Environmental statement - Flyndre and Cawdor - Maersk Oil
Environmental statement - Flyndre and Cawdor - Maersk Oil
Environmental statement - Flyndre and Cawdor - Maersk Oil
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
<strong>Flyndre</strong> <strong>and</strong> <strong>Cawdor</strong> <strong>Environmental</strong> Statement<br />
Section 7 Conclusions<br />
7. CONCLUSIONS<br />
A detailed EIA of the development has been carried out in order to determine the potential impacts<br />
on the environment <strong>and</strong> their significance. The identification of the potential impacts was based on<br />
the nature of the proposed activities <strong>and</strong> was undertaken using available literature <strong>and</strong> guidance<br />
documents, industry specific experience <strong>and</strong> discussions with relevant authorities including DECC,<br />
JNCC <strong>and</strong> Marine Scotl<strong>and</strong>. The EIA process will continue throughout the project with the<br />
incorporation of the commitments made in this ES into the design process, construction <strong>and</strong><br />
ultimately affecting the way in which the field is produced.<br />
7.1. ENVIRONMENTAL EFFECTS<br />
The development area is considered to be a typical CNS offshore environment there are no biological<br />
habitats or other features that are particularly sensitive to the type of development proposed. No<br />
Annex I habitats are present within the vicinity of the development. The project may impact very<br />
briefly upon fisheries in the area during the installation period.<br />
The environmental aspects of the key activities during the production phase were identified <strong>and</strong>,<br />
where possible, the potential effects quantified in terms of their likelihood, potential significance <strong>and</strong><br />
magnitude. The results were assessed on the basis of the risk posed to the environment <strong>and</strong> were<br />
summarised as either low, moderate or high risk.<br />
The initial screening assessment showed that the majority of the key activities are of low risk <strong>and</strong> that<br />
there are no key activities which are of high risk. During the drilling phase the risk associated with the<br />
deliberate discharge of drilling fluids <strong>and</strong> the associated chemicals were found to be moderate. An<br />
uncontrolled 90 day blowout from wells was also found to be of a moderate risk as no beaching is<br />
predicted to occur.<br />
Noise resulting from piling was also found to be of a moderate risk as was the discharge of produced<br />
water during production. Disturbance of historic cuttings piles at the Clyde platform was also<br />
identified as a moderate environmental risk, further engineering studies are planned in relation to the<br />
design of the riser <strong>and</strong> umbilical tie in points, only when this is completed will a better assessment of<br />
the potential for disturbance of cuttings be possible, so this is remains a project uncertainty.<br />
Following the identification of suitable mitigation measures, an additional assessment was<br />
undertaken for the activities which were initially identified to be of moderate risk. With the adoption<br />
of appropriate mitigation there are only low residual risks to the environment.<br />
7.2. MINIMISING ENVIRONMENTAL IMPACT<br />
Overall, the execution of the proposed development following the incorporation of the control<br />
measures, is not expected to have a significant impact on the environment.<br />
In order to capture the commitments <strong>and</strong> environmental issues identified from the assessment of the<br />
<strong>Flyndre</strong> <strong>and</strong> <strong>Cawdor</strong> development, these will be transferred into <strong>Maersk</strong> <strong>Oil</strong>’s action tracker, ‘Synergi’.<br />
The Synergi system is used for the management of reports <strong>and</strong> data relating to <strong>and</strong> actions resulting<br />
from:<br />
Incidents<br />
Audits<br />
D/4114/2011 7 ‐ 1