Combination 4: Into service, Wind parallel<br />
Coefficients<br />
BG1 Self weight<br />
BG2 Self weight toeboards<br />
BG3 Service load Main floor<br />
BG4 Service load Main floor<br />
BG9 Working wind load parallel with facade<br />
22<br />
<strong>Advanced</strong> <strong>Training</strong><br />
With the Combinations in Ultimate Limit State, a safety factor γF of 1,50 on the load cases is taken,<br />
conformable to the code EN 12811 §10.3.2. The safety factor γM on the material is 1,10.<br />
For the serviceability γF and γM shall be taken as 1,00.