Ballast - RailCorp Engineering Internet

Ballast - RailCorp Engineering Internet Ballast - RailCorp Engineering Internet

engineering.railcorp.nsw.gov.au
from engineering.railcorp.nsw.gov.au More from this publisher
29.03.2013 Views

Engineering Manual Track Owner: Chief Engineer Track Approved by: Andrew Wilson Technical Specialist Wheel/Rail TMC 241 BALLAST Authorised by: Version 2.4 Issued June 2012 Malcolm Kerr Chief Engineer Track Disclaimer This document was prepared for use on the RailCorp Network only. RailCorp makes no warranties, express or implied, that compliance with the contents of this document shall be sufficient to ensure safe systems or work or operation. It is the document user’s sole responsibility to ensure that the copy of the document it is viewing is the current version of the document as in use by RailCorp. RailCorp accepts no liability whatsoever in relation to the use of this document by any party, and RailCorp excludes any liability which arises in any manner by the use of this document. Copyright The information in this document is protected by Copyright and no part of this document may be reproduced, altered, stored or transmitted by any person without the prior consent of RailCorp. UNCONTROLLED WHEN PRINTED Page 1 of 33 Engineering Manual

<strong>Engineering</strong> Manual<br />

Track<br />

Owner: Chief Engineer Track<br />

Approved<br />

by:<br />

Andrew Wilson<br />

Technical Specialist<br />

Wheel/Rail<br />

TMC 241<br />

BALLAST<br />

Authorised<br />

by:<br />

Version 2.4<br />

Issued June 2012<br />

Malcolm Kerr<br />

Chief Engineer Track<br />

Disclaimer<br />

This document was prepared for use on the <strong>RailCorp</strong> Network only.<br />

<strong>RailCorp</strong> makes no warranties, express or implied, that compliance with the contents of this document shall be<br />

sufficient to ensure safe systems or work or operation. It is the document user’s sole responsibility to ensure that the<br />

copy of the document it is viewing is the current version of the document as in use by <strong>RailCorp</strong>.<br />

<strong>RailCorp</strong> accepts no liability whatsoever in relation to the use of this document by any party, and <strong>RailCorp</strong> excludes<br />

any liability which arises in any manner by the use of this document.<br />

Copyright<br />

The information in this document is protected by Copyright and no part of this document may be reproduced, altered,<br />

stored or transmitted by any person without the prior consent of <strong>RailCorp</strong>.<br />

UNCONTROLLED WHEN PRINTED Page 1 of 33<br />

<strong>Engineering</strong> Manual


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

Document control<br />

Version Date Summary of change<br />

1.0 October 2006 First issue as a <strong>RailCorp</strong> document. Includes content from<br />

C 2514, RTS.3648, RTS.3652, CTN 01/01, CTN 03/10<br />

2.0 April 2007 Additional reference; Addition of <strong>Ballast</strong> Quantities tables;<br />

Addition of restrictions on ballast stabiliser operation near<br />

bridges<br />

2.1 December 2009 Format changes<br />

2.2 July 2010 New Section C4-4 <strong>Ballast</strong> Sampling<br />

2.3 August 2011 C3 - Competencies updated for current National<br />

Competencies<br />

2.4 June 2012 Changes detailed in Chapter Revisions<br />

Summary of changes from previous version<br />

Summary of change Chapter<br />

Control changes Control<br />

Pages<br />

Reformatted to new template – Page numbering converted to continuous<br />

numbering. Separate document control on individual chapters removed<br />

New chapter “<strong>Ballast</strong> stockpiling” – includes content from CTN 12/04 5<br />

New chapter “<strong>Ballast</strong> sampling” moved from C4-4; inclusion of guidance on<br />

inspection on delivery; inclusion of examples of good and poor ballast – includes<br />

content from CTN 12/04<br />

Chapters renumbered<br />

© Rail Corporation Page 2 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4<br />

All<br />

6<br />

7, 8, 9, 10,<br />

11, 12<br />

Updated content to reflect change to ESC 240 7<br />

C9-3 New section “Restrictions near signalling equipment” – establishes restrictions<br />

on operation of DTS near points<br />

9


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

Contents<br />

Chapter 1 Introduction......................................................................................................................4<br />

C1-1 Purpose .............................................................................................................................4<br />

C1-2 Context ..............................................................................................................................4<br />

C1-3 How to read the Manual ....................................................................................................4<br />

C1-4 References ........................................................................................................................5<br />

Chapter 2 Management Requirements ...........................................................................................6<br />

Chapter 3 Competencies..................................................................................................................7<br />

Chapter 4 Laying <strong>Ballast</strong> ..................................................................................................................8<br />

C4-1 Planning.............................................................................................................................8<br />

C4-2 Establish unloading rates ..................................................................................................9<br />

C4-3 Unloading procedure .........................................................................................................9<br />

Chapter 5 <strong>Ballast</strong> stockpiling.........................................................................................................13<br />

Chapter 6 <strong>Ballast</strong> sampling............................................................................................................14<br />

C6-1 At the quarry....................................................................................................................14<br />

C6-2 Site delivery.....................................................................................................................14<br />

C6-3 From stockpiles ...............................................................................................................14<br />

C6-4 In-track sampling .............................................................................................................14<br />

Chapter 7 Restoring ballast profile ...............................................................................................19<br />

Chapter 8 <strong>Ballast</strong> regulating ..........................................................................................................21<br />

C8-1 Machine application / operation.......................................................................................21<br />

C8-2 Machine capabilities ........................................................................................................21<br />

C8-3 Setting the plough blades................................................................................................21<br />

C8-4 Transferring ballast..........................................................................................................22<br />

C8-5 Profiling shoulders...........................................................................................................22<br />

C8-6 Brooming .........................................................................................................................22<br />

C8-7 The finished product........................................................................................................23<br />

Chapter 9 <strong>Ballast</strong> Stabilising..........................................................................................................24<br />

C9-1 Conditions required for effective stabilising of track........................................................24<br />

C9-2 Restrictions on or near structures ...................................................................................24<br />

C9-3 Restrictions near signalling equipment ...........................................................................24<br />

