Preamble:<br />
34<br />
Chapter – 5<br />
BASES AND SURFACE COURSES (BITUMINOUS)<br />
1 Various alternatives <strong>for</strong> machines <strong>and</strong> materials have been provided. The one that suits a particular<br />
situation <strong>and</strong> design may be adopted.<br />
2 The outputs considered <strong>for</strong> construction equipment are <strong>for</strong> compacted quantities <strong>of</strong> relevant items<br />
<strong>and</strong> not <strong>for</strong> loose quantities.<br />
3 In case <strong>of</strong> prime coat <strong>and</strong> tack coat, average quantities <strong>of</strong> binder indicated in specifications have<br />
been taken.<br />
4 Tack coat <strong>and</strong> prime coat, wherever provided, are required to be measured <strong>and</strong> paid separately.<br />
5 Cleaning <strong>of</strong> surface is a part <strong>of</strong> the item <strong>of</strong> prime coat <strong>and</strong> tack coat. As such cleaning <strong>of</strong> surface<br />
has not been provided <strong>for</strong> bituminous courses as the same is already catered in prime/tack coat.<br />
However, <strong>for</strong> those cases where such coats are not required to be done, cleaning <strong>of</strong> surface shall<br />
be included <strong>and</strong> paid.<br />
6 Rolling <strong>of</strong> bituminous courses is required to be done as per Clause 501.6 <strong>of</strong> MORD Specifications.<br />
Provision in the analysis has been made accordingly. It has been observed during actual practice at<br />
work sites, that the availability <strong>of</strong> road roller is generally inadequate. As compaction is the key to<br />
good construction, this point is being specifically highlighted to ensure that adequate number <strong>of</strong><br />
road rollers as per provision in the rate analysis are deployed at site.<br />
7 Spreading <strong>of</strong> bituminous materials shall be done by mechanical means except in areas where a<br />
mechanical paver cannot have access.<br />
8 Hot Mazdoor is the one who work <strong>for</strong> Bitumen heating/spreading or spreading <strong>of</strong> hot bituminous<br />
mix. He will be paid the same wages. However, he will be provided safety kits containing normally<br />
gumboots, h<strong>and</strong> gloves, dark goggles, barnol, country soap, coconut oil, tarring outfits, etc. For this<br />
purpose, additional 0.5 per cent sundries have been provided in the analysis <strong>of</strong> rates in addition to<br />
the normal sundries covered by overheads.<br />
9 Where the proposed aggregates fail to pass the stripping value test, an approved adhesion agent<br />
shall be added to the binder as per Clause 507.2.4 with the approval <strong>of</strong> the Engineer <strong>and</strong> cost <strong>of</strong> the<br />
adhesion agent shall be added under the subhead <strong>of</strong> materials.<br />
10 The Factor <strong>for</strong> usage <strong>of</strong> rollers has been taken as 0.65 in case <strong>of</strong> Bituminous Macadam only.