Cast Iron Condensing <strong>Boiler</strong>s – Installation <strong>Manual</strong><br />
Primary/Secondary Piping<br />
Although acceptable, the system is not as cost effective<br />
as reverse return piping. Figure 12 shows a typical<br />
primary/secondary piping system. A dedicated pump is<br />
used to maintain a constant water fl ow through the<br />
boiler. Systems using multiple boilers can be installed<br />
using a primary/secondary manifold system, Figure 13.<br />
Piping For Use With Cooling Units<br />
The boiler, when used in connection with a refrigeration<br />
system, must be installed so the chilled medium is piped<br />
in parallel with the boiler. Appropriate valves must be used<br />
to prevent the chilled water from entering the boiler.<br />
Figure 10 - Typical Single <strong>Boiler</strong> Piping (RECOMMENDED)<br />
(Circulator pump must be sized for minimum water fl ow rate of boiler, including system pressure drop)<br />
HIOM-64<br />
When a boiler is connected to a heating coil that may<br />
be exposed to refrigerated air from an air handling<br />
device, the piping system must be equipped with fl owcontrol<br />
valves or some other automatic means of<br />
preventing gravity circulation of the boiler water during<br />
the cooling cycle.<br />
It is essential that following boiler shut off,<br />
the boiler pump continue to operate for<br />
approximately (5) minutes to dissipate the<br />
heat away from the heat exchanger.<br />