Power distribution<br />
DTEK's power distribution enterprises continued the upgrade<br />
of the existing equipment and the construction of the new<br />
units. Particularly, the reconstruction works were performed<br />
at Druzhkovka, Davydovka-Severnaya, Zueyvka, Ugolno-<br />
Rtutnaya, Novomakeyevka, and Shvernik (all Service-Invest)<br />
substations, as well as at Skiv, Oktyabrskaya, and Yuzhno-<br />
Donbasskaya #1 substations (all DTEK PES-Energougol).<br />
The renovations of the high-voltage transmission lines also<br />
continued. Additionally, Service-Invest completed the construction<br />
of the two substations, one of which is intended to<br />
supply electricity to Donetsk airport.<br />
The construction of Airport–110 kV substation was carried<br />
out within the framework of preparations to Euro–2012<br />
and was completed precisely on schedule. For the first time<br />
in Donbass, the new generation of electric equipment (ABB,<br />
Sweden-Switzerland) was installed. The total volume of investment<br />
amounted to $9.8m.<br />
The total volume of investment in the construction and the reconstruction<br />
of Service-Invest substations in <strong>2011</strong> amounted to<br />
$26m, and that of DTEK PES-Energougol – amounted to $5m.<br />
In <strong>2011</strong>, the volume of investment in developing Kievenergo's<br />
heat generation amounted to $19.1m. A large-scale<br />
reconstruction of Kievenergo's heating infrastructure was<br />
performed, in total worth approximately $14m.<br />
Occupational safety<br />
DTEK continued the implementation of the corporate standard<br />
for the individual safety gear. The total volume of project<br />
investment in the reporting year amounted to $2.2m.<br />
DTEK completed the certification of occupational safety management<br />
systems to comply with OHSAS 18001:2007 at<br />
the following enterprises: Service-Invest, DTEK PES-Energougol,<br />
Mospinskoye, Pavlogradskaya, Kurakhovskaya, DTEK Dobropolskaya,<br />
and DTEK Oktyabrskaya Enrichment Plants, as well as Socis,<br />
DTEK Service, and Pershotravensk Repair Mechanical Plant.<br />
The total volume of investment amounted to $21.8m.<br />
38<br />
14 DTEK's enterprises completed the certification of their environmental<br />
management systems to comply with ISO 14001:2004.<br />
The total volume of investment amounted to $0.6m.<br />
Focus points of the year<br />
In <strong>2011</strong>, DTEK's enterprises demonstrated significant growth<br />
of their production indicators, compared to 2010.<br />
10 DTEK Pavlogradugol, DTEK Komsomolets Donbassa Mine, and DTEK Dobropolyeugol.<br />
11 The volume of electricity of Vostokenergo and Dneproenergo, with the latter being an associated company in <strong>2011</strong><br />
(DTEK owned a 47.55% share).<br />
12 The indicators of Service-Invest and DTEK PES Energougol summarized, excluding Donetskoblenergo.<br />
The volume of coal mining by DTEK's mines 10 in <strong>2011</strong> amounted<br />
to 22.9m tonnes, cumulative 11 power generation increased<br />
to 33.0bn KW•hour, distribution – to 14.1bn KW•hour 12 .<br />
The increaed production of all DTEK's enterprises resulted<br />
from the implemented operational improvements, the ongoing<br />
large-scale equipment upgrade program, as well as<br />
the company's growth after purchasing the new assets.<br />
In June DTEK created DTEK Neftegaz, a subsidiary company,<br />
which will be responsible for oil and gas projects' development,<br />
on land and in deep sea. The development of oil and<br />
gas business will, in the long term, allow DTEK to diversify its<br />
fuel base and to provide for the needs of its power generating<br />
units fueled by gas and mazut (annual gas consumption<br />
exceeds 3bn cubic meters). The company will also be drilling<br />
methane from coal beds and gas from shale. DTEK has<br />
been implementing the pilot projects in this area since 2007.<br />
Currently, several mines of DTEK Pavlogradugol and DTEK<br />
Dobropolyeugol are running methane utilization projects.<br />
DTEK plans to launch the similar projects at the other mines<br />
of the two stated enterprises.<br />
In August, DTEK, Kiev City State Administration, and USAID<br />
signed a Memorandum of Cooperation under the Municipal<br />
Heating Reform Project, to improve the infrastructure and<br />
the energy efficiency of the Kiev city heat supply system.<br />
DTEK won the tender of the State Property Fund of Ukraine<br />
for the sale of a 25% share in Kievenergo, having proposed<br />
the price of $56.3m. As a result, DTEK controls a 71.82%<br />
sharein Kievenergo.