Pressure tests<br />

The initial high pressure test on components<br />

that could be exposed to well pressure (BOP<br />

stack, choke manifold and choke lines) should<br />

be to the rated working pressure of the ram<br />

BOP’s or to the rated working pressure of the<br />

wellhead that the stack is installed on,<br />

whichever is lower.<br />

Initial pressure tests are defined as those<br />

tests that should be performed on location<br />

before the well is spaded or before the<br />

<strong>equipment</strong> is put into operational service.