In this preparati<strong>on</strong> stage of the project, the technical and ec<strong>on</strong>omic divisi<strong>on</strong> is in charge of<br />

providing assistance to the Study Team.<br />

Functi<strong>on</strong>al Divisi<strong>on</strong><br />

1.PMU Office<br />

2.Finance & Statistics<br />

Divisi<strong>on</strong><br />

3.Technical &<br />

Ec<strong>on</strong>omic Divisi<strong>on</strong><br />

4.Land Acquisiti<strong>on</strong><br />

Divisi<strong>on</strong><br />

Project Management<br />

(PM) Divisi<strong>on</strong><br />

1.Can Tho Bridge<br />

PM Div.<br />

2.PM Div. No. 1<br />

3.PM Div. No. 2<br />

4.PM Div. No. 3<br />

5.PM Div. No. 4<br />

6.PM Div. No. 5<br />

7.PM Div. No. 6<br />

Source: Decisi<strong>on</strong> No.1349 QD/TCCB-PMUMT dated May 3, 2006<br />

GENERAL DIRECTOR<br />

VICE GENERAL DIRECTORS<br />

7-4<br />

Organizati<strong>on</strong> in<br />

charge of<br />

preparati<strong>on</strong> for<br />

project operati<strong>on</strong><br />

Expressway<br />

Temporary<br />

Management Center<br />

Figure 7-1 Organizati<strong>on</strong> Chart of PMU My Thuan<br />

PMU My Thuan has 106 pers<strong>on</strong>nel as detailed in Table 7-2 below.<br />

Table 7-2 List of Pers<strong>on</strong>nel of PMU My Thuan<br />

No. Descripti<strong>on</strong> Number Ratio (%)<br />

1 Level over university 8 7<br />

2 Graduate from University 74 70<br />

3<br />

4<br />

Higher educati<strong>on</strong> level,<br />

Intermediate Level<br />

Technical workers and other<br />

laborers<br />

Source: PMU My Thuan’s web site (http://113.161.71.177/Home.aspx)<br />

(b) Project Implementati<strong>on</strong> Reports<br />

7 7<br />

17 16<br />

106 100%<br />

Representative<br />

Offices<br />

1.Rep. Office in Hanoi<br />

2.Rep. Office in Can<br />

Tho<br />

During the Project implementati<strong>on</strong>, PMU My Thuan is resp<strong>on</strong>sible for the preparati<strong>on</strong><br />

and submissi<strong>on</strong> of the following reports to MOT, MPI, MOF and the people’s committees of<br />

provinces where the Project will be implemented:<br />

♢ M<strong>on</strong>thly report within 10 days at the end of each m<strong>on</strong>th.<br />

♢ Quarterly report within 15 days at the end of each quarter.<br />

♢ Annual report within 1 m<strong>on</strong>th after the following year.