21.04.2013 Views

Installation 1. Preparations 2. Connecting pipes 3. Connecting fittings

Installation 1. Preparations 2. Connecting pipes 3. Connecting fittings

Installation 1. Preparations 2. Connecting pipes 3. Connecting fittings

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

4. Shortening pipe lengths<br />

VML <strong>pipes</strong> are delivered in standard lengths of 3m. The required pipe lengths can be<br />

obtained on site with a pipe cutting machine or a belt saw. The first step is to cut the VML<br />

pipe to the exact length and to remove the insulation from the spigot.<br />

a) Mark cutting positions<br />

Cut I: measure of complete required<br />

pipe length<br />

Cut II: length of insulation removal<br />

as follows:<br />

DN 50 74 mm<br />

DN 80 77mm<br />

DN 100 86 mm<br />

DN 125 95 mm<br />

DN 150 95 mm<br />

DN 200 100 mm<br />

b) Cut pipe at the required length (cut I)<br />

c) Cut steel plate cover and insulation (cut<br />

II). Maximum cutting depth 10 mm!!<br />

d) Remove steel plate cover and<br />

insulation.<br />

2

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!