Chapter 10 <strong>Ballast</strong> cleaning .............................................................................................................26<br />

C10-1 Planning...........................................................................................................................26<br />

C10-2 <strong>Ballast</strong> Cleaning procedure .............................................................................................26<br />

Chapter 11 Track reconditioning using off track plant .................................................................28<br />

C11-1 Planning...........................................................................................................................28<br />

C11-2 Reconditioning procedure ...............................................................................................28<br />

Chapter 12 Loading Spent <strong>Ballast</strong> Wagons....................................................................................33<br />

C12-1 Material weights...............................................................................................................33<br />

C12-2 Checking for overloading.................................................................................................33<br />

© Rail Corporation Page 3 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

Chapter 1 Introduction<br />

C1-1 Purpose<br />

C1-2 Context<br />

This manual provides requirements, processes and guidelines for the installation and<br />

maintenance of ballast.<br />

The manual is part of <strong>RailCorp</strong>'s engineering standards and procedures publications.<br />

More specifically, it is part of the Civil <strong>Engineering</strong> suite that comprises standards,<br />

installation and maintenance manuals and specifications.<br />

Manuals contain requirements, processes and guidelines for the management of track<br />

assets and for carrying out examination, construction, installation and maintenance<br />

activities.<br />

The manual is written for the persons undertaking installation and maintenance activities.<br />

It also contains management requirements for Civil Maintenance Engineers and Team<br />

Managers needing to know what they are required to do to manage ballast installation<br />

and repair activities on their area, and production managers needing to know what they<br />

are required to do to manage the renewal activity their teams are undertaking.<br />

C1-3 How to read the Manual<br />

The best way to find information in the manual is to look at the Table of Contents starting<br />

on page 3. Ask yourself what job you are doing? The Table of Contents is written to<br />

reflect work activities.<br />

When you read the information, you will not need to refer to <strong>RailCorp</strong> <strong>Engineering</strong><br />

standards. Any requirements from standards have been included in the sections of the<br />

manual and shown like this:<br />

The construction and maintenance acceptance limits detailed below are extracted from<br />

<strong>RailCorp</strong> Standard ESC 240- <strong>Ballast</strong>.<br />

Operating Class<br />

Main line<br />

<strong>Ballast</strong> shoulder width (mm)<br />

Design Acceptance<br />

Minimum Maximum Minimum Maximum<br />

CWR and LWR 400 700 390 700<br />

Reference is however made to other Manuals.<br />

© Rail Corporation Page 4 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

C1-4 References<br />

C1-4.1 Australian and International Standards<br />

AS 1141 – Methods for sampling and testing aggregates - Method 3.1: Sampling—<br />

Aggregates<br />

C1-4.2 <strong>RailCorp</strong> Documents<br />

ESC 200 – Track System<br />

ESC 240 – <strong>Ballast</strong><br />

TMC 001 – Civil Technical Competencies and <strong>Engineering</strong> Authority<br />

TMC 203 – Track Inspection Manual<br />

TMC 211 – Track Geometry & Stability Manual<br />

TMC 222 – Rail Welding Manual<br />

TMC 223 – Rail Adjustment Manual<br />

TMC 300 – Structures General<br />

TMC 403 – Track Reconditioning Manual<br />

© Rail Corporation Page 5 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

Chapter 2 Management Requirements<br />

To be determined<br />

© Rail Corporation Page 6 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

Chapter 3 Competencies<br />

NOTE: These competencies may enable activities to be carried out in other manuals.<br />

For a comprehensive list of all activities that are covered by a given competency see<br />

<strong>Engineering</strong> Manual TMC 001 - Civil Technical Competencies and <strong>Engineering</strong> Authority.<br />

To carry out this work You need these competencies<br />

Restore ballast profile<br />

either manually or with<br />

ballast regulators and<br />

stabilisers<br />

Undertake track<br />

reconditioning that<br />

involves reconstruction of<br />

track formation and<br />

capping<br />

Certify track during or<br />

after reconstruction of<br />

track formation and<br />

capping<br />

Lay ballast from ballast<br />

trains or using off-track<br />

plant<br />

Remove ballast from<br />

sleeper bays or shoulders<br />

by manual methods,<br />

mechanical excavation<br />

with off track plant, ballast<br />

sleds, ballast undercutters<br />

or ballast cleaners<br />

Load spent ballast<br />

wagons<br />

Certify track during or<br />

after ballasting<br />

TLIS2030A - Carry out track ballasting<br />

TLIS3037A - Install and repair rail earthworks<br />

TLIS3037A - Install and<br />

repair rail earthworks<br />

TLIS3025A - Implement ballast unloading<br />

TLIS2030A - Carry out track ballasting<br />

TLIS3037A - Install and<br />

repair rail earthworks<br />

TLIS2030A - Carry out track<br />

ballasting<br />

AND TLIB3094A - Check and<br />

repair track geometry<br />

OR TLIS2030A - Carry out track<br />

ballasting<br />

AND TLIB3094A - Check and<br />

repair track geometry<br />

© Rail Corporation Page 7 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

Chapter 4 Laying <strong>Ballast</strong><br />

C4-1 Planning<br />

This chapter describes the methods used in <strong>RailCorp</strong> to lay ballast using ballast trains<br />

and plough vans.<br />

1. Assess the work. Identify potential hazards by inspection of the section to be<br />

ballasted. The hazards may include:<br />

o Interlockings.<br />

o Electrical Wires.<br />

o Trainstops.<br />

o Rail lubricators.<br />

o Sleeper condition.<br />

Warning!!<br />

Before you lay ballast over sleepers and fastenings you MUST consider the<br />

condition of the sleepers and make arrangements for the removal of the<br />

ballast.<br />

o Turnouts, bridges and culverts.<br />

o Embankments.<br />

o Additional hazards associated with Night Work.<br />

o Weather conditions.<br />

2. Order the ballast train.<br />

o Use only NDFF (air operated) wagons in multiple track areas.<br />

o Order wet ballast or wet on site.<br />

o Order, specifically, 81 Class Even numbered Locomotives with Speed<br />

Master Control.<br />

3. Check, mark and protect the location of signal and electrical connections,<br />

rodding etc.<br />

© Rail Corporation Page 8 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

C4-2 Establish unloading rates<br />

Establish the ballast unloading locations clear of turnouts, bridges, obstructions and<br />

equipment. Use Table 1 and Table 2 for guidance on unloading rates.<br />

16t/20m Nil each Side<br />

12t/20m Half Shoulder one<br />

side - Nil other side<br />

8t/20m Half shoulder both<br />

sides<br />

4t/20m Full Shoulder one<br />

side - Half other side<br />

- Full Shoulder both<br />

sides<br />

SHOULDER - CONCRETE AND TIMBER SLEEPERS<br />

Table 1 - Assessment of Shoulder ballast profile Timber and Concrete sleepers<br />

