<strong>Homeowner</strong> <strong>Information</strong> <strong>Package</strong><br />

7<br />

Delayed Occupancy<br />

Compensation (This Section Applies<br />

to Condominium Unit Buyers Only)<br />

The Act specifies that your builder may delay<br />

occupancy of your condominium unit for up<br />

to five days without giving notice or paying<br />

compensation. They may also delay occupancy<br />

for up to 135 days with proper written notice as<br />

described below without paying compensation.<br />

If, however, the closing date of your new home<br />

is delayed more than five days without proper<br />

written notice, or more than 135 days in total<br />

from the confirmed occupancy date specified<br />

in your purchase agreement (either the original<br />

confirmed occupancy date or a new date specified<br />

in accordance with your purchase agreement), then<br />

you may be entitled to compensation from your<br />

builder up to a maximum of $5,000.<br />

If you agree to extend your confirmed occupancy<br />

date by way of an amendment to your purchase<br />

agreement, you may not be eligible for<br />

compensation. There is no compensation for delays<br />

caused by strikes, fire, floods, civil insurrection or<br />

“acts of God”. In addition, compensation is not<br />

payable for delays for which you are responsible.<br />

If you are unsure about your rights regarding<br />

delayed occupancy, you may wish to seek the<br />

advice of a lawyer.<br />

What’s the difference between “confirmed”<br />

and “tentative” occupancy dates?<br />

Every purchase agreement for a condominium unit<br />

will include either a confirmed occupancy date or<br />

a tentative occupancy date. If a tentative occupancy<br />

date is given, your builder is required to inform<br />

you in writing of the confirmed occupancy date<br />

no later than 30 days after the roof assembly is<br />

completed (or another specific stage of construction<br />

as specified in the purchase agreement). If you are<br />

not given notice of the confirmed occupancy date<br />

by at least 90 days before the tentative occupancy<br />

date, then the tentative occupancy date will<br />

automatically become the confirmed occupancy<br />

date for the purpose of calculating compensation<br />

for the delay.<br />

What constitutes “proper notice” from<br />

my builder about a delay in the occupancy<br />

of my home?<br />

Once the confirmed occupancy date is established,<br />

your builder is allowed to extend it as follows:<br />

Once by up to 15 days if they give you written<br />

notice of the new confirmed occupancy date at<br />

least 35 days in advance; or<br />

Once by up to 120 days, if they give you written<br />

notice of the new confirmed occupancy date at<br />

least 65 days in advance. If that is insufficient,<br />

your builder may further extend the date by<br />

an additional 15 days, if they give you proper<br />

written notice of the new confirmed occupancy<br />

date at least 35 days in advance and if the final<br />

new confirmed occupancy date is not more<br />

than 135 days later than the original confirmed<br />

occupancy date.