(Audit) for scrutinizing, remarks and corrections. These proposals are<br />

examined by the Spot Auditor and his staff.<br />

2.23 PENALTY:<br />

When the Contractor has exceeded the time limit stipulated in the contract, he is liable to pay<br />

penalty as specified in the tender conditions.<br />

The Asst. General Manager (Civil) is competent, under these conditions, to<br />

(a) impose the full penalty or<br />

(b) take into account non-working days on which no work could<br />

be done because of circumstances entirely beyond the control<br />

of the Contractor by adding the period of such non-working<br />

days to the contractual date of completion and arriving at a<br />

new expected date of completion to which extent penalty, only<br />

under these circumstances, could be offset to the advantage<br />

of the Contractor.<br />

The Asst. General Manager (Civil)’s approval is obtained when extenuating<br />

circumstances exist for reduction or complete waiver of penalty or in any<br />

other circumstances.<br />

2.24 DELETION OF ITEM FROM CONTRACT:<br />

At times original work provided for in contract is found unnecessary or it<br />

is envisaged that the same may not be executed at the time of progress of<br />

work. In such cases the Asst. General Manager (Civil) is competent to<br />

sanction the deletion of such work from the contract. In the case of<br />

addition of an item to the contract, the inclusion of the extra item requires<br />

the Asst. General Manager (Civil)’s approval.