<strong>Gujarat</strong> State Road Development Corporation Ltd. Improvement and<br />
Widening of Bagodara-Wataman-Tarapur-Vasad road [ State Highway <strong>–</strong> 8 ]<br />
The earlier presentation on the proposed improvement and strengthening of Bagodara-<br />
Wataman-Tarapur-Vasad road of state highway-8.included salient features like proposed<br />
Right of Way, Construction aspects, Existing land user pattern, need of the project,<br />
environmental aspects related to water and land etc. It was also informed by the project<br />
proponent that the proposed widening shall entail additional land acquisition. After detailed<br />
deliberations by the experts, additional Terms of Reference were prescribed<br />
1. Detailed study flora & fauna of the study area and impact analysis due to proposed<br />
project<br />
2. Detailed study on hydrology, drainage pattern of the study area and impact analysis<br />
due to proposed project and mitigation measures.<br />
3. Land acquisition details and change in land use pattern due to proposed project<br />
especially with respect to agricultural land as well as likely impact.<br />
4. Impact on water bodies surrounding the project site i.e. in study area due to proposed<br />
project..<br />
5. Top soil management plan for the proposed project.<br />
6. Detailed Environmental Management Plan of the stone crushing plants, hot mix<br />
plants, Ready Mix Concrete plants that may come up temporarily for this projects.<br />
7. Detailed Safety provisions proposed during the construction of the project..<br />
8. Bar chart of the project specifying time period.<br />
9. Details on the consumption of water during construction and operation, source of<br />
water supply and permissions from the concerned authority in the case of ground<br />
water extraction.<br />
10. Clearance from the Forest department for the existing tree cutting and details of<br />
compensatory plantation plan.<br />
11. Detailed Environment Management Plan along with all proposed mitigation measures<br />
for both construction phase and operation phase.<br />
12. Base line status of Ambient air quality and modeling indicating the likely impact on<br />
ambient air quality due to proposed activities in operation phase.<br />
13. Detailed green-belt development plan.<br />
14. Highway design drawing with cross section showing road thickness, super elevation,<br />
road slope to drain water etc