View/Open - University of Zululand Institutional Repository
View/Open - University of Zululand Institutional Repository View/Open - University of Zululand Institutional Repository
163 costs), the situation prevailing before the floods. The scheme was valid for a period of 30 months, effective from the 1st of October 1987. In order to qualify for the subsidy, a particular farm unit had to be situated in the flood disaster area. Secondly, only those farm units which were recognized by the then Department of Agriculture and Water Supply (now the Department of Agriculture), as having suffered flood damage, were eligible for the subsidy. Documentary proof of flood damage accompanied by a map indicating the areal extent of the damage, plus other relevant information, was required. Applicants were given six months in which to register for the scheme. No flood repairs, for which a subsidy was requested, could be undertaken prior to consent by the Department. The only exception was the repair of damage to fences and stock watering systems essential for the continuation of farming activities. These repairs could be made immediately after the subsidy application had been lodged. Written consent from the Department specified the repairs which could be undertaken, as well as the materials needed (for which invoices had to be obtained and submitted to the Department). The consent included plans and specifications in accordance with which the subsidized repairs had to be undertaken. Land users were also entitled to submit their own plans and specifications. If these proposals were accepted by the Department, then the damage was to be repaired as per the plans submitted. The Department had to be notified once the subsidiz.ed repairs had been completed (within the stipulated period according to the consent). Failure to notify the Department could have resulted in a refusal to pay any subsidy, or a postponement of payment. Where flood damage was unlikely to be repaired within the consent period, the Department was empowered to extend that period (on application by the land user), provided that the maximum period of 30 months was observed. Notification of the.completion of repairs by the land user, included a written statement providing the exact dimensions and specifications of the repairs undertaken, in accordance with the agreed plans. Repairs were required to be functional (where applicable). Confirmation was also needed that the repairs had been undertaken using new materials, except where otherwise permitted. Alternatively, Departmental staff were required to inspect the farm unit and to compile a report on the repairs. Inspection of the repairs could be carried out either before or after the subsidy had been paid.
11111.'.111:11111 164 If it became evident that the repairs had not been undertaken in accordance with the agreed plans, or that the repairs did not qualify for a subsidy for any other reason, then no subsidy was payable until the issue had been resolved. Where the land user had received flood assistance by means of a loan in terms of the Agricultural Credit Act No. 28 of 1966, the subsidy was used as payment or part payment of the amount (plus interest), due to the State as a result of such assistance. If it became apparent that no subsidy should have been paid for repairs, or that the dimensions and specifications of the repairs claimed to have been undertaken were incorrect (and that the amount paid as subsidy exceeded the amount that was lawfully payable as subsidy), then the land user was required to repay the money, together with interest as calculated in terms of the Exchequer and Audit Act No. 66 of 1975. If any other error was made in calculating the subsidy, the land user was obliged to repay the money (paid in error) within 60 days. Failure to pay within a period of 60 days, would result in interest being levied in accordance with the latter Act. A tariff list approved by the then Minister of Agriculture and Water Supply served as the basis for calculating the amount of subsidy due, in terms of the flood relief scheme. Different tariff lists may be approved in future for other flood disaster areas. NOTES:
- Page 115 and 116: 112 Attention has also been focused
- Page 117 and 118: 114 10.17 Some legal aspects of wat
- Page 119 and 120: 116 time (mean exceedance flow), du
- Page 121 and 122: IIII.IIWIIIII 118 10.17.4 Use of wa
- Page 123 and 124: 1[lIlIIIIIIJ. 120 Government dams,
- Page 125 and 126: 10.18.4 River diversions 122 Depart
- Page 127 and 128: 124 10.18.6 Irrigation districts an
- Page 129 and 130: 111(11111:41m'l 126 Table J36: Irri
- Page 131 and 132: Table J37: Irrigation boards in Nat
- Page 133: Tabla J37: Irrigation boards In Nat
- Page 136 and 137: 133 Table J38: Some urban areas in
- Page 138 and 139: 135 Table J38: Some urban areas in
- Page 140 and 141: Table J38: 137 Some urban areas in
- Page 142 and 143: 139 Source: (i) After Ardington, E.
