<strong>National</strong> <strong>Park</strong> <strong>Service</strong> FY 2013 Budget Justifications<br />

information desk, the Yellowstone Association bookstore, interpretive staff offices, as well as media<br />

and Web services operations.<br />

Ranking Categories: Identify the percent of the project that is in the following categories of need.<br />

7 % Critical Health or Safety Deferred Maintenance 0 % Energy Policy, High Performance Sustain Bldg CI<br />

37 % Critical Health or Safety Capital Improvement 0 % Critical <strong>Mission</strong> Deferred Maintenance<br />

38 % Critical Resource Protection Deferred Maintenance 10 % Other Deferred Maintenance<br />

5 % Critical Resource Protection Capital Improvement 3 % Code Compliance Capital Improvement<br />

0 % Other Capital Improvement<br />

Capital Asset Planning Required?(Y or N): [ Y ]<br />

VE Required(Y or N): Y Type: C Scheduled(YY): FY 06 Completed(YY): FY 2006<br />

Project Costs and Status<br />

Project Cost Estimate (This PDS): $'s %<br />

Deferred Maintenance Work : $ 4,887,850 55<br />

Capital Improvement Work: $ 3,999,150 45<br />

Total Component Estimate: $ 8,887,000 100<br />

Class of Estimate: C<br />

Estimate Escalated to FY: 2013<br />

Dates: Sch’d (qtr/yy)<br />

Construction Start/Award: 2Q⁄2013<br />

Project Complete: 4Q⁄2014<br />

CONST-21<br />

Total Project Score: 782<br />

Project Funding History (Entire Project):<br />

Appropriated to Date: $ 478,000<br />

Requested in FY 2013 Budget: $ 8,887,000<br />

Future Funding to Complete Project: $ 0<br />

Project Total: $ 9,365,000<br />

Planning and Design Funds<br />

Planning Funds Received in FY 2005-2008 $ 168,300<br />

Design Funds Received in FY 2008 $ 309,700<br />

Project Data Sheet<br />

DOI Approved:<br />

Prepared/Last Updated: 06/2011<br />

(mm/yy)<br />

YES<br />

Annual Operation & Maintenance Costs($s)<br />

Current: $ 1,500,000 Projected: $1,554,099 Net Change: $54,099