13.04.2013 Views

Paper Technology Journal 17 - Voith

Paper Technology Journal 17 - Voith

Paper Technology Journal 17 - Voith

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

2<br />

Specialists visited the mill and examined<br />

all current threading processes thoroughly.<br />

They discussed the threading difficulties<br />

with personnel at the mill and developed<br />

a detailed optimization plan based<br />

on their findings.<br />

The first problematic threading section<br />

was Dryer 52 to the last Coater ropes<br />

section. Originally, the tail was transferred<br />

into the rope nip by air nozzles located<br />

under a mini doctor blade. This<br />

system did not operate properly and required<br />

operator involvement when blowing<br />

the tail into the rope nip. The new solution<br />

from <strong>Voith</strong> TTG included a multiple<br />

VTT Turbo conveyor system to stabilize<br />

the tail, eliminate the double tail and to<br />

provide a reliable, controlled transfer into<br />

the rope nip. The VTT Turbo conveyors<br />

are built with internal turbines that generate<br />

a large amount of vacuum. These<br />

conveyors also include an internal Drum<br />

Drive for efficient operation and space<br />

savings. This section was rebuilt during<br />

the summer of 2002, approximately eight<br />

weeks before the main shut, allowing a<br />

smooth and efficient take-over for the operators.<br />

This contributed to a good startup<br />

after the main rebuild as the operators<br />

were already familiar with the new<br />

threading technology.<br />

The second optimized section was the<br />

Dryer to Size Press section. Again, the<br />

original system used air nozzles to blow<br />

the tail into the ropes. This manual sys-<br />

3<br />

Finishing<br />

tem was very unreliable and compromised<br />

operator safety. The optimized solution<br />

included a multiple VTT Turbo conveyor<br />

section with a Flip Tray transfer device<br />

and a Tail Ripper. The Flip Tray was<br />

mounted directly on the dryer cylinder<br />

doctor to allow for the movement of the<br />

scanners and other equipment. The purpose<br />

of the Flip Tray was to stabilize the<br />

tail during the transfer. The Tail Ripper<br />

was used to efficiently eliminate the double<br />

tail.<br />

The third section to be optimized was<br />

Dryer 2R to the 1st Coater Ropes section.<br />

Again, air nozzles were used in the original<br />

transfer. As the air nozzles were located<br />

under the doctor blade, the system<br />

didn’t operate properly and required operator<br />

involvement. The new solution included<br />

VTT Turbo conveyors, a Flip Tray<br />

and a Tail Ripper. In this section, the Flip<br />

Tray moves the tail onto the conveyor<br />

where the tail is kept under control and<br />

transferred into the rope nip. The rope<br />

nip was also relocated to allow for a better<br />

tail transfer into the coater ropes.<br />

The results of the optimization process<br />

were exceptional. Right after the system<br />

start-up, threading was successful 85%<br />

on the first attempt and 100% within<br />

three attempts. Threading times were<br />

also significantly reduced allowing for increased<br />

machine efficiency and production.<br />

Other benefits from the optimization<br />

included elimination of double tail, no<br />

Min<br />

30<br />

25<br />

20<br />

15<br />

10<br />

5<br />

0<br />

20<br />

Fig. 2: VTT Turbo conveyor<br />

installed at Condat.<br />

Fig. 3: Dryer to size press<br />

drawing; optimized threading<br />

at Condat.<br />

Fig. 4: Threading times before<br />

and after optimization.<br />

Before optimization<br />

After optimization<br />

10<br />

15<br />

5<br />

30<br />

15<br />

Coater 1 Coater 2 Film Press<br />

Sections<br />

43<br />

manual intervention, improved operator<br />

safety, limited maintenance requirements<br />

and space savings. <strong>Voith</strong> TTG took full<br />

ownership of the threading process during<br />

start-up resulting in a significant<br />

threading improvement.<br />

Within six months of the start-up, total<br />

time losses at the coater sections had<br />

been reduced by 35%. The optimization<br />

resulted in a significant 65% reduction in<br />

threading downtime. The mill and operators<br />

are also impressed with the reliability<br />

of the threading system and the effect<br />

the system has had on operator safety.<br />

The ultimate result of this optimization is<br />

a 4% increase in total machine efficiency.<br />

In a very short time, less than seven<br />

months, this installation has proven to be<br />

very successful. The co-operation between<br />

<strong>Voith</strong> and the customer Condat<br />

made it possible to reach all the deadlines<br />

and make this installation a true<br />

success.<br />

<strong>17</strong>/04<br />

4

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!