l<strong>on</strong>ger, the main bridge secti<strong>on</strong> is straight under Alternative 2.<br />

As a result, Alternative 2 is selected as the most feasible route am<strong>on</strong>g the alternatives (Table 3-15 provides<br />

the comparis<strong>on</strong> of the three alternatives).<br />

Table 3-15 Comparis<strong>on</strong> of Alternative Routes<br />

Evaluati<strong>on</strong> items Alternative 1 Alternative 2 Alternative 3<br />

Road alignment Most smooth<br />

Slightly shifted<br />

A curved secti<strong>on</strong> with<br />

alignment<br />

eastward 50-100m small radius is<br />

from Alternative 1 to introduced to avoid<br />

avoid houses.<br />

power line towers.<br />

Side span of main<br />

bridge includes a part<br />

of curve secti<strong>on</strong>.<br />

Affected houses Many houses near Less than Alt-1.<br />

Less than Alt-1.<br />

old ferry terminal<br />

(309 houses)<br />

(160 houses)<br />

(170 houses)<br />

Main River width is 550 River width is 550 m River width is 500 m<br />

Bridge m and c<strong>on</strong>structi<strong>on</strong> and c<strong>on</strong>structi<strong>on</strong> cost and c<strong>on</strong>structi<strong>on</strong> cost<br />

cost is high. Depth is high. Depth at river is less. Depth at river<br />

at river center is center is more than 30 center is more than 30<br />

Cost<br />

good<br />

bad<br />

poor<br />

3-32<br />

good<br />

good<br />

poor<br />

bad<br />

good<br />

better