Installation Instructions<br />

5.4.7 Generator installation below waterline<br />

If the generator cannot be attached at least 600 mm above the<br />

waterline, a vent valve must be installed at the raw water line.<br />

Possible heeling must be taken into consideration if installed at the "mid-ship<br />

line"! The water hose for the external vent valve is located at the back of the<br />

sound insulated capsule. This hose is split in the middle and extended<br />

respectively at each end by an additional hose and a connecting nipple. Both<br />

hose ends must be led outside of the sound cover, if possible 600 mm over<br />

the waterline in the mid-ship line. The valve is connected at the highest place<br />

to the two hose ends. If the valve jams the cool water line cannot be de-aerated<br />

after stopping the generator, the water column is not discontinued and<br />

water can penetrate into the combustion chamber of the engine. This will<br />

lead to damage the engine in a short term!<br />

Fig. 5.4.7-2: Rubber hose for vent valve - example<br />

The rubber hose for the external vent valve will be cut...<br />

...and bend upwards.<br />

Both hose ends will be extended respectively with a hose and<br />

connected with a vent valve 600 mm over the waterline.<br />

Example<br />

Fig. 5.4.7-1: Vent valve<br />

Fig. 5.4.7-3: Split rubber hose for vent valve<br />

7.5.12 Panda_4000s_PMS_SCB_FCB_eng.R04 - Kapitel/Chapter 5: Installation Instructions Seite/Page 59