<strong>National</strong> <strong>Park</strong> <strong>Service</strong> FY 2013 Budget Justifications<br />

Ranking Categories: Identify the percent of the project that is in the following categories of need.<br />

44 % Critical Health or Safety Deferred Maintenance 0 % Energy Policy, High Performance Sustain Bldg CI<br />

14 % Critical Health or Safety Capital Improvement 0 % Critical <strong>Mission</strong> Deferred Maintenance<br />

21 % Critical Resource Protection Deferred Maintenance 0 % Other Deferred Maintenance<br />

11 % Critical Resource Protection Capital Improvement 10 % Code Compliance Capital Improvement<br />

0 % Other Capital Improvement<br />

Capital Asset Planning Required?(Y or N): [ Y ]<br />

VE Required(Y or N): Y Type: C Scheduled(YY): FY 2012 Completed(YY):<br />

Project Cost Estimate (This PDS): $'s %<br />

Deferred Maintenance Work : $ 4,043,650 65<br />

Capital Improvement Work: $ 2,177,350 35<br />

Total Component Estimate: $ 6,221,000 100<br />

Class of Estimate: C<br />

Estimate Escalated to FY: 2013<br />

Dates: Sch’d (qtr/yy)<br />

Construction Start/Award: 3Q/2013<br />

Project Complete: 4Q/2014<br />

Project Costs and Status<br />

CONST-17<br />

Total Project Score: 826<br />

Project Funding History (Entire Project):<br />

Appropriated to Date: $ 358,000<br />

Requested in FY 2013 Budget: $ 6,221,000<br />

Future Funding to Complete Project: $ 0<br />

Project Total: $ 6,579,000<br />

Planning and Design Funds<br />

Planning Funds Received in FY 2011 $ 358,000<br />

Design Funds Received in FY NA $ ____<br />

Project Data Sheet<br />

DOI Approved:<br />

Prepared/Last Updated: 06/2011<br />

(mm/yy)<br />

YES<br />

Annual Operation & Maintenance Costs($s)<br />

Current: $295,000 Projected: $245,000 Net Change: - $50,000