10t/20m Nil in Crib<br />

5t/20m Half Full Crib<br />

- Full Crib<br />

18t/20m Nil in Crib<br />

9t/20m Half Full Crib<br />

- Full Crib<br />

13t/20m Nil in Crib<br />

7t/20m Half Full Crib<br />

- Full Crib<br />

CRIB - TIMBER SLEEPERS<br />

CRIBS - HEAVY DUTY CONCRETE SLEEPERS<br />

CRIBS - MEDIUM DUTY CONCRETE SLEEPERS<br />

Table 2 - Assessment of Crib <strong>Ballast</strong> Profile Timber and Concrete sleepers<br />

C4-3 Unloading procedure<br />

© Rail Corporation Page 9 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

C4-3.1 Operating <strong>Ballast</strong> Wagons by DAY<br />

• Do not get on / off wagons unless the train is completely stopped and the worksite<br />

is protected from other traffic.<br />

• Do not ride on non-pneumatic wagons.<br />

• Do not hang from outside of any wagon.<br />

• Do not put yourself between or underneath any wagon at any time.<br />

• Unlock pneumatic wagons with the key prior to the consist moving off.<br />

• Unlock the plough blade and check movement in all positions.<br />

C4-3.2 Operating <strong>Ballast</strong> Wagons by NIGHT<br />

C4-3.3 Laying ballast<br />

• Mount a 5 KVA generator (tested, tagged, with RCD fitted) and four (4) work lights<br />

(tested and tagged) securely to the plough wagon.<br />

• Position lights to light up the work area around the plough wagon.<br />

• Each person must have:<br />

– A hand held torch with securing strap, or a<br />

– A construction safety helmet fitted with a secured head lamp and battery pack.<br />

• Illuminate work areas by mobile flood light units where possible. (inspected, tested,<br />

tagged and RCD fitted)<br />

1. Discharge ballast at the required rate.<br />

Make sure that the number of doors open simultaneously does not result in<br />

excessive ballast.<br />

2. DO NOT drop ballast around points e.g. between running rails and check rails,<br />

bridge guards, switch blades and stock rails.<br />

Excessive ballast may cause derailments.<br />

3. Be careful not to discharge excessive ballast in restricted locations (cuttings,<br />

platforms, tunnels etc.). The plough or ballast regulators may not be able to<br />

remove enough ballast, resulting in trains tripping.<br />

4. DO NOT ballast over transom top bridges etc.<br />

Excessive ballast will result in ballast being ploughed into waterways or onto<br />

roads.<br />

5. DO NOT ballast around train-stops, signals and track connections.<br />

6. BE CAREFUL when unloading to keep the ballast load even in each wagon<br />

(see Figure 1).<br />

© Rail Corporation Page 10 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

<br />

Figure 1 - Uneven loading of ballast wagons<br />

If ALL doors in a wagon are ¾ to fully open it can cause derailment due to<br />

ballast flooding.<br />

<strong>Ballast</strong> wagons can operate in a worksite up to 25km/h with a load imbalance<br />

resulting from discharge of 25% of ballast through one of the side discharge<br />

doors (see Figure 2).<br />

Figure 2 - 25% discharge through one side door<br />

DO NOT discharge any more ballast without an appropriate offset discharge<br />

from the centre or opposite side doors.<br />

In situations where hopper doors have failed with more than 25% of ballast<br />

unloaded from one side door ONLY, the wagons may leave the worksite at a<br />

maximum speed of 25kph to travel to a siding for detachment.<br />

7. Operate the ballast plough.<br />

<br />

<br />

Ensure the plough van is up when passing trainstops.<br />

C4-3.4 Release the ballast train<br />

1. Carry out the following checks before you release the ballast train:<br />

o Make sure that all the doors are securely closed and locked with the ballast<br />

key and any loose ballast is removed from the ballast wagons.<br />

o Make sure that ALL ballast is emptied from wagons. If ballast cannot be<br />

completely unloaded from any wagon refer to the procedure for unloading<br />

unbalanced Wagons in (C4-3.3) above.<br />

o Make sure that the plough blade is secured in the travel position and locked.<br />

© Rail Corporation Page 11 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

C4-3.5 Checking the site<br />

1. Clear any ballast from signal, electrical connections, rodding etc.<br />

2. Inspect culverts and cess drains for blockages by excess ballast.<br />

Remove excess ballast manually or with mechanical equipment.<br />

3. Examine connections visually for signs of break or damage.<br />

Contact signalling or electrical personnel if damage is visible or suspected.<br />

4. Certify track.<br />

Certify the track using the procedure in <strong>RailCorp</strong> <strong>Engineering</strong> Manual TMC 211<br />

– Track Geometry & Stability.<br />

o Are there any obstructions to train operations? Are clearances for trip arms<br />

and wheels satisfactory?<br />

o Are there any obstructions to operation of signalling equipment?<br />

o Are there any obstructions to operation of points?<br />

o Are flangeways in turnouts and level crossings clear?<br />

If work is unsatisfactory, apply appropriate speed restrictions in accordance with<br />

the operating limits in <strong>RailCorp</strong> <strong>Engineering</strong> Manual TMC 203 - Track<br />

