13.04.2013 Views

Paper Technology Journal 19 - Voith

Paper Technology Journal 19 - Voith

Paper Technology Journal 19 - Voith

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

● Project duration max. 18 months<br />

● Shutdown time max. 65 days, incl. the<br />

extensive civil engineering work.<br />

The project developed, based on these<br />

targets, from the first day on into a superlative<br />

for design, planning and logistics.<br />

<strong>Voith</strong> was able to convince the customer<br />

in the project phase that this could<br />

only be achieved by minimizing the interfaces,<br />

i.e. by <strong>Voith</strong> <strong>Paper</strong> supplying all<br />

the equipment and taking overall responsibility.<br />

The order covered not only<br />

the paper machine based on the proven<br />

One Platform Concept with DuoCentri-<br />

1<br />

NipcoFlex Press and Online Janus Calender,<br />

but also all auxiliaries, the approach<br />

flow system including broke pulper as<br />

well as the complete production line engineering.<br />

As part of the Process Line<br />

Package (PLP), the scope of supply also<br />

covered the process pumps, tanks, piping<br />

and air system equipment as well as the<br />

entire installation work, start-up and personnel<br />

training.<br />

Project handling<br />

Cramped space conditions and the linkage<br />

of the process piping and wiring with<br />

paper machines 7 and 8 that have grown<br />

over the years rendered the implementation<br />

of the rebuild activities difficult.<br />

During the planning phase further basic<br />

knowledge of the extent of the construction<br />

work to be carried out in the peripheral<br />

system became transparent. This<br />

necessary civil engineering work required<br />

detailed progress and deadline schedules.<br />

Optimal implementation of the<br />

activities between civil engineering and<br />

mechanical engineering was required to<br />

meet the time frame.<br />

When the old PM was shut down on<br />

July 2, 2004, a meticulously planned<br />

rebuild action began. The first machine<br />

parts in the wet end had hardly been dismantled<br />

when the civil engineering work<br />

began with excavators lifted in through<br />

the roof to demolish almost the complete<br />

machine framing.<br />

The dismantling of the cabling, which has<br />

grown over the decades, had to be prepared<br />

in tricky detailed work. Tracing of<br />

Fig. 1: Maxau PM 6.<br />

Fig. 2: Schematic of Maxau PM 6.<br />

Fig. 3: Wire change.<br />

21<br />

cable routes, existing dead cables, identifying<br />

the cables and safety-conscious<br />

dismantling of the cables called for<br />

months of preparation work. The result<br />

was extremely positive. Neither of the<br />

two paper machines still running was<br />

stopped, and the safety requirements<br />

were all met.<br />

The reel section with Sirius reel and<br />

Janus calender were already installed<br />

when the construction workers were still<br />

working on the wet-end foundations.<br />

At times more than 1,300 erectors, civil<br />

engineering workers, electricians, pipe<br />

layers, etc., were performing the impossible<br />

on a daily basis in cramped space<br />

conditions: punctually on August 31,<br />

2004 the main part of the installation<br />

work was finished and the start-up team<br />

could begin with the check-outs.<br />

<strong>19</strong>/05<br />

3

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!