AFMAN 23-110 Volume 1<br />
Part 4, Chapter 1<br />
1A2<strong>1.1</strong>. Number Of Characters: One.<br />
1A21.2. Type Of Code: Alpha (except I and O).<br />
ATTACHMENT 1A-21<br />
SHIPMENT HOLD <strong>CODES</strong><br />
NOTES:<br />
When MILSTRIP requisition material is delayed at a shipping activity after it has been picked,<br />
packed, marked and made ready for shipment, the de lay will be recorded on the shipment planning<br />
worksheet using the appropriate code below and will be reported for inclusion in the MILSTRIP shipment<br />
status (record position 51) and material release confirmation document.<br />
Table 1A2<strong>1.1</strong>. MILSTRIP Shipment Status.<br />
Code Explanation<br />
A Shipment unit held for consolidation.<br />
B Awaiting carrier equipment.<br />
C Awaiting export or domestic traffic release.<br />
D Delay due to diversion to surface resulting from challenge by air clearance activity.<br />
E Delay resulting from challenge by air clearance activity for which no diversion to surface<br />
occurs and material was shipped by air.<br />
F Embar go<br />
G Strikes, riots, civil commotion.<br />
H Acts of God.<br />
J Shipment delayed to process customer cancellation request(s).<br />
K Diversion to surface movement due to characteristics of material that preclude air shipment e.g.,<br />
size, weight, or hazard classification.<br />
L Delay requested and/or concurred in by consignee.<br />
M Delay to comply with valid delivery dates at CONUS destinations/outloading terminals.<br />
N Delay due to diversion to air (requisition priority upgraded).<br />
P-Y Reserved.<br />
Z Holding action of less than 24 hours from date material is available for shipment.<br />
1–45