Inspection.<br />

© Rail Corporation Page 12 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

Chapter 5 <strong>Ballast</strong> stockpiling<br />

When ballast and other material is being delivered to site for later use in track, it is<br />

important that ballast is managed to minimise the opportunity for segregation or<br />

contamination.<br />

<strong>Ballast</strong> should be stockpiled on a clean level area well clear of other materials such as<br />

road base or spoil. The movement of loading machinery needs to be considered in<br />

determining the separation required.<br />

To avoid segregation ballast should be laid out in horizontal layers. Unloading ballast<br />

onto the top of a cone shaped stockpile is the most likely to result in segregation.<br />

<strong>Ballast</strong> should not be reclaimed from the bottom of a stockpile where there is a danger of<br />

contamination from the underlying earth. Any unused ballast to be reclaimed should be<br />

inspected to ensure it is not contaminated.<br />

© Rail Corporation Page 13 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

Chapter 6 <strong>Ballast</strong> sampling<br />

This chapter specifies the methods for sampling of delivered ballast to assess<br />

contamination. Samples should be tested for acceptance in accordance with ESC 240.<br />

Some examples of poor quality ballast are shown in Figure 3 to Figure 8. Examples of<br />

good quality ballast are shown in Figure 9 to Figure 12.<br />

<strong>Ballast</strong> sampling may be required in the following circumstances:<br />

• There are reports that ballast as supplied does not meet specification (e.g too<br />

many fines).<br />

• The work specification requires testing of ballast prior to delivery, on site or after<br />

installation.<br />

• The source of the ballast and/or the method of delivery is new or there is reason to<br />

be concerned that the ballast will meet acceptance standards.<br />

Use the following techniques to take ballast samples.<br />

C6-1 At the quarry<br />

Take samples using the methods detailed in AS 1141 Method 3.1.<br />

C6-2 Site delivery<br />

If the ballast is coming from a truck the material should be visually inspected as it is<br />

unloaded. Delivery should be suspended if a truck load appears to have excessive fines<br />

material.<br />

C6-3 From stockpiles<br />

Remove the top 75mm layer of stones as these have been typically washed clean.<br />

Take random samples in the top, middle and bottom of the stockpile.<br />

Where visible segregation occurs:<br />

C6-4 In-track sampling<br />

• Establish the extent of the segregation.<br />

• Take a sample of the segregated material. If there are different levels of<br />

contamination sample each of these<br />

• Record the % of the stockpile affected by segregation (by surface area).<br />

In-track sampling is not required if:<br />

• ballast has been checked at stockpile and there is no visible evidence of<br />

contamination on the finished track, and<br />

• ballast has been actively monitored during installation and no contamination is<br />

evident<br />

Sampling of ballast laid on track should be taken during ballasting or immediately<br />

afterwards.<br />

© Rail Corporation Page 14 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

Examine ballast condition. If there is visible contamination;<br />

• Establish the extent of the contamination<br />

• Take a sample of the segregated material. If there are different levels of<br />

contamination sample each of these<br />

For sampling of existing track<br />

• Scrape off the top layer of ballast to see if there is contamination.<br />

• Check a number of locations by visual examination. It should be easy to check a<br />

large number of sites.<br />

• Where a small number of contaminated sites are found establish their extent<br />

(mainly track length)<br />

• Take samples from the contaminated sites and representative samples from some<br />

of the uncontaminated sites<br />

Figure 3 - Poor quality ballast with excessive small material.<br />

Figure 4 - Poor ballast is visible once surface stones have been removed.<br />

© Rail Corporation Page 15 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

Figure 5 - Excessive small material in the ballast. Note the layer of larger stones on the<br />

top. Quite often a thin layer of larger stones will overlay poor quality ballast.<br />

Figure 6 - Excessive small material along the shoulder highlighted in red. The fine<br />

material is visible along the shoulder once the larger stones on the surface have<br />

been removed.<br />

Figure 7 - Poor ballast quality in stockpile. The fines can be seen once the surface<br />

stones are removed.<br />

© Rail Corporation Page 16 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

Figure 8 - This is poor ballast that has been reused from a previous closedown. It still<br />

has vegetation and sleeper debris in it. Quality checks should be made of any<br />

ballast recovered for reuse.<br />

Figure 9 - This ballast is OK.<br />

© Rail Corporation Page 17 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

Figure 10 - This ballast is OK.<br />

Figure 11 - This ballast is OK.<br />

Figure 12 - <strong>Ballast</strong> in stockpile once the surface stones have been removed. This ballast<br />

is OK. Note there is always a thin coating of fines on the ballast.<br />

© Rail Corporation Page 18 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

Chapter 7 Restoring ballast profile<br />

This chapter describes the methods used in <strong>RailCorp</strong> to obtain standard ballast profile by<br />

manual methods or off-track plant.<br />

1. Manual boxing up may be needed after minor fettling or resleepering works.<br />

2. Use ballast from a stockpile or from excess ballast on the track. Check that it is<br />

free of mud and excessive fine material. DON’T put poor ballast, ashes,<br />

screenings and quarry dust back in track. If possible, use ballast forks to “sift”<br />

out the fine material.<br />

3. Restore ballast profile to the following standard.<br />

The construction and maintenance acceptance limits detailed below are extracted from<br />

<strong>RailCorp</strong> Standard ESC 240- <strong>Ballast</strong><br />

Crib and shoulder height<br />

The ballast shall be profiled to the top of the centre and end of the sleepers.<br />

Shoulder Slope<br />

For freestanding ballast, the slope of the ballast shoulder is assumed to be 1:1.5<br />

(height:width).<br />

<strong>Ballast</strong> shoulder width<br />

<strong>Ballast</strong> Shoulder width is measured from the extreme end of the sleeper, not the<br />

visible end when the track is fully ballasted.<br />

The ballast shoulder should extend horizontally from the sleeper end. It is,<br />

however, acceptable for the ballast shoulder to be profiled in the plane of the<br />

sleeper for a normal ballast shoulder width (nominally 400mm) to suit ballast<br />

regulators. Any extended shoulders, such as on bridges, should be horizontal.<br />

Operating Class<br />

Main line<br />

<strong>Ballast</strong> shoulder width (mm)<br />

Design Acceptance<br />

Minimum Maximum Minimum Maximum<br />

CWR and LWR 400 700 390 700<br />

Siding<br />

CWR and LWR 400 700 390 700<br />

Loose Rail 300 700 290 700<br />

Table 3 - <strong>Ballast</strong> shoulder width design and acceptance limits<br />

