In this preparati<strong>on</strong> stage of the project, the technical and ec<strong>on</strong>omic divisi<strong>on</strong> is in charge of<br />
providing assistance to the Study Team.<br />
Functi<strong>on</strong>al Divisi<strong>on</strong><br />
1.PMU Office<br />
2.Finance & Statistics<br />
Divisi<strong>on</strong><br />
3.Technical &<br />
Ec<strong>on</strong>omic Divisi<strong>on</strong><br />
4.Land Acquisiti<strong>on</strong><br />
Divisi<strong>on</strong><br />
Project Management<br />
(PM) Divisi<strong>on</strong><br />
1.Can Tho Bridge<br />
PM Div.<br />
2.PM Div. No. 1<br />
3.PM Div. No. 2<br />
4.PM Div. No. 3<br />
5.PM Div. No. 4<br />
6.PM Div. No. 5<br />
7.PM Div. No. 6<br />
Source: Decisi<strong>on</strong> No.1349 QD/TCCB-PMUMT dated May 3, 2006<br />
GENERAL DIRECTOR<br />
VICE GENERAL DIRECTORS<br />
7-4<br />
Organizati<strong>on</strong> in<br />
charge of<br />
preparati<strong>on</strong> for<br />
project operati<strong>on</strong><br />
Expressway<br />
Temporary<br />
Management Center<br />
Figure 7-1 Organizati<strong>on</strong> Chart of PMU My Thuan<br />
PMU My Thuan has 106 pers<strong>on</strong>nel as detailed in Table 7-2 below.<br />
Table 7-2 List of Pers<strong>on</strong>nel of PMU My Thuan<br />
No. Descripti<strong>on</strong> Number Ratio (%)<br />
1 Level over university 8 7<br />
2 Graduate from University 74 70<br />
3<br />
4<br />
Higher educati<strong>on</strong> level,<br />
Intermediate Level<br />
Technical workers and other<br />
laborers<br />
Source: PMU My Thuan’s web site (http://113.161.71.177/Home.aspx)<br />
(b) Project Implementati<strong>on</strong> Reports<br />
7 7<br />
17 16<br />
106 100%<br />
Representative<br />
Offices<br />
1.Rep. Office in Hanoi<br />
2.Rep. Office in Can<br />
Tho<br />
During the Project implementati<strong>on</strong>, PMU My Thuan is resp<strong>on</strong>sible for the preparati<strong>on</strong><br />
and submissi<strong>on</strong> of the following reports to MOT, MPI, MOF and the people’s committees of<br />
provinces where the Project will be implemented:<br />
♢ M<strong>on</strong>thly report within 10 days at the end of each m<strong>on</strong>th.<br />
♢ Quarterly report within 15 days at the end of each quarter.<br />
♢ Annual report within 1 m<strong>on</strong>th after the following year.