- Page 144 and 145: 141 i111_1illll1l noted above!. are
- Page 146 and 147: 143 (ii) The Directorate of Land an
- Page 148 and 149: 145 1111111111111 the Board will as
- Page 150 and 151: 147 Table J40: Administrative regio
- Page 152 and 153: 149 111II1.llllIf:J Government Noti
- Page 154 and 155: 151 111I.lIllllil1 Government agenc
- Page 156 and 157: 153 Table J43: Joint Services Board
- Page 159 and 160: 156 Source: (i) After Jenkin, F. (e
- Page 161 and 162: 158 Chief Directorate: Administrati
- Page 163 and 164: Source: See also: Note: 160 Afterth
- Page 165: 162 off low - responsible inter ali
- Page 169 and 170: tlll••••I:IB11 NOTES: 166
- Page 171 and 172: Contents 167 CHAPTER 11: GROUNDWATE
- Page 173: Tables 169 Table K1: Some geologica
- Page 178 and 179: 174 Bate, 1992}*. The use of water
- Page 180 and 181: 176 X313, Pretoria, 0001; as well a
- Page 183 and 184: 179 a particular site, then a stati
- Page 185 and 186: 181 111...1[111 of streams and rive
- Page 187 and 188: 183 good. with a total dissolved so
- Page 189 and 190: (iii) Holocene sands lQuaternary) 1
- Page 191 and 192: 187 Table K1: Some geological forma
- Page 193 and 194: 189 fault-bounded blocks, although
- Page 195 and 196: 191 11.6.4 Aquifer characteristics
- Page 197 and 198: 193 coarse and the latter, fine and
- Page 199 and 200: 195 111.BIII!I!111 The yields of bo
- Page 202 and 203: 11...,].11 198 11.7 Methods of grou
- Page 205 and 206: 201 11...11111 Table K3: Methods of
- Page 207 and 208: 203 boreholes are drilled for both
- Page 209 and 210: 205 1111111111'.1 3838. The borehol
- Page 211 and 212: 207 11.11 Standards applicable to t
- Page 213 and 214: (a) Gravity springs 209 Gravity spr
- Page 215: Table K4: Spring discharge in the V
163<br />
costs), the situation prevailing before the floods. The scheme was valid for a period <strong>of</strong> 30<br />
months, effective from the 1st <strong>of</strong> October 1987.<br />
In order to qualify for the subsidy, a particular farm unit had to be situated in the flood<br />
disaster area. Secondly, only those farm units which were recognized by the then<br />
Department <strong>of</strong> Agriculture and Water Supply (now the Department <strong>of</strong> Agriculture), as<br />
having suffered flood damage, were eligible for the subsidy. Documentary pro<strong>of</strong> <strong>of</strong> flood<br />
damage accompanied by a map indicating the areal extent <strong>of</strong> the damage, plus other<br />
relevant information, was required. Applicants were given six months in which to register<br />
for the scheme. No flood repairs, for which a subsidy was requested, could be undertaken<br />
prior to consent by the Department. The only exception was the repair <strong>of</strong> damage to<br />
fences and stock watering systems essential for the continuation <strong>of</strong> farming activities.<br />
These repairs could be made immediately after the subsidy application had been lodged.<br />
Written consent from the Department specified the repairs which could be undertaken, as<br />
well as the materials needed (for which invoices had to be obtained and submitted to the<br />
Department). The consent included plans and specifications in accordance with which the<br />
subsidized repairs had to be undertaken. Land users were also entitled to submit their own<br />
plans and specifications. If these proposals were accepted by the Department, then the<br />
damage was to be repaired as per the plans submitted.<br />
The Department had to be notified once the subsidiz.ed repairs had been completed (within<br />
the stipulated period according to the consent). Failure to notify the Department could<br />
have resulted in a refusal to pay any subsidy, or a postponement <strong>of</strong> payment. Where flood<br />
damage was unlikely to be repaired within the consent period, the Department was<br />
empowered to extend that period (on application by the land user), provided that the<br />
maximum period <strong>of</strong> 30 months was observed. Notification <strong>of</strong> the.completion <strong>of</strong> repairs by<br />
the land user, included a written statement providing the exact dimensions and<br />
specifications <strong>of</strong> the repairs undertaken, in accordance with the agreed plans. Repairs<br />
were required to be functional (where applicable). Confirmation was also needed that the<br />
repairs had been undertaken using new materials, except where otherwise permitted.<br />
Alternatively, Departmental staff were required to inspect the farm unit and to compile a<br />
report on the repairs. Inspection <strong>of</strong> the repairs could be carried out either before or after<br />
the subsidy had been paid.