Design ballast shoulder width is one factor that contributes to overall track lateral<br />

stability. Additional ballast shoulder width above the minimum and a ballast<br />

windrow up to rail height outside the sleeper may be necessary in areas of poor<br />

track lateral stability to provide adequate resistance to track buckling on sharp<br />

curves where design radius is outside normal limits.<br />

© Rail Corporation Page 19 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

Rail Level<br />

Gauge<br />

Face<br />

Figure 13 - Location of ballast windrow<br />

4. Check that top of sleeper and all fastenings are visible.<br />

5. If insufficient ballast is available to meet the above requirements:<br />

In summer months<br />

o box up the high side of track on curves by taking metal from the low side<br />

In cold weather<br />

o box up the low side of track on curves by taking metal from the high side<br />

6. Certify track<br />

Location of<br />

ballast windrow<br />

Certify the track using the procedure in TMC 211.<br />

o If work has not been completed because of insufficient ballast, assess<br />

whether a speed restriction is required using the operating limits in<br />

TMC 203.<br />

© Rail Corporation Page 20 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

Chapter 8 <strong>Ballast</strong> regulating<br />

This chapter describes the methods used in <strong>RailCorp</strong> to obtain standard ballast profile<br />

using ballast regulators, either as part of resurfacing operations or, when required, as a<br />

separate operation.<br />

C8-1 Machine application / operation<br />

There are various makes and models of <strong>Ballast</strong> Regulators however their functions and<br />

the principles of operation are similar.<br />

The operating controls may differ and some machines may have different attachments<br />

which could make them more complex to operate.<br />

C8-2 Machine capabilities<br />

A Regulator is not a Bulldozer, or a Backhoe. It will not push three tonnes of ballast and it<br />

cannot be used to clean out cess drains. Don't expect it to do something it was not<br />

designed to do.<br />

Always consider the job you have to do and the type, size and power of the machine.<br />

• When ploughing, if the track is flooded, lower the ploughs once the machine is<br />

moving (take a run-up) and only lower the ploughs to about half the ballast depth.<br />

• Avoid bulldozing!<br />

• DO NOT ram into ballast. This causes a sudden build up of ballast over the track<br />

and causes damage to the ploughs and hydraulics and places undue stress on the<br />

transmission. It could also derail the machine.<br />

• Avoid axle and drive shaft damage. When wheel spin develops, this places stress<br />

on the transmission components. Lift the ploughs slightly to reduce the load you<br />

are trying to push.<br />

• Do as many passes as necessary to complete the job.<br />

• Obstacles:- Always be alert for fixed obstacles such as:<br />

– Impedance bonds (turtles)<br />

– Train stops<br />

– Culverts<br />

– Signal wiring<br />

– Signal potheads<br />

– Guard rails<br />

– Interlocking gear<br />

All loose hazards should be removed from the track. e.g. sleeper plates, fish plates.<br />

These can all cause damage to the machine and may derail it.<br />

C8-3 Setting the plough blades<br />

1. When ploughing ballast out from the centre of the track, the plough<br />

configuration should be an inverted 'V' as seen from the operator cabin.<br />

2. When ploughing in to fill cribs and bring metal from outside the rails the ploughs<br />

form a 'V' to collect and push the ballast forward.<br />

© Rail Corporation Page 21 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

C8-4 Transferring ballast<br />

1. Where ballast has to be transferred from one side to the other, it should be<br />

done in stages one rail at a time if the ballast is too heavy.<br />

2. If necessary, depending on the machines power and the amount of ballast,<br />

lower the blade to half depth of the ballast to clear space for transferred metal to<br />

flow to.<br />

3. When one side has been cleared, then transfer the ballast from the other side.<br />

4. With both ploughs lowered, the full transfer can take place in the next pass.<br />

C8-5 Profiling shoulders<br />

Shoulders are an area where metal is often wasted. This may mean other areas are left<br />

short of metal or extra ballast has to be ordered if what is available is not utilized.<br />

C8-6 Brooming<br />

1. Profile shoulders to meet the acceptance limits in Section C8-7.<br />

2. ALWAYS REMEMBER THE MACHINE’S CAPABILITIES.<br />

3. Boxing wings only have a limited capacity and this governs the number of<br />

passes needed to complete the job.<br />

MAKE AS MANY PASSES AS NECESSARY.<br />

4. Avoid trying to wing up all the ballast on the first pass if there is too much.<br />

This only causes the ballast to flow over the wing and run towards the toe of the<br />

shoulder creating a windrow that eventually becomes out of reach.<br />

This problem is compounded on tracks with steep shoulders.<br />

The ballast must be able to flow somewhere.<br />

5. A MORE EFFECTIVE METHOD<br />

o On the first pass, angle the wing in so it is almost parallel and place the tip<br />

about half way down the shoulder.<br />

o This will deposit the ballast at the end of the sleepers and at the same time<br />

cut a 'gutter' through the shoulder so that metal picked up on the next pass<br />

has somewhere to flow to.<br />

o The second pass fills the gutter at the same time profiling the ballast to the<br />

correct batter angle.<br />

o The positioning of the rear of the blade determines where the ballast will be<br />

deposited.<br />

o On the next pass with the front ploughs the windrow you built up on the<br />

sleeper ends will fill any cribs with the excess going to the shoulder batter.<br />

It is important to become familiar with how your machines broom should be set up as<br />

there are different requirements for each type of machine.<br />

1. To remove ballast from around the sleeper fastenings, strip as much ballast as<br />

you can with the ploughs first to lessen the load on the broom AND save time.<br />

© Rail Corporation Page 22 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

2. Adjust the broom so the tufts just brush the tops of the sleepers.<br />

3. This will avoid brushing out the cribs.<br />

4. Once the broom is properly adjusted, you only need to regulate the travelling<br />

speed of the machine to alter the quality of the job left.<br />

5. MODERATE SPEED - Always use the machine the way the manufacturer<br />

recommends.<br />

C8-7 The finished product<br />

Particular attention should be paid to whether the machine should be in work or<br />

travel when winging up.<br />

Make sure you restore the standard ballast profile to meet the requirements detailed in<br />

