20.03.2013 Views

East Cambridgeshire District Council Water Cycle Study Detailed ...

East Cambridgeshire District Council Water Cycle Study Detailed ...

East Cambridgeshire District Council Water Cycle Study Detailed ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

In summary:<br />

Stage 2 <strong>Water</strong> <strong>Cycle</strong> <strong>Study</strong>: Final Report<br />

Sept 2011<br />

39<br />

<strong>Cambridgeshire</strong> Horizons<br />

<strong>East</strong> <strong>Cambridgeshire</strong> – <strong>Detailed</strong> WCS<br />

• The remaining residual allocated and windfall development proposed for Bottisham should<br />

be limited to an annual completion rate agreeable with both AWS and the Environment<br />

Agency up to 2015; It is likely that the 50 outstanding permissions will take any available<br />

headroom that can be identified up to 2013 and hence growth from allocations and windfalls<br />

should not be granted permission without confirmation from AWS and the Environment<br />

Agency that capacity is available up to 2015;<br />

• ECDC should meet monthly with AWS and the Environment Agency to determine a suitable<br />

annual completion rate up to 2015 until a long term solution can be determined;<br />

• ECDC should facilitate workshops with AWS and Environment Agency to develop a long<br />

term solution to be developed in time to implement in the next Asset Management Plan<br />

period (2015 to 2020) to allow all remaining residual growth to take place.<br />

New Solution Requirements – Future Good Potential<br />

There are two wastewater catchments where Good status cannot be achieved following the<br />

growth – these are:<br />

• Soham (for phosphate); and<br />

• Bottisham (for phosphate).<br />

The modelling assessments have shown that for both Soham and Bottisham, the receiving<br />

watercourse downstream of Bottisham could not achieve Good status without the growth and it<br />

is therefore factors other than the proposed growth that are preventing the achievement of<br />

future Good status. Attainment of future good status is therefore not a barrier to growth and ‘no<br />

deterioration’ consents detailed in Table 3-3 above need only be considered in this WCS.<br />

Ely Alternative Option<br />

The capacity assessment for both of the Ely WwTWs indicates there is sufficient combined<br />

capacity to accept wastewater from growth within existing consents. However, consideration is<br />

being given to the location of a new WwTW to the north of Ely. A meeting was held between<br />

AWS, <strong>Cambridgeshire</strong> County <strong>Council</strong> and ECDC to discuss the relocation of Cresswells Lane<br />

WwTW on 4th October 2010. AWS is open to such a move but it is too early to make any<br />

commitments and scheme viability is expected to be a key issue. The benefits will need to be<br />

weighed against the costs when options for serving Ely North are evaluated. The policy position<br />

in LDF documents will also be a consideration. AWS has therefore left the option of relocation<br />

to Ely North open in the Minerals and Waste LDF evidence and intends to continue this position<br />

at Public Examination.<br />

Preliminary technical feasibility of this option has been considered in this <strong>Detailed</strong> study by<br />

assuming a theoretical position where a new WwTW is constructed in close proximity to the<br />

potential North Ely development sites. It is assumed that all existing wastewater flow and all<br />

future flow from development from Ely would be transferred to the new WwTW and both Ely<br />

Old and Ely New WwTW would be closed and discharges stopped.<br />

The modelling has shown that, from a WFD and water quality perspective only, such an option<br />

would be technically feasible without resulting in a downstream deterioration in current quality,<br />

and that good status could be achieved downstream for all parameters when growth is

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!