b) whether all the tenderers have fulfilled the General Condition of<br />

contract and tender condition;<br />

c) whether comparative statement has been prepared and ranking is<br />

given correctly;<br />

d) Whether contract is awarded to the lowest tenders and if not,<br />

reason for over looking for lower offer;<br />

e) to ensure competent authority for awarding the contracts,<br />

considering the contract amount;<br />

f) to ensure that intending contractor/bidder has paid EMD /PEMD;<br />

g) if contract amount exceeds the sanction amount, whether sanction<br />

of proper authority is availed for exceeding amount.<br />

2.6 EARTH FILLING:<br />

2.6.1 (a) In Open Spaces:<br />

Before earth filling is done, measurements of the ground in its original state are taken by<br />

means of leveling instruments. The levels are taken at suitable spots from cross sections of<br />

embankments before the start of work.<br />

After the levels of the ground in its original state are taken, earth filling is started. On its<br />

completion, measurements are again taken at the same spots on the filled up ground.<br />

2.6.2 (b) In other spaces:<br />

When it is not possible to measure earth filling from cross sections by the above method due to<br />

the land being marshy, watery, etc., payment is certified on the basis of the lorry measurement system.<br />

The cubic contents of the lorries emptied in the plot are recorded. From the sum of quantities