Chapter 7.<br />

© Rail Corporation Page 23 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

Chapter 9 <strong>Ballast</strong> Stabilising<br />

<strong>Ballast</strong> Stabilisers are designed to very quickly rearrange the relative position of track<br />

ballast in a controlled manner to reduce uncontrolled settlement and to improve both<br />

vertical and lateral stability of the track.<br />

The <strong>Ballast</strong> Stabiliser grips both rails with rollers and creates in the rails and sleepers a<br />

horizontal vibration. This vibrating action combined with a controlled vertical loading<br />

crates a similar vibration in the ballast, which causes the individual ballast stones to move<br />

relative to each other and to position themselves together to form the best fit. This<br />

stabilising action is, in effect, controlled settlement and is achieved very rapidly by the<br />

<strong>Ballast</strong> Stabiliser at rates varying from 500 to 1700 metres/hr.<br />

One pass of the Stabiliser is approximately equivalent to 100,000 tonnes of rail traffic.<br />

C9-1 Conditions required for effective stabilising of track<br />

To gain effective results from the use of <strong>Ballast</strong> Stabilisers the following conditions must<br />

apply:<br />

• <strong>Ballast</strong> should be relatively clean and free flowing. The machine should not be<br />

used on heavily fouled or cemented ballasted track.<br />

• <strong>Ballast</strong> must be disturbed prior to using the stabiliser so that it can flow under the<br />

actions of the machine. (For best results the track should be ballast cleaned<br />

and/or tamped prior to stabilising).<br />

• The track must be regulated to fill cribs and form shoulders so that there is<br />

sufficient ballast to allow for ballast loss due to settlement of the ballast during the<br />

stabilising process.<br />

• Rail to sleeper fastenings must be sound so that the horizontal oscillation<br />

generated by the machine can be transmitted through the rails and sleepers into<br />

the ballast.<br />

• The track must be in the required position and to desired standard prior to<br />

stabilising. The machine can correct some minor faults in top and superelevation<br />

but is not designed to correct major faults in track geometry or poor quality after<br />

tamping.<br />

• In order to obtain uniform consolidation and settlement the machine should be kept<br />

moving at a constant speed. The stabiliser must also work far enough behind<br />

preceding machines so that its operation is not hampered by slower production<br />

machines or by any problems with the machines ahead.<br />

C9-2 Restrictions on or near structures<br />

<strong>Ballast</strong> stabilisers may, under certain conditions, excite critical vibration frequencies in<br />

nearby structures.<br />

As a result, some operating restrictions are imposed on <strong>Ballast</strong> Stabilisers on and near<br />

structures. The restrictions are documented in <strong>Engineering</strong> Manual TMC 300 - Structures<br />

General.<br />

C9-3 Restrictions near signalling equipment<br />

Whilst stabilising can be undertaken on plain track at stabilising pressures from 40bar for<br />

light, 60 -70bar for medium and 100bar for heavy stabilising, results from testing<br />

undertaken by <strong>RailCorp</strong> in 2011established that points machines can suffer significant<br />

© Rail Corporation Page 24 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

damage when subject to these vibration pressures. Accordingly DO NOT operate the<br />

stabilizer at pressures greater than 40bar any closer than 7m to the A bearer of any set of<br />

points. This will limit the acceleration in the points motor to approximately 2g which is<br />

equivalent to the normal vibration experienced from a fully loaded freight train and will<br />

cause no damage to the signalling equipment.<br />

© Rail Corporation Page 25 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

Chapter 10 <strong>Ballast</strong> cleaning<br />

C10-1 Planning<br />

This chapter describes the methods used in <strong>RailCorp</strong> remove and replace ballast using<br />

<strong>Ballast</strong> cleaning machines.<br />

During the months of temperature extremes care must be exercised to prevent<br />

breakaway or misalignments occurring.<br />

Track should not be ballast cleaned when the rail temperature is outside the range 15 to<br />

38 0 C unless appropriate action is taken to correct the adjustment and restore stability of<br />

the track. Refer to the guidelines in <strong>Engineering</strong> Manual TMC 211 - Track Geometry &<br />

Stability.<br />

In Summer, before commencing any work, the Project Supervisor and the Civil<br />

Maintenance Engineer MUST ensure WTSA requirements have been addressed and<br />

appropriate arrangements are in place. They MUST agree on:<br />

1. the allowable scope of work,<br />

2. the WTSA stability loss at the work location, both before AND after the work,<br />

3. the effect of the work on stability, and<br />

4. any actions required to control the risk of misalignments, eg DTS, speeds.<br />

Special attention must be paid by maintenance staff to work locations where adjustment<br />

may not have been completed.<br />

C10-2 <strong>Ballast</strong> Cleaning procedure<br />

1. “Cut in” the ballast cleaning machine.<br />

The machine is “cut in” by moving one sleeper and digging a hole to allow the<br />

placement of the cutter bar under the track and connection of the cutting chain.<br />

o Remove ballast to the bottom of a sleeper in the bay between sleepers.<br />

o Remove sleeper fastenings. Place fastenings aside for easy recovery.<br />

o Remove the sleeper. Place the sleeper aside for easy recovery.<br />

o Remove ballast for the cutter bar.<br />

o Excavate ballast to a depth of 300mm below rail and a width 500mm either<br />

side of the rail.<br />

o Insert the cutter bar under the track.<br />

o Drive the machine into the correct position.<br />

o Join links in the cutter bar and connect firmly to the machine.<br />

2. Remove ballast<br />

o Operate the ballast cleaning machine to excavate ballast with the cutter<br />

chain.<br />

o In “Screening Mode” the ballast material is passed through a vibrating<br />

screen.<br />

o Return reusable ballast to the track using side conveyor belts. The screen<br />

may be adjusted to regulate the return of ballast to the high rail to restore the<br />

superelevation.<br />

© Rail Corporation Page 26 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

o The spoil is deposited on the main spoil conveyor and loaded via the main<br />

conveyor boom into spoil wagons for removal from site.<br />

o In “Excavation Mode” all material is deposited on the main spoil conveyor for<br />

