<strong>National</strong> <strong>Park</strong> <strong>Service</strong> FY 2013 Budget Justifications<br />

Ranking Categories: Identify the percent of the project that is in the following categories of need.<br />

33 % Critical Health or Safety Deferred Maintenance 0 % Energy Policy, High Performance Sustain Bldg CI<br />

0 % Critical Health or Safety Capital Improvement 33 % Critical <strong>Mission</strong> Deferred Maintenance<br />

34 % Critical Resource Protection Deferred Maintenance 0 % Other Deferred Maintenance<br />

0 % Critical Resource Protection Capital Improvement 0 % Code Compliance Capital Improvement<br />

0 % Other Capital Improvement<br />

Capital Asset Planning 300B Analysis Required: [ YES ] Total Project Score: 700<br />

Project Costs and Status<br />

Project Cost Estimate (This PDS): $'s %<br />

Deferred Maintenance Work : $ 3,481,000 100<br />

Capital Improvement Work: $ 0 0<br />

Total Project Estimate*: $ 3,481,000 100<br />

Class of Estimate: B<br />

Estimate Escalated To FY: 2013<br />

Dates: Sch’d (qtr/yy)<br />

Construction Start/Award: 2Q/2013<br />

Project Complete: 2Q/2014<br />

Project Funding History (Entire Project): $’s<br />

Appropriated to Date*: $ 273,045,000<br />

Pre-2000 Planning*: $<br />

Land Acquisition*: $<br />

CONST-25<br />

8,080,000<br />

29,880,000<br />

Requested in FY 2013 Budget: $ 3,481,000<br />

Required to Complete Project: $ 10,166,000<br />

Project Total*: $ 324,652,000<br />

Project Data Sheet<br />

Prepared/Last Updated: 06/2011<br />

Annual Operation & Maintenance Costs($s)<br />

Current: $ 0 Projected: $ 0 Net Change: $ 0<br />

DOI Approved:<br />

YES<br />

* Appropriated to Date and the Project Total, above, include American Recovery and Reinvestment Act (ARRA)<br />

funding of $44.448 million. Pre-FY 2000 planning ($8.08 million), and land acquisition to date ($29.88 million) have<br />

been added for clarity.