06.04.2013 Views

Damages: Lessons from Harmon - White & Case

Damages: Lessons from Harmon - White & Case

Damages: Lessons from Harmon - White & Case

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

This article fi rst appeared in Construction Law (Butterworths LexisNexis)<br />

Volume 14, Issue 9 November 2003 pp 29-31.<br />

<strong>Damages</strong>: <strong>Lessons</strong> <strong>from</strong><br />

<strong>Harmon</strong><br />

Ellis Baker and Anthony Lavers<br />

<strong>White</strong> & <strong>Case</strong>, London<br />

Ellis Baker and Anthony Lavers of <strong>White</strong> &<br />

<strong>Case</strong> continue their analysis of remedies<br />

potentially available to contractors aggrieved<br />

by breach of European procurement<br />

rules. <strong>Damages</strong> may prove to be generous<br />

runners up prizes, they suggest.<br />

Key Points:<br />

■ Article 2 of the EU Remedies Directives<br />

sets out the remedies for breach of the<br />

EU Procurement rules.<br />

■ The awarding authority had been<br />

operating a covert ‘buy British’ policy.<br />

■ The judge made clear that he considered<br />

that the remedies arose not just under<br />

statute but in contract.<br />

■ Neither the Remedies Directives nor<br />

the UK regulations give detailed guidance<br />

on how the claim for damages for lost<br />

profi t should be calculated.<br />

■ Awarding authorities have good reason<br />

to be concerned about the extent of<br />

their risk exposure.<br />

■ <strong>Damages</strong> may constitute a generous<br />

runners-up prize.<br />

■ In the fi rst part of the article, the authors<br />

considered non-fi nancial remedies,<br />

principally the injunction.<br />

11.05 | 01252<br />

■ This part concentrates on fi nancial<br />

remedies and specifi cally on the measure<br />

of damages which might be claimed.<br />

Background<br />

Article 2 of the EU Remedies Directives<br />

sets out the remedies which must be<br />

provided by Member States for breach of<br />

the EU Procurement rules. The remedies<br />

provided for in Article 2 are specifi cally the<br />

power to take interim measures, to quash<br />

decision unlawfully taken and to award<br />

damages to persons harmed by them.<br />

The purpose here is to concentrate on<br />

the third of these, namely damages,<br />

and on the position on calculation of<br />

damages since the high profi le litigation<br />

on Portcullis House.<br />

The case of <strong>Harmon</strong> CFEM Facades UK<br />

Ltd v. The Corporate Offi ce of the House<br />

of Commons [2000] 67 Con LR 1, offered<br />

a classic example of how the remedy of<br />

damages can be claimed by a disappointed<br />

tenderer for breach of the rules and also<br />

of the interaction between European<br />

procurement law and English common<br />

law. The Parliamentary Works Directorate<br />

(PWD), the client, awarded a curtain walling/<br />

fenestration contract to a British fi rm,<br />

Seele Alvis, in connection with Portcullis<br />

House, the new addition to Parliamentary<br />

accommodation at Westminster. <strong>Harmon</strong>,<br />

Ellis Baker<br />

Partner<br />

Anthony Lavers<br />

Professional Support<br />

Lawyer<br />

1


<strong>Damages</strong>: <strong>Lessons</strong> <strong>from</strong> <strong>Harmon</strong><br />

also British but subsidiary of a French company, had<br />

submitted the lowest tender and believed that it<br />

would be successful, <strong>Harmon</strong> requested the reason<br />

for its failure, as it was entitled to do under the Public<br />

Works Contract Regulations. The PWD informed<br />

<strong>Harmon</strong> that the main criterion was overall value for<br />

money. It transpired in the course of evidence that the<br />

PWD had been operating a covert so called ‘buy British’<br />

policy, whereas <strong>Harmon</strong> had been intending to use<br />

principally French manufactured products. PWD had<br />

not explained to <strong>Harmon</strong> that they intended to award<br />

the contract on any other basis than the lowest tender.<br />

They failed either to specify the alternative criterion of<br />

‘most economically advantageous tender’ or to explain<br />

its meaning. In fact, they committed a host of breaches<br />

both of the European Procurement Regulations<br />

and of the Commission’s 1994 Guidance specifi cally<br />

on avoidance of ‘negotiations with candidates or<br />

tenderers on fundamental aspects of contracts,<br />

variations in which are likely to distort competition,<br />

and in particular on prices’. This kind of preferential<br />

contact between client and tenderer is known<br />

as ‘fl irting’ and PWD’s fl irting enabled the ultimately<br />

successful tenderers to re-price and tender to a<br />

different specifi cation <strong>from</strong> <strong>Harmon</strong>.<br />

HHJ Humphrey LLoyd QC in the Technology and<br />

Construction Court, held PWD to be both in breach<br />

of the Public Works Regulations and the Commission<br />

Guidance and the law of contract and tort. The<br />

PWD was held to have committed the tort of<br />

misfeasance in public offi ce, in awarding a contract<br />

in the knowledge that there had been a breach of<br />

the requisite procedure.<br />

The Judge made clear that he considered that the<br />

remedies arose not just under statute but in contract.<br />

The Canadian case of Emery Construction ltd v.<br />

St. John’s Roman Catholic School Board [1996] 28<br />

CLR (2d) 1, was cited as authority for the proposition<br />

that ‘a contract may exist at common law against a<br />

statutory background which might otherwise provide<br />

the exclusive remedy … it is now clear in English law<br />

that in the public sector where competitive tenders<br />

are sought and responded to, a contract comes<br />

into existence whereby the prospective employer<br />

impliedly agrees to consider all tenderers fairly.’<br />

(emphasis supplied).<br />

The <strong>Harmon</strong> case offers an instructive insight as to<br />

how the question of damages will be treated.<br />

<strong>Harmon</strong> sought damages for:<br />

(i) tender costs;<br />

(ii) lost profi t; and<br />

(iii) to refl ect PWD’s conduct (aggravated and<br />

exemplary damages).<br />

Tender Costs<br />

Here there was a causation issue. In dealing with it,<br />

the judge revealed the extent to which the English<br />

law of contract would play a determinative role: ‘As<br />

a matter of general approach I consider that where<br />

compensation is sought by a tenderer for being<br />

deprived of opportunity to be awarded the contract,<br />

the approach should be to award damages on a<br />

‘contractual’ basis, rather than on a ‘tortious’ basis,<br />

although the remedy is a statutory remedy.’<br />

Causation would be approached thus (in relation to<br />

the failure to specify the award criteria): ‘if the criteria<br />

had been specifi ed, <strong>Harmon</strong> would have known of<br />

the basis and either would not have tendered or, if<br />

it did tender, would have been entitled to expect<br />

that its tender would have been considered on the<br />

prescribed basis. In the former case, it would need to<br />

establish that its tender either would have succeeded<br />

or would have stood a good chance of succeeding.’<br />

<strong>Harmon</strong>’s claim for tender costs was based upon<br />

principles contained in the Remedies Directive:<br />

‘where a claim is made for damages representing<br />

the costs of preparing a bid or of participating in an<br />

award procedure, in order to obtain reimbursement<br />

of his costs, to prove that the contract would<br />

have been awarded to him in the absence of<br />

such infringement.<br />

Article 2(7) of the Utilities Remedies Directive<br />

includes the following:<br />

‘where a claim is made for damages representing the<br />

costs of preparing a bid or of participating in an award<br />

procedure, the person making the claim shall be<br />

required only to prove an infringement of community<br />

law in the fi eld of procurement or national rules<br />

implementing that law and that he would have had<br />

a real chance of winning the contract and that, as a<br />

2


<strong>Damages</strong>: <strong>Lessons</strong> <strong>from</strong> <strong>Harmon</strong><br />