disposal.<br />

3. Measure and record depth of cut and the crossfall at each survey location.<br />

The acceptance standards detailed in Table 4 must be met:<br />

Depth of cut<br />

Limit<br />

+0mm - 50mm from design formation level.<br />

Crossfall 75mm to the Up cess.<br />

Table 4 – <strong>Ballast</strong> cleaning acceptance limits<br />

4. “Cut out” the ballast cleaning machine.<br />

The machine is “cut out” by moving one sleeper and disconnecting the cutting<br />

chain to remove the cutter bar.<br />

5. Lay ballast (See Chapter 4).<br />

6. Resurface the track using methods detailed in TMC 211 – Track Geometry &<br />

Stability.<br />

Attention should be given to the points of insertion and removal, until the track<br />

has completely settled down.<br />

7. Restore ballast profile using methods detailed in Chapter 4 and Chapter 7. The<br />

profile must meet the acceptance limits detailed in Chapter 7.<br />

8. Check worksite.<br />

o Do not block drainage systems with old sleepers, fastenings or plates.<br />

o Stack all used materials neatly where it is not in the way.<br />

o Examine connections visually for signs of break or damage. Contact<br />

signalling or electrical personnel if damage is visible or suspected.<br />

9. Certify track.<br />

Certify the track using the procedure in TMC 211.<br />

o If work has not been completed and sleepers are left untied, assess whether<br />

a speed restriction is required using the operating limits in TMC 203.<br />

o If sleepers have not been packed, or geometry has not been corrected apply<br />

appropriate restrictions in accordance with the operating limits in TMC 203.<br />

© Rail Corporation Page 27 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

Chapter 11 Track reconditioning using off track plant<br />

C11-1 Planning<br />

1. In locations where the track formation is planned for renewal, a formation<br />

design needs to be established by the Principal Geotechnical Engineer. The<br />

investigation and design will be undertaken following the principals detailed in<br />

<strong>RailCorp</strong> <strong>Engineering</strong> Manual TMC 403 - Track Reconditioning.<br />

2. Detailed survey must be carried out before the re-conditioning takes place to<br />

determine:<br />

C11-2 Reconditioning procedure<br />

o depth of excavation,<br />

o top of capping layer,<br />

o top of bottom ballast, and<br />

o height of rail and alignment of the completed re-conditioning.<br />

1. Install Anchor points at each end of site (in CWR) - See Figure 14.<br />

Creep Control Point<br />

Not less<br />

than 55m<br />

Section to be<br />

removed<br />

Not less<br />

than 55m<br />

Creep Control Point<br />

Anchor Point<br />

Anchor Point<br />

Area to be<br />

readjusted at<br />

completion of<br />

work (clear of<br />

creep points)<br />

Figure 14 - Maintaining rail adjustment in track adjoining major renewal<br />

© Rail Corporation Page 28 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

2. Install Creep Control marks on each rail not less than 55 m from the cut-in point<br />

at each end of site (CWR track only) - See Figure 14<br />

If there is a fixed point (e.g. elastic fastened transom top bridge, turnout or level<br />

crossing) less than 55m from the rerailing site use the fixed point as the creep<br />

control point.<br />

3. Cut the track<br />

Use a rail saw or oxy cutting equipment to cut the track into panels that are not<br />

too long or heavy for the machinery you have available to handle.<br />

Alternatively you can remove fastenings, rails and sleepers separately.<br />

4. Remove the panels<br />

Using the machinery available, place the panels out of the way of the main<br />

worksite. While the excavation is happening, these panels should be resleepered.<br />

5. Excavate the site<br />

Some things you will have to think about before the excavation may be:<br />

o The type of machinery used to excavate and the means by which you will<br />

dispose of the “spoils”<br />

o “G Wagons” may be used to remove the spoils. When using the “G<br />

Wagons”, make sure they are not overloaded as this can cause problems<br />

elsewhere in the system. (See Chapter 12 for guidance on avoiding<br />

overloading of wagons).<br />

o Access for Tip Trucks.<br />

o How deep must you excavate?. Unless an alternative design is approved by<br />

the Chief Engineer track the ballast depth must meet the following<br />

standards.<br />

The construction and maintenance acceptance limits for ballast depth detailed below<br />

are extracted from <strong>RailCorp</strong> Standard ESC 240- <strong>Ballast</strong>.<br />

<strong>Ballast</strong> depth<br />

<strong>Ballast</strong> depth is the distance from the underside of the sleeper to the top of the<br />

finished formation.<br />

On superelevated track, the depth of ballast is measured from under the low rail.<br />

<strong>Ballast</strong> depth shall be either "High" or "Medium" or "Low" in accordance with the<br />

existing or proposed track structure class detailed in <strong>RailCorp</strong> standard ESC 200<br />

and as detailed in Table 5and Table 6.<br />

Category<br />

Design <strong>Ballast</strong> depth(mm)<br />

Minimum Maximum<br />

High H 350 500<br />

Medium M 300 500<br />

Low L 250 500<br />

L(150) 150 500<br />

L(100) 100 500<br />

L(Nom) Nominal 500<br />

Table 5 - <strong>Ballast</strong> depth categories<br />

© Rail Corporation Page 29 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

Operating Class<br />

Main line<br />

Passenger Main<br />

Line<br />

Mixed Passenger<br />

Freight Main Line<br />

Sleeper type<br />

Medium duty<br />

concrete<br />

Heavy duty concrete<br />

Medium duty<br />

concrete<br />

Heavy duty concrete<br />

New Existing<br />

<strong>Ballast</strong><br />

depth<br />

(Note 3)<br />

Sleeper type<br />

<strong>Ballast</strong><br />

depth<br />

(Note 1, 2)<br />

L Timber L<br />

M Timber M<br />

Light Line NA Timber L<br />

Heavy Freight<br />

Option<br />

Sidings<br />

General Yard (1) Medium duty<br />

concrete<br />

Passenger<br />

operations/ or<br />

maintenance<br />

Heavy duty concrete H<br />

Medium duty<br />

concrete<br />

Heavy duty<br />

concrete<br />

L Timber L(150)<br />

L Timber L(150)<br />

Passenger Siding Timber L(100) Timber L(100)<br />

<strong>Engineering</strong><br />

Timber L(Nom) Timber L(Nom)<br />

Maintenance Siding<br />

Table 6 - <strong>Ballast</strong> height<br />

Note 1. Full ballast depth in existing track includes ballast that is not free draining.<br />

