Hotmix Paving<br />

• Tack must be applied to new pavement surfaces<br />

immediately prior to the next lift when:<br />

– 10 days have elapsed<br />

– it has rained since placing the last lift<br />

– the surface has become dirty<br />

• Tie-ins to adjoining (existing) pavements must be saw<br />

cut (transversely) to provide a clean vertical joint<br />

• Tie-in smoothness is enhanced by cutting transverse<br />

“butt joints”<br />

• Hotmix used to overlay concrete can be saw cut &<br />

sealed over the concrete joints to prevent reflective<br />

cracking