consequence of that infringement, that chance was<br />

adversely affected’.<br />

This is widely regarded as applying to all cases<br />

under EU procurement regime and not only to those<br />

covered by the Utilities Directive.<br />

HH Judge LLoyd’s summary of the position was<br />

that ‘<strong>Harmon</strong> is entitled to recover its tender costs,<br />

taken by themselves, on the grounds that it ought<br />

to have been awarded the contract and would then<br />

have recovered. However, if this was incorrect and<br />

PWD would have gone to a re-tendering process,<br />

damages should be calculated by the ‘loss of a chance’<br />

principle, under which <strong>Harmon</strong>’s chances of being<br />

awarded the contract was assessed at 70 per cent.<br />

Lost Profi ts<br />

The <strong>Harmon</strong> case is also important because neither<br />

the Remedies Directives nor the UK regulations give<br />

detailed guidance on how the claim for damages<br />

for lost profi t should be calculated. <strong>Harmon</strong> had<br />

succeeded in establishing as a fact that the margin<br />

for risk and profi t (which are usually diffi cult to<br />

disaggregate) in its tender was between £4.5 million<br />

and £5 million. A further factor favouring <strong>Harmon</strong><br />

which should be taken into account in calculating<br />

damages was that <strong>Harmon</strong> (UK) was operating as<br />

part of a company group structure: ‘As a matter<br />

of principle, I see no reason why <strong>Harmon</strong> cannot<br />

recover the intra group margin as part of its gross<br />

margin, since in my view it is again necessary to<br />

be realistic and commercial about activities incurred<br />

within a group and those incurred as a result of<br />

subcontracts placed outside a group … it was not<br />

to be expected that the selected tenderer would not<br />

have called upon other companies within the Group<br />

to provide services and, indeed, capital for which<br />

and upon which those other companies would be<br />

entitled to show a return or profi t’.<br />

<strong>Harmon</strong> was unsuccessful in arguing that its<br />

liquidation should not be taken into account in<br />

calculating damages for lost profi t: “if … it is<br />

established that the fi nancial position of <strong>Harmon</strong> …<br />

would have been such that it is probable that the<br />

liquidator would have been unable to continue the<br />

contract or to resist forfeiture, then clearly the amount<br />

of profi t which would actually have been recovered<br />

by <strong>Harmon</strong> had it been awarded the contract and<br />

carried it out would necessarily be affected by it.’<br />

Aggravated or Exemplary <strong>Damages</strong><br />

<strong>Harmon</strong> was not successful in recovering aggravated<br />

or exemplary damages, which would only have been<br />

ordered on the basis of the awarding body’s behaviour<br />

and its impact: ‘it is a bad case but not exceptional.<br />

The defendant’s conduct is not unconstitutional nor<br />

do I consider that it is oppressive which is no more<br />

than the effect of directed governmental power on an<br />

individual. <strong>Harmon</strong> was not oppressed in that ordinary<br />

sense of the word. To describe that has happened<br />

as oppressive, or as the excessive or insolent use<br />

of power … would mean that virtually every case of<br />

misfeasance would attract exemplary damages.’<br />

<strong>Harmon</strong> (No 2)<br />

Before leaving the lessons of the <strong>Harmon</strong> litigation<br />

it is worth referring to <strong>Harmon</strong> CFEM Facades<br />

(UK) Ltd v. Corporate Offi cer of the House of<br />

Commons (No 2) [2000] Con LR 21, where HHJ LLoyd<br />

had to consider the calculation of an interim payment<br />

of damages for tender costs and loss of profi t pending<br />

the investigation of causation and quantum issues.<br />

HH Judge LLoyd was not impressed by the<br />

House of Commons’ argument that the face of<br />

<strong>Harmon</strong>’s liquidation might make any money paid<br />

to it irrecoverable: the client’s position is normally<br />

adequately protected by CPR Rule 25.7(4) ‘the court<br />

must not order an interim payment of more than a<br />

reasonable proportion of the likely amount of the<br />

fi nal judgment.’<br />

He concluded that it was probable that <strong>Harmon</strong><br />

would not have gone into liquidation if it had been<br />

awarded the contract. It would thus have made a<br />

profi t of about £3.7 million and should receive an<br />

interim award of one third of that. It should also be<br />

compensated for the chance of getting a subsequent<br />

related contract and profi t on it and for being<br />

‘black balled’ by a main contractor to whom it was<br />

subcontractor on other projects, harming its cash fl ow.<br />

<strong>Harmon</strong> would also have benefi ted in the latter<br />

stages of the project <strong>from</strong> the appreciation of the<br />

£sterling against the French franc.<br />

3


<strong>Damages</strong>: <strong>Lessons</strong> <strong>from</strong> <strong>Harmon</strong><br />

On tender costs, <strong>Harmon</strong> should receive an interim<br />

payment of 95 per cent of the lowest estimate<br />

of those accepted by the House of Commons’<br />

own expert.<br />

Conclusion<br />

The remedy of damages, at least to judge <strong>from</strong> the<br />

<strong>Harmon</strong> experience, is broadly accommodating<br />

to an unsuccessful tenderer who can make out<br />

a breach of the rules and satisfy probability<br />

requirements of causation. Indeed, awarding<br />

authorities have good reason to be concerned<br />

about the extent of their risk exposure when such<br />

matters as intra group profi t, subsequent contracts,<br />

relationships with contractors on other projects<br />

and currency fl uctuations are factored into the<br />

calculation of quantum.<br />

While aggrieved tenderers might typically be expected<br />

to prefer to prevent an award in breach and reprise the<br />

tendering exercise, if this has been lost because of the<br />

stage reached, damages may constitute not so much<br />

a token consolation as a generous runners-up prize.<br />

Ellis Baker, Partner and Head of Construction &<br />

Engineering Practice Group and Anthony Lavers,<br />

Barrister and Professional Support Lawyer,<br />

<strong>White</strong> & <strong>Case</strong>, London<br />

The information in this article is for educational<br />

purposes only; it should not be construed as<br />

legal advice.<br />

Copyright © 2005 <strong>White</strong> & <strong>Case</strong><br />

4

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!