Free draining ballast may include ballast with fines such as sand, brake<br />

dust and other fine material that does not restrict water flow.<br />

2: Existing track may not necessarily achieve the target ballast depth.<br />

3: Use of the design ballast depths with poor subgrades may still cause the<br />

subgrade to be over stressed. Detailed investigation and analysis of the<br />

whole track structure including the substructure condition may be<br />

necessary in these problem situations. It can equally be demonstrated that<br />

in areas with very good subgrades (natural or designed) it is possible to<br />

provide adequate support to the track structure with lower ballast depths<br />

than those specified in Table 6.<br />

Through turnouts the minimum ballast depth under turnout bearers is to be maintained<br />

by lowering the formation level as required. The change in level of the formation is to<br />

be ramped off at a maximum grade of 1 in 200 relative to the track grade.<br />

Whilst the excavation is taking place, there are many jobs that can be done,<br />

such as:<br />

o Quality control i.e. how deep is the excavation?<br />

o Resleepering the panels<br />

o Boring holes in the ends of the rails<br />

o Construction of drainage<br />

© Rail Corporation Page 30 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4<br />

H


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

6. Renew the formation.<br />

The formation should be rolled and compacted to give a firm base for the track.<br />

7. Renew the capping layer.<br />

A special grade of road base is laid down to the depth and width detailed in the<br />

design, then rolled and compacted in 100m layers, making sure the crossfall is<br />

correct.<br />

If required by the formation design geotextile fabric may be used to assist the<br />

capping layer in diverting water away from the formation and stopping mud and<br />

dirt coming up through the capping layer.<br />

8. Replace the bottom ballast.<br />

Install bottom ballast using off-track plant from ballast stockpiled on site.<br />

9. Replace the panels.<br />

Using the machinery available, place the panels close as possible to the design<br />

track alignment.<br />

Reconnect track to allow ballasting and resurfacing operations.<br />

10. Re-ballast the track in readiness for the final re-surfacing either from stockpiles<br />

on site or by using ballast trains (See Chapter 4).<br />

11. Resurface the track using methods detailed in TMC 211 – Track Geometry &<br />

Stability.<br />

12. Restore ballast profile using methods detailed Chapter 4 and Chapter 7. The<br />

profile must meet the acceptance limits detailed in Chapter 7.<br />

13. Weld the panels together using the aluminothermic welding method detailed in<br />

TMC 222.<br />

14. Adjust Track (see TMC 223). This includes the track between the cut-in point<br />

and the creep control points.<br />

15. Check the creep control points following the adjustment.<br />

16. If there has been more than 10mm of creep in either direction on either rail<br />

arrange for a track stability assessment to be undertaken by the Maintenance<br />

Team Manager.<br />

The Maintenance Team Manager's assessment should determine what<br />

additional adjustment may be required.<br />

The staging of rail removal works should consider the effect on track stability.<br />

For example, night rerailing might cause excess steel in the next section to be<br />

rerailed, causing a track to buckle if the next day is hot.<br />

17. Update Creep control points to reflect any changes in track adjustment.<br />

18. Check worksite.<br />

o Do not block drainage systems with old sleepers, fastenings or plates.<br />

o Stack all used materials neatly where it is not in the way.<br />

o Examine connections visually for signs of break or damage. Contact<br />

signalling or electrical personnel if damage is visible or suspected.<br />

© Rail Corporation Page 31 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

19. Certify track.<br />

Certify the track using the procedure in TMC 211.<br />

o If work has not been completed and sleepers are left untied, assess whether<br />

a speed restriction is required using the operating limits in TMC 203.<br />

o If sleepers have not been packed, or geometry has not been corrected apply<br />

appropriate restrictions in accordance with the operating limits in TMC 203.<br />

© Rail Corporation Page 32 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4


<strong>RailCorp</strong> <strong>Engineering</strong> Manual — Track<br />

<strong>Ballast</strong> TMC 241<br />

Chapter 12 Loading Spent <strong>Ballast</strong> Wagons<br />

C12-1 Material weights<br />

Spent <strong>Ballast</strong> (spoil) wagons, coded NDCH and NDMX, are used by civil staff to remove<br />

spent ballast and formation material from restricted worksites.<br />

The differing weights of wet and dry ballast and clay may result in overloading of wagons<br />

if care is not exercised in loading.<br />

Advice on the relative weights of typical spoil materials is detailed in Table 7 below.<br />

Material Tonnes/m 3<br />

<strong>Ballast</strong> - new loose 1.7<br />

<strong>Ballast</strong> cleaning spoil (damp/wet) 2.2<br />

Road base (very dry) 1.9<br />

Road base (very wet) 2.2<br />

Road base (dry-moist, normal condition) 2.0<br />

Clay - wet, well packed 2.2<br />

Clay - wet, lumpy 2.0<br />

Table 7 – Relative soil weights<br />

From Table 7 it is clear that the volume of spoil wagons allows severe overloading,<br />

particularly for wagons over 10m in length.<br />

Supervision of loading is critical to avoid overloading and unbalanced loading (particularly<br />

when loading from the side with off-track plant).<br />

C12-2 Checking for overloading<br />

Wagons may be loaded until the load bearing coil spring in the bogie compress to be<br />

3mm apart. This will provide for a margin of safety from the minimum 2mm gap specified<br />

in Rolling stock standards.<br />

The 3mm minimum clearance can be measured by inserting the gauge (detailed in Figure<br />

15 below) between the coils of the wagon springs.<br />

The gauge is 10mm wide, 3mm thick and 100mm long with a hole to allow attachment to<br />

a key ring.<br />

4mm dia<br />

100mm<br />

Figure 15 - Spent ballast loading gauge<br />

10mm<br />

3mm<br />

© Rail Corporation Page 33 of 33<br />

Issued June 2012 UNCONTROLLED WHEN PRINTED Version 2.4

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!