Cmt.#<br />

DRAFT COMPLETION REPORT FOR THE REMEDIATION OF SOILS and DRY SEDIMENTS AT LOAD LINES 1-4 (RVAAP 08-11) AT THE<br />

RAVENNA ARMY AMMUNITION PLANT, RAVENNA, OHIO<br />

COMMENT RESPONSE TABLE<br />

JUNE 19, 2008<br />

Page #<br />

Line #<br />

Comment<br />

Ohio EPA (Eileen Mohr)<br />

A-1 Cover and Title Page Change Title, add in “and Dry Sediments”<br />

be<strong>for</strong>e Remediation of Soils<br />

Recommendation<br />

Response<br />

The title will be changed to:<br />

“<strong>Remedial</strong> <strong>Action</strong> <strong>Completion</strong> <strong>Report</strong><br />

<strong>for</strong> <strong>the</strong> Remediation of Soils and Dry<br />

Sediments at RVAAP08-11 (Load<br />

Lines 1-4).<br />

A-2 CD Change title to match Cover and Title page The title will be changed to match<br />

<strong>the</strong> Cover and Title page.<br />

A-3<br />

A-4<br />

Disclaimer Statement<br />

page<br />

Contractor Statement<br />

of Independent<br />

Technical Review<br />

Remove Disclaimer Statement page <strong>for</strong><br />

<strong>the</strong> <strong>Final</strong> version.<br />

Need to make consistent with Cover and<br />

Title Page<br />

The disclaimer statement as been<br />

removed from <strong>the</strong> <strong>Final</strong> document.<br />

The title will be changed to match<br />

<strong>the</strong> Cover and Title page. See<br />

Comment A-2.<br />

A-5 List of Appendices Correct spelling of Construction The text has been revised to say<br />

Line 2<br />

“Construction”.<br />

A-6 Page 1-4, Line 18 Add “s” to foundation The text has been revised to say<br />

“foundations”.<br />

A-7 Page 2-2, Line 4 Add “<strong>Final</strong>” be<strong>for</strong>e Interim ROD The text has been revised to say<br />

“<strong>Final</strong> Interim ROD”.<br />

A-8 Page 2-3, Line 1 Add “<strong>Final</strong>” be<strong>for</strong>e Interim ROD The text has been revised to say<br />

“<strong>Final</strong> Interim ROD”.<br />

A-9 Page 2-3, Line 6 Add “<strong>Final</strong>” be<strong>for</strong>e Interim ROD The text has been revised to say<br />

“<strong>Final</strong> Interim ROD”.<br />

A-10 Page 3-1, Line 6 Change “plans” to “planned” The text has been revised to say<br />

“planned”.<br />

A-11 Page 3-2, Line 17 Change “excavations” to “excavation” The text has been revised to say<br />

A-12 Page 3-3, Lines 7-9 Add a statement that field data showed <strong>the</strong><br />

required stability prior to sampling<br />

(removed enough well volume to ensure a<br />

viable sample was collected,<br />

measurements had stabilized, etc.) and<br />

“excavation”.<br />

The text has been revised to say<br />

“Although unable to include in this<br />

report, <strong>the</strong> field measurement data<br />

was collected in accordance with<br />

Section 3.2.2 and indicated that <strong>the</strong><br />

Shaw Environmental, Inc. 1 of 13